Environmental Impact [E(TA)31]Assessment Ordinance
(Cap. 499)
Section 5(7)
Environmental Impact Assessment
Study Brief No. ESB-101/2002
Project
Title: Drainage Improvements in Southern Lantau
Name of Applicant:
Drainage Services Department
(hereinafter known as
the “Applicant”)
1. BACKGROUND
1.1
An application (No. ESB-101/2002) for an
Environmental Impact Assessment (EIA) study brief under section 5(1) of the
Environmental Impact Assessment Ordinance (EIAO) was submitted by the Applicant
on 22 March 2002 with a Project Profile (No. PP-165/2002) for the captioned
proposed project.
1.2 The
proposed project includes the following major items of works:
(i)
Pak Ngan Heung River with location shown
in Figure 1:
(a)
construction of approximately 140 m
four-cell culvert flood bypass under the emergency vehicle access (EVA) for the
hairpin meander leading downstream of the access bridge;
(b)
construction of approximately 130m of
channel by using grasscrete and masonry lined banks with natural bed both at
the upstream and downstream of the flood bypass culvert and reprovision of the EVA and the 3.5 m wide access road; and
(c)
extension and enlarging of existing
U-channel of approximately 120 m to reroute the runoff from Butterfly Hill
around the low lying area of Ling Tsui Tau Tsuen into the Pak Ngan Heung River.
(ii)
Tai Tei Tong River with location shown in
Figure 2: construction of 350 m of channel using grasscrete and masonry lined
banks with natural bed from Mui Wo primary School to the rivers confluence.
(iii) Luk
Tei Tong 2 River with location shown in Figure 3: construction of 400m of
channel using grasscrete and masonry lined banks with natural bed.
(iv) Luk
Tei Tong River with location shown in Figure 3 : Extension of existing gabion
channelisation downstream to River Silver confluence using a grasscrete and
masonry lined channel with natural bed.
1.3 The
proposed project is a Designated Project under Schedule 2 Part I of the EIAO
and requires an environmental permit under the EIAO for its construction and
operation.
1.4 Pursuant to
section 5(7)(a) of the EIAO, the Director of Environmental Protection (the
Director) issues this EIA study brief to the Applicant to carry out an EIA
study.
1.5
The purpose
of this EIA study is to provide information on the nature and extent of
environmental impacts arising from the construction and operation of the
proposed project and related activities taking place concurrently. This information will contribute to
decisions by the Director on:
(i) the overall
acceptability of any adverse environmental consequences that are likely to
arise as a result of the proposed project;
(ii)
the conditions and requirements for the
detailed design, construction and operation of the proposed project to mitigate
against adverse environmental consequences wherever practicable; and
(iii) the
acceptability of residual impacts after the proposed mitigation measures are
implemented.
2. OBJECTIVES
OF THE EIA STUDY
2.1
The objectives of the EIA study are as
follows:
(i)
to describe the proposed project and associated
works together with the requirements for carrying out the proposed project;
(ii) to identify and
describe the elements of the community and environment likely to be affected by
the proposed project and/or likely to cause adverse impacts to the proposed
project, including both the natural and man-made environment and the associated
environmental constraints;
(iii) to identify and
quantify emission sources and determine the significance of impacts on
sensitive receivers and potential affected uses;
(iv) to identify any
potential impacts from point and non-point pollution sources on the identified
water systems and sensitive receivers during the construction and operation
stages;
(v)
to identify and quantify any potential
losses and damage to flora, fauna and wildlife habitats;
(vi)
to identify any potential impacts to the
historical, archaeological and cultural resources and propose measures to
mitigate these impacts;
(viii) to propose the provision of
infrastructure or mitigation measures so as to minimize pollution,
environmental disturbance and nuisance during construction and operation of the
proposed project;
(ix) to identify, predict
and evaluate the residual (i.e. after practicable mitigation) environmental
impacts and the cumulative effects expected to arise during the construction
and operation phases of the proposed project in relation to the sensitive
receivers and potential affected uses;
(x) to identify,
assess and specify methods, measures and standards, to be included in the
detailed design, construction and operation of the proposed project, which are
necessary to mitigate these environmental impacts and reducing them to
acceptable levels;
(xi) to investigate the extent
of secondary environmental impacts that may arise from the proposed mitigation
measures and to identify constraints associated with the mitigation measures
recommended in the EIA study, as well as the provision of any necessary
modification;
(xii)
to design and specify the environmental
monitoring and audit requirements, if required, to ensure the implementation
and the effectiveness of the environmental protection and pollution control
measures adopted; and
(xiii) to consider alternatives with
a view to avoiding or minimizing the potential environmental impacts to the
sensitive uses, and to compare the environmental benefits and dis-benefits of
each of the different drainage channel design and to provide reasons for
selecting the preferred design(s) and to describe the part environmental
factors played in the selection.
3. DETAILED
REQUIREMENTS OF THE EIA STUDY
3.1 The
Purpose
The
purpose of this study brief is to scope the key issues of the EIA study. The Applicant has to demonstrate in the
EIA report that the criteria in the relevant sections of the Technical
Memorandum on the EIA Process of the EIAO (hereinafter referred to as the TM)
are fully complied with.
3.2 The
Scope
The
scope of this EIA study covers the proposed project mentioned in section 1.2
above. The EIA study shall address
the likely key issues described below; together with any key issues identified
during the course of the EIA study.
(i)
the potential impacts on the drainage
system, hydrology, ground water, and water quality on the Luk Tei Tong
freshwater marsh during construction and operation phases of the proposed
project,
(ii)
the potential aquatic and terrestrial
ecological impacts on the Luk Tei Tong freshwater marsh and Butterfly Hill
Conservation Area arising from the construction works, including loss of
habitats, removal of vegetation and disturbance to animals of the proposed
project;
(iii)
the potential noise and dust impacts to
sensitive receivers during the construction phases, in particular at areas near
the school(s), village houses and other residential dwellings of the proposed
project; and
(iv)
the potential impacts on the cultural
heritage sites, in particular Chung Hau Archaeological Site, and the two historical
watch towers at Luk Tei Tong and Chung Hau, if they are affected by the
construction works of the proposed project.
3.3
Consideration
of the Alternative Drainage Channel Designs and Construction Methods
3.3.1 The
Alternative Drainage Channel Designs
The
project has potential to cause loss of habitat at the Luk Tei Tong freshwater
marsh and the associated riparian habitat and the Butterfly Hill. The Applicant should justify in the EIA
report why the drainage channel design stated in the project Profile has been
selected among other possible alternatives, including environmental and other
considerations. A comparison of the environmental benefits and dis-benefits of
the possible drainage channel designs shall be made.
3.3.2
Consideration
of Alternative Construction Methods and Sequences of Works
Having
regard to the cumulative effects of the construction period and the possible
adverse construction impacts to the affected sensitive receivers along the
rivers, the EIA study shall also explore alternative construction methods and
sequences of works for the proposed project with a view to avoiding and
minimising adverse environmental impacts to the maximum practicable
extent. A comparison of the
environmental benefits and dis-benefits of applying different construction
methods shall be made. The
Applicant shall take into account the environmental implications of potential
flooding at downstream areas in wet seasons during construction phases in the
comparison.
3.3.3
Taking into the comparisons in sections
3.3.1 and 3.3.2 above, the Applicant shall recommend/justify the adoption of
the drainage channel design that will avoid or minimize adverse environmental
impacts.
3.4 Technical
Requirements
The
Applicant shall conduct the EIA study to address all environmental aspects of
the activities as described in the scope as set out above and subject to the
findings under section 3.3. The
EIA study shall include the following technical requirements on specific
impacts:-
3.4.1 Ecological Impact (Both Terrestrial and Aquatic)
3.4.1.1 The
Applicant shall follow the criteria and guidelines for evaluating and assessing
ecological impact as stated in Annexes 8 and 16 of the TM respectively. The assessment area for the purpose of
terrestrial ecological assessment shall include all areas within 500 m distance
from the site boundary of the works areas, or the area likely to be impacted by
the proposed project. For aquatic
ecology, the assessment area shall be the same as for the water quality
assessment described in section 3.4.2.2.
3.4.1.2 (i) The
project involves channelization of natural rivers, which will disturb the
bottom sediments, alter water movement of the four rivers (Pak Ngan Heung
River, Tai Tei Tong River, Luk Tei Tong River, and Luk Tei Tong 2 River) and
affect the riparian habitats.
Therefore important habitats including the Luk Tei Tong freshwater
marsh, which has a direct ecological linkage with the Luk Tei Tong river
system, and Butterfly Hill and the flora and fauna living in or associated with
the rivers may be affected by the project. As such, the ecological baseline of the four
rivers and the affected areas should be properly established, the environmental
impact from the project thoroughly assessed and effective mitigation measures
suggested in the EIA report;
(ii) In
the ecological impact assessment, the Applicant shall examine the flora, fauna
and other components of the ecological habitats within the assessment
area. The aim shall be to protect,
maintain or rehabilitate the natural environment. The assessment shall identify and quantify as far as
possible the potential ecological impacts on the areas such as natural river,
riparian, wetland and woodland habitats and the associated wildlife arising
from the proposed project, including the impacts of any haul roads, temporary
work sites and access.
3.4.1.3 The
assessment shall include the following:
(i) A
review of the findings of relevant studies and collating all the available
information regarding the ecological characters of the assessment area;
(ii) Evaluation
of the information collected and identification of any information gap relating
to the assessment of potential ecological impacts to the terrestrial and
aquatic environment;
(iii) Carrying
out the necessary ecological field surveys (the duration of which shall be at
least 9 months and shall cover both the wet and dry seasons) and investigations
to verify the information collected, fill the information gaps identified and
fulfil the objectives of the EIA study;
(iv) Establishing
the general ecological profile and describing the characteristics of each
habitat found; major information to be provided shall include:
(a)
description
of the physical environment;
(b)
habitat
maps of suitable scale (1:1000 to 1:5000) showing the types and locations of
habitats in the assessment area;
(c)
description
of the ecological characteristics of each habitat type including size,
vegetation type, species present, dominant species found, species diversity and
abundance, community structure, seasonality and inter-dependence of the
habitats and species, and presence of any features of ecological importance;
(d)
representative
colour photos of each habitat type and of any important ecological features
identified;
(e)
species
found that are rare, endangered and/or listed under local legislation,
international conventions for conservation of wildlife/habitats or red data
books;
(v)
Investigation
and description of the existing wildlife uses of relevant habitats with special
attention to those wildlife groups and habitats of conservation interests;
including:
(a)
woodlands;
(b)
natural
stream courses and associated stream fauna;
(c)
wetlands;
(d)
vertebrates
(e.g. avifauna, mammals, fish, herpetofauna);
(e)
macro-invertebrates
(e.g. dragonflies, butterflies);
(f)
and any
other habitats and wildlife groups identified as having special conservation
interests such as Romer’s Free Frog by this EIA study;
(vi)
Description
of all recognized sites of conservation importance in the proposed project site
and its vicinity and assessment of whether these sites will be affected by the
proposed project or not;
(vii)
Using suitable methodology,
identification and quantification as far as possible of any direct, indirect,
on-site, off-site, primary, secondary and cumulative ecological impacts such as
destruction of habitats, reduction of species abundance/diversity, loss of
feeding grounds, reduction of ecological carrying capacity, habitat
fragmentation; and in particular habitat loss and disturbance to stream and
wetland-dependent wildlife groups during the construction stage;
(viii)
Evaluation
of the significance and acceptability of the ecological impacts identified
using well-defined criteria;
(ix)
Recommendations
for all possible alternatives, such as modifications of layout and design and
practicable mitigation measures to avoid, minimize and/or compensate for the
adverse ecological impacts identified, such as reinstatement of habitats
temporarily affected by the proposed project to its original state and if
possible with some enhancement features;
(x)
Evaluation
of the feasibility and effectiveness of the recommended mitigation measures and
definition of the scope, type, location, implementation arrangement, resources
requirement, subsequent management and maintenance of such measures;
(xi)
The EIA
study shall aim at maintaining the natural streams in the study area if the
ecological field survey as described in (iii) above suggested that they are
ecologically important streams.;
(xii)
The EIA
study shall address the impact on aquatic wildlife in streams due to this
project. The study period should include June/July as high summer and wet
season, October as passage migration period, and January to April as dry season
and spring migration period.
The habitants of the streams / rivers, i.e. aquatic wildlife, will be
firstly affected by the project;
(xiii)
The EIA
study shall address the habitat loss, in particular at freshwater marsh at Luk
Tei Tong, and the hydrology due to the captioned project
(xiv)
Determination
and quantification as far as possible of the residual ecological impacts after
implementation of the proposed mitigation measures;
(xv)
Evaluation
of the severity and acceptability of the residual ecological impacts using
well-defined criteria;
(xvi)
A review
of the need for and recommendation for any ecological monitoring programme is
required; and
(xvii)
Planning on
the ecological monitoring after channelization of the three rivers should be
included in the future EIA to assess the successfulness of recolonization of
flora and fauna in the disturbed rivers and riparian habitats. Contingency habitat rehabilitation plan
should also be considered in the EIA, in case wildlife recolonization is shown
to be unsuccessful.
3.4.2 Water
Quality Impact
3.4.2.1 The
Applicant shall follow the criteria and guidelines for evaluating and assessing
water pollution as stated in Annexes 6 and 14 of the TM respectively.
3.4.2.2 The assessment area for
the water quality impact assessment shall include all areas within 500 m from
the project boundary, the area shall include but not limited to the Luk Tei
Tong freshwater marsh. This assessment
area could be extended to include other areas such as stream courses and the
associated water system in the vicinity being impacted during the course of the
EIA study if found justifiable.
3.4.2.3 The
Applicant shall identify and analyse all physical, chemical and biological
disruptions of fresh water or ground water system(s), catchment area(s),
stormwater channel(s) and coastal water(s) arising from the construction and
operation of the proposed project.
3.4.2.4 The
Applicant shall include (1) the construction phase impacts on water quality at
the site (2) operational phase impacts on water quality at Luk Tei Tong
freshwater marsh and downstream of the site due to the natural process of
siltation, flows and water velocity, and re-suspensions of sediments. Essentially, the assessment shall
address the following:
(i)
Collection and review of background
information on the existing and planned water systems and their respective
catchments and sensitive receivers which might be affected by the proposed
project during construction and operation;
(ii)
Characterization
of water and sediment quality of the water systems
and respective catchments and sensitive receivers which might be affected by
the proposed project during construction and operation based on existing
information or appropriate site survey and tests;
(iii)
Identification and analysis of all
existing and planned activities and beneficial uses related to the water
system(s) and identification of all water sensitive receivers. The Applicant shall
refer to, inter alia, those
developments and uses earmarked on the relevant outline zoning plans, outline
development plans and layout plans;
(iv)
Identification
of pertinent water and sediment quality objectives and establishment of other
appropriate water and sediment quality criteria or standards for the water
system(s) and all the sensitive receivers in (i) & (iii) above;
(v)
Review the specific construction methods
and configurations, and operation of the proposed project. Identification of any alteration of existing water courses,
natural streams/ponds, flow regimes, ground water levels and catchment types or
areas;
(vi)
Identification,
analysis and quantification of all existing, likely future water and sediment
pollution sources, including point discharges and non-point sources to surface
water runoff and analyse these in relation to the provision and adequacy of
future facilities to reduce such pollution in terms of capacity and levels of
treatment; evaluation and quantification through
appropriate site investigation and tests to the pollution loading intercepted
by the proposed project and discharged into the Luk Tei Tong freshwater marsh
and the downstream water bodies; evaluation and quantification of the
flows and pollution loads collected and discharged into the existing and
planned downstream water courses and drainage systems before and after
operation of the proposed project;
(vii)
Establishment
and provision of a pollution load inventory on the
quantities and characteristics of all existing and likely future water
pollution sources identified above.
Field investigation and laboratory tests shall be conducted as appropriate
to fill in any major information gaps;
(viii)
Cumulative impacts due to all other
committed and planned projects and activities or pollution sources in the area
along the identified water system(s) and sensitive receivers shall be
identified and assessed;
(ix)
Assessment and evaluation of any potential
water quality impacts on the identified water system(s), respective catchments
and sensitive receivers due to sewage arising from the construction stage. Any effluent generated will require
appropriate collection, treatment and disposal to within standards and
objectives and criteria established in (iv) above;
(x)
Assessment
and evaluation of any potential stormwater
and construction runoff impacts on the water system(s), respective catchments
and sensitive receivers during construction stages as to reduce the water and
sediment quality impacts to within standards, objectives and criteria
established in (iv) above. Best
management practices shall be recommended to reduce any potential impacts
arising from stormwater runoff during both construction and operation phases;
Waste Water and Non-point Sources Pollution
(xi)
Proposals for
effective and practicable infrastructure upgrading or provision, water
pollution prevention and mitigation measures to be implemented during the
construction and operation stages to reduce the water quality impacts to within
acceptable levels of standards.
Requirements to be incorporated in the project contract document shall
also be proposed;
(xii)
Evaluation and quantification
of residual impacts on the water system(s) and the sensitive receivers with
regard to the appropriate water quality criteria, standards or guidelines.
3.4.2.5 The EIA report shall propose measures to
avoid the improved drainage channels to be used to collect and divert the grey
water from the local villages and discharge it to some previously unpolluted
streams in the nearby area.
3.4.3 Construction
Air Quality Impact
3.4.3.1 The
Applicant shall follow the criteria and guidelines for evaluating and assessing
construction air quality impact as stated in section 1 of Annex 4 and Annex 12
of the TM respectively.
3.4.3.2 The
assessment area for the construction air quality impact assessment shall generally
be defined by a distance of 500 m from the boundary of the proposed project
works sites, yet it may be extended depending on the circumstances and the
scale of the proposed project.
3.4.1.3 The Applicant shall assess the air
pollutant concentrations with reference to the Guidelines for Local-Scale Air Quality
Assessment Using Models issued by the Environmental Protection Department (EPD)
of the HKSAR dated March, 2000.
3.4.1.4 The air quality assessment shall
include the following:
Background and
analysis of activities
(xviii)
Provide background information relating
to air quality issues relevant to the proposed project, e.g. description of the
types of activities of the proposed project.
(xix)
Give an account, where appropriate, of the
consideration/measures that had been taken into consideration in the planning
of the proposed project to abate the air pollution impact. That is, the Applicant shall consider
alternative construction methods/phasing programmes to minimize the construction
air and dust impacts.
(xx)
Present the background air quality levels
in the assessment area for the purpose of evaluating the cumulative
construction air quality impacts.
Identification
of Air Sensitive Receivers (ASRs) and examination of emission/dispersion
characteristics
(xxi)
Identify and describe representative
existing and planned/committed ASRs that would likely be affected by the
proposed project, including those earmarked on the relevant Outline Zoning
Plans, Development Permission Area Plans, Outline Development Plans and Layout
Plans. The Applicant shall select
the assessment points of the identified ASRs such that they represent the worst
impact point on these ASRs. A map
showing the location and a description including the name of the buildings,
their uses and height of the selected assessment points shall be given. The separation distances of these ASRs
from the nearest emission sources should also be given.
(v) Provide an exhaustive list of
air pollutant emission sources, including any nearby emission sources, which
are likely to have impact on the proposed project. Examples of construction stage emission sources include
stock piling, concrete batching and vehicular movements on unpaved haul roads
on site and so forth. Confirmation
of the validity of the assumptions and the magnitude of the activities (e.g.
volume of construction materials handled) shall be obtained from the relevant
government/authorities and documented.
Impact Assessment
(vi) The Applicant shall follow the
requirements of the Air Pollution Control (Construction Dust) Regulation in
dust control to ensure construction dust impacts are controlled to within the
relevant standards as stipulated in section 1 of Annex 4 of the TM. A monitoring and audit program during
the construction stage shall be implemented to verify the effectiveness of the
control measures and to ensure that the construction dust levels are brought
under control.
(vii) If the Applicant anticipates a significant
construction dust impact that will likely cause exceedance of the recommended
limits in the TM at the ASRs despite incorporation of the dust control measures
stated in (vi) above, a quantitative assessment shall be carried out to
evaluate the construction dust impact at the identified ASRs. The Applicant shall follow the
methodology below when carrying out the assessment.
Quantitative
Assessment Methodology
(viii) The Applicant shall apply the general
principles enunciated in the modelling guidelines while making allowance for
the specific characteristic of the proposed project. Specific methodology must be documented to such level of
detail (preferably with tables and diagrams) to allow the readers of the EIA
report to grasp how the model is set up to simulate the situation at hand
without referring to the model input files. Details of the calculation of the emission rates of air
pollutants and a map showing the emission sources for input to the modelling
shall be presented in the EIA report.
The Applicant must ensure consistency between the text description and
the model files at every stage of submission. In case of doubt, prior agreement of the general methodology
between the Applicant and the Director is advised.
(ix) The Applicant shall identify the
key/representative air pollutant parameters related to construction activities
(types of pollutants and the averaging time concentration) to be evaluated and
provide explanation for choosing these parameters for the assessment of the
impact of the proposed project.
(x) The Applicant shall calculate
the cumulative air quality impact at the identified ASRs and compare these
results against the criteria set out in section 1 of Annex 4 in the TM. The predicted air quality impacts (both
unmitigated and mitigated) shall be presented in the form of summary tables and
pollution contours, for comparison with relevant air quality standards and for
examination of the land use implications of these impacts. Plans of suitable scale should be used
for presentation of pollution contours for determining buffer distances
required.
Mitigating
Measures for Non-compliance
(xi) The Applicant shall propose
remedies and mitigating measures, where the predicted air quality impact
exceeds the criteria set in section 1 of Annex 4 in the TM. These measures and any constraints on
future land use planning shall be agreed with the relevant government
departments/authorities and documented.
The Applicant shall demonstrate quantitatively that the resultant
impacts after incorporation of proposed mitigating measures will comply with
the criteria stipulated in section 1 of Annex 4 in the TM.
Submission
of Model Files
(xii) All input and output file(s) of the
model run(s) shall be submitted to the Director in electronic format.
3.4.4 Construction
Noise Impact
3.4.4.1 The Applicant shall follow the
criteria and guidelines for evaluating and assessing construction noise impact
as stated in Annexes 5 and 13 of the TM respectively.
3.4.4.2 The construction noise impact
assessment shall include the following:
(i) Determination of
Assessment Area
The
assessment area for the construction noise impact assessment shall include all
areas within 300 m from the project boundary. Subject to the agreement of the Director, the assessment
area could be reduced accordingly if the first layer of Noise Sensitive
Receivers (NSRs), closer than 300 m from the project boundary, provides
acoustic shielding to those NSRs further from the site.
(ii) Provision of Background
Information and Existing Noise Levels
The
Applicant shall provide all background information relevant to the proposed
project, including relevant previous or current studies. Unless necessary for planning
standards, it will not be necessary to investigate the existing noise levels.
(iii) Identification of NSRs
(a) The Applicant shall refer to
Annex 13 of the TM when identifying the NSRs. The NSRs shall include all existing NSRs and all planned/committed
noise sensitive developments and uses earmarked on the relevant outline zoning
plans, outline development plans, layout plans and other published plans,
including any land use and development applications approved by Town Planning
Board. For planned noise sensitive
land uses without committed layouts, the Applicant shall work out indicative
site layouts based on the relevant planning parameters.
(b) The Applicant shall select
assessment points to represent all identified NSRs for carrying out
quantitative noise assessment described below. The assessment points shall be agreed with the Director
prior to the quantitative noise assessment. A map showing the location and description such as name of
building, use, and floors of each and every selected assessment point shall be
given.
(iv) Provision of an Emission
Inventory of the Noise Sources
The
Applicant shall provide an inventory of noise sources including construction
equipment for construction noise assessment. Confirmation of the validity of the inventory shall be
obtained from the relevant government departments/authorities.
(v) Construction Noise
Assessment
(a) The Applicant shall carry out
assessment of noise impact from construction (excluding percussive piling)
during day time, i.e. 7 a.m. to 7 p.m., on weekdays other than general holidays
in accordance with the methodology stipulated in sections 5.3 and 5.4 of Annex
13 of the TM. The criteria in
Table 1B of Annex 5 of the TM shall be adopted in the assessment.
(b) To minimize the construction
noise impact, alternative construction methods (e.g. to replace percussive
piling) shall be explored and recommended as far as practicable. If the unmitigated construction noise levels
are found to exceed the relevant criteria, the Applicant shall propose
practicable direct mitigation measures (including movable barriers, enclosures,
quieter alternative methods, re-scheduling and restricting hours of operation
of noisy task) to minimize the impact.
If the mitigated noise levels still exceed the relevant criteria, the
duration of the noise exceedance shall be given.
(c) The applicant shall confirm
whether construction work during restricted hours is required. If affirmative, the applicant shall
evaluate whether construction works in restricted hours as defined under the
Noise Control Ordinance (NCO) are feasible or not in the context of programming
construction works. Reference
shall be made to the relevant technical memoranda issued under the NCO. Regardless of the results of the
construction noise impact assessment for restricted hours, the Noise Control
Authority will process the Construction Noise Permit application, if necessary,
based on the NCO, the relevant technical memoranda issued under the NCO and the
contemporary conditions/situations.
This aspect should be explicitly stated in the noise chapter and the
conclusions and recommendations chapter in the EIA report.
3.4.5 Waste Management Implications
3.4.5.1 The Applicant shall follow the criteria
and guidelines for evaluating and assessing waste management implications as
stated in Annexes 7 and 15 of the TM respectively.
3.4.5.2 The assessment of waste management
implications shall cover the following:
(i) Analysis
of Activities and Waste Generation
Identification
of the quantity, quality and timing of the waste arising as a result of the
construction and operation activities, based on the sequence and duration of
these activities;
(ii) Proposal for
Waste Management
(a) Prior to
considering the disposal options for various types of wastes, opportunities for
reducing waste generation and on-site or off-site re-use shall be fully
evaluated. Measures, which can be
taken in the planning and design stages e.g. by modifying the design approach
and in the construction stage for maximizing waste reduction shall be
separately considered;
(b) After considering
all the opportunities for reducing waste generation and maximizing re-use, the
types and quantities of the wastes required to be disposed of as a consequence
shall be estimated and the disposal options for each type of waste shall be
described in detail. Pre-treatment
processes for slurry before disposal shall be addressed in details. The disposal method recommended for
each type of waste shall take into account the result of the assessment in (c)
below; and
(c) The impact caused
by handling (including labelling, packaging & storage), collection, and
disposal of wastes shall be addressed in detail and appropriate mitigation
measures be proposed. This
assessment shall cover the following areas:
-
potential hazard;
-
air and odour emissions;
-
noise;
-
wastewater discharge; and
-
public transport.
3.4.6 Illustration Materials
The Applicant
shall submit design proposal in the form of cross sectional plans, perspective
drawings and photomontages, where appropriate, that covers the form and
external finishes of the proposed treatment works, and provision of landscape
design proposals.
3.4.7 Impact on
Cultural Heritage
3.4.7.1
The Applicant shall follow the criteria
and guidelines for evaluating and assessing the cultural heritage impacts as stated
in section 2 of Annex 10 and sections 1 and 2 of Annex 19 of the TM
respectively.
3.4.7.2
The cultural heritage impact assessment
shall include the following:
(i)
The Applicant shall identify all cultural
heritage sites that might be adversely affected by the proposed project. The inventory shall include known and
unknown archaeological sites, pre-1950 buildings and structures, post-1950
buildings and structure of high architectural and historical significance, and
historic landscape features (e.g. sites of historical events, sites providing a
significant historical record, a setting for buildings/monuments of
architectural/archaeological importance, historic field patterns, tracks, fish
ponds and cultural elements (i.e. fung shui woodlands and clan graves).
(ii)
The Applicant shall assess the extent to
which those cultural heritage sites might be directly and indirectly affected
and recommend possible alternatives (such as modification of layout and design
of the proposed project) and practicable monitoring and mitigation measures to
be agreed with the Director to avoid or keep the adverse impacts on the
cultural heritage sites to the minimum.
Besides, a checklist including all the affected cultural heritage sites,
impacts identified, recommended mitigation measures as well as the
implementation agent and period shall also be included in the EIA report.
(iii)
In case where the sources of information
prove to be inadequate or where the proposed project area has not been
adequately studied before, field surveys and site investigations shall be
conducted to assemble the necessary data.
Regarding the assessment study on cultural heritage, it shall be
conducted by qualified persons with proven records to archaeological and
historical building research works in Hong Kong. The archaeological survey shall be carried out by a
qualified archaeologist who shall obtain a License from the Antiquity Authority
before undertaking the field evaluation under the Antiquities and Monuments
Ordinance (Cap.53).
(iv)
The information of all the identified
archaeological sites, historic buildings and structures including their
ownership, historical background, 1:1000 scale location plans, photographs and
the like together with the nearby work areas shall be provided. Special attention shall be paid to the
Chung Hau Archaeological Site, historic buildings and structures in the
vicinity of the proposed project including the following historic building: the
two historical watch towers at Luk Tei Tong and Chung Hau
4. ENVIRONMENTAL
MONITORING & AUDIT (EM&A) REQUIREMENTS
4.1 The Applicant shall identify
in the EIA study whether there is any need for EM&A activities during the
construction and operation phases of the proposed project and, if affirmative,
to define the scope of the EM&A requirements for the proposed project in
the EIA study.
4.2 Subject to the confirmation
of the EIA study findings, the Applicant shall comply with the requirements as
stipulated in Annex 21 of the TM.
The Applicant shall also propose real-time reporting of monitoring data
for the proposed project through a dedicated internet website.
4.3 The Applicant
shall prepare a project implementation schedule, in the form of a checklist as
shown in Appendix 1 attached to this study brief, containing all the EIA study
recommendations and mitigation measures with reference to the implementation
programme.
5. SUMMARY OF
ENVIRONMENTAL OUTCOMES
5.1 The EIA report shall
contain a summary of the key environmental outcomes arising from the EIA study,
including the population and environmentally sensitive areas protected,
environmentally friendly designs recommended, key environmental problems
avoided, and environmental benefits of environmental protection measures
recommended.
6. DURATION OF
VALIDITY
6.1 The EIA study
brief is valid for 36 months after the date of issue. If the EIA study does not commence within this period, the
Applicant shall apply to the Director for a fresh EIA study brief before
commencement of the EIA study.
7. REPORT
REQUIREMENTS
7.1 In preparing the
EIA report, the Applicant shall refer to Annex 11 of the TM for the contents of
an EIA report. The Applicant shall
also refer to Annex 20 of the TM which stipulates the guidelines for the review
of an EIA report.
7.2 The Applicant
shall supply the Director with the following number of copies of the EIA report
and the executive summary:
(i) 50 copies
of the EIA report in English and 80 copies of the executive summary (each
bilingual in both English and Chinese) as required under section 6(2) of the
EIAO to be supplied at the time of application for approval of the EIA report.
(ii) when necessary,
any addendum to the EIA report and the executive summary submitted in (i) above as required under section 7(1) of the
EIAO, to be supplied upon advice by the Director for public inspection.
(iii) 20 copies of the EIA
report in English and 50 copies of the executive summary (each bilingual in
both English and Chinese) with or without Addendum as required under section
7(5) of the EIAO, to be supplied upon advice by the Director for consultation
with the Advisory Council on the Environment.
7.3 The Applicant shall,
upon request, make additional copies of the above documents available to the
public, subject to payment by the interested parties of full costs of printing.
7.4 In addition, to
facilitate the public inspection of the EIA report via the EIAO Internet
Website, the Applicant shall provide electronic copies of both the EIA report
and the executive summary prepared in Hyper Text Markup Language (HTML)
(version 4.0 or later) and in Portable Document Format (PDF)(version 4.0 or
later), unless otherwise agreed by the Director. For the HTML version, a content page capable of providing
hyperlinks to each section and sub-section of the EIA report and the executive
summary shall be included in the beginning of the document. Hyperlinks to all figures, drawings and
tables in the EIA report and executive summary shall be provided in the main
text from where the respective references are made. All graphics in the report shall be in interlaced GIF format
unless otherwise agreed by the Director.
7.5 The electronic
copies of the EIA report and the executive summary shall be submitted to the
Director at the time of application for approval of the EIA report.
7.6
When the EIA report and the executive
summary are made available for public inspection under section 7(1) of the
EIAO, the content of the electronic copies of the EIA report and the executive
summary must be the same as the hard copies and the Director shall be provided
with the most up to date electronic copies.
7.7 To promote
environmentally friendly and efficient dissemination of information, both hard
copies and electronic copies of future EM&A reports recommended by the EIA
study shall be required and their format shall be agreed by the Director.
8. OTHER
PROCEDURAL REQUIREMENTS
8.1 If there is any change
in the name of the Applicant for this EIA study brief, the Applicant mentioned
in this study brief must notify the Director immediately.
8.2 If there is any
key change in the scope of the proposed project mentioned in section 1.2 of
this EIA study brief and in Project Profile (No. PP-165/2002), the Applicant
must seek confirmation from the Director in writing on whether or not the scope
of issues covered by this EIA study brief can still cover the key changes, and
the additional issues, if any, that the EIA study must also address. If the changes to the proposed project
fundamentally alter the key scope of the EIA study brief, the Applicant shall
apply to the Director for a fresh EIA study brief.
-- End of Study Brief --
EIA Study Brief No.
ESB-101/2002
April 2002
Environmental
Assessment and Noise Division
Environmental
Protection Department
Appendix
1
Implementation
Schedule
Project
Title: Drainage Improvements in Southern Lantau
EIA
Ref. |
EM&A
Ref. |
Recommended Mitigation Measures |
Objectives of the Recommended Measure & Main Concern
to Address |
Who to implement the measure? |
Location of the measure |
When to implement the measure? |
What requirements or standards for the measure to achieve? |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Figure
1 | Figure 2 | Figure 3