TABLE OF CONTENTS
16. ENVIRONEMTNAL MONITORING
AND AUDIT REQUIREMENTS
16.5 Sewerage
and Sewage Treatment Implications
16.6 Waste
Management Implications
16.8 Ecology
(Terrestrial and Marine)
16.14 Electric and
Magnetic Fields
List of Tables
Table 16.1 Summary of Key EM&A Requirements for DP1, DP2 and
DP3
Operation
Phase
Protection of Floral Species of Conservation Importance
Protection of Faunal Species of Conservation Importance
Translocation of Affected Coral Colonies
Monitoring of Mitigation Measures for Disturbance Impact
Built Heritage
Archaeology
Marine Archaeology
Construction Phase
· At the ground surface before excavation commences;
· Immediately before any worker enters the excavation;
· At the beginning of each working day for the entire period the excavation remains open; and
· Periodically through the working day whilst workers are in the excavation.
· Directly after the excavation has been completed; and
· Periodically whilst the excavation remains open.
Operational Phase
· LFG monitoring should be carried out within the ground floor of buildings and enclosures within the 250 m Consultation zone, prior to the operation and for the first year of operation, monthly monitoring is recommended. Should the monitoring reveal the presence of landfill gas joints sealings shall be inspected and sealed.
· During the operational phase of the Project, prior to entry into service rooms / voids, manholes and chambers, pre-entry monitoring for landfill gases shall be conducted, following the requirements of the Factories and Industrial Undertaking (Confined Spaces) Regulation is recommended.
· In addition, if any construction is required for the maintenance work during operational stage, the responsible party should follow the monitoring works stated in Chapter 8 - Hazards Arising During Construction of the LFGHA Guidance Note.
· Any service voids, manholes or chambers which are large enough to permit access to personnel should be subject to entry safety procedures. Works in confined spaces are controlled by the Factories and Industrial Undertakings (Confined Spaces) Regulation of the Factories and Industrial Undertakings Ordinance and the Safety Guide to Working in Confined Spaces should be followed to ensure compliance with the Regulation.
Table 16.1 Summary of Key EM&A Requirements for DP1, DP2 and DP3
Environmental Impact |
Summary of EM&A Requirements |
|
DP 1 – Construction and
operation of a carriageway bridge for motor vehicles |
|
|
Air Quality |
·
Construction dust monitoring and regular site audit during
construction period |
|
Noise |
·
Construction noise monitoring and regular site audit during
construction period ·
Monitoring of road traffic noise impact during 1st year
after road opening or full population intake of protected NSRs, whichever is
the latest. |
|
Water Quality |
·
Marine water quality monitoring and regular site
audit during construction period |
|
Sewerage and Sewage Treatment Implications |
·
N/A |
|
Waste Management Implications |
·
Regular audits and site inspections should be
carried out during construction phase |
|
Land Contamination |
·
If the recommended further works confirm remediation works is
required, regular site audit during construction phase is required to ensure the
implementation of proposed mitigation measures effectively |
|
Ecology |
·
Regular site audit should be carried out throughout the construction
phase |
|
Fisheries |
·
N/A |
|
Landscape and Visual |
·
Landscape and
visual monitoring during construction and 12-month establishment period
during operation phase. |
|
Cultural Heritage |
·
If antiquities or supposed antiquities under the
Antiquities and Monuments Ordinance (Cap. 53) are discovered during the construction
works within the Project boundary of TKO 137 and TKO 132, the project proponent is required to inform AMO
immediately for discussion of appropriate mitigation measures to be agreed by
AMO before implementation by the project proponent to the satisfaction of
AMO. |
|
Hazard to Life |
·
N/A |
|
Landfill Gas Hazard |
·
No EM&A required as construction and operation
of DP1 is outside the landfill 250 m Consultation Zone |
|
Electric and Magnetic Field |
·
N/A |
|
DP 2 - Construction and
operation of Reclamation works |
|
|
Air Quality |
·
Construction dust monitoring and regular site audit
during construction period |
|
Noise |
·
Construction noise monitoring and regular site audit during
construction period |
|
Water Quality |
·
Marine water quality monitoring and regular site
audit during the marine construction period. |
|
Sewerage and Sewage Treatment Implications |
·
NA |
|
Waste Management Implications |
·
Regular audits and site inspections should be
carried out during construction phase |
|
Land Contamination |
·
N/A |
|
Ecology |
·
Translocation of affected coral colonies |
|
Fisheries |
·
N/A |
|
Landscape and Visual |
·
Landscape and visual monitoring during construction
and 12-month establishment period during operation phase |
|
Cultural Heritage |
·
Monitoring of
ground-borne vibration, tilting and ground settlement should be employed for
Fat Tau Chau House Ruin SAI (SAI185). ·
Air Pollution Control (Construction Dust) Regulation
shall be followed for Fat Tau Chau House Ruin SAI (SAI185). Dust suppression measures and good site
practice should be observed for Fat Tau Chau House Ruin SAI (SAI185). ·
The areas with data gaps and the uninvestigated anomaly should be
designated as archaeological exclusion zones (AEZs) during the marine works
of the Project to ensure no impact on the seabed in these locations from
anchoring of work vessels. ·
If antiquities or
supposed antiquities under the Antiquities and Monuments Ordinance (Cap. 53)
are discovered during the construction works within the Project boundary of
TKO 137 and TKO 132, the project proponent is required to inform AMO
immediately for discussion of appropriate mitigation measures to be agreed by
AMO before implementation by the project proponent to the satisfaction of
AMO. |
|
Hazard to Life |
·
N/A |
|
Landfill Gas Hazard |
·
No EM&A required as construction and operation
of DP2 is outside the landfill 250 m Consultation Zone |
|
Electric and Magnetic Field |
·
N/A |
|
DP3 - Construction and
operation of TKO 137 Effluent Polishing Plant |
|
|
Air Quality |
·
Construction dust monitoring and regular site audit
during construction period ·
Odour monitoring (in term of H2S concentration)
at inlets and outlets of each DO unit in the first three years upon operation
of EPP ·
Odour patrol during the period of regular and ad hoc
maintenance or cleaning of the deodorizing unit of EPP ·
Odour Complaint Registration System for EPP
introduced in EM&A Programme |
|
Noise |
·
Construction noise monitoring and regular site audit during
construction period ·
Operation noise monitoring for fixed plants during
the testing and commissioning stage, subject to detail requirements to be
confirmed in the FNMP |
|
Water Quality |
·
Regular site audit during construction period ·
Marine water quality monitoring and audit during the
first year of EPP operation and in case of emergency discharge from the EPP |
|
Sewerage and Sewage Treatment Implications |
·
NA |
|
Waste Management Implications |
·
Regular audits and site inspections should be
carried out during construction phase |
|
Land Contamination |
·
If the recommended further works confirm remediation works is
required, regular site audit during construction phase is required to ensure the
implementation of proposed mitigation measures effectively |
|
Ecology |
·
Regular site audit should be carried out throughout the construction
phase |
|
Fisheries |
·
N/A |
|
Landscape and Visual |
·
Landscape and visual monitoring during construction
and 12-month establishment period during operation phase |
|
Cultural Heritage |
·
If antiquities or supposed antiquities under the
Antiquities and Monuments Ordinance (Cap. 53) are discovered during the
construction works within the Project boundary of TKO 137 and TKO 132, the project proponent is required to inform AMO
immediately for discussion of appropriate mitigation measures to be agreed by
AMO before implementation by the project proponent to the satisfaction of
AMO. |
|
Hazard to Life |
·
N/A |
|
Landfill Gas Hazard |
·
Project proponents of future developments located
within the 250 m Consultant Zone shall conduct a detailed LFGHA following the
LFGHA Guidance Note issued by EPD at detailed design stage to re-confirm the
landfill gas hazard risk and undertake detailed design of the mitigation
measures, as appropriate. ·
The monitoring programme (e.g. proposed parameters,
locations and frequency of landfill gas monitoring) should be submitted to
EPD for approval in a detailed LFGHA during the detailed design stage. |
|
Electric and Magnetic Field |
·
N/A |
|