TABLE OF CONTENTS
1.2 Environmental Impact Assessment
Study
1.3 Purpose of this Executive Summary
2.2 Appreciation of Existing Environment
2.3 Constraints and Opportunities for Project
Development
2.4 General Description of the Project
2.5 Revised Recommended Outline
Development Plan (RODP)
2.8 Development Programme for the
Project
2.9 Existing Brownfield Interface with New
Development
3. Key findings of the environmental
impact assessment
3.5 Sewerage and Sewage Treatment
Implications
3.6 Waste Management Implications
3.9 Ecological Impact (Terrestrial and
Aquatic)
3.11 Impact on Cultural Heritage
3.13 Landscape and Visual Impacts
3.14 Impact from Electric and Magnetic
Fields
4. ENVIRONMENTAL MONITORING AND AUDIT
5. SUMMARY OF ENVIRONMENTAL OUTCOMES
List of Tables
Table 2.1 Land Use Budget of the Revised
RODP
Table 2.2 Schedule 2 Designated Projects in the STLMC DN
Table 5.1 Summary of Key Environmental Problems Avoided and
Sensitive Areas Protected
Table 6.1 Summary of Environmental Impacts
List of Figures
Project Location Plan |
|
Revised Recommended Outline Development Plan (RODP) |
|
Location of Designated Projects |
i)
the overall acceptability of any adverse
environmental consequences that are likely to arise as a result of the Project
and its staged implementation;
ii)
the conditions and requirements for the detailed
design, construction and operation of the Project to
mitigate against adverse environmental consequences wherever practicable; and
iii)
the acceptability of residual impacts after the
proposed mitigation measures are implemented.
·
Section
2 presents purpose, scope and development of the Project;
·
Section
3 presents the key findings of the environmental impact assessment;
·
Section
4 describes the proposed environmental monitoring and audit programme for the Project;
·
Section
5 presents a summary of environmental outcomes; and
·
Section
6 presents the conclusions.
Southern Project Area bounded
by Ki Lun Shan and Ngau Tam Shan
Ø
Sam Po Shue Wetland Conservation
Park (SPS WCP)
Ø
Highly Accessible
Ø
Enhanced Cross-Boundary Traffic Connectivity
Ø
Enhanced Railway Network and Integrated Public
Transport Network
Ø
Favourable Geographical Location
Ø
Plentiful Natural and Landscape Features
Ø
Rich Cultural Heritage
Ø
Land Resources
Ø
Infrastructure Constraints
i)
The elevated section of LMC Spur Line and the two major
distributors traversing the Project area, i.e. San Tin Highway and Fanling Highway, will pose environmental constraints to the
nearby developments. Other existing major distributors including Castle Peak
Road – San Tin, San Tam Road, Kwu Tung Road, Lok Ma
Chau Road and Ha Wan Tsuen East Road are also
potential air pollution and noise sources that will likely generate
environmental impacts to the nearby developments.
ii)
The existing overhead line cables near Chau Tau area at the
east and Pang Loon Tei area at the south of the Project require vertical and
horizontal separation distance from adjacent proposed land uses in accordance
with the Hong Kong Planning Standards and Guidelines would limit the
development potential of the adjacent Project areas.
iii)
There is an existing pig farm falling outside of the Project
area to the east of Chau Tau Village. Besides, a sewage treatment plant is
located within San Tin Barracks in close proximity of
the Project area. The future developments should observe relevant requirements
on odour impacts, with reference to the findings of the EIA Report of this
Project.
Ø
Environment Constraints
i)
The feasibility of surrounding lands is considered
comprehensively when planning the land use of the Project. To fully
leverage the strategic positioning of the Project, a substantial area of land
for I&T purposes shall be provided. However, due to the presence of hills
on the eastern and southern sides of the Project, particularly the natural
slopes in the southeastern part of the Loop, where the terrain is high and
steep, substantial earthwork, soil filling, and infrastructure works would be
required to form extensive sites. Considering factors such as associated
environmental impact, ground condition, cost, and development programme, the said natural slope is therefore not
recommended for development for I&T purposes. Hence, the development lands
shall expand towards the inland area closer to the fishponds, while minimising any impact on bird habitats and bird flight
corridors. By utilising a portion of the fishponds in
a reasonable manner, the planning layout of the Project can be enhanced.
ii)
The existing conservation-related zonings, including CA,
OU(CDWEA), OU(CDWRA), GB and SSSI zone have been carefully reviewed in the
formulation of the Revised RODP to uphold the principle of co-existence of
development and conservation within the context of sustainable development.
Ø
Consideration of the Traditional Villages and Permitted
Burial Grounds during Planning
Ø Proliferation of
Brownfield Operations Grounds
Ø Government, Institution or
Community Developments
Ø Preservation of Natural and Landscape Features
Ø Flooding Risk
·
Residential sites for high density public and private
residential developments. About 50,000
to 54,000 new flats will be provided to accommodate about 147,000 to 159,000
persons upon full development. The
public and private housing mix under assessment is about 70:30.
· Village resite area for re-provisioning the affected village house/building lots.
·
Mixed use developments
comprising residential, commercial / office, hotel, retail, dining
and entertainment uses as landmark developments around two proposed railway
stations with Transport Interchange Hubs (TIHs).
·
I&T sites to provide
space for I&T development with a range of complementary uses, e.g. office,
convention facilities, hotel, retail, dining and
educational facilities, etc, to promote the concept
of “work-live-learn-play”.
·
Logistics, Storage and Workshops (LSW) sites for
development of MSBs for modern industries, which may also accommodate
brownfield operations affected by Government projects. Open-air operation are also allowed to suit the operational needs of
various kinds of LSW uses.
·
A wide variety of G/IC
facilities such as social welfare facilities and educational facilities,
community facilities, cultural and recreational facilities, etc. to serve the
needs of the local residents and/or a wider district.
·
A variety of infrastructural
facilities such as DCS, EPP, ESSs, sewage pumping station (SPS), WRP to
serve the needs of the local residents and/or a wider
district.
·
Open space including riverside park for greening, recreation and leisure use
to increase liveability and to create a balanced and vibrant community and for
enhancing climate resilience by incorporating floodable landscape with flood
attenuation facilities.
·
Amenity strips to enhance the amenity and to serve as visual buffers.
·
Green belt to maintain the key natural features and protect existing natural
areas.
·
One Primary Distributor Road (Dual 2-lane Standard).
·
Six District Distributor
Roads (Single 2-lane / Dual 2-lane Standard).
·
Twenty-six Local Distributor Roads (Single 4-lane / Single 2-lane Standard).
·
Comprehensive Pedestrian Walkway
and Cycle Track Network to promote walking and
cycling within the Project area.
Table 2.1 Land Use Budget of the Revised RODP
Land Use |
Area (ha) |
% |
Residential and Mixed Uses |
60.2 |
11.2% |
Other Specified Uses (I&T) |
211.7 |
39.3% |
Other Specified Uses (Logistics, Storage and
Warehouse) |
16.2 |
3.0% |
Public Facilities |
90.7 |
16.8% |
Open Space |
55.6 |
10.3% |
New Roads |
76.7 |
14.2% |
Amenity |
27.5 |
5.1% |
Total Development Area |
539 |
100% |
33.5 |
- |
|
Green Belt |
37.5 |
- |
Total Project Area |
610 |
- |
Remarks: The above
Land Use Budget is based on the Revised RODP.
Due to rounding, the figures presented may not
add up precisely to the totals provided and percentages may not precisely
reflect the absolute figures.
Table 2.2 Schedule 2 Designated Projects in the STLMC DN
Ref. No. |
Schedule 2 Designated Project |
Work Component /Reference in Revised RODP |
||
DP1 1 |
A.1 |
A carriageway for
motor vehicles that is an expressway, trunk road, primary distributor road or
district distributor road |
Construction and
operation of a new primary distributor (Road P1) and six new district
distributor roads (Roads D1, D2, D3, D4, D5 and D6). |
|
DP2 1 |
F.1 |
Sewage treatment
works with an installed capacity of more than 15,000m3 per day |
Construction and
operation of STLMC Effluent Polishing Plant (treatment capacity of 125,000 m3/day) |
|
F.2 |
Sewage treatment works with an installed capacity of more than 5,000m3
per day; and a boundary of which is less than 200m from the nearest boundary
of an existing or planned residential area and educational institution |
|||
DP3 1 |
F.4 |
A facility for generating, from sewage effluent treated by a sewage
treatment plant, reclaimed water for use by the general
public |
Construction and operation of STLMC Water Reclamation Plant |
|
DP4 2 |
G.2 |
A refuse transfer station |
Construction and operation of a refuse transfer station |
|
DP5 2 |
H.1 |
A 400kV electricity substation and transmission line |
Construction and operation of two 400kV electricity substations |
|
DP6 1 |
I.1 |
A drainage channel or river training and diversion works located less
than 300 m from the nearest boundary of an existing or planned conservation
area |
Revitalisation works (i.e. river training, diversion works) for San
Tin Eastern Main Drainage Channel are located less than 300m from
Conservation Area 3 |
|
DP7 1 |
P.1 |
A residential or recreational development, other than New Territories
exempted houses, within Deep Bay Buffer Zone 2 |
Recreational development for proposed Sites O.1.1, O.1.2, and O.1.3
(as open space) encroach into Deep Bay Buffer Zone 2 |
Note:
1
Subject to an Environmental Permit application for
both construction and operation phases of the DP under this EIA Study.
2
Subject to separate EIA Study, as required.
3
The future zonings of the concerned ‘Conservation
Area’ as shown in Figure 2.2 are
subject to change due to the land use proposal as reflected in the Revised RODP.
·
Comprehensive
pedestrian network –
Comprehensive pedestrian network of the Project connects residential and employment nodes to provide
continuous walkways for pedestrians. It
could promote walking from homes to workplaces, retail
and services, as well as the revitalised drainage channel for various purposes.
·
Open
space network / green linkages – A series of open space corridors branching off the
main comprehensive pedestrian network, including the open spaces along drainage
channel and linear parks along major road.
They shall provide additional pedestrian connections to the surrounding
residential communities and employment areas, and further to the green and
natural areas.
·
Robust cycling network – The Project provides a robust cycling network which
link effectively to the existing and planned cycle tracks within and outside the Project. The proposed
cycling network would connect to the existing cycle tracks from Yuen Long to
KTN and the Loop to create a continuous
cycling environment that extends to other destinations beyond the Project
area. Routes within the Project would be
provided parallel to the major roadways to serve commuting needs, as well as to
provide some other routes within the proposed open space areas for leisure.
·
Site
formation and development works for one “Public
Housing” (“RSc”) site, one “Dedicated Rehousing Estate”
(“DRE”) site, village resite and one “Private
Housing” (“R1”) site at south-west of the Project area
· Site formation and development works for “Other Specified Uses” (“OU”) sites for key infrastructures including EPP, food waste pre-treatment facilities, fresh water service reservoir (FWSR) and reclaimed water service reservoir (RWSR), WRP, DCS, sewerage pumping stations (SPSs), stormwater pumping stations (SmPSs), ESS, RTS, refuse collection point (RCP), etc.
· Site formation and development works
for “Government, Institution or Community” (“G/IC”) sites
·
Site
formation and development works for “Other Specified Uses (Innovation and
Technology)” (“OU(I&T)”) sites and “OU(LSW)” sites
·
Site
formation and development works for “Education” (“E”) sites
·
Primary
Distributor Road P1 and associated interchange/junction works connecting with
San Sham Road, Castle Peak Road and San Tin
Interchange
·
District
Distributors Road D1 (portion), D2 (portion), D3, D4 and D6, associated
interchange/junction works connecting with San Tin Highway and Castle Peak
Road, local roads, pedestrian connectivity including footbridge and subway, and
associated pedestrian walkway and cycle tracks
·
Common Utilities Enclosure
(CUE) along the roads
and utilities laying works for future development of relevant sites, such as
watermains, power supply cables, DCS pipes, telecommunication cables, etc.
·
Associated
open spaces and amenity areas
·
Site
formation and development works for “RSc” and “R1”
sites at south and south-east of the Project area
· Site formation and development works for “OU” sites for key infrastructures including DCS, ESSs, PTI, FSD facilities, etc.
· Site formation and development works for “GIC” sites
·
Site
formation and building works for “OU(I&T)” sites at north-west and
south-east of the Project area
·
Site
formation and development works for “E” sites
·
District
Distributors Road D1 (portion), D2 (remaining portion) and D5, associated
interchange/junction works connecting with San Tin Highway and Kwu Tung Road, local roads, pedestrian connectivity
including footbridge and subway, and associated pedestrian walkway and cycle tracks
·
CUE
along the roads and utilities laying works for future development of relevant
sites, such as watermains, power supply cables, DCS pipes, telecommunication
cables, etc.
·
Associated
open spaces and amenity areas
·
Site
formation and development works for “RSc” site at
south of the Project area
·
Site
formation and development works for “Other Specified Uses (Mixed Use)”
(“OU(MU)”) sites at proposed San Tin Station and proposed station near Chau Tau
including the associated TIHs
·
Site
formation and development works for “G/IC” sites for Cultural and Recreational
Complex and Wetland Conservation Park Management Office
·
District
Distributors Road D1 (remaining portion), local roads connecting the sites with
existing and completed road network and associated pedestrian walkway and cycle
tracks
·
Utilities
laying works for future development of relevant sites, such as watermains,
power supply cables, DCS pipes, telecommunication cables, etc.
·
Associated
open spaces and amenity areas
Table 5.1 Summary of Key Environmental Problems Avoided and Sensitive Areas Protected
Design
Approaches |
Environmental
Problems Avoided and Sensitive Areas Protected |
Avoidance of impact on core
area of Mai Po Lung Village Egretry and protection
of the birds’ flight path |
·
The core
area of MPLV Egretry would be retained and
protected in “O”. A 70m wide NBA to
the north of MPLV Egretry would be designated to
protect the flight paths for birds. |
Avoidance of impact on Mai
Po Village Egretry and protection of the
birds’ flight path |
·
MPV Egretry falling outside of the Project boundary would be
retained and not be affected. ·
Most bird
flight paths would not be affected by the Project while some bird flight
paths would also be protected by 35m wide NBA at the western fringe of the
I&T site and restricting the building height of AFCD Wetland Conservation
Park Management Office to 2 storeys. |
Reprovision of San Tin
Open Storage Area Night Roost at “O” along the bank of the diverted STWMDC
and Ha Wan Tsuen Night Roost at an area adjacent to the proposed AFCD
Fisheries Research Centre |
·
To
compensate the two affected night roosts (San Tin Open Storage Area Night
Roost and Ha Wan Tsuen Night Roost) located within the Project area |
Preservation of a
300m-wide bird flight corridor between LMC Meander and Sam Po Shue (i)
Providing 20m and 35m wide
NBAs at I&T sites and imposing stringent building height control (≤15mPD) along the 300m wide bird flight corridor (ii)
Restricting building
height adjacent to the 300m wide bird flight corridor to 35mPD |
·
To protect
the east-west bird flight corridor near the Loop |
Provision of 35m wide NBAs
along the development boundary fronting Sam Po Shue with building height restrictions
(35mPD / 15mPD) descending towards the NBAs |
·
NBA serving as “eco-interface” together with
descending building height restrictions would minimise
the disturbance
impact on wetlands in Sam Po Shue |
Enhancement of wetlands at Proposed SPS WCP |
·
The ecological function and capacity of wetlands in
Sam Po Shue would be enhanced under the Proposed SPS WCP |
Provision of Fisheries Enhancement Area at Proposed SPS WCP |
·
The fisheries resources of the proposed SPS WCP would
be enhanced |
Provision of AFCD Fisheries Research Centre |
·
Allow promotion of scientific research on aquaculture
to facilitate the upgrading and transformation of the fisheries industries
supporting the proposed SPS WCP |
Revitalisation of mitigation wetland and provision of 20m wide NBA along STEMDC |
·
STEMDC would be revitalised
to enhance biodiversity ·
The NBA could serve as “eco-interface” to minimise disturbance on the revitalised
mitigation wetland and promote wildlife usage |
Revitalisation of STWMDC |
·
STWMDC will be revitalised
to serve as green buffer and enhance biodiversity |
Provision of wildlife corridors |
·
Wildlife corridors are proposed to mitigate habitat
fragmentation and maintain the movement corridor for non-flying mammals
including species of conservation importance |
Avoidance
of encroachment on the existing recognised villages |
·
Existing
recognised villages including Shek Wu Wai, Chau Tau Tsuen, Tung Chun Wai, Yan
Shau Wai, On Loong Tsuen, Wing Ping Tsuen, Fan Tin, San Loong Tsuen and Ching Loong Tsuen would be preserved |
Avoidance of encroachment
on cultural heritage resources |
·
No
Declared Monuments and Graded Historic Buildings within the Project boundary ·
Declared
Monuments and Graded Historic Buildings in the vicinity of Project boundary
would not be affected |
Reuse of treated sewage
effluents |
·
To reduce
amount of effluent discharge from the new EPP thus minimise pollution loading
to Deep Bay |
Clearing of existing odour
sources |
·
All
livestock farms within the Project boundary will be removed |
Avoidance of direct
impacts on natural watercourse |
·
The
natural watercourse near the woodland habitat at Pang Loon Tei would be
retained |
Providing greening to create natural carbon sink |
·
Green
coverage would be increased to include vertical greening and multi-layered
green space |
Providing sustainable
transport infrastructure to promote low-carbon
living |
·
Pedestrian-friendly
environment and robust cycling network are proposed to promote walkability
and cycling for low-carbon living |
Table 6.1 Summary
of Environmental Impacts
Impact
Prediction Results (Without Mitigation) |
Key
Relevant Standards/Criteria |
Extents
of Exceedance Predicted (Without
Mitigation) |
Impact
Avoidance Measures / Mitigation Measures |
Residual
Impacts (After Implementation of Mitigation Measures) |
|
Air Quality Impact |
|||||
Construction Impact |
|||||
·
Representative existing residential, commercial
developments and government uses within 500m from the boundary of the Project
site |
The potential sources of air quality impact associated with the
construction works would include excavation, material handling, spoil removal
and wind erosion, as well as construction activities of other concurrent
projects within 500m assessment area. |
·
Annexes 4 and 12 of the EIAO-TM TSP 1-hr average conc.: 500 μg/m3 ·
Air Quality Objectives (AQO) RSP o 24-hr average conc.: 100 μg/m3
(Number of exceedances allowed: 9) o Annual average conc.: 50 μg/m3 FSP o 24-hr average conc.: 50 μg/m3
(Number of exceedances allowed: 18) o Annual average conc.: 25 μg/m3 |
·
N/A |
Regular
watering on construction work areas, exposed surface
and paved haul roads to dust suppression. Dust suppression measures stipulated in Air
Pollution Control (Construction Dust) Regulation and good site practices
listed below should be carried out to further minimise construction dust
impact. ·
Use of regular watering to reduce dust emissions
from exposed site surfaces and unpaved roads, particularly during dry
weather. ·
Use of frequent watering for particularly dusty
construction areas and areas close to ASRs. ·
Side enclosure and covering of any aggregate or
dusty material storage piles to reduce emissions. Where this is not practicable owing to
frequent usage, watering shall be applied to aggregate fines. ·
For the work sites close to the ASR with a
separation distance less than 5m, provide hoardings of not less than 5m high
from ground level along the site boundary; for the work sites close to the
ASRs with a separation distance less than 10 m, provide hoardings of not less
than 3.5 m high from ground level along the site boundary; for the other work
sites, provide hoarding not less than 2.4m high from ground level along site
boundary except for site entrance or exit. ·
Avoid position of material stockpiling areas, major
haul roads and dusty works within the construction site close to concerned
ASRs. ·
Avoid unnecessary exposed earth. ·
Locate all the dusty activities away from any nearby
ASRs as far as practicable. ·
Open stockpiles shall be avoided or covered. Where possible, prevent placing dusty
material storage piles near ASRs. ·
Tarpaulin covering of all dusty vehicle loads
transported to, from and between site locations. ·
Establishment and use of vehicle wheel and body
washing facilities at the exit points of the site. ·
Where possible, routing of vehicles and positioning
of construction plant should be at the maximum possible distance from ASRs. ·
Imposition of speed controls for vehicles on site
haul roads. ·
Instigation of an environmental monitoring and
auditing program to monitor the construction process in
order to enforce controls and modify method of work if dusty
conditions arise. |
·
No residual impacts anticipated |
Operation Impact |
|||||
·
Existing and planned residential, commercial
developments and government uses within 500m from the boundary of the Project
site |
Air Quality Impact Year 2031 NO2 ·
19th highest 1-hr average conc.: 105 – 154 μg/m3 ·
Annual average conc.: 11 – 33 μg/m3 RSP ·
10th highest 24-hr average conc: 68 – 72 μg/m3 ·
Annual average: 27 – 29 μg/m3 FSP ·
19th highest 24-hr average conc: 35 – 39 μg/m3 ·
Annual average: 15 – 17 μg/m3 Year 2034 NO2 ·
19th highest 1-hr average conc.: 108 – 168 μg/m3 ·
Annual average conc.: 11 – 32 μg/m3 RSP ·
10th highest 24-hr average conc: 68 – 72 μg/m3 ·
Annual average: 27 – 29 μg/m3 FSP ·
19th highest 24-hr average conc: 35 – 39 μg/m3 ·
Annual average: 15 - 17 μg/m3 Year 2039 NO2 ·
19th highest 1-hr average conc.: 107 – 172 μg/m3 ·
Annual average conc.: 10 – 30 μg/m3 RSP ·
10th highest 24-hr average conc: 67 – 72 μg/m3 ·
Annual average: 27 – 29 μg/m3 FSP ·
19th highest 24-hr average conc: 34 – 38 μg/m3 ·
Annual average: 15 – 17 μg/m3 |
·
AQO NO2 o 1-hr average conc.: 200 μg/m3
(Number of exceedances allowed: 18) o Annual average conc.: 40 μg/m3 RSP o 24-hr average conc.: 100 μg/m3
(Number of exceedances allowed: 9) o Annual average conc.: 50 μg/m3 FSP o 24-hr average conc.: 50 μg/m3
(Number of exceedances allowed: 18) o Annual average conc.: 25 μg/m3 |
NO2, RSP and
FSP ·
No exceedance was predicted |
·
No mitigation measure is required. |
·
No residual impacts anticipated |
|
Odour Impact < 5 odour units based on an averaging time of 5 seconds for planned
RTS, EPP and SPSs, except at existing ASRs A26 and A33 |
·
Annex 4 of EIAO-TM ·
5 odour units based on an averaging time of 5
seconds |
·
Potential odour exceedances were predicted at two
existing ASRs A26 and A33 for a short duration of time (up to 0.89% and 6.00%
of time in a year) during operation phase of the Project. |
·
Specific building considerations has been
incorporated in the assessment and are recommended to be implemented in the
future designs. Fresh air intakes at Site G.5.8, G.5.9, G.5.10, G.5.11,
G.5.12 and OU(I&T)3.1.8 should be positioned 20mAG or above. Air sensitive
use lower than 20mAG should be avoid at these sites. School blocks at Site
E.5.1 and E.5.2 should be positioned away from the exceedance area. |
·
The Project would only contribute less than 0.02
OU/m3 and less than 0.07 OU/m3 at A26 and A33
respectively, less than 0.1 OU/m3. ·
The Project will bring improvement in odour impact
on the existing ASRs with exceedance of odour criterion. It is therefore
concluded that there is no adverse residual odour impact arising from the
Project. |
Noise Impact |
|||||
Construction Airborne Noise Impact |
|||||
·
Representative residential uses, education institution, place of public worship, barracks and noise sensitive temporary structures within
300m from the boundary of the Project Site |
·
60 – 93 dB(A) |
·
Annexes 5 and 13 of the EIAO-TM ·
Leq(30 min) 75dB(A) at 1m from the façade of residential
dwellings, place of public worship, barracks and noise sensitive temporary
structures ·
Leq(30 min) 70dB(A) at 1m from the façade of Educational
Institutions and 65 dB(A) during examinations |
·
Exceedance of the noise
criteria by up to 18 dB(A) |
·
Use of Quality Powered Mechanical Equipment ·
Use of Movable Noise Barrier, Purpose-built Noise
Barrier, Noise Insulating Fabric and Noise Enclosure ·
Sequencing Operation of Construction Activities at
critical works area ·
Reduction of PME at critical works area ·
Avoid carrying out particularly noisy construction
activities during examination periods ·
Use of Quieter Construction Methods such as silent
piling by press-in method, bursting system and quieter type blade saw. ·
Good site practices -
Only well-maintained plant should be operated on
site and plant should be serviced regularly. -
Silencers or mufflers on construction plant should
be utilised and should be properly maintained. -
Mobile plant should be sited as far away from sensitive
uses as possible. -
Machines and plant that may be in intermittent use
should be shut down between works periods or should be throttled down to a
minimum. -
Plant known to emit noise strongly in one direction
should, where possible, be orientated so that noise is directed away from the
nearby sensitive uses. -
Material stockpiles and other structures should be
effectively utilized to screen noise from on-site construction activities. |
·
No residual impacts anticipated |
Operation Impact |
|||||
·
Representative existing residential uses,
educational institutions, place of public worship, barracks, noise sensitive
temporary structures and planned residential developments within 300m from
the boundary of the Project Site |
Road Traffic Noise
Impact ·
Predicted overall noise levels: up to 84 dB(A) ·
Predicted road traffic noise levels of the Project
roads: up to 83 dB(A) Fixed Noise
Sources Impact ·
Predicted noise level: 27 – 56 dB(A) ·
Maximum allowable SWL: 59 – 109 dB(A) |
Road Traffic Noise ·
Annexes 5 and 13 of the EIAO-TM ·
EIAO-GN 12/2010 ·
L10(1 hour) 70dB(A) at 1m from the façade
of residential dwellings / noise sensitive temporary structures ·
L10(1 hour) 70dB(A) at 1m from the façade
of barracks ·
L10(1 hour) 65dB(A) at 1m from the façade
of educational institute and place of public worship Fixed Noise
Sources Impact ·
Annexes 5 and 13 of the EIAO-TM ·
Appropriate ANL -5 dB(A) as shown in Table 2 of IND-TM
or the prevailing background noise level |
Road Traffic Noise ·
Exceedance of the noise criteria by up to 14 dB(A) Fixed Noise
Sources Impact ·
No exceedance predicted. |
Road Traffic Noise ·
Provision of low noise
road surfacing (LNRS) ·
Provision of vertical barrier and cantilever noise
barriers on Project Road sections. ·
Provision of at-receiver mitigation measures such as
acoustic window / acoustic balcony. Fixed Noise
Sources Impact ·
No mitigation measure required. ·
If the future fixed noise source will exceed the
specified maximum SWLs as shown in Table 4.24 in the EIA report, the
relevant government department / future operator shall install acoustic
silencers, noise barrier or acoustic enclosure to ensure the noise compliance
of the fixed noise source. The relevant government department/future operator
shall also take into account the latest available
information at the time of detailed design to review and update the maximum
allowable SWL as appropriate. Noise commissioning test for fixed noise
sources will be carried out by relevant government departments/ future
operators before operation of fixed noise sources. |
·
No residual impacts anticipated. |
Water Quality Impact |
|||||
Construction Impact |
|||||
·
Representative water sensitive receivers in the vicinity of the Project and within 500m from the boundary of
the Project, covers the Deep Bay WCZ as designated under the WPCO |
The potential sources of water quality impact
associated with the construction works would include: ·
General construction activities; ·
Construction site run-off; ·
Construction works near watercourses; ·
Construction works in watercourses; ·
Removal or diversion of watercourses; ·
Removal or filling of ponds and wet areas; ·
Accidental spillage; ·
Sewage from construction workforce; and ·
Groundwater from contaminated areas, contaminated
site run-off and wastewater from land decontamination. |
·
Annexes 6 and 14 of the EIAO-TM ·
Water Quality Objectives for the Deep Bay WCZ ·
Technical Memorandum on Standards for Effluents
Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters
(TM-DSS) ·
Practical Note for Professional Persons (ProPECC) PN 1/23 and 2/23 ·
Hong Kong Planning Standards and Guidelines ·
Environmental, Transport and Works Bureau (ETWB)
Technical Circular (Works) No. 5/2005 |
·
N/A |
·
Mitigation measures and good site practices in ProPECC PN 2/23 “Construction Site Drainage” ·
Waste Disposal Ordinance ·
Provision of temporary sanitary facilities, such as
chemical toilets, for construction workforce ·
Precaution measures in ETWB Technical Circular
(Works) No. 5/2005 ·
Groundwater infiltration minimisation strategies and
post-grouting ·
Proper interception and
treatment of contaminated site runoff and wastewater from land
decontamination in compliance with the TM-DSS ·
Proper treatment or
recharge of contaminated groundwater in compliance with the TM-DSS |
·
No residual impacts anticipated |
Operation Impact |
|||||
·
Representative water sensitive receivers in the
vicinity of the Project and within 500m from the boundary of the Project,
covers the Deep Bay WCZ as designated under the WPCO |
Potential water quality impacts associated with the
operation phase include: ·
Sewage Disposal Strategy for the New Developments; ·
Emergency Discharge from the New STLMC EPP; ·
Sewage and Sewerage System; ·
Emergency Discharge from Sewage Pumping Stations
(SPSs); ·
Treated Effluent Reuse; ·
Surface Run-off from New Developments; ·
Changes of Hydrology and Potential Flooding Risk ·
Revitalisation and Greening of Drainage Channel Banks; ·
Maintenance flushing for RWSR; ·
Maintenance flushing for FWSR; ·
Potential Impact from Refuse Transfer Stations and RCPs ·
Spent Effluent from DCS; and ·
Maintenance of Drainage System. |
·
Annexes 6 and 14 of the EIAO-TM ·
Water Quality Objectives for the Deep Bay WCZ ·
Technical Memorandum on Standards for Effluents
Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters
(TM-DSS) ·
ProPECC PN 1/23 ·
ETWB TC (Works) No. 14/2004 ·
Guidelines for the Design of Small Sewage Treatment
Plant |
·
N/A |
·
Provide back-up power for dual power supply in case
of power failure to sustain the function of pumping and treatment facilities
at the EPP and SPS. ·
Provision of standby unit
for all major equipment in case of break down / emergency at the EPP and SPS. ·
Regular maintenance and checking of plant equipment. ·
Emergency Response Plan / Contingency Plan ·
Follow ETWB TC (Works) No. 14/2004 Maintenance of
Stormwater Drainage Systems and Natural Watercourse |
·
No adverse residual impacts anticipated |
Sewerage and Sewage
Treatment Implications |
|||||
·
Existing and planned sewerage system, sewage
treatment and disposal facilities |
·
Increase in sewage discharge arising from the population ·
Odour impact |
·
EPD
Report No. EPD/TP 1/05 Guidelines
for Estimating Sewage Flows (GESF) for Sewerage Infrastructure Planning
Version 1.0 ·
DSD
Sewage Manual Part 1 (Key Planning Issues and Gravity Collection System) ·
Annex
14 of EIAO-TM |
·
N/A |
·
Enclose
the pumping station inside building structure with odour control measures
such as scrubber and activated charcoal filter at the exhaust of the
ventilation system |
·
N/A |
Waste Management
Implications |
|||||
Construction Impact |
|||||
·
N/A |
·
Around 97,200 m3 of non-inert C&D
materials and 10,337,500 m3 of inert C&D materials will be
generated from site clearance, site formation works, construction of new
buildings and infrastructures. ·
Chemical wastes will be generated from Building
demolition, plant operation and maintenance of mechanical equipment, at a few
cubic metres per month. ·
Around 1,950 kg per day of general refuse will be
generated from construction works and site- based staff and workers ·
Small amount of excavated sediment from pond
excavation works ·
Insignificant amount of floating refuse from
construction activities along river channels or water bodies |
·
Annexes 7 and 15 of the EIAO-TM ·
Waste Disposal Ordinance (Cap. 354) ·
Waste Disposal (Chemical Waste) (General) Regulation
(Cap. 354C) ·
Waste Disposal (Charges for Disposal of Construction
Waste) Regulation (Cap. 354N) ·
Land (Miscellaneous Provisions) Ordinance (Cap. 28) ·
Public Health and Municipal Services Ordinance (Cap.
132BK) – Public Cleansing and Prevention of Nuisances Regulation ·
Air Pollution Control Ordinance (APCO) |
·
N/A |
·
Implementation of good site practices, waste
reduction measures and proper storage, collection
and transport of waste ·
Careful design, planning and good site management to
reduce generation of C&D materials ·
Monitoring of disposal of C&D waste with
trip-ticket system and installing CCTV on site ·
Precautionary measures for handling and disposal of
asbestos containing materials |
·
No residual impact anticipated |
Operation Impact |
|||||
·
N/A |
·
Small quantity of chemical wastes in the order of a
few cubic metres per month will be generated from public facilities and
maintenance of facilities and equipment ·
More than 500 tonnes per day of municipal solid
waste ·
About 160 m3/day of sewage sludge and 22
m3/day of screening and grits will be generated from the EPP |
·
Annexes 7 and 15 of the EIAO-TM ·
Waste Disposal Ordinance (Cap. 354) ·
Waste Disposal (Chemical Waste) (General) Regulation
(Cap. 354C) ·
Public Health and Municipal Services Ordinance (Cap.
132BK) – Public Cleansing and Prevention of Nuisances Regulation |
·
N/A |
·
Implementation of waste reduction measures and
proper storage, collection and transport of waste |
·
No residual impact anticipated |
Land Contamination |
|||||
·
Future occupants |
·
A total of 195 potentially contaminated sites are
currently used as container storage, equipment/machinery storage; recycling
facilities, vehicle repair/maintenance workshops, diesel refuelling, waste
dumping ground, metal workshops etc. |
·
Annex 19 of the EIAO-TM ·
Guidance Note for Contaminated Land Assessment and
Remediation (EPD, Revised in April 2023) ·
Practice Guide for Investigation and Remediation of
Contaminated Land (EPD, Revised in April 2023) ·
Guidance Manual for Use of Risk-based Remediation
Goals for Contaminated Land Management (EPD, Revised in April 2023) |
·
N/A |
·
The Project Proponent shall carry out site
investigation and sampling works in accordance with
the Contamination Assessment Plan for 9 potential contaminated sites with
detail site reconnaissance at a later stage. ·
Recommended works include: site re-appraisal, SI
works as well as submission of supplementary Contamination Assessment Plan(s)
(CAP(s)), Contamination Assessment Report(s) (CAR(s)) and Remediation Action
Plan(s) (RAP(s)) for the EPD’s approval after the sites are handed
over to project proponent for development.
If contaminated soil and/or groundwater were identified, remediation
should be carried out according to EPD's approved RAP(s) and Remediation Report(s)
(RR(s)) should be submitted to EPD for agreement after completion of the
remediation works. No development
works shall be commenced prior to EPD's agreement of the RR(s). ·
Any soil / groundwater contamination would be
identified and properly treated prior to the construction works. |
·
No residual impact anticipated. |
·
Future occupants |
·
High levels of naturally occurring arsenic in soil
is confirmed by ground investigation works. |
·
Previous EIA Report (AEIAR-175/2013 – North East New Territories New Development Areas) ·
Guidance Note for Contaminated Land Assessment and
Remediation (EPD, Revised in April 2023) ·
Practice Guide for Investigation and Remediation of
Contaminated Land (EPD, Revised in April 2023) ·
Guidance Manual for Use of Risk-based Remediation
Goals for Contaminated Land Management (EPD, Revised in April 2023) |
·
N/A |
·
Further arsenic assessment and a detailed treatment
approach has been proposed based on the Revised RODP. |
·
No residual impact anticipated. |
Landfill Gas Hazard |
|||||
Construction Impact |
|||||
·
Onsite construction workers |
·
Quantitative landfill gas hazard is conservatively
assessed as “Very Low” risk for construction phase based on the source,
pathway and target risk categories for the proposed development located
within the Consultation Zone of the Ngau Tam Mei Landfill. |
·
Annex 7 & 19 of the EIAO-TM ·
Landfill Gas Hazard Assessment Guidance Note |
·
N/A |
·
No precautionary measures are required |
·
No residual impact anticipated. |
Operation Impact |
|||||
·
Future occupants |
·
Quantitative landfill gas hazard is conservatively
assessed as “Low” for operation phase based on the source, pathway and target
risk categories for the proposed development located within the Consultation
Zone of the Ngau Tam Mei Landfill. |
·
Annex 7 & 19 of the EIAO-TM ·
Landfill Gas Hazard Assessment Guidance Note |
·
N/A |
·
Generic measures may be limited to passive gas
control such as provision of barriers to the movement of gas or high
permeability vents such as no-fines gravel in trenches between the landfill
and development. ·
The designer of the building works should undertake
detailed design of the mitigation measures during the detailed design stage. |
·
No residual impact anticipated. |
Ecological Impact (Terrestrial
and Aquatic) |
|||||
Construction Impact |
|||||
·
Recognised Sites of Conservation Importance ·
Wetland Habitats (e.g.
ponds, marsh / reed, watercourses) ·
Other terrestrial
habitats (e.g. woodland) ·
Egretries, Night Roosts, and
Flight Paths ·
Wildlife (including flora
and fauna species of conservation importance) |
·
Major permanent loss of
wetland habitats (ponds and other freshwater wetland habitats) ·
Permanent loss of woodland
habitat ·
Fragmentation of
terrestrial habitats ·
Potential direct Impact on
egretry and roosting sites ·
Potential obstruction of major flight paths ·
Direct impact on species of conservation importance
and associated habitats ·
Potential direct injury / mortality of wildlife
species ·
Indirect disturbance
impact (e.g. air quality, noise, light pollution, high-rise building, traffic
and visual) on sites of conservation importance, natural habitats
and associated wildlife in the vicinity |
·
Annexes 8 and 16 of the EIAO-TM ·
EIAO Guidance Notes Nos. 3/2010, 6/2010, 7/2010 and
10/2010 |
·
N/A |
·
Enhancement measure at Deep Bay
and wetland enhancement
in the proposed SPS WCP ·
Avoided loss of woodland at Pang Loon Tei ·
Off-site woodland compensation ·
Minimisation of direct encroachment,
pre-construction survey and establishing buffer area for both MPLV and MPV Egretries ·
Seasonal control of construction works at egretries and night roosts ·
Pre-construction survey, re-provision of roosting
substratum for night roosts and establishing buffer area ·
Pre-construction survey and transplantation /
translocation, and nest control measures for species of conservation
importance ·
Establishment of hoarding and regular auditing ·
Using non-transparent panels for noise enclosure,
adopting non-glaring tinted materials, or superimposing dark patterns at the majority of glazing along barriers and structures ·
Good site practices with mitigation measures for
noise, dust, water quality impacts |
·
No adverse residual
impact anticipated |
Operation Impact |
|||||
·
Recognised Sites of Conservation Importance ·
Wetland Habitats (e.g.
ponds, marsh / reed, watercourses) ·
Other terrestrial
habitats (e.g. woodland) ·
Egretries, Night Roosts, and
Flight Paths |
·
Disturbance impacts (e.g. air quality, noise, light
pollution, high-rise building, traffic and visual) to the site of
conservation importance, natural habitats and
associated wildlife in the vicinity ·
Potential obstruction of flight path ·
Bird collision with man-made structures |
·
Same as construction phase |
·
N/A |
·
Wetland enhancement in the proposed SPS WCP ·
Establishment of Open Space around MPLV
Egretry with enhancement measures ·
Provision of NBA and eco-interface and landscape
buffer along the edge of the Sam Po Shue WCP with stepped building height
towards to the wetland to minimise disturbances to the wetlands concerned ·
Provision of NBA with stepped building height to
preserve birds’ flight paths to/from the MPLV Egretry
and MPV Egretry and the east-west birds’ flight
corridor in the northern part of the Project Area ·
Provision of wildlife corridors ·
Using non-transparent panels for noise enclosure,
adopting non-glaring tinted materials, or superimposing dark patterns at the majority of glazing along barriers and structures ·
Greening opportunity on buildings such as green
façades and green roofs |
·
No adverse residual impact anticipated |
Fisheries Impact |
|||||
·
Pond Culture Fisheries (aquaculture activities &
fisheries production) |
·
Direct loss of active fishponds and inactive
fishponds ·
Secondary Impact from wetland compensation |
·
EIAO-TM Annexes 9 & 17 ·
Water Pollution Control Ordinance (Cap. 358) |
·
N/A |
·
Fisheries enhancement area ·
Fisheries Research Centre ·
Improving fisheries production by incorporating
modernised aquaculture and innovative technological advancement for fisheries
management |
·
No residual impact anticipated |
Cultural Heritage Impact |
|||||
Construction Impact |
|||||
·
Cultural
heritage and other identified items |
·
Indirect
impacts of ground-borne vibration, settlement and tilting would be
anticipated on a grade 3 historic building, namely Entrance Gate, Enclosing
Walls and Shrine, Yan Shau Wai (HBN186). ·
For
other identified items, indirect impacts of ground-borne vibration,
settlement and tilting would be anticipated on seven (7) non-building
structures, namely Gurkha Cemetery (BH03), Mans’ Boundary
Stone (BH06), Grave of Man Lun Fung ("麒麟吐玉書”)
(BH07), Grave of Man Chung Luen (BH08), Grave of Man Chu Shui (BH10), Grave
of Mrs Man Leung (BH11) and Grave of Chong Yin Kei
(BH12), as well as two (2) buildings, namely,
Yeung Hau Temple (San Tin) (MPT01) and
Structure between No. 5 and No. 7, Shek Wu Wai (SWW01). ·
Direct
impact would be anticipated to Tin Tak Heroes Temple (MPL01), Mai Po Lung
Vegetable Marketing Co-operative Society Ltd. (MPL02), Sun Tin Vegetable
Marketing Co-operative Society Ltd. (SHT01). ·
Direct
impact would be anticipated to seven (7) archaeologically sensitive areas
(ASA), namely Hop Shing Wai ASA, Mai Po ASA, Mai Po Lung (South) ASA, Shek Wu
Wai ASA, Siu Hum Tsuen (West) ASA, Siu Hum Tsuen (East) ASA and Pang Loon Tei
ASA. ·
Mai Po Lung (North) ASA is reserved as an egretry. No impact
on archaeology is anticipated, no mitigation measure is required, subjected
to the detailed design of this area.
Should construction works involving soil disturbance are anticipated
during the detailed design stage, project proponent should review the impact
assessment and propose adequate mitigation measures to AMO for approval. |
·
EIAO-TM
Annexes 10 and 19 ·
Guidelines
for Cultural Heritage Impact Assessment ·
Antiquities and Monuments Ordinance (A&MO)
(Cap.53) ·
Buildings Ordinance |
·
N/A |
Monitoring of vibration, settlement and tilting ·
Monitoring
of vibration, settlement and tilting incorporated with a set of Alert, Alarm
and Action (3As) system shall be employed for Entrance Gate, Enclosing Walls
and Shrine, Yan Shau Wai (HBN186) (grade 3 historic building) during the
construction phase. ·
Monitoring
proposal should be submitted to AMO and
relevant stakeholder(s) for consideration before commencement of works. ·
Records
of monitoring should be submitted regularly to AMO. ·
AMO
should be alerted in case any irregularities are observed. Baseline
condition survey and baseline vibration impact assessment ·
Baseline
condition survey and baseline vibration impact assessment should be conducted
for the seven (7) non-building structures by a qualified building surveyor or
qualified structural engineer during pre-construction stage of the proposed
developments. ·
Survey
results shall be submitted to AMO for record. Monitoring of vibration, settlement and tilting ·
Monitoring
of vibration, settlement and tilting incorporated with a set of Alert, Alarm
and Action (3As) system shall be employed for other identified items
including seven (7) non-building structures and two (2) buildings during the
construction phase under Buildings Ordinance.
The actual 3As criteria shall be further confirmed via an assessment
on the effects of ground-borne vibrations, settlements and tilting on these
items. ·
Prior
agreement and consent should be sought from the owner(s), stakeholder(s) and relevant Government department(s) for the
installation of monitoring points on the building before commencement of the
works. ·
Record
of monitoring should be submitted regularly to the Buildings Department
during the construction under Buildings Ordinance. ·
Buildings
Department should be alerted in case any irregularities are observed. Safe
Access ·
A
safe access route shall be maintained for visitors during the construction
stage for Yeung Hau Temple (San Tin) (MPT01), Gurkha Cemetery (BH03), Grave
of Man Lun Fung ("麒麟吐玉書”)
(BH07), Grave of Man Chung Luen (BH08), Grave of Man Chu Shui (BH10) and
Grave of Mrs Man Leung (BH11). ·
Physical
protective barriers/ covers or intervention/cushioning materials, including
but not limited to covering or sheltering, shall be provided during the
proposed construction works to separate the works areas from Yeung Hau Temple
(San Tin) (MPT01). ·
No
piling works shall be allowed within the protective zone. ·
No
worker or any construction related equipment(s) and material(s) should
trespass the protective zone. ·
The
contractor should propose the actual extent of the protective zone and
suitable protective covering materials to the satisfaction of AMO prior to
the commencement of the proposed construction works. Dust Suppression ·
Implementation
of mitigation measures in the Air Pollution Control (Construction Dust)
Regulation, dust suppression measures and good site practice should be
observed by the project proponent during the construction phase in order to avoid dust accumulation on the Yeung Hau
Temple (San Tin) (MPT01) and Grave of Chong Yin Kei (BH12). Cartographic
and Photographic Record ·
Cartographic and photographic records, and other
documentation means (such as 3D scanning or photogrammetry), on the Tin Tak
Heroes Temple (MPL01), Mai Po Lung Vegetable Marketing Co-operative Society
Ltd. (MPL02), Sun Tin Vegetable Marketing Co-operative Society Ltd. (SHT01)
should be conducted before any works to commence. A copy of the
documentation should be provided to AMO for record. Archaeological Watching Brief ·
Archaeological Watching Brief is recommended to
be carried out in Shek Wu Wai ASA and Mai Po Lung (South) ASA should works
involve soil disturbance occurred (such as site formation) during the
construction phase. ·
The
scope, methodology and programme of the
archaeological survey shall be agreed with AMO. Further Archaeological Survey ·
Further
archaeological survey is required at later stage after land resumption but
before site formation for these areas with archaeological potential, namely
Hop Shing Wai ASA, Mai Po ASA, Siu Hum Tsuen (West) ASA, Siu Hum Tsuen (East)
ASA and Pang Loon Tei ASA. ·
The
scope, methodology and programme of the
archaeological survey shall be agreed with AMO. Precautionary Measure ·
If
antiquities or supposed antiquities under the Antiquities and Monuments
Ordinance (Cap. 53) are discovered, the project proponent is required to inform
AMO immediately for discussion of appropriate mitigation measures to be
agreed by AMO before implementation by the project proponent to the
satisfaction of AMO. |
·
No residual impact anticipated |
Operation Impact |
|||||
·
Cultural heritage and other identified items |
·
No adverse impact would be anticipated on both built
heritages, other identified items and archaeology
during the operation phase. |
·
EIAO-TM Annexes 10 and 19 ·
Guidelines for Cultural Heritage Impact Assessment |
·
N/A |
·
No mitigation measure would be required |
·
No residual impact
anticipated |
Landscape and Visual
Impacts |
|||||
Construction Impact |
|||||
·
Landscape Resources (LRs) |
·
Insubstantial impact on Ponds near Ngau Tam Mei
(LR3.3), Natural Watercourse (LR4) ·
Slight impact on modified watercourse (LR5), plantation
on slope (LR12.1), shrubland (LR13), and grassland (LR14) ·
Moderate impact on Marsh/ Reedbed (LR1),
Compensatory wetland (LR2), Semi-Natural Watercourse (LR6), Seasonal Wet
Grassland (LR7), Woodland (LR10), Mixed Woodland (LR11), Plantation along
roadside (LR12.2), Village/ Orchard (LR15), Vegetation in developed
(Including residential area and man-made structure) (LR16), Vegetation in
Waste land/open storage/ temporary area (LR17) ·
Substantial impact on Ponds around San Tin and Sam
Po Shue (LR3.1), Ponds around Siu Hum Tsuen and Shek Wu Wai San Tsuen
(LR3.2), Wet Agricultural Land (LR8), Dy Agricultural Land (LR9) |
·
Annexes 10 and 18 of the EIAO-TM ·
EIAO-GN 8/2010
(Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
·
N/A |
·
Preservation of existing vegetation ·
Transplantation of existing trees ·
Reinstatement of temporarily disturbed landscape areas ·
Minimising disturbance on watercourses ·
Minimising topographical changes ·
Construction of decorative hoarding around
construction works ·
Advancing planting of screen planting ·
Management of construction activities and facilities ·
Creating interface between ponds, wetland
and the proposed Project |
·
Insubstantial residual impact on LR3.3, LR4 ·
Slight residual impact on LR5, LR12.1, LR13, LR14 ·
Moderate residual impact on LR1, LR2, LR6, LR7,
LR10, LR11, LR12.2, LR15, LR16, LR17 ·
Substantial residual impact on LR3.1, LR3.2, LR8,
LR9 |
·
Landscape Character Areas (LCAs) |
·
Insubstantial impact on Institutional Landscape
(LCA8) ·
Slight impact on Urban Peripheral Village Landscape
(LCA5), Miscellaneous Rural Fringe Landscape (LCA6), Comprehensive
Residential Development (LCA7), Transportation Corridor Landscape (LCA9) ·
Moderate impact on Settled Valley Landscape (LCA1),
Upland And Hillside Landscape (LCA2), Miscellaneous
Urban Fringe Landscape (LCA10) ·
Substantial impact on Rural Inland Plain Landscape
(LCA4), Rural Coastal Plain Landscape (LCA3) |
·
Annexes 10 and 18 of the EIAO-TM ·
EIAO-GN 8/2010
(Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
·
N/A |
·
Preservation of existing vegetation ·
Transplantation of existing trees ·
Reinstatement of temporarily disturbed landscape areas ·
Minimising disturbance on watercourses ·
Minimising topographical changes ·
Construction of decorative hoarding around
construction works ·
Advancing planting of screen planting ·
Management of construction activities and facilities ·
Creating interface between ponds, wetland
and the proposed project |
·
Insubstantial residual impact on LCA8 ·
Slight residual impact on LCA5, LCA6, LCA7, LCA9 ·
Moderate residual impact on LCA1, LCA2 and LCA10 ·
Substantial residual impact on LCA3, LCA4 |
·
Visually Sensitive Receivers (VSRs) |
·
Insubstantial impact on Residents of Fair View Park
(R7), Residents of Proposed Kwu Tung New Town
Development and Ma Tso Lung area (R8), Workers around Castle peak road (Mai
Po section) (O2) ·
Slight impact on Residents of Vineyard and low-rise
residential area along Tam Mei Road (R5), Users of MTR Lok Ma Chau Station
(T2), Traveler of Fan Ling Highway (T3), Workers of Open Storage/ Industrial
usage of Ngau Tam Mei (O1), Industrial and potential tertiary users of Kwu Tung and Pak Shek Au (O4), Workers in open (O5), Lok
Ma Chau Police Station (GIC 1) ·
Moderate impact on Mid-rise residents of Maple
Garden, Palm Springs and Royal Palm (R1), Residents of Mai Po San Tsuen, Mai
Po Lo Wai (R2), Residents of Chau Tau Village ,Poon Uk
Tsuen (R6), Future residents of the Loop (R9), Residents of Shek Wu Wai ,
recreational users of Shek Wu Wai Playground (R10), Residents of Fisherman
San Tsuen (R11), Travelers of San Tin Highway (T1), Visitors of Mai Po Marsh
Wetland reserve (REC 2), Park visitors of San Tin park and Man Tin Cheung
Park (REC 4), Hikers of Lam Tsuen Country Park (REC 5), Future users of SPS
WCP (REC 6), Farmer in Agricultural land near Lok Ma Chau Control
Point (O3), Future workers of the Loop development (O6), Users of Gurkha
Cemetery (GIC 2), Users of San Tin Barracks (GIC 3), Users of Tam Mei Barracks
(GIC 4) ·
Substantial impact on Hikers along Ngau Tam Shan
Hiking Trail (REC 1) |
·
Annexes 10 and 18 of the EIAO-TM ·
EIAO-GN 8/2010
(Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
·
N/A |
·
Preservation of existing vegetation ·
Transplantation of existing trees ·
Reinstatement of temporarily disturbed landscape areas ·
Minimising disturbance on watercourses ·
Management of construction activities and facilities ·
Control of night-time lighting ·
Construction of decorative hoarding around
construction works ·
Advancing planting of screen planting ·
Creating interface between ponds, wetland
and the proposed project |
·
Insubstantial residual impact on R4, R7, R8, O2 ·
Slight residual impact on R5, T2, T3, O1, O4, O5,
GIC 1 ·
Moderate residual impact on R1, R2, R6, R9, R10,
R11, T1, REC 2, REC 4, REC 5, REC 6, O3, O6, GIC 1, GIC 2, GIC 3 ·
Substantial residual impact on R3, REC1, REC 3 |
Operation Impact |
|||||
·
Landscape Resources (LRs) |
·
Insubstantial impact on LR2, LR3.3, LR4 ·
Slight impact on LR2, LR5, LR12.1, LR13, LR14 ·
Moderate impact on LR1, LR3.1, LR6, LR7, LR10, LR11,
LR12.2, LR15, LR16, LR17 ·
Substantial impact on LR3.1, LR3.2, LR8, LR9 |
·
Annexes 10 and 18 of the EIAO-TM ·
EIAO-GN 8/2010
(Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
·
N/A |
·
Sensitive and aesthetically pleasing design of
aboveground structures ·
Landscape integration of build development ·
Provision of roadside planting/ amenity planting/
peripheral screening or planting ·
Provision of new tree planting ·
Incorporation of green roof ·
Watercourse impact mitigation within WCA ·
Revitalisation and naturalisation of river to create
a blue green network ·
Maximise greening on engineering structures and surfaces ·
Landscape treatment on slope ·
Sensitive design of landscape areas / provision of
open space ·
Creation of landscape buffer ·
Watercourse impact mitigation within WCA |
·
Insubstantial residual impact on Day 1: LR2, LR3.3,
LR4, LR5, LR12.1, LR13, LR14 ·
Slight residual impact on Day 1: LR1, LR3.1, LR6,
LR7, LR10, LR11, LR12.2, LR15, LR16, LR17 ·
Moderate residual impact on Day 1: LR1, LR2, LR3.1,
LR6, LR7, LR10, LR11, LR12.2, LR16, LR17 ·
Substantial residual impact on Day 1: LR3.2, LR8,
LR9 ·
Insubstantial residual impact in Year 10: LR1, LR2,
LR3.1, LR3.3, LR4, LR5, LR6, LR7, LR10, LR11, LR12.1, LR12.2, LR13, LR14,
LR15, LR16, LR17 ·
Slight residual impact in Year 10: LR3.2, LR8, LR9 |
·
Landscape Character Areas (LCAs) |
·
Insubstantial impact on LCA8 ·
Slight impact on LCA5, LCA6, LCA7, LCA9, LCA10 ·
Moderate impact on LCA1, LCA2 ·
Substantial impact: LCA3, LCA4 |
·
Annexes 10 and 18 of the EIAO-TM ·
EIAO-GN 8/2010
(Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
·
N/A |
·
Sensitive and aesthetically pleasing Design of
Aboveground structures ·
Landscape integration of Build Development ·
Provision of roadside Planting/ Amenity planting/
peripheral screening or planting ·
Provision of new tree planting ·
Incorporation of Green Roof ·
Sensitive design of noise barriers ·
Revitalisation and naturalisation of river to create
a Blue green network ·
Landscape treatment on slope ·
Sensitive design of landscape areas / provision of
Open Space ·
Off-site woodland compensation ·
Creation of landscape buffer ·
Stepped building height profile. ·
Provision of breezeway/ airpaths ·
Watercourse impact mitigation within WCA ·
Maximise greening on engineering structures and surfaces ·
Watercourse impact mitigation within WCA |
·
Insubstantial residual impact on Day 1: LCA5- LCA10 ·
Slight residual impact on Day 1: LCA1 and LCA2 ·
Moderate residual impact on Day 1: LCA3 and LCA4 ·
Insubstantial residual impact in Year 10 on all LCAs
except LCA3 and LCA4 where residual impact would be slight |
·
Visually Sensitive Receivers (VSRs) |
·
Insubstantial impact on R4, R7, R8, O2, ·
Slight impact on R5, T3, O1, O4, O5, GIC 1 ·
Moderate impact on R1, R2, R6, R9, R10, R11, T1, T2,
REC 2, REC 4, REC 5, REC 6, O3, O6, GIC 2, GIC 3, GIC 4 ·
Substantial impact on R3, REC1, REC 3 |
·
Annexes 10 and 18 of the EIAO-TM ·
EIAO-GN 8/2010
(Preparation of LVIA under the Environmental Impact Assessment Ordinance) |
·
N/A |
·
Sensitive and aesthetically pleasing Design of
Aboveground structures ·
Landscape integration of Build Development ·
Provision of roadside Planting/ Amenity planting/
peripheral screening or planting ·
Provision of new tree planting ·
Incorporation of Green Roof ·
Sensitive design of noise barriers ·
Control of Night-time Lighting Glare ·
Revitalisation and naturalisation of river to create
a Blue green network ·
Maximise greening on engineering structures and surfaces ·
Landscape treatment on slope ·
Sensitive design of landscape areas / provision of
Open Space ·
Off-site woodland compensation ·
Creation of landscape buffer ·
Stepped building height profile ·
Provision of breezeway/ airpaths ·
Provision of view corridor ·
Sensitive layout design of above-ground structures ·
Watercourse impact mitigation within WCA |
·
Insubstantial residual impact on Day 1: R4, R7, R8 ·
Slight residual impact on Day 1: R5, T3, O1, O4, O5,
GIC 1 ·
Moderate residual impact on Day 1: R1, R2, R6, R9,
R10, R11, T1, T2, REC 2, REC 4, REC 5, O3, O6, GIC 2, GIC 3, GIC 4 ·
Substantial residual impact on Day 1: R3, REC1, REC
3 ·
Insubstantial residual impact in Year 10: R4, R7,
R8, T3, O1, O2, O4, O5, GIC 1 ·
Slight residual impact in Year 10: R1, R5, R6, REC
2, REC 4, GIC 4 ·
Moderate residual impact in Year 10: R2, R10, R11,
T1, T2, REC5, REC6, O3, O6, GIC2, GIC3 ·
Substantial residual impact in Year 10: R3, REC1,
REC 3 |
Hazard to Life |
|||||
·
Existing and planned population in the vicinity of
the HP Gas Pipeline, EPP and the 2 GFSs |
· The off-site individual risk level is far below 1×10-5 per
year, it is considered acceptable and in
compliance with the relevant criterion in Annex 4 of EIAO-TM ·
The societal risks fall within the “Acceptable”
region in both assessment years |
·
Annex 4 of the EIAO-TM |
·
N/A |
·
No adverse impact is anticipated. Nonetheless,
implementation of good safety practices and design measures for the EPP are
recommended. |
·
No residual impact anticipated |
Electric and Magnetic Field
|
|||||
·
Existing 400kV overhead cable |
·
Electric field strength measured ranged from 0.2 V/m
to 198 V/m ·
Magnetic flux measured ranged from 0.04 μT to 1.48 μT |
·
Hong Kong Planning Standards and Guidelines ·
International Commission on Non-ionizing Radiation
Protection (Standard for General Public Exposure: 5,000 V/m & 100 μT; Standard for Occupational Exposure 10,000 V/m &
500 μT) |
·
N/A |
·
Not necessary |
·
No residual impact anticipated |
[1] The 253 ha will compensate for the potential impact on pond habitats in the northern portion of the Project site, including the direct loss of about 89 ha of contiguous pond habitat due to filling of fishponds within the development boundary of San Tin Technopole, and indirect disturbance to adjacent contiguous pond habitat of about 63 ha outside the development boundary of San Tin Technopole.
[2] The 35 ha will compensate for the potential impact on
other freshwater wetland habitats, including the direct loss of about 28 ha (at
a compensation ratio of 1:1) within the development boundary of San Tin
Technopole, and indirect disturbance to about 8 ha outside of development
boundary (at a compensation ratio of 1:1 to 1:0.5, depending on the distance of
habitat from development boundary).