Content |
Chapter Title Page
Figure 1.1:_ General
Layout Plan Figure 1.2:_ Location
of Secondary Boundary Fence and Noise Monitoring Station at Section 4 |
Tables
This is the 7th Monthly EM&A Report for
the works carried out during the reporting month from 1 to 31 December 2010,
and presents a summary of the environmental monitoring and audit works, list of
activities, and mitigation measures implemented during the abovementioned
reporting month.
Site Activities
The following major construction activities took place
during the reporting month:
Works Order No. 1 (ASD 010962):
¡ No major works. (Substantial
completion was certified on 12 October 2010.)
Works Order No. 2 (ASD 010969):
¡ Tree pruning work;
¡ Installation of transparent panel
for the new boundary fence;
¡ Construction of footing of the new
boundary fence;
¡ Construction of steel frame and mesh
for the new boundary fence; and
¡ Excavation works for footing of
steel fence.
Works Order No. 3 (ASD 010974):
¡ Erection of hoarding for the new
check point;
¡ Excavation at the new check point
site; and
¡ Formation of blinding layer for the
new check point.
Breach of Action and Level Limits
There was no breach of Action or Limit levels for
noise level (measured as Leq) in the reporting month.
Complaints
There was no record of complaints received in the reporting month.
Notification of Summons and Successful Prosecutions
There was no record of Notification of summons and
successful prosecution in the reporting month.
Reporting Changes
There are no reporting changes in the reporting month.
Future Key Issues
Future key issues to be considered in the forthcoming
month include:
Air
¡ Regular maintenance of all plant and
equipment;
¡ Handling of any excavated dusty
materials or stockpile of dusty materials;
¡ Spraying of water prior to any
loading, unloading or transfer of dusty materials; and
¡ Washing of vehicles before leaving
the construction sites.
Noise
¡ Location of noisy equipment and
noisy activities relative to the Noise Sensitive Receivers (NSRs);
¡ Avoiding the operation of unused
equipment, and minimising the use of Powered Mechanical Equipment (PME) and
parallel use of noisy equipment / machinery;
¡ Adoption of Level 1 site-specific
direction mitigation measures (use of quiet plant and movable noise barrier)
for construction/demolition work undertaken at a distance of 60m or less to the
NSRs; and
¡ Regular maintenance of all plant and
equipment.
Water Quality
¡ No discharge of silty water into the
storm drain and drainage channel within and the vicinity of the site;
¡ Removal off-site of construction
plant causing pollution to water system due to leakage of oil or fuel; and
¡ Temporary stockpiling of excavated
soil in a specially designated area with provision of tarpaulin cover.
Waste
¡ Control measures at the stockpiling
area to prevent the generation of dust and pollution of stormwater channels,
fish ponds or river channels;
¡ Segregation, storage, transportation
and disposal of different types of waste; and
¡ Keeping of records of quantities of
wastes generated, recycled and disposal (with locations).
Ecology
¡ Good site practices for controlling
the dust and water quality; and
¡ Clear definition of works limit to
avoid impact on adjacent habitats.
Landscape and Visual
¡ Retain tree with high amenity or
ecology value and contributing most to landscape and amenity of site;
¡ Precautionary area around trees to
be retained equal to half of the tree canopy diameter;
¡ Prohibition of the storage of
materials including fuel, the movement of construction vehicles, and the
refuelling and washing of equipment including concrete mixers within the
precautionary area;
¡ Pruning of the branches of existing
trees identified for transplantation and retention;
¡ Rectification and repair of damaged
vegetation following the construction phase to its original condition;
¡ Careful monitoring of all works
affecting the trees identified for retention and transplantation; and
¡ Enforcement of construction site
controls including storage of materials, location and appearance of site
accommodation and the careful design of site lighting to prevent light spillage.
Environmental mitigation measures will be implemented
on site as recommended and weekly site audits will be carried out to ensure
that the environmental conditions are acceptable.
The Frontier Closed Area (FCA) is an
integral part of the package of measures aimed at maintaining the integrity of
the boundary of the Hong Kong Special Administrative Region (HKSAR) with
mainland
The PBF and SBF (hereafter referred
to as ‘The Project’) will be erected along the northern and southern curbs of
the realigned BPR respectively to facilitate the Hong Kong Police Force (HKPF)
in combating cross-boundary criminal activities. The reduced FCA will comprise a narrow strip
of land covering the realigned BPR and areas to its north, together with the
points of crossing the boundary (i.e. the Boundary Control Points and Sha Tau
Kok town). Areas south of the SBF will
generally be excised from the FCA.
An Environmental Impact Assessment
(EIA) for the proposed works was carried out under the Environmental Impact
Assessment Ordinance (EIAO, Cap 499). An EIA Report and an Environmental
Monitoring and Audit (EM&A) Manual were completed in January 2009 and
approved by the Environmental Protection Department (EPD) in April 2009
(Register No. AEIAR-136/2009). The entire length of the proposed works is about
21.7 km from west of Pak Hok Chau to east of Sha Tau Kok and is divided into
four sections. A general layout plan of the Project site is presented in Figure
1.1, while the location of the SBF at Section 4 in
Sha Tau Kok is presented in Figure
1.2.
An Environmental Permit (EP)
covering the overall proposed works was issued in June 2009 (Permit No.
EP-347/2009). An application for Variation of the Environmental Permit (VEP)
(Application No. VEP-314/2010) was subsequently submitted on 24 May 2010 and
the amended Environmental Permit (Permit No. EP-347/2009/A) was issued by EPD
on 9 June 2010.
With regard to Section 4, an
application for a Further Environmental Permit (FEP) covering the works under Works
Order No. ASD 010962 (also known as Works Order No. 1) was submitted to EPD on
2 March 2010 (Application No. FEP-104/2010) and this was granted on 29 March
2010 (Permit No. FEP-03/347/2009). Furthermore, another application for an FEP
covering the works under Works Order Nos. ASD 010969 and ASD 010974 (also known
as Works Order Nos. 2 and 3 respectively) – including a new section of SBF
consisting of transparent panel, a new checkpoint and kiosk – was submitted to
EPD on 13 August 2010 (Application No. FEP-112/2010) and was granted on 7
September 2010 (Permit No. FEP-04/347/2009/A).
The Architectural Services
Department (ArchSD) has been entrusted with the management of the Project by
the Project Proponent – the Secretary for Security of the HKSAR Government.
Mott MacDonald Hong Kong Limited (MMHK) has in turn been commissioned by ArchSD
as the consulting engineer for the entire Project under Consultancy Agreement
No. 9SN005, and is the Engineer’s Representative (ER) for construction of the
Project.
For Section 4 of the Project, MMHK
and ENVIRON Hong Kong Limited (ENVIRON) have been commissioned as the
Environmental Team (ET) and Independent Environmental Checker (IEC)
respectively to undertake the Environmental Monitoring and Audit (EM&A)
programme as described in the approved EM&A Manual of the Project. Also,
the Contract to undertake and perform the construction works for Section 4 was
awarded to Chun Wo Construction & Engineering Company Limited (‘The
Contractor’) and is scheduled to last for approximately 18 months. It formally
commenced on 28 May 2010, and the construction works and EM&A programme
under the above-mentioned EP and FEP(s) also commenced on this date. The
construction works programme is presented in Appendix A.
This monthly EM&A report
summarises the environmental monitoring and audit works, list of activities and
mitigation measures implemented at Section 4 during the period of 1 to 31
December 2010 inclusive (‘reporting month’).
The scope of works for Section 4
consists of:
¡ Erection of an SBF from the entrance
of the Sha Tau Kok town (i.e. the location of ‘Gate One’) to the Sha Tau Kok
Control Point (approximately 0.5 km);
¡ Use of transparent panel for a
section of an SBF;
¡ Provision of a two-storey high
checkpoint at ‘Gate One’;
¡ Addition of a kiosk/guard house on
an existing footpath of
¡ Removal of the existing checkpoint
at Shek Chung Au.
The organisation chart and lines of
communication with respect to the on-site environmental management structure
together with the contact information of the key personnel are shown in Appendix B.
1.3
Works Undertaken in the Reporting
Month
The following activities have taken
place during the reporting month:
Works Order No. 1 (ASD 010962):
¡ No major works. (Substantial
completion was certified on 12 October 2010.)
Works Order No. 2 (ASD 010969):
¡ Tree pruning work;
¡ Installation of transparent panel
for the new boundary fence;
¡ Construction of footing of the new
boundary fence;
¡ Construction of steel frame and mesh
for the new boundary fence; and
¡ Excavation works for footing of
steel fence.
Works Order No. 3 (ASD 010974):
¡ Erection of hoarding for the new
check point;
¡ Excavation at the new check point
site; and
¡ Formation of blinding layer for the
new check point.
Figure 1.1: General Layout Plan
Figure 1.2: Location of Secondary
Boundary Fence and Noise Monitoring Station at Section 4
2.1
Summary of EM&A Requirements
The EM&A programme requires
environmental monitoring of construction noise as well as environmental site
inspections for air quality, noise, water quality, waste management, ecology,
landscape and visual, as specified in the approved EM&A Manual.
Originally, the EM&A Manual
designated two locations as noise monitoring stations during the construction
phase. However, currently noise levels at only one of these monitoring stations
(as shown in Figure
1.2) are monitored. The reasons for this arrangement
are detailed in Section 3.2.
A summary of impact EM&A
requirements is presented in Table
2.1. The Environmental Quality Performance Limits and
the Event and Action Plans (for construction noise only) are shown in Appendix
C and Appendix
D respectively.
Table 2.1: Summary of EM&A Impact
Requirements
Parameters |
Description |
Location(s) |
Frequency |
Duration |
Air |
On-site
Inspection |
Active Works Sites |
Weekly |
During Construction |
Noise |
Leq,
30min |
STK-DBD |
Weekly |
During Construction |
Waste management |
On-site Waste Audit |
Active Works Sites |
Weekly |
During Construction |
On-site Waste Inspection |
||||
Wastewater |
On-site Wastewater Audit |
Active Works Sites |
Weekly |
During Construction |
Ecology |
On-site Audit of Recommended Ecological Mitigation Measures |
Active Works Sites |
Periodically (by Contractor) |
As specified in EM&A Manual (see Table E.5) |
Landscape and Visual |
On-site Audit of Recommended Landscape and Visual Mitigation Measures |
Active Works Areas |
Regular intervals (by Contractor/ Landscape Sub-Contractor) |
As specified in EM&A Manual (see Table E.6) |
General Site Conditions |
Environmental Site Inspection |
Works areas and areas affected by works |
Weekly |
During Construction |
2.2
Implementation of Environmental
Mitigation Measures
The Contractor is required to
implement mitigation measures listed in the latest valid EP and FEP(s) (where applicable),
EIA Report and EM&A Manual. During routine site inspections, the
Contractor's implementation of mitigation measures, if any, are to be inspected
and reviewed. A schedule of the implementation of mitigation measures
identified at the EIA stage is given in Appendix
E.
3.1
Monitoring Parameters, Frequency and
Duration
Following the requirements in the
EM&A Manual for noise, noise monitoring has to be carried out during the
construction phase. Continuous noise monitoring for the A-weighted levels Leq,
L10 and L90 is undertaken once per every week during
daytime hours (between 07:00 and 19:00) on normal weekdays.
Table 3.1 summarizes the monitoring parameters, frequency
and duration of air quality monitoring. The noise monitoring schedule during
the reporting month is presented in Appendix
F.
Table 3.1: Noise Monitoring Parameters,
Frequency and Duration
Monitoring
Station |
Parameter |
Frequency |
Duration |
STK-DBD |
Leq, L90 & L10 |
Once every
week |
30 min |
Originally, two construction noise
monitoring stations were proposed in the EM&A Manual, namely: STK03 (Block
1, Sha Tau Kok Estate) and STK05 (Village House at Sha Tau Kok). STK03 was
mainly selected for the construction works related to the SBF and the new
checkpoint in Sha Tau Kok, while STK05 was mainly selected for the removal of
the existing checkpoint at Shek Chung Au.
However, access to STK03 to perform
noise monitoring was not granted, therefore an alternative nearby location –
STK-DBD (HKPF Operation Base, Sha Tau Kok Division, Border District) – was
proposed by ET and agreed to by IEC and EPD. Baseline noise monitoring was
subsequently conducted at STK-DBD from 16 to 29 March 2010.
Currently, there is no solid
timetable or programme for the demolition works of the existing checkpoint at
Shek Chung Au, although the end of 2011 has been proposed as a possible
commencement date. This is subject to future confirmation of the demolition
programme by the Security Bureau and HKPF. No noise monitoring at STK05 has
been carried out at this stage.
As a result, only one noise impact
monitoring station is included in the current EM&A programme for Section 4.
The location of the agreed noise quality monitoring station is listed in Table
3.2 and shown in Figure 1.2.
Table 3.2: Noise Impact Monitoring
Location
Monitoring
Station |
Description of Location |
Type of measurement |
STK-DBD |
HKPF Operational Base, Sha Tau Kok Division, Border District |
Façade |
Integrating Sound Level Meter will be
used for noise monitoring. It is a Type 1 sound level meter capable of giving a
continuous readout of the noise level readings including equivalent continuous
sound pressure level (Leq) and percentile sound pressure level (Lx).
They comply with International Electrotechnical Commission Publications
651:1979 (Type 1) and 804:1985 (Type 1). Table 3.3 summarizes the noise monitoring equipment model
being used.
Table 3.3: Noise Monitoring Equipment
Equipment |
Model(s) |
Integrating Sound Level Meter |
Rion NL-31 |
Acoustic Calibrator |
Castle GA607 |
The
calibration frequencies of the monitoring equipment are provided in Table
3.4.
Table 3.4: Noise Monitoring Equipment
Calibration Frequencies
Equipment, Model and Serial Number |
Calibration Frequency |
Calibration Due Date(s) |
Integrating Sound Level Meter Rion NL-31 (serial number 01262786) |
Every year |
10 May 2011 |
Acoustic Calibrator Castle GA607 (serial number 040162) |
Every year |
20 Dec 2010 & 8 Dec 2011 |
The calibration certificates are
presented in Appendix
G.
¡ The Sound Level Meter was set on a
tripod at a height of at least 1.2 m above the ground.
¡ Façade measurements were made at the
monitoring locations.
¡ The battery condition was checked to
ensure the correct functioning of the meter.
¡ Parameters such as frequency
weighting, the time weighting and the measurement time were set as follows:
- frequency weighting: A
- time weighting: Fast
- time measurement: 5-minute intervals
(between 07:00 and 19:00); Leq (30 min) was determined by
calculating the logarithmic average of six Leq (5-min) data.
¡ Prior to and after each noise
measurement, the meter was calibrated using a Calibrator for 94 dB at 1
kHz. If the difference in the
calibration level before and after measurement was more than 1 dB, the
measurement would be considered invalid and have to be repeated after
re-calibration or repair of the equipment.
¡ During the monitoring period, the Leq,
L10 and L90 noise levels were recorded. In addition, any site observations and noise
sources were recorded on a standard record sheet.
3.5.2
Maintenance and Calibration
¡ The microphone head of the sound
level meter and calibrator is cleaned with soft cloth at quarterly intervals.
¡ The meter and calibrator are sent to
the supplier or Hong Kong Laboratory Accreditation Scheme (HOKLAS) laboratory
to check and calibrate at yearly intervals.
3.6
Results of Impact Monitoring
The measured construction noise levels, in
terms of Leq (30-min), during the reporting month are summarised in Table
3.5. Detailed
results, including general weather conditions and graphical presentations are
presented in Appendix K.
Table 3.5: Results of Noise Impact
Monitoring
Monitoring Station |
Measured Leq (30-min) Range, dB(A) |
Limit Level for Leq, dB(A) |
STK-DBD |
64 – 66 |
75 |
Note: All figures are rounded off to the
nearest whole number.
No exceedance of Action / Limit Levels for
construction noise was recorded.
No direct comparison between the measured noise
levels and the construction noise levels predicted in the EIA Report for this
Project was possible due to the minor nature of site works conducted during the
reporting month.
Wind data obtained from the nearest Hong Kong
Observatory monitoring station, at Ta Kwu Ling, covering all noise monitoring
days during the reporting month is included in Appendix K.
Environmental site inspections were
carried out on a weekly basis to monitor the proper implementation of environmental
pollution control and mitigation measures for Section 4. In the reporting
month, three monthly site inspections were carried out jointly by the ER,
Contractor, ET and IEC on 1, 22 and 31 December 2010, and additional weekly
site inspections were carried out by the ER, Contractor and ET on 7 and 16
December 2010. The EM&A schedule is presented in Appendix F.
Major findings provided jointly by
the ET and IEC during the joint monthly site inspections, and provided by ET
during the additional weekly site inspections, are summarised in Table 4.1. In general, the works site areas were found to
be in compliance with the environmental mitigation requirements listed in the
EM&A Manual and no adverse impacts were found.
Table 4.1: Summary of Environmental
Site Inspections
Date of Inspection |
Major Observations |
Status |
1 Dec 2010 |
The Contractor is reminded to display a copy of the master EP and FEP (no. FEP-04/347/2009/A) at the works site for the new checkpoint. |
A copy of the master EP and FEP (no. FEP-04/347/2009/A) was displayed at the new checkpoint work site, as observed on 16 Dec 2010. (closed) |
|
The Contractor is reminded to provide covering for all construction and demolition (C&D) material stockpiles at the works site for the new checkpoint. |
No C&D material stockpiles were observed at the new checkpoint works site, as observed on 16 Dec 2010. (closed) |
|
The Contractor is reminded to provide all necessary tree protection works in the areas covered by Works Order No. 2. |
The Contractor is again reminded to provide and maintain all necessary tree protection works in the areas covered by Works Order No. 2. This includes placement of construction materials away from trees and proper fencing of precautionary areas, as observed on 8 Jan 2011. Pending Contractor’s ongoing action. |
7 Dec 2010 |
No new observations. |
- |
16 Dec 2010 |
No new observations. |
- |
22 Dec 2010 |
Oil/liquid containers at the main works site and new checkpoint works site were without drip trays. The Contractor is asked to follow-up as soon as possible. |
The oil/liquid containers had been removed from site, as observed on 31 Dec 2010. (closed) |
|
The Contractor is reminded to provide suitable dust mitigation measures (e.g. water spray) during excavation works at the new checkpoint site. |
Tarpaulin covers were provided for a stockpile of excavated material. No excavation works were observed at the new checkpoint site during the follow-up site inspection on 31 Dec 2010. (closed) |
|
The Contractor is reminded that no discharge of site run-off, including groundwater, is allowed without a Water Pollution Control Ordinance (WPCO) effluent discharge licence being obtained first. |
No discharge of site run-off (including groundwater) was observed during the follow-up site inspection on 31 Dec 2010. (closed) |
31 Dec 2010 |
A small amount of excavated material had spilt through a gap in the site hoarding and onto the public area. The Contractor is asked to remove this material and provide suitable measures to prevent such event from re-occurring. |
The spilt material was removed. Also, extra hoarding and cement was provided at the gaps in existing site hoarding, as observed on 8 Jan 2011. (closed) |
|
Accumulated construction dust was observed at the new checkpoint site entrance. The Contractor is asked to implement suitable mitigation measures. |
Extra hoarding was provided at the site entrance. However, some construction dust was still observed in the public area and should be cleared as soon as possible, as observed on 8 Jan 2011. |
During the reporting month, two
environmental meetings were held on 1 and 31 December 2010.
4.3
Status of Environmental Submissions,
Permits and Licences
A summary of status of all
environmental submissions, valid permits/licences, and/or notifications to EPD
for this Project during the reporting month is presented in Table 4.2. A summary of submissions made under the valid EP
and FEP(s) for Section 4 during the same period is presented in Table 4.3.
Table 4.2: Status of Environmental
Submissions, Permits and Licences
Statutory Reference |
Description |
Permit / Reference No. |
Valid Period |
Status |
EIAO |
Environmental Permit |
EP-347/2009/A |
9 Jun 2010 – present |
Valid |
EIAO |
Further Environmental Permit |
FEP-03/347/2009 |
29 Mar 2010 – present |
Valid |
EIAO |
Application for Further Environmental Permit (Remaining Section) |
FEP-112/2010 |
- |
Submitted to EPD on 13 Aug 2010. Approved by EPD on 7 Sep 2010. |
EIAO |
Further Environmental Permit (Remaining Section) |
FEP-04/347/2009/A |
7 Sep 2010 – present |
Valid |
APCO |
Notification pursuant to Section 3(1) of the Air Pollution Control (Construction Dust) Regulation (Form NA) |
312959 EPD notified on 4 Jan 2010 |
- |
Valid |
Legend: EIAO – Environmental Impact Assessment Ordinance
(Cap 499)
APCO – Air
Pollution Control Ordinance (Cap 311)
WPCO – Water
Pollution Control Ordinance (Cap 358)
WDO – Waste
Disposal Ordinance (Cap 354)
NCO – Noise
Control Ordinance (Cap 400)
Table 4.3: Environmental Submissions Made under the Valid EP & FEP(s) during
the Reporting Month
EP/FEP Ref. |
Description |
Submission Date |
EP Condition 4.5 & FEP Condition 4.5 |
Monthly EM&A Report (Nov 2010) |
14 Dec 2010 |
4.4
Advice on the Solid and Liquid Waste
Management Status
The construction and demolition
(C&D) material and general refuse generated by Section 4 of the Project in
the reporting month are shown in Appendix
I. Wastes were handled and disposed from site in
accordance with the EM&A Manual and all relevant legislation and
regulations.
4.5
Review of Environmental Monitoring
Procedures
The monitoring works conducted by
the Environmental Team have been reviewed regularly. No changes in the
environmental monitoring procedures are considered necessary at this stage.
4.6
Implementation Status of
Environmental Mitigation Measures
An Implementation Schedule of
Mitigation Measures from the EIA Report / EM&A Manual is provided in Appendix
E, in the following order (see Table 4.4):
Table 4.4: Implementation Schedule of
Mitigation Measures
Parameter |
Table |
Air Quality |
|
Noise |
|
Water Quality |
|
Waste Management |
|
Ecology |
|
Landscape and Visual |
5.1
Non-compliance of Action and Limit
Levels
There was no breach of Action or
Limit Levels for construction noise impact monitoring in the reporting month.
No environmental complaints were
received or made against Section 4 of the Project during the reporting month.
The complaint log is presented in Appendix
J.
5.3
Notifications of Summons and
Successful Prosecutions
No notifications of summons or
successful prosecution were received or made against Section 4 of the Project
during the reporting month.
6.1
Construction Programme for the Next
Reporting Month
The major construction works
forecast for Section 4 in January 2011 will be:
Works Order No. 1 (ASD 010962):
¡ No major works forecast.
Works Order No. 2 (ASD 010969):
¡ Tree felling and pruning work;
¡ Tree transplant;
¡ Delivery of materials to site;
¡ Excavation works for the new
boundary fence;
¡ Construction of footing of the new
boundary fence;
¡ Fabrication works for the new
boundary fence;
¡ Erection of steel frame along the
boundary fence; and
¡ Installation of transparent panel
for the new boundary fence..
Works Order No. 3 (ASD 010974):
¡ Erection of hoarding for the new
check point building;
¡ Excavation at the new check point
site; and
¡ Construction of footing for the new
check point building.
6.2
Key Issues for the Next Reporting
Month
Based on the forecast major
construction works listed in Section 6.1, the key environmental issues to be considered in
December 2010 include:
¡ All plant and equipment to be
maintained to prevent any undue air emissions.
¡ Any excavated dusty materials or
stockpile of dusty materials should be covered entirely by impervious sheeting
or sprayed with water so as to maintain the entire surface wet, and recovered
or backfilled or reinstated within 24 hours of the excavation or unloading;
¡ All dusty materials should be
sprayed with water prior to any loading, unloading or transfer; and
¡ Every vehicle should be washed to
remove any dusty materials from its body and wheels before leaving the
construction sites.
¡ Noisy equipment and noisy activities
should be located as far away from the Noise Sensitive Receivers (NSRs) as is
practical;
¡ Unused equipment should be turned
off. Powered Mechanical Equipment (PME) should be kept to a minimum and the
parallel use of noisy equipment / machinery should be avoided;
¡ Adoption of Level 1 site-specific
direction mitigation measures (use of quiet plant and movable noise barrier)
for construction/demolition work undertaken at a distance of 60m or less to the
NSRs; and
¡ Regular maintenance of all plant and
equipment.
¡ No discharge of silty water into the
storm drain and drainage channel within and the vicinity of the site;
¡ Any construction plant which causes
pollution to the water system due to leakage of oil or fuel shall be removed
off-site immediately; and
¡ Excavated soil which needs to be
temporarily stockpiled should be stored in a specially designated area and
provided with a tarpaulin cover to avoid runoff into the drainage channels.
¡ Control measures should be taken at
the stockpiling area to prevent the generation of dust and pollution of
stormwater channels, fish ponds or river channels;
¡ Different types of waste should be
segregated, stored, transported and disposed of in accordance with the relevant
legislative requirements and guidelines; and
¡ Records of quantities of wastes
generated, recycled and disposal (with locations) shall be kept.
¡ Good site practices for controlling
the dust and water quality (avoid stockpiles adjacent to wetlands, covering the
stockpiles with impervious sheeting, control of vehicle speed, no discharge of
silty water to the rivers, streams and drainage channels); and
¡ Clear definition of works limit to
avoid impact on adjacent habitats.
¡ Retain trees that have high amenity
or ecology value and contribute most to the landscape and amenity of the site
and its immediate environs;
¡ Creation of precautionary area
around trees to be retained equal to half of the tree canopy diameter.
Precautionary area to be fenced;
¡ Prohibition of the storage of
materials including fuel, the movement of construction vehicles, and the
refuelling and washing of equipment including concrete mixers within the
precautionary area;
¡ Pruning of the branches of existing
trees identified for transplantation and retention to be based on the principle
of crown thinning maintaining their form and amenity value;
¡ The rectification and repair of
damaged vegetation following the construction phase to its original condition
prior to the commencement of the works or replacement using specimens of the
same species, size and form where appropriate to the design intention of the area
affected;
¡ All works affecting the trees
identified for retention and transplantation will be carefully monitored. This
includes the key stages in the preparation of trees, the implementation of
protection measures and health monitoring throughout the construction period;
and
¡ Construction site controls should be
enforced including the storage of materials, the location and appearance of
site accommodation and the careful design of site lighting to prevent light
spillage.
6.3
Monitoring Schedule for the Next
Reporting Month
The tentative schedule for
environmental monitoring in January 2011 is provided in Appendix F. Actual monitoring dates may change due to unforeseen
events such as inclement weather.
The construction phase and EM&A
programme for Section 4 commenced on 28 May 2010. EM&A was performed from 1
to 31 December 2010 during which some minor site works have commenced. All
monitoring and audit results in the reporting month were checked and reviewed.
Construction noise monitoring was
carried out in the reporting month. As no noise-related complaint was received
or follow-up by ET during the reporting month, no Action Level exceedance was
recorded. All noise monitoring results obtained complied with the Limit Level.
Environmental site inspections were
carried out five times during the reporting month. During the site audits,
recommendations on remedial actions were given to the Contractor for any
deficiencies identified.
Wastes were handled and disposed
from site in accordance with the EM&A Manual and all relevant legislation
and regulations.
No environmental complaints,
notification of summons of successful prosecutions were received or made
against Section 4 of the Project during the reporting month.
Overall, the EM&A programme for
Section 4 during the reporting month was in compliance with the relevant EIA
Report, EM&A Manual, EP and FEP(s) and all relevant legislation and
regulations.
No further recommendations were made
at this stage pending more site progress achieved.
Appendix A.
Construction Works Programme |
Appendix B.
Project Organisation Chart for
Section 4 |
Table C.1: Action and Limit Levels for
Construction Noise
Time Period |
Action Level |
Limit Level |
Daytime (07:00-19:00) except general holidays and Sundays Measurements in Leq (30min) |
When one documented complaint is received |
75 dB(A) |
Table D.1: Event
and Action Plan for Construction Noise
EVENT |
ACTION |
|
|
|
|
ET Leader |
IEC |
ER |
Contractor |
Action Level |
1. Notify IEC and the Contractor. 2. Carry out investigation. 3. Report the results of investigation to IEC and the Contractor. 4. Discuss with the Contractor and formulate remedial measures. 5. Increase monitoring frequency to check mitigation measures. |
1. Review with analyzed results submitted by ET. 2. Review the proposed remedial measures by the Contractor and advise ER accordingly. 3. Supervise the implement of remedial measures. |
1. Confirm receipt of notification of exceedance in writing. 2. Notify the Contractor. 3. Require the Contractor to propose remedial measures for the analyzed noise problem. 4. Ensure remedial measures are properly implemented. |
1. Submit noise mitigation proposals to IEC. 2. Implement noise mitigation proposals. |
Limit Level |
1. Identify the source. 2. Notify IEC, ER, EPD and the Contractor. 3. Repeat measurement to confirm findings. 4. Increase monitoring frequency. 5. Carry out analysis of Contractor’s working procedures to determine possible mitigation to be implemented. 6. Inform IEC, ER, and EPD the causes & actions taken for the exceedances. 7. Assess effectiveness of the Contractor’s remedial actions and keep IEC, EPD and ER informed of the results. 8. If exceedance stops, cease additional monitoring. |
1. Discuss amongst ER, ET Leader and the Contractor on the potential remedial actions. 2. Review the Contractor’s remedial actions whenever necessary to assure their effectiveness and advise ER accordingly. 3. Supervise the implementation of remedial measures. |
1. Confirm receipt of notification of exceedance in writing. 2. Notify the Contractor. 3. Require the Contractor to propose remedial measures for the analyzed noise problem. 4. Ensure remedial measures are properly implemented. 5. If exceedance continues, consider what activity of the work is responsible and instruct the Contractor to stop that activity of work until the exceedance is abated. |
1. Take immediate action to avoid further exceedance. 2. Submit proposals for remedial actions to IEC within 3 working days of notification. 3. Implement the agreed proposals. 4. Resubmit proposals if problem still not under control. 5. Stop the relevant activity of works as determined by the ER until the exceedance is abated. |
Table E.1: Recommended Mitigation
Measures – Air Quality
EIA Ref. |
EM&A Manual Ref. |
Recommended Mitigation Measures |
Who to implement? |
When to implement? (1) |
Implementation Status (2) |
2.5.2 |
3.2.2 |
The
following good site practice should be implemented: ¡ any excavated dusty materials or stockpile
of dusty materials should be covered entirely by impervious sheeting or
sprayed with water so as to maintain the entire surface wet, and recovered or
backfilled or reinstated within 24 hours of the excavation or unloading; ¡ the working area of excavation should be
sprayed with water immediately before, during and immediately after the
operations so as to maintain the entire surface wet; ¡ dusty materials carried by vehicle leaving
a construction site should be covered entirely by clean impervious sheeting; ¡ the area where vehicle washing takes place
and the section of the road between the washing facilities and the exit point
should paved with concrete, bituminous materials or hardcores; ¡ the portion of road leading only to a
construction site that is within 30m of designated vehicle entrance or exit
should be kept clear of dusty materials; ¡ all dusty materials should be sprayed with
water prior to any loading, unloading or transfer; ¡ vehicle speed should be limited to 10kph
except on completed access roads; ¡ every vehicle should be washed to remove
any dusty materials from its body and wheels before leaving the construction
sites. |
Contractor |
DC |
4, ! |
Legend: (1) DC - During Construction
(2) 4 - Implemented
P - Partially Implemented
5 - Not Implemented
REC - Rectified by Contractor
(REC) - Partially Rectified by Contractor
! - Pending Contractor’s Rectification
Action
N/A - Not Applicable
Table E.2: Recommended Mitigation
Measures – Noise
EIA Ref. |
EM&A Manual Ref. |
Recommended Mitigation Measures |
Who to implement? |
When to implement? (1) |
Implementation Status (2) |
3.8.14 |
4.8.1 |
The following good site practical should be
implemented: ¡ The Contractor shall adopt the Code of
Practice on Good Management Practice to Prevent Violation of the Noise
Control Ordinance (Chapter 400) (for Construction Industry) published by EPD; ¡ The Contractor shall observe and comply
with the statutory and non-statutory requirements and guidelines; ¡ Before commencing any work, the Contractor
shall submit to the Engineer Representative for approval the method of
working, equipment and noise mitigation measures intended to be used at the
site; ¡ The Contractor shall devise and execute
working methods to minimise the noise impact on the surrounding sensitive
uses, and provide experienced personnel with suitable training to ensure that
those methods are implemented; ¡ Noisy equipment and noisy activities
should be located as far away from the Noise Sensitive Receivers (NSRs) as is
practical; ¡ Unused equipment should be turned
off. Powered Mechanical Equipment
(PME) should be kept to a minimum and the parallel use of noisy equipment /
machinery should be avoided; ¡ Regular maintenance of all plant and
equipment; ¡ Material stockpiles and other structures
should be effectively utilised as noise barriers, where practicable. |
Contractor |
DC |
4 |
3.8.1 -3.8.3 |
4.8.2 -4.8.3 |
Other than good site practice, the
Contractor is required to adopt Levels 1 and 2 site-specific direct
mitigation measures as specified below during the construction phase. With construction / demolition work
undertaken at a distance of 60m or less to the NSRs, below mitigation
measures should be included: Level 1 – Use of Quiet Plant and Movable Noise Barrier ¡ The Contractor shall obtain particular
models of plant that are quieter than standards given in the Technical
Memorandum on Noise from Construction Work other than Percussive Piling
(GW-TM). ¡ Purpose-built movable noise barriers should be used to mitigate construction noise directly at sources that are not usually mobile provide that the direct line of sight to the source is blocked. |
Contractor |
DC |
N/A |
3.8.9 |
4.8.4 |
In addition to the use of quiet plant and
movable noise barrier, alternative demolition method of existing boundary
fence at Section 2-3 shall be used where demolition works would be undertaken
at a distance of 12m or less to the NSRs. These particular mitigation
measures should be included: Level 2 – Alternative Demolition Method of Existing Boundary Fence ¡ The use of welder is recommended to
replace the use of hand-held driller; ¡ The use of hand-held breaker with movable
noise barrier is recommended to replace the use of mini-robot mounted
breaker; and the duration for the use of hand-held breaker is minimal as only
the surface level of the footing to be broken; and ¡ The removal of the footing of the existing boundary fence should be carried by concrete crusher mini-robot mounted after the surface level broken by hand-held breaker. |
Contractor |
DC |
N/A |
Legend: (1) DC -
During Construction
(2) 4 - Implemented
P - Partially Implemented
5 - Not Implemented
REC - Rectified by Contractor
(REC) - Partially Rectified by Contractor
! - Pending Contractor’s Rectification
Action
N/A - Not Applicable
Table E.3: Recommended Mitigation
Measures – Water Quality
EIA Ref. |
EM&A Manual Ref. |
Recommended Mitigation Measures |
Who to implement? |
When to implement? (1) |
Implementation Status (2) |
4.7.1 |
5.3.1 |
Good site practices in
addition to the implementation of mitigation measures would minimize the
impact to the surrounding environment. General Prevention and Precaution Measures: ¡ The site should be confined to avoid silt
runoff to the site. ¡ No discharge of silty water into the storm
drain and drainage channel within and the vicinity of the site. ¡ Any soil contaminated with chemicals/oils
shall be removed from site and the void created shall be filled with suitable
materials. ¡ Stockpiles to be covered by tarpaulin to
avoid spreading of materials during rainstorms; ¡ Suitable containers shall be used to hold
the chemical wastes to avoid leakage or spillage during storage, handling and
transport; ¡ Chemical waste containers shall be
labelled with appropriate warning signs in English and Chinese to avoid accidents. there shall also be clear instructions
showing what action to take in the event of an accidental; ¡ Storage areas shall be selected at safe
locations on site and adequate space shall be allocated to the storage area; ¡ Any construction plant which causes
pollution to the water system due to leakage of oil or fuel shall be removed
off-site immediately; ¡ Spillage or leakage of chemical waste to
be controlled by using suitable absorbent materials; ¡ Chemicals will always be stored on drip
trays or in bunded areas where the volume is 110% of the stored volume; ¡ Regular clearance of domestic waste
generated in the temporary sanitary facilities to avoid waste water
spillage. ¡ Temporary sanitary facilities to be provided for on-site workers during construction. |
Contractor |
DC |
4, REC |
4.7.2 - 4.7.3 |
5.3.2 - 5.3.3 |
Concreting Work A temporary drainage channel and associated facilities should be provided to collect the runoff generated and prevent concrete-contaminated water from entering watercourses. Adjustment of pH can be achieved by adding a suitable neutralising reagent to wastewater prior to discharge. The concreting works should be temporarily isolated with proper methods, such as by placing of sandbags or silt curtains with lead edge at bottom and properly supported props. |
Contractor |
DC |
N/A |
4.7.4 |
5.3.4 |
Soil Excavation and
Stockpiling Excavated soil which needs to be temporarily stockpiled should be stored in a specially designated area and provided with a tarpaulin cover to avoid runoff into the drainage channels. |
Contractor |
DC |
4, REC |
4.7.5 - 4.7.6 |
5.3.5 -5.3.6 |
Site Depot All compounds in works areas should be located on areas of hard standing with provision of drainage channels and settlement ponds where necessary to allow interception and controlled release of settled/treated water. Hard standing compounds should drain via an oil interceptor. The oil interceptor should be regularly inspected and cleaned to avoid wash-out of oil during storm conditions. A bypass should be provided to avoid overload of the interceptor's capacity. Any contractor generating waste oil or other chemicals as a result of his activities should register as a chemical waste producer. Disposal of the waste oil should be done by a licensed collector. Good housekeeping practices should be implemented to minimise careless spillage and to keep the storage and the work space in a tidy and clean condition. Appropriate training including safety codes and relevant manuals should be given to the personnel who regularly handle the chemicals on site. |
Contractor |
DC |
P |
4.7.7 |
5.3.7 |
Construction of
Checkpoint Sewage system should be constructed to divert domestic sewage, which will be generated from the sanitary facilities provided in the new checkpoint at Sha Tau Kok, to public sewer connected to government sewage treatment facilities. |
Contractor |
DC |
N/A |
Legend: (1) DC - During Construction
(2) 4 - Implemented
P - Partially Implemented
5 - Not Implemented
REC - Rectified by Contractor
(REC) - Partially Rectified by Contractor
! - Pending Contractor’s Rectification
Action
N/A - Not Applicable
Table E.4: Recommended Mitigation
Measures – Waste Management
EIA Ref. |
EM&A Manual Ref. |
Recommended Mitigation Measures |
Who to implement? |
When to implement? (1) |
Implementation Status (2) |
5.6.7 |
6.3.6 |
Site Clearance The topsoil and vegetation removed and excavated material may have to be temporarily stockpiled on-site. Control measures should be taken at the stockpiling area to prevent the generation of dust and pollution of stormwater channels, fish ponds or river channels. However, to eliminate the risk of blocking drains in the wet season, it is recommended that stockpiling of excavated materials during the wet season should be avoided as far as practicable. |
Contractor |
DC |
4 |
5.6.10 - 5.6.12 |
6.3.8 |
Construction and
Demolition Materials Careful design, planning and good site management can minimize over-ordering and generation of waste materials such as concrete mortars and cement grouts. The design of formwork should maximize the use of standard wooden panels so to achieve high reuse levels. Alternatives such as steel formwork or plastic facing should be considered to increase the potential for reuse. The Contractor should recycle as much of the C&D materials as possible on-site. Proper segregation of waste on-site will increase the feasibility of certain components of the waste stream by the recycling contractors. Different areas of the worksite shall be designated for such segregation and storage wherever site conditions permit. Trip-ticket system should be employed to monitor the disposal of C&D material and solid at public filling facilities and landfills, and to control fly-tipping. Government has established a differentiated charging scheme for the disposal of waste to landfill, construction waste sorting facilities and public fill facilities. This will provide additional incentives to reduce the volume of waste generated and to ensure proper segregation of wastes. |
Contractor |
DC |
4 |
5.6.13 - 5.6.14 |
6.3.9 - 6.3.13 |
Chemical Waste For those processes which generate chemical
waste, it may be possible to find alternatives which generate reduced
quantities or even no chemical waste, or less dangerous types of chemical
waste. Chemical waste that is produced, as defined
by Schedule 1 of the Waste Disposal (Chemical Waste) (General) Regulation,
should be handed in accordance with the Code of Practice on the Packaging,
Handling and Storage of Chemical Waste as follows: Containers used for the storage of chemical
wastes should: ¡ be suitable for the substance they are
holding, resistant to corrosion, maintained in a good condition, and securely
closed: ¡ have a capacity of less than 450 litres
unless the specification have been approved by the EPD; and ¡ display a label in English and Chinese in
accordance with instructions prescribed in Schedule 2 of the Regulations, The storage area for chemical wastes should: ¡ be clearly labelled and used solely for
the storage of chemical waste; ¡ be enclosed on at least 3 sides; ¡ have an impermeable floor and bunding, of
capacity to accommodate 110% of the volume of the largest container or 20% by
volume of the chemical waste stored in that area whichever is the greatest; ¡ have adequate ventilation; ¡ be covered to prevent rainfall entering
(water collected within the bund must be tested and disposed as chemical
waste if necessary); and ¡ be arranged so that incompatible materials
are adequately separated. Disposal of chemical waste should: ¡ be via a licensed waste collector; and ¡ be to a facility licensed to receive
chemical waste, such as the Chemical Waste Treatment Facility which also
offers a chemical waste collection service and can supply the necessary
storage containers, or ¡ to be re-user of the waste, under approval from the EPD. |
Contractor |
DCP |
N/A |
5.6.16 |
6.3.15 |
General Refuse Should be stored in enclosed bins or compaction units separate from C&D and chemical wastes. The Contractor should employ a reputable waste collector to remove general refuse from the site, separate from C&D and chemical wastes, on a regular basis to minimise odour, pest and litter impacts. Burning of refuse on construction sites is prohibited by law. |
Contractor |
DC |
4 |
5.6.18 |
6.3.16 |
Construction Waste
Management Plan A construction waste management plan (CWMP) should be prepared and developed by the contractor to ensure proper collection, treatment and disposal of waste on site. This CWMP will also take into account the requirement to handle chemical wastes on site which will need to be managed by a licensed waste collection contractor. |
Contractor |
DC |
4 |
Legend: (1) DC - During Construction
DCP -
During Construction Planning
(2) 4 - Implemented
P - Partially Implemented
5 - Not Implemented
REC - Rectified by Contractor
(REC) - Partially Rectified by Contractor
! - Pending Contractor’s Rectification
Action
N/A - Not Applicable
Table E.5: Recommended Mitigation
Measures – Ecology
EIA Ref. |
EM&A Manual Ref. |
Recommended Mitigation Measures |
Who to implement? |
When to implement? (1) |
Implementation Status (2) |
Table 6.38 |
7.2 |
Ecological Impacts on Floral Species of
Conservation Concern ¡ Erection of protective fencing to protect
the plant during construction period |
Contractor |
DC |
4 |
Table 6.40 |
7.2 |
Potential Ecological Impacts on Offsite
Habitats ¡ Good site practices for controlling the
dust and water quality (avoid stockpiles adjacent to wetlands, covering the
stockpiles with impervious sheeting, control of vehicle speed, no discharge
of silty water to the rivers, streams and drainage channels); ¡ Clear definition of works limit to avoid
impact on adjacent habitats. |
Contractor |
DC |
4 |
Table 6.39 - Table 6.45 |
7.2 |
Disturbance to Wetland-Dependent Birds,
Raptors, Terrestrial Birds and Egretry ¡ Good working practices include switching
off unused equipment, keep minimum number of powered mechanical equipment in
operation at the same period, the use of stockpiles and other structures to
form noise barriers where practicable, avoidance of feeding the wildlife to
cause disturbance, site confinement and proper cover of stockpiles with
impervious sheeting to minimize construction noise, uncontrolled surface
runoff and discharge of silts; ¡ Avoidance of construction works using
Power Mechanical Equipments within the Wetland Conservation Area during bird
migratory season (15th November – 15th March); and ¡ Restriction of excavation works within a
150m buffer zone from the egretry to ardeid non-breeding season (from August
to February). |
Contractor |
DC |
4 |
Legend: (1) DC -
During Construction
(2) 4 - Implemented
P - Partially Implemented
5 - Not Implemented
REC - Rectified by Contractor
(REC) - Partially Rectified by Contractor
! - Pending Contractor’s Rectification
Action
N/A - Not Applicable
Table E.6: Recommended Mitigation
Measures – Landscape and Visual
EIA Ref. |
EM&A Manual Ref. |
Recommended Mitigation Measures |
Who to implement? |
When to implement? (1) |
Implementation Status (2) |
|
|
Preservation of Existing
Vegetation |
|
|
|
Table 7-13 CP1 |
Table 9-1 |
¡ To retain trees
that have high amenity or ecology value and contribute most to the landscape
and visual amenity of the site and its immediate environs. |
Project Landscape Architect / Contractor |
TCP |
4 |
Table 7-13 CP1 |
Table 9-1 |
¡ Creation of
precautionary area around trees to be retained equal to half of the trees
canopy diameter. Precautionary area to be fenced. |
Project Landscape Architect / Contractor |
BCP |
4 |
Table 7-13 CP1 |
Table 9-1 |
¡ Prohibition of the
storage of materials including fuel, the movement of construction vehicles,
and the refuelling and washing of equipment including concrete mixers within
the precautionary area. |
Project Landscape Architect / Contractor |
TCP |
P, ! |
Table 7-13 CP1 |
Table 9-1 |
¡ Phased segmental
root pruning for trees to be retained and transplanted over a suitable period
(determined by species and size) prior to lifting or site formation works
which affect the existing rootball of trees identified for retention. The
extent of the pruning will be based on the size and the species of the tree
in each case. |
Project Landscape Architect / Contractor |
TCP |
4 |
Table 7-13 CP1 |
Table 9-1 |
¡ Pruning of the
branches of existing trees identified for transplantation and retention to be
based on the principle of crown thinning maintaining their form and amenity
value. |
Project Landscape Architect / Contractor |
TCP |
4 |
Table 7-13 CP1 |
Table 9-1 |
¡ The watering of
existing vegetation particularly during periods of excavation when the water
table beneath the existing vegetation is lowered. |
Project Landscape Architect / Contractor |
TCP |
N/A |
Table 7-13 CP1 |
Table 9-1 |
¡ The rectification
and repair of damaged vegetation following the construction phase to its
original condition prior to the commencement of the works or replacement
using specimens of the same species, size and form where appropriate to the
design intention of the area affected. |
Project Landscape Architect / Contractor |
TCP |
N/A |
Table 7-13 CP1 |
Table 9-1 |
¡ All works
affecting the trees identified for retention and transplantation will be
carefully monitored. This includes the
key stages in the preparation of the trees, the implementation of protection
measures and health monitoring through out the construction period. |
Project Landscape Architect / Contractor |
TCP |
P, ! |
Table 7-13 CP1 |
Table 9-1 |
¡ Detailed landscape
and tree preservation proposals will be submitted to the relevant government
departments for approval under the lease conditions and in accordance with
ETWB TCW No. 2/2004 and WBTC No. 3/2006. |
Project Landscape Architect / Contractor |
TCP |
P |
Table 7-13 CP1 |
Table 9-1 |
¡ The tree
preservation works should be implemented by approved Landscape Contractors
and inspected and approved on site by a qualified Landscape Architect. A tree
protection specification would be included within the contract documents. |
Contractor |
TCP |
4 |
|
|
Preservation of Existing
Topsoil |
|
|
|
Table 7-13 CP2 |
Table 9-1 |
¡ Topsoil disturbed during the construction
phase should be tested using a standard soil testing methodology and where it
is found to be worthy of retention stored for re-use. |
Contractor |
TCP |
4 |
Table 7-13 CP2 |
Table 9-1 |
¡ The soil will be stockpiled to a maximum
height of 2m and will be either temporarily vegetated with hydroseeded grass
during construction or covered with a waterproof covering to prevent erosion. |
Contractor |
TCP |
4 |
Table 7-13 CP2 |
Table 9-1 |
¡ The stockpile should be turned over on a
regular basis to avoid acidification and the degradation of the organic
material, and reused after completion. Alternatively, if this is not
practicable, it should be considered for use elsewhere, including other
projects. |
Contractor |
TCP |
4 |
|
|
Permanent and Temporary
Works Areas |
|
|
|
Table 7-13 CP3 |
Table 9-1 |
¡ Where appropriate to the final design the
landscape of these works areas should be restored following the completion of
the construction phase. |
Contractor |
TCP |
N/A |
Table 7-13 CP3 |
Table 9-1 |
¡ Construction site controls should be
enforced including the storage of materials, the location and appearance of
site accommodation and the careful design of site lighting to prevent light
spillage. |
Contractor |
TCP |
4 |
|
|
Mitigation Planting |
|
|
|
Table 7-13 CP4 |
Table 9-1 |
¡
Replanting
of disturbed vegetation should be undertaken at the earliest possible stage
of the construction phase. |
Contractor |
TCP |
N/A |
Table 7-13 CP4 |
Table 9-1 |
¡ Use of native plant species predominantly
in the planting design for the buffer areas. |
Contractor |
TCP |
N/A |
Table 7-13 CP4 |
Table 9-1 |
¡ The tree planting works should be
implemented by approved Landscape Contractors and inspected and approved on
site by a qualified Landscape Architect. A tree planting specification would
be included within the contract documents. |
Contractor |
TCP |
N/A |
|
|
Transplantation of Existing Trees |
|
|
|
Table 7-13 CP5 |
Table 9-1 |
¡ The tree transplanting works should be
implemented by approved Landscape Contractors and inspected and approved on
site by a qualified Landscape Architect. A tree protection / transplanting
specification would be included within the contract documents. |
Contractor |
PTCPW |
N/A |
|
|
Design of the Fence and associated Structures |
|
|
|
Table 7-14 OP1 |
Table 9-2 |
Design of Boundary Fence, 1.
Integrated
design approach – the boundary fence should integrated, as far as technically
feasible, with existing built structures such as existing road, footpath and
track and embankment of fishponds,
river and drainage channel as part of design mitigation measures to reduce
the potential cumulative impact of the proposed works. The location and
orientation of the police check points should be away from landscape and
visually sensitive areas such wetland, fishpond and agricultural field. 2.
Building
massing - the proposed use of simple responsive design for the built
structures with a low building height profile to reduce the potential visual
mass of the structure within a rural context. 3.
Treatment
of built structures - the architectural design should seek to reduce the
apparent visual mass of the facilities further through the use of natural
materials such as wooden frame, vertical greening or other sustainable
materials such as recycled plastic. 4.
Responsive
building and fence finishes - In terms of the proposed finishes natural tones
should be considered for the colour palette with non-reflective finishes are
recommended to reduce glare effect. The use of colour blocking on the
proposed fence could be used to break up the visual mass of the structure. 5.
Responsive
lighting design – Aesthetic design of architectural and track lighting with
following glare design measures: -
Directional
and full cut off lighting is recommended particularly for areas adjacent to
existing village to minimise light spillage. -
Minimise
geographical spread of lighting, only applied for safety and security
reasons; -
Limited
lighting intensity to meet the minimum safety and operation requirement; and - High-pressure sodium road lighting is recommended for more stringent light control reducing spillage and thus visual impacts. |
ArchSD |
TDP |
P |
|
|
Compensatory Planting Proposals |
|
|
|
Table 7-14 OP2 |
Table 9-2 |
¡ Utilise native to |
Contractor |
TDP |
P |
Table 7-14 OP2/3 |
Table 9-2 |
¡ A qualified or registered landscape
architect will be involved in the design, construction supervision and
monitoring, and maintenance period to oversee the implementation of the
recommended landscape and visual mitigation measures including the tree
preservation and landscape works on site. |
Contractor |
TDP |
4 |
Table 7-14 OP2 |
Table 9-2 |
Tree
and Shrub Planting – Given the rural nature of the proposed alignment it is
recommended that the where possible tree and shrub species which are native
to |
Contractor |
TDP |
P |
Table 7-14 OP2 |
Table 9-2 |
Compensatory
Planting Proposals – Given the works extent is largely limited along existing
roadside embankment to minimise impact to existing village settlements and
valuable landscape resources such as wetland, fishpond, stream course and
existing trees, and considered the importance of tree retention within the
works area, new tree planting will concentrate in selected new amenity areas
along the alignment, infilling between retained and transplanted trees. The
preliminary planting proposals for the proposed works include the planting of
some 357 new trees utilising a combination of mature to light standard sized
stock (i.e. approximately 15% of mature trees, 75% of standard trees, and 10%
light standard trees). These trees will be planted in woodland clumps and
small tree groups at strategic locations to de-emphasise the horizontality of
the fence alignment. Based on preliminary findings the proposed planting will
result in a compensatory planting ratio of 1:1 (new planting: trees
recommended for felling). This compares favourably with the report's
assertion that some 357 trees would be felled due to the proposed works. With
the proposed preservation of existing trees, transplantation of trees in
conflict with the proposals and the planting of new trees the project area
will contain approximately 2000 trees. Trees forming part of the new planting
will provide screening to neighbourhood villagers and will utilise species
native to |
Contractor |
TDP |
P |
Legend: (1) TCP -
Throughout Construction Phase
BCP - Before Construction Phase Commences
PTCPW - Prior to the Commencement of the Proposed
Works
TDP - Throughout Design Phase
(2) 4 - Implemented
P - Partially Implemented
5 - Not Implemented
REC - Rectified by Contractor
(REC) - Partially Rectified by Contractor
! - Pending Contractor’s
Rectification Action
N/A - Not Applicable
Appendix F.
EM&A Schedule |
Appendix G.
Calibration Certificates |
Table I.1: Monthly Summary Waste Flow
Table for 2010
|
Actual Quantities of Inert C&D
Materials Generated Monthly (in ‘000 m3) |
Actual Quantities of C&D Wastes
Generated Monthly |
||||||||||||||||||
Month |
Total Quantity Generated |
Broken Concrete |
Reused in the Contract |
Reused in other Projects |
Disposed of at Public Fill |
Metals (‘000 kg) |
Paper/ Cardboard (‘000 kg) |
Plastics (‘000 kg) |
Chemical waste (‘000 kg) |
Others (e.g. refuse) (‘000 m3) |
||||||||||
|
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Jan |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
Feb |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
- |
Mar |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
Apr |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
May |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0.0195 |
Jun |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
Sub-total |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0.0195 |
Jul |
- |
0.0195 |
- |
0 |
- |
0 |
- |
0 |
- |
0.0195 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0.013 |
Aug |
- |
0.1625 |
- |
0 |
- |
0 |
- |
0 |
- |
0.1625 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0.013 |
Sep |
- |
0.2405 |
- |
0 |
- |
0 |
- |
0 |
- |
0.2405 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
Oct |
- |
0.0780 |
- |
0 |
- |
0 |
- |
0 |
- |
0.0780 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0.0007 |
Nov |
- |
0.1755 |
- |
0 |
- |
0 |
- |
0 |
- |
0.1755 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
Dec |
- |
0.2925 |
- |
0 |
- |
0 |
- |
0 |
- |
0.2925 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0.0065 |
Total |
- |
0.9685 |
- |
0 |
- |
0 |
- |
0 |
- |
0.9685 |
- |
0 |
- |
0 |
- |
0 |
- |
0 |
- |
0.0527 |
Table J.1: Complaint Log for the Reporting Month (December 2010)
Log Ref. |
Location |
Complainant / Date of Contact |
Details of Complaint |
Investigation / Mitigation Action |
File Closed |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Note: No environmental complaint was received
in December 2010.
Appendix K.
Weather Information from Hong Kong Observatory |
This
Appendix presents wind data obtained from the nearest Hong Kong Observatory
monitoring station, at Ta Kwu Ling, during noise impact monitoring days.