3 Dimensional Electronic Visualization of Major Findings and Elements of the EIA Report

Traffic Noise Impact

Air Quality Impact

Landscape and Visual Impact

 

----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

 


Major Findings of Traffic Noise Impact Assessment

With the provision of a 2.5 m high vertical noise barrier for the planned school, no adverse noise impacts are predicted at the NSRs during the operational phase of the Project.  In the design year for the Project, the traffic noise levels for the case with the Project in operation will not be significantly higher, ie by 1.0 dB(A) or more, than those for the case without the Project.  Based on the above, the traffic noise impact due to the Project is considered insignificant.  Furthermore, the mitigated noise levels due to the road sections within the meaning of Item A.1 of Schedule 2 under the EIAO complied with the noise criteria as stipulated in the EIAO-TM.

Please click to launch the 3D visualization

Back to Top

 

 


Major Findings of Air Quality Impact Assessment

A quantitative assessment was conducted using the peak hourly traffic flow of the proposed new roads and the surrounding road network. The prediction indicated no exceedance of hourly and daily average concentrations of Nitrogen Dioxide (NO2) or daily average concentrations of Respirable Suspended Particulates (RSP) in the vicinity of the Project.

Please click the following to view:

Locations of Air Sensitive Receivers
Predicted hourly NO2 at 1.5m above ground level
Predicted hourly NO2 at 10m above ground level
Predicted daily NO2at 1.5m above ground level
Predicted daily NO2at 10m above ground level
Predicted daily RSP at 1.5m above ground level
Predicted daily RSP at 10m above ground level

Back to Top

 

 


Major Findings of Visual Impact Assessment

Four Visually Sensitive Receivers (VSRs), VSR1 Sun Yuen Long Centre, VSR2 Pok Oi Hospital, VSR3 Kwong Ming Ying Loi School and VSR4 Yeung Uk Tsuen, were identified. There will be negligible residual impacts (impact at year 10) on all four VSRs.

Please click the following to view:

Locations of Visually Sensitive Receivers
Photomontage from VSR1
Photomontage from VSR2
Photomontage from VSR3
Photomontage from VSR4
Photomontage from VSR5

Back to Top