EIA Study Brief No.
ESB-102/2002
May 2002
Environmental Impact Assessment
Ordinance (Cap. 499), Section 5 (7)
Environmental Impact
Assessment Study Brief No. ESB-102/2002
Project
Title : Reprovisioning of
Diamond Hill Crematorium
Name of Applicant:
Architectural Services Department
(hereinafter known as
the "Applicant")
1. BACKGROUND
1.1 An
application (No. ESB-102/2002) for an Environmental Impact Assessment (EIA)
study brief under section 5(1) of the Environmental Impact Assessment Ordinance
(EIAO) was submitted by the captioned Applicant on 25th March 2002 with
a Project Profile (No. PP-166/2002).
1.2 The Applicant proposes to construct a new crematorium of 6 cremators with total capacity of 1,260 kg per hour to replace the existing 6 cremators (hereinafter referred as the Project). The location of the Project is shown in Figure No. 1 in the Project Profile. The Project also includes the provision of a full range of ancillary facilities required for the operation of a crematorium, including:
(a) air pollution control systems to control the emission
of the cremators
(b) four service halls
(c) four joss paper burners
(d) emergency generator room
(e) underground fuel tanks
(f) mortuary
(g) office accommodation
(h) store rooms and dangerous goods store
(i) public toilets
(j) parking spaces for coaches and private cars
(k) refuse storage chambers
(l) garden of remembrance
1.3
Pursuant to section 5(7)(a) of the EIAO,
the Director of Environmental Protection (the Director) issues this EIA study
brief to the Applicant to carry out an EIA study for the Project.
1.4 The purpose of this EIA study is to provide information on the nature and extent of environmental impacts arising from the construction and operation of the proposed project and related activities taking place concurrently. This information will contribute to decisions by the Director on:
(i) the overall
acceptability of any adverse environmental consequences that are likely to
arise as a result of the proposed project;
(ii) the conditions and
requirements for the detailed design, construction and operation of the proposed project to mitigate
against adverse environmental consequences wherever practicable; and
(iii) acceptability of residual
impacts after proposed mitigation measures are implemented.
2. OBJECTIVES
OF THE EIA STUDY
2.1 The
objectives of the EIA study are as follows:
(i) to describe the
proposed project together with the requirements for carrying out the proposed
project;
(ii)
to identify and describe elements of
community and environment likely to be affected by the proposed project and/or
likely to cause adverse impacts to the proposed project, including natural and
man-made environment and the associated environmental constraints;
(iii)
to describe the considerations given in
selecting the proposed site, layout, design (including technology to be adopted
for the new cremators), and construction method; to provide reasons for
selecting the preferred option and to describe the part environmental factors
played in the selection process;
(iv)
to identify and quantify emission sources
and determine the significance of impacts on sensitive receivers and
potentially affected uses;
(v)
to identify and quantify waste management
requirements and propose measures to mitigate or prevent impacts, and measures
to be adopted to avoid introducing land contamination at the new cremators’
site;
(vi)
to identify and quantify any potential
visual impacts and to propose measures to mitigate impacts;
(vii)
to identify the negative impacts and
propose the provision mitigation measures so as to minimize pollution,
environmental disturbance and nuisance during construction and operation of the
project;
(viii)
to identify, predict and evaluate the
residual (i.e. after practicable mitigation) environmental impacts and the
cumulative effects expected to arise during the construction and operation
phases of the proposed project in relation to the sensitive receivers and
potential affected uses;
(ix)
to identify, assess and specify methods,
measures and standards, to be included in the detailed design, construction and
operation of the proposed project which are necessary to mitigate these
environmental impacts and cumulative effects and reduce them to acceptable
levels;
(x)
to identify constraints associated with
the mitigation measures recommended in the EIA study; and
(xi)
to design and specify an environmental
monitoring program, and if required, other environmental monitoring and audit
requirements, to ensure the implementation and the effectiveness of the
recommended environmental protection and pollution control measures.
3. DETAILED
REQUIREMENTS OF THE EIA STUDY
3.1 The purpose
of this study brief is to scope the key issues of the EIA study. The Applicant has to demonstrate in the
EIA report that the criteria in the relevant sections of the Technical
Memorandum on the Environmental Impact Assessment Process of the Environmental
Impact Assessment Ordinance (hereinafter referred to as the TM) are fully
complied with.
3.2 The Scope
3.2.1 The
scope of this EIA study shall cover the project proposed in the Project Profile
and shall include the works and facilities mentioned in section 1.2 above. Figure 1 of this Study Brief shows the
location of the new and existing crematoriums. The EIA study shall address the likely key issues described
below, together with any key issues identified during the course of the study
and the
cumulative environmental impacts of the Project, through interaction or in
combination with other existing, committed and planned developments in the
vicinity of the Project:
(i) the
consideration given in selecting the proposed site, layout, design (including
technology to be adopted for the new cremators), and construction method for
the Project;
(ii) the
air quality impacts arising from the construction and operation of the Project;
(iii) the measures to be adopted to avoid introducing land
contamination at the new cremators’ site, as well as the waste management for
the construction and operation of the Project;
(iv) the
visual impacts from the construction and operation of the Project;
(v)
the safety requirements related to
storage of fuel;
(vi)
the construction and
operational noise impacts of the Project;
and,
(vii) handling of any
effluent discharge from the air pollution control/scrubbing systems for the new
crematorium during operation stage;.
3.2.2 The
Applicant shall also assess all the environmental impacts during the
transitional stage of the Project before the existing cremators cease
operation, scenarios to include test runs of the new cremators concurrently
with the existing cremators remain operative in full service.
3.3.3 Regarding
the potential cumulative impacts, other projects under planning to be
considered to include, but not necessarily limited to, the construction stage
impacts due to the proposed Diamond Hill No. 2 Fresh Water Service Reservoir
and any potential developments on the cleared land along Po Kong Village Road
near the Project’s site.
3.3 Decommissioning
of the Existing Diamond Hill Crematorium
3.3.1 Section 4.2 of the Project Profile stated that the existing Diamond
Hill Crematorium will be decommissioned when the proposed new crematorium is in
operation. However, section 1.2 of
the Project Profile on the project scope only listed out those work items
related to the new cremators but did not mention the decommissioning of the
existing cremators. The Applicant shall state clearly whether or not the
decommissioning of the existing cremators is covered under the EIA Study.
3.3.2 If the Applicant confirms that environmental impacts of
the decommissioning and demolition of the existing cremators is covered in the
EIA Study, the Applicant shall also address in the EIA the issues stated in
Appendix A to this Study Brief related to the decommissioning element.
3.3.3 If
the Applicant confirms that
environmental impacts of the decommissioning and demolition of the existing
cremators is not covered in the EIA Study, the Applicant shall provide information on the future plan on the existing
cremators, including any plan on the assessment of the environmental impacts of
the decommissioning project.
3.4 Description
of Siting, Layout, Design and Construction Methods Considered
3.4.1 The existing operation of the
Diamond Hill Crematorium which is located in the urban area surrounded by many
residential developments is of concern to the public. There have been environmental complaints against the smoke
and odour emissions from the cremators.
In addition, several schools located close to the Crematorium are
currently under construction.
3.4.2 Given the general public’s
concerns on the existing location of the Crematorium, while the Project Profile
stated that the Project would provide cremators of advance technology, the
Applicant shall state the justifications for continually using the proposed site
for the reprovisioning proposal.
3.4.3 The Applicant shall also describe
the consideration given to other possible layout(s) within the proposed site,
available technology options for the new cremators, and alternative
construction method to minimise excessive nuisances during the construction
stage of the Project. In
particular, such considerations should cover the potential environmental
impacts to nearby existing and planned sensitive receivers when different
layout, technology or construction method are used. The Applicant shall state the justifications for the
selecting the proposed layout, technology and construction method.
Technical Requirements
3.5 The
Applicant shall conduct the EIA study to address all environmental aspects of
the works and activities as described in the scope as set out above.
3.6 The EIA
study shall include the following technical requirements on specific impacts.
3.6.1 Air Quality Impact
3.6.1.1 The Applicant shall follow the criteria and guidelines
for evaluating and assessing air quality impact as stated in section 1 of Annex
4 and Annex 12 of the TM respectively.
3.6.1.2 The
assessment area for air quality impact shall be defined by a distance of 500 m
from the boundary of the project site, yet it may be extended depending on the
circumstances and the scale of the project.
3.6.1.3 The
Applicant shall assess the air pollutant concentrations making reference to the
relevant sections of the air modelling guideline in Appendices B-1 to B-4 to
this EIA Study Brief, or other methodology as agreed by the Director. The Applicant shall make reference to
the Guidelines with respect to construction dust impacts, cumulative
construction dust impact and stack emissions evaluation. In consideration of construction dust
impact, the Applicant shall make reference to the Fugitive Dust Model (FDM) in
Appendixes B-1 and B-3; in consideration of cumulative construction dust
impact, the Applicant shall make reference to the FDM in Appendixes B-1, B-2
and B-3; in consideration of stack emissions evaluation, the Applicant shall
make reference to the Industrial Source Complex Dispersion Model (ISCST3) in
Appendixes B-1 and B-4.
3.6.1.4 The
air quality assessment shall cover the construction and operation of the
Project, and include the following:
Background
and analysis of activities
(i) Provide
background information relating to air quality issues relevant to the project,
e.g. description of the types of activities during construction stage of the project
such as site clearance, excavation, material handling and wind erosion that
will likely give rise to dust emissions and those activities during operation
stage of the project such as operation of the cremators that will give off
gaseous emissions.
(ii) Give
an account, where appropriate, of the consideration/measures that had been
taken into consideration in the planning of the project to abate the air
pollution impact. That is, the Applicant should state the considerations given
to the use of various potential construction methods/phasing programmes and
cremator technologies and modes of operation to minimise the constructional and
operational air quality impact respectively. For example, consideration should be given to the use of
gaseous fuel to reduce emissions during cremation.
(iii)
Present the background air quality levels
in the assessment area for the purpose of evaluating the cumulative
constructional and operational air quality impacts. Also compare and present the anticipated improvements over
the existing level in terms of air emission data.
Identification
of ASRs and examination of emission/dispersion characteristics
(iv)
Identify and describe representative
existing and planned/committed air sensitive receivers (ASRs) that would likely
be affected by the project, including those earmarked on the relevant Outline
Zoning Plans, Development Permission Area Plans, Outline Development Plans and
Layout Plans. The Applicant shall select the assessment points of the
identified ASRs such that they represent the worst impact point of these ASRs.
A map showing the location and a description including the name of the
buildings, their uses and height of the selected assessment points shall be
given. The separation distances of these ASRs from the nearest emission sources
should also be given. Please also
note that the proposed Diamond Hill No. 2 Fresh Water Service Reservoir has
been planned for construction in the near future and would be about 150 meters
from the proposed new crematorium.
(v)
Provide an exhaustive list of air
pollutant emission sources, including any nearby emission sources which are
likely to have impact on the project based on the analysis of the
constructional and operational activities of the project in (i) above. Examples of constructional stage
emission sources include stock piling, concrete batching, etc. Examples of
operational stage emission sources include cremators, any nearby industrial
source, etc. Confirmation of the validity of the assumptions and the magnitude
of the activities (e.g. volume of construction materials handled etc.) shall be
obtained from the relevant government department/authorities and documented.
Constructional
air quality impact
(vi) The
Applicant shall follow the requirements of the Air Pollution Control (Construction
Dust) Regulation in dust control to ensure construction dust impacts are
controlled within the relevant standards as stipulated in section 1 of Annex 4
of the TM. An audit and monitoring program during constructional stage shall be
initiated to verify the effectiveness of the control measures and to ensure
that the construction dust levels be brought under control.
(vii)
If the Applicant anticipates a
significant construction dust impact that will likely cause exceedance of the
recommended limits in the TM at the ASRs despite incorporation of the dust
control measures stated in (vi) above, a quantitative assessment should be
carried out to evaluate the construction dust impact at the identified ASRs
based on the emission strength of the emission sources identified in (v) above.
The Applicant shall follow (x) to (xiii) below when carrying out the
quantitative assessment.
Operational
air quality impact
(viii)
In addition to preparing a list of emission
sources required in (v) above, the Applicant shall state the target emission
levels for the cremators, and compare them with the standards specified in the
latest set of Guidance Note on the Best Practicable Means for Crematoria issued
by the Air Management Group of EPD, and other relevant overseas standards. The target emission levels, including
but not limited to that for dioxin, should be agreed with the Director prior to
the carrying out of the quantitative assessment on operational air quality
impact.
(ix)
The Applicant shall calculate the
expected air pollutant concentrations at the identified ASRs. Calculations for
the expected impact shall be based on an assumed reasonably worst case scenario
under normal operating conditions and during the testing stage of the new
cremators. Special attention shall
be placed on the testing stage of the new cremators when there is potential for
both the existing and new cremators being operated and emitting air pollutants
concurrently. The evaluation shall
be based on the strength of the emission sources identified in (v) and (viii)
above. The Applicant shall follow (x) to (xiii) below when carrying out the
quantitative assessment.
Quantitative
Assessment Methodology
(x)
The Applicant shall apply the general
principles, where applicable, enunciated in the modeling guidelines in
Appendices B1 to B-4 while making allowance for the specific characteristic of
the Project. This specific methodology must be documented in such level of
details (preferably with tables and diagrams) to allow the readers of the
assessment report to grasp how the model is set up to simulate the situation at
hand without referring to the model input files. Details of the calculation of
the emission rates of air pollutants and a map showing the emission sources and
the identified ASRs for input to the modeling shall be presented in the report.
The Applicant must ensure consistency between the text description and the
model files at every stage of submission. In case of doubt, prior agreement
between the Applicant and the Director on the specific modelling details should
be sought.
(xi)
The Applicant shall identify the
key/representative air pollutant parameters (types of pollutants and the
averaging time concentration) to be evaluated and provide explanation for
choosing these parameters for the assessment of the impact of the project. Among the identified parameters,
emissions such as toxic air pollutants (including but not limited to dioxins)
and odour (if any) shall be included.
(xii)
The Applicant shall calculate the
cumulative air quality impact at the identified ASRs and compare these results
against the criteria set out in section 1 of Annex 4 in the TM. The predicted
air quality impacts (both unmitigated and mitigated) shall be presented in the
form of summary table and pollution contours, for comparison with relevant air
quality standards and examination of the land use implications of these
impacts. Plans of suitable scale should be used for presentation of pollution
contour for determining buffer distances required. In order to get a full picture of air emissions in
particular dioxins from the proposed Project, an inventory figure (in g
I-TEQ/year) should be estimated and presented.
Mitigating measures for non-compliance
(xiii)
The Applicant shall propose remedies and
mitigating measures where the predicted air quality impact exceeds the criteria
set in section 1 of Annex 4 in the TM. These measures and any constraints on
future land use planning shall be agreed with the relevant government
departments/authorities and documented. The Applicant shall demonstrate
quantitatively that the resultant impacts after incorporation of the proposed
mitigating measures will comply with the criteria stipulated in section 1 of Annex
4 in the TM.
Submission of model files
(xiv)
All input and output file(s) of the model
run(s) shall be submitted to the Director in electronic format.
3.6.2 Land Contamination Impact
& Waste Management
Land Contamination Prevention
3.6.2.1To prevent contamination
problems from arising in future, the Applicant shall:
(i) identify
the possible sources of contamination, including but not limited to dioxin, in
their operations; and
(ii) formulate
appropriate operational practices, waste management strategies and
precautionary measures for prevention of contamination problems.
Waste
Management Implications
3.6.2.2 The Applicant shall follow the criteria and
guidelines for evaluating and assessing waste management implications as stated
in Annexes 7 and 15 of the TM, respectively.
3.6.2.3 The assessment of waste management implications
shall cover the following:
(i)
Analysis of Activities and Waste
Generation
(a) The
Applicant shall identify the quantity, quality and timing of the waste arising
as a result of the construction and operation activities, based on the sequence
and duration of these activities.
(ii)
Proposal for Waste Management
(a) Prior
to considering the disposal options for various types of wastes, opportunities
for reducing waste generation and on-site or off-site re-use shall be fully
evaluated. Measures which can be
taken in the planning and design stages e.g. by modifying the design approach
and in the construction stage for maximising waste reduction shall be
separately considered.
(b) Having
taken into account all the opportunities for reducing waste generation and
maximising reuse, the types and quantities of the wastes required to be
disposed of as a consequence shall be estimated and the disposal options for
each type of waste described in detail.
The disposal method recommended for each type of wastes shall take into
account of the result of the assessment in section (c) below.
(c) The
impact caused by handling (including labeling, packaging & storage),
collection, and disposal of wastes shall be addressed in detail and appropriate
mitigation measures proposed. This
assessment shall cover the following areas:
(i) potential
hazard;
(ii)
air & odour emission;
(iii) noise;
(iv) wastewater
discharge;
(v) public
transport.
3.6.3 Visual Impact
3.6.3.1 The Applicant shall follow the
criteria and guidelines for evaluating and assessing visual impact as stated in
section 1 of Annex 10 and in Annex 18 of the TM, respectively. The assessment shall also cover all
items classified as Designated Projects under Schedule 2 of the EIAO. Both
construction and operational impacts shall be assessed. In particular, the transition stage
where both the existing and new crematoriums co-exist shall be covered.
3.6.3.2 The assessment area for the visual
impact assessment shall be defined by the visual envelope of the project.
3.6.3.3 The Applicant shall review relevant
outline development plans, outline zoning plans, layout plans, other published
land use plans, planning briefs, studies and guidelines on landscape framework,
urban design concept, designated view corridors, open space network and
landscape links that may affect the appreciation of the project. The aim is to gain an insight to the
future outlook of the area affected so as to assess whether the project can fit
into surrounding setting. Any
conflict with published land use plan(s) should be highlighted and appropriate
follow-up action should be recommended.
3.6.3.4 The Applicant shall assess the
visual impacts of the proposed development. In particular, the cumulative visual impacts of the existing
and proposed crematorium shall be assessed and taken into account in the
formulation of mitigation measures and the assessment of residual impacts. As
some nearby sensitive receivers have direct line of sight to the site,
mitigation measures such as proper landscape screening shall be provided. The visual impact assessment shall
include the following:
(i) identification
and plotting of visual envelope of the project within the assessment area;
(ii) identification
of the key groups of sensitive receivers within the visual envelope and their
views at both ground level and elevated vantage points;
(iii) description
of the visual compatibility of the project with the surrounding, and the
planned setting and its obstruction and interference with the key views of the
adjacent areas; and
(iv) the
severity of visual impacts in terms of nature, distance and number of sensitive
receivers. The visual impacts of
the project with and without mitigation measures shall also be included so as
to demonstrate the effectiveness of the proposed mitigation measures.
3.6.3.5 Alternative layout, design and
construction method that would avoid or reduce the identified visual impacts
shall be evaluated for comparison before adopting other mitigation or
compensatory measures to alleviate the impacts. The mitigation measures proposed shall not only be concerned
with damage reduction but should also include consideration of potential
enhancement of existing visual quality.
The Applicant shall recommend mitigation measures to minimise the
adverse effects identified above, including provision of a landscape design.
3.6.3.6 The mitigation measures shall
include provision of screen planting, revegatation of disturbed land,
compensatory planting, provisioning of amenity areas, design of structures,
provision of finishes to structures, colour scheme and texture of material used
and any measures to mitigate the impacts on existing land use. Parties shall be identified for the on
going management and maintenance of the proposed mitigation works to ensure
their effectiveness throughout the operation phase of the project. A practical programme and funding
proposal for the implementation of the recommended measures shall be provided.
3.6.3.7 Annotated illustration materials
such as coloured perspective drawings, plans and section/elevation diagrams,
photographs taken at vantage points, and computer-generated photomontage shall
be adopted to fully illustrate the visual impacts of the project to the
satisfaction of the Director. The
Applicant shall record the technical details in preparing the illustration that
may need to be submitted for verification of accuracy of the illustrations.
3.6.4 Hazard to Life
The
Applicant shall state the fuel for cremation process of the Project. If fuel gas is used, the Applicant
shall confirm that it is provided by direct fuel gas pipeline and there will be
no on-site storage of the fuel gas.
For other non-fuel gas dangerous goods (DG) defined in the Dangerous
Goods Ordinance (Cap. 295) but not covered by the Gas Safety Ordinance (Cap.
51), the Applicant shall confirm that the storage quantity would be similar to
that in the existing crematorium or petrol filling stations and that the
storage will comply with FSD’s safety requirements.
3.6.5 Noise Impact
3.6.5.1 The Applicant shall follow the
criteria and guidelines for evaluating and assessing noise impact as stated in
Annexes 5 and 13 of the TM respectively.
3.6.5.2 The noise impact assessment shall
include the followings:
(i)
Determination
of Assessment Area
The
noise impact assessment shall include all areas within 300m from the project boundary.
Subject to the agreement of the Director, the assessment area could be reduced
accordingly if the first layer of noise sensitive receivers, closer than 300m
from the project boundary, provides acoustic shielding to those receivers
located further away.
(ii)
Provision
of Background Information
The
Applicant shall provide all background information relevant to the project
including relevant previous and current studies. Unless involved in the
planning standards, no existing noise levels are particularly required.
(iii)
Identification
of Noise Sensitive Receivers
(a) The
Applicant shall refer to Annex 13 of the TM when identifying the noise
sensitive receivers (NSRs). The NSRs shall include all existing ones and all
planned or committed noise sensitive developments and uses earmarked on the
relevant Outline Zoning Plans, Outline Development Plans and Layout Plans.
(b) The
Applicant shall select assessment points to represent all identified NSRs for
carrying out quantitative noise assessment described below. The assessment
points shall be agreed with the Director prior to the quantitative noise
assessment. A map showing the location and description including name of
building, use, and floors of each and every selected assessment point shall be
given.
(iv)
Provision
of an Emission Inventory of the Noise Sources
The
Applicant shall provide an inventory of noise sources including construction
equipment for construction and demolition noise assessment and fixed plant
equipment for operational noise assessment. Confirmation of the validity of the
inventory shall be obtained from the relevant government
departments/authorities.
(v)
Construction
/ Demolishing Noise Assessment
(a) The
Applicant shall carry out assessment of noise impact from construction
(excluding percussive piling) of the project during day time, i.e. 7 a.m. to 7
p.m., on weekdays other than general holidays in accordance with the
methodology stipulated in paragraphs 5.3. and 5.4 of Annex 13 of the TM. The
criteria in Table 1B of Annex 5 of the TM shall be adopted in the assessment.
(b)
To minimize
the construction noise impact, alternative construction methods to replace
percussive piling shall be proposed as far as practicable.
(c)
If the
unmitigated construction noise levels are found to exceed the relevant criteria,
the Applicant shall propose practicable direct mitigation measures (including
movable barriers, enclosures, quieter alternative methods, re-scheduling and
restricting hours of operation of noisy task(s) to minimize the impact. If the mitigated noise levels still
exceed the relevant criteria, the duration of the noise exceedance shall be
given.
(d)
In case the
Applicant would like to evaluate whether construction works in restricted hours
as defined under the Noise Control Ordinance (NCO) are feasible or not in the
context of programming construction works, reference should be made to the
relevant technical memoranda issued under the NCO. Regardless of the results of construction noise impact
assessment for restricted hours, the Noise Control Authority will consider a
well-justified Construction Noise Permit (CNP) application, once filed, based
on the NCO, the relevant technical memoranda issued under the NCO, and the
contemporary condition/situations of adjoining land uses and any previous
complaints against construction activities at the site before making his
decision in granting a CNP. This
aspect should be explicitly stated in the noise chapter and the conclusions and
recommendations chapter in the EIA report.
(vi)
Operational
Noise
(a) The
Applicant shall analyze the scope of the proposed system to identify noise
sources for the purpose of noise impact assessment.
(b)
The
Applicant shall calculate the expected noise using standard acoustic
principles. Calculations for the
expected noise shall be based on assumed plant inventories and utilization
schedule for the worst case scenario.
The Applicant shall calculate the noise levels taking into account of
correction of tonality, impulsiveness and intermittency in accordance with the
Technical Memorandum for the Assessment of Noise from Places other than
Domestic Premises, Public Places or Construction Sites.
(c)
The
Applicant shall present the existing and future noise levels in Leq (30 mins)
at the NSRs at various representative floor levels (in mPD) on tables and plans
of suitable scales. Quantitative assessment at the NSRs for proposed fixed
noise source(s) shall be carried out and compared against the criteria set out
in Table 1A of Annex 5 of the TM.
(d)
Proposals
for Noise Mitigation Measures
The Applicant shall propose direct
technical remedies in all situations where the predicted noise level exceeds
the criteria set out in Table 1A of Annex 5 of the TM to protect the affected
NSRs. Specific reasons for not
adopting certain direct technical remedies in the design to reduce the noise to
a level meeting the criteria in the TM or to maximize the protection for the
NSRs should be clearly quantified and laid down. The total number of dwellings
and other noise sensitive element that will be benefited by the provision of
direct technical remedies should be provided.
The total number of dwellings and other
noise sensitive elements that will still be exposed to noise above the criteria
with the implementation of all recommended direct technical remedies shall be
quantified.
In case where a number of the NSRs cannot
all be protected by the recommended direct technical remedies, the Applicant
shall consider alternatives to reduce the impacts.
(vii)
Assessment
of Side Effects and Constraints
The
Applicant shall identify, assess and propose means to minimize any side effects
and to resolve any potential constraints arising from the inclusion of any
recommended direct technical remedies.
3.6.6 Water Quality
The
Applicant shall provide a general description of any air pollution control
system and any scrubbing system for the new cremators, and confirm that there
will be no effluent discharge from the new cremators or any associated air
pollution control/scrubbing system, nor increase in sewage load due to the
reprovisioning proposal.
Otherwise, the Applicant shall demonstrate that there would be no
adverse impact due to the effluent discharges, including an assessment on the
discharges on the sewerage system downstream of the Project area and propose
mitigation measures, if required.
3.6.7 Summary of Environmental
Outcomes
3.6.7.1 The EIA report shall contain a summary of the
key environmental outcomes arising from the EIA study, including the population
and environmentally sensitive areas protected, environmentally friendly designs
recommended, key environmental problems avoided, compensation areas included
and the environmental benefits of environmental protection measures
recommended.
3.6.7.2 The potential net environmental benefits, in
particular from air emission point of view, due to the replacement of the existing crematorium by the
new crematorium shall be stated.
3.6.8 Environmental
Monitoring and Audit (EM&A) Requirements
3.6.8.1 The Applicant shall present in the
EIA study a detailed environmental monitoring program including the frequency
of measurements of dioxins and other pollutants for air emissions and
ashes. In addition, the Applicant
shall also identify in the EIA study whether there is any need for other
EM&A requirements during the construction and operation phases of the
proposed developments. The
scope of the the environmental monitoring program and, if identified, other
EM&A requirements for the Project shall be clearly defined in the EIA study.
3.6.8.2 The Applicant shall comply with the requirements as stipulated in
Annex 21 of the TM.
3.6.8.3 The
Applicant shall prepare a project implementation schedule (in the form of a
checklist as shown in Appendix C to this EIA study brief) containing all the
EIA study recommendations and mitigation measures with reference to the
implementation programme.
4. DURATION
OF VALIDITY
This EIA study brief is valid
for 36 months from the date of issue.
If the EIA study does not commence within this period, the Applicant
shall apply to the Director for another EIA study brief afresh before
commencement of the EIA study.
5. REPORT
REQUIREMENTS
5.1 In preparing the EIA report, the
Applicant shall refer to Annex 11 of the TM for the contents of an EIA report.
The Applicant shall also refer to Annex 20 of the TM which stipulates the
guidelines for the review of an EIA report.
5.2 The
Applicant shall supply the Director with the following number of copies of the
EIA report and the Executive Summary :
(i)
50 copies of the EIA report in English
and 80 copies of the executive summary (each bilingual in both English and
Chinese) as required under section 6(2) of the EIAO to be supplied at the time
of application for approval of the EIA report.
(ii) when
necessary, addendum to the EIA report and the executive summary submitted in
5.2 (i) above as required under
section 7(1) of the EIAO, to be supplied upon advice by the Director for public
inspection.
(iii) 20 copies
of the EIA report in English and 50 copies of the executive summary (each
bilingual in both English and Chinese) with or without Addendum as required
under section 7(5) of the EIAO, to be supplied upon advice by the Director for
consultation with the Advisory Council on the Environment.
5.3 The
Applicant shall, upon request, make additional copies of the above documents
available to the public, subject to payment by the interested parties of full
costs of printing.
5.4 In
addition, to facilitate the public inspection of the EIA Report via the EIAO
Internet Website, the applicant shall provide electronic copies of both the EIA
Report and the Executive Summary Report prepared in HyperText Markup Language
(HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0
or later), unless otherwise agreed by the Director. For the HTML version, a content page capable of providing
hyperlink to each section and sub-section of the EIA Report and the Executive Summary
Report shall be included in the beginning of the document. Hyperlinks to all
figures, drawings and tables in the EIA Report and Executive Summary shall be
provided in the main text from where the respective references are made. All graphics in the report shall be in
interlaced GIF format unless otherwise agreed by the Director.
5.5 The
electronic copies of the EIA report and the Executive Summary shall be
submitted to the Director at the time of application for approval of the EIA
Report.
5.6 When the EIA
Report and the Executive Summary are made available for public inspection under
section 7(1) of the EIA Ordinance, the content of the electronic copies of the
EIA Report and the Executive Summary must be the same as the hard copies and
the Director shall be provided with the most updated electronic copies.
5.7 To promote environmentally
friendly and efficient dissemination of information, both hardcopies and
electronic copies of future EM&A reports recommended by the EIA study shall
be required and their format shall be agreed by the Director.
6. OTHER
PROCEDURAL REQUIREMENTS
6.1 During the
course of the EIA study, if there is any change in the name of Applicant for
this EIA study brief, the Applicant in this study brief must notify the
Director immediately.
6.2 If
there is any key change in the scope of the Project mentioned in Section 1.2 of
this EIA study brief and in Project Profile (No. PP-166/2002), the Applicant
must seek confirmation from the Director in writing on whether or not the scope
of issues covered by this EIA study brief can still cover the key changes, and
the additional issues, if any, that the EIA study must also address. If the changes to the Project
fundamentally alter the key scope of the EIA study brief, the Applicant shall
apply to the Director for a fresh EIA study brief.
---
END OF EIA STUDY BRIEF ---
May
2002
Environmental
Assessment and Noise Division
Environmental
Protection Department
Site Boundary of the Project on New Crematorium Existing
Diamond Hill Crematorium Legend: Proposed
New Crematorium Environmental Impact Assessment Study Brief
(ESB-102/2002) Reprovisioning
of Diamond Hill Crematorium (Based
on Figure no. 1 in Project Profile, ref. no. PP-166/2002, for the Project) Location Plan Figure No. 1
APPENDIX
A
Key Issues of the EIA Study related to
the Decommissioning of the Existing Diamond Hill
Crematorium
If the Applicant
confirms that this EIA study also covers the decommissioning and demolition of
the existing Diamond Hill Crematorium, the Applicant shall include in the EIA
the following key issues and EIA technical requirements with respect to the
decommissioning and demolition of the existing crematorium:
A.1 General
The
Applicant shall address the technical requirements specified in the body of the
Study Brief with respect to
alternative construction method, nuisance and disturbance during the decommissioning
stage including construction noise, construction dust, waste management, and
any cumulative impacts due to the decommissioning work and other parts of the
project, or other planned projects.
A.2 Land Contamination and Contaminated Materials Disposal
A.2.1 The Applicant shall follow the
guidelines for evaluating and assessing potential land contamination issues as
stated in Sections 3.1 and 3.2 in Annex 19 of the TM.
A.2.2 The Applicant shall provide a clear and detailed account of
the present land use (including description of the activities, chemicals and
hazardous substances handled with clear indication of their storage and
location by reference to a site map) and the relevant landuse history in
relation to possible land contamination and present of contaminated materials
requiring disposal, in particular those contaminated by dioxin (including
accident records, change of landuse and the like).
A.2.3 During the execution of the EIA study, the Applicant
shall submit a contamination assessment plan (CAP) to the Director for
endorsement prior to conducting an actual contamination impact assessment of
the land/site/materials requiring disposal. The CAP shall include proposals on sampling and analysis
required and shall aim at determining the nature and the extent of the
contamination of the land/site/materials requiring disposal.
A.2.4 Based on the endorsed CAP, the
Applicant shall conduct a contamination impact assessment. If land/material contamination is confirmed,
a remedial action plan shall be prepared to formulate necessary remedial
measures and disposal methods. The field investigation and sampling work should
be conducted in a safe and proper manner and the remedial action plan shall
ensure that the contaminated soil and materials would be handled and disposed
of in safely and properly.
----
END OF APPENDIX A ----
APPENDIX
B-1
Guidelines on Choice of Models and Model
Parameters
1. Introduction
1.1 To expedite the
review process by the Authority and to assist project proponents or
environmental consultants with the conduct of air quality modelling exercises
which are frequently called for as part of environmental impact assessment
studies, this paper describes the usage and requirements of a few commonly used
air quality models.
2. Choice of
models
2.1 The models
which have been most commonly used in air quality impact assessments, due
partly to their ease of use and partly to the quick turn-around time for
results, are of Gaussian type and designed for use in simple terrain under
uniform wind flow. There are circumstances when these models are not suitable
for ambient concentration estimates and other types of models such as physical,
numerical or mesoscale models will have to be used. In situations where
topographic, terrain or obstruction effects are minimal between source and
receptor, the following Gaussian models can be used to estimate the near-field
impacts of a number of source types including dust, traffic and industrial
emissions.
Model |
Applications |
FDM |
for evaluating fugitive and open dust
source impacts (point, line and area sources) |
CALINE4 |
for evaluating mobile traffic emission
impacts (line sources) |
ISCST3 |
for evaluating industrial chimney
releases as well as area and volumetric sources (point, area and volume
sources); line sources can be approximated by a number of volume sources. |
These frequently used models
are also referred to as Schedule 1 models (see attached list).
2.2
Note that both FDM and CALINE4 have a height limit on elevated sources (20 m
and 10m, respectively). Source of elevation above these limits will have to be
modelled using the ISCST3 model or suitable alternative models. In using the
latter, reference should be made to the 'Guidelines on the Use of Alternative
Computer Models in Air Quality Assessment'.
2.3
The models
can be used to estimate both short-term (hourly and daily average) and
long-term (annual average) ambient concentrations of air pollutants. The model
results, obtained using appropriate model parameters (refer to Section 3) and
assumptions, allow direct comparison with the relevant air quality standards
such as the Air Quality Objectives (AQOs) for the relevant pollutant and time
averaging period.
3. Model input
requirements
3.1
Meteorological Data
3.1.1 At least 1
year of recent meteorological data (including wind speed, wind direction,
stability class, ambient temperature and mixing height) from a weather station
either closest to or having similar characteristics as the study site should be
used to determine the highest short-term (hourly, daily) and long-term (annual)
impacts at identified air sensitive receivers in that period. The amount of
valid data for the period should be no less than 90 percent.
3.1.2 Alternatively,
the meteorological conditions as listed below can be used to examine the worst
case short-term impacts:
Day time:
stability class D; wind speed 1 m/s (at 10m height); worst-case wind angle;
mixing height 500 m
Night time:
stability class F; wind speed 1 m/s (at 10m height); worst case wind angle;
mixing height 500 m
This is a common practice with using the
CALINE4 model due to its inability to handle lengthy data set.
3.1.3 For situations
where, for example, (i) the model (such as CALINE4) does not allow easy
handling of one full year of meteorological data; or (ii) model run time is a
concern, the followings can be adopted in order to determine the daily and
annual average impacts:
(i)
perform a frequency occurrence analysis of one year of meteorological data to
determine the actual wind speed (to the nearest unit of m/s), wind direction
(to the nearest 10o) and stability (classes A to F) combinations and
their frequency of occurrence;
(ii) determine the short term hourly impact under all of the
identified wind speed, wind direction and stability combinations; and
(iii) apply the frequency data with the short term results to
determine the long term (daily / annual) impacts.
Apart from the above,
any alternative approach that will capture the worst possible impact values
(both short term and long term) may also be considered.
3.1.4 Note that the anemometer
height (relative to a datum same for the sources and receptors) at which wind
speed measurements were taken at a selected station should be correctly entered
in the model. These measuring positions can vary greatly from station to
station and the vertical wind profile employed in the model can be grossly
distorted from the real case if incorrect anemometer height is used. This will
lead to unreliable concentration estimates.
3.1.5 An additional
parameter, namely, the standard deviation of wind direction, σΘ, needs to be provided as input to the
CALINE4 model. Typical values ofσΘrange
from 12o for rural areas to 24o for highly urbanised areas under 'D'
class stability. For semi-rural such as new development areas, 18o is more appropriate under the same
stability condition. The following reference can be consulted for typical
ranges of standard deviation of wind direction under different stability
categories and surface roughness conditions.
Ref.(1): Guideline On
Air Quality Models (Revised), EPA-450/2-78-027R, United States Environmental
Protection Agency, July 1986.
3.2 Emission
Sources
All the identified sources relevant to a
process plant or a study site should be entered in the model and the emission
estimated based on emission factors compiled in the AP-42 (Ref. 2) or other
suitable references. The relevant sections of AP-42 and any parameters or
assumptions used in deriving the emission rates (in units g/s, g/s/m or g/s/m2) as required by the model should be
clearly stated for verification. The physical dimensions, location, release
height and any other emission characteristics such as efflux conditions and
emission pattern of the sources input to the model should also correspond to
site data.
If the emission of a source varies with
wind speed, the wind speed-dependent factor should be entered.
Ref.(2): Compilation of
Air Pollutant Emission Factors, AP-42, 5thEdition, United States
Environmental Protection Agency, January 1995.
3.3 Urban/Rural Classification
Emission sources may be located in a
variety of settings. For modelling purposes these are classed as either rural
or urban so as to reflect the enhanced mixing that occurs over urban areas due
to the presence of buildings and urban heat effects. The selection of either
rural or urban dispersion coefficients in a specific application should follow
a land use classification procedure. If the land use types including
industrial, commercial and residential uses account for 50% or more of an area
within 3 km radius from the source, the site is classified as urban; otherwise,
it is classed as rural.
3.4 Surface
Roughness Height
This parameter is closely related to the
land use characteristics of a study area and associated with the roughness
element height. As a first approximation, the surface roughness can be estimated
as 3 to 10 percent of the average height of physical structures. Typical values
used for urban and new development areas are 370 cm and 100 cm, respectively.
3.5 Receptors
These include discrete receptors
representing all the identified air sensitive receivers at their appropriate
locations and elevations and any other discrete or grid receptors for
supplementary information. A receptor grid, whether Cartesian or Polar, may be
used to generate results for contour outputs.
3.6 Particle Size
Classes
In evaluating the impacts of
dust-emitting activities, suitable dust size categories relevant to the dust
sources concerned with reasonable breakdown in TSP (< 30 μm) and RSP (< 10 μm) compositions should be used.
3.7 NO2 to NOx Ratio
The conversion of NOx to NO2 is a result of a series of complex photochemical reactions
and has implications on the prediction of near field impacts of traffic
emissions. Until further data are available, three approaches are currently
acceptable in the determination of NO2:
(a)
Ambient Ratio Method (ARM) - assuming 20% of NOx to be NO2;
or
(b) Discrete Parcel Method (DPM, available in the CALINE4
model); or
(c) Ozone Limiting Method (OLM) - assuming the tailpipe
NO2 emission to be 7.5% of NOx and the background ozone
concentration to be in the range of 57 to 68 μg/m3 depending on the
land use type (see also EPD reference paper 'Guidelines on Assessing the
'TOTAL' Air Quality Impacts').
3.8
Odour Impact
In assessing odour impacts, a much shorter
time-averaging period of 5 seconds is required due to the shorter exposure
period tolerable by human receptors. Conversion of model computed hourly
average results to 5-second values is therefore necessary to enable comparison
against recommended standard. The hourly concentration is first converted to
3-minute average value according to a power law relationship which is stability
dependent (Ref. 3) and a result of the statistical nature of atmospheric
turbulence. Another conversion factor (10 for unstable conditions and 5 for
neutral to stable conditions) is then applied to convert the 3-minute average
to 5-second average (Ref. 4). In summary, to convert the hourly results to
5-second averages, the following factors can be applied:
|
Stability Category |
1-hour to 5-sec Conversion Factor |
|
A & B |
45 |
|
C |
27 |
|
D |
9 |
Under 'D' class stability, the
5-second concentration is approximately 10 times the hourly average result. Note,
however, that the combined use of such conversion factors together with the
ISCST results may not be suitable for assessing the extreme close-up impacts of
odour sources.
Ref.(3): Richard A.
Duffee, Martha A. O' Brien and Ned Ostojic, 'Odor Modeling - Why and How',
Recent Developments and Current Practices in Odor Regulations, Controls and
Technology, Air & Waste Management Association, 1991.
Ref.(4): A.W.C. Keddie,
'Dispersion of Odours', Odour Control - A Concise Guide, Warren Spring
Laboratory, 1980.
3.9 Plume Rise
Options
The ISCST3 model provides by default a
list of the U.S. regulatory options for concentration calculations. These are
all applicable to the Hong Kong situations except for the 'Final Plume Rise' option.
As the distance between sources and receptors are generally fairly close, the
non-regulatory option of 'Gradual Plume Rise' should be used instead to
give more accurate estimate of near-field impacts due to plume emission.
However, the 'Final Plume Rise' option may still be used for assessing the
impacts of distant sources.
3.10 Portal
Emissions
These include traffic emissions from
tunnel portals and any other similar openings and are generally modelled as
volume sources according to the PIARC 91 (or more up-to-date version)
recommendations (Ref. 5, section III.2). For emissions arising from underpasses
or any horizontal openings of the like, these are treated as area or point
sources depending on the source physical dimensions. In all these situations,
the ISCST3 model or more sophisticated models will have to be used instead of
the CALINE4 model. In the case of portal emissions with significant horizontal
exit velocity which cannot be handled by the ISCST3 model, the impacts may be
estimated by the TOP model (Ref. 6) or any other suitable models subject to
prior agreement with EPD. The EPD's 'Guidelines on the Use of Alternative
Computer Models in Air Quality Assessment' should also be referred to.
Ref.(5): XIXth World
Road Congress Report, Permanent International Association of Road Congresses
(PIARC), 1991.
Ref.(6): N. Ukegunchi,
H. Okamoto and Y. Ide "Prediction of vehicular emission pollution around a
tunnel mouth", Proceedings 4th International Clean Air Congress, pp.
205-207, Tokyo, 1977.
3.11 Background
Concentrations
Background concentrations are required to
account for far-field sources which cannot be estimated by the model. These
values, to be used in conjunction with model results for assessing the total
impacts, should be based on long term average of monitoring data at location
representative of the study site. Refer to EPD reference paper 'Guidelines on
Assessing the 'TOTAL' Air Quality Impacts' for further information.
3.12 Output
The highest short-term and long-term averages
of pollutant concentrations at prescribed receptor locations are output by the
model and to be compared against the relevant air quality standards specified
for the relevant pollutant. Contours of pollutant concentration are also
required for indicating the general impacts of emissions over a study area.
Copies of model files in electronic
format should also be provided for EPD's reference.
The information contained in this
Appendix is only meant to assist the Applicant in performing the air quality assessment. The Applicant must exercise
professional judgement in applying this general information for the
Project.
Schedule 1
Air Quality
Models Generally Accepted by
Hong Kong
Environmental Protection Department for
Regulatory Applications as at 1 July 1998*
Industrial Source Complex Dispersion
Model - Short Term Version 3 (ISCST3)
or the latest version developed by U.S. Environmental Protection Agency
California Line Source Dispersion Model
Version 4 (CALINE4) or
the latest version developed by Department of Transportation, State of
California, U.S.A.
Fugitive Dust Model (FDM) or the latest version developed by U.S.
Environmental Protection Agency
* EPD is continually
reviewing the latest development in air quality models and will update this
Schedule accordingly.
APPENDIX
B-2
Guidelines on Assessing the 'TOTAL' Air
Quality Impacts
1. Total Impacts
- 3 Major Contributions
1.1 In evaluating
the air quality impacts of a proposed project upon air sensitive receivers,
contributions from three classes of emission sources depending on their
distance from the site should be considered. These are:
|
Primary contributions: |
project induced |
|
Secondary contributions: |
pollutant-emitting activities
in the immediate neighbourhood |
|
Other contributions: |
pollution not accounted for
by the previous two |
2. Nature of
Emissions
2.1 Primary
contributions
In
most cases, the project-induced emissions are fairly well defined and quite
often (but not necessarily) the major contributor to local air quality impacts.
Examples include those due to traffic network, building or road construction
projects.
2.2
Secondary contributions
Within
the immediate neighbourhood of the project site, there are usually pollutant
emitting activities contributing further to local air quality impacts. For most
local scale projects, any emission sources in an area within 500m radius of the
project site with notable impacts should be identified and included in an air
quality assessment to cover the short-range contributions. In the exceptional
cases where there is one or more significant sources nearby, the study area may
have to be extended or alternative estimation approach employed to ensure these
impacts are reasonably accounted for.
2.3
Background contributions
The
above two types of emission contributions should account for, to a great
extent, the air quality impacts upon local air sensitive receivers, which are
often amenable to estimation by the 'Gaussian Dispersion' type of models.
However, a background air quality level should be prescribed to indicate the
baseline air quality in the region of the project site, which would account for
any pollution not covered by the two preceding contributions. The emission
sources contributing to the background air quality would be located further
afield and not easy to identify. In addition, the transport mechanism by which
pollutants are carried over long distances (ranging from 1km up to tens or
hundreds of kms) is rather complex and cannot be adequately estimated by the
'Gaussian' type of models.
3. Background Air
Quality - Estimation Approach
3.1 The approach
In
view of the difficulties in estimating background air quality using the air
quality models currently available, an alternative approach based on monitored
data is suggested. The essence of this approach is to adopt the long-term
(5-year) averages of the most recent monitored air quality data obtained by
EPD. These background data would be reviewed yearly or biennially depending on
the availability of the monitored data. The approach is a first attempt to
provide a reasonable estimate of the background air quality level for use in
conjunction with EIA air quality assessment to address the cumulative impacts
upon a locality. This approach may be replaced or supplemented by superior
modelling efforts such as that entailed in PATH (Pollutants in the Atmosphere
and their Transport over Hong Kong), a comprehensive territory-wide air quality
modelling system currently being developed for Hong Kong. Notwithstanding this,
the present approach is based on measured data and their long term regional
averages; the background values so derived should therefore be indicative of
the present background air quality. In the absence of any other meaningful way
to estimate a background air quality for the future, this present background
estimate should also be applied to future projects as a first attempt at a
comprehensive estimate until a better approach is formulated.
3.2
Categorisation
The
monitored air quality data, by 'district-averaging' are further divided into
three categories, viz, Urban, Industrial and Rural/New Development. The
background pollutant concentrations to be adopted for a project site would
depend on the geographical constituency to which the site belongs. The
categorisation of these constituencies is given in Section 3.4. The monitoring
stations suggested for the 'district-averaging'(arithmetic means) to derive
averages for the three background air quality categories are listed as follows:
Urban:
Kwun Tong, Sham Shui Po, Tsim Sha Tsui and Central/Western
Industrial: Kwun Tong, Tsuen Wan and Kwai Chung
Rural/New Development: Sha Tin, Tai Po, Junk Bay, Hong Kong South and Yuen Long
The
averaging would make use of data from the above stations wherever available.
The majority of the monitoring stations are located some 20m above ground.
3.3 Background pollutant
values
Based
on the above approach, background values for the 3 categories have been
obtained for a few major air pollutants as follows:
POLLUTANT |
URBAN |
INDUSTRIAL |
RURAL/NEW DEVELOPMENT |
NO2 |
59 |
57 |
39 |
SO2 |
21 |
26 |
13 |
O3 |
62 |
68 |
57 |
TSP |
98 |
96 |
87 |
RSP |
60 |
58 |
51 |
All
units are in micrograms per cubic metre. The above values are derived from 1992
to 1996 annual averages with the exception of ozone which represent annual average
of daily hourly maximum values for year 1996.
In
cases where suitable air quality monitoring data representative of the study
site such as those obtained from a nearby monitoring station or on-site
sampling are not available for the prescription of background air pollution
levels, the above tabulated values can be adopted instead. Strictly speaking,
the suggested values are only appropriate for long term assessment. However, as
an interim measure and until a better approach is formulated, the same values
can also be used for short term assessment. This implies that the short term
background values will be somewhat under-estimated, which compensates for the
fact that some of the monitoring data are inherently influenced by secondary
sources because of the monitoring station location.
Indeed,
if good quality on-site sampling data which cover at least one year period are
available, these can be used to derive both the long term (annual) and short
term (daily / hourly) background values, the latter are usually applied on an
hour to hour, day to day basis.
3.4 Site
categories
The
categories to which the 19 geographical constituencies belong are listed as
follows:
DISTRICT |
AIR QUALITY CATEGORY |
Islands |
Rural/New Development |
Southern |
Rural/New Development |
Eastern |
Urban |
Wan Chai |
Urban |
Central & Western |
Urban |
Sai Kung |
Rural/New Development |
Kwun Tong |
Industrial |
Wong Tai Sin |
Urban |
Kowloon City |
Urban |
Yau Tsim |
Urban |
Mong Kok |
Urban |
Sham Shui Po |
Urban |
Kwai Tsing |
Industrial |
Sha Tin |
Rural/New Development |
Tsuen Wan |
Industrial |
Tuen Mun |
Rural/New Development |
Tai Po |
Rural/New Development |
Yuen Long |
Rural/New Development |
Northern |
Rural/New Development |
3.5 Provisions for ‘double-counting’
The
current approach is, by no means, a rigorous treatment of background air
quality but aims to provide an as-realistic-as-possible approximation based on limited
field data. 'Double-counting' of 'secondary contributions' may be apparent
through the use of such 'monitoring-based' background data as some of the
monitoring stations are of close proximity to existing emission sources.
'Primary contributions' due to a proposed project (which is yet to be realised)
will not be double-counted by such an approach. In order to avoid
over-estimation of background pollutant concentrations, an adjustment to the
values given in section 3.3 is possible and optional by multiplying the
following factor:
(1.0 -
ESecondary
contributions/ETerritory)
where E stands for emission.
The
significance of this factor is to eliminate the fractional contribution to
background pollutant level of emissions due to 'secondary contributions' out of
those from the entire territory. In most cases, this fractional contribution to
background pollutant levels by the secondary contributions is minimal.
4. Conclusions
4.1
The above described approach to estimating the total air quality impacts of a
proposed project, in particular the background pollutant concentrations for air
quality assessment, should be adopted with immediate effect. Use of short term
monitoring data to prescribe the background concentrations is no longer
acceptable.
The information contained in this
Appendix is only meant to assist the Applicant in performing the air quality
assessment. The Applicant must
exercise professional judgement in applying this general information for the
Project.
APPENDIX
B-3
Guidelines
on the Use of Alternative Computer Models
in Air Quality Assessment
1. Background
1.1 In Hong Kong,
a number of Gaussian plume models are commonly employed in regulatory applications
such as application for specified process licences and environmental impact
assessments (EIAs). These frequently used models (as listed in Schedule 1
attached; hereafter referred to as Schedule 1 models) have no regulatory status
but form the basic set of tools for local-scale air quality assessment in Hong
Kong.
1.2 However, no
single model is sufficient to cover all situations encountered in regulatory
applications. In order to ensure that the best model available is used for each
regulatory application and that a model is not arbitrarily applied, the project
proponent (and/or its environmental consultants) should assess the capabilities
of various models available and adopt one that is most suitable for the project
concerned.
1.3 Examples of
situations where the use of an alternative model is warranted include:
(i) the
complexity of the situation to be modelled far exceeds the capability of the
Schedule 1 models; and
(ii) the performance of an alternative model is
comparable or better than the Schedule 1 models.
1.4 This paper
outlines the demonstration / submission required in order to support the use of
an alternative air quality model for regulatory applications for Hong Kong.
2. Required
Demonstration / Submission
2.1 Any model
that is proposed for air quality applications and not listed amongst the
Schedule 1 models will be considered by EPD on a case-by-case basis. In
such cases, the proponent will have to provide the followings for EPD's
review:
(i) Technical details of the proposed
model; and
(ii) Performance evaluation of the proposed model
Based on the above information, EPD will
determine the acceptability of the proposed model for a specific or general
applications. The onus of providing adequate supporting materials rests
entirely with the proponent.
2.2 To provide
technical details of the proposed model, the proponent should submit documents
containing at least the following information:
(i) mathematical formulation and data
requirements of the model;
(ii) any previous performance evaluation of the model; and
(iii) a complete set of model input and output file(s) in commonly used
electronic format.
2.3 On
performance evaluation, the required approach and extent of demonstration
varies depending on whether a Schedule 1 model is already available and
suitable in simulating the situation under consideration. In cases where no
Schedule 1 model is found applicable, the proponent must demonstrate that the
proposed model passes the screening test as set out in USEPA Document
"Protocol for Determining the Best Performing Model" (Ref. 1).
2.4 For cases
where a Schedule 1 model is applicable to the project under consideration but
an alternative model is proposed for use instead, the proponent must
demonstrate either that
(i) the highest
and second highest concentrations predicted by the proposed model are within 2
percent of the estimates obtained from an applicable Schedule 1 model (with
appropriate options chosen) for all receptors for the project under
consideration; or
(ii) the proposed
model has superior performance against an applicable Schedule 1 model based on
the evaluation procedure set out in USEPA Document "Protocol for
Determining the Best Performing Model" (Ref. 1).
2.5 Should EPD
find the information on technical details alone sufficient to indicate the
acceptability of the proposed model, information on further performance
evaluation as specified in Sections 2.3 and 2.4 above would not be necessary.
2.6 If the proposed
model is an older version of one of the Schedule 1 models or was previously
included in Schedule 1, the technical documents mentioned in Section 2.2 are
normally not required. However, a performance demonstration of equivalence as
stated in Section 2.4 (i) would become necessary.
2.7 If EPD is
already in possession of some of the documents that describe the technical
details of the proposed model, submission of the same by the proponent is not
necessary. The proponent may check with EPD to avoid sending in duplicate
information.
The information contained in this
Appendix is only meant to assist the Applicant in performing the air quality
assessment. The Applicant must
exercise professional judgement in applying this general information for the Project.
Schedule
1
Air Quality Models Generally Accepted by
Hong Kong Environmental Protection Department for
Regulatory Applications as at 1 July 1998*
Industrial Source Complex Dispersion
Model - Short Term Version 3 (ISCST3)
or the latest version developed by U.S. Environmental Protection Agency
California Line Source Dispersion Model
Version 4 (CALINE4) or
the latest version developed by Department of Transportation, State of
California, U.S.A.
Fugitive Dust Model (FDM) or the latest version developed by U.S.
Environmental Protection Agency
Ref.
(1): William M. Cox, "Protocol for Determining the Best Performing
Model" Publication No. EPA-454/R-92-025; U.S. Environmental Protection
Agency, Research Triangle Park, NC.
* EPD is continually reviewing the latest development in air quality models and will update this Schedule accordingly.
APPENDIX
B-4
Guidelines
on Estimating Height Restriction and
Position of Fresh Air Intake Using Gaussian Plume Models
1. Introduction
1.1 Two
situations in Hong Kong call for an assessment of ambient pollution
concentration as a function of height, namely, the determination of
(i)
height restriction for new buildings in areas subject to poor air quality aloft
as a result of elevated emission sources nearby; and
(ii)
optimum / acceptable location of fresh-air intakes for centrally
air-conditioned buildings.
1.2 Simple
Gaussian plume models like the Industrial Source Complex Dispersion Model - Short
Term Version 3 (ISCST3) have been commonly used in Hong Kong for predicting air
quality with a view to addressing the two situations above. This guideline
provides a practical approach to applying the ISCST3 model to these two
situations in order to safeguard air quality. The application limits of the
ISCST3 model must, however, be observed (refer to its User's Guide). Suitable
alternatives such as wind tunnel modelling or more sophisticated numerical
modelling may have to be used instead if the situation warrants.
2. Approach
2.1 The
concentration pattern at sensitive receivers produced by emissions from a
single stack is different from that produced by multiple stacks. However, in
most cases, the emission characteristics of one particular stack can be used to
approximate the concentration pattern at sensitive receivers due to its
dominance. An exception to this generalisation occurs when there exist a number
of stacks concentrating in a small area but having large differences in
emission characteristics such as emission height, stack dimensions, efflux
velocity and temperature.
General Situation
2.2 A case can be
considered general if it belongs to one of the following categories:
(i)
Vertical concentration profile at receptors is contributed solely by emissions
from one stack with diameter less than or equal to 1m;
(ii)
Vertical concentration profile at receptors is dominated by emissions from one
stack with none of the contributing stacks having tip diameter larger than 1m and
the stacks are not clustered in space (i.e. not of similar distance nor in the
same direction from the receptor);
(iii)
Vertical concentration profile at receptors is dominated by emissions from more
than one stack with no contributing stack(s) having tip diameter larger than 1m
and the stacks are not clustered horizontally; and
(iv)
Vertical concentration profile at receptors is dominated by emissions from more
than one stack with no contributing stack(s) having tip diameter larger than 1m
and the dominant stacks clustered horizontally, but the stack gas
characteristics and emission heights of these dominant stacks are not
significantly different.
2.3 Since only
fewer than 3% of stacks registered in Hong Kong have tip diameter larger than 1m,
these "large" stacks are treated individually as suggested in section
2.5.
2.4 For the
general case, we have performed a sensitivity study (Annex I) based on a single
stack to determine the uncertainty associated with plume heights arising from input
data of limited accuracy. On the basis of these findings, we recommend the
followings:
(i)
Conduct an air quality modelling exercise using the stack emission
characteristics dictated by the situation.
(ii)
The restricted height range will be the region of unacceptable air quality with
a 10m safety margin added to both ends. The modelling exercise should therefore
address the full receptor height range and 10m beyond.
Special Situation
2.5 For all other
situations not covered by those in Section 2.2 above, the following procedures
are recommended:
(i)
Conduct an air quality modelling exercise using the minimum values of stack gas
exit velocity and stack gas temperature (i.e. 6ms-1 and 373K,
respectively).
(ii)
Conduct a second modelling exercise based on the maximum (or calculated,
whichever is higher) values of stack gas exit velocity and stack gas
temperature of the respective ranges (Table 1).
(iii)
The results from the first and second runs above are then used to delimit the
upper and lower end of the range of unacceptable air quality, respectively.
2.6 In conducting
the air quality modelling exercise, background pollutant concentrations should
also be allowed for. The "Guidelines on Assessing the 'TOTAL' Air Quality
Impacts" can be referred to.
Annex I
Sensitivity
Study on the Height of Maximum Impact at a Receptor
A. Approach
A.1 In assessing
the impact of emission from a point source using ISCST3, the following
parameters would affect the plume rise:
a.
stack height;
b. stack diameter;
c. stack gas temperature;
d. stack gas exit velocity;
e. ambient temperature; and
f. stack tip wind velocity.
A.2 The first two
parameters above are clearly specified and not subject to change. The last two
parameters are part of the meteorological input independent of plume
characteristics. Uncertainty in the plume rise calculation is introduced
through:
a.
the limited ability of the plume rise algorithm to replicate nature; and
b. the uncertainty
in the effluent's characteristics as represented by the stack gas temperature
and stack gas exit velocity.
A.3 The first
type of uncertainty attends all mathematical representation of complex reality.
Users of model results will have to come to terms with this limitation.
However, in modelling air quality for general environmental assessment (e.g.
ground level concentration, safe set-back distance, ..., etc.), attempts are
usually made to produce a 'conservative' estimate. Though this conservative
estimate does not address the accuracy of the algorithm, which varies from case
to case and cannot be determined without an unrealistic amount of monitoring in
most cases, it is generally practiced and accepted as sufficient to safeguard
the air quality at sensitive receivers.
A.4 In the same
vein, we are attempting to specify procedures that would produce 'conservative'
results to safeguard air quality at air sensitive receptors that are dependent
on the vertical position of the plume. The complication in this attempt is the
definition of 'conservative' results. For the case of height restriction,
estimation based on a lower plume rise would be conservative. For determining
the optimum locations of fresh-air intakes, enough margin would have to be
allowed for at both the upper and lower ends of the acceptable locations.
A.5 Since the values of
the stack gas temperature and stack gas exit velocity affect the plume rise, a
sensitivity test was conducted to delimit the uncertainty in plume rise due to
these two parameters.
B. Sensitivity Study
B.1 The base case
of the sensitivity test is selected such that the plume rise due to buoyancy
(represented by the stack gas temperature) and momentum (represented by the
stack gas exit velocity) is at a minimum. This corresponds to choosing the
minimum values of the stack gas exit velocity and temperature in the respective
ranges. Performing sensitivity tests on this base case would amplify the
resulting deviation, thus producing conservative results.
B.2 By studying
the emission characteristics of the industrial stacks in Hong Kong, it is found
that exit velocities and stack gas temperatures for most industrial stacks vary
between 6 - 10 ms-1 and 373 - 573K. For the sensitivity tests, the
values of the exit gas velocity and exit gas temperature are varied within
these ranges to determine the maximum uncertainty in plume rise. The details of
the parameters used in the base case are given in Table 1.
B.3 The same
procedure was repeated for different values of the stack tip diameter (between
0.1 and 1m) and for different ambient temperatures (between 0 and 40oC).
C. Results
C.1 Within a
horizontal distance of 20 to 1,000m from the stack, the sensitivity tests’
results show that the plume centre line height will not differ by more than 10m
from that of the base case for the specified ranges of parameter values. Also,
within the ranges tested, this plume centre line height is not significantly
affected by the ambient temperature and stack tip diameter. Furthermore, the
maximum concentration at a certain distance from the stack is not sensitive to
the changes in the stack gas exit velocity and stack gas temperature.
C.2 Further tests
show that some plume rise values resulting from the specified ranges of
parameters may deviate from the base case plume rise by more than 10m if the
stack tip diameter is larger than 1m.
Table
1
Input
Parameters in the Base Case
Chimney Characteristics |
Rationale |
height of emission - 100m |
the height was chosen to represent the typical height of
emission for chimneys in industrial areas |
stack tip diameter - 1m |
approximate 97% of the stacks have diameters less than 1m according
to EPD's Enforcement Management System (EMS) |
exit velocity - 6 ms-1 |
the minimum exit velocity required by the licence |
exit gas temperature - 373K |
the minimum of the range typical of those stacks servicing
industrial boilers |
emission strength -
1gs-1 |
a reference emission
strength |
Meteorological Conditions |
Rationale |
(included in a meteorological file) |
follows the USEPA's meteorological conditions for
screening procedure, i.e. A: 1, 2, 3 ms-1 |
mixing height - 500m |
as the emission height of the source is at 100m, the predicted
concentration and the height of maximum impact are insensitive to this value |
ambient temperature - 298K |
a typical ambient temperature used in Hong Kong |
Receptor
receptor distance
- 20, 40, 60, 80, 100, 150, 200, 250, 300, 350, 400, 450, 500, 600, 700, 800,
900, 1000m downwind from the source
receptor height
- 80 - 200m of 10m intervals
Other Options
(following typical choices in modelling exercises)
dispersion coefficient - urban
wind profile exponents - default
vertical temperature gradient - default
gradual plume rise option
stack tip downwash option
no building downwash option
The information contained in this Appendix is only meant to assist the
Applicant in performing the air quality assessment. The Applicant must exercise professional judgement in
applying this general information for the Project.
Implementation Schedule
Reprovisioning of Diamond Hill Crematorium
EIA Ref. |
EM&A Ref. |
Recommended Mitigation Measures |
Objectives of the Recommended Measure & Main
Concerns to address |
Who to implement the measure ? |
Location of the measure |
When to implement the measure ? |
What requirements or standards for the measure to achieve ? |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|