1                    INTRODUCTION

1.1              Project Background

1.1.1          The Central and Wan Chai Reclamation Feasibility Study, completed in 1989, examined the development of approximately 108 hectares of new reclamation and 60 hectares of water basin, together with existing land to be redeveloped, along the Central, Wan Chai and Causeway Bay shoreline.  The study also identified the need for an east-west strategic route along the northshore of Hong Kong Island, to relieve the overloaded traffic on the existing east-west routes.  This trunk route comprised a tunnel section through Central and Wan Chai (the Central-Wan Chai Bypass) and an elevated roadway along the Causeway Bay shoreline (the Island Eastern Corridor Link), connecting to the existing Island Eastern Corridor.

1.1.2          The Central and Wan Chai Reclamation Feasibility Study proposed development to be carried out in five stages.  Central Reclamation Phase I, for accommodating the Hong Kong Central Station of the Airport Railway, was completed in June 1998.  Central Reclamation Phase II, at the previous Tamar Basin, was completed in September 1997.  Wan Chai Reclamation Phase I, for the extension to the Hong Kong Convention and Exhibition Centre (HKCEC), was completed in July 1997.  Detailed design for Central Reclamation Phase III (CRIII) is currently in progress.

1.1.3          The Wan Chai Development Phase II (WDII) is the fifth phase in the implementation of the Central and Wan Chai Reclamation, following Central Reclamation Phases I, II and III and Wan Chai Reclamation Phase I.  Figure 1 indicates the site location of the WDII project.

1.1.4          As a result of considerable public concern over reclamation in the Victoria Harbour, the Protection of the Harbour Ordinance was enacted on 30 June 1997, and was amended by the Protection of the Harbour (Amendment) Ordinance 1999 enacted on 2 December 1999 (the Harbour Ordinances).  Under the Harbour Ordinances, the Harbour is to be protected and preserved as a special public asset and a natural heritage and there shall be a presumption against reclamation in the Harbour.  The reclamation for CRIII as proposed in the original scope of the Central and Wan Chai Reclamation was reviewed and subsequently reduced.  To comply with the Harbour Ordinances, the WDII project (hereafter the ‘Project’) has also to be reviewed.

1.1.5          The main objective of the Project is, now, not to reclaim land for development, but to provide land for key transport infrastructure and facilities.  The key transport infrastructure for which land needs to be provided comprises the Central-Wan Chai Bypass (CWB), the Island Eastern Corridor Link (IECL), the proposed North Hong Kong Island Line (NIL) and the proposed fourth rail harbour crossing section of the Shatin to Central Link (SCL).  In addition, the Project will also include the reprovisioning of any existing waterfront facilities affected by the Project as well as any necessary measures to improve the resultant shoreline so that an attractive waterfront promenade would be created for the enjoyment of the public.

1.2              Objectives of the EIA Study

1.2.1          According to the EIA Study Brief, the objectives of this EIA Study is to provide information on the nature and extent of environmental impacts arising from the WDII development works.  All related activities taking place concurrently shall also be assessed to investigate the potential cumulative impacts.  This information will contribute to decision on whether or not:

(a)    the adverse environmental impacts are within the established  standards / guidelines;

(b)    there are any conditions and requirements for the detailed design, construction and operation, of the proposed Project; and

(c)    the residual impacts (impacts after the proposed mitigation measures are implemented) are within the established standards / guidelines.

1.3              Consideration of Environmental Impact Assessment Ordinance

1.3.1          The proposed Project is an engineering feasibility study of an urban development project with a study area covering more than 20 ha.  Under the Environmental Impact Assessment Ordinance (EIAO), this Project is classified as a Schedule 3 Designated Project (DP) under item 1 of the Schedule 3 “Major Designated Projects Requiring Environmental Impact Assessment Reports”.  A detailed environmental assessment for approval by the Director of Environmental Protection (DEP) is required.

1.3.2          The Project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated.  Table 1.1 summarises the five individual DPs under this Project.  Figure 2 shows the locations of these Schedule 2 DPs.

Table 1.1         Schedule 2 Designated Projects involved in the Wan Chai Development Phase II under the EIAO

Designated Project

EIAO Reference

Remarks

Reclamation works (including associated dredging works)

Schedule 2, Part I, C.1

Reclamation more than 5 ha in size

WDII major roads (including Road P2)

Schedule 2, Part I, A.1

Primary / district distributor roads

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.6

A submarine sewage outfall

Kellett Island Marina

Schedule 2, Part I, O.2

A marina designed to provide moorings for not less than 30 vessels used primary for pleasure or recreation

Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation which is less than 100 m from a seawater intake point.

 

1.3.3          While this EIA Study is undertaken as part of the Comprehensive Feasibility Study of WDII and under Schedule 3 of the EIAO, the EIA Report has also included environmental impact assessments of the Schedule 2 DPs identified in Table 1.1 above, for the application of EPs for individual Schedule 2 DPs.

1.3.4          The CWB&IECL project, which includes road sections within the WDII project area, is a trunk road and is considered as a DP under Schedule 2, Part I, A.1.  An EIA has been conducted separately by Highway Department's Consultant for the CWB&IECL project in accordance with Schedule 2 of the EIAO.

1.3.5          The WDII study has also confirmed that there will be a need, after 2016, for the North-South Link, which provides a direct link to the Wan Chai hinterland in order to overcome traffic congestion on the existing Canal Road Corridor.  However, the North-South Link and its associated slip road connections will be implemented as separate items from the current WDII project, at a later stage.  It will be subject to detailed engineering assessment to confirm the technical viability.  The North-South Link is a DP under the EIAO and an EIA will be required to confirm its environmental acceptability under the EIAO.  The current EIA for WDII has not included the North-South Link.

 


2                    PROJECT DESCRIPTION

2.1              Site Location and Study Area

2.1.1          The WDII Study Area is demarcated by Hing Fat Street to the east, Victoria Park Road and Gloucester Road to the south and Fenwick Pier Street to the west.

2.1.2          The study area comprises urban development on existing reclaimed land along the Wan Chai and Causeway Bay shoreline, together with existing seabed along the shoreline that will be reclaimed under the Project.  Major land uses within the study area include the HKCEC Extension, the Wan Chai ferry piers, the Wan Chai Public Cargo Working Area (PCWA), the Royal Hong Kong Yacht Club (RHKYC), the Police Officers' Club and the Causeway Bay Typhoon Shelter.

2.1.3          New land will be formed along the Wan Chai and Causeway Bay shoreline, primarily for the construction of key infrastructure and to provide an attractive waterfront with a new public promenade.  A total reclamation area of some 28.5 ha is envisaged, with the newly reclaimed land forming a narrow strip of land along the existing Wan Chai and Causeway Bay shorelines, from the interface with the CRIII project west of the HKCEC Extension to the east of the Causeway Bay typhoon shelter.  The road layout and land use proposals are shown in Figures 3 and 4.

2.2              Project Requirements, Scope and Benefits

            Project Requirements

2.2.1          The Project is driven by the need for the implementation of the Trunk Road, which is defined as the section of road extending from Rumsey Street Flyover Extension in Central to the Island Eastern Corridor (IEC) in Causeway Bay, comprising the CWB and the IECL.

2.2.2          The Trunk Road will form an east-west strategic route through Central and Wan Chai.  The Trunk Road is an essential element of Government’s strategic transportation planning for Hong Kong and is required to provide relief to the existing main east-west route (that is, Connaught Road - Harcourt Road - Gloucester Road).  The Trunk Road was originally proposed under the Central and Wanchai Reclamation Feasibility Study, under which its feasibility was established.

2.2.3          Apart from providing land for key transport infrastructure and facilities, the Project can also create a coherent pattern of land use and for the development of an appropriate waterfront ‘edge’ to the existing urban area.  The Project will therefore consider imaginative and high quality measures to develop a waterfront of international standard for the enjoyment of residents and tourists.  This is in line with the intentions expressed in the Chief Executive’s 1999 Policy Address, in which he stated his commitment to the improvement of Hong Kong's waterfront, with open plazas, landscaped areas, shops and restaurants, for the enrichment of Hong Kong's quality of life.

            Project Scope

2.2.4          The scope of the Project comprises:

(i)                  land formation for key transport infrastructure and facilities, including the CWB, (comprising a dual 3-lane Trunk Road tunnel and two separate 2-lane single-way tunnels linking HKCEC to Causeway Bay forming the Wan Chai Bypass), the IECL, the NIL, the SCL and the necessary ground level road connections to facilitate through traffic from Central to Wan Chai;

(ii)                the waterfront promenade and other essential facilities; land is also required for the associated / supporting facilities for the waterfront promenade.

(iii)       reprovisioning / protection of existing facilities and structures affected by the land formation works mentioned above, and provision for a Government helipad;

(iv)              extension, modification, reprovisioning or protection of existing storm water drainage outfalls, sewerage outfalls, Wan Chai East Screening Plant and watermains affected by the revised land use and land formation works mentioned above, and upgrading of hinterland storm water drainage system and sewerage system, which would be rendered insufficient by the land formation works mentioned above;

(v)                provision of ground level roads, road bridges, footbridges, necessary transport facilities and the associated utility services;

(vi)       construction of the new waterfront promenade, landscape works and the associated utility services.

2.3              Works Programme

2.3.1          The WDII construction works are anticipated to commence on site in March 2004, with completion of the Project by February 2010.  Construction needs to be carried out in stages in order to meet the services and utilities reprovisioning requirements and construction sequencing constraints.  A staged construction programme, with works in each area being carried out sequentially, has been developed to meet the objectives of the Project.  The staging of the reclamation works, with respect to the above issues and constraints, is shown indicatively in Figure 5.

2.4              Related Projects

2.4.1          The following projects are related to the WDII project:

(i)    Territory Development Department's CRIII project, comprising reclamation along the Central waterfront for transport infrastructure needs (including the CWB and NIL) and basic land use requirements.  CRIII construction will take place from August 2002 to March 2007.

(ii)       Highways Department's CWB&IECL project, for the construction of the CWB and IECL from Rumsey Street Flyover Extension in Central to the IEC in Causeway Bay.  The construction of the CWB tunnel structures through WDII and CRIII will be entrusted to the WDII and CRIII projects respectively.  Construction will commence in March 2004 and the project will be completed in February 2012.

(iii)      Highways Department's Causeway Bay Flyover project, which will be constructed from May 2003 to February 2006.

2.5              Interrelationship between the WDII, CRIII and CWB&IECL Projects

2.5.1          The WDII, CRIII and CWB&IECL projects will be implemented over the time period from 2002 to 2012.  These projects all lie along the north shore of Hong Kong Island: CRIII and WDII are contiguous projects which will provide land for key transport infrastructure, while the CWB&IECL project forms a new trunk road from Central to Causeway Bay which will straddle both the CRIII and WDII projects.

2.5.2          The interrelationship between these three projects is essentially a function of their overlapping implementation programmes and the physical overlapping of both the CRIII and WDII projects by the CWB&IECL project.  This overlapping is clearly demonstrated in Figure 6, which also indicates the overall construction programmes of these three projects.

2.5.3          With respect to the assessment of environmental impacts for the WDII Project, the key indicators of air, noise and water quality will be influenced by the cumulative effects of overlapping programmes of construction works and by the physical intrusion through each others' project areas.  These cumulative effects can be summarised as follows:

·         For the overlapping period of the WDII and CRIII projects (ie from the start of WDII construction to the end of CRIII construction), air, noise and water quality impacts will arise due to the construction works in both the CRIII and WDII project areas.  (Concurrent CWB construction works will be taking place at the Central Interchange, but these will not affect the WDII project area.)  Within the area of influence at the WDII/CRIII interface, there will be cumulative air quality and noise impacts caused by each project on the other.  Cumulative water quality impacts from both the CRIII and WDII reclamation works, which will be taking place over the same period of time, will prevail over the water quality impacts of the individual projects, and will affect both project areas.

·         During the period from end of CRIII construction to end of WDII construction, air, noise and water quality impacts will arise due to construction works in the WDII project area, and cumulative air and noise impacts will also arise due to the concurrent construction of the IECL.

·         During the operational stage of all three projects:

·         air quality and noise impacts may arise due to the cumulative traffic on the WDII roads, the CRIII roads and on the CWB and IECL (the new Trunk Road);

·         water quality impacts may arise as a result of the combined new shoreline configuration of the WDII and CRIII projects.

These cumulative impacts will prevail over the operational impacts of the individual projects.

2.5.4          The effects of these cumulative impacts have been accounted for in the environmental assessments by presenting worst case scenarios with due recognition of the contributions to the impacts at any sensitive receiver from all concurrent works, no matter from which project.  The EIA Reports of all three projects present the cumulative air and noise impacts during both the construction and operation stages, insofar as they affect the respective project areas, and the results of the cumulative water quality impact assessment are presented in both the WDII and CRIII EIA Reports.  Mitigation measures proposed under all three projects are taken into account in the assessments of residual impacts.  In so doing, environmental impacts are addressed in a comprehensive manner, such that the overall picture of potential environmental conditions can be obtained over the whole north shore area.

 

3                    SUMMARY OF THE EIA

3.1              Introduction

3.1.1          The following sections summarise the nature and extent of the key environmental impacts and outcomes arising from the construction and operation of the Project and related activities taking place concurrently.  Further details, including the recommended mitigation measures, are provided in the EIA Report.  The key sensitive receivers in the study area, with respect to air quality, noise and water quality, are indicated in Figure 7.  Section 3.12 also provides a summary of key environmental impacts avoided and protection and benefits afforded to sensitive environmental resources and populations.

3.2              Air Quality Impacts

Construction Phase

3.2.1          During reclamation, filling and surcharging were identified as the major dust sources.  Entrusted work of the CWB tunnel section would also cause potential dust nuisance during excavation and backfilling.  Exceedences of both 1-hour and 24-hour Total Suspended Particulates (TSP) objectives (500 mg m-3 and 260 mg m-3) are predicted at almost all air sensitive receivers (ASRs) from Wan Chai to Causeway Bay.  For example, maximum predicted 1-hour and 24-hour TSP levels at HKCEC Extension are 3,371 mg m-3 and 1,753 mg m-3, respectively.

3.2.2          In order to achieve the air quality objectives, the following dust suppression measures are suggested:

Ÿ           strictly limit the truck speed on site to below 10 km per hour and water spraying to keep the haul roads in wet condition;

Ÿ           twice daily watering of the work site with active operations when the weather and the work site are dry;

Ÿ           watering during excavation and material handling;

Ÿ           provision of vehicle wheel and body washing facilities at the exit points of the site, combined with cleaning of public roads where necessary; and

Ÿ           tarpaulin covering of all dusty vehicle loads transported to, from and between site locations.

3.2.3          With the above mitigation measures, the air quality at all ASRs will comply with the 1-hour and 24-hour TSP criteria.  (Using the above example again, the maximum predicted 1-hour and 24-hour TSP levels at HKCEC Extension, after mitigation, are 394 mg m-3 and 251 mg m-3, respectively.)  There will be no residual adverse air quality impact due to the WDII construction activities and the cumulative effects of concurrent projects.

Operational Phase

3.2.4          The dispersions of nitrogen dioxide (NO2), respirable suspended particulates (RSP) and carbon monoxide (CO), arising from the background pollutant levels within and adjacent to WDII, vehicle emissions from open road networks, tunnel portal and ventilation building emissions from the CWB, tunnel portal emissions from the Cross Harbour Tunnel, and portal emissions from existing underpasses and planned deckovers, have been modelled.

3.2.5          The predicted 1-hour average NO2, 24-hour average NO2, 24-hour average RSP and 1-hour average CO concentrations at 1.5 m above ground are in the range of 114 to 291 mg m-3, 79 to 150 mg m-3, 62 to 130 mg m-3 and 1,820 to 6,621 mg m-3, respectively.  These are all within the air quality objective limits.

3.2.6          No adverse cumulative air quality impacts are predicted at the air sensitive areas for the operational phase.  No mitigation measures are required.

3.3              Noise Impacts

Construction Phase

3.3.1          WDII construction noise impacts have been predicted for daytime activities, taking into account other concurrent projects including the CRIII and CWB&IECL projects and the Causeway Bay Flyover project.  The predicted unmitigated noise levels range from 60 to 89 dB(A) at the representative noise sensitive receivers (NSRs), including residential developments along Hing Fat Street and Gloucester Road, at the performing art centres and at the HKCEC Extension.

3.3.2          With the use of silenced equipment and movable barriers for WDII construction tasks and implementation of the noise mitigation measures proposed in the CRIII and CWB&IECL EIA Reports, the noise levels at all residential NSRs would comply with EIAO-TM construction noise criteria during normal daytime working hours, with mitigated noise levels being in the range of 60 to 75 dB(A).  Some noise exceedences of 4 to 7 dB(A) are still predicted at the performing art centres and at the HKCEC Extension.  However, these NSRs are equipped with central air-conditioning systems and good noise insulation facilities, and they do not rely on openable windows for ventilation.  No adverse noise impacts are therefore expected for the indoor environments of these NSRs.

3.3.3          An indicative assessment has been undertaken for possible construction activities during restricted hours (1900 to 2300) associated with the reclamation works of the Project.  With the reduction of plant numbers, adoption of quiet plant and reduction of on-time percentage for some equipment, the predicted noise levels at all representative residential NSRs would comply with the construction noise criterion of 65 dB(A).  Noise exceedences of the 65 dB(A) criterion at HKCEC are still predicted at certain periods, for plant working close to the HKCEC Extension.  It should be noted that the results of the construction noise impact assessment for restricted hours (1900 to 2300) are for indicative purposes; the Noise Control Authority will process any CNP application, based on the NCO and the relevant technical memoranda in addition to considering the contemporary situations / conditions.

Operational Phase

3.3.4          The potential road traffic noise impacts have been assessed for the worst-case traffic flows in 2027, taking into consideration the recommended noise barrier mitigation measures on the IECL as proposed in the CWB&IECL EIA Report.  The noise levels at a number of NSRs are predicted to exceed the EIAO-TM traffic noise criterion of 70 dB(A) for residential buildings.  However, noise exceedences at these NSRs are mainly attributed to the existing roads and to the proposed IECL (reference can be made to the CWB&IECL EIA Report).  The ‘New’ WDII road noise contributions to the overall noise level is negligible (that is, less than 1.0 dB(A)).  In addition, some NSRs such as the Art Centre and HKCEC Extension are equipped with central air-conditioning systems and noise insulation, and they do not rely on openable windows for ventilation.  Therefore, adverse traffic noise impacts are not expected at the indoor environment of these NSRs.  No operational mitigation measures are necessary for the proposed WDII roads.

3.3.5          No adverse impact from helicopter noise and fixed noise sources including ventilation shaft noise from the CWB ventilation buildings are anticipated at the existing and planned NSRs.

3.4              Hydrodynamics, Water and Sediment Quality Impacts

Construction Phase

Marine-based Impact

3.4.1          The water quality impacts during the reclamation of WDII have been quantitatively assessed by numerical modelling.  Suspended sediment is identified as the most significant water quality parameter during the reclamation.  The worst-case scenarios during reclamation, taking into account the anticipated reclamation stages and possible overlapping dredging and filling activities, were assessed.  The assessment also takes into account the cumulative effects that arise from the adjacent CRIII reclamation and other concurrent reclamation works in the Harbour.  It is predicted that potential water quality impacts could occur at seawater intakes along the Central and Wan Chai shorelines and in the Causeway Bay typhoon shelter, with a maximum concentration of suspended solids (SS) at the surface layer up to 263 mg L-1.  However, the water quality impacts on the seawater intakes can be effectively minimised with the implementation of proposed mitigation measures, which include silt curtains around the dredging operations, silt screens at the intakes and bulk filling behind constructed seawalls.  Maximum surface SS levels at the seawater intakes will be less than 30 mg L-1 after the implementation of these measures and  there will be no residual adverse water quality impacts due to the WDII reclamation and due to the cumulative effects from other concurrent reclamation activities.

Land-based Impact

3.4.2          Water quality impacts from land-based construction, including road works, waterfront facilities and public utilities, are associated with the surface runoff, effluent discharge from the site and sewage from on-site construction workers.  Impacts can be controlled to comply with statutory standards by implementing mitigation measures such as on-site drainage and sediment traps to control run-off.  No unacceptable residual impact on water quality is anticipated.

Operational Phase

Hydrodynamics

3.4.3          An assessment of the hydrodynamic impact due to the WDII reclamation has been undertaken for the new coastline configuration which will be constructed under the WDII project, and the adjacent CRIII project.  Potential impacts to tidal flows have been assessed by comparing the baseline and operation phase conditions.  It is concluded that, during the operation phase, the WDII reclamation alone will result in minimal change to the tidal flow regime (with a change of mean discharges through Victoria Harbour of less than 0.5%).  Flow speed distributions within Victoria Harbour before and after implementation of WDII are very similar and the reclamation will cause only slight change to the prevailing currents in the study area.

3.4.4          It is therefore concluded that the WDII reclamation will have minimal impact on the hydrodynamic regime in the study area.

Water Quality

3.4.5          An assessment of the water quality impacts during the operation of WDII has also been undertaken.  Comparison between the baseline and operational water quality modelling results suggests that the levels of pollutants near Wan Chai and the neighbouring areas are similar under both baseline and operational scenarios.  No unacceptable impacts associated with the operation of the WDII upon the water quality in Victoria Harbour are envisaged.  Operation phase mitigation measures are not considered necessary.

3.5              Waste Management

3.5.1          The total volume of dredged sediment for the WDII reclamation is estimated to be approximately 0.99 Mm3.  A review of the sediment quality data from the marine ground investigation works indicates that some 0.6 Mm3 of the marine sediments to be dredged in the proposed WDII area would be classified as Category H (ie high levels of contaminants).  The dredged sediment will therefore not be suitable for open sea disposal.  However, with the implementation of mitigation measures in accordance with the requirements of Works Branch Technical Circular (WBTC) No. 3/2000, and disposal to the contaminated mud pits at East Sha Chau, no residual adverse impact is predicted.

3.5.2          In the Causeway Bay typhoon shelter, Category H sediment with high concentrations of PCBs have been identified and biological screening will be required for the sediment sampling and testing to be carried out in the further ground investigation works at the design phase of the Project.  To cater for the possibility that some of these sediments may fail the biological screening tests, special disposal arrangements have been reviewed; containment of the contaminated sediments in geosynthetic containers before disposal at the East Sha Chau contaminated mud pits is proposed to prevent any release of material to the marine environment.  Field trials are recommended to establish the optimum handling method for this approach.

3.5.3          Wastes generated by construction activities will include construction and demolition (C&D) materials (including excavated material), general refuse and chemical waste.  Provided that these identified waste arisings are handled, transported and disposed of using approved methods and that the recommended good site practices as identified in the EIA Report are strictly followed, adverse environmental impacts are not anticipated.  The C&D material should be sorted on-site into inert C&D material (ie public fill), for reuse in the reclamation, and C&D waste for recycling or disposal.

3.6              Land Contamination

3.6.1          The land contamination assessment included a review of site history and existing environmental information, and a preliminary site inspection.  Two possible contaminated land sites have been identified: the A. King Marine shipyard in the Causeway Bay typhoon shelter and the boatyard area of the RHKYC.  Potential contaminants arising from shipyard operations and the yacht club have been identified, however, based on available information, the potential for land contamination in these areas is not considered to be insurmountable.

3.6.2          It is proposed that site investigation should be conducted prior to the commencement of site clearance / construction works.  The requirements for EM&A with respect to land contamination, if necessary, should be determined upon completion of the site investigation works.

3.7              Terrestrial Ecology

3.7.1          The terrestrial ecological resources within the study area comprise a variety of habitat types including man-made terrestrial habitat and associated bird community.  No terrestrial sensitive receivers are in the vicinity of the study area and the nearest country park, the Aberdeen Country Park, is approximately 2 km inland to the south.  Apart from isolated trees over the study area, the most significant green area is Victoria Park.  The ecological assessment indicates that the terrestrial ecological resources present within the study area are of low ecological value.

3.7.2          It is anticipated that no specific mitigation measures will be required for the potential terrestrial ecological impacts to preserve ecological resources in the study area.  Tree loss will be compensated by landscaping.  No unacceptable terrestrial ecological impacts are anticipated.

3.8              Marine Ecology

3.8.1          The marine ecological resources within the study area comprise a variety of habitat types including artificial seawall, natural intertidal shoreline and soft bottom benthic habitat.  There are no ecological sensitive receivers, such as Sites of Special Scientific Interest, Fish Culture Zones and Marine Parks and/or Reserves and other areas of ecological importance or conservation interest, in and within the vicinity of the study area.  The ecological assessment indicates that the marine ecological resources within the WDII area are considered to be of low ecological value.

3.8.2          The dredging and reclamation works will result in the permanent loss of approximately 28.5 hectares of soft bottom benthic habitat.  Approximately 1,110m of rock armoured sloping seawall and 440m of sloping seawall (with granite facing) will be permanently lost due to reclamation or removal of existing breakwaters.  Approximately 2,800m of existing vertical seawall will also be lost during the reclamation, but some 1.5 km of new caisson wave energy absorbing seawall and 1.3 km of new blockwork seawall will be constructed.  These seawalls are expected to provide habitat of similar ecological value to that of the existing blockwork seawalls that constitutes the main part of the reclaimed intertidal habitat.  Since the benthic community and intertidal community in the study area are of low ecological value, only minor impacts are anticipated from the reclamation works.

3.8.3          Based on the water quality modelling, the marine ecological impact associated with the WDII development is considered to be low.  It is anticipated that the new seawalls would not cause adverse impact to the recolonisation of intertidal marine organisms.  Similar intertidal flora and fauna existing at present are expected to recolonise the new seawall, which is largely restricted to encrusting sessile.

3.9              Landscape and Visual Impacts

3.9.1          A landscape and visual impact assessment (LVIA) has been conducted to assess the impacts of the proposed developments within the WDII, for both the construction and operation phases, on the surrounding area.  Landscape and visual mitigation measures would be achieved principally through the realisation of a Master Landscape Plan encompassing the following objectives:

·            the establishment of a network of open spaces providing for a range of functions including pedestrian circulation and as a venue for community events;

·            the creation of major landscape spaces forming pedestrian arteries linking the waterfront with existing open spaces, proposed and existing adjacent developments and other areas of the city;

·            the establishment of an integrated, pedestrian oriented streetscape which will enhance pedestrian movement, integrate the proposed and existing developments within an overall landscape framework and generally improve the quality of  the public environment;

·            the provision of green buffer areas to mitigate negative environmental conditions associated with transport corridors, especially for the proposed IECL;

·            the development of an integrated, fully co-ordinated design, incorporating all foreseeable functional requirements such as utilities, drainage reserves, and pumping stations;

·            the creation of a high quality Waterfront Park which will reflect and integrate with that proposed for the Central Reclamation development;

·            the provision of open space linkage between the Central Reclamation and HKCEC in the west, the RHKYC, Victoria Park and stretching to North Point to the east.

3.9.2          The ability to create a world-class harbour frontage, in respect of visual and landscape impacts, is somewhat constrained in the area adjacent to the IECL.  This is due to the dominating visual presence of the IECL and also because a large landscape area would lie under the IECL.  The screening of the IECL from users of the waterfront is dependent on the ability to plant substantial large canopy trees over the drainage reserve along this promenade.  Tree planting over the drainage reserve is therefore a very critical component of the overall mitigation measures.

3.9.3          The proposed entertainment complex may partially obstruct some views from nearby residential development, however, with sensitive design, the proposed built form may act as an alternative mitigation measure to alleviate in part the negative impacts brought about by the IECL and its associated noise barriers.

3.9.4          During the construction phase, the potentially most significant impacts would be:

·            Substantial landscape impacts on street tree planting in Wanchai North and on the landscape character of the streets and open spaces in Wanchai North and Causeway Bay.  The HKCEC promenade, Convention Avenue, RHKYC and Causeway Bay typhoon shelter areas would be particularly affected.  The total number of trees affected is in the order of 420.

·            Substantial visual impacts on the majority of buildings in Wanchai, Wanchai North and Causeway Bay that have a harbour outlook.  The RHKYC and Police Officers' Club would be surrounded by the various developments, which would create a large magnitude of change in views during construction.  Substantial impacts on some of the public open spaces in Wanchai North and Causeway Bay.  The areas of permanent and temporary loss of the public open spaces are approximately 1.05 ha and 0.2 ha respectively.

3.9.5          For the operation phase, after all mitigation measures have been implemented and have matured over 10 years, there would still be some residual adverse landscape and visual impacts, the most significant impacts being:

·            Substantial visual impacts on the buildings in Wan Chai North which would have their harbour views blocked by the proposed CDA development, on buildings along Gloucester Road in Causeway Bay which would have their harbour views partially obscured by the proposed hotel / commercial development and which would also have clear views of the IECL, and on the Police Officers' Club which would be visually dominated by the IECL and the proposed hotel / commercial development.

3.9.6          The remaining landscape and visual impacts would be adverse impacts of slight or insubstantial significance, or beneficial impacts of slight or moderate significance. 

3.9.7          Overall, it is considered that, in terms of Annex 10 of the EIAO-TM, the residual landscape and visual impacts of the WDII project are acceptable with mitigation measures.  With respect to the individual Schedule 2 DPs, the residual landscape and visual impacts are also categorised as acceptable with mitigation measures.

3.9.8          A Master Landscape Plan, which illustrates the landscaping intentions for the WDII project, is presented in Figure 8.

3.10          Biogas

3.10.1      Organically enriched marine bottom sediment is planned to be left in-situ at the WDII reclamation within the western and eastern corners of the Causeway Bay Typhoon Shelter.  As methane gas could be generated under anaerobic conditions, there is a potential for this gas to be released either during construction or after development of the reclaimed area.

3.10.2      The predicted methane emission from the WDII reclamation suggests that the methane gas generation potential is not expected to pose a development constraint.  In view of the exceedence of the recommended maximum “safe” rate of methane emission under the worst case scenario of 100% biodegradable total organic carbon and the identification of ‘at risk’ rooms at the proposed developments at the western and eastern corners of the typhoon shelter reclamation, it is recommended that monitoring of gas emission rates should be undertaken in the immediate post-reclamation period.  The review of the gas monitoring results would determine the need for gas protection measures to be incorporated in the building design to prevent the ingress and / or accumulation of any methane gas emissions to potentially dangerous concentrations.  With the incorporation of the recommended gas protection measures in the design of the developments, if necessary, together with the implementation of other recommended precautionary measures during construction activities, the risk to people and property due to biogas emissions from the WDII reclamation is considered to be low. 

3.11          Environmental Monitoring and Audit

3.11.1      Environmental monitoring and audit are recommended for construction stage dust, noise and water quality, to check compliance with relevant statutory criteria and to ensure the effectiveness of the mitigation measures.  Site inspection / audit is also recommended for waste management during construction and for implementation of landscaping measures during operation.  Details of the recommended mitigation measures, monitoring procedures and locations are presented in a stand-alone EM&A Manual.  This will enable the Contractor to have early warning and provide necessary action to reduce impacts at specific areas if the assessment criteria are approached.  The effectiveness of on-site control measures could also be evaluated through a monitoring exercise.  All the recommended mitigation measures should be incorporated into the EM&A programme for implementation.

3.12          Environmental Benefits, Designs, Key Protection Measures and Enhancements

3.12.1      The key benefits associated with the Project will be the provision of land required for the future transport infrastructure, including the proposed CWB and IECL, NIL and SCL, and the provision of a new waterfront promenade for the enjoyment and benefit of the public.  Environmental benefits arising from the Project include:

·            the existing air sensitive receivers from Central to Causeway Bay will be protected from adverse construction air quality impact by the recommended dust control measures during construction phase;

·            no adverse operational air quality impacts at the existing and planned air sensitive receivers from Central to Causeway Bay;

·            the existing noise sensitive receivers from Central to Causeway Bay will be protected from adverse construction noise impact by the adoption of quiet powered mechanical equipment during the construction phase;

·            no adverse road traffic noise impacts at the existing noise sensitive receivers from Central to Causeway Bay are attributed to the ‘New’ WDII roads;

·            adverse water quality impacts at the seawater intakes along the Central, Wan Chai and Causeway Bay waterfront are avoided during reclamation works by the adoption of mitigation measures, including reduction in dredging rates, implementation of silt curtains and installation of silt screens; and

·            minimisation of changes to the existing tidal flow regime in Victoria Harbour through the adoption of an optimum reclamation configuration.

 

4                    OVERALL CONCLUSION

4.1.1          The findings of this EIA have provided information on the nature and extent of environmental impacts arising from the construction and operation of the Project.  The EIA has, where appropriate, identified mitigation measures to ensure compliance with environmental legislation and standards.

4.1.2          Overall, the EIA Report for the development of WDII has predicted that the Project will generally comply with environmental standards and legislation after the proposed construction and operation stage mitigation measures are implemented.  This EIA has also demonstrated the general acceptability of the residual impacts from the Project and the protection of the population and environmentally sensitive resources.  Environmental monitoring and audit mechanisms have been recommended before and during construction and operation, where necessary, to verify the accuracy of the EIA predictions and the effectiveness of recommended mitigation measures.