Environmental Impact Assessment Ordinance (Cap.
499)
Section 5 (7)
Environmental Impact Assessment Study Brief No.
ESB-098/2002
Project Title : South East Kowloon Development – Kai Tak
Approach Channel
Reclamation
Name of Applicant : Kowloon
Development Office,
Territory Development
Department
(hereinafter known as
the “Applicant”)
1. BACKGROUND
1.1
An application (No. ESB-098/2002)
for an Environmental Impact Assessment (EIA) study brief under section 5(1) of
the Environmental Impact Assessment Ordinance (EIAO) was submitted by the
Applicant on 14 March 2002 with a Project Profile (No. PP-162/2002).
1.2
The Schedule 2 Designated
Projects as defined in the EIAO covered under this study brief includes the
works as described in Section 1.4(3) of the Project Profile (PP) for the
formation of approximately 28 ha of land (at the Kai Tak Approach Channel
(KTAC)), which constitutes a Designated Projects by
virtue of Item C.1 of Schedule 2 of the EIAO for reclamation works of more than
5 ha in size and the associated dredging works. The works described in section 1.4(1) of the PP to clean up
the contaminated sediment in the KTAC and to elimination odours resulting from
the anaerobic decomposition of the organics in the sediment are integral parts
of the reclamation and dredging works in the context of this EIA study
brief. These works are hereinafter
referred as the “Project”. The location
of the Project is shown in Figure 1.
1.3
For the avoidance of
doubt, the performance of the pilot tests for sediment treatment as detailed in
section 1.4(2) of the PP, the extension and widening of Kai Tak Nullah and
laying of the Jordan Valley box culvert as detailed in section 1.4(4) of the
PP, the construction of advance portions of the planned road tunnels underneath
the extended box culverts (part of Roads D4 and D5) as detailed in section
1.4(5) of the PP and demolition works for the former airport taxiway bridge
across KTAC as detailed in section 1.4(6) of the PP are not considered
Designated Projects, and are not covered within the scope of this EIA study
brief.
1.4 The
SEKDCFS is a Designated Project under Item 1 in Schedule 3 of the EIAO for
“Major Designated Projects Requiring EIA Reports”. On 11 June 2001, the Applicant submitted the environmental
impact assessment (EIA) report for the SEKDCFS [EIA Report (Volume 1 & 2) –
July 2001; EIA Executive Summary – July 2001 and Environmental Monitoring and
Audit Manual – July 2001] (SEKDCFS-EIA) to the Director for approval under the
EIAO. Under the EIAO, the
SEKDCFS-EIA was exhibited for public inspection from 31 July 2001 to 29 August
2001 during which no public comments were received. The findings of the SEKDCFS-EIA were presented to the
Advisory Council of the Environment (ACE) and the report was endorsed by the
ACE on 17 September 2001 as a Schedule 3 EIA without conditions. On 25 September 2001, the SEKDCFS-EIA
was approved as a Schedule 3 EIA by the Director under the EIAO (EIAO Register
Ref: AEIAR-044/2001).
1.5 Based
on a preliminary design concept, the SEKDCFS-EIA established the broad
environmental feasibility of the various development packages under SEKD and
their cumulative impacts on the existing, committed and planned land-uses in
the redevelopment as well as new development areas within SEKD. A number of Schedule 2 Designated
Projects are covered under the SEKDCFS-EIA, including the Designated Projects
described in section 1.2 above. It is recommended in the SEKDCFS-EIA
that during the detailed design stage and prior to the application of the
Environmental Permit for the construction and operation of the Schedule 2
Designated Projects, detailed EIAs be undertaken. These EIAs shall make reference to the SEKDCFS-EIA for those
assessed impacts, and shall complete any further studies on outstanding
environmental issues or on new environmental issues that may emerge during the
design stage of the project. In
general, the scope for these works is expected to be consistent with that of
the SEKDCFS-EIA and that in the Outline Master
Development Plan for the SEKDCFS.
1.6 Pursuant
to section 5(7)(a) of the EIAO, the Director issues this EIA study brief to the
Applicant to carry out an EIA study for the Project as detailed in section 1.2 above.
1.7 In
setting out the scope of the issues to be addressed in this EIA study, the
Director has considered the findings and recommendations of the SEKDCFS-EIA,
and that the work scope detailed in section 1.2
above is generally consistent with that covered under the SEKDCFS-EIA. The purpose of this study brief is to
scope the key issues of this EIA study and to specify the environmental issues
that are required to be reviewed, updated and assessed, as appropriate, in the
EIA report in the light of the availability of additional information during
the design and construction stage of the project.
1.8 The
purpose of this EIA report is to provide information on the nature and extent of
environmental impacts arising from the construction and operation of the
project and related activities taking place concurrently, with reference to the
relevant findings and recommendations of the SEKDCFS-EIA. This information will contribute to
decisions by the Director on:-
(i) the overall
acceptability of any adverse environmental consequences that are likely to
arise as a result of the Project;
(ii)
the conditions and requirements for the
detailed design, construction and operation of the Project to mitigate against
adverse environmental consequences wherever practicable; and
(iii)
the acceptability of residual impacts
after the proposed mitigation measures are implemented.
2. OBJECTIVES
OF THE EIA STUDY
2.1
The objectives of the
EIA study are as follows:-
(i) to describe the
proposed project and associated works together with the requirements for
carrying out the proposed project;
(ii) to identify and
describe the elements of the community and environment likely to be affected by
the proposed project and/or likely to cause adverse impacts to the proposed
project, including the natural and man-made environment and the associated
environmental constraints;
(iii) to identify and
quantify emission sources and determine the significance of impacts on
sensitive receivers and potential affected uses;
(iv)
to propose the provision of mitigation
measures so as to minimize pollution, environmental disturbance and nuisance
during construction of the Project;
(v)
to investigate the feasibility, practicability,
effectiveness and implications of the proposed mitigation measures;
(vi) to identify, predict
and evaluate the residual environmental impacts (i.e. after practicable
mitigation) and the cumulative effects expected to arise during the construction
phase of the project in relation to the sensitive receivers and potential
affected uses;
(vii) to identify, assess and
specify methods, measures and standards, to be included in the detailed design and
construction of the project which are necessary to mitigate these environmental
impacts and reducing them to acceptable levels;
(viii) to investigate the extent of
secondary environmental impacts that may arise from the proposed mitigation
measures and to identify constraints associated with the mitigation measures
recommended in the EIA study, as well as the provision of any necessary
modification; and
(ix) to design and specify
the environmental monitoring and audit requirements, if required, to ensure the
implementation and the effectiveness of the environmental protection and
pollution control measures adopted; and
3. DETAILED
REQUIREMENTS OF THE EIA STUDY
3.1 The
Purpose
The purpose of this study brief is to
scope the key issues of the EIA study.
The Applicant has to demonstrate in the EIA report that the criteria in
the relevant sections of the Technical Memorandum on the Environmental Impact
Assessment Process of the EIAO (hereinafter referred to as “the TM”) are fully
complied with.
3.2 The
Scope
The scope of this EIA study shall cover
the Project as detailed in sections
1.2 above.
The EIA study shall address the likely key issues described below,
together with any other key issues identified during the course of the EIA
study:-
(i)
identify, with suitable justifications
and rationale behind the selection, as based on the results of sediment
investigation, assessment and pilot tests, a preferred sediment remediation
strategy and reclamation method for KTAC with reference to, but not limited to
no dredged reclamation with in situ treatment, dredge reclamation with ex
situ treatment, and minimum dredge reclamation with a combination of in
situ and/or ex
situ treatments;
(ii)
the potential odour impact arising from
the reclamation works at the KTAC, including any impact that may arise from
associated dredging and sediment treatment works;
(iii)
the potential risks associated with
biogas, the handling of contaminated sediment during construction as affecting
construction site workers; and risk of biogas and residual contaminants as
affecting future occupants of the formed land over the KTAC;
(iv)
the potential water quality impacts
during reclamation, due to in situ and ex situ treatments of
contaminated sediments, dredging, reclamation runoff and effluent discharge;
(v)
if ex situ treatment method for
the contaminated KTAC sediment is recommended, the environmental nuisances such
as dust, odour, noise and water that would be associated with the treatment
method and the feasibility of reusing the treated sediment, including any
potential for associated land contamination impact;
(vi)
the potential impacts associated with
waste generation during construction both in quantity and quality;
(vii)
the details of the
construction programme, the construction methodologies and an assessment of the
extent to which the technology(ies) to be employed for treatment of the
contaminated sediment is(are) proven technology(ies); and
Cumulative
impact
(viii)
the
cumulative construction impacts from the Project and other potentially
concurrent activities within the vicinity at SEKD, including but not limiting
to the “Construction and demolition materials recycling facility at Kai Tak” by
CED, “Temporary public filling barging point at Kai Tak” by CED, “Kai Tak North
Apron Early Development Package by TDD, works relating to temporary reprovision
of existing facility along runway (e.g., DG Ferry Pier and public cargo working
area), extension and widening of the Kai Tak Nullah, laying of the Jordan
Valley box culvert, and other drainage outfalls into KTAC as detailed in
section 1.4(4) of the PP, the construction of advance portions of the road
tunnels underneath the extended box culvert (part of Roads D4 and D5) as detailed
in section 1.4(5) of the PP, and demolition of the former taxiway bridge across
KTAC as detailed in section 1.4(6) of the PP.
3.3 Consideration
of Alternative Technologies for Treatment of Contaminated Sediment and
Alternative Dredging Methods
3.3.1 The
EIA shall present the rationale behind selecting certain sediment treatment and
reclamation methods and any alternative methods that have been considered in
the light of any additional information available during the design stage. A review of available technologies for
the treatment of contaminated sediment and how these technologies compare for
factors including but not limited to their effectiveness, implementability and
environmental advantages for the KTAC reclamation works.
3.3.2 The
EIA shall present the rationale behind selecting certain dredging methods and
any alternative methods that have been considered in the light of any
additional information available during the design stage, and how the preferred
methods serve to minimize adverse environmental effects.
3.4 Technical
Requirements
The
Applicant shall conduct the EIA study to address all environmental aspects of
the activities as described in the scope as set out above. The EIA study shall include the
following technical requirements on specific impacts.
3.4.1 Construction
Methodologies and Programme
3.4.1.1 The Applicant shall include in the EIA report
details of the construction programme and methodologies.
3.4.2 Sediment
Contamination Impact
3.4.2.1 The Applicant shall make reference to the
SEKDCFS-EIA, extract and present all relevant information from the SEKDCFS-EIA
on the Project to address the sediment contamination impacts as detailed in sections 1.2 above. A review shall be carried out to
identify for any information gap and to carry out further investigations as
necessary. Any new and additional
information arising from the construction and operation of the Project shall
also be presented.
3.4.2.2 The EIA report shall cover the followings:-
(i)
an overview of the sediment quality of
the KTAC based on findings of previous investigations made under the
SEKDCFS-EIA and any additional investigations found necessary as a result of
the review required under section
3.4.2.1 above.
This shall include a historic review of polluting land uses upstream of
the KTAC and their associated pollutants, site and sediment characterization,
investigation methodology, investigative results with presentation of all
relevant field and laboratory investigation results, including the results of
the bench-scale and pilot-scale sediment treatability tests recommended in the
SEKDCFS-EIA;
(ii)
a detailed review of currently available
sediment treatment methods and dredging methods (including but not limited to
descriptions of the technologies and a comparison of their effectiveness and
implementability, environmental advantages and disadvantages.);
(iii)
an assessment of the results from section 3.4.2.2(i) and (ii) above and, based on these
results, review the applicability of the recommendations on the sediment
treatment and reclamation options for the KTAC in the SEKDCFS-EIA;
(iv)
A presentation of the findings of bench
scale tests and pilot tests for sediment treatment as recommended in the
SEKDCFS-EIA and review of currently available reclamation and sediment
treatment methods as mentioned in section 3.4.2.2(i)
and (ii) above; the tests shall be conducted with a view to determining
the followings:-
(a) treatability
of the contaminated sediment by in-situ methods;
(b) treatability
of the contaminated sediment by ex-situ methods;
(c)
the risk of any harmful bi-products that
may be created in the sediment remediation process, such as hexavalent
chromium;
(d)
characteristics and quantity of wastewater
generated during ex situ treatment, if recommended;
(e)
release of chemicals and mobilization of
contaminants to the water column for in situ treatment, if recommended;
(f)
the potential for biogas production; and
(g)
engineering design requirements for
application of in-situ treatment method including but not limited to well size,
spacing and construction and water quality monitoring requirements.
(v)
an assessment of the potential risk
associated with biogas and any risk from residual contaminants on future
occupants of the formed land at KTAC; and risk to workers associated with
biogas and handling of contaminated sediment during the construction stage;
(vi)
based on the results of sediment
investigation, assessment and pilot tests as detailed in sections 3.4.2.2(i), (ii), (iii), (iv) & (v)
above, identify a preferred sediment remediation strategy and reclamation
method for KTAC with reference to, but not limited to, the following three
options considered in the SEKDCFS-EIA:-
no-dredge reclamation with in situ
treatment;
dredge reclamation with ex situ treatment;
and
minimum dredged reclamation with in
situ and/or ex situ treatment.
The
reclamation and sediment remediation strategy shall be selected with a view to
minimize dredging requirements, with due consideration to the acceptability of
the final land use following sediment treatment and reclamation of the KTAC
area and adjacent lands. The
feasibility of the preferred reclamation and sediment remediation strategy for
application on a full-scale level for KTAC shall be clearly demonstrated; and
(vii)
detailed engineering design of the
reclamation and sediment remediation methodologies shall be presented, together
with a reasonable estimate of the volume of contaminated sediment.
(viii)
If in-situ treatment is to be
adopted (leaving sediment in place), the monitoring of biogas emission at KTAC
reclamation should be included.
The EIA shall also include the followings:-
(a)
a proposal on collection and analysis of
representative samples for the agreement of the Director; and
(b)
a proposal, with justifications, on
monitoring, mitigation and protection measures on proposed developments, if
found necessary.
3.4.3 Water
Quality Impact
3.4.3.1 The Applicant shall make reference to the
SEKDCFS-EIA, extract and present all relevant information from the SEKDCFS-EIA
on the Project as detailed in sections
1.2 above, and incorporate any new and additional
information to address the water quality impacts arising from the construction
and operation of the Project. The
Applicant shall follow the criteria and guidelines for evaluating and assessing
water pollution as stated in Annexes 6 and 14 of the TM, respectively.
3.4.3.2 The EIA report shall cover the following:-
(i)
the water quality impacts arising from
the reclamation works at the KTAC during the construction stage, including any
associated dredging and sediment treatment works based on the preferred
reclamation method and sediment remediation strategy recommended in accordance
with section
3.4.2.2(vi)
above. The treatment and disposal
requirement for the wastewater generated due to ex situ sediment
treatment shall be assessed. If
the quantity of the wastewater generated is outside the flow band as stipulated
in the Technical Memorandum – Standards for Effluents Discharged into
Drainage and Sewerage Systems, Inland and Coastal Water under the Water
Pollution Control Ordinance (WPCO-TM), or there are substances in the
wastewater that are not covered in the WPCO-TM, the impacts due to the
wastewater disposal shall be quantitatively assessed. The methodology of assessment shall be agreed with the
Director;
(ii)
the cumulative water quality impacts due
to the construction of the Project and other concurrent projects within SEKD as
detailed in sections 3.2
(viii) above;
(iii)
recommendation of a water quality
monitoring programme based on section
3.4.3.2(i) & (ii) above. Particular attention shall be given to
the design of the monitoring programme to detect whether the applied chemicals
/ by-products / pollutants attached to the sediment will be released /
mobilised to the water column.
3.4.3.3 The study area shall include all areas within
and 300m beyond the boundary of the Project, plus the Victoria Harbour Water
Control Zone (WCZ), the Eastern Buffer WCZ and the Western Buffer WCZ as
declared under the Water Pollution Control Ordinance.
3.4.3.4 The Applicant shall review and update the
construction water quality impacts assessment of the SEKDCFS-EIA on the
reclamation works at the KTAC as detailed in sections 3.4.3.2(i)
above, taking on board additional information on the preferred reclamation
method and sediment remediation strategy recommended in accordance with section 3.4.2.2(vi)
above. For this purpose, the
Applicant shall carry out the assessment making reference to similar
methodologies adopted in the SEKDCFS-EIA.
Additional information on the water and sediment quality of the KTAC
collected from recent investigation, including data from the bench-scale and
pilot-scale tests for sediment remediation assessment as recommended in the
SEKDCFS-EIA shall be incorporated
in the assessment.
3.4.4 Air
Quality Impact
3.4.4.1 The Applicant shall make reference to the
SEKDCFS-EIA, extract and present all relevant information from the SEKDCFS-EIA
on the Project as detailed in sections
1.2 above, and incorporate any new and additional
information to address the air quality impacts arising from the construction of
the Project. The Applicant shall
follow the criteria and guidelines for evaluating and assessing air pollution as stated in section 1 of Annexes 4 and 12 of the TM, respectively.
3.4.4.2 The EIA report shall cover the followings:-
(i)
the dust and odour impact arising from
the reclamation works at the KTAC, including any associated dredging and
sediment treatment works. If ex
situ treatment method for the contaminated KTAC sediment is recommended, the
associated emissions including dust and odour;
(ii)
the cumulative impacts due to the
construction of the Project, including the cumulative construction dust impacts
from the Project and other concurrent projects within SEKD as detailed in sections 3.2 (viii)
above.
3.4.4.3 The study area for air quality impact
assessment shall generally be defined by a distance of 500 metres from the
boundary of the Project and any work sites proposed under the Project, but
shall be extended to include any major emission sources that may have a bearing
on the environmental acceptability of the Project. The Applicant shall review and update the information as included
in the SEKDCFS-EIA with regards to the existing and planned / committed air
sensitive receivers (ASRs) within the study area at the time of the Project
works, including those earmarked on the relevant Outline Zoning Plans, Outline
Development Plans and Layout Plans.
In identifying planned ASRs, reference shall also be made to the Outline
Master Development Plan for the SEKDCFS and development proposals approved by
Town Planning Board. The Applicant
shall select the assessment points of the identified ASRs that represent the
worst point of these ASRs. A map
showing the location and description such as the name of building, use and
height of the selected assessment points shall be given. The separation distances of these ASRs
from the nearest emission sources shall also be given.
3.4.4.4 The Applicant shall assess the odour impact
from the reclamation works at the KTAC (including any associated dredging and
sediment treatment works) in accordance with section
3.4.4.6 below.
3.4.4.5 The EIA report shall cover the construction
dust impacts arising from all construction works associated with the Project
and any concurrent works within the study area and in accordance with section 3.4.4.6 below.
3.4.4.6 The air quality impact assessment shall include
the following:-
Background
and analysis of activities
(i)
Provide background information relating
to air quality issues relevant to the project, e.g. description of the types of
activities during construction stage of the project such as reclamation that
will likely give rise to dust emissions.
(ii)
Give an account, where appropriate, of
the consideration/measures that had been taken into consideration in the
planning of the project to abate the air pollution impact. That is, the Applicant shall consider alternative
construction methods/phasing programmes to minimise the constructional air
quality impact. Examples include
use of marine access routes for transportation of construction materials to
avoid dust impact on ASRs due to haul road transport during construction.
(iii)
Present the background air quality levels
in the assessment area for the purpose of evaluating the cumulative
constructional air quality impacts.
Identification
of ASRs and examination of emission/dispersion characteristics
(iv)
Identify and describe representative
existing and planned/committed air sensitive receivers (ASRs) that would likely
be affected by the project as indicated in section
3.4.4.3 above.
(v)
Provide an exhaustive list of air
pollutant emission sources, including any nearby emission sources which are
likely to have impact on the project based on the analysis of the construction
activities of the project in (i) above. Example of construction stage emission
sources include stock piling, blasting, concrete batching, vehicular movements
on unpaved haul roads on site and odour associated with dredging and sediment
treatment works, etc. Confirmation
of the validity of the assumptions and the magnitude of the activities shall be
obtained from the relevant government department/authorities and documented.
Constructional
air quality impact
(vi)
The Applicant shall follow the
requirements of the Air Pollution Control (Construction Dust) Regulation in
dust control to ensure construction dust impacts are controlled within the relevant
standards as stipulated in section 1 of Annex 4 of the TM. The Applicant shall also initiate an
audit and monitoring program during constructional stage to verify the
effectiveness of the control measures and to ensure that the construction dust levels
be brought under proper control when such program is identified to be
necessary.
(vii)
If the Applicant anticipates a
significant construction dust impact that will likely cause exceedance of the
recommended limits in the TM at the ASRs apart from the incorporation of the
dust control measures stated in (vi) above, a
quantitative assessment should be carried out to evaluate the construction dust
impact at the identified ASRs based on the emission strength of the emission
sources identified in (v) above. The Applicant shall follow (ix) to (xii) below when carrying out the
quantitative assessment.
(viii)
The Applicant shall follow (ix) to (xii) below to assess the impact (including
odour) arising from the reclamation works at the KTAC, including any associated
dredging and sediment treatment works.
Quantitative
Assessment Methodology
(ix)
The Applicant shall apply the general
principles enunciated in the modelling guidelines (Guidelines for Local-Scale
Air Quality Assessment Using Models issued by the Modelling Section, Air Policy
Group, Environmental Protection Department, HKSAR dated March, 2000) in
Appendices A-1, A-2 and A-3 attached, while making allowance for the specific
characteristic of each project.
This specific methodology must be documented in such level of details
(preferably with tables and diagrams) to allow the readers of the assessment
report to grasp how the model is set up to simulate the situation at hand
without referring to the model input files. Details of the calculation of the emission rates of air
pollutants and a map showing all the road links for input to the modelling
shall be presented in the report.
The Applicant must ensure consistency between the text description and
the model files at every stage of submission. In case of doubt, prior agreement
between the Applicant and the Director on the specific modelling details is
advised.
(x)
The Applicant shall, based on the nature
of the activities analysed in (v) above,
identify the key/representative air pollutant parameters (types of pollutants
and the averaging time concentration) to be evaluated and provide explanation
for choosing these parameters for the assessment of the impact of the project.
(xi)
The Applicant shall calculate the
expected cumulative air pollutant concentrations at the identified ASRs and
compare these results against the criteria set out in section 1 of Annex 4 in
the TM. The predicted air quality
impacts (both unmitigated and mitigated) shall be presented in the form of
summary table and pollution contours, for comparison with relevant air quality
standards and examination of the land use implications of these impacts. Plans of suitable scale shall be used
for presentation of pollution contour to allow proper determination of buffer
distances requirements.
Submission
of model files
(xii)
All input and output file(s) of the model
run(s) shall be submitted to the Director in electronic format.
3.4.5 Noise
Assessment
3.4.5.1 The noise assessment is required only if ex
situ sediment treatment is recommended for the KTAC reclamation works in
accordance with section 3.4.2.2(vi) above and
that the sediment treatment facility is within 300m of any existing noise
sensitive receivers.
3.4.5.2 The Applicant shall follow the criteria and
guidelines for evaluating and assessing the construction noise impacts arising
from the project as stated in Annexes 5 and 13 of the TM, respectively.
3.4.5.3 The study
area for the noise impact assessment shall include all areas within 300m from
the Project boundary. For the
purpose of assessing the noise impact, the Applicant shall include all existing
noise sensitive receivers (NSRs).
The Applicant shall select assessment points to represent all identified
NSRs for carrying out quantitative noise assessment for construction noise
impacts. A map showing the
location and description such as name of building, use, and floors of each and
every selected assessment point shall be given.
3.4.5.4 The fixed
source noise impacts due to operation of sediment treatment facility shall be
assessed as follows:-
(i)
The Applicant shall
calculate the expected noise using standard acoustics principles. Calculations for the expected noise
shall be based on assumed plant inventories and utilization schedule for the
worst-case scenario. The Applicant
shall calculate the noise levels taking into account of correction of tonality,
impulsiveness and intermittence in accordance with the Technical Memorandum for
the Assessment of Noise from Places other than Domestic Premises, Public Places
or Construction Sites.
(ii)
The Applicant shall
present the noise levels in Leq (30 min) at the NSRs at various
representative floor levels (in m P.D.) on tables and plans of suitable scale.
(iii)
A quantitative
assessment at the NSRs for the fixed noise source shall be
carried out and compared against the
criteria set out in Table 1A of Annex 5 of the TM.
(iv)
The Applicant shall
propose direct mitigation measures within the project limits in all situations
where predicted noise level exceeds criteria set out in Table 1A of Annex 5 of
TM to protect affected NSRs.
3.4.6 Waste
Management Implications
3.4.6.1 The Applicant shall make reference to the
SEKDCFS-EIA, present all relevant information from the SEKDCFS-EIA on the
Project as detailed in sections
1.2 above, and incorporate any new and additional
information to address the waste impacts arising from the construction and
operation of the Project. The
Applicant shall follow the criteria and guidelines for evaluating and assessing
waste management implications as stated in Annexes 7 and 15 of the TM,
respectively.
3.4.6.2 The EIA report shall cover the followings:-
(i)
the quantity, quality and timing of the
waste arising as a result of the construction and operation activities, based
on the sequence and duration of these activities;
(ii)
the consideration of the
opportunities for reducing waste generation and on-site or off-site re-use
prior to considering the disposal options for various types of wastes. Measures which can be taken in the planning
and design stages, e.g. by modifying the design approach and in the
construction stage for maximizing waste reduction shall be separately
considered;
(iii)
having taken into account all the
opportunities for reducing waste generation and maximising reuse, the Applicant
shall estimate the types and quantities of the wastes required to be disposed
of as a consequence and shall describe the disposal options for each type of
waste in detail. The disposal
method recommended for each type of wastes shall take into account the result
of the assessment set out below.
The EIA report shall state clearly the disposal outlets for the wastes
identified; and
(iv)
the impact caused by handling (including
labelling, packaging & storage), collection, and disposal of wastes shall
be addressed in detail and appropriate mitigation measures proposed.
(a) potential hazard;
(b) air & odour
emission;
(c) noise;
(d) wastewater discharge;
and
(e) public transport.
3.4.7 Impacts
Summary
To facilitate easy retrieval of important information,
a summary of environmental impacts in the form of a table, or any other form
approved by the Director, showing the assessment points, results of impact
predictions, relevant standards or criteria, extents of exceedances predicted,
mitigation measures proposed and residual impacts, after mitigation measures
are implemented, etc., shall be given at the end of every chapter on each
individual impact in the EIA report as well as the Executive Summary.
3.4.8 Summary
of Environmental Outcomes
The
EIA report shall contain a summary of key environmental outcomes with suitable
plans and tables as appropriate; arising from the EIA study, including the
population and environmentally sensitive areas protected, environmentally
friendly designs recommended, key environmental problems avoided, compensation
areas included and the environmental benefits of environmental protection
measures recommended.
4. ENVIRONMENTAL
MONITORING & AUDIT (EM&A) REQUIREMENTS
4.1 The
Applicant shall also review the need for EM&A and/or environmental
management (EMS) activities during the construction and operation phases of the
Project with reference to the SEKDCFS-EIA and with consideration to any new and
additional information on the Project and, if affirmative:-
(i) to define the scope of the
EM&A requirements for the proposed developments in the EIA study; and/or
(ii) to set out the EMS requirements for
the construction and operation of the proposed developments to achieve
satisfactory environmental performance.
4.2 Subject to
the confirmation of the EIA study findings, the Applicant shall comply with the
requirements as stipulated in Annex 21 of the TM.
4.3 The
Applicant shall prepare a project implementation schedule (in the form of a
check list as shown in Appendix B) containing
all the EIA study recommendations and mitigation measures with reference to the
implementation programme.
5. DURATION
OF VALIDITY
5.1 This EIA
study brief is valid for 36 months after the date of issue. If the EIA study does not commence within
this period, the Applicant shall apply to the Director for a fresh EIA study
brief before commencement of the EIA study.
6. REPORT
REQUIREMENTS
6.1 In
preparing the EIA report, the Applicant shall refer to Annex 11 of the TM for
the contents of an EIA report. The Applicant shall also refer to Annex 20 of
the TM which stipulates the guidelines for the review of an EIA report.
6.3 The
Applicant shall supply the Director with the following number of copies of the
EIA report and the executive summary:
(i) 50
copies of the EIA report in English and 80 copies of the executive
summary (each bilingual in both English and Chinese) as required under section
6(2) of the EIAO to be supplied at the time of application for approval of the
EIA report;
(ii) when necessary,
addendum to the EIA report and the executive summary submitted in (i) above as required under section 7(1) of the
EIAO, to be supplied upon advice by the Director for public inspection;
(ii)
20 copies
of the EIA report in English and 50 copies of the executive summary
(each bilingual in both English and Chinese), with or without Addendum as
required under section 7(5) of the EIAO, to be supplied upon advice by the
Director for consultation with the Advisory Council on the Environment; and
(iii)
5 copies
of the EIA report in English and 10 copies of the executive summary
(each bilingual in both English and Chinese), with or without Addendum as
required under section 7(5) of the EIAO, for deposition in the Register, if and
when the EIA report is approved by the Director, as required under section 8(5)
of the EIAO.
6.4 The
Applicant shall make additional copies of the above documents available to the
public, subject to payment by the interested parties of full costs of printing.
6.5 In
addition, to facilitate the public inspection of the EIA report via the EIAO
Internet Website, the applicant shall provide electronic copies of both the EIA
report and the Executive Summary Report prepared in HyperText Markup Language
(HTML) (version 4.0 or later) and in DynaDoc Format (version 3.0 or later) [for
Chinese documents] and in Portable Document Format (PDF version 3.0 or later)
[for English documents], unless otherwise agreed by the Director. For the HTML version, a content page
capable of providing hyperlink to each section and sub-section of the EIA
report and the Executive Summary Report shall be included in the beginning of
the document, and all graphics in the report shall be in interlaced GIF format.
6.6 The
electronic copies of the EIA report and the Executive Summary shall be
submitted to the Director at the time of application for approval of the EIA
Report.
6.7 When the
EIA report and the Executive Summary are made available for public inspection
under section 7(1) of the EIAO, the content of the electronic copies of the EIA
report and the Executive Summary must be the same as the hard copies and the
Director shall be provided with the most updated electronic copies.
6.7 To promote
environmentally friendly and efficient dissemination of information, for future
EM&A reports recommended by the EIA study, both hardcopies and electronic
copies shall be required and their format shall be agreed by the Director.
7. OTHER
PROCEDURAL REQUIREMENTS
7.1 During the
EIA study, if there is any change in the name of the Applicant for this EIA
study brief, the Applicant mentioned in this study brief must notify the
Director immediately.
7.2 If there is
any key change in the scope of the project mentioned in section 1.2 of this EIA study brief and in the Project Profile
(No.PP-162/2002), the Applicant must seek confirmation from the Director in
writing on whether or not the scope of issues covered by this EIA study brief
can still cover the key changes, and the additional issues, if any, that the
EIA study must also address. If
the changes to the project fundamentally alter the key scope of the EIA study
brief, the Applicant shall apply to the Director for another EIA study brief
afresh.
----
END OF STUDY BRIEF ----
April
2002
Environmental
and Noise Division
Environmental
Protection Department
Appendix A-1
Guidelines on Choice of Models and Model Parameters
1. Introduction
1.1 This paper describes the usage and requirements of a few commonly used air quality models.
2.
Choice
of Models
2.1 The models
which have been most commonly used in air quality impact assessments, due
partly to their ease of use and partly to the quick turn-around time for
results, are of Gaussian type and designed for use in simple terrain under
uniform wind flow. There are circumstances when these models are not suitable
for ambient concentration estimates and other types of models such as physical,
numerical or mesoscale models will have to be used. In situations where
topographic, terrain or obstruction effects are minimal between source and
receptor, the following Gaussian models can be used to estimate the near-field
impacts of a number of source types including dust, traffic and industrial
emissions.
Model
Applications
FDM for
evaluating fugitive and open dust source impacts (point, line and area sources)
CALINE4 for
evaluating mobile traffic emission impacts (line sources)
ISCST3 for
evaluating industrial chimney releases as well as area and volumetric sources
(point, area and volume sources); line sources can be approximated by a number
of volume sources.
These
frequently used models are also referred to as Schedule 1 models (see attached
list).
2.2
Note that both FDM and CALINE4 have a
height limit on elevated sources (20 m and 10m, respectively). Source of
elevation above these limits will have to be modelled using the ISCST3 model or
suitable alternative models. In using the latter, reference shall be made to
the 'Guidelines on the Use of Alternative Computer Models in Air Quality
Assessment' in Appendix B-3.
2.3
The models can be used to estimate both
short-term (hourly and daily average) and long-term (annual average) ambient
concentrations of air pollutants. The model results, obtained using appropriate
model parameters (refer to Section 3) and assumptions, allow direct comparison
with the relevant air quality standards such as the Air Quality Objectives
(AQOs) for the relevant pollutant and time averaging period.
3. Model
Input Requirements
3.1 Meteorological
Data
3.1.1 At least 1 year of recent
meteorological data (including wind speed, wind direction, stability class, ambient
temperature and mixing height) from a weather station either closest to or
having similar characteristics as the study site shall be used to determine the
highest short-term (hourly, daily) and long-term (annual) impacts at identified
air sensitive receivers in that period.
The amount of valid data for the period shall be no less than 90
percent.
3.1.2 Alternatively, the
meteorological conditions as listed below can be used to examine the worst case
short-term impacts:
Day
time:
stability
class D; wind speed 1 m/s (at 10m height); worst-case wind angle; mixing height
500 m
Night
time:
stability
class F; wind speed 1 m/s (at 10m height); worst case wind angle; mixing height
500 m
This
is a common practice with using the CALINE4 model due to its inability to
handle lengthy data set.
3.1.3 For situations where, for
example, (i) the model (such as CALINE4) does not allow easy handling of one
full year of meteorological data; or (ii) model run time is a concern, the
followings can be adopted in order to determine the daily and annual average
impacts:
(i)
perform a frequency occurrence analysis
of one year of meteorological data to determine the actual wind speed (to the
nearest unit of m/s), wind direction (to the nearest 10o) and
stability (classes A to F) combinations and their frequency of occurrence;
(ii)
determine the short term hourly impact
under all of the identified wind speed, wind direction and stability
combinations; and
(iii)
apply the frequency data with the short
term results to determine the long term (daily / annual) impacts.
Apart
from the above, any alternative approach that will capture the worst possible
impact values (both short term and long term) may also be considered.
3.1.4 Note that the anemometer height
(relative to a datum same for the sources and receptors) at which wind speed
measurements were taken at a selected station should be correctly entered in
the model. These measuring
positions can vary greatly from station to station and the vertical wind
profile employed in the model can be grossly distorted from the real case if
incorrect anemometer height is used. This will lead to unreliable concentration
estimates.
3.1.5 An additional parameter,
namely, the standard deviation of wind direction, σΘ,
needs to be provided as input to the CALINE4 model. Typical values ofσΘ
range from 12o for rural areas to 24o for highly
urbanised areas under 'D' class stability. For semi-rural such as new
development areas, 18o is more appropriate under the same stability
condition. The following reference can be consulted for typical ranges of
standard deviation of wind direction under different stability categories and
surface roughness conditions.
Ref.(1): Guideline On Air Quality Models (Revised), EPA-450/2-78-027R, United States Environmental Protection Agency, July 1986.
3.2 Emission
Sources
All
the identified sources relevant to a process plant or a study site shall be
entered in the model and the emission estimated based on emission factors
compiled in the AP-42 (Ref. 2) or other suitable references. The relevant
sections of AP-42 and any parameters or assumptions used in deriving the
emission rates (in units g/s, g/s/m or g/s/m2) as required by the model shall
be clearly stated for verification. The physical dimensions, location, release
height and any other emission characteristics such as efflux conditions and
emission pattern of the sources input to the model shall also correspond to
site data.
If
the emission of a source varies with wind speed, the wind speed-dependent
factor shall be entered.
Ref.(2): Compilation of Air Pollutant Emission Factors, AP-42, 5thEdition, United States Environmental Protection Agency, January 1995.
3.3 Urban/Rural
Classification
Emission
sources may be located in a variety of settings. For modelling purposes these
are classed as either rural or urban so as to reflect the enhanced mixing that
occurs over urban areas due to the presence of buildings and urban heat
effects. The selection of either rural or urban dispersion coefficients in a
specific application shall follow a land use classification procedure. If the
land use types including industrial, commercial and residential uses account
for 50% or more of an area within 3 km radius from the source, the site is classified
as urban; otherwise, it is classed as rural.
3.4 Surface
Roughness Height
This
parameter is closely related to the land use characteristics of a study area
and associated with the roughness element height. As a first approximation, the
surface roughness can be estimated as 3 to 10 percent of the average height of
physical structures. Typical values used for urban and new development areas
are 370 cm and 100 cm, respectively.
3.5 Receptors
These
include discrete receptors representing all the identified air sensitive
receivers at their appropriate locations and elevations and any other discrete
or grid receptors for supplementary information. A receptor grid, whether
Cartesian or Polar, may be used to generate results for contour outputs.
3.6 Particle
Size Classes
In
evaluating the impacts of dust-emitting activities, suitable dust size
categories relevant to the dust sources concerned with reasonable breakdown in
TSP (< 30 μm)
and RSP (< 10 μm)
compositions shall be used.
3.7 NO2
to NOx Ratio
The
conversion of NOx to NO2 is a result of a series of
complex photochemical reactions and has implications on the prediction of near
field impacts of traffic emissions. Until further data are available, three
approaches are currently acceptable in the determination of NO2:
(a)
Ambient Ratio Method (ARM) - assuming 20%
of NOx to be NO2; or
(b)
Discrete Parcel Method (DPM, available in
the CALINE4 model); or
(c)
Ozone Limiting Method (OLM) - assuming
the tailpipe NO2 emission to be 7.5% of NOx and the
background ozone concentration to be in the range of 57 to 68 μg/m3
depending on the land use type (see also the reference paper 'Guidelines on
Assessing the 'TOTAL' Air Quality Impacts' in Appendix B-2).
3.8 Plume Rise
Options
The
ISCST3 model provides by default a list of the U.S. regulatory options for
concentration calculations. These are all applicable to the Hong Kong
situations except for the 'Final Plume Rise' option. As the distance between
sources and receptors are generally fairly close, the non-regulatory option
of 'Gradual Plume Rise' shall be
used instead to give more accurate estimate of near-field impacts due to plume
emission. However, the 'Final Plume Rise' option may still be used for assessing
the impacts of distant sources.
3.9 Portal
Emissions
These
include traffic emissions from tunnel portals and any other similar openings
and are generally modelled as volume sources according to the PIARC 91 (or more
up-to-date version) recommendations (Ref. 3, section III.2). For emissions
arising from underpasses or any horizontal openings of the like, these are
treated as area or point sources depending on the source physical dimensions.
In all these situations, the ISCST3 model or more sophisticated models will
have to be used instead of the CALINE4 model. In the case of portal emissions
with significant horizontal exit velocity which cannot be handled by the ISCST3
model, the impacts may be estimated by the TOP model (Ref. 4) or any other suitable
models subject to prior agreement with EPD. The 'Guidelines on the Use of Alternative Computer Models in
Air Quality Assessment' should also be referred to in Appendix B-3.
Ref.(3):
XIXth World Road Congress Report, Permanent International Association of Road
Congresses (PIARC), 1991.
Ref.(4): N. Ukegunchi, H. Okamoto and Y. Ide "Prediction of vehicular emission pollution around a tunnel mouth", Proceedings 4th International Clean Air Congress, pp. 205-207, Tokyo, 1977.
3.10 Background
Concentrations
Background
concentrations are required to account for far-field sources which cannot be
estimated by the model. These values, to be used in conjunction with model
results for assessing the total impacts, should be based on long term average
of monitoring data at location representative of the study site. Please make
reference to the paper 'Guidelines on Assessing the 'TOTAL' Air Quality
Impacts' in Appendix B-2 for further information.
3.11 Output
The
highest short-term and long-term averages of pollutant concentrations at
prescribed receptor locations are output by the model and to be compared
against the relevant air quality standards specified for the relevant
pollutant. Contours of pollutant concentration are also required for indicating
the general impacts of emissions over a study area.
Copies
of model files in electronic format should also be provided for EPD's
reference.
------------------------------------------------------------------------------------------------------
Schedule 1
Air Quality Models
Generally Accepted by
Hong Kong
Environmental Protection Department for
Regulatory
Applications as at 1 July 1998
Industrial
Source Complex Dispersion Model - Short Term Version 3 (ISCST3)
or the latest version developed by U.S. Environmental Protection Agency
California
Line Source Dispersion Model Version 4 (CALINE4)
or the latest version developed by Department of Transportation, State of
California, U.S.A.
Fugitive Dust Model (FDM) or the latest version developed by U.S. Environmental Protection Agency
Appendix A-2
Guidelines on Assessing the 'TOTAL' Air Quality Impacts
1. Total
Impacts - 3 Major Contributions
1.1
In evaluating the air quality impacts of
a proposed project upon air sensitive receivers, contributions from three
classes of emission sources depending on their distance from the site should be
considered. These are:
Primary
contributions: project
induced
Secondary
contributions: pollutant-emitting
activities in the immediate neighbourhood
Other
contributions: pollution
not accounted for by the previous two
(Background
contributions)
2. Nature
of Emissions
2.1 Primary
contributions
In
most cases, the project-induced emissions are fairly well defined and quite
often (but not necessarily) the major contributor to local air quality impacts.
Examples include those due to traffic network, building or road construction
projects.
2.2 Secondary
contributions
Within
the immediate neighbourhood of the project site, there are usually pollutant
emitting activities contributing further to local air quality impacts. For most
local scale projects, any emission sources in an area within 500m radius of the
project site with notable impacts should be identified and included in an air
quality assessment to cover the short-range contributions. In the exceptional
cases where there is one or more significant sources nearby, the study area may
have to be extended or alternative estimation approach employed to ensure these
impacts are reasonably accounted for.
2.3 Background
contributions
The
above two types of emission contributions should account for, to a great
extent, the air quality impacts upon local air sensitive receivers, which are
often amenable to estimation by the 'Gaussian Dispersion' type of models.
However, a background air quality level should be prescribed to indicate the
baseline air quality in the region of the project site, which would account for
any pollution not covered by the two preceding contributions. The emission
sources contributing to the background air quality would be located further
afield and not easy to identify. In addition, the transport mechanism by which
pollutants are carried over long distances (ranging from 1km up to tens or
hundreds of kms) is rather complex and cannot be adequately estimated by the
'Gaussian' type of models.
3. Background
Air Quality - Estimation Approach
3.1 The
approach
In
view of the difficulties in estimating background air quality using the air
quality models currently available, an alternative approach based on monitored
data is suggested. The essence of this approach is to adopt the long-term
(5-year) averages of the most recent monitored air quality data obtained by
EPD. These background data would be reviewed yearly or biennially depending on
the availability of the monitored data. The approach is a first attempt to
provide a reasonable estimate of the background air quality level for use in
conjunction with EIA air quality assessment to address the cumulative impacts
upon a locality. This approach may be replaced or supplemented by superior
modelling efforts such as that entailed in PATH (Pollutants in the Atmosphere
and their Transport over Hong Kong), a comprehensive territory-wide air quality
modelling system currently being developed for Hong Kong. Notwithstanding this,
the present approach is based on measured data and their long term regional
averages; the background values so derived should therefore be indicative of
the present background air quality. In the absence of any other meaningful way
to estimate a background air quality for the future, this present background
estimate should also be applied to future projects as a first attempt at a
comprehensive estimate until a better approach is formulated.
3.2 Categorisation
The
monitored air quality data, by 'district-averaging' are further divided into
three categories, viz, Urban, Industrial and Rural/New Development. The background
pollutant concentrations to be adopted for a project site would depend on the
geographical constituency to which the site belongs. The categorisation of
these constituencies is given in Section 3.4. The monitoring stations suggested
for the 'district-averaging'(arithmetic means) to derive averages for the three
background air quality categories are listed as follows:
Urban: Kwun
Tong, Sham Shui Po, Tsim Sha Tsui and Central/Western
Industrial: Kwun
Tong, Tsuen Wan and Kwai Chung
Rural/New
Development: Sha
Tin, Tai Po, Junk Bay, Hong Kong South and Yuen Long
The
averaging would make use of data from the above stations wherever available.
The majority of the monitoring stations are located some 20m above ground.
3.3 Background
pollutant values
Based
on the above approach, background values for the 3 categories have been
obtained for a few major air pollutants as follows:
POLLUTANT |
URBAN |
INDUSTRIAL |
RURAL / NEW DEVELOPMENT |
NO2 |
59 |
57 |
39 |
SO2 |
21 |
26 |
13 |
O3 |
62 |
68 |
57 |
TSP |
98 |
96 |
87 |
All
units are in micrograms per cubic metre. The above values are derived from 1992
to 1996 annual averages with the exception of ozone which represent annual
average of daily hourly maximum values for year 1996.
In
cases where suitable air quality monitoring data representative of the study
site such as those obtained from a nearby monitoring station or on-site
sampling are not available for the prescription of background air pollution
levels, the above tabulated values can be adopted instead. Strictly speaking, the suggested values
are only appropriate for long term assessment. However, as an interim measure
and until a better approach is formulated, the same values can also be used for
short term assessment. This implies that the short term background values will
be somewhat under-estimated, which compensates for the fact that some of the
monitoring data are inherently influenced by secondary sources because of the
monitoring station location.
Indeed,
if good quality on-site sampling data which cover at least one year period are
available, these can be used to derive both the long term (annual) and short
term (daily / hourly) background values, the latter are usually applied on an
hour to hour, day to day basis.
3.4 Site
categories
The
categories to which the 19 geographical constituencies belong are listed as
follows:
DISTRICT |
AIR QUALITY CATEGORY |
Islands |
Rural / New Development |
Southern |
Rural / New Development |
Eastern |
Urban |
Wan Chai |
Urban |
Central & Western |
Urban |
Sai Kung |
Rural / New Development |
Kwun Tong |
Industrial |
Wong Tai Sin |
Urban |
Kowloon City |
Urban |
Yau Tsim |
Urban |
Mong Kok |
Urban |
Sham Shui Po |
Urban |
Kwai Tsing |
Industrial |
Sha Tin |
Rural / New Development |
Tsuen Wan |
Industrial |
Tuen Mun |
Rural / New Development |
Tai Po |
Rural / New Development |
Yuen Long |
Rural / New Development |
Northern |
Rural / New Development |
3.5 Provisions for
'double-counting’
The
current approach is, by no means, a rigorous treatment of background air
quality but aims to provide an as-realistic-as-possible approximation based on
limited field data. 'Double-counting' of 'secondary contributions' may be apparent
through the use of such 'monitoring-based' background data as some of the
monitoring stations are of close proximity to existing emission sources.
'Primary contributions' due to a proposed project (which is yet to be realized)
will not be double-counted by such an approach. In order to avoid
over-estimation of background pollutant concentrations, an adjustment to the
values given in Section 3.3 is possible and optional by multiplying the
following factor:
(1.0 - ESecondary contributions/ETerritory)
where E stands for emission.
The
significance of this factor is to eliminate the fractional contribution to
background pollutant level of emissions due to 'secondary contributions' out of
those from the entire territory. In most cases, this fractional contribution to
background pollutant levels by the secondary contributions is minimal.
4. Conclusions
4.1 The above
described approach to estimating the total air quality impacts of a proposed
project, in particular the background pollutant concentrations for air quality
assessment, should be adopted with immediate effect. Use of short term
monitoring data to prescribe the background concentrations is no longer
acceptable.
Appendix A-3
Guidelines on the Use of Alternative Computer Models in Air Quality Assessment
1. Background
1.1
In Hong Kong, a number of Gaussian plume
models are commonly employed in regulatory applications such as application for
specified process licences and environmental impact assessments (EIAs). These
frequently used models (as listed in Schedule 1 attached; hereafter referred to
as Schedule 1 models) have no regulatory status but form the basic set of tools
for local-scale air quality assessment in Hong Kong.
1.2
However, no single model is sufficient to
cover all situations encountered in regulatory applications. In order to ensure
that the best model available is used for each regulatory application and that
a model is not arbitrarily applied, the project proponent (and/or its
environmental consultants) should assess the capabilities of various models
available and adopt one that is most suitable for the project concerned.
1.3
Examples of situations where the use of
an alternative model is warranted include:
(i)
the complexity of the situation to be
modelled far exceeds the capability of the Schedule 1 models; and
(ii) the
performance of an alternative model is comparable or better than the Schedule 1
models.
1.4 This
paper outlines the demonstration / submission required in order to support the
use of an alternative air quality model for regulatory applications for Hong
Kong.
2. Required
Demonstration / Submission
2.1 Any
model that is proposed for air quality applications and not listed amongst the
Schedule 1 models will be considered by EPD on a case-by-case basis. In such cases, the proponent will have
to provide the followings for EPD's review:
(i)
Technical details of the proposed model;
and
(ii)
Performance evaluation of the proposed
model
Based
on the above information, EPD will determine the acceptability of the proposed
model for a specific or general applications. The onus of providing adequate
supporting materials rests entirely with the proponent.
2.2 To
provide technical details of the proposed model, the proponent should submit
documents containing at least the following information:
(i)
mathematical formulation and data
requirements of the model;
(ii)
any previous performance evaluation of
the model; and
(iii)
a complete set of model input and output file(s)
in commonly used electronic format.
2.3
On performance evaluation, the required
approach and extent of demonstration varies depending on whether a Schedule 1
model is already available and suitable in simulating the situation under
consideration. In cases where no Schedule 1 model is found applicable, the
proponent must demonstrate that the proposed model passes the screening test as
set out in USEPA Document "Protocol for Determining the Best Performing
Model" (Ref. 1).
2.4
For cases where a Schedule 1 model is
applicable to the project under consideration but an alternative model is
proposed for use instead, the proponent must demonstrate either that
(i)
the highest and second highest
concentrations predicted by the proposed model are within 2 percent of the
estimates obtained from an applicable Schedule 1 model (with appropriate
options chosen) for all receptors for the project under consideration; or
(ii)
the proposed model has superior
performance against an applicable Schedule 1 model based on the evaluation procedure
set out in USEPA Document
"Protocol for Determining the Best Performing Model" (Ref. 1).
2.5
Should EPD find the information on
technical details alone sufficient to indicate the acceptability of the
proposed model, information on further performance evaluation as specified in
Sections 2.3 and 2.4 above would not be necessary.
2.6
If the proposed model is an older version
of one of the Schedule 1 models or was previously included in Schedule 1, the
technical documents mentioned in Section 2.2 are normally not required. However, a performance demonstration of
equivalence as stated in Section 2.4 (i) would become necessary.
2.7
If EPD is already in possession of some
of the documents that describe the technical details of the proposed model,
submission of the same by the proponent is not necessary. The proponent may
check with EPD to avoid sending in duplicate information.
-------------------------------------------------------------------------------------------------------
Schedule
1
Air Quality Models Generally Accepted
by
Hong Kong
Environmental Protection Department for
Regulatory
Applications as at 1 July 1998
Industrial
Source Complex Dispersion Model - Short Term Version 3 (ISCST3)
or the latest version developed by U.S. Environmental Protection Agency
California
Line Source Dispersion Model Version 4 (CALINE4)
or the latest version developed by Department of Transportation, State of
California, U.S.A.
Fugitive
Dust Model (FDM) or the latest version developed by U.S. Environmental
Protection Agency
-------------------------------------------------------------------------------------------------------
Ref. (1): William M. Cox, "Protocol for Determining the Best Performing Model" Publication No. EPA-454/R-92-025; U.S. Environmental Protection Agency, Research Triangle Park, NC.
Appendix
B
Implementation
Schedule
South
East Kowloon Development – Kai Tak Approach Channel Reclamation
EIA
Ref. |
EM&A
Ref. |
Recommended Mitigation Measures |
Objectives of the Recommended Measure & Main Concern
to Address |
Who to implement the measure? |
Location of the measure |
When to implement the measure? |
What requirements or standards for the measure to achieve? |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|