Press Releases

Press Release

Dredging and dumping of mud from Central Reclamation Phase III under control

In response to media enquiries, a spokesman for the Environmental Protection Department (EPD) said today (October 9) that measures have been put in place to control the environmental impact of the dredging and dumping of mud from the Central Reclamation Phase III project.

The spokesman said the project had gone through the statutory environmental impact assessment (EIA) process. The public and the Advisory Council on the Environment were consulted on the EIA before endorsement.

The EIA concluded that with the implementation of the recommended mitigation measures, the amount of contamination released from marine sediments during dredging should be minimal and not result in any adverse impacts on the surrounding waters.

An Environmental Monitoring and Audit Programme is in place to ensure that the environmental impact resulting from the project is kept to within acceptable levels.

The mitigation measures include providing silt curtains around the dredging sites, controlling the dredging rate, using closed grab dredgers, etc.

The dredged contaminated mud would be disposed of at the special seabed pits at East Sha Chau using the confined aquatic disposal method.

"As the recent court hearing did not grant an injunction, we do not anticipate any problem with issuing permits under the Dumping At Sea Ordinance for the disposal of contaminated mud from the project site at the East Sha Chau Contaminated Mud Disposal Site.

"A long-term extensive environmental monitoring programme has been put in place since the early 1990s. It consists of water quality, sediment and biota monitoring, together with a risk assessment on the impact on dolphins and humans.

"No adverse environmental impact has been detected," the spokesman noted.

The report on the results of the monitoring programme was submitted to the Scientific Group Meeting of the International Maritime Organisation (IMO) in May 2002.

The report was well received without dispute from participants of the Meeting including Greenpeace International.

The spokesman said: "A team from the Civil Engineering Department is stationed on site at East Sha Chau to ensure strict disposal procedures and depth filling level are followed and observed.

"The daily disposal rate is also regulated to ensure no impact from excessive dumping. Capping of the pit is practised to prevent dispersion of the contaminated mud from the pit.

"Only specified vessels are allowed to carry out the dumping operation. The barges are equipped with satellite based Automatic Self-Monitoring Devices to prevent short dumping."

End/Thursday, October 9, 2003





 
Back to topdot_clear.gifTable of Content