Environmental Impact
Assessment Ordinance (Cap. 499)
Section 5(7)
Environmental Impact
Assessment Study Brief No. ESB-103/2002
Project
Title: Drainage Improvements in Northern New Territories – Package C
Name of Applicant:
Drainage Services Department
(hereinafter known as
the “Applicant”)
1. BACKGROUND
1.1
An application (No. ESB-103/2002) for an
Environmental Impact Assessment (EIA) Study Brief (SB) under section 5(1) of
the Environmental Impact Assessment Ordinance (EIAO) was submitted by the
Applicant on 9 May 2002 with a Project Profile (No. PP-168/2002) for the
captioned project.
1.2
The purpose of the Project is to
alleviate the flooding problems and to facilitate future development in Lung
Yeuk Tau, Man Ukp
Pin, Loi Tung and Lin Ma Hang areas by improving the secondary and local storm
water drainage systems in accordance with the recommendation of the 55CD
“Drainage Master Plan Study in the Northern New Territories” (DMP Study).
1.3
The Project comprises the construction of
drainage channels and associated works to improve the secondary and local
drainage systems in the Lung Yeuk Tau, Man Uk Pin, Loi Tung and Lin Ma Hang
areas. The proposed location and
scale of the drainage improvement works (the Project), identified to be
Designated Project (DP) under the EIAO is shown in attached Figures 1, 2, 3, 4
and Table 1.1 below.
Table 1.1 Scale of Proposed Drainage Works
Proposed Drainage Channel
Ref. No. |
Location |
Detail of Proposed
Channel |
|
Approx. Length (m) |
Average Base Width
(m) |
||
MUP03 (Figure 2) |
Drainage channel in Man Uk Pin area |
120 |
2 |
MUP04 A (Figure 2) |
Drainage channel in Man Uk Pin area |
400 |
4 |
MUP04 B (Figure 2) |
Drainage channel in Man Uk Pin area |
180 |
1 |
MUP05 (Figure 2) |
Drainage channel in Man Uk Pin area |
1000 |
8 |
LYT04 (Figure 3) |
Drainage channel in Lung Yeuk Tau area |
400 |
3 |
LMH01 (Figure 4) |
Drainage channel at Lin Ma Hang |
250 |
3 |
1.4
The Project is a Designated Project under
the EIAO by virtue of I.1(b) of the SCHEDULE 2, PART I of the EIAO with
specific Designated Project Elements as listed below.
(i)
Drainage channels at Man Uk Pin (MUP03,
MUP04A, MUP04B, and MUP05) that discharge into an area within 300m from the
nearest boundary of an existing “Conservation Area” land use zoning [Item
I.1(b)(vii) of Schedule 2 of EIAO].;
(ii)
Drainage channel at Lung Yeuk Tau (LYT04)
that discharges into an area within 300m of an existing site of cultural
heritage, the Entrance Tower of Ma Wat Wai, at Ma Wat Wai, Ling Yeuk Tau [Item
I.1(b)(ii) of Schedule 2 of EIAO].; and
(iii)
Drainage channel at Lin Ma Hang (LMH01)
that discharges into an area within 300m of a planned site of specific scientific interest (SSSI),
Lin Ma Hang Stream, at Lin Ma Hang [Item I.1(b)(i) of Schedule 2 of EIAO].
1.5
Pursuant to section 5(7)(a) of the EIAO,
the Director of Environmental Protection (the Director) issues this EIA study
brief to the Applicant to carry out an EIA study.
1.6
The purpose of this EIA study is to
provide information on the nature and extent of environmental impacts arising
from the construction and operation of the proposed Project and related
activities taking place concurrently.
This information will contribute to decisions by the Director on:
(i)
The overall acceptability of any adverse
environmental consequences those are likely to arise as a result of the
proposed Project.;
(ii)
The conditions and requirements for the
detailed design, construction and operation of the proposed Project to mitigate
against adverse environmental consequences wherever practicable and reasonable.; and
(iii)
The acceptability of residual impacts,
after the proposed mitigation measures are implemented.
2. OBJECTIVES
OF THE EIA STUDY
2.1
The objectives of the EIA study are as
follows:
(i)
To describe the proposed Project and
associated works together with the requirements for carrying out the proposed
Project.;
(ii) To identify and
describe the elements of the community and environment likely to be affected by
the proposed Project and/or likely to cause adverse impacts to the proposed
Project, including both the natural and man-made environment.;
(iii) To identify and
quantify emission sources and determine the significance of impacts on
sensitive receivers and potential affected uses.;
(iv) To identify any
potential impacts from point and non-point pollution sources on the identified
water systems and sensitive receivers during the construction and operation
stages.;
(v)
To identify and quantify any potential
losses and damage to flora, fauna and wildlife habitats.;
(vi)
To identify and quantify, where
applicable, any potential landscape and visual impacts and determine the
significance of impacts on sensitive receivers.;
(vii)
To identify any potential impacts to the
historical, archaeological and cultural resources and propose measures to
mitigate these impacts.;
(viii) To propose
the provision of infrastructure or mitigation measures so as to minimize
pollution, environmental disturbance and nuisance during construction and
operation of the proposed Project.;
(ix) To
identify, predict and evaluate the residual (i.e. after practicable mitigation)
environmental impacts and the cumulative effects expected to arise during the
construction and operation phases of the proposed Project in relation to the
sensitive receivers and potential affected uses.;
(x) To identify,
assess and specify methods, measures and standards, to be included in the
detailed design, construction and operation of the proposed Project, which are
necessary to mitigate these environmental impacts and reducing them to
acceptable levels.;
(xi) To investigate the
extent of secondary environmental impacts that may arise from the proposed
mitigation measures and to identify constraints associated with the mitigation
measures recommended in the EIA study, as well as the provision of any
necessary modification.;
(xii)
To design and specify the environmental
monitoring and audit requirements, if required, to ensure the implementation
and the effectiveness of the environmental protection and pollution control
measures adopted.; and
(xiii) To consider alternative flood
alleviation options with a view to avoiding or minimizing the potential
environmental impacts to the SSSI at
Lin Ma Hang, the “Conservation Area” zone in Man Uk Pin, the site(s) of
cultural heritage and other sensitive uses, and to compare the
environmental benefits and dis-benefits of each of the different option and to
provide reasons for selecting the preferred option and to describe the part
environmental factors played in the selection.
3. DETAILED
REQUIREMENTS OF THE EIA STUDY
3.1 The Purpose
The
purpose of this study brief is to scope the key issues of the EIA study. The
Applicant has to demonstrate in the EIA report that the criteria in the
relevant sections of the Technical Memorandum on the EIA Process of the EIAO
(hereinafter referred to as the TM) are fully complied with.
3.2 The
Scope
The
scope of this EIA study covers the Designated Project (MUP03, MUP04A, MUP04B,
MUP05, LYT04 and LMH01) as mentioned in Sections 1.2 and 1.3 above. The EIA study shall address the likely
key issues described below, together with any key issues identified during the
course of the EIA study.
(i)
Review the merit and
effectiveness of the
proposed Project as a means to alleviate flooding in the areas, in particular, the
proposed drainage channels at Lin Ma Hang (LMH01) and at Loi Tung (MUP04A).
(ii)
Exploration of alternatives to include but not
limited to different solutions to alleviate the flooding in the areas and to
avoid serious environmental and ecological impacts, which could not be
satisfactorily mitigated. Examples shall include but not limited to different options of channel design: such as by-pass design, bunds as flood
barriers design, flood pond design, and other environmentally friendly design, especially for
those parts of the Project likely to result in adverse ecological impacts.;
(iii)
Tthe potential noise and dust impacts
of the proposed Project to sensitive receivers during the construction phases,
in particular at the school(s), village houses and other
residential premises located near the Designated Project Sites.;
(iv)
The potential impacts to
the coastal water quality,
marine ecological habitat and ecosystem due to the discharge of stormwater into the coastal waters during the
construction and operational phases.Tthe potential
aquatic and terrestrial ecological impacts arising from the construction works,
including loss of habitats, removal of vegetation and disturbance to animals.
The ecological assessment shall demonstrate that the proposed drainage works
would not cause a net loss in both wetland area and function, and any negative
residual impacts should be fully addressed and mitigated. The assessment shall
fully address all direct, indirect and cumulative impacts resulting from the
proposed project;
(v)
The potential impacts arising from the
temporary storage and subsequent disposal of waste generated during the construction and operational phases.
(vi)
The potential impacts
arising from the soil runoff into the stream courses located in the nearby
areas where the dredged/excavated soils are to be stored, leading to fish kill
and permanent damage to the aquatic ecosystem.
(vii)
The potential
impacts on the planned Sites of Special
Scientific Interest (SSSI), “Lin Ma Hang Stream”, at Lin Ma Hang, the Conservation
Areas (CA) in Man Uk Pin, and the Site of Cultural Heritage at Ma Wat Wai, Lung
Yeuk Tau during the
construction and
operational phases.
;
(viii)
The potential aquatic and terrestrial ecological
impacts arising from the construction and operational phases, including loss of habitats,
removal of vegetation, the impact and disturbance to the foraging ground for
the bats in the vicinity of Lin Ma Hang stream and the stream at Loi Tung, and disturbance to animals
and wild life. The ecological assessment shall demonstrate that the proposed
drainage works would not cause any net loss in either wetland area and function, and any residual impacts
shall be fully addressed and
mitigated. The assessment shall fully address all direct, indirect and
cumulative impacts resulting from the proposed Project during the construction and the operational phases, including any subsequent
regular maintenance works. The design of the drainage
system shall take into account established and new environmentally friendly
design concept to mitigate the ecological impacts.
(ix)
Tthe potential landscape and visual
impacts arising from the removal of vegetation, and construction of the
drainage system. The design of the drainage system shall take into account
established and new environmentally friendly design concept to mitigate the
landscape and visual impacts of the site.; and
(x)
Tthe potential impacts of the proposed
Project on the cultural heritage sites, in particular the “Entrance Tower of Ma
Wat Wai, Lung Yeuk Tau”, that is likely to be affected by the construction
works. The design of the drainage channel shall demonstrate that impact on the
cultural heritage site be avoided or minimized.
3.3
Consideration
of the Merit of the Proposed Project, Alternative Means, Avoidance of
Environmental Impacts and Alternative Drainage Design
3.3.1 Consideration
of the Merit of the Proposed Project for Flood Alleviation
The Applicant shall further study
and review the merit of
the proposed Project as a means to alleviate flooding in the areas. In
particular, the drainage channel at Loi Tung within Man Uk Pin (i.e. MUP04A)
and the drainage channel at Lin Ma Hang (i.e. LMH01) need detailed research. Information and/or evidence
to include data of hydraulic and
hydrological preodictions of Loi Tung (Man Uk Pin) and Lin Ma Hang areas (with or without the proposed drainage channels in place) are required,
in justifying the merit and effectiveness of the proposed Project
for flood alleviation against the ecological loss and other environmental
impacts.
Consideration of Alternative Means and Avoidance of
Environmental Impacts
The
Applicant shall critically consider alternative means to achieve flood
alleviation instead of through stream training, widening, channelizing at Loi
Tung and Lin Ma Hang areas in order to avoid direct ecological impacts on:
·
the Lin Ma Hang stream and the stream at
Loi Tung;
·
the tributaries and wet lands associated
with these streams; and
·
the aquatic life, wildlife and habitats
that depend on these streams and its associated tributaries and wetlands.
Consideration
of Alternative Drainage Design
Apart from the alignments,
and locations, and design of channelization that are proposed
in the Project Profile, the Applicant shall also consider
different option designs that are practicable and reasonable,
to include but not limited to the drainage improvement designs such as: (a) by-pass design, (b) bunds as flood barriers
design,des (c) flood pond design,
(d) other environmentallyecological friendly design; alternative alignment on channel improvements; alternative locations of
stormwater drains and their discharge points; and others.
An evaluation system that
assesses A comparison of the environmental benefits and dis-benefits of all practicable
solutions described above shall be included. The potential ecological impacts on the aquatic
life, stream, its surroundings and the wildlife therein shall form one of
the key criterion
to be included in the evaluation
system. The final recommended drainage improvement designg
options(s), alignment option(s) and locations of the storm water drains and
discharge points shall be adequately assessed,
evaluated and justified, taking the key criteria included in the
evaluation system. and any desilting devices minimising uncontrolled
sediment discharge into the
sea shall be made.
3.3.2
Consideration of
Alternative Construction Methods
Having
regard to the cumulative effects for the construction of the six different
drainage improvement works (MUP3, MUP04A, MUP04B, MUP05, LYT04 and LMH01) and
the severity of the construction impacts to the affected sensitive receivers
along the drainage channels and the stormwater drains, the EIA study shall also
explore alternative construction methods for the Designated Project with a view
to avoiding adverse environmental impacts as far as practicable. A comparison
of the environmental benefits and dis-benefits of applying different
construction methods shall be made. In comparison, the Applicant shall also
take into account the cumulative environmental implications of potential
flooding at downstream areas during wet seasons throughout different
construction phases.
3.3.3 Based
on the comparisons as described in sections 3.3.1 and 3.3.2 above, the
Applicant shall recommend and justify the adoption of alignment or location options
that will avoid or minimize adverse environmental effects as far as
practicable.
3.4 Technical
Requirements
The
Applicant shall conduct the EIA study to address all environmental aspects of
the activities as described in the scope as set out above and subject to the
findings under section 3.3. The EIA study shall include the following technical
requirements on specific impacts.
3.4.1 Construction
Dust Impact
3.4.1.1
The Applicant shall follow the criteria
and guidelines for evaluating and assessing air quality impact as stated in section
1 of Annex 4 and Annex 12 of the TM respectively.
3.4.1.2
The assessment area for the construction
dust impact assessment shall generally be defined by a distance of 500 m from
the boundary of the Project work sites, yet it may be extended depending on the
circumstances and the scale of the Designated Project.
3.4.1.4 The
construction dust impact assessment shall include the following:
Background
and analysis of activities
(i) Provide background information relating
to air quality issues relevant to the Project, e.g. description of the types of
activities of the Project.
(ii) Give an account, where appropriate, of
the consideration/measures that had been taken into consideration in the
planning of the Project to abate the air pollution impact. That is, the Applicant shall consider
alternative construction methods/phasing programmes to minimize the
constructional air quality impact, e.g. use of marine access routes for
transportation of construction materials to avoid dust impact on air sensitive
receivers due to haul road transport during construction.
(iii) Present
the background air quality levels in the assessment area for the purpose of
evaluating the cumulative constructional air quality impacts.
Identification
of Air Sensitive Receivers (ASRs) and examination of emission/dispersion
characteristics
(iv) Identify
and describe representative existing and planned/committed ASRs that would
likely be affected by the Project, including those earmarked on the relevant Outline
Zoning Plans, Development Permission Area Plans, Outline Development Plans and
Layout Plans. The Applicant
shall select the assessment points of the identified ASRs such that they
represent the worst impact point on these ASRs. A map showing the location and a description including the
name of the buildings, their uses and height of the selected assessment points
shall be given. The separation
distances of these ASRs from the nearest emission sources shouldshall also be given.
(v)
Provide an exhaustive list of air
pollutant emission sources, including any nearby emission sources, which are
likely to have impact on the Project.
Examples of construction stage emission sources include stock piling,
blasting, concrete batching and vehicular movements on unpaved haul roads on
site and so forth. Confirmation of
the validity of the assumptions and the magnitude of the activities (e.g.
volume of construction materials handled) shall be obtained from the relevant
government/authorities and documented.
(vi) The
Applicant shall follow the requirements of the Air Pollution Control
(Construction Dust) Regulation in dust control to ensure construction dust
impacts are controlled to within the relevant standards as stipulated in
section 1 of Annex 4 of the TM. A
monitoring and audit program during the construction stage shall be implemented
to verify the effectiveness of the control measures and to ensure that the
construction dust levels are brought under control.
(vii) If
the Applicant anticipates a significant construction dust impact that will
likely cause exceedance of the recommended limits in the TM at the ASRs despite
incorporation of the dust control measures stated in (ii) above, a quantitative
assessment shall be carried out to evaluate the construction dust impact at the
identified ASRs. The Applicant shall
follow the methodology below when carrying out the assessment.
Quantitative
Assessment Methodology
(viii) The
Applicant shall apply the general principles enunciated in the modelling guidelines “Guidelines for Local-Scale
Air Quality Assessment Using Models”, issued by EPD in March 2000 (available
in EPD’s webpage under “Air” Section), while making allowance for the specific
characteristic of the Project. This specific methodology must be documented to
such level of detail (preferably with tables and diagrams) to allow the readers
of the assessment report to grasp how the model is set up to simulate the
situation at hand without referring to the model input files. Details of the calculation of the
emission rates of air pollutants for input to the modeling shall be presented in
the report. The Applicant must
ensure consistency between the text description and the model files at every
stage of submission. Prior
agreement of the general methodology between the Applicant and the Director is required.
(ix) The
Applicant shall identify the key/representative air pollutant parameters related
to construction activities (types of pollutants and the averaging time
concentration) to be evaluated and provide explanation for choosing these
parameters for the assessment of the impact of the Project.
(x)
The Applicant shall calculate the cumulative
air quality impact at the identified ASRs and compare these results against the
criteria set out in section 1 of Annex 4 in the TM. The predicted air quality impacts (both unmitigated and
mitigated) shall be presented in the form of summary tables and pollution
contours, for comparison with relevant air quality standards and for examination
of the land use implications of these impacts. Plans of suitable scale shouldshall be used for
presentation of pollution contours for determining buffer distances required.
Mitigating
Measures for Non-compliance
(xi)
The Applicant shall propose remedies and
mitigating measures, where the predicted air quality impact exceeds the
criteria set in section 1 of Annex 4 in the TM. These measures and any constraints on future land use
planning shall be agreed with the relevant government departments/authorities
and documented. The Applicant
shall demonstrate quantitatively that the resultant impacts after incorporation
of proposed mitigating measures will comply with the criteria stipulated in
section 1 of Annex 4 in the TM.
Submission
of Model Files
(xii)
All input and output file(s) of the model
run(s) shall be submitted to the Director in electronic format.
3.4.2 Construction
Noise Impact
3.4.2.1 The
Applicant shall follow the criteria and guidelines for evaluating and assessing
construction noise impact as stated in Annexes 5 and 13 of the TM,
respectively.
3.4.2.2 The
construction noise impact assessment shall include the following:
(i) Determination of Assessment Area
The
"Assessment Area" for the construction noise impact assessment shall
include all areas within 300 m from the Project boundary. Subject to the
agreement of the Director, the assessment area could be reduced accordingly if
the first layer of noise sensitive receivers, closer than 300 m from the
Project boundary, provides acoustic shielding to those receivers further from
the site.
(ii) Provision of Background
Information and Existing Noise Levels
The
Applicant shall provide all background information relevant to the Project,
including relevant previous or current studies.
(iii) Identification
of Noise Sensitive Receivers
(a) The Applicant shall refer to Annex
13 of the TM when identifying the noise sensitive receivers (NSRs). The NSRs shall include all existing
NSRs and all planned/committed noise sensitive developments and uses earmarked
on the relevant Outline Zoning Plans, Outline Development Plans, Layout Plans
and other published plans, including any land use and development applications
approved by Town Planning Board.
For planned noise sensitive land uses without committed layouts, the
Applicant shall work out indicative site layouts based on the relevant planning
parameters.
(b) The Applicant shall select
assessment points to represent all identified NSRs for carrying out
quantitative noise assessment described below. The assessment points shall be agreed with the Director
prior to the quantitative noise assessment. A map showing the location and
description such as name of building, use, and floors of each and every
selected assessment point shall be given.
(iv) Provision of an Emission Inventory of the
Noise Sources
The Applicant
shall provide an inventory of noise sources including construction equipment
for construction noise assessment. Confirmation of the validity of the
inventory shall be obtained from the relevant government
departments/authorities.
(v) Construction Noise Assessment
(a) The
Applicant shall carry out assessment of noise impact from construction
(excluding percussive piling) of the Designated Project during day time, i.e. 7
a.m. to 7 p.m., on weekdays other than general holidays in accordance with the
methodology stipulated in paragraphs 5.3 and 5.4 of Annex 13 of the TM. The criteria in Table 1B of Annex 5 of
the TM shall be adopted in the assessment.
(b) To minimize the construction noise
impact, alternative construction methods to replace percussive piling shall be
explored and recommended as far as practicable.
(c) If the unmitigated construction
noise levels are found to exceed the relevant criteria, the Applicant shall
propose practicable direct mitigation measures (including movable barriers,
enclosures, quieter alternative methods, re-scheduling and restricting hours of
operation of noisy task) to minimize the impact. If the mitigated noise levels still exceed the relevant
criteria, the duration of the noise exceedance shall be given.
(d) The applicant shall confirm whether
construction work during restricted hours is required. If affirmative, the applicant shall
evaluate whether construction works in restricted hours as defined under the
Noise Control Ordinance (NCO) are feasible or not in the context of programming
construction works. Reference
shall be made to the relevant technical memoranda issued under the NCO. Regardless of the results of the
construction noise impact assessment for restricted hours, the Noise Control
Authority will process the Construction Noise Permit (CNP) application, if
necessary, based on the NCO, the relevant technical memoranda issued under the
NCO, and the contemporary conditions/situations. This aspect shouldshall be explicitly stated in the noise chapter
and the conclusions and recommendations chapter in the EIA report.
3.4.3 Water
Quality Impact
3.4.3.1
The Applicant shall follow the criteria
and guidelines for evaluating and assessing water pollution as stated in
Annexes 6 and 14 of the TM, respectively.
3.4.3.2
The assessment area for the water quality impact
assessment shall include all areas within 500m from the Project boundary of the
Designated Project Sites. This study area could be extended to include
other areas such as stream courses and the associated water system, including
the coastal water of Deep Bay, where the water from the Project will eventually
discharge into, being impacted during the course of the EIA study if found
justifiable.
3.4.3.3
The Applicant shall identify and analyse
all physical, chemical and biological disruptions of marine, fresh water or
ground water system(s), catchment area(s), stormwater channel and coastal water
arising from the construction and operation of the Designated Project.
3.4.3.4
The Applicant shall include (1) the construction
phase impacts on water quality at the site; and (2) the operational phase
impacts on water quality at downstream of the site due to the natural process
of siltation, flows and water velocity, and re-suspensions of sediments. Essentially,
the assessment shall address the following:
(i)
Collection and review of background
information on the existing and planned water systems and their respective
catchments and sensitive receivers which might be affected by the Project
during construction and operation.
(ii)
Characterization
of water and sediment quality of the water systems
and respective catchments and sensitive receivers which might be affected by
the Project during construction and operation based on existing information or
appropriate site survey and tests.
(iii)
Identification and analysis of all
existing and planned future activities and beneficial uses related to the water
system(s) and identification of all water sensitive receivers. The Applicant shall
refer to, inter alia, those
developments and uses earmarked on the relevant Outline Zoning Plans, Outline
Development Plans and Layout Plans.
(iv)
Identification
of pertinent water and sediment quality objectives and establishment of other
appropriate water and sediment quality criteria or standards for the water
system(s) and all the sensitive receivers, particularly the aquatic biota of conservation
importance, in (i) above.
(v)
Review the specific construction methods
and configurations, and operation of the Project. Identification of any alteration of existing watercourses,
natural streams/ponds, shoreline or bathymetry, flow regimes, ground water
levels and catchment types or areas.
(vi)
Identification,
analysis and quantification of all existing, likely future water and sediment
pollution sources, including point discharges and non-point sources to surface
water runoff and analyze these in relation to the provision and adequacy of
future facilities to reduce such pollution in terms of capacity and levels of
treatment; evaluation and quantification through
appropriate site investigation and tests to the pollution loading intercepted
by the Project and discharged into the Shenzhen River and Inner Deep Bay;
evaluation and quantification
of the flows and pollution loads collected and
discharged into the existing and planned downstream water courses and drainage
systems before and after operation of the Project.
(vii)
Establishment
and provision of a pollution load inventory on the
quantities and characteristics of all existing and likely future water
pollution sources identified above. Field investigation and laboratory tests
shall be conducted as appropriate to fill in any major information gaps.
(viii)
Cumulative
impacts due to all other committed and planned projects, activities or
pollution sources within a boundary of 300m from both sides along the
identified water system(s) and sensitive
receivers shall be identified and assessed through undertaking a hydraulic
modelling.
(ix)
Assessment and evaluation of any
potential water quality impacts on the identified water system(s), respective
catchments and sensitive receivers due to sewage arising from the construction
stage. Any effluent generated will
require appropriate collection, treatment and disposal to within standards and
objectives and criteria established in (iv) above.
(x)
Assessment
and evaluation of any potential stormwater
and construction runoff impacts on the water system(s), respective catchments
and sensitive receivers, particularly the aquatic biota of conservation importance,
during construction stages and operational phase maintenance works (such as regular
desilting and dredging) so as
to reduce the water and sediment quality impacts to within standards,
objectives and criteria established in (iv) above. Best management practices
shall be recommended to reduce any potential impacts arising from site and stormwater runoff during both
construction and operation phases.
(xi)
Establishment
of the erosion control plan during construction as per assessment carried out
in point (x) above. This erosion control plan shall incorporate details such as
locations, sizes and types of best management practices, which will be used to
reduce stormwater pollution arising from construction works.
(xii)
In case of small scale dredging
works and with the prior written approval by the Director, the Applicant shall
assess the potential increase in turbidity and suspended solids levels in the
water column due to disturbance of marine sediments during dredging. The
potential for release of contaminants during dredging shall also be addressed
using the chemical testing results derived from sediment samples collected on
site and relevant historic dataThe Applicant shall assess the pattern of the
sediment deposition and the potential increase in turbidity and suspended
solids levels in the water column due to the disturbance of sediments during dredging. The potential for
the release of contaminants during dredging shall also be addressed using the
chemical testing results derived from sediment samples collected on site and
relevant historic data.
In
case of large scale dredging works, the Applicant in addition to the above
assessment shall conduct a full scale mathematical modelling which include
simulating situation during various construction phases and upon completion of
dredging, assessing both the local and global effects on flow regime, erosion
and sediment pattern and water quality due to the interim and ultimate
alteration of shoreline and bathymetry as a result of dredging marine sediment.
The modelling assessment shall take into account the additional pollution loading
and oxygen demand exerted by sediment disturbed and any fill materials. The
mathematical modelling requirements are set out in Annex I attached to this
study brief;
(xiii)
The Applicant shall
identify whether the discharge of runoff into the Shenzhen River and Inner Deep
Bay during the operational phase will give rise to adverse impacts on water
quality in accordance with the TM.
The Applicant shall evaluate any water quality impacts, including
changes in sediment erosion or deposition pattern, downstream salinity profile
and effect on aquatic organisms.
This assessment shall have regard for the frequency, duration, volume
and flow rate of the discharge and its pollutant and sediment load.
(xiv)
The Applicant shall
assess the effect of the blackish tidal influence from Inner Deep Bay/Shenzhen
River, propose mitigation measures such as tidal barriers/flow management
devices and evaluate the environmental benefits/dis-benefits of mitigation
measures.
Waste Water and Non-point Sources Pollution
(xv)
Proposals for effective
and practicable infrastructure upgrading or provision, water pollution
prevention and mitigation measures to be implemented during the construction
and operational stages to reduce the water quality impacts to within acceptable
levels of standards. Requirements
to be incorporated in the Project contract document shall also be proposed.
(xvi)
Evaluation and
quantification of residual impacts on the water system(s) and the sensitive
receivers with regard to the appropriate water quality criteria, standards or
guidelines.
Protection
Against Accidental Spillage
(xvii) Specification of an emergency contingency
plan for the construction and operation phase of the proposed Project to
contain and remove all accidental spillage along the channel maintenance road(s)/haul
road(s) at short notice and to prevent or to minimize the quantities of
contaminants from the stream water and sensitive habitats.
3.4.4 Waste Management Implications
3.4.4.1 The
Applicant shall follow the criteria and guidelines for evaluating and assessing
waste management implications as stated in Annexes 7 and 15 of the TM,
respectively.
3.4.4.2 The
assessment of waste management implications shall cover the following:
(i) Analysis of
Activities and Waste Generation
Identification of the quantity, quality
and timing of the waste arising as a result of the construction and operation
activities, based on the sequence and duration of these activities.
(ii) Should dredging be required,
the Applicant shall evaluate and quantify the possible impacts arising from the
dredging works. The Applicant shall identify clearly the nature, extent and
rate of the dredging works, and the volume of sediment disturbed. Appropriate
laboratory tests such as elutriate tests (USACE) and sediment pore water
(interstitial water) analyses shall be performed on the sediment samples to
simulate and quantify the degree of mobilization of various contaminants such
as metals, ammonia, trace organic contaminants and chlorinated pesticides into
the water column during dredging. Identification
and quantification of all dredging, fill extraction, filling, mud/sediment
transportation and disposal activities and requirements. Potential fill source and dumping
ground to be involved shall also be identified. Field investigation, sampling and chemical and biological
laboratory tests to characterize the sediment/mud concerned shall be conducted
as appropriate. The ranges of
parameters to be analyzed; the number, type and methods of sampling; sample
preservation; chemical and biological laboratory test method; and the
laboratory to be used shall be subject to the approval of the Director. Any seriously contaminated sediment
which requires special treatment and/or disposal arrangement in accordance with
WBTC No.3/2000 shall be identified by both chemical and biological tests. If the presence of such sediment is
confirmed, the Applicant shall identify the most appropriate treatment and/or
disposal arrangement and demonstrate its feasibility. Identification
and quantification of all dredging, fill extraction, filling, mud/sediment
transportation and disposal activities and requirements. Potential fill source and dumping
ground to be involved shall also be identified. Field
investigation, sampling and chemical and biological laboratory tests to
characterize the sediment/mud concerned shall be conducted as appropriate. The ranges
of parameters to be analyzed; the number, type and methods of sampling; sample
preservation; chemical and biological laboratory test method to be used shall
be subject to the approval of the Director.
The categories of sediments
which require different types of disposal in accordance with WBTC No.3/2000
shall be identified by both chemical and biological tests, and their quantities
estimated. If the presence of any
seriously contaminated sediment which requires Type 3 disposal is confirmed,
the Applicant shall identify the most appropriate treatment and/or disposal
arrangement and demonstrate its feasibility. Identification
and evaluation of the best practicable dredging methods to minimize dredging
and dumping requirements and demand for fill sources based on the criterion
that existing marine mud shall be left in place and not to be disturbed as far
as possible.
(ii) Proposal for Waste Management
(a) Prior to considering the
disposal options for various types of wastes, opportunities for reducing waste
generation and on-site or off-site re-use shall be fully evaluated. Measures, which can be taken in the
planning and design stages e.g. by modifying the design approach and in the
construction stage for maximizing waste reduction shall be separately
considered.
(b) After considering all the
opportunities for reducing waste generation and maximizing re-use, the types
and quantities of the wastes, required to be disposed of as a consequence shall
be estimated and the disposal options for each type of waste shall be described
in detail. Pre-treatment processes for slurry before disposal shall be
addressed in details. The disposal
method recommended for each type of waste shall take into account the result of
the assessment in (c) below.
(c) The impact caused by handling
(including labeling, packaging & storage), collection, and disposal of
wastes shall be addressed in detail and appropriate mitigation measures
proposed. This assessment shall
cover the following aspects:
- potential hazard;
- air and odour
emissions;
- noise emission;
-
wastewater discharge (including but not limited to the run off of pollutant
from the storage of extract/fills materials under heavy rain); and
- public transport.
(iii) Land
Contamination Assessment:
(a)
If land lots/sites
within the study area boundary, due to their past or present land uses, are assessed
to be potentially contaminated, a detailed account of the present activities
and past land history in relation to possible land contamination shouldshall be provided.
(b)
The list of potential
contaminants which are anticipated to be found in these potential contaminated
sites shouldshall be provided and
the possible remediation options shouldshall be discussed.
3.4.5. Ecological Impact
(Both Terrestrial and Aquatic) Assessment [Except LYT04]
3.4.5.1.
The
Applicant shall follow the criteria and guidelines for evaluating and assessing
ecological impacts as stated in Annexes 8 and 16 of the TM, respectively. The assessment area for the purpose of
terrestrial ecological assessment shall include all areas within 500m distance,
from the site boundary of the proposed works areas, and the area likely to be impacted
by the drainage channels at Lin Ma Hang (LMH01) and Loi Tung, Man Uk Ping
(MUP03, MUP04A, MUP04B, MUP05).
For aquatic ecology, the assessment area shall be the same as for water
quality assessment described in Section 3.4.3.2.
3.4.5.2.
In the
ecological impact assessment, the Applicant shall examine the flora, fauna and
other components of the ecological habitats within the assessment area. The aim shall be to avoid direct and
indirect impact, protect, maintain or rehabilitate the natural
environment. The assessment shall
identify and quantify as far as possible the potential ecological impacts
associated with the Project, including the impacts of any haul roads and
temporary access. The potential
impact on water quality and aquatic ecology from the discharge of stormwater
into the Shenzhen River and Inner Deep Bay waters during the operational phase,
shall also be addressed.
3.4.5.3.
The
assessment shall include the following:
(i)
A review
of the findings of relevant studies and collating all the available information, including but not limited to
the fresh water fish
species in Lin Ma Hang stream as listed in Annex 1,
regarding the ecological characters of the assessment area.
(ii)
Evaluation
of the information collected and identification of any information gap relating
to the assessment of potential ecological impacts to the terrestrial and
aquatic environment.
(iii)
Carrying
out the necessary field surveys [the duration of which shall be at least 12
months (four
seasons) and shall cover the wet and dry seasons] and investigations to verify
the information collected, fill the information gaps identified and fulfil the
objectives of the EIA study.
(iv)
Establishing
the general ecological profile and describing the characteristics of each
habitat found; major information to be provided shall include:
(a)
Description
of the physical environment.
(b) Preparation of habitat maps of suitable scale
(1:1000 to 1:5000) showing the types and locations of habitats in the
assessment area.
(c) Definition and characterization of the
ecological characteristics of each habitat type including size, vegetation
type, species present, dominant species found, species diversity and abundance,
community structure, seasonality and inter-dependence of the habitats and
species, and presence of any features of ecological importance and species of conservation
of important.
(d)
Presentation
of representative colour photos of each habitat type and of any important
ecological features identified.
(e) Listing of species found that are rare,
endangered and/or listed under local legislation, international conventions for
conservation of wildlife/habitats or red data books.
(v)
Investigation
and description of the existing wildlife uses of relevant habitats with special
attention to those wildlife groups and habitats of conservation interest;
including country parks, special areas, sites of special scientific interest,
mangrove stands, wetlands, natural stream courses, rivers, woodlands and shrublands;
vertebrates, macroinvertebrates, and any other habitats and wildlife groups
identified as having special conservation interests by this EIA study.
(vi)
Description
of all recognized sites of conservation importance in the proposed development
site and its vicinity and assessment of whether these sites will be affected by
the proposed development or not.
(vii)
Using
suitable methodology, identification and quantification as far as possible of
any direct, indirect, on-site, off-site, primary, secondary and cumulative
ecological impacts such as destruction of habitats, disturbance to wildlife,
reduction of species abundance/diversity, loss of feeding grounds,
reduction of ecological carrying capacity, habitat fragmentation; and in
particular the following:;
(a)
The
habitat loss and disturbance to wildlife and aquatic life during the construction
stage, for example the assessment shall assess (i) the construction impacts on the freshwater fish
in the stream courses and the associated water systems in the vicinity, (ii) the impacts due to the
loss of foraging ground of bats, in particular those inhabit the nearby Lin Ma
Hang Lead Mine and iii) the noise impacts of the proposed construction
works on waterfowl in the area.
(b)
operational impacts on stream ecological conditions, aquatic life
and other wildlife through any changes in the flow regimeperiodic
storm discharges at the portal.Operational impacts on the stream and their riparian
habitats, aquatic life and other wildlife (such as barking deer, fish-eating
bat, woodcock and frogs) therein due to any changes in the ecological
conditions of the habitats and flow regime.;
(c)
Impacts due to
maintenance works (such as regular desilting and dredging) on stream habitatas, aquatic life and flow
regime.
(d)
Cumulative
impacts due to other proposed development projects in the vicinity, for
example, the proposed extension of NENT landfill site.
(viii)
Evaluation
of the significance and acceptability of the ecological impacts identified
using well-defined criteria.
(ix)
Recommendations
for all possible alternatives, such as modifications of route alignment, layout
and design and practicable mitigation measures to avoid, minimize and/or
compensate for the adverse ecological impacts identified, such as reinstatement
of habitats temporarily affected by the proposed development to its original
state and if possible with some enhancement features.
(x)
Evaluation
of the feasibility and effectiveness of the recommended mitigation measures and
definition of the scope, type, location, implementation arrangement, resources
requirement, subsequent management and maintenance of such measures.
(xi)
Determination
and quantification as far as possible of the residual ecological impacts after
implementation of the proposed mitigation measures;
(xii)
Evaluation
the severity and acceptability of the residual ecological impacts using
well-defined criteria.
(xiii)
A review
of the need for and recommendation for any ecological monitoring programme
required.
3.4.6
Landscape and Visual
Impact
3.4.6.1
The Applicant shall
follow the criteria and guidelines as stated in Annexes 10, 11, and 18, 20 and 21 of the
Technical Memorandum and
the Guidance Notes EIAO No. 8/2002 on the preparation of Landscape and Visual
Impact Assessment under the EIAO.for evaluating and assessing
landscape arid visual impacts of any above ground structures and
work areas associated with the proposed project. Landscape and
visual impacts during both construction and operation phases within the Study
Area shall be assessed.
3.4.6.2
The assessment area for landscape impact assessment shall include all
areas within a 500m distance from the Project while the assessment area for the
visual impact assessment shall be defined by the visual envelope of the Project.
3.4.6.3
The Applicant
shall review
relevant outline development plan(s), outline zoning plan(s), layout plan(s) or
planning briefs and studies which may identify areas of high landscape value
and recommend green belt and conservation area designations. The aim is to gain
an insight to the future outlook of the area affected so as to assess whether
the Project can fit into the surrounding setting. Any conflict with statutory
town plan(s) shouldshall be highlighted and appropriate
follow-up action shouldshall be recommended.
3.4.6.4
The Applicant shall describe, appraise, analyze and evaluate the
existing landscape resources and character of the assessment area. A system shouldshall be derived for
judging landscape and visual impact significance as required under the TM. The
sensitivity of the landscape framework and its ability to accommodate change
shall be particularly focused on. The Applicant shall identify the degree of
compatibility of the Project with the existing and planned landscape setting.
The landscape impact assessment shall quantify the potential landscape impact
as far as possible so as to illustrate the significance of such impacts arising
from the proposed development. Clear mapping of the landscape impact is
required. A tree survey shall be carried out and the impacts on existing mature
trees shall be addressed.
3.4.6.5
The Applicant shall assess the visual impacts of
the proposed Project. Clear illustration including mapping of visual impact is
required. The assessment shall include the following:
(i) Identification
and plotting of visual envelope of the proposed Project within the assessment
area.
(ii) Identification
of the key groups of sensitive receivers within the visual envelope with regard
to views from both ground level and elevated vantage points.
(iii) Description
of the visual compatibility of the proposed Project such as channel wall,
possible inflatable dam and associated pumping station with the surrounding and
the planned setting, and its obstruction arid interference with key views of
the adjacent areas.
(iv) The
severity of visual impacts in terms of distance, nature and number of sensitive
receivers shall be identified. The visual impacts of the proposed Project with
and without mitigation measures shall be included so as to demonstrate the
effectiveness of the proposed mitigation measures.
3.4.6.6
The Applicant shall evaluate the merits of
preservation in totality, in parts of total destruction of existing landscape.
In addition, alternative alignment design and construction method that would
avoid or reduce the landscape and visual impact shall be evaluated for
comparison before adopting other mitigation or compensatory measures to alleviate
the impacts. The mitigation measures proposed shall not only be concerned with
damage reduction but shouldshall also include consideration of potential
enhancement of existing landscape. The Applicant shall recommend mitigation
measures to minimize the adverse effects identified above, including provision
of a landscape design.
3.4.6.7
The mitigation measures shall also include the
preservation of vegetation, transplanting of mature trees, provision of screen
planting, re-vegetation of disturbed lands, compensatory planting, design of
structure, provision of finishes to structure, colour scheme and texture of
material used and any measures to mitigate the disturbance of the existing land
use. Parties shall be identified for the on going management and maintenance of
the proposed mitigation works to ensure their effectiveness throughout the
operation phase of the Project. A practical programme and funding proposal for
the implementation of the recommended measures shall be provided.
3.4.6.8
Colour perspective drawing, plans and
section/elevation diagrams, annotated oblique aerial photographs, photographs
taken at vantage points, and computer-generated photomontage shall be adopted
to illustrate the landscape and visual impacts of the proposed Project to the
satisfaction of the Director. The Applicant shall record the technical details
in preparing the illustration, which may need to be submitted for verification
of the accuracy of the illustration.
3.4.7
Impact
on Cultural Heritage (For Designated Project LYT04 only)
3.4.7.1
The Applicant shall
carry out cultural heritage impact assessment of the designated pProjects,
in particular at the drainage channel (LYT04), LYT04 in accordance with. The Applicant
shall follow the criteria and guidelines for evaluating and assessing the
cultural heritage impacts as stated in Annexes 10 and Annex 19 of the TM,
respectively.
3.4.7.2
The heritage impact assessment
information shall include the following:
(i)
The Applicant shall identify all sites of
cultural heritage that might be adversely affected by the impacts due to
vibration associated with the construction activities of the designated
projects. The EIA study shall
establish a comprehensive inventory of archaeological sites, historic buildings
and structures located within or in close proximity to the designated project
area, that might have the potential to be affected. A plan showing the location
of both the proposed works and all sites of cultural heritage identified is
required. Besides, a check list including all the affected sites of cultural
heritage, impacts identified, recommended mitigation measures as well as the
implementation agent and period shall also be included in the EIA report.
(ii)
The Applicant shall assess the extent to
which those sites of cultural heritage might be directly and indirectly
affected and recommend possible alternatives (such as modification of layout
and design of the project) and practicable monitoring and mitigation measures
to avoid or keep the adverse impacts on the site of cultural heritage to the
minimum.
(iii) Special
attention shall be paid to the sites of cultural heritage in the vicinity of
the Project including the following monument.
l
The
Entrance Tower of Ma Wat Wai at Lung Yeuk Tau.
(iv) A
map in 1:1000 scale indicating the boundary of the identified built heritage
and declared monuments together with the nearby work areas in proper scale
shall be made.
In the event
that supplementary studies are needed and are agreed by the Director, the
Applicant can draw necessary reference to Annex II on the “Criteria for
Cultural Heritage Impact Assessment” and “Requirements of Built Heritage Impact
Assessment (BHIA)”.
4.
ENVIRONMENTAL
MONITORING & AUDIT (EM&A) REQUIREMENTS
4.1
The Applicant shall identify in the EIA
study whether there is any need for EM&A activities during the construction
and operation phases of the Project and, if affirmative, to define the scope of
the EM&A requirements for the Project in the EIA study.
4.2
Subject to the confirmation of the EIA
study findings, the Applicant shall comply with the requirements as stipulated
in Annex 21 of the TM. The
Applicant shall also propose real-time reporting of monitoring data for the
Project through a dedicated internet website.
4.3
The Applicant shall prepare a project
implementation schedule (in the form of a checklist) containing all the EIA
study recommendations and mitigation measures with reference to the
implementation programme.
5.
SUMMARY
OF ENVIRONMENTAL OUTCOMES
5.1
The EIA report shall contain a summary of
the key environmental outcomes arising from the EIA study, including the
population and environmentally sensitive areas protected, environmentally
friendly designs recommended, key environmental problems avoided, and
environmental benefits of environmental protection measures recommended.
6.
DURATION
OF VALIDITY
6.1
This EIA study brief is valid for 36
months after the date of issue. If
the EIA study does not commence within this period, the Applicant shall apply
to the Director for a fresh EIA study brief before commencement of the EIA
study.
7.
REPORT
REQUIREMENTS
7.1
In preparing the EIA report, the Applicant
shall refer to Annex 11 of the TM for the contents of an EIA report. The
Applicant shall also refer to Annex 20 of the TM, which stipulates the
guidelines for the review of an EIA report.
7.2
The Applicant shall supply the Director
with the following number of copies of the EIA report and the executive
summary:
(i)
50 sets copyies of the EIA report (in English and Chinese) and 80 sets copyies of the
executive summary (each bilingual in both English and
Chinese) as required under section 6(2) of the EIAO to be supplied at the time
of application for approval of the EIA report.
(ii)
When necessary, any addendum to the EIA
report and the executive summary submitted in (i) above as required under section 7(1) of the EIAO, to be supplied upon
advice by the Director for public inspection.
(iii)
20 sets copycopies of the EIA
report (in English
and Chinese) and 50
copies of the executive summary (each bilingual in both English and
Chinese) with or without Addendum as required under section 7(5) of the EIAO,
to be supplied upon advice by the Director for consultation with the Advisory
Council on the Environment.
7.3
The Applicant shall, upon request, make
additional copies of the above documents available to the public, subject to
payment by the interested parties of full costs of printing.
7.4
In addition, to facilitate the public
inspection of the EIA Report via the EIAO Internet Website, the Applicant shall
provide electronic copies of both the EIA Report and the Executive Summary
Report prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and
in Portable Document Format (PDF) version 4.0 or later), unless otherwise
agreed by the Director. For the
HTML version, a content page capable of providing hyperlinks to each section
and sub-section of the EIA Report and the Executive Summary Report shall be
included in the beginning of the document. Hyperlinks to all figures, drawings and tables in the EIA Report
and Executive Summary shall be provided in the main text from where the
respective references are made. All
graphics in the report shall be in interlaced GIF format unless otherwise
agreed by the Director.
7.5
The electronic copies of the EIA report
and the Executive Summary shall be submitted to the Director at the time of
application for approval of the EIA Report.
7.6
When the EIA Report and the Executive
Summary are made available for public inspection under section 7(1) of the
EIAO, the content of the electronic copies of the EIA Report and the Executive
Summary must be the same as the hard copies and the Director shall be provided
with the most up to date electronic copies.
7.7
To promote environmentally friendly and
efficient dissemination of information, both hard copies and electronic copies
of future EM&A reports recommended by the EIA study shall be required and
their format shall be agreed by the Director.
8.
OTHER
PROCEDURAL REQUIREMENTS
8.1
If there is any change in the name of the
Applicant for this EIA study brief, the Applicant mentioned in this study brief
must notify the Director immediately.
8.2
If there is any key change in the scope
of the project mentioned in section 1.2 and 1.3 of this EIA study brief and in
the Project Profile (No. PP-168/2002), the Applicant must seek confirmation
from the Director in writing on whether or not the scope of issues covered by
this EIA study brief can still cover the key changes, and the additional
issues, if any, that the EIA study must also address. If the changes to the project fundamentally alter the key
scope of the EIA study brief, the Applicant shall apply to the Director for a
fresh EIA study brief.
JuneMay 2002
Environmental Assessment and Noise
Division
Environmental Protection Department
Annex I
Water Quality Modelling
Requirements
1. The modelling software shall be fully 3-dimensional
capable of accurately simulating the stratified condition, salinity transport,
and effect of wind and tide within the model area.
2. The modelling software shall consist of hydrodynamic and
particle dispersion modules.
The hydrodynamic module shall have been proven with successful applications
locally and overseas.
Annex 1 |
Figure 1 |
Figure 2 |
Figure 3 |
Figure 4