TABLE OF CONTENTS
Summary of
EM&A Programme Requirements
Monitoring
Parameters, Frequency and Duration
Summary of
Inspection – 4 November 2008
Summary of Inspection
– 18 November 2008
Next
Landscape and Visual Audit Schedule
6. ENVIRONMENTAL SITE INSPECTION
AND AUDIT
Assessment of
Environmental Monitoring Results
Advice on the
Solid and Liquid Waste Management Status
Environmental
Licenses and Permits
Implementation
Status of Environmental Mitigation Measures
Summary of
Exceedances of the Environmental Quality Performance Limit
Summary of Complaints,
Notification of Summons and Successful Prosecutions
Construction
Programme for the Coming Months
Monitoring
Schedule for the Coming Months
8. CONCLUSIONS AND RECOMMENDATIONS
List
of Tables
Table 1.1 Contact
Information of Key Personnel
Table 2.1 Air Quality
Monitoring Equipment
Table 2.2 Air Quality
Monitoring Parameters, Frequency and Duration
Table 2.3 Locations of
Air Quality Monitoring Stations
Table 2.4 Summary of
1-hour TSP Monitoring Results in the Reporting Period
Table 2.5 Summary of
24-hour TSP Monitoring Results in the Reporting Period
Table 3.1 Noise
Monitoring Equipment
Table 3.2 Locations of Noise
Monitoring Stations
Table 3.3 Summary of Noise
Monitoring Results in the Reporting Period
Table 6.1 Summary of
Environmental Licensing and Permit Status
List of Figures
Figure 2.1 Locations of Air Quality and Noise
Monitoring Stations
Figure 6.1 Environmental Complaint Handling
Procedures
List of Appendices
Appendix A Project Organization Structure
Appendix B Construction Programme
Appendix C Implementation
Schedule of Mitigation Measures (EMIS)
Appendix D Action and Limit Levels for Air Quality and Noise
Appendix E Calibration Certificates
Appendix F Air Quality Monitoring Results and
Graphical Presentation
Appendix I Noise Monitoring Results
and Graphical Presentation
Appendix J Detailed Landscape and Visual Monitoring
Report
Appendix K ET’s
Site Inspection Summaries
Appendix L Monitoring Schedules
The Project “Landslide Preventive Works at Po Shan, Mid-levels – Design
and Construction (Natural Terrain Risk Mitigation Works)” (hereafter called
“the Project”) includes the installation of about 700 numbers of soil nails and
about 60 numbers of raking drains on the natural terrain within the concerned
area.
The impact environmental monitoring and audit for the Project includes
the air quality, noise, ecology, landscape and visual monitoring. The
construction of the Project and the EM&A programme commenced on 1 April
2008.
This report documented the findings of EM&A works conducted in the
period between 1 and 30 November 2008. As informed by the Contractor,
construction activity in the reporting period were:
-
Soil nail
installation at Portion B1 and Portion C; and
-
Soil nail head construction at
Portion A1.
Breaches of Action and Limit
Levels
There was no action / limit level exceedance recorded for 1-hour and
24-hour TSP monitoring.
In the reporting month, all noise level recorded complied with the limit
level.
Complaint, Notification of
Summons and Successful Prosecution
There was no complaint, notification of summons and successful
prosecution received in the reporting month.
Reporting Change
There was no reporting change required in the reporting month.
Future Key Issues
The weather in the forthcoming month is expected to be dry and windy. The
Contractor should maintain sufficient dust suppression measures, such as proper
treatment of exposed slope and earth, and provide water spraying to any dusty
construction activities.
It is also recommended to implement all necessary preventive measures to
avoid oil leakage on ground / soil, such as provision of drip trays for all oil
drums / chemical containers. In the event of oil leakage, the Contractor should
properly remove the contaminated soil and dispose of as chemical waste. Construction
waste and general refuse should be properly collected and disposed of.
1.1
The project site is located at the mostly
undeveloped hillside above the residential development at
1.2
The objective of the Project “Landslide Preventive
Works at Po Shan, Mid-levels – Design and Construction (Natural Terrain Risk
Mitigation Works)” under Contract CE 28/2004 (GE) is to carry out detailed
design and supervision of landslide preventive works on local repair of the
hillside to minimize slope deterioration and shallow instability.
1.3
The proposed landslide preventive works would be
constructed to protect the existing residential developments at the toe of the
project site.
1.4
The scope of works of this Project includes the
installation about 700 numbers of soil nails and about 60 numbers of raking
drains on the natural terrain within the concerned area. The length of the soil
nails is about
1.5
The Project is anticipated to complete in 10 months
after the commencement of construction.
1.6
According to the Environmental Permit (EP-235/2005/B)
and the EM&A Manual of the Project, there is a need of an EM&A
programme including air quality, noise, ecology, and landscape and visual
monitoring.
1.7
ENSR Asia (HK) Ltd. (ENSR) was employed by the
Contractor,
1.8
This is the eighth monthly Environmental Monitoring
and Audit (EM&A) Report under the Contract CE 28/2004 (GE) – Landslide
Preventive Works at
1.9
The project organization is
shown in Appendix A. The key personnel contact names and numbers are summarized
in Table 1.1
.
Table 1.1 Contact Information
of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
CEDD |
Senior Engineer |
H. W. Sun |
2762 5375 |
2714 0247 |
ER (MGS) |
Resident Engineer |
Andrew J. Westmoreland |
3188 0400 |
3188 0775 |
Assistant Resident Engineer |
S. F. Chau |
3188 0400 |
3188 0775 |
|
IEC
(ENVIRON) |
Independent
Environmental Checker |
David
Yeung |
3743
0788 |
3548
6988 |
Contractor
(CCJV) |
Project
Manager |
Eddie
Tang |
3188
0538 |
3188
1710 |
Safety
and Environmental Officer |
Ken
Fong |
3188
0538 |
3188
1710 |
|
ET
(ENSR) |
ET
Leader |
Edith
Ng |
3105
8525 |
2891
0305 |
1.10
The Contactor has carried
out major activities in the reporting month. Details of the works undertaken in
this reporting period are listed below:
-
Soil
nail installation at Portion B1 and Portion C; and
-
Soil nail head construction at
Portion A1.
1.11
The general layout plan of
the Project site showing the contract area is shown in Figure 1.1. The
construction programme is provided in Appendix B.
1.12
The mitigation measures
implementation schedule are presented in Appendix C.
Summary of EM&A Programme Requirements
1.13
The EM&A programme
required environmental monitoring for air quality, noise, ecology and landscape
and visual and environmental site inspections for air quality, noise, ecology,
landscape and visual and waste management. The EM&A requirements for each
parameter described in the following sections include:
-
All monitoring parameters;
-
Monitoring schedules for
the reporting month and forthcoming months;
-
Action and Limit levels for
all environmental parameters;
-
Event / Action Plan;
-
Environmental mitigation
measures, as recommended in the Project EIA study final report; and
-
Environmental requirement
in contract documents.
2.1
In accordance with the EM&A Manual, 1-hour and
24-hour TSP levels at 2 air quality monitoring stations were established. Impact
1-hour and 24-hour TSP monitoring was conducted for at least once every 7 days during
the construction phase of the Project. The Action and Limit level of the air
quality monitoring is provided in Appendix D.
2.2
24-hour TSP air quality monitoring was performed
using High Volume Sampler (HVS) located at each designated monitoring station.
The HVS meets all the requirements of the EM&A Manual. Portable direct
reading dust meters were used to carry out the 1-hour TSP monitoring. Table 2.1
summarises the equipment used.
Table 2.1 Air Quality
Monitoring Equipment
Equipment |
Model |
High
Volume Sampler |
GS
2310 Accu-vol system |
Calibrator |
GMW 25 |
1-hour
TSP Dust Meter |
Laser
Dust Monitor – Model LD-3 |
Monitoring Parameters, Frequency and Duration
2.3
Table 2.2 summarizes the monitoring parameters,
frequency and duration of impact TSP monitoring.
Table 2.2 Air Quality Monitoring Parameters, Frequency and Duration
Parameter |
Frequency and Duration |
|
CA1 & CA2 |
24-hour
TSP |
At least once every 7 days |
1-hour TSP |
At least 3 times every 7 days |
2.4
Both monitoring stations were set up at the
proposed locations in accordance with EM&A Manual. Table 2.3 describes
details of the two monitoring stations. The monitoring locations are shown in
Figure 2.1.
Table 2.3 Locations of Air
Quality Monitoring Stations
Monitoring Station |
Identity / Description |
CA1 |
Access
road to Po Shan Mansions |
CA2 |
Podium
of |
24-hour TSP Monitoring
Installation
2.5
The HVS was installed in the vicinity of the air
sensitive receivers. The following
criteria were considered in the installation of the HVS.
·
A horizontal platform with appropriate support to
secure the sampler against gusty wind was provided.
·
The distance between the HVS and any obstacles,
such as buildings, was at least twice the height that the obstacle protrudes
above the HVS.
·
A minimum of 2 meters separation from walls,
parapets and penthouse was required for rooftop sampler.
·
No furnace or incinerator flues were nearby.
·
Airflow around the sampler was unrestricted.
·
Permission was obtained to set up the samplers and
to obtain access to the monitoring stations.
·
A secured supply of electricity is needed to
operate the samplers.
Preparation of Filter Papers
·
Glass fibre filters, G810 were labeled and sufficient filters that were
clean and without pinholes were selected.
·
All filters were equilibrated in the conditioning environment for 24
hours before weighing. The conditioning
environment temperature was around
·
ALS Technichem (HK) Pty Ltd. has comprehensive quality
assurance and quality control programmes.
Field Monitoring
·
The power supply was checked to ensure the HVS works properly.
·
The filter holder and the area surrounding the filter were cleaned.
·
The filter holder was removed by loosening the four bolts and a new
filter, with stamped number upward, on a supporting screen was aligned
carefully.
·
The filter was properly aligned on the screen so that the gasket formed
an airtight seal on the outer edges of the filter.
·
The swing bolts were fastened to hold the filter holder down to the
frame. The pressure applied should be
sufficient to avoid air leakage at the edges.
·
Then the shelter lid was closed and was secured with the aluminum strip.
·
The HVS was warmed-up for about 5 minutes to establish run-temperature
conditions.
·
A new flowrate record sheet was set into the flow recorder.
·
The range specified in the EM&A Manual was between 0.6
·
The programmable timer was set for a sampling period of 24 hrs +
1 hr, and the starting time, weather condition and the filter number were
recorded.
·
The initial elapsed time was recorded.
·
At the end of sampling, the sampled filter was removed carefully and
folded in half length so that only surfaces with collected particulate matter
were in contact.
·
It was then placed in a clean plastic envelope and sealed.
·
All monitoring information was recorded on a
standard data sheet.
·
Filters were sent to ALS Technichem (HK) Pty Ltd. for
analysis.
Maintenance and Calibration
·
The HVS and its accessories are maintained in good working condition,
such as replacing motor brushes routinely and checking electrical wiring to
ensure a continuous power supply.
·
HVSs are calibrated using GMW-25 Calibration Kit prior to the
commencement of baseline air quality monitoring, and will be calibrated at
bi-monthly intervals throughout all stages of the impact monitoring.
·
Calibration records are shown in Appendix E.
1-hour TSP Monitoring
Measuring Procedures
2.6
The measuring procedures of the 1-hour dust meter
are in accordance with the Manufacturer’s Instruction Manual as follows:
·
Set POWER to “ON”, push
·
Push the knob at MEASURE position.
·
Push “O-ADJ” button. (Then meter’s indication is 0).
·
Push the knob at SENSI ADJ position and set the meter’s indication to S
value described on the Test Report using the trimmer for SENSI ADJ.
·
Pull out the knob and return it to MEASURE position.
·
Push “START” button.
Maintenance and Calibration
·
The 1-hour TSP meter would be checked at 3-month intervals and
calibrated at 1-year intervals throughout all stages of the air quality
baseline monitoring. Calibration records are shown in Appendix E.
2.7
The monitoring results for 1-hour TSP and 24-hour
TSP are summarized in Table 2.4 and 2.5 respectively and the monitoring results
are provided in Appendix F.
Table 2.4 Summary of 1-hour TSP Monitoring Results in the Reporting Period
|
Average
(mg/m3) |
Range
(mg/m3) |
Action
Level (mg/m3) |
Limit
Level (mg/m3) |
CA1 |
72.9 |
58.6 – 82.2 |
309.3 |
500 |
CA2 |
68.2 |
58.1 – 81.7 |
319.6 |
500 |
Table 2.5 Summary of 24-hour TSP Monitoring Results in the Reporting Period
|
Average
(mg/m3) |
Range
(mg/m3) |
Action
Level (mg/m3) |
Limit
Level (mg/m3) |
CA1 |
42.1 |
19.5 – 61.1 |
166.8 |
260 |
CA2 |
61.2 |
34.4 – 102.1 |
187.0 |
260 |
2.8
Air quality monitoring was
carried out for both 1-hour TSP and 24-hour TSP at all the monitoring stations
in the reporting month.
2.9
The air quality monitoring results, in terms of
1-hour TSP and 24-hour TSP, were below the action and limit level at both
monitoring locations in the reporting month. The event action plan is annexed
in Appendix G.
2.10
Weather information including wind speed and wind
direction is annexed in Appendix H. The information was obtained from Hong Kong
Observatory Victoria Peak Automatic Weather Station and Central Pier Anemometer
Station.
3.1
In accordance with the EM&A Manual, impact noise levels should be
obtained at 2 noise monitoring stations. Impact noise monitoring was conducted
for at least once per week during the construction phase of the Project. The
Action and Limit level of the noise monitoring is provided in Appendix D.
3.2
Integrating Sound Level Meter was employed for noise monitoring. They were Type 1 sound level meters capable
of giving a continuous readout of the noise level readings including equivalent
continuous sound pressure level (Leq) and percentile sound pressure
level (Lx). They comply with International Electrotechnical Commission
Publications 651:1979 (Type 1) and 804:1985 (Type 1). Portable electronic wind speed indicator
capable of measuring wind speed in m/s was employed to check the wind
speed. Table 3.1 details the noise
monitoring equipment used.
Table 3.1 Noise Monitoring
Equipment
Equipment |
Model |
Integrating Sound Level Meter |
Rion NL-31 |
Calibrator |
Rion NC-73 |
3.3
Two monitoring stations were set up in accordance
with EM&A Manual. Table 3.2 describes details of the two monitoring
stations. The monitoring locations are shown in Figure 2.1.
Table
3.2 Locations of Noise Monitoring
Stations
Monitoring Station |
Identity / Description |
CN1 |
Block A, |
CN2 |
Block A, |
3.4
One set of 30-mins measurement at each monitoring station between 0700
and 1900 on normal weekdays at a frequency of once per week was required to
determine the impact noise level. Leq, L10 and L90
would be recorded.
Monitoring Procedures
·
The Sound Level Meter was set on a tripod at a
height of
·
Façade measurements were made at all three monitoring
locations.
·
The battery condition was checked to ensure the
correct functioning of the meter.
·
Parameters such as frequency weighting, the time
weighting and the measurement time were set as follows:
-
frequency weighting: A
-
time weighting: Fast
-
time measurement: Leq(30 minutes) during
non-restricted hours i.e. between 07:00 and 19:00 on normal weekdays
·
Prior to and after each noise measurement, the
meter was calibrated using a Calibrator for 94 dB at 1000 Hz. If the difference in the calibration level
before and after measurement was more than 1 dB(A), the measurement would be
considered invalid and repeat of noise measurement would be required after
re-calibration or repair of the equipment.
·
The wind speed was frequently checked with a
portable wind meter.
·
During the monitoring period, the Leq ,
L10 and L90 were recorded. In addition, site conditions and noise
sources were recorded on a standard record sheet.
·
Noise measurement was paused during periods of high
intrusive noise (e.g. dog barking, helicopter noise) if possible. Observations
were recorded when intrusive noise was unavoidable.
·
Noise monitoring was cancelled in the presence of
fog, rain, wind with a steady speed exceeding
Maintenance and Calibration
·
The microphone head of the sound level meter and
calibrator is cleaned with soft cloth at quarterly intervals.
·
The meter should be checked and calibrated at yearly intervals.
·
Calibration details for the sound level meter and calibrator are
provided in Appendix E.
3.5
The monitoring results for noise are summarized in
Table 3.3 and the monitoring data is provided in Appendix I.
Table
3.3 Summary of Noise Monitoring
Results in the Reporting Period
|
Average,
dB(A), Leq (30 mins) |
Range,
dB(A), Leq (30 mins) |
Limit
Level, dB(A), Leq (30 mins) |
CN1 |
59.7 |
58.8 – 60.1 |
75.0 |
CN2 |
58.8 |
58.3 – 59.1 |
75.0 |
3.6
There was no noise complaint received in the reporting month, hence, no
action level exceedance was recorded. At both monitoring locations, CN1 and
CN2, all the monitoring results (daytime) were below the limit level of 75
dB(A).
3.7
All the monitoring results lied within the range of the predicted noise
levels in the EIA report.
3.8
Major noise sources during the noise monitoring included the
construction activities from the Project and another project under the same
contract (concurrent project) carried out in the vicinity and nearby traffic
noise.
4.1
As required under Environmental Permit No. EP-235/2005/B, the Permit
Holder is required to carry out monitoring of the plant species of conservation
interest to check on the health and condition of the plants twice a month
during the construction period of the Project.
4.2
It is required to undertake the ecological tasks to fulfill the
requirements of the Environmental Permit (EP).
As required by Conditions 2.11 and 3.5 of the EP, a suitably qualified ecologist with 7 or more years
of relevant experience shall be employed to conduct the ecological monitoring.
4.3
The ecological monitoring was carried out for plant individuals of
conservation interest identified within the proposed works area.
4.4
The ecological monitoring was conducted twice in the reporting month on 11
and 25 November 2008 by Ms. Gigi C C Lam, who had over 7 years of relevant ecological
experience.
4.5
The plants of conservation interest, which were tagged during the
baseline survey, were checked during each monitoring.
4.6
Site clearance, soil nailing and scaffolding works were in progress
during the monitoring visits. Most of the
tagged vegetation has been fenced off and was found to be in good condition
during the monitoring visits in November 2008. However, the
fencing for the tree group (V001 to V013) was found broken.
4.7
The leaves of vegetation located near the operation
of soil nailing were covered heavily
with dust.
4.8
A heavy cable of the soil nailing machine was
found hanging on tree trunk and branch T6788 and T9795.
4.9
Trunks of trees located above
5.1
During the construction phase
of the Project, landscape and visual monitoring should be carried out bi-weekly
by a Registered Landscape Architect (RLA) to check if the design, implementation
and maintenance of the landscape and visual mitigation measures are fully realized.
A detailed report is annexed in Appendix J.
Summary of Inspection – 4 November 2008
Matters Arising from Previous Inspections
5.2
Removal of construction
waste previously found piled deep around existing tree T614 was
outstanding. The Contractor was reminded
to remove the construction waste around the tree as soon as possible.
5.3
It was still observed that
the Contractor had not removed the dead trees, including a tree with rotten
trunk at the base located near existing tree T534. The Contractor was recommended to remove all
the dead and rotten trees away from the footpath area for safety.
5.4
It was still observed that
rectification of many of the tree identification numbers for the existing
retained trees were outstanding. The
Contractor was reminded to re-instate the tree numbers on existing trees for
ease of reference as soon as possible.
5.5
It was noted that
compensatory planting proposal for the replacement of dead tree T611 was
outstanding. The Contractor was
recommended to seek Engineer’s agreement on the replacement planting as soon as
possible.
5.6
It was noted that the
Contractor’s clarification of the status of existing trees T516, T517, T666,
and T698 was outstanding. The Contractor
was reminded to provide necessary information as soon as possible.
Protection of Existing Trees
5.7
It was noted that several
undersized existing trees had been unnecessarily broken. The Contractor was reminded to be more
careful in order to minimize damage on trees in future.
Recommendations
5.8
The Contractor was
recommended to remove dead / rotten trees from site for safety.
5.9
The Contractor was reminded
to rectify all ineligible tree identification numbers for all existing trees.
5.10
The Contractor was
recommended to clarify the status of missing trees as soon as possible.
5.11
The Contractor was
recommended to seek Engineer’s agreement on the replacement planting for dead
tree.
5.12
The Contractor was
recommended to clear away all construction waste away from existing tree and
not to place it against trees in future.
5.13
The Contractor was
recommended to minimize unnecessary damage on existing trees, especially the
undersized trees.
Summary of Inspection – 18 November 2008
Matters Arising from Previous Inspections
5.14
It was noted that the
Contractor had cleared out most of the construction waste piled deep around the
base of existing tree T614. However,
there are still some stones remaining and the Contractor was also reminded to
clear it away as soon as possible.
5.15
It was still observed that
the Contractor had not removed the dead trees, including a tree with rotten
trunk at the base located near existing tree T534. The Contractor was recommended to remove all
the dead and rotten trees away from the footpath area for safety.
5.16
It was still observed that
rectification of many of the tree identification numbers for the existing
retained trees were outstanding. The
Contractor was reminded to re-instate the tree numbers on existing trees for ease
of reference as soon as possible.
5.17
It was noted that the
Contractor’s clarification of the status of existing trees T516, T517, T666,
and T698 was outstanding. The Contractor
was reminded to provide necessary information as soon as possible.
Protection of Existing Trees
5.18
It was observed that the
Contractor had pruned some of the existing tree branches to facilitate soil
nailing works. However, as required
under the contract Particular Specification, the Contractor shall seek the Engineer’s
agreement prior to carry out any tree pruning works. Therefore, the Contractor was reminded to
seek Engineer’s agreement for pruning of existing trees in future.
Recommendations
5.19
The Contractor was
recommended to clear away all construction waste away from existing tree and
not to place it against trees in future.
5.20
The Contractor was reminded
to rectify all ineligible tree identification numbers for all existing trees.
5.21
The Contractor was
recommended to remove dead / rotten trees from site for safety. The Contractor
was also reminded to record and report all dead trees as found on site to the
Engineer for record.
5.22
The Contractor was
recommended to clarify the status of missing trees as soon as possible.
5.23
The Contractor was
recommended to seek Engineer’s agreement on the replacement planting for dead
tree.
5.24
The Contractor was
recommended to seek Engineer’s agreement prior to tree pruning works in future.
Next Landscape and Visual Audit Schedule
5.25
The landscape and visual
audits in the next reporting month was tentatively scheduled to 2, 16 and 30 December
2008.
6.1
Site Inspections were
carried out on a weekly basis to monitor the implementation of proper
environmental pollution control and mitigation measures for the Project. In the
reporting month, 4 site inspections were carried out on 4, 11, 18 and 25 November
2008. The detail findings of the landscape and visual audits in the reporting
month are presented separately in Section 5. The environmental site inspection
summaries are attached in Appendix K. Particular observations are described
below.
Air Quality
6.2
Exposed earth / sediment was observed accumulated
on the slope of
Noise
6.3
No adverse observation was
identified in the reporting month.
Water Quality
6.4
Deposited silt was observed
accumulated inside the u-channel at Row T. The Contractor was requested to
clear the deposited silt more frequently.
Chemical and Waste Management
6.5
Soil nail installation controllers and chemical
containers were found placed on ground without drip tray at Row AM, Row AO, Row
AF, Row AP and Row AW. The Contractor was reminded to provide drip trays to all
plants and chemical containers on site.
Ecology
6.6
A heavy cable of the soil nailing machine was found
hanging on tree trunk and branch T6788 and T9795.
6.7
Trunks of trees located above
Landscape and Visual
6.8
Removal of construction waste previously found
piled deep around existing tree T614 was outstanding. The Contractor was reminded to remove the
construction waste around the tree as soon as possible.
6.9
The Contractor had not removed the dead trees,
including a tree with rotten trunk at the base located near existing tree
T534. The Contractor was recommended to
remove all the dead and rotten trees away from the footpath area for safety.
6.10
Rectification of many of the tree identification
numbers for the existing retained trees was outstanding. The Contractor was reminded to re-instate the
tree numbers on existing trees for ease of reference as soon as possible.
6.11
Compensatory planting proposal for the replacement
of dead tree T611 was outstanding. The
Contractor was recommended to seek Engineer’s agreement on the replacement
planting as soon as possible.
6.12
Contractor’s clarification of the status of
existing trees T516, T517, T666, and T698 was outstanding. The Contractor was reminded to provide
necessary information as soon as possible.
6.13
Several undersized existing
trees had been unnecessarily broken. The
Contractor was reminded to be more careful in order to minimize damage on trees
in future.
6.14
It was observed that the
Contractor had pruned some of the existing tree branches to facilitate soil
nailing works. However, as required
under the contract Particular Specification, the Contractor shall seek the
Engineer’s agreement prior to carry out any tree pruning works. Therefore, the Contractor was reminded to
seek Engineer’s agreement for pruning of existing trees in future.
Assessment of Environmental Monitoring Results
6.15
All monitoring results were
audited against the Action / Limit levels and any exceedance would be validated
and issued when necessary.
6.16
The monitoring results in
the reporting period were comparable with the EIA predictions. Detailed
discussions are given in Section 2 and 3.
Advice on the Solid and Liquid Waste Management Status
6.17
The Contractor is
registered as a chemical waste producer for this Project. The Chemical Waste
Storage Area located at the Contractor’s site office area was properly
maintained in the reporting month.
6.18
As advised by the
Contractor, 16.82 ton of non-inert C&D waste was disposed offsite to SENT
landfill in the reporting month. C&D waste generated was reused on site as
much as possible.
Environmental Licenses and Permits
6.19
The environmental licenses
and permits for this Project and valid in the reporting month is summarized in Table
6.1.
Table 6.1 Summary of
Environmental Licensing and Permit Status
Description |
Permit No. |
Valid Period |
Remarks |
|
From |
To |
|||
Environmental
Permit |
EP-235/2005/B |
23/11/07 |
-- |
- Installation of about 700 nos. of soil nails and about 60 nos. of
raking drains in the natural terrain; - Rock slope stabilisation works at upper portion of the natural
terrain; and - Other associated works. |
Registration
as a Chemical Waste Producer |
5213-141-C3250-02 |
13/12/06 |
-- |
Spent
lubricating oil and mineral oil |
Effluent
Discharge License |
EP880/W10/XX0261 |
07/11/06 |
31/12/11 |
-- |
Notification
of Constriction Work under APCO (Construction Dust) |
001012125 |
18/07/06 |
-- |
-- |
Implementation Status of Environmental Mitigation
Measures
6.20
In response to the site
audit findings, the Contractor carried out corrective actions.
6.21
A summary of the
Implementation Schedule of Mitigation Measures (EMIS) is presented in Appendix C.
Most of the necessary mitigation measures were implemented properly.
Summary of Exceedances of the Environmental Quality
Performance Limit
6.22
All 1-hour TSP, 24-hour TSP
and noise monitoring results complied with the Action / Limit levels.
6.23
No exceedance was recorded
in the reporting month.
Summary of Complaints, Notification of Summons and
Successful Prosecutions
6.24
The Environmental Complaint
Handling Procedure is annexed in Figure 6.1.
6.25
No environmental complaint, notification of summons
and successful prosecutions was received in the reporting month.
Construction Programme for the Coming Months
7.1
The construction programme
for the Project is provided in Appendix B.
7.2
The major construction work
in November 2008 will be:
-
Soil nail
installation at Portion B2 and Portion C;
-
Construction
of Soil Nail Heads at Portion A1; and
-
Rock
slope/boulder stabilization works at Portion B2 and Portion C.
7.3
Key issues to be considered
in the coming month included:
-
Sufficient dust suppression
measures should be maintained;
-
Collection of construction
waste should be carried out regularly;
-
Site runoff should be
properly collected and treated prior to discharge;
-
Construction activities
should avoid causing damage to the trees and to plants species of conservation
interest; and
-
Quieter powered mechanical
equipment should be used.
7.4
The following mitigation
measures are required:
Air Quality Impact
-
Regular watering should be
used during soil nailing;
-
Dusty material stockpiled
should be completely covered;
-
Dusty activities should be
re-scheduled if high-wind conditions encountered;
-
Open burning should be
strictly prohibited;
-
All dusty vehicle loads
transporting to, from and between site locations should be covered with
tarpaulin;
-
Vehicle wheel and body
washing facilities should be used at all exit points of the site;
-
Wind shield, dust
extraction units or water spraying should be used at the loading points.
Construction Noise Impact
-
Quieter powered mechanical
equipment should be used;
-
Insulating fabric should be
used for drill rigs during drilling process;
-
Noise generating construction
works should be carried out during daytime only;
-
Noise barriers or other
measures should be used to minimize disturbance to the bat roost;
-
Plant on site should be
properly maintained and serviced regularly;
-
Mobile plants should be
sited as far from NSRs as possible;
-
Machines and plant in
intermittent use should be throttled down;
-
Strong noise emitting
plants, wherever possible, should be oriented so that noise is directed away
from the nearby NSRs;
-
Material stockpiles,
wherever possible, should be effectively utilized to screen noise from
construction activities;
-
Movable noise barrier with
surface mass in excess of 7kg/m2 should be used for PME wherever
possible;
-
Noise insulating fabric
should be adopted for drill rig operating in Works Area E.
Water Quality Impact
-
Prevent runoff water from
entering the nearby water-bodies;
-
Silt traps and oil / grease
separators should be regularly cleaned and maintained;
-
Outlet pipe extending above
the slope surface should be installed;
-
Air should be used as the
flushing medium of the drilling equipment;
-
Earth bunds or sand bag
barriers should be provided on-site to direct storm water to silt removal
facilities;
-
Exposed slope / soil
surface and opened stockpile of more than 50m3 should be covered
with tarpaulin;
-
Oils and fuels should be
used and stored in designated area.
Chemical and Waste Management
-
Debris and rubbish on-site
should be collected, handled and disposed of properly;
-
Waste skips should be
provided to collect general refuse and construction wastes;
-
Soil contamination with
fuel leaked from construction plants should be removed off-site;
-
Sufficient waste disposal
points with regular collection should be provided;
-
Appropriate measures should
be provided to minimize windblown litter and dust during transportation of
waste;
-
Different containers should
be used to segregate and store different types of waste;
-
Encourage collection of aluminum
cans, PET bottles and paper by providing separate bins;
-
Unused chemicals should be
recycles wherever possible;
-
Proper storage and site
practices should be adopted to minimize the potential for damage and
contamination of construction materials;
-
Oils and fuels should be
stored in designated area;
-
Plan and stock construction
materials carefully to minimize waste generation.
Ecological Impact
-
Soil nail installation
should avoid / minimize damage of root system to the existing plants;
-
Fences should be erected
along the boundary of the works area
-
Disturbance to the natural
woodland and shrubland habitats should be minimized by preventing tipping,
vehicle movements and encroachment of personnel onto the adjacent area;
-
Permanent casing should be
provided to the drillhole of soil nail;
-
Placement of equipment or
stockpile should be located in designated areas to minimize disturbance to natural
or moderate-high ecological value habitats;
-
Construction activities
should be restricted to works areas;
-
Disturbance to existing
vegetation should be minimized wherever possible.
Landscape and Visual Impact
-
Designation of
“no-intrusion zones” and record any trespass and damage to existing vegetation;
-
Soil nails on site should
avoid tree trunks and tree roots;
-
Dust and erosion control
should be provided for exposed soil;
-
For tree planting
operations, method statement should be checked against specification
requirements;
-
All retained trees within
the working boundary should be checked regularly;
-
Control over appearance of
hoarding, construction plants / machines;
-
Security floodlights should
be carefully selected to avoid light pollution.
Monitoring Schedule for the Coming Months
7.5
The tentative schedule for
environmental monitoring in December 2008 is provided in Appendix L.
8.1
The construction phase of
the project commenced in April 2008.
8.2
1-hour TSP and 24-hour TSP
monitoring was carried out in the reporting month. All monitoring results
complied with the action / limit level. No exceedance was recorded.
8.3
All impact daytime noise
monitoring results complied with the limit level in the reporting month.
8.4
Environmental site inspections were carried out 4
times in November 2008. Recommendations on remedial actions were given to the
Contractor for the deficiencies identified during the site audit.
8.5
Two landscape and visual
audits were carried out in the reporting month. The Contractor was
recommended to rectify all ineligible tree identification numbers for existing
trees on site. The Contractor was also recommended to seek Engineer’s agreement prior to tree pruning works.
8.6
Two ecological audits were
carried out in the reporting month. The
Contractor was reminded to take all necessary actions to protect the leaves,
branches, trunks, and root system of the retained vegetation through
implementation of appropriate mitigation measures. All tagged plants of conservation interested
should be fenced off properly
with clear sign to avoid any damage. Construction materials should be stored and supported by fixed scaffold within the designated works area in a proper manner.
8.7
No environmental complaint,
notification of summons and prosecution was received in the reporting month.
8.8
According to the
environmental site inspections performed in the reporting month, the following
recommendations were provided:
Air Quality Impact
-
Soil nail workstations on
site should be properly enclosed.
Construction Noise Impact
-
Nil
Water Quality Impact
-
Sedimentation tanks on site
should be properly maintained;
-
Site effluent must be collected
and treated prior to discharge to public drain;
-
U-channels should be kept
clear of mud, debris, leaves, construction waste and materials; and
-
Soil and exposed earth at
all working platforms and slopes should be cleaned up.
Chemical and Waste Management
-
Drip trays should be provided
to all plants and chemical containers on site;
-
Oils and fuels should be
stored in designated area;
-
C&D waste, debris and general
refuse on-site should be collected, handled and disposed of properly; and
-
Waste skips should be
provided to collect general refuse and construction wastes.
Ecological Impact
-
Construction materials should be well
supported by fixed storage devices but not on trees within the works area;
-
Regular
watering should be carried out to wash dust covered on leaves of vegetation; and
-
All plant species of
conservation interest should be fenced off properly with clear sign,
especially for those located near major access road and areas likely to be
impacted by construction activities.
Landscape and Visual Impact
-
Dead / rotten trees should
be removed from site for safety;
-
All ineligible tree
identification numbers for all existing trees should be rectified;
-
The status of missing trees
should be clarified as soon as possible;
-
All construction waste should
be kept away from existing tree and should not be placed against trees in
future;
-
Unnecessary damage on
existing trees, especially the undersized trees, should be minimized;
-
All dead trees as found on
site should be recorded and report to the Engineer; and
-
The Contractor was
recommended to seek Engineer’s agreement prior to tree pruning works in future.