Appendix X

Content > Designated Projects with Construction Activities being monitored by EPD between 1.4.1998 and 31.12.2001

Designated Projects with Construction Activities being monitored by EPD between 1.4.1998 and 31.12.2001

Project Title Commencement of Project Activities Remarks

1.

Cable Landing Work in Deep Water Bay for SEA-ME-WE3 Fibre Optic Submarine Cable System Mid January 1999 Completed in January 1999

2.

Felling of five Power Station Chimneys at Tsing Yi Power Station November 1998 Completed in November 1998

3.

Removal of Sediment of Lo Tik Wan. Sok Kwu Wan and Cheung Sha Wan Fish Culture Zones November 1998 Completed in February 1999
4.

Improvement to Stream Course at Pui O

March 1999 Completed in February 2000
5.

Local Improvement to Tung Chung Road at Pak Kung Au and near Cheung Sha

May 1999 Completed in early 2001
6.

Outlying Islands Transfer Facilities at Sok Kwu Wan

End of January 1999 Completed in May 2000
7.

IS-085 Construction of pier at Luk Chau Tsuen, Lamma Island

September 1999 Completed in mid 2001
8.

IS-087 Extension of Pier at Lo Tik Wan, North Lamma

July 2000 Completed in early 2001
9.

Removal of Sediment in Sham Wan Fish Culture Zone

March 1999 Completed in July 1999
10.

Removal of Temporary Rock Bund from Existing Seabed at Ha Pak Nai

June 1999 Completed in July 1999
11.

Advance Works for Cyberport Development at Telegraph Bay

September 1999 Completed in mid 2001
12.

Construction and operation of temporary bus depot at Area 85 Tsueng Kwan O

January 2000 Completed in July 2000
13.

IMT Dredging works

April 2000 Completed in April 2000
14.

Reprovision of Pond Fish Wholesale Market

March 2000 Completed in April 2000
15.

In-house Wastewater Treatment Facility for Wastewater collected from Oil Interceptors of Retail Stations

December 1999 Completed in March 2000
16.

Proposed Installation of Integrated Mobile Phone Base Station at Ma On Shan Country Park

February 2000 Completed in May 2000
17.

Telecommunications Installation for the North Asia (NAC) Fibre Optic Submarine Cable System - Form 4 and Supporting Information

End of September 2000 Completed in December 2000
18.

Proposed Installation of Integrated Mobile Phone Base Station at Shing Mun Country Park

October 2000 Completed in May 2001
19.

Installation of Radio Base Station at Kei Ling Ha (Sai Sha Road), Sai Kung

October 2000 Completed in October 2000
20.

East Asian Crossing (EAC) Cable System (TKO)

December 2000 Completed in June 2001
21.

Proposal to establish one temporary wind monitoring station on Lamma Island for evaluating wind power as a renewable energy source

October 2001 Completed in November 2001
22.

Main Drainage Channels for Ngau Tam Mei Phase 1

July 1999 Scheduled completion in March 2002
23.

West Rail Phase 1

October 1998 Scheduled completion in 2003
24.

Hiram's Highway Improvement - between Nam Wai and Ho Chung and Upgrading of Local Access Roads

July 1999 Scheduled completion in end 2002
25.

Kai Tak Airport North Apron Decommissioning

November 1998 Scheduled completion in early 2002
26.

MTR Tseung Kwan O Extension - Phases I & II

Early 1999 Scheduled completion in end 2002
27. Widening of Tolo Highway between Island House Interchange and in Ma Liu Shui Interchange Mid 2000 Scheduled completion 2005
28. Main Drainage channels for Yuen Long and Kam Tin, in Remainder Phase 1 June 1999 Scheduled completion May 2002
29. Highway between Shap Pat Heung Interchange and Pok Oi Interchange - Remaining Works Mid 1999 Scheduled completion in early 2002
30. Improvement to Kam Tin Road, Stage 1 April 1999 Scheduled completion in early 2002
31. SK-078 Reconstruction of Pier at Pak A, Sai Kung End 2000 Schedule completion in January 2002
32.

Tin Shui Wai Development Engineering Investigation for Development of Areas 3, 30 & 31 of the Development Zone and the Reserve Zone (District Distributor Road D3)

October 1999 Scheduled completion in mid 2002
33.

Outlying Islands Sewerage - Stage I Phase 1 Cheung Chau Outfall Replacement

December 1999 Scheduled completion in March 2002
34. Reconstruction of Pak Sha Wan public pier Sai Kung May 2000 Scheduled completion in mid 2002
35. Advance Engineering Infrastructure Works for Pak Shek Kok Development (Widening of Tolo Highway between Island House Interchange and Ma Liu Shui Interchange) - Northern Access Road August 1999 Scheduled completion in late 2002
36. Advance Engineering Infrastructure Works for Pak Shek Kok Development - Northern Access Road October 1999 Scheduled completion in late 2002
37. Advance Engineering Infrastructure Works for Pak Shek Kok Development - Southern Access and Sewage Pumping Station October 1999 Scheduled completion in late 2002
38. Widening of Fo Tan Road and Related Improvement Measures in Fo Tan March 2000 Scheduled completion in December 2002
39. Rural Drainage Rehabilitation Scheme, Stage 2 Phase 3 - Mo Fan Heung Stream Rehabilitation July 1999 Scheduled completion in October 2003
40. Improvement Works and Road Reconstruction work at Sham Mong Road; Construction & Widening of Road P1 September 1999 Scheduled completion in November 2003
41. Road and Drainage Works for Tiu Keng Leng September 1999 Scheduled completion in July 2002
42. TW-032 Construction of Pier at Angler's Beach, Sham Tseng October 2000 Scheduled completion in early 2004
43. Construction of Roads and Drains to Serve the Housing Development in Area 56 Tuen Mun May 2000 Scheduled completion in early 2004
44. East Rail Extension - Tai Wai to Ma On Shan October 2000 Scheduled completion in early 2004
45. Engineering Infrastructure for Cyberport Development at Telegraph Bay - Entrusted Works (excluding advance works) December 1999 Scheduled completion in 2007
46. Tin Shui Wai Phase 4 Light Rail Extension June 2000 Scheduled completion in December 2002
47. Light Rail Transit (LRT) Extension in Tin Shui Wai Reserve Zone and Grade Separation of the LRT with Pui To Road and Tsing Lun Road in Tuen Mun July 1999 Scheduled completion in May 2003
48. Improvements to Island Eastern Corridor Section between North Point Interchange and Sai Wan Ho Mid 2000 Late's 2003
49. Sha Tin Sewage Treatment Works, Stage III Extension March 2001 Scheduled completion in February 2009
50. 132kV Overhead Pole Line and Underground Cable from the existing Po Lam Substation to the existing Tui Min Hoi Substation - Circuit No. 2 February 2000 Scheduled completion in February 2002
51. Sewage Pumping Station at Tung Tau Industrial Area, Yuen Long Mid 2000 Scheduled completion in November 2002
52. New World First Bus Permanent Depot at Chai Wan February 2000 Project completed in August 2001. Operational EM&A on-going
53. Construction of an International Theme Park in Penny's Bay of North Lantau and its Essential Associated Infrastructures May 2000 Scheduled completion in October 2008
54. Hung Hom to Tsim Sha Tsui Extension October 2000 Scheduled completion in 2004
55. Northern Access Road for Cyberport Development at Telegraph Bay October 2000 Scheduled completion in July 2003
56. Submarine Cable Landing Installation in Tong Fuk Lantau for End of Asia Pacific Cable Networks 2 (APCN2) Fibre Optic Submarine Cable System October 2000 Scheduled completion in early 2002
57. Proposed Temposed Temporary Bus Depot at Tseung Kwan O, End of Area 85 October 2000 End of May 2001
58. Replacement of Cremators at the Kwai Chung Crematorium February 2001 Scheduled completion in mid 2002
59. Conversion of two existing gas turbines into combined cycle unit Late 2001 Scheduled completion in 2004
60. Karting Mall at Kai Tak November 2000 Project completed. Operational EM&A on-going
61. New T&T (Hong Kong) Limited- Domestic Cable Route Mid 2001 Scheduled completion in early 2002
62. Artificial Reef Deplyment in Outer Port Shelter September 2001 End 2003
63. Castle Peak Road Improvement between Sham Tseng and Ka Koon Tsuen, Tsuen Wan : Construction of Reclamation and Associated Seawall Late 2001 Scheduled completion in 2005
64. Castle Peak Road Improvement between Sham Tseng and Ka Koon Tsuen, Tsuen Wan : Construction of Reclamation and Associated Seawall Late 2001 Scheduled completion in 2005
65. Castle Peak Road Improvement between Ting Kau and Sham Tseng :Construction of Reclamation and Associated Seawall at Sham Tseng Late 2001 Scheduled completion in 2005
66. Penny's Bay Reclamation Late 2001 Scheduled completion in 2005
67. Proposed Headquarter and Bus Maintenance Depot in Chai Wan Late 2001 Scheduled completion in 2003