Environmental Impact Assessment Ordinance (Cap. 499),
Section 5(7)
Environmental Impact Assessment Study Brief No. ESB-133/2005
Project Title : LAMMA
POWER STATION UNITS L4 & L5
FLUE GAS DESULPHURIZATION PLANT RETROFIT PROJECT
(hereinafter
known as the "Project")
Name of Applicant
: THE HONGKONG
ELECTRIC CO., LTD.
(hereinafter
known as the "Applicant")
1. BACKGROUND
1.1 An application (No.
ESB-133/2005) for an Environmental Impact Assessment (EIA) study brief under
section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was
submitted by the Applicant on 21 September 2005 with a Project Profile (No.
PP-261/2005) (the Project Profile).
1.2
The
proposed Project is to retrofit two existing 350MW coal-fired generating units,
namely L4 and L5, of the Lamma Power Station with Flue Gas Desulphurization
(FGD) plant for reducing the overall sulphur dioxide emission from the Lamma
Power Station. It is proposed to adopt the “Wet Limestone- Gypsum” process for
the FGD plants. Location of the Project is given in the Figure No. 2.4a of the
Project Profile and is reproduced in Appendix A.
1.3
The
scope of the Project includes the following major works:
-
Installation
of FGD plants with FGD efficiency of 90% for the two 350MW coal-fired Units L4
and L5 by adding the followings equipments :
s
Two
sets of FGD absorbers and associated ductworks;
s
Two
sets of booster fans;
s
Two
sets of gas-gas heaters;
s
FGD
Switchgear and Equipment Building; and
s
Gypsum
dewatering system comprising two sets of hydrocyclones and belt filters; and
-
Demolition
of the existing Numbers 4 and 5 Light Oil Tanks, each of 250m3
capacity, and relocation of some pipeworks to provide areas for the
installation of FGD plants.
1.4
The
Project is a material change to an exempted designated project, the Lamma Power
Station as a Public Utility Electricity Power Plant (Item D.1 Part I Schedule
2 of the EIAO), under the EIAO because of the changes induced by the FGD
operations to the types and quantities of emissions, wastes and effluents. In
addition, the demolition of two existing Light Oil Tanks is a designated
project under item 16 Part II (Decommissioning Projects) Schedule 2 of
the EIAO (i.e. A store for oil with a storage capacity exceeding 200 tonnes).
1.5
Pursuant
to section 5(7)(a) of the EIAO, the Director of Environmental Protection (the
Director) issues this EIA study brief to the Applicant to carry out an EIA
study.
1.6
The purpose of this EIA study
is to provide information on the nature and extent of environmental impacts
arising from the construction, operation and decommissioning of the Project and
related activities that take place concurrently. This information will
contribute to decisions by the Director on:
(i) the overall
acceptability of any adverse environmental consequences that is to arise as a
result of the Project and the associated activities of the Project;
(ii)
the
conditions and requirements for the detailed design, construction, operation and decommissioning of the
Project to mitigate against adverse environmental consequences; and
(iii)
the
acceptability of residual impacts after the proposed mitigation measures are
implemented.
2. OBJECTIVES
OF THE EIA STUDY
2.1 The
objectives of the EIA study are as follows:
(i)
to
describe the Project and associated works together with the requirements and
environmental benefits for carrying out the Project;
(ii)
to
identify if there are other types of Designated Projects under Schedule 2 of
the EIAO to be covered in the Project;
(iii)
to identify and describe the elements of the
community and environment likely to be affected by the Project and/or to likely
cause adverse impacts to the Project, including both the natural and man-made
environment and the associated environmental constraints;
(iv)
to identify and quantify emission sources and
determine the significance of impacts on sensitive receivers and potential
affected uses;
(v)
to identify and quantify any potential land
contamination caused, to determine the significance of the impact and to
propose measures to mitigate the impact;
(vi)
to propose the provision of infrastructure or
mitigation measures to minimize pollution, environmental disturbance and
nuisance during construction, operation and decommissioning of the Project;
(vii)
to investigate the feasibility, practicability,
effectiveness and implications of the proposed mitigation measures;
(viii)
to identify, predict and evaluate the residual
environmental impacts (i.e. after practicable mitigation) and the cumulative
effects expected to arise during the construction, operation and
decommissioning phases of the Project in relation to the sensitive receivers
and potential affected uses;
(ix)
to identify, assess and specify methods,
measures and standards, to be included in the detailed design, construction,
operation and decommissioning of the Project which are necessary to mitigate
these environmental impacts and cumulative effects and reduce them to
acceptable levels;
(x)
to investigate the extent of the secondary
environmental impacts that may arise from the proposed mitigation measures and
to identify constraints associated with the mitigation measures recommended in
the EIA study, as well as the provision of any necessary modification; and
(xi)
to design and specify the environmental
monitoring and audit requirements to ensure the effective implementation of the
recommended environmental protection and pollution control measures.
3. DETAILED
REQUIREMENTS OF THE EIA STUDY
3.1 The
Purpose
The
purpose of this study brief is to scope the key issues of the EIA study and to
specify the environmental issues that are required to be reviewed and assessed
in the EIA report. The Applicant
has to demonstrate in the EIA report that the criteria in the relevant sections
of the Technical Memorandum on the Environmental Impact Assessment Process of
the Environmental Impact Assessment Ordinance (hereinafter referred to as “the
TM”) are met.
3.2 The Scope
The
scope of this EIA study shall cover the Project proposed in the Project Profile
and shall include the works and facilities mentioned in Sections 1.2 and 1.3
above. The EIA study shall address
the key issues described below, together with any other key issues identified
during the course of the EIA study and the cumulative environmental impacts of
the Project, through interaction or in combination with other existing,
committed, planned and known potential developments in the vicinity of the
Project:
(i)
the hazards and environmental impacts associated
with the potential land contamination arising from demolition of the two
existing Numbers 4 and 5 Light Oil Tanks, and the secondary hazards and
environmental impacts that may arise from remediation of contaminated land;
(ii)
the potential air quality impacts, both positive
and negative, caused by the FGD plants during operation of the Project; and
(iii)
the potential water quality impact and waste
management implication caused by the FGD plants during operation of the
Project.
3.3 Consideration
of Alternatives
3.3.1 Need for the Project
The
Applicant shall present in the EIA the information on the need for and the
environmental benefits of the Project and the Project’s implementation
programme.
3.3.3 Consideration of
Alternative Construction/Decontamination Methods
Having regard to the findings of the land contamination
assessment, the EIA study shall explore alternative
construction/decontamination methods for the Project, with a view to avoiding
hazards and adverse environmental impacts to the maximum practicable extent. A
comparison of the environmental benefits and dis-benefits of applying different
construction/decontamination methods shall be made with a view to recommending
the preferred methods to avoid adverse on-site and off-site environmental
impact to the maximum practicable extent.
3.4 Technical
Requirements
The
Applicant shall conduct the EIA study to address the environmental aspects as
described in Sections 3.1, 3.2 and 3.3 above. The assessment shall be based on
the best and latest information available during the course of the EIA study.
The Applicant shall assess the cumulative environmental impacts from the
Project with other interacting projects. The Applicant shall include in the EIA
report details of the construction and decommissioning programme and
methodologies.
The Applicant
shall review previously studies or EIA reports which are relevant to the
Project and extract relevant information for the purpose of this EIA study. The
following studies or EIA reports shall be referred to :
-
Environmental Impact Assessment of Units L7 and
L8 Lamma Power Station (EIAO Register No. EIA-012/BC);
-
Environmental Impact Assessment of a 1,800MW
Gas-Fired Power Station at Lamma Extension (EIAO Register No. AEIAR-010/1999);
and
-
Project Profile - Lamma Power Station Conversion
of Two Existing Gas Turbines (GT5 and GT7) into a Combined Cycle Unit (EIAO
Register No. PP-093/2000)
The EIA study
shall meet the following technical requirements on specific impacts, unless
otherwise approved by the Director specifically in writing.
3.4.1 Land Contamination
3.4.1.1 The Applicant shall
follow the guidelines as stated in Sections 3.1 and 3.2 of Annex 19 in the TM
for evaluation and assessing potential land contamination issues due to
the demolition of the existing Light Oil Tanks and the relocation of pipeworks
of the Project, as stipulated in Section 1.3 above.
3.4.1.2 The Applicant shall provide a clear and
detailed account of the present land use (including description of the
activities, chemicals and hazardous substances handled with clear indication of
their storage and location by reference to a site layout plan), the relevant
past land use history in relation to possible land contamination (e.g. accident
records, etc.) and the presence of any contaminated materials.
3.4.1.3 The Applicant shall submit a contamination
assessment plan (CAP) to the Director for agreement prior to conducting a
contamination assessment of the site. The CAP shall include proposals on
sampling and analysis required and shall aim at determining the nature and
extent of the contamination of the site.
3.4.1.4 Based on the agreed CAP, the Applicant shall
conduct a land contamination assessment and compile a Contamination Assessment
Report (CAR) to document the findings and to confirm whether the site is
contaminated or not. If land contamination is confirmed, a remediation
action plan (RAP) shall be prepared to formulate in detail any necessary
remedial measures for management of the contaminated soil and materials.
3.4.1.5 The field investigation and sampling work
should be conducted in a safe and proper manner and the RAP shall provide
necessary measures for ensuring that the contaminated soil and materials will
be handled and managed in a safe and proper manner.
3.4.1.6 The Applicant shall prepare the CAP, CAR and,
if necessary, the RAP in accordance with ProPECC Practice Note No. 3/94
“Contaminated Land Assessment and Remediation” and other relevant guidance
notes.
3.4.1.7 The Applicant shall address any hazards and
environmental impacts associated with the potential land contamination, if
confirmed, and the secondary hazards and environmental impacts that may arise
from remediation and disposal of contaminated soil and materials. The
assumptions, methodology, data, findings, recommendations and conclusions of
CAP, CAR and, if necessary, the RAP shall be included in the EIA report.
3.4.2 Air Quality Impact
3.4.2.1 The Applicant shall follow the criteria and guidelines as stated in
Section 1 of Annex 4 and Annex 12 of the TM for evaluating and assessing the
air quality impact due to the operation of the Project, as stipulated in
Sections 1.2 and 1.3 above.
3.4.2.2 As stipulated in Section 1.2 above, the Project is for reducing the
overall sulphur dioxide emission from the Lamma Power Station. The Applicant
may carry out a comparative study to demonstrate if the stack emission impacts
of the coal-fired Units L4 & L5 before and after the Project will lead to
lower air quality impacts at the Air Sensitive Receivers (ASRs) including the
areas of Lamma Island, Cheung Chau as well as Southern District and Central
& Western District of Hong Kong Island by using either a simple screening
tool such as ISCST3 Gaussian model or a more sophisticated tool, such as wind
tunnel test, if necessary. If result of the comparative study shows that the air
quality impacts at ASRs are worsened, the air quality impact assessment
following the technical requirements as described in Section 3.4.2.5 below
shall be carried out to evaluate the cumulative impacts at the identified ASRs
against the criteria set out in section 1 of Annex 4 of the TM. The cumulative
assessment for the stack emission impact shall take into account the project
specific impacts together with a regional-wide emission impact for background
concentration.
3.4.2.3 The study area for air quality impact assessment shall generally be
defined by a distance of 500 metres from the boundary of the project site, and
it shall be extended to include other areas that may have a bearing on the
environmental acceptability of the Project. For this Project, the assessment
shall include the existing and planned/committed air sensitive receivers within
the study area, areas of Lamma Island, Cheung Chau as well as Southern District
and Central & Western District of Hong Kong Island where the air quality
may be potentially affected by the Project. Such assessment shall be based on
the best available information at the time of the assessment.
3.4.2.4 The Applicant shall assess the air pollutant concentrations with
reference to the Guidelines for Local-Scale Air Quality Assessment Using Models
given in Appendices B1 – B3 or other methodology as agreed by the Director.
3.4.2.5 The air quality impact assessment shall include the following:
(i) Background and Analysis of Activities
(a)
Provide
background information relating to air quality issues relevant to the Project,
e.g. description of the types of activities of the Project that may affect air
quality during operation stage.
(b)
Present
background air quality levels in the assessment area for the purpose of
evaluating cumulative operational air quality impacts.
(c)
Consider
alternative modes of operation to minimize the operational air quality impact.
(ii) Identification of Air Sensitive Receivers
(ASRs) and Examination of Emission/ Dispersion Characteristics
(a) Identify and describe representative existing and
planned/committed ASRs that would be affected by the Project, including those
earmarked on the relevant Outline Zoning Plans, Development Permission Area
Plans, Outline Development Plans and Layout Plans. The Applicant shall select
the assessment points of the identified ASRs such that they represent the worst
impact point of these ASRs. A map showing the location and description
including name of buildings, their uses and height of the
selected assessment points shall be given. The separation distances of these
ASRs from the nearest emission sources shall also be given.
(b)
Provide
an exhaustive list of air pollutant emission sources within the Lamma Power
Station which are to have impact related to the Project based on the analysis
of the operational activities in Section 3.4.2.5(i) above. Apart from stack
emissions, it is also necessary to address any air quality issue due to
additional marine traffic emissions for transportation of materials including
limestone and gypsum. Besides, if the likely concurrent projects are identified
relevant, its possible emissions shall also be taken into account in the air
quality impact assessment. Confirmation of the validity of the assumptions and
the magnitude of the activities shall be obtained from the relevant parties and
documented.
(c)
Describe
any topographical and man-made features that may affect the dispersion
characteristics of the area.
(iii) Operational Phase Air Quality Impact
(a)
The Applicant shall assess the expected air pollutants, including gaseous emissions
and dust, at the identified ASRs based on an assumed reasonably worst-case
scenario. The evaluation shall be based on the strength of the emission sources
identified in Section 3.4.2.5(ii)(b) above. The Applicant shall follow the
methodology as described in Section 3.4.2.5 (iv) below when carrying out the
quantitative assessment.
(iv) Quantitative Assessment Methodology
(a) In choosing the types of models (such as physical
or numerical) to be used for quantitative assessment of the operational phase
air quality impact, the Applicant shall apply the general principles enunciated
in the modelling guidelines in Appendices B-1 to B-3 while making allowance for
the specific characteristics of the Project. The specific methodology must be
documented in such level of details (preferably with tables and diagrams) to
allow the readers of the assessment report to grasp how the model is set up to
simulate the situation at hand without referring to the model input files.
Details of the calculation of the emission rates of air pollutants for input
into the modelling shall be presented in the EIA report. The Applicant must
ensure consistency between the text description and the model files. In case of
doubt, prior agreement between the Applicant and the Director on the specific
modelling details should be sought.
(b)
The
Applicant shall identify the key/representative air pollutant parameters (types
of pollutants and the averaging time concentration) to be evaluated and provide
explanation for choosing these parameters for the assessment of the impact of
the Project.
(c)
If
the predicted air quality impacts at the ASRs are worsened by the Project, the
Applicant shall calculate the cumulative air pollutant concentrations at the
identified ASRs identified under Section 3.4.2.5(ii) above and compare these
results against the criteria set out in Section 1 of Annex 4 in the TM. The
predicted air quality impacts (both unmitigated and mitigated) shall be
presented in the form of summary table and pollution contours as appropriate,
to be evaluated against the relevant air quality standards and on any effect
they may have on the land use implications. If applicable, plans of a suitable
scale should be used to present pollution contour to allow buffer distance
requirements to be determined properly.
(v) Mitigation Measures for Non-compliance
The Applicant shall propose
remedies and mitigating measures where the predicted air quality impact exceeds
the criteria set in Section 1 of Annex 4 in the TM. If these measures will
result in any constraints on future land use planning outside the project site,
the Applicant shall liaise with the relevant government departments/authorities
and document the agreement in the EIA Report in order to demonstrate that the
proposed measures are feasible and practicable. The Applicant shall demonstrate
quantitatively that the residual impacts after incorporation of the proposed
mitigating measures will comply with the criteria stipulated in Section 1 of
Annex 4 in the TM.
(vii) Submission of Model Files
Input and output file(s) of
the model run(s) shall be submitted to the Director in electronic format.
3.4.3
Water
Quality Impact
3.4.3.1
The Applicant shall follow the criteria and
guidelines as stated in Annexes 6 and 14 of the TM for evaluating and assessing
water quality impacts arising
from the the Project.
3.4.3.2
The study area for this water quality assessment
shall cover the
Southern Water Control Zone (as shown in Appendix C) as designated under the
Water Pollution Control Ordinance (WPCO). This study area could be extended to
include other areas if they are found also being impacted during the course of
the EIA study and have a bearing on the environmental acceptability of the
Project.
3.4.3.3
The
Applicant shall identify and analyse physical, chemical and biological
disruptions of marine, fresh water or ground water system(s), catchment
area(s), storm water pipeline, submarine outfalls, and coastal water arising during construction and operation of the
Project. The water quality impact assessment shall cover major aspects of
concern which include impacts of demolition and relocation of existing facilities
with reference to the findings of the Land Contamination Assessment in Section
3.4.1 above and impacts of wastewater and effluent treatment and disposal
during operational stage of the Project.
3.4.3.4
The
Applicant shall include the following in the water quality impact assessment :
i)
collection and
review of background information on the existing and planned water system(s)
and the respective catchment(s) and sensitive receivers which might be affected
by the Project. Characterization of water and sediment quality of those
affected or potentially affected areas based on the collected information or
site surveys and tests as appropriate;
ii)
identification
and analysis of existing and planned future activities and beneficial uses
related to the water system(s) and identification of water sensitive receivers;
iii)
Establishment of pertinent water and sediment quality
objectives, criteria and standards for the water system(s) and sensitive
receivers in Sections 3.4.3.4 (i) and (ii) above;
iv)
identification, analysis and quantification of
existing and likely future water and sediment pollution sources and loading,
including point discharges and non-point sources to surface water runoff, spent
industrial wastewater from the Project and other process wastewater. If
appropriate, field investigation and laboratory tests shall be conducted. An
emission inventory on the quantities and characteristics of all these pollution
sources shall be provided;
v)
analysis of the provision and adequacy of existing
wastewater treatment plants and sewerage infrastructure and wastewater
management practices to treat and dispose of the wastewater identified in
Section 3.4.3.4 (iv) above;
vi)
assessment of the cumulative impacts due to other
related concurrent and planned projects, activities or pollution sources within
the Lamma Power Station;
vii)
proposals for upgrading or providing any effective
infrastructure, water pollution prevention and mitigation measures to be
implemented during the construction and operational stages so as to avoid and
reduce the water and sediment quality impacts, and to rectify any deficiencies
and potential problems as may be identified in Sections 3.4.3.4 (v) and (vi)
above, to within acceptable standards. Requirements to be incorporated in the
Project’s contract document shall also be proposed. Best management practices
to reduce storm water and non-point source pollution shall be investigated and
proposed as appropriate; and
viii)
evaluation and
quantification of residual impacts on the water system(s) and the sensitive
receivers with regard to the appropriate water and sediment quality objectives,
criteria and standards established in Section 3.4.3.4 (iii) above.
3.4.4 Waste
Management Implications
3.4.4.1 The Applicant shall follow the criteria and guidelines as stated in Annexes 7 and 15
of the TM for evaluating and assessing waste management implications arising from
the Project.
3.4.4.2
The assessment of
waste management implications shall cover the following:
(i) Analysis
of Activities and Waste Generation
The
Applicant shall identify the quantity, quality and timing of the waste and
chemical waste arising as a result of the construction and operation activities
of the Project.
(ii) Proposal
for Waste Management
(a)
Prior to
considering the disposal options for various types of wastes, opportunities for
reducing waste generation, on-site or off-site re-use and recycling shall be
evaluated. Measures which can be
taken in the planning and design stages, e.g. by modifying the design approach
and in the construction stage for maximizing waste reduction shall be
considered. Gypsum, the solid by-product arising from the
operation of the Project, shall be reused e.g. in cement manufacturing,
wallboard production, etc;
(b)
After considering
the opportunities for reducing waste generation and maximizing re-use, the
types and quantities of the wastes required to be disposed of as a consequence
shall be estimated and the disposal options for the wastes shall be described
in detail. The disposal options recommended for each type of wastes shall take
into account the result of the assessment in item (c) below; and
(c)
The impact caused
by handling (including stockpiling, labelling, packaging & storage),
collection, transportation and disposal of wastes shall be addressed in detail
and appropriate mitigation measures shall be proposed. This assessment shall
cover the following areas :
-
potential hazard;
-
air and odour
emissions;
-
noise; and
-
wastewater
discharge,
if any.
3.4.5
Noise
Impact
3.4.5.1
The
Applicant shall follow the criteria and guidelines as stated in Annexes 5 and
13 of the TM for evaluating and addressing the noise impacts arising from the
operational stage of the Project.
3.4.5.2
As
stipulated in Section 1.3 above, the Project involves equipments of much
smaller quantities and sizes as compared with other existing equipments in the
Lamma Power Station. It is envisaged that the Project will have insignificant
contribution to the cumulative operational noise of the Lamma Power Station.
The Applicant shall assess the expected operational noise arising from the
Project using standard acoustics principle and compare against the criteria set
out in Table 1A of Annex 5 of the TM. The Applicant shall propose direct
technical remedies within the project limits in situations where the predicted
noise level exceeds the criteria set out in Table 1A of Annex 5 of the TM.
3.4.6
Construction
Phase Air Quality and Noise Impacts
3.4.6.1 The Applicant shall follow the
requirements stipulated under the Air Pollution Control (Construction Dust)
Regulation to ensure that construction dust which may arise as a result of
construction works are controlled within the relevant standards as stipulated
in Section 1 of Annex 4 of the TM.
3.4.6.1
The
Applicant shall propose the good site practices and/or any other mitigation
measures to ensure that construction noise which may arise as a result of
construction works are controlled within the relevant objectives, criteria,
standards or guidelines.
3.4.7
Visual
Illustration
3.4.7.1
The Applicant shall provide layout plans,
elevations, sections in appropriate scale and with dimensions, perspective
drawings and photomontages to show the form, appearance and colour scheme of
the Project representative viewpoints.
3.4.8 Summary of
Environmental Outcomes
3.4.8.1 The EIA report shall contain a summary of
the key environmental outcomes arising from the EIA study, including the
environmental benefits of the Project, the population and environmentally
sensitive areas protected, environmentally friendly designs recommended, key
environmental problems avoided and the environmental benefits of environmental
protection measures recommended.
3.4.9 Environmental
Monitoring and Audit (EM&A) Requirements
3.4.9.1 The Applicant shall identify and
justify in the EIA study whether there is any need for EM&A activities
during construction and operation phases of the Project and, if affirmative, to
define the scope of EM&A requirements for the Project.
3.4.9.2 Subject to confirmation of EIA
findings, the Applicant shall comply with requirements as stipulated in Annex
21 of the TM. The Applicant shall also propose and justify the need of any
real-time reporting of monitoring data for the Project through a dedicated
internet website.
3.4.9.3 The Applicant shall prepare a
project implementation schedule (in the form of a checklist as shown in
Appendix D to this EIA study brief) containing the EIA study recommendations
and mitigation measures with reference to the implementation programme.
4. DURATION
OF VALIDITY
4.1 This EIA study brief is valid
for 36 months from the date of issue.
If the EIA study does not commence within this period, the Applicant
shall apply to the Director for a fresh EIA study brief before commencement of
the EIA study.
5. REPORT
REQUIREMENTS
5.1 In
preparing the EIA report, the Applicant shall refer to Annex 11 of the TM for
the contents of an EIA report. The Applicant shall also refer to Annex 20 of
the TM, which stipulates the guidelines for the review of an EIA report.
5.2 The
Applicant shall supply the Director with the following number of copies of the
EIA report and the executive summary:
(i) 50
copies of the EIA report in English and 80 copies of the executive summary
(each bilingual in both English and Chinese) as required under section 6(2) of
the EIAO to be supplied at the time of application for approval of the EIA
report.
(ii) when
necessary, addendum to the EIA report and the executive summary submitted in
5.2 (i) above as required under section 7(1) of the EIAO, to be supplied
upon advice by the Director for public inspection.
(iii) 20 copies
of the EIA report in English and 50 copies of the executive summary (each
bilingual in both English and Chinese) with or without Addendum as required
under section 7(5) of the EIAO, to be supplied upon advice by the Director for
consultation with the Advisory Council on the Environment.
5.3 The
Applicant shall, upon request, make additional copies of above documents
available to the public, subject to payment by the interested parties of full
costs of printing.
5.4 In addition, to facilitate
public inspection of the EIA report via the EIAO Internet Website, the
Applicant shall provide electronic copies of both the EIA report and the
executive summary prepared in HyperText Markup Language (HTML) (version 4.0 or
later) and in Portable Document Format (PDF version 4.0 or later), unless
otherwise agreed by the Director.
For the HTML version, a content page capable of providing hyperlink to
each section and sub-section of the EIA report and the executive summary shall
be included in the beginning of the document. Hyperlinks to all figures,
drawings and tables in the EIA report and executive summary shall be provided
in the main text from where the respective references are made. All graphics in the report shall be in
interlaced GIF format unless otherwise agreed by the Director.
5.5 The
electronic copies of the EIA report and the executive summary shall be
submitted to the Director at the time of application for approval of the EIA
report.
5.6 When the EIA report and the
executive summary are made available for public inspection under s.7(1) of the
EIAO, the content of the electronic copies of the EIA report and the executive
summary must be the same as the hard copies and the Director shall be provided
with the most updated electronic copies.
5.7 To promote
environmentally friendly and efficient dissemination of information, both
hardcopies and electronic copies of future EM&A reports recommended by the
EIA study shall be required and their format shall be agreed by the Director.
6. OTHER
PROCEDURAL REQUIREMENTS
6.1 If there is any change in the
name of Applicant for this EIA study brief during the course of the EIA study,
the Applicant must notify the Director immediately.
6.2
If
there is any key change in the scope of the Project mentioned in Sections 1.2
and 1.3 of this EIA study brief and in Project Profile (No. PP-261/2005), the
Applicant must seek confirmation from the Director in writing on whether or not
the scope of issues covered by this EIA study brief can still cover the key
changes, and the additional issues, if any, that the EIA study must also
address. If the changes to the
Project fundamentally alter the key scope of the EIA study brief, the Applicant
shall apply to the Director for a fresh EIA study brief.
--- END OF
EIA STUDY BRIEF ---
October 2005
Environmental
Assessment Division
Environmental
Protection Department
Appendix A
Appendix B-1
Guidelines on Choice of Models and Model Parameters
[The
information contained in this Appendix is only meant to assist the Applicant in
performing the air quality assessment.
The Applicant must exercise professional judgment in applying this
general information for the Project.]
1. Introduction
1.1 To expedite the review process
by the Authority and to assist project proponents or environmental consultants
with the conduct of air quality modelling exercise which are frequently called
for as part of environmental impact assessment studies, this paper describes
the usage and requirements of a few commonly used air quality models.
2.
Choice of Models
2.1 The models
which have been most commonly used in air quality impact assessments, due
partly to their ease of use and partly to the quick turn-around time for
results, are of Gaussian type and designed for use in simple terrain under
uniform wind flow. There are circumstances when these models are not suitable
for ambient concentration estimates and other types of models such as physical,
numerical or mesoscale models will have to be used. In situations where
topographic, terrain or obstruction effects are minimal between source and
receptor, the following Gaussian models can be used to estimate the near-field
impacts of a number of source types including dust, traffic and industrial
emissions.
Model
Applications
FDM for
evaluating fugitive and open dust source impacts (point, line and area sources)
CALINE4 for
evaluating mobile traffic emission impacts (line sources)
ISCST3 for
evaluating industrial chimney releases as well as area and volumetric sources
(point, area and volume sources); line sources can be approximated by a number
of volume sources.
These
frequently used models are also referred to as Schedule 1 models (see attached
list).
2.2
Note that both FDM and CALINE4 have a height
limit on elevated sources (20 m and 10m, respectively). Source of elevation
above these limits will have to be modelled using the ISCST3 model or suitable
alternative models. In using the latter, reference should be made to the
'Guidelines on the Use of Alternative Computer Models in Air Quality
Assessment' in Appendix B-3.
2.3
The models can be used to estimate both
short-term (hourly and daily average) and long-term (annual average) ambient
concentrations of air pollutants. The model results, obtained using Section 3)
and assumptions, allow direct comparison with the relevant air quality
appropriate model parameters (refer to standards such as the Air Quality
Objectives (AQOs) for the relevant pollutant and time averaging period.
3. Model
Input Requirements
3.1 Meteorological
Data
3.1.1 At least 1 year of recent
meteorological data (including wind speed, wind direction, stability class,
ambient temperature and mixing height) from a weather station either closest to
or having similar characteristics as the study site should be used to determine
the highest short-term (hourly, daily) and long-term (annual) impacts at
identified air sensitive receivers in that period. The amount of valid data for
the period should be no less than 90 percent.
3.1.2 Alternatively, the
meteorological conditions as listed below can be used to examine the worst case
short-term impacts:
Day
time:
stability
class D; wind speed 1 m/s (at 10m height); worst-case wind angle; mixing height
500 m
Night
time:
stability
class F; wind speed 1 m/s (at 10m height); worst case wind angle; mixing height
500 m
This
is a common practice with using the CALINE4 model due to its inability to
handle lengthy data set.
3.1.3 For situations where, for
example, (i) the model (such as CALINE4) does not allow easy handling of one
full year of meteorological data; or (ii) model run time is a concern, the
followings can be adopted in order to determine the daily and annual average
impacts:
(i)
perform
a frequency occurrence analysis of one year of meteorological data to determine
the actual wind speed (to the nearest unit of m/s), wind direction (to the
nearest 10o) and stability (classes A to F) combinations and their
frequency of occurrence;
(ii)
determine
the short term hourly impact under all of the identified wind speed, wind
direction and stability combinations; and
(iii)
apply
the frequency data with the short term results to determine the long term
(daily / annual) impacts.
Apart
from the above, any alternative approach that will capture the worst possible
impact values (both short term and long term) may also be considered.
3.1.4 Note that the anemometer
height (relative to a datum same for the sources and receptors) at which wind
speed measurements were taken at a selected station should be correctly entered
in the model. These measuring positions can vary greatly from station to
station and the vertical wind profile employed in the model can be grossly
distorted from the real case if incorrect anemometer height is used. This will
lead to unreliable concentration estimates.
3.1.5 An additional parameter,
namely, the standard deviation of wind direction, σΘ, needs to be provided as
input to the CALINE4 model. Typical values ofσΘ range from 12o
for rural areas to 24o for highly urbanised areas under 'D' class
stability. For semi-rural such as new development areas, 18o is more
appropriate under the same stability condition. The following reference can be
consulted for typical ranges of standard deviation of wind direction under
different stability categories and surface roughness conditions.
Ref.(1): Guideline On Air Quality Models (Revised), EPA-450/2-78-027R, United States Environmental Protection Agency, July 1986.
3.2 Emission
Sources
All
the identified sources relevant to a process plant or a study site should be
entered in the model and the emission estimated based on emission factors
compiled in the AP-42 (Ref. 2) or other suitable references. The relevant
sections of AP-42 and any parameters or assumptions used in deriving the
emission rates (in units g/s, g/s/m or g/s/m2) as required by the
model should be clearly stated for verification. The physical dimensions,
location, release height and any other emission characteristics such as efflux
conditions and emission pattern of the sources input to the model should also
correspond to site data.
If
the emission of a source varies with wind speed, the wind speed-dependent
factor should be entered.
Ref.(2): Compilation of Air Pollutant Emission Factors, AP-42, 5th Edition, United States Environmental Protection Agency, January 1995.
3.3 Urban/Rural
Classification
Emission
sources may be located in a variety of settings. For modelling purposes these
are classed as either rural or urban so as to reflect the enhanced mixing that
occurs over urban areas due to the presence of buildings and urban heat
effects. The selection of either rural or urban dispersion coefficients in a
specific application should follow a land use classification procedure. If the
land use types including industrial, commercial and residential uses account
for 50% or more of an area within 3 km radius from the source, the site is
classified as urban; otherwise, it is classed as rural.
3.4 Surface
Roughness Height
This
parameter is closely related to the land use characteristics of a study area
and associated with the roughness element height. As a first approximation, the
surface roughness can be estimated as 3 to 10 percent of the average height of
physical structures. Typical values used for urban and new development areas
are 370 cm and 100 cm, respectively.
3.5 Receptors
These
include discrete receptors representing all the identified air sensitive
receivers at their appropriate locations and elevations and any other discrete
or grid receptors for supplementary information. A receptor grid, whether
Cartesian or Polar, may be used to generate results for contour outputs.
3.6 Particle
Size Classes
In
evaluating the impacts of dust-emitting activities, suitable dust size
categories relevant to the dust sources concerned with reasonable breakdown in
TSP (< 30 μm) and RSP (< 10 μm) compositions should be used.
3.7 NO2
to NOx Ratio
The
conversion of NOx to NO2 is a result of a series of
complex photochemical reactions and has implications on the prediction of near
field impacts of traffic emissions. Until further data are available, three
approaches are currently acceptable in the determination of NO2:
(a)
Ambient Ratio Method (ARM) - assuming 20% of NOx
to be NO2; or
(b)
Discrete Parcel Method (DPM, available in the
CALINE4 model); or
(c)
Ozone Limiting Method (OLM) - assuming the
tailpipe NO2 emission to be 7.5% of NOx and the
background ozone concentration to be in the range of 57 to 68 μg/m3
depending on the land use type (see also the EPD reference paper 'Guidelines on
Assessing the 'TOTAL' Air Quality Impacts' in Appendix B-2).
3.8 Odour Impact
In
assessing odour impacts, a much shorter time-averaging period of 5 seconds is
required due to the shorter exposure period tolerable by human receptors.
Conversion of model computed hourly average results to 5-second values is
therefore necessary to enable comparison against recommended standard. The
hourly concentration is first converted to 3-minute average value according to
a power law relationship which is stability dependent (Ref. 3) and a result of
the statistical nature of atmospheric turbulence. Another conversion factor (10
for unstable conditions and 5 for neutral to stable conditions) is then applied
to convert the 3-minute average to 5-second average (Ref. 4). In summary, to
convert the hourly results to 5-second averages, the following factors can be
applied:
Stability
Category 1-hour
to 5-sec Conversion Factor
A
& B 45
C 27
D 9
E
& F 8
Under
‘D’ class stability, the 5-second concentration is approximately 10 times the
hourly average result. Note, however, that the combined use of such conversion
factors together with the ISCST results may not be suitable for assessing the
extreme close-up impacts of odour sources.
Ref.(3): Richard A. Duffee, Martha A. O’Brien and Ned Ostojic, ‘Odor Modeling – Why and How’, Recent Developments and Current Practices in Odor Regulations, Controls and Technology, Air & Waste Management Association, 1991.
Ref.(4): A.W.C. Keddie, ‘Dispersion of Odours’, Odour Control – A Concise Guide, Warren Spring Laboratory, 1980.
3.9 Plume Rise
Options
The
ISCST3 model provides by default a list of the U.S. regulatory options for
concentration calculations. These are all applicable to the Hong Kong
situations except for the 'Final Plume Rise' option. As the distance between
sources and receptors are generally fairly close, the non-regulatory option
of 'Gradual Plume Rise' should be
used instead to give more accurate estimate of near-field impacts due to plume
emission. However, the 'Final Plume Rise' option may still be used for assessing
the impacts of distant sources.
3.10 Portal Emissions
These
include traffic emissions from tunnel portals and any other similar openings
and are generally modelled as volume sources according to the PIARC 91 (or more
up-to-date version) recommendations (Ref. 5, section III.2). For emissions
arising from underpasses or any horizontal openings of the like, these are
treated as area or point sources depending on the source physical dimensions.
In all these situations, the ISCST3 model or more sophisticated models will
have to be used instead of the CALINE4 model. In the case of portal emissions
with significant horizontal exit velocity which cannot be handled by the ISCST3
model, the impacts may be estimated by the TOP model (Ref. 6) or any other suitable
models subject to prior agreement with EPD. The EPD’s 'Guidelines on the Use of
Alternative Computer Models in Air Quality Assessment' should also be referred
to in Appendix B-3.
Ref.(5):
XIXth World Road Congress Report, Permanent International Association of Road
Congresses (PIARC), 1991.
Ref.(6): N. Ukegunchi, H. Okamoto and Y. Ide "Prediction of vehicular emission pollution around a tunnel mouth", Proceedings 4th International Clean Air Congress, pp. 205-207, Tokyo, 1977.
3.10 Background Concentrations
Background
concentrations are required to account for far-field sources which cannot be
estimated by the model. These values, to be used in conjunction with model
results for assessing the total impacts, should be based on long term average of
monitoring data at location representative of the study site. Please make
reference to the paper 'Guidelines on Assessing the 'TOTAL' Air Quality
Impacts' in Appendix B-2 for further information.
3.11 Output
The
highest short-term and long-term averages of pollutant concentrations at
prescribed receptor locations are output by the model and to be compared
against the relevant air quality standards specified for the relevant
pollutant. Contours of pollutant concentration are also required for indicating
the general impacts of emissions over a study area.
Copies
of model files in electronic format should also be provided for EPD's
reference.
------------------------------------------------------------------------------------------------------
Schedule 1
Air Quality Models
Generally Accepted by
Hong Kong Environmental
Protection Department for
Regulatory Applications
as at 1 July 1998*
Industrial
Source Complex Dispersion Model - Short Term Version 3 (ISCST3) or the
latest version developed by U.S. Environmental Protection Agency
California
Line Source Dispersion Model Version 4 (CALINE4) or the latest version
developed by Department of Transportation, State of California, U.S.A.
Fugitive
Dust Model (FDM)
or the latest version developed by U.S. Environmental Protection Agency
* EPD
is continually reviewing the latest development in air quality models and will
update this Schedule accordingly.
Appendix B-2
Guidelines on Assessing the 'TOTAL' Air Quality Impacts
[The
information contained in this Appendix is only meant to assist the Applicant in
performing the air quality assessment.
The Applicant must exercise professional judgment in applying this
general information for the Project.]
1. Total
Impacts - 3 Major Contributions
1.1
In evaluating the air quality impacts of a
proposed project upon air sensitive receivers, contributions from three classes
of emission sources depending on their distance from the site should be
considered. These are:
Primary contributions: project
induced
Secondary
contributions: pollutant-emitting
activities in the immediate neighbourhood
Other contributions: pollution
not accounted for by the previous two
(Background
contributions)
2. Nature
of Emissions
2.1 Primary
contributions
In
most cases, the project-induced emissions are fairly well defined and quite
often (but not necessarily) the major contributor to local air quality impacts.
Examples include those due to traffic network, building or road construction
projects.
2.2 Secondary
contributions
Within
the immediate neighbourhood of the project site, there are usually pollutant
emitting activities contributing further to local air quality impacts. For most
local scale projects, any emission sources in an area within 500m radius of the
project site with notable impacts should be identified and included in an air
quality assessment to cover the short-range contributions. In the exceptional
cases where there is one or more significant sources nearby, the study area may
have to be extended or alternative estimation approach employed to ensure these
impacts are reasonably accounted for.
2.3 Background
contributions
The
above two types of emission contributions should account for, to a great
extent, the air quality impacts upon local air sensitive receivers, which are
often amenable to estimation by the 'Gaussian Dispersion' type of models.
However, a background air quality level should be prescribed to indicate the
baseline air quality in the region of the project site, which would account for
any pollution not covered by the two preceding contributions. The emission
sources contributing to the background air quality would be located further
afield and not easy to identify. In addition, the transport mechanism by which
pollutants are carried over long distances (ranging from 1km up to tens or
hundreds of kms) is rather complex and cannot be adequately estimated by the
'Gaussian' type of models.
3. Background
Air Quality - Estimation Approach
3.1 The
approach
In
view of the difficulties in estimating background air quality using the air
quality models currently available, an alternative approach based on monitored
data is suggested. The essence of this approach is to adopt the long-term
(5-year) averages of the most recent monitored air quality data obtained by
EPD. These background data would be reviewed yearly or biennially depending on
the availability of the monitored data. The approach is a first attempt to
provide a reasonable estimate of the background air quality level for use in
conjunction with EIA air quality assessment to address the cumulative impacts
upon a locality. This approach may be replaced or supplemented by superior
modelling efforts such as that entailed in PATH (Pollutants in the Atmosphere
and their Transport over Hong Kong), a comprehensive territory-wide air quality
modelling system currently being developed for Hong Kong. Notwithstanding this,
the present approach is based on measured data and their long term regional
averages; the background values so derived should therefore be indicative of
the present background air quality. In the absence of any other meaningful way
to estimate a background air quality for the future, this present background
estimate should also be applied to future projects as a first attempt at a
comprehensive estimate until a better approach is formulated.
3.2 Categorisation
The
monitored air quality data, by 'district-averaging' are further divided into
three categories, viz, Urban, Industrial and Rural/New Development. The
background pollutant concentrations to be adopted for a project site would
depend on the geographical constituency to which the site belongs. The
categorisation of these constituencies is given in Section 3.4. The monitoring
stations suggested for the 'district-averaging'(arithmetic means) to derive
averages for the three background air quality categories are listed as follows:
Urban: Kwun
Tong, Sham Shui Po, Tsim Sha Tsui and Central/Western
Industrial: Kwun
Tong, Tsuen Wan and Kwai Chung
Rural/New Development: Sha Tin,
Tai Po, Junk Bay, Hong Kong South and Yuen Long
The
averaging would make use of data from the above stations wherever available.
The majority of the monitoring stations are located some 20m above ground.
3.3 Background
pollutant values
Based
on the above approach, background values for the 3 categories have been
obtained for a few major air pollutants as follows:
POLLUTANT |
URBAN |
INDUSTRIAL |
RURAL / NEW
DEVELOPMENT |
NO2 |
59 |
57 |
39 |
SO2 |
21 |
26 |
13 |
O3 |
62 |
68 |
57 |
TSP |
98 |
96 |
87 |
RSP |
60 |
58 |
51 |
All
units are in micrograms per cubic metre. The above values are derived from 1992
to 1996 annual averages with the exception of ozone which represent annual
average of daily hourly maximum values for year 1996.
In
cases where suitable air quality monitoring data representative of the study
site such as those obtained from a nearby monitoring station or on-site
sampling are not available for the prescription of background air pollution
levels, the above tabulated values can be adopted instead. Strictly speaking, the suggested values
are only appropriate for long term assessment. However, as an interim measure
and until a better approach is formulated, the same values can also be used for
short term assessment. This implies that the short term background values will
be somewhat under-estimated, which compensates for the fact that some of the
monitoring data are inherently influenced by secondary sources because of the
monitoring station location.
Indeed,
if good quality on-site sampling data which cover at least one year period are
available, these can be used to derive both the long term (annual) and short
term (daily / hourly) background values, the latter are usually applied on an
hour to hour, day to day basis.
3.4 Site
categories
The
categories to which the 19 geographical constituencies belong are listed as
follows:
DISTRICT |
AIR QUALITY
CATEGORY |
Islands |
Rural / New
Development |
Southern |
Rural / New
Development |
Eastern |
Urban |
Wan Chai |
Urban |
Central
& Western |
Urban |
Sai Kung |
Rural / New
Development |
Kwun Tong |
Industrial |
Wong Tai
Sin |
Urban |
Kowloon
City |
Urban |
Yau Tsim |
Urban |
Mong Kok |
Urban |
Sham Shui
Po |
Urban |
Kwai Tsing |
Industrial |
Sha Tin |
Rural / New
Development |
Tsuen Wan |
Industrial |
Tuen Mun |
Rural / New
Development |
Tai Po |
Rural / New
Development |
Yuen Long |
Rural / New
Development |
Northern |
Rural / New
Development |
3.5 Provisions
for 'double-counting’
The
current approach is, by no means, a rigorous treatment of background air
quality but aims to provide an as-realistic-as-possible approximation based on
limited field data. 'Double-counting' of 'secondary contributions' may be
apparent through the use of such 'monitoring-based' background data as some of
the monitoring stations are of close proximity to existing emission sources.
'Primary contributions' due to a proposed project (which is yet to be realized)
will not be double-counted by such an approach. In order to avoid
over-estimation of background pollutant concentrations, an adjustment to the
values given in Section 3.3 is possible and optional by multiplying the
following factor:
(1.0 - ESecondary contributions/ETerritory)
where E stands for emission.
The
significance of this factor is to eliminate the fractional contribution to
background pollutant level of emissions due to 'secondary contributions' out of
those from the entire territory. In most cases, this fractional contribution to
background pollutant levels by the secondary contributions is minimal.
4. Conclusions
4.1 The above
described approach to estimating the total air quality impacts of a proposed
project, in particular the background pollutant concentrations for air quality
assessment, should be adopted with immediate effect. Use of short term
monitoring data to prescribe the background concentrations is no longer
acceptable.
Appendix B-3
[The
information contained in this Appendix is only meant to assist the Applicant in
performing the air quality assessment.
The Applicant must exercise professional judgment in applying this
general information for the Project.]
1. Background
1.1
In Hong Kong, a number of Gaussian plume models
are commonly employed in regulatory applications such as application for
specified process licences and environmental impact assessments (EIAs). These
frequently used models (as listed in Schedule 1 attached; hereafter referred to
as Schedule 1 models) have no regulatory status but form the basic set of tools
for local-scale air quality assessment in Hong Kong.
1.2
However, no single model is sufficient to cover
all situations encountered in regulatory applications. In order to ensure that
the best model available is used for each regulatory application and that a
model is not arbitrarily applied, the project proponent (and/or its
environmental consultants) should assess the capabilities of various models
available and adopt one that is most suitable for the project concerned.
1.3
Examples of situations where the use of an
alternative model is warranted include:
(i)
the
complexity of the situation to be modelled far exceeds the capability of the
Schedule 1 models; and
(ii) the
performance of an alternative model is comparable or better than the Schedule 1
models.
1.4 This
paper outlines the demonstration / submission required in order to support the
use of an alternative air quality model for regulatory applications for Hong
Kong.
2. Required
Demonstration / Submission
2.1 Any
model that is proposed for air quality applications and not listed amongst the
Schedule 1 models will be considered by EPD on a case-by-case basis. In such cases, the proponent will have
to provide the followings for EPD's review:
(i)
Technical details of the proposed model; and
(ii)
Performance evaluation of the proposed model
Based
on the above information, EPD will determine the acceptability of the proposed
model for a specific or general applications. The onus of providing adequate
supporting materials rests entirely with the proponent.
2.2 To
provide technical details of the proposed model, the proponent should submit
documents containing at least the following information:
(i)
mathematical formulation and data requirements
of the model;
(ii)
any previous performance evaluation of the
model; and
(iii)
a complete set of model input and output file(s)
in commonly used electronic format.
2.3
On performance evaluation, the required approach
and extent of demonstration varies depending on whether a Schedule 1 model is
already available and suitable in simulating the situation under consideration.
In cases where no Schedule 1 model is found applicable, the proponent must
demonstrate that the proposed model passes the screening test as set out in
USEPA Document "Protocol for Determining the Best Performing Model"
(Ref. 1).
2.4
For cases where a Schedule 1 model is applicable
to the project under consideration but an alternative model is proposed for use
instead, the proponent must demonstrate either that
(i)
the highest and second highest concentrations predicted
by the proposed model are within 2 percent of the estimates obtained from an
applicable Schedule 1 model (with appropriate options chosen) for all receptors
for the project under consideration; or
(ii)
the proposed model has superior performance
against an applicable Schedule 1 model based on the evaluation procedure set
out in USEPA Document
"Protocol for Determining the Best Performing Model" (Ref. 1).
2.5
Should EPD find the information on technical
details alone sufficient to indicate the acceptability of the proposed model,
information on further performance evaluation as specified in Sections 2.3 and
2.4 above would not be necessary.
2.6
If the proposed model is an older version of one
of the Schedule 1 models or was previously included in Schedule 1, the
technical documents mentioned in Section 2.2 are normally not required. However, a performance demonstration of
equivalence as stated in Section 2.4 (i) would become necessary.
2.7
If EPD is already in possession of some of the
documents that describe the technical details of the proposed model, submission
of the same by the proponent is not necessary. The proponent may check with EPD
to avoid sending in duplicate information.
-------------------------------------------------------------------------------------------------------
Schedule 1
Air Quality Models Generally Accepted by
Hong Kong Environmental
Protection Department for
Regulatory Applications
as at 1 July 1998*
Industrial
Source Complex Dispersion Model - Short Term Version 3 (ISCST3) or the
latest version developed by U.S. Environmental Protection Agency
California
Line Source Dispersion Model Version 4 (CALINE4) or the latest version
developed by Department of Transportation, State of California, U.S.A.
Fugitive Dust
Model (FDM) or the latest version developed by U.S. Environmental
Protection Agency
-------------------------------------------------------------------------------------------------------
Ref.
(1): William M. Cox, "Protocol
for Determining the Best Performing Model" Publication No.
EPA-454/R-92-025; U.S. Environmental Protection Agency, Research Triangle Park,
NC.
* EPD
is continually reviewing the latest development in air quality models and will
update this Schedule accordingly.
Appendix C
Appendix D
Implementation Schedule
EIA Ref. |
EM&A
Ref. |
Recommended
Mitigation Measures |
Objectives
of the Recommended Measure & Main
Concerns to address |
Who to
implement the measure ? |
Location of
the measure |
When to
implement the measure ? |
What
requirements or standards for the measure to achieve ? |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|