TABLE OF CONTENTS
Monitoring Parameter, Frequency and Schedule
3. ENVIRONMENTAL
SITE INSPECTION
Review of Environmental Monitoring Procedures
Assessment of Environmental Monitoring Results
Advice on the Solid and Liquid Waste Management
Status
Environmental Licences and Permits
Implementation Status of Environmental
Mitigation Measures
Summary of Exceedances of the Environmental
Quality Performance Limit
Summary of Complaints, Notifications of Summons
and Successful Prosecutions
Construction Programme for the Coming Months
Monitoring Schedule for the Coming Months
5. CONCLUSIONS AND RECOMMENDATIONS
List of Tables
Table 1.1 Contact Information of Key Personnel
Table 2.1 Air Quality Monitoring Equipment
Table 2.2 Frequency of Air Quality Monitoring
Table 2.3 Air Quality Monitoring Stations
Table 2.4 Summary of 1-hr TSP Monitoring Results
Table 2.5 Summary of 24-hr TSP Monitoring Results
Table 3.1 Actual Amounts of Waste Generated in June 2008
Table 3.2 Summary of Environmental Licensing and Permit Status
Table 3.3 Summary of Environmental Complaints and Prosecutions
List of Figures
Figure 1.1 General
Site Layout for TKO Area 137
Figure 2.1 Air
Quality Environmental Monitoring Station for TKO Area 137
Appendices
Appendix A Project
Organization Chart
Appendix B Construction
Programme
Appendix C Action
and Limit Levels for Air Quality
Appendix D Monitoring
Schedule for June 2008
Appendix E Calibration
Certificates
Appendix F Air Quality
Monitoring Results and Graphical Presentation
Appendix H ET’s Site Inspection Summary
Appendix I Implementation
Schedule of Mitigation Measures (EMIS)
Appendix L Tentative
Schedule for July 2008
Appendix M Cumulative
Statistics on Complaints
Introduction
This
is the thirty-second monthly Environmental Monitoring and Audit (EM&A)
report prepared by Maunsell Environmental Management Consultants Limited
(MEMCL), which changed the name to ENSR Asia (HK) Ltd. (ENSR) on 1 May 2007 for
the “Temporary Construction Waste Sorting Facility at Tseung Kwan O Area 137”
(the Project). This report documents the findings of EM&A Works conducted
during the impact period in June 2008 for Tseung Kwan O Area 137.
As advised by
the Contractor, the project commenced on 12 November 2005. The construction
activities in June 2008 were:
l
Operation of Construction Waste Sorting Facilities
(CWSF) by mechanical sorting plant;
l
Disposal of sorted waste to Landfill and Fill Bank;
l
Maintenance work for haul road and mechanical
sorting plant; and
l
Operation of sorting facility at Area B3 and Area
A2.
Environmental
Monitoring Works
Air Quality
1-hr TSP Monitoring
All
the monitoring data complied with the AL levels in the reporting month. The
1-hr TSP monitoring results remained at an acceptable level during the
construction and operation of the temporary CWSF.
24-hr TSP Monitoring
All
the monitoring data complied with the AL levels in the reporting month. The
24-hr TSP monitoring results remained at an acceptable level during the construction
and operation of the temporary CWSF.
Complaints, Non-compliance and
Prosecutions
Following up
with the complaints received in the previous month, emission of smoke and
malodour from the non-inert waste stockpile in Area A2 had
been ceased since the fire was extinguished on 22 May 2008. More dump trucks
had been deployed to hasten the removal of non-inert
waste in Area A2.
No
complaint, non-compliance or prosecution was received in the reporting month.
Permits and Licences
No
new permit or license was obtained in the reporting month.
Environmental Site Inspection
There were 4 site inspections conducted in June
2008. General refuse and blockage were observed inside the u-channel in Area B2
and inside the u-channel next to the trapezoidal channel in
Area A respectively. The
Contractor was reminded to remove the refuse and properly maintain the drainage
system.
Silt was observed accumulated
in the desilting pit next to the trapezoidal channel in Area A. The Contractor
was reminded to clear the silt regularly. The Contractor was also reminded to provide
tarpaulin sheets under plants during maintenance.
Oil
stains were observed beside generator no.1 next to the Contractor’s site office
in Area B1. The Contractor was reminded to clear the oil stain and disposed of
as chemical waste.
Sand
bund and temporary channel leading to a temporary soakaway pit was provided
along the edge of the trapezoidal channel in Area A2. Site runoff without
treatment was found discharged to the trapezoidal channel. The Contractor was
reminded to provide proper drainage system to collect the site runoff water to
prevent untreat runoff, divert all site runoff to soakaway pits or divert all
treated runoff to designated discharge point for discharge.
Future Key Issues
The
weather is expected to be wet and windy in the forthcoming month and as such,
the Contractor should provide
preventive measures to prevent surface runoff, such as bunding around the site boundaries, and to confirm that
a functional temporary drainage
system is in place around the site. The Contractor should also maintain sufficient
dust suppression measures for vehicle movement along haul roads and during
sorting activities during sunny days. It
is recommended to implement sufficient mitigation measures to eliminate dust
generation from dumping and sorting activities.
It
is also recommended to implement all necessary preventive measures to avoid oil
leakage on ground/soil, such as provision of drip trays for all oil
drums/chemical containers and placement of tarpaulin sheets on the ground
during maintenance of equipment on site. In the event of any oil leakage
problem, the Contractor should properly remove the leaked oil and handle the
contaminated soil as chemical waste.
1.1
Maunsell Environmental Management
Consultants Limited (MEMCL), which changed the name to ENSR Asia (HK) Ltd.
(ENSR) on 1 May 2007 was commissioned by Paul Y. – CREC(HK) Joint Venture to
undertake the Environmental Monitoring and Audit (EM&A) works for the
construction phase of the Temporary Construction Waste Sorting Facility (CWSF)
at Tseung Kwan O Area 137 (TKO 137) (hereafter called “the Project”).
1.2
An Environmental Permit (No.:
EP-134/2002/F) was granted to the Project on 26 January 2006. The scale and
scope of this project as stated in the EP include:
·
Site clearance;
·
Construction of a temporary storm water system;
·
Stockpiling of 6 million m3 of public
fill;
·
Setting up two barging points: one at the Tseung
Kwan O Basin (TKO Basin) and one at the Construction and Demolition Material
Sorting Facility (C&DMSF) for transporting the stockpiled public fill by
barges;
·
Setting up a temporary barging point at the
existing Explosives Off-loading Barging Point located in the south-eastern part
of Area 137 for the period of May 2004 to December 2004 for transporting the
stockpiled public fill by barge;
·
Construction and operation of a C&DMSF;
·
Setting up a Construction and Demolition Material
Crushing Facility at the TKO Basin; and
·
Remove the temporary fill bank.
1.3
Under the EP, construction and
operation of the construction and demolition material sorting facility is
within the scope. Therefore, the said activities in the temporary CWSF in TKO
137 are under the governance of the EP.
1.4
In accordance with the Particular
Specification of the Project, baseline monitoring was not required. However,
the baseline conditions as well as action and limit levels of the Project was
established based on the baseline data collected by Fill Bank at TKO 137.
1.5
This is the thirty-second monthly
Environmental Monitoring and Audit (EM&A) Report under Contract CV/2004/13
– Temporary Construction Waste Sorting Facilities at Tseung Kwan O Area 137 and
Tuen Mun Area 38. This report presents a summary of the environmental
monitoring and inspection works, list of activities, and mitigation measures
carried out by the ET for the temporary CWSF at TKO 137 in June 2008.
1.6
The project organization is shown
in Appendix A.
1.7
The key personnel contact names
and numbers are summarised in Table 1.1
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
CEDD |
Engineer |
Mr. Lawrence Ng |
2762 5582 |
2714 0113 |
IEC(MateriaLab) |
IEC |
Mr.
Joseph Poon |
2450
8238 |
2450
6138 |
Contractor (Paul Y -CREC(HK) JV) |
Project
Manager |
Mr.
Joe Au |
9378 3331 |
2623 9426 |
Site
Agent |
Mr.
Y T Wong |
9475
6376 |
-- |
|
ET (ENSR) |
ET Leader |
Mr. Y T Tang |
2893 1551 |
2891 0305 |
1.8
The construction phase of the
Project commenced on 12 November 2005. As informed by the Contractor, the
activities during this reporting month included:
l
Operation of Construction Waste Sorting Facilities
(CWSF) by mechanical sorting plant;
l
Disposal of sorted waste to Landfill and Fill Bank;
l
Maintenance work for haul road and mechanical
sorting plant; and
l
Operation of sorting facility at Area B3 and Area
A2.
1.9
The general layout plan of the
Project sites showing the contract areas are shown in Figure 1.1.
1.10
The construction programme is
provided in Appendix B.
1.11
Air quality monitoring is
required under the Particular Specification of the Project. The description and
detailed monitoring requirements for air quality are provided in Section 2 of
this Report.
1.12
Environmental site inspection is
required by the ET on a weekly basis. Detailed inspection requirements are
provided in Section 3 of this Report.
2.1
In accordance with the Particular Specification of
the Project, ET is required to conduct 1-hr and 24-hr TSP monitoring at the
temporary CWSF in TKO 137 during the construction and operation periods to
ensure the activities in the Project does not generate dust which exceeds the
acceptable level. Appendix C shows the Action and Limit Levels for the
environmental monitoring works.
2.2
High volume sampler (HVS - Model
GS-2310 Accu-vol) complete with the appropriate sampling inlets was installed
for 24-hr TSP sampling. The HVS is composed of a motor, a filter holder, a flow
controller and a sampling inlet and its performance specification complies with
USEPA Standard Title 40, Code of Federation Regulations Chapter 1 (Part 50
Appendix B). A portable dust meter was used for the 1-hr TSP monitoring. Table
2.1 summarises the equipment used.
Table 2.1 Air Quality Monitoring Equipment
Equipment |
Model |
HVS |
GS 2310
Accu-vol system |
Calibrator |
GMW 25 |
1-hour TSP Dust Meter |
Laser Dust
Monitor – Model LD-3 |
Calibrator – Dust Meter |
Rupprecht & Patashnick TEOM® |
Monitoring Parameter, Frequency and Schedule
2.3
The monitoring parameters and
frequency are summarised in Table 2.2. The monitoring schedule for the
reporting period is shown in Appendix D.
Table 2.2 Frequency of Air Quality Monitoring
Parameters |
Frequency |
24-hour TSP |
Once/week |
1-hour TSP |
Three times/week |
2.4
The location for the air quality
monitoring station TKO2 is provided in Table 2.3 and depicted in Figure 2.1.
Table 2.3 Air Quality Monitoring Stations
Station
ID |
Identity/Description |
TKO2 |
Combined Reception & Exit Office in Area B1 |
24-hour TSP Monitoring
Operating/Analytical Procedures
2.5
Operating/analytical
procedures for the operation of HVS are as follows:
·
The sampler was placed on a horizontal platform
with appropriate supporting structure such that:
-
no two samplers were placed less than 2 metres
apart.
-
the distance between the sampler and an obstacle,
such as buildings, was at least twice the height that the obstacle protrudes
above the sampler.
-
a minimum of 2 metres separation from walls,
parapets and penthouses was required for the rooftop samplers.
-
a minimum of 2 metres separation from any
supporting structure, measured horizontally was required.
-
airflow around the sampler was unrestricted.
-
no furnaces or incineration flues were operating
near the sampler.
-
the sampler was more than 20 metres from the
dripline.
-
Any wire fence and gate, to protect the sampler,
should not cause any obstruction during monitoring.
·
Prior to the commencement of the dust sampling, the
flow rate of the high volume sampler was properly set (between 1.1 m3/min.
and 1.4 m3/min.) in accordance with the manufacturer's instruction
to within the range recommended in USEPA Standard Title 40, CFR Part 50.
·
For TSP sampling, fibreglass filters (G810) were
used [Note: these filters have a collection efficiency of > 99% for
particles of 0.3 mm diameter].
·
After sampling, the filter was transferred from the
filter holder of the HVS to a sealable plastic bag and sent to the laboratory
for weighing. The elapsed time was also recorded.
·
Before weighing, all filters were conditioned for
24 hours before weighing under temperature of 25°C ±3°C and the relative
humidity (RH) < 50% ±5%, preferably 40%.
·
All measurement procedures in section 4.3 to 4.9 of
the EM&A Manual were followed during the reporting period.
Maintenance
2.6
Proper
maintenance would be provided for the HVS:
·
The HVS motors and their accessories have been
properly maintained. Appropriate maintenance such as routine motor brushes
replacement (time interval for replacement is about 500 hours) and electrical
wiring checking have been conducted to ensure that the equipment and necessary
power supply were in good working condition.
1-hour TSP Monitoring
Measuring Procedures
2.7
The sampler was
placed with appropriate supporting structure. The requirements of the location
of the sampler were the same as HVS and were presented in Section 2.5 of this
report.
2.8
The measuring
procedures of the 1-hour dust meter were in accordance with the Manufacturer’s
Instruction Manual as follows:
·
Set POWER to “ON”, push BATTERY button, make sure
that the meter’s indicator is in the range with a red line and allow the
instrument to stand for about 3 minutes (Then, the air sampling inlet has been
capped).
·
Push the knob at MEASURE position.
·
Push “O-ADJ” button. (Then meter’s indication is
0).
·
Push the knob at SENSI ADJ position and set the
meter’s indication to S value described on the Test Report using the trimmer
for SENSI ADJ.
·
Pull out the knob and return it to MEASURE
position.
·
Push “START” button.
·
All measurement procedures in section 4.3 to 4.9 of
the approved EM&A Manual were followed during the impact monitoring period.
Maintenance
2.9
Air suction
inlet was normally closed unless in operation. Regular cleaning of the air
suction inlet was provided.
Wind Data
2.10
Historically, the meteorological
data for Fill Bank operations at the site was obtained from the in-situ wind
station for TKO 137 under previous contracts. Therefore, such practice would be
maintained to ensure consistence of meteorological data for the contract in the
Fill Bank.
Calibration Details
24-hour TSP Monitoring
2.11
The HVS was calibrated upon installation on site
and prior to commissioning. Subsequent calibration would be provided at 2-month
intervals using GMW-25 Calibration Kit. The flow rate of the HVS with mass flow
controller was calibrated using an orifice calibrator. Five-point calibration
was adopted.
2.12
The HVS was calibrated on 28
April 2008 Calibration details are provided in Appendix E.
1-hour TSP Monitoring
2.13
The 1-hour TSP meters were
checked at 3-month intervals to confirm normal operation of the equipment and
calibrated at 1-year interval throughout all stages of the air quality impact
monitoring.
2.14
The
1-hour TSP meters were calibrated on 16 June 2008 and the next calibration will
be conducted by 14 June 2009.
2.15
In the reporting month, all the
1-hr and 24-hr TSP monitoring events were carried out in accordance with the
schedule.
2.16
The actual monitoring program for
June 2008 is presented in Appendix D. All monitoring data and graphical
presentations of the monitoring results are provided in Appendix F. Table 2.4
lists out three 1-hr TSP monitoring results and Table 2.5 lists out all the
24-hr TSP monitoring results.
Table 2.4 Summary of 1-hr TSP Monitoring Results
Date |
TKO2 |
Monitoring Status |
|||
1st 1-hr TSP (mg/m3) |
2nd 1-hr TSP (mg/m3) |
3rd 1-hr TSP (mg/m3) |
Exceedance1 |
||
07/06 |
74.0 |
73.0 |
75.5 |
X |
Regular |
13/06 |
81.7 |
82.5 |
83.2 |
X |
Regular |
19/06 |
105.0 |
104.0 |
102.6 |
X |
Regular |
25/06 |
76.5 |
75.8 |
77.1 |
X |
Regular |
1. L – limit level exceedance;
A - action level exceedance; X – not
an exceedance
Table 2.5 Summary of 24-hr TSP Monitoring Results
Date |
TKO2 |
Monitoring Status |
|
24-hr TSP (mg/m3) |
Exceedance1 |
||
06/06 |
73.5 |
X |
Regular |
12/06 |
59.9 |
X |
Regular |
18/06 |
41.1 |
X |
Regular |
24/06 |
150.7 |
X |
Regular |
1. L – limit
level exceedance; A - action level
exceedance; X – not an exceedance
2.17
There was
no exceedance of 1-hour and 24-hour TSP monitoring recorded in the reporting
month.
2.18
Besides
the construction activities inside the Project site, other potential dust
sources included the dump truck traffic, dumping and manual sorting of inert
waste inside the Fill Bank of TKO 137.
2.19
Wind data, including wind speed
and wind direction, are annexed in Appendix G.
3. ENVIRONMENTAL SITE INSPECTION
3.1
Environmental site
inspections are required to inspect the construction activities and operation
of the temporary CWSF in order to ensure that appropriate environmental
protection and pollution control mitigation measures are properly implemented.
3.2
There were 4 site inspections conducted in June
2008 for the temporary CWSF at TKO 137 on
6, 11, 19, and 26 June
2008.
3.3
Site inspections were carried out by ET to monitor
the implementation of proper environmental pollution control and mitigation
measures for the Project. After the site inspection, the Contractor was
notified of the ET’s observations and recommendations. A corrective action plan
detailing the environmental observations had also been prepared by the ET. The
Contractor then completed this plan to propose/report their remedial works.
This corrective action plan submission procedure was adopted for each
subsequent ET’s inspection to notify all the relevant parties of the
Contractor’s follow up actions. The site inspection summaries are attached in
Appendix H. Particular observations are described as follows:
Air Quality
·
Automatic wheel washing
facilities were installed at the site egress of the Project.
·
Although the weather
condition was sometimes rainy in the reporting month, water truck was deployed
for dust suppression for dumping and sorting activities.
·
Vehicles were travelling below the speed limit in
the temporary CWSF. There were sufficient speed limit signs on site to advise
the drivers.
Noise
·
The major noise source was vehicle movement in the
temporary CWSF. Since the nearby NSRs were remote from the temporary CWSF, the
noise impact was minimal. There was no specific observation noted regarding
noise issue.
Water Quality
·
The u-channel next to the trapezoidal channel in
Area A was found blocked and muddy water was overflowed into the trapezoidal
channel directly without passing the desilting pit. The Contractor was
requested to clear the blockage in the u-channel and properly maintain the
drainage system, particularly during wet season.
·
Deposited silt was observed accumulated in the
desilting pit next to the trapezoidal channel in Area A next to the CEDD site
office and deposited silt and general refuse was observed inside the u-channel
in Area B2. The Contractor was reminded to remove the silt and refuse and
properly maintain the drainage system.
·
Sand bund and temporary channel leading to a
temporary soakaway pit was provided along the edge of the trapezoidal channel
in Area A2. Minor site runoff without treatment was found discharged to the
trapezoidal channel. The Contractor was reminded to provide proper drainage
system to collect the site runoff water to prevent untreat runoff, divert all
site runoff to soakaway pits or divert all treated runoff to designated
discharge point for discharge.
·
Besides the afore-said issues, it was recommended
to arrange maintenance for the silt traps at the wheel washing bays before and
after rainstorms so as to ensure their maximum treatment capacities.
Chemical and Waste Management
·
No tarpaulin sheet was provided to excavators C7
and C13 next to the trapezoidal channel in Area A and oil stain was observed
under excavator C7. The Contractor was reminded to provide tarpaulin sheets
under the plants, clear the oil stain and dispose of the contaminated soil as
chemical waste.
·
Oil stains and oily water were observed beside
generator no.1 next to the Contractor’s site office in Area B1. The Contractor
was reminded to clear the oil stains and oily water and disposed of as chemical
waste.
·
A hole was found on the drip tray under a generator
on the VGF tipping hall in Area A. The Contractor was requested to seal the
hole on the drip tray to prevent oil leakage.
·
The Contractor provided waste skips to collect general
refuse and would dispose of them regularly to the SENT Landfill.
Landscape and Visual
·
Hoarding was erected at the site egress and aligned
along the site boundary in connection with the Fill Bank at TKO 137.
Review of Environmental Monitoring Procedures
3.4
The monitoring works conducted by the ET were
inspected regularly. The observations for the monitoring works were recorded
and summarised as follows:
·
The monitoring team recorded the observations
around the monitoring stations within and outside of the construction site.
·
The monitoring team recorded the temperature, air
pressure and general weather condition on the monitoring day.
Assessment of Environmental Monitoring Results
3.5
All monitoring results were audited against the A/L
levels and any exceedances would be validated.
3.6
The monitoring results in this reporting period
were comparable with the established action and limit levels.
Advice on the Solid and Liquid Waste Management Status
3.7
As advised by the Contractor,
there were disposal of sorted inert material, sorted non-inert material and
metal in the reporting month. The actual amounts of different types of waste
generated by the activities of the Project in the month are shown in Table 3.1.
Table 3.1 Actual Amounts of Waste Generated in June 2008
Waste Type |
Actual Amount |
Disposal Locations |
Public fill
collected |
48611.5 ton |
- |
Sorted waste (inert material) |
5276.72 ton |
TKO Fill Bank |
Sorted waste (non-inert material) |
42124.21 ton |
SENT Landfill |
Recycling (Metal) |
19.72 ton |
Recycling companies |
Non-inert
C&D waste |
0 ton |
SENT Landfill |
Inert C&D
waste |
0 ton |
TKO Fill Bank |
Chemical waste |
0 kg |
Chemical Waste Treatment Centre |
3.8
The Contractor should provide sufficient drip trays
for all the oil drums/chemical containers. Besides, these drip trays should be
covered by tarpaulin sheet to minimize rainfall accumulation.
3.9
The Contractor should use suitable containers with
proper labels to store chemical wastes inside a designated chemical waste store
in accordance with Code of Practice on the
Packaging, Labelling and Storage of Chemical Wastes. The Contractor should also
advise their workers of the proper procedures in handling the chemical waste. All the trip
tickets for chemical waste disposal were properly kept in the site office. No
disposal of chemical waste was undertaken in the reporting month.
3.10
The Contractor should provide sufficient preventive
measures during equipment maintenance works so as to avoid oil leakage on the
ground. In the event of any oil leakage, the Contractor should clean up the
polluted soil and handle all the materials using for this cleaning works as
chemical waste.
Environmental Licences and Permits
3.11
No new environmental license and permit was
obtained in the reporting month.
3.12
The status of all permits/licences obtained/in use
during the reporting period are summarised in Table 3.2.
Table
3.2 Summary of Environmental
Licensing and Permit Status
Description |
Permit No. |
Valid Period |
Remarks |
|
From |
To |
|||
Environmental Permit |
EP-134/2002/F |
26/1/06 |
- |
(Valid) ·
Site
clearance ·
Construction
of a temporary storm water system ·
Stockpiling
of 6 million m3 of public fill ·
Setting
up two barging points for transporting the stockpiled public fill by barges ·
Setting
up a temporary barging point at the existing Explosive Off-loading Barging
Point for the period of May 2004 to December 2004 for transporting the
stockpiled public fill by barge ·
Construction
and operation of a Construction and Demolition Material Sorting Facility
(C&DMSF) ·
Setting
up a Construction and Demolition Material Crushing Facility at the ·
Remove
the temporary fill bank |
Registration as
a Chemical Waste Producer |
5213-839-P2896-01 |
25/1/06 |
-- |
(Registered) |
Certificate of
Approval – Air Pollution Control (Furnaces, Ovens and Chimneys) (Installation
and Alteration) Regulations |
-- |
4/9/06 |
-- |
(Approved) |
Effluent
Discharge License |
RE/D1180/839/1 |
13/11/06 |
30/11/11 |
(Valid) |
Implementation Status of Environmental Mitigation Measures
3.13
An updated summary of the Environmental Mitigation
Implementation Schedule (EMIS) is presented in Appendix I. Most of the
necessary mitigation measures were implemented properly. Any deficiencies were
noted in the remarks of the schedule.
Summary of Exceedances of the Environmental Quality Performance Limit
3.14
There was no exceedance of 1-hour and 24-hour TSP
monitoring recorded in the reporting month.
3.15
The event action plans are attached in Appendix J.
Summary of Complaints, Notifications of Summons and Successful
Prosecutions
3.16
Following up with the complaints received in the
previous month regarding the nuisance caused by open burning, heavy smoke and
malodour, emission of smoke and malodour from the
non-inert waste stockpiled in Area A2 had been ceased, since the fire was
extinguished on 22 May 2008. During the weekly site inspections in the
reporting month, the stockpiled non-inert waste in the Area A2 was sufficiently
dampened. More dump trucks had been deployed to hasten the removal of the non-inert waste in Area A2.
3.17
No complaint, notification of summons and
prosecutions was received in the reporting month. A summary of environmental
complaints and prosecutions was given in Table 3.3 and the cumulative
statistics of complaints is presented in Appendix M.
Table 3.3 Summary of
Environmental Complaints and Prosecutions
Complaints logged |
Summons served |
Successful Prosecution |
|||
June 2008 |
Cumulative |
June 2008 |
Cumulative |
June 2008 |
Cumulative |
0 |
24 |
0 |
0 |
0 |
0 |
4. FUTURE
KEY ISSUES
Construction Programme for the Coming Months
4.1
The construction programme for
the Project is shown in Appendix B.
4.2
The activities to be conducted in
the next two months included:
l
Operation of Construction Waste Sorting Facilities
(CWSF) by mechanical sorting plant;
l
Disposal of sorted waste to Landfill and Fill Bank;
l
Maintenance work for haul road and mechanical
sorting plants; and
l
Operation of sorting facility at Area B3 and Area
A2.
4.3
Key issues to be considered in
the coming month include:
·
Removal
of non-inert waste stockpile in Area A2;
·
Chemical and waste management;
·
Treatment of runoff and
wastewater prior to discharge;
·
Dust generated from loading and
unloading activities; and
·
Dust generated from dump trucks
traffic.
4.4
The following mitigation measures
are required:
Air Quality Impact
·
To prohibit any open burning on site;
·
To provide adequate water spraying on haul roads
and working platforms;
·
To operate and maintain automatic wheel washing
facilities properly;
·
To dampen the fill material prior to unloading or
movement;
·
To provide road sweeping on all paved haul roads
and the public roads outside site egress;
·
To provide proper maintenance for equipment and
vehicles on site;
·
To ensure implementation of the dust mitigation
measures for the construction activities, if any;
·
To maintain proper operation of the mist spraying
systems;
·
To ensure vehicle speed below 10 km/hr in the
temporary CWSF;
·
To investigate any other dust sources around the
air sensitive receivers; and
·
To follow up any exceedance, if any, caused by the
temporary CWSF operation.
Noise Impact
·
To identify the noise sources inside and outside of
the site;
·
To follow up any exceedance caused by the temporary
CWSF operation;
·
To switch off equipment if not in use;
·
To operate silent equipment; and
·
To re-schedule the work activities in the event of
valid noise exceedance.
Water Quality Impact
·
To operate and maintain the wastewater treatment
facility for the site toilet;
·
To provide covers for the drip trays to avoid
stagnant water ponding due to rainfall;
·
To ensure cleanliness of
oil interceptor bypass tank and all the drainage channels;
·
To maintain the existing silt trap to ensure
sufficient treatment of wheel wash water frequently;
·
To maintain the drainage system in the temporary
CWSF; and
·
To avoid formation of any stagnant water or provide
insecticide to avoid mosquito breeding in the temporary CWSF.
Chemical and Waste Management
·
To remove waste from the site regularly;
·
To properly store and handle chemical wastes on
site;
·
To implement trip ticket system for all the
imported public fill and general refuse disposal;
·
To provide and manage sufficiently sized drip trays
for diesel drums or chemical containers;
·
To maintain proper housekeeping at the workshop
area;
·
To provide all the preventive measures during
equipment maintenance;
·
To remove the oil stains in the event of leakage
and handle all the materials using for this cleaning works as chemical waste; and
·
To identify C&D material by packaging,
labelling, storage, transportation and disposal in accordance with statutory
regulations.
Monitoring Schedule for the
Coming Months
4.5
The tentative schedule for
environmental monitoring programme for July 2008 is shown in Appendix L.
5. CONCLUSIONS
AND RECOMMENDATIONS
5.1
Environmental monitoring of air
quality (1-hr TSP and 24-hr TSP) for the Project was performed in June 2008. There was no exceedance of 1-hour and 24-hour TSP
monitoring recorded in the reporting month.
5.2
Environmental site inspections
were conducted 4 times in the reporting month. Deposited silt and general
refuse was observed inside the u-channel in Area B2 and inside the desilting
pit near CEDD site office. The Contractor was reminded to remove the refuse and
properly maintain the drainage system. The Contractor was also reminded to
provide proper drainage system in Area A2 to collect the site runoff water to
prevent untreat runoff from discharging to the trapezoidal channel.
5.3
No complaint, non-compliance,
notifications of summons or prosecutions was received in the reporting month.
5.4
According to the environmental
site inspections performed in the reporting month, the following
recommendations were provided:
Air Quality
·
Ensure the frequency of water
spraying on haul roads, unloading areas and stockpiles to be sufficient to
suppress the dust sources;
·
Provide proper maintenance for
the powered mechanical equipment and barges to avoid emission of dark smoke;
·
Provide water spraying onto the
truckloads during inspection of fill material;
·
Conduct
road sweeping on the public road and the main haul roads outside and near the
site egress by the road sweeper;
·
Undertake
water spraying on stockpiling area by water bowers;
·
Erect
adequate speed limit signs to advise the truck drivers of the speed limit;
·
Operate mist spraying systems and
automatic water sprinklers in the temporary CWSF;
·
Implement the dust mitigation measures for the
construction activities;
·
Designate proper haul roads to
ensure effective water spraying; and
·
Ensure all vehicles to be washed
before leaving the site egress by provision, operation and maintenance of
automatic wheel washing facilities.
Construction Noise
·
Conduct noisy activities at a
farther location from the NSR.
Water Quality
·
Maintain the drainage system,
including the trapezoidal channels;
·
Operate and maintain the
treatment system for the site toilet; and
·
Remove the stagnant water or
provide pesticide for the stagnant water in the permanent desilting chambers,
if any.
Chemical and Waste Management
·
Remove waste materials from site
regularly to avoid accumulation;
·
Handle and store chemical wastes
properly;
·
Remove unwanted material in the
existing stockpiles and avoid further dumping of such material;
·
Provide and maintain sufficient
drip trays for diesel drums, chemical containers, chemical waste storage drums
and diesel operated generator set;
·
Maintain good housekeeping at the
workshop area;
·
Ensure sufficient tarpaulin
sheets are provided to cover drip trays;
·
Avoid soil being polluted during
oil filling and equipment maintenance; hence, properly remove and store the
contaminated soil, if any, and
·
Provide a proper chemical waste
store.
Landscape and Visual
·
Erect all the site
hoardings/chaining fences in accordance with agreed design at proper location.