Construction Contracts in Operation (as at 1.10.2024)
PWP Item No. / Contract No. |
Project |
Location |
Contractor |
Contract Sum |
Date of Award |
Current Position |
Estimated Works Completion Date |
5041DR / |
Development of West New Territories landfill |
Nim Wan, Tuen Mun |
Veolia Environmental Services (Hong Kong) Limited |
$2,000 million capital cost $393 million/year operating cost (2024-25 estimate)
|
May 1993 |
Operation commenced in November 1993
|
2057 |
5042DR / 5164DR |
Development of Southeast New Territories landfill
|
Tai Chik Sha, TKO |
Green Valley Landfill Limited |
$2,300 million capital cost
|
August 1993
|
Operation commenced in September 1994, closed on 21 November 2021 |
2058
|
Southeast New Territories landfill Extension |
$1,865 million capital cost (est.)
|
April 2018 | Operation commenced on 21 November 2021 | ||||
5033DR / |
Development of Northeast New Territories landfill |
Ta Kwu Ling, NT |
Far East Landfill Technologies Limited |
$1,650 million capital cost $619 million/year operating cost (2024-25 estimate)
|
July 1994 |
Operation commenced in June 1995 |
2057 |
5163DR / |
Northeast New Territories landfill extension |
Ta Kwu Ling, NT |
Veolia Hong Kong Holding Limited |
$6,134 million capital cost |
January |
Construction commenced in December 2022 and is in progress |
2068 |
5192DR EP/SP/186/21 |
West New Territories landfill extension | Nim Wan, Tuen Mun | Hong Kong Resources Recovery Park | $27,309 million capital cost | August 2023 | Design commenced in September 2023 and is in progress | 2081 |
5184DR / |
Refurbishment and upgrading of West Kowloon transfer station |
West Kowloon Reclamation area, between the West Kowloon Expressway and Stonecutters Island |
China Harbour Engineering Company Limited |
$2,625.6 million capital cost
|
November 2022 |
Refurbishment and upgrading works commenced in June 2023 and construction is in progress |
2028 |
5185DR / |
Refurbishment and upgrading of Island West and Island East transfer stations |
Island West transfer station: Mount Davis, Kennedy Town Island East transfer station: Sun Yip Street, Chai Wan |
China Harbour Engineering Company Limited |
$2,079.9 million capital cost |
November 2022 |
Refurbishment and upgrading works commenced in June 2023 and construction is in progress |
2027 |
5186DR / EP/SP/221/22 |
North Lantau transfer station and Outlying Islands transfer facilities second follow-on contract | OITF: Mui Wo, Peng Chau, Hei Ling Chau, Cheung Chau, Yung Shue Wan, Sok Kwu Wan, Ma Wan | Canvest - Paul Y. Joint Venture | $442.2 million capital cost | July 2023 | Refurbishment and upgrading works commenced in March 2024 and construction is in progress | 2027 |
5187DR / EP/SP/221/22 |
NLTS: Siu Ho Wan, North Lantau | $558.2 million capital cost |