6. ENVIRONMENTAL SITE INSPECTION
AND AUDIT
Assessment of
Environmental Monitoring Results
Advice on the
Solid and Liquid Waste Management Status
Environmental
Licenses and Permits
Implementation
Status of Environmental Mitigation Measures
Summary of
Exceedances of the Environmental Quality Performance Limit
Summary of Complaints,
Notification of Summons and Successful Prosecutions
Construction
Programme for the Coming Months
Monitoring Schedule
for the Coming Months
8. CONCLUSIONS AND RECOMMENDATIONS
List
of Tables
Table
1.1 Contact
Information of Key Personnel
Table 2.1 Air Quality Monitoring Equipment
Table 2.2 Air Quality Monitoring
Parameters, Frequency and Duration
Table 2.3 Locations of Air Quality
Monitoring Stations
Table 2.4 Summary of 1-hour TSP
Monitoring Results in the Reporting Period
Table 2.5 Summary of 24-hour TSP
Monitoring Results in the Reporting Period
Table 3.1 Noise Monitoring Equipment
Table 3.2 Locations of Noise
Monitoring Stations
Table 3.3 Summary of Noise Monitoring
Results in the Reporting Period
Table 6.1 Summary of Environmental
Licensing and Permit Status
List of Figures
Figure 2.1 Locations of Air Quality and Noise
Monitoring Stations
Figure 6.1 Environmental Complaint Handling
Procedures
List of Appendices
Appendix A Project Organization Structure
Appendix B Construction Programme
Appendix C Implementation
Schedule of Mitigation Measures (EMIS)
Appendix D Action and Limit Levels for Air Quality and Noise
Appendix E Calibration Certificates
Appendix F Air Quality Monitoring Results and
Graphical Presentation
Appendix I Noise Monitoring
Results and Graphical Presentation
Appendix J Detailed Landscape and Visual Monitoring
Report
Appendix K ET’s
Site Inspection Summaries
Appendix L Monitoring Schedules
The Project “Landslide Preventive Works at Po Shan, Mid-levels – Design
and Construction (Natural Terrain Risk Mitigation Works)” (hereafter called
“the Project”) includes the installation of about 700 numbers of soil nails and
about 60 numbers of raking drains on the natural terrain within the concerned
area.
The impact environmental monitoring and audit for the Project includes
the air quality, noise, ecology, landscape and visual monitoring. The
construction of the Project and the EM&A programme commenced on 1 April
2008.
This report documented the findings of EM&A works conducted in the
period between 1 and 31 December 2008. As informed by the Contractor,
construction activities in the reporting period were:
-
Soil nail
installation works Portion C;
-
Soil nail head construction at
Portion A1; and
-
Rock slope stabilization works
at Portion C and Portion B2.
Breaches of Action and Limit
Levels
There was no action / limit level exceedance recorded for 1-hour and
24-hour TSP monitoring.
In the reporting month, all noise level recorded complied with the limit
level.
Complaint, Notification of
Summons and Successful Prosecution
There was no complaint, notification of summons and successful
prosecution received in the reporting month.
Reporting Change
There was no reporting change required in the reporting month.
Future Key Issues
The weather in the forthcoming month is expected to be dry and windy. The
Contractor should maintain sufficient dust suppression measures, such as proper
treatment of exposed slope and earth, and provide water spraying to any dusty
construction activities.
It is also recommended to implement all necessary preventive measures to
avoid oil leakage on ground / soil, such as provision of drip trays for all oil
drums / chemical containers. In the event of oil leakage, the Contractor should
properly remove the contaminated soil and dispose of as chemical waste. Construction
waste and general refuse should be properly collected and disposed of.
1.1
The project site is located at the mostly
undeveloped hillside above the residential development at
1.2
The objective of the Project “Landslide Preventive
Works at Po Shan, Mid-levels – Design and Construction (Natural Terrain Risk
Mitigation Works)” under Contract CE 28/2004 (GE) is to carry out detailed
design and supervision of landslide preventive works on local repair of the
hillside to minimize slope deterioration and shallow instability.
1.3
The proposed landslide preventive works would be
constructed to protect the existing residential developments at the toe of the
project site.
1.4
The scope of works of this Project includes the
installation about 700 numbers of soil nails and about 60 numbers of raking
drains on the natural terrain within the concerned area. The length of the soil
nails is about
1.5
The Project is anticipated to complete in 10 months
after the commencement of construction.
1.6
According to the Environmental Permit (EP-235/2005/B)
and the EM&A Manual of the Project, there is a need of an EM&A
programme including air quality, noise, ecology, and landscape and visual
monitoring.
1.7
ENSR Asia (HK) Ltd. (ENSR) was employed by the
Contractor,
1.8
This is the ninth monthly Environmental Monitoring
and Audit (EM&A) Report under the Contract CE 28/2004 (GE) – Landslide
Preventive Works at
1.9
The project organization is
shown in Appendix A. The key personnel contact names and numbers are summarized
in Table 1.1
.
Table 1.1 Contact Information
of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
CEDD |
Senior Engineer |
H. W. Sun |
2762 5375 |
2714 0247 |
ER (MGS) |
Resident Engineer |
Freddie Chan |
3188 0400 |
3188 0775 |
Assistant Resident Engineer |
S. F. Chau |
3188 0400 |
3188 0775 |
|
IEC
(ENVIRON) |
Independent
Environmental Checker |
David
Yeung |
3743
0788 |
3548
6988 |
Contractor
(CCJV) |
Project
Manager |
C.
Y. Mak |
3188
0538 |
3188
1710 |
Safety
and Environmental Officer |
Ken
Fong |
3188
0538 |
3188
1710 |
|
ET
(ENSR) |
ET
Leader |
Edith
Ng |
3105
8525 |
2891
0305 |
1.10
The Contactor has carried
out major activities in the reporting month. Details of the works undertaken in
this reporting period are listed below:
-
Soil
nail installation works Portion C;
-
Soil nail head construction at
Portion A1; and
-
Rock slope stabilization works
at Portion C and Portion B2.
1.11
The general layout plan of
the Project site showing the contract area is shown in Figure 1.1. The
construction programme is provided in Appendix B.
1.12
The mitigation measures
implementation schedule are presented in Appendix C.
Summary of EM&A Programme Requirements
1.13
The EM&A programme
required environmental monitoring for air quality, noise, ecology and landscape
and visual and environmental site inspections for air quality, noise, ecology,
landscape and visual and waste management. The EM&A requirements for each
parameter described in the following sections include:
-
All monitoring parameters;
-
Monitoring schedules for
the reporting month and forthcoming months;
-
Action and Limit levels for
all environmental parameters;
-
Event / Action Plan;
-
Environmental mitigation
measures, as recommended in the Project EIA study final report; and
-
Environmental requirement
in contract documents.
2.1
In accordance with the EM&A Manual, 1-hour and
24-hour TSP levels at 2 air quality monitoring stations were established. Impact
1-hour and 24-hour TSP monitoring was conducted for at least once every 7 days during
the construction phase of the Project. The Action and Limit level of the air
quality monitoring is provided in Appendix D.
2.2
24-hour TSP air quality monitoring was performed
using High Volume Sampler (HVS) located at each designated monitoring station.
The HVS meets all the requirements of the EM&A Manual. Portable direct
reading dust meters were used to carry out the 1-hour TSP monitoring. Table 2.1
summarises the equipment used.
Table 2.1 Air Quality
Monitoring Equipment
Equipment |
Model |
High
Volume Sampler |
GS
2310 Accu-vol system |
Calibrator |
GMW 25 |
1-hour
TSP Dust Meter |
Laser
Dust Monitor – Model LD-3 |
Monitoring Parameters, Frequency and Duration
2.3
Table 2.2 summarizes the monitoring parameters,
frequency and duration of impact TSP monitoring.
Table 2.2 Air Quality Monitoring Parameters, Frequency and Duration
Parameter |
Frequency and Duration |
|
CA1 & CA2 |
24-hour
TSP |
At least once every 7 days |
1-hour TSP |
At least 3 times every 7 days |
2.4
Both monitoring stations were set up at the
proposed locations in accordance with EM&A Manual. Table 2.3 describes
details of the two monitoring stations. The monitoring locations are shown in
Figure 2.1.
Table 2.3 Locations of Air
Quality Monitoring Stations
Monitoring Station |
Identity / Description |
CA1 |
Access
road to Po Shan Mansions |
CA2 |
Podium
of |
24-hour TSP Monitoring
Installation
2.5
The HVS was installed in the vicinity of the air
sensitive receivers. The following
criteria were considered in the installation of the HVS.
·
A horizontal platform with appropriate support to
secure the sampler against gusty wind was provided.
·
The distance between the HVS and any obstacles,
such as buildings, was at least twice the height that the obstacle protrudes
above the HVS.
·
A minimum of 2 meters separation from walls,
parapets and penthouse was required for rooftop sampler.
·
No furnace or incinerator flues were nearby.
·
Airflow around the sampler was unrestricted.
·
Permission was obtained to set up the samplers and
to obtain access to the monitoring stations.
·
A secured supply of electricity is needed to
operate the samplers.
Preparation of Filter Papers
·
Glass fibre filters, G810 were labeled and sufficient filters that were
clean and without pinholes were selected.
·
All filters were equilibrated in the conditioning environment for 24
hours before weighing. The conditioning
environment temperature was around
·
ALS Technichem (HK) Pty Ltd. has comprehensive quality
assurance and quality control programmes.
Field Monitoring
·
The power supply was checked to ensure the HVS works properly.
·
The filter holder and the area surrounding the filter were cleaned.
·
The filter holder was removed by loosening the four bolts and a new
filter, with stamped number upward, on a supporting screen was aligned
carefully.
·
The filter was properly aligned on the screen so that the gasket formed
an airtight seal on the outer edges of the filter.
·
The swing bolts were fastened to hold the filter holder down to the
frame. The pressure applied should be
sufficient to avoid air leakage at the edges.
·
Then the shelter lid was closed and was secured with the aluminum strip.
·
The HVS was warmed-up for about 5 minutes to establish run-temperature
conditions.
·
A new flowrate record sheet was set into the flow recorder.
·
The range specified in the EM&A Manual was between 0.6
·
The programmable timer was set for a sampling period of 24 hrs +
1 hr, and the starting time, weather condition and the filter number were
recorded.
·
The initial elapsed time was recorded.
·
At the end of sampling, the sampled filter was removed carefully and
folded in half length so that only surfaces with collected particulate matter
were in contact.
·
It was then placed in a clean plastic envelope and sealed.
·
All monitoring information was recorded on a
standard data sheet.
·
Filters were sent to ALS Technichem (HK) Pty Ltd. for
analysis.
Maintenance and Calibration
·
The HVS and its accessories are maintained in good working condition,
such as replacing motor brushes routinely and checking electrical wiring to ensure
a continuous power supply.
·
HVSs are calibrated using GMW-25 Calibration Kit prior to the
commencement of baseline air quality monitoring, and will be calibrated at
bi-monthly intervals throughout all stages of the impact monitoring.
·
Calibration records are shown in Appendix E.
1-hour TSP Monitoring
Measuring Procedures
2.6
The measuring procedures of the 1-hour dust meter
are in accordance with the Manufacturer’s Instruction Manual as follows:
·
Set POWER to “ON”, push
·
Push the knob at MEASURE position.
·
Push “O-ADJ” button. (Then meter’s indication is 0).
·
Push the knob at SENSI ADJ position and set the meter’s indication to S
value described on the Test Report using the trimmer for SENSI ADJ.
·
Pull out the knob and return it to MEASURE position.
·
Push “START” button.
Maintenance and Calibration
·
The 1-hour TSP meter would be checked at 3-month intervals and
calibrated at 1-year intervals throughout all stages of the air quality
baseline monitoring. Calibration records are shown in Appendix E.
2.7
The monitoring results for 1-hour TSP and 24-hour
TSP are summarized in Table 2.4 and 2.5 respectively and the monitoring results
are provided in Appendix F.
Table 2.4 Summary of 1-hour TSP Monitoring Results in the Reporting Period
|
Average
(mg/m3) |
Range
(mg/m3) |
Action
Level (mg/m3) |
Limit
Level (mg/m3) |
CA1 |
75.2 |
68.4 – 86.1 |
309.3 |
500 |
CA2 |
71.4 |
65.4 – 79.5 |
319.6 |
500 |
Table 2.5 Summary of 24-hour TSP Monitoring Results in the Reporting Period
|
Average
(mg/m3) |
Range
(mg/m3) |
Action
Level (mg/m3) |
Limit
Level (mg/m3) |
CA1 |
39.0 |
32.2 – 52.7 |
166.8 |
260 |
CA2 |
75.2 |
56.0 – 94.8 |
187.0 |
260 |
2.8
Air quality monitoring was
carried out for both 1-hour TSP and 24-hour TSP at all the monitoring stations
in the reporting month.
2.9
The air quality monitoring results, in terms of
1-hour TSP and 24-hour TSP, were below the action and limit level at both
monitoring locations in the reporting month. The event action plan is annexed
in Appendix G.
2.10
Weather information including wind speed and wind
direction is annexed in Appendix H. The information was obtained from Hong Kong
Observatory Victoria Peak Automatic Weather Station and Central Pier Anemometer
Station.
3.1
In accordance with the EM&A Manual, impact noise levels should be
obtained at 2 noise monitoring stations. Impact noise monitoring was conducted
for at least once per week during the construction phase of the Project. The
Action and Limit level of the noise monitoring is provided in Appendix D.
3.2
Integrating Sound Level Meter was employed for noise monitoring. They were Type 1 sound level meters capable
of giving a continuous readout of the noise level readings including equivalent
continuous sound pressure level (Leq) and percentile sound pressure
level (Lx). They comply with International Electrotechnical Commission
Publications 651:1979 (Type 1) and 804:1985 (Type 1). Portable electronic wind speed indicator
capable of measuring wind speed in m/s was employed to check the wind
speed. Table 3.1 details the noise monitoring
equipment used.
Table 3.1 Noise Monitoring
Equipment
Equipment |
Model |
Integrating Sound Level Meter |
Rion NL-31 |
Calibrator |
Rion NC-73 |
3.3
Two monitoring stations were set up in accordance
with EM&A Manual. Table 3.2 describes details of the two monitoring
stations. The monitoring locations are shown in Figure 2.1.
Table
3.2 Locations of Noise Monitoring
Stations
Monitoring Station |
Identity / Description |
CN1 |
Block A, |
CN2 |
Block A, |
3.4
One set of 30-mins measurement at each monitoring station between 0700
and 1900 on normal weekdays at a frequency of once per week was required to
determine the impact noise level. Leq, L10 and L90
would be recorded.
Monitoring Procedures
·
The Sound Level Meter was set on a tripod at a
height of
·
Façade measurements were made at all three
monitoring locations.
·
The battery condition was checked to ensure the
correct functioning of the meter.
·
Parameters such as frequency weighting, the time
weighting and the measurement time were set as follows:
-
frequency weighting: A
-
time weighting: Fast
-
time measurement: Leq(30 minutes) during
non-restricted hours i.e. between 07:00 and 19:00 on normal weekdays
·
Prior to and after each noise measurement, the
meter was calibrated using a Calibrator for 94 dB at 1000 Hz. If the difference in the calibration level
before and after measurement was more than 1 dB(A), the measurement would be
considered invalid and repeat of noise measurement would be required after
re-calibration or repair of the equipment.
·
The wind speed was frequently checked with a
portable wind meter.
·
During the monitoring period, the Leq ,
L10 and L90 were recorded. In addition, site conditions and noise sources
were recorded on a standard record sheet.
·
Noise measurement was paused during periods of high
intrusive noise (e.g. dog barking, helicopter noise) if possible. Observations
were recorded when intrusive noise was unavoidable.
·
Noise monitoring was cancelled in the presence of
fog, rain, wind with a steady speed exceeding
Maintenance and Calibration
·
The microphone head of the sound level meter and
calibrator is cleaned with soft cloth at quarterly intervals.
·
The meter should be checked and calibrated at yearly intervals.
·
Calibration details for the sound level meter and calibrator are
provided in Appendix E.
3.5
The monitoring results for noise are summarized in
Table 3.3 and the monitoring data is provided in Appendix I.
Table
3.3 Summary of Noise Monitoring
Results in the Reporting Period
|
Average,
dB(A), Leq (30 mins) |
Range,
dB(A), Leq (30 mins) |
Limit
Level, dB(A), Leq (30 mins) |
CN1 |
59.7 |
58.8 – 60.6 |
75.0 |
CN2 |
58.8 |
58.3 – 59.4 |
75.0 |
3.6
There was no noise complaint received in the reporting month, hence, no
action level exceedance was recorded. At both monitoring locations, CN1 and
CN2, all the monitoring results (daytime) were below the limit level of 75
dB(A).
3.7
All the monitoring results lied within the range of the predicted noise
levels in the EIA report.
3.8
Major noise sources during the noise monitoring included the
construction activities from the Project and another project under the same
contract (concurrent project) carried out in the vicinity and nearby traffic
noise.
4.1
As required under Environmental Permit No. EP-235/2005/B, the Permit
Holder is required to carry out monitoring of the plant species of conservation
interest to check on the health and condition of the plants twice a month
during the construction period of the Project.
4.2
It is required to undertake the ecological tasks to fulfill the
requirements of the Environmental Permit (EP).
As required by Conditions 2.11 and 3.5 of the EP, a suitably qualified ecologist with 7 or more years
of relevant experience shall be employed to conduct the ecological monitoring.
4.3
The ecological monitoring was carried out for plant individuals of
conservation interest identified within the proposed works area.
4.4
The ecological monitoring was conducted twice in the reporting month on 9
and 23 December 2008 by Ms. Gigi C C Lam, who had over 7 years of relevant
ecological experience.
4.5
The plants of conservation interest, which were tagged during the
baseline survey, were checked during each monitoring.
4.6
Site clearance, soil nailing and scaffolding works were in progress
during the monitoring visits. Most of the
tagged vegetation has been fenced off and was found to be in good condition
during the monitoring visits in December 2008.
4.7
Signs of grout leakage on a natural drainage path were recorded. The hardened grout covered the drainage path
between
4.8
The leaves of vegetation located near the
operation area of soil nailing works were covered heavily
with dust and were subsequently washed by soil nail contractor upon
request. Some of the fabric shields next
to the soil nailing machine were found to be worn out.
4.9
A major site access near Row AF was not
clearly demarcated and vegetation was removed to give way to the access.
5.1
During the construction phase
of the Project, landscape and visual monitoring should be carried out bi-weekly
by a Registered Landscape Architect (RLA) to check if the design,
implementation and maintenance of the landscape and visual mitigation measures
are fully realized. A detailed report is annexed in Appendix J.
Summary of Inspection – 2 December 2008
Matters Arising from Previous Inspections
5.2
It was still observed that
the Contractor had not removed the dead trees, including a tree with rotten
trunk at the base located near existing tree T534. The Contractor was recommended to remove all
the dead and rotten trees away from the footpath area for safety.
5.3
It was still observed that
rectification of many of the tree identification numbers for the existing
retained trees were outstanding. The
Contractor was reminded to re-instate the tree numbers on existing trees for
ease of reference as soon as possible.
5.4
It was noted that
compensatory planting proposal for the replacement of dead tree T611 was
outstanding. The Contractor was
recommended to seek Engineer’s agreement on the replacement planting as soon as
possible.
5.5
It was noted that the
Contractor’s clarification of the status of existing trees T516, T517, T666,
and T698 was outstanding. The Contractor
was reminded to provide necessary information as soon as possible.
Protection of Existing Trees
5.6
It was noted that some
excavated rocks for soil nail heads were piled against the based of an existing
tree. The Contractor was reminded to
clear the rocks away from the tree as soon as possible.
5.7
A tree was observed with
its branch hacked off and left with scars.
The contractor was reminded that pruning of tree branch requires
permission from the Engineer and that pruning of tree branch shall be carried
out by approved landscape contractor.
5.8
It was observed that the
Contractor had used an existing tree as support to tie the large hose. The Contractor was requested to remove the
hose from the tree as soon as possible.
Recommendations
5.9
The Contractor was
recommended to clear and remove dead / rotten trees from site for safety.
5.10
The Contractor was reminded
to rectify all ineligible tree identification numbers for all existing trees.
5.11
The Contractor was
recommended to clarify the status of missing trees as soon as possible.
5.12
The Contractor was
recommended to seek Engineer’s agreement on the replacement planting for dead
tree.
5.13
The Contractor was
recommended to clear away excavated rocks from existing tree and not to place
it against trees in future.
5.14
The Contractor was reminded
to seek Engineer’s agreement prior to carry out tree pruning works, which
should be carried out by approved landscape contractor in future.
Summary of Inspection – 16 December 2008
Matters Arising from Previous Inspections
5.15
The Contractor had cleared
out the remaining stones around the base of existing tree T614.
5.16
Also, the Contractor had
removed the excavated rocks previously found piled against the based of
existing tree.
5.17
The Contractor had removed
tie support for the large hose from existing tree.
5.18
It was still observed that
the Contractor had not removed the dead trees, including a tree with rotten
trunk at the base located near existing tree T534. The Contractor was recommended to remove all
the dead and rotten trees away from the footpath area for safety.
5.19
It was still observed that
rectification of many of the tree identification numbers for the existing
retained trees were outstanding. The
Contractor was reminded to re-instate the tree numbers on existing trees for
ease of reference as soon as possible.
5.20
It was noted that the
Contractor’s clarification of the status of existing trees T516, T517, T666,
and T698 was outstanding. The Contractor
was reminded to provide necessary information as soon as possible.
Protection of Existing Trees
5.21
It was observed the tree
bark of an existing tree with protective hessian wrappings was damaged by
scrapings from the moving of pipe sleeves for stock piling nearby. The
Contractor was requested to provide better tree protection and to ensure moving
of equipments and materials do not damage existing trees.
Recommendations
5.22
The Contractor was reminded
not to damage the tree barks and to provide better tree protections while
carried out works near vicinity of existing trees.
5.23
The Contractor was reminded
to rectify all ineligible tree identification numbers for all existing trees.
5.24
The Contractor was
recommended to remove dead / rotten trees from site for safety. The Contractor
was also reminded to record and report all dead trees as found on site to the
Engineer for record.
5.25
The Contractor was
recommended to clarify the status of missing trees as soon as possible.
5.26
The Contractor was
recommended to seek Engineer’s agreement on the replacement planting for dead
tree.
Summary of Inspection – 30 December 2008
Matters Arising from Previous Inspections
5.27
The Contractor had provided
new hessian tree protective wrapping to the existing tree previously found with
damaged bark.
5.28
It was still observed that
the Contractor had not removed the dead trees, including a tree with rotten
trunk at the base located near existing tree T534. The Contractor was recommended to remove all
the dead and rotten trees away from the footpath area for safety.
5.29
It was still observed that
rectification of many of the tree identification numbers for the existing
retained trees were outstanding. The
Contractor was reminded to re-instate the tree numbers on existing trees for
ease of reference as soon as possible.
5.30
It was noted that the
Contractor’s clarification of the status of existing trees T516, T517, T666,
and T698 was outstanding. The Contractor
was reminded to provide necessary information as soon as possible.
Protection of Existing Trees
5.31
It was observed that 10
pipe sleeves were stockpiled against an existing tree. The contractor was requested to remove
immediately the stockpile away from the tree.
Recommendations
5.32
The Contractor was reminded
remove the pipe stockpile away from the existing tree and not to stockpile
materials and equipment against trees on site.
5.33
The Contractor was reminded
to rectify all ineligible tree identification numbers for all existing trees.
5.34
The Contractor was
recommended to remove dead / rotten trees from site for safety. The Contractor
was also reminded to record and report all dead trees as found on site to the
Engineer for record.
5.35
The Contractor was
recommended to clarify the status of missing trees as soon as possible.
5.36
The Contractor was
recommended to seek Engineer’s agreement on the replacement planting for dead trees.
Next Landscape and Visual Audit Schedule
5.37
The landscape and visual
audits in the next reporting month was tentatively scheduled to 13 and 20 January
2009.
6.1
Site Inspections were
carried out on a weekly basis to monitor the implementation of proper
environmental pollution control and mitigation measures for the Project. In the
reporting month, 4 site inspections were carried out on 2, 9, 16, 23 and 30 December
2008. The detail findings of the landscape and visual audits in the reporting
month are presented separately in Section 5. The environmental site inspection
summaries are attached in Appendix K. Particular observations are described
below.
Air Quality
6.2
No adverse observation was
identified in the reporting month.
Noise
6.3
No adverse observation was
identified in the reporting month.
Water Quality
6.4
No adverse observation was
identified in the reporting month.
Chemical and Waste Management
6.5
Several chemical containers
were observed placed on ground and on the slope without drip tray at Row AF,
Row AN, Row AS and Row AT. The Contractor was reminded to provide drip trays to
all chemical containers and dispose of the empty chemical containers as
chemical waste.
6.6
Oil stains were observed on
ground and over a drill rig at
Ecology
6.7
The fabric shield for soil nailing works was found
to be worn out and did not function properly to prevent the dust generated
during soil nailing works from affecting the vegetation nearby.
6.8
Serious grout leakage was recorded from
6.9
The boundary of a major site access near Row AF was
not clearly demarcated.
Landscape and Visual
6.10
The Contractor still had
not removed the dead trees, including a tree with rotten trunk at the base
located near existing tree T534. The
Contractor was recommended to remove all the dead and rotten trees away from
the footpath area for safety.
6.11
Rectification of many of
the tree identification numbers for the existing retained trees was
outstanding. The Contractor was reminded
to re-instate the tree numbers on existing trees for ease of reference as soon
as possible.
6.12
Compensatory planting
proposal for the replacement of dead tree T611 was outstanding. The Contractor was recommended to seek
Engineer’s agreement on the replacement planting as soon as possible.
6.13
The Contractor’s
clarification of the status of existing trees T516, T517, T666, and T698 was
outstanding. The Contractor was reminded
to provide necessary information as soon as possible.
6.14
Some excavated rocks for
soil nail heads were piled against the based of an existing tree. The Contractor was reminded to clear the
rocks away from the tree as soon as possible.
6.15
A tree was observed with
its branch hacked off and left with scars.
The Contractor was reminded that pruning of tree branch requires
permission from the Engineer and that pruning of tree branch shall be carried
out by approved landscape Contractor.
6.16
The Contractor had used an
existing tree as support to tie the large hose.
The Contractor was requested to remove the hose from the tree as soon as
possible.
6.17
The tree bark of an
existing tree with protective hessian wrappings was damaged by scrapings from
the moving of pipe sleeves for stock piling nearby. The Contractor was
requested to provide better tree protection and to ensure moving of equipments
and materials do not damage existing trees.
6.18
10 pipe sleeves were
stockpiled against an existing tree. The
Contractor was requested to remove immediately the stockpile away from the
tree.
Assessment of Environmental Monitoring Results
6.19
All monitoring results were
audited against the Action / Limit levels and any exceedance would be validated
and issued when necessary.
6.20
The monitoring results in
the reporting period were comparable with the EIA predictions. Detailed
discussions are given in Section 2 and 3.
Advice on the Solid and Liquid Waste Management Status
6.21
The Contractor is
registered as a chemical waste producer for this Project. The Chemical Waste
Storage Area located at the Contractor’s site office area was properly
maintained in the reporting month.
6.22
As advised by the
Contractor, 7.04 ton of non-inert C&D waste was disposed offsite to SENT
landfill in the reporting month. C&D waste generated was reused on site as
much as possible.
Environmental Licenses and Permits
6.23
The environmental licenses
and permits for this Project and valid in the reporting month is summarized in Table
6.1.
Table 6.1 Summary of
Environmental Licensing and Permit Status
Description |
Permit No. |
Valid Period |
Remarks |
|
From |
To |
|||
Environmental
Permit |
EP-235/2005/B |
23/11/07 |
-- |
- Installation of about 700 nos. of soil nails and about 60 nos. of
raking drains in the natural terrain; - Rock slope stabilisation works at upper portion of the natural
terrain; and - Other associated works. |
Registration
as a Chemical Waste Producer |
5213-141-C3250-02 |
13/12/06 |
-- |
Spent
lubricating oil and mineral oil |
Effluent
Discharge License |
EP880/W10/XX0261 |
07/11/06 |
31/12/11 |
-- |
Notification
of Constriction Work under APCO (Construction Dust) |
001012125 |
18/07/06 |
-- |
-- |
Implementation Status of Environmental Mitigation
Measures
6.24
In response to the site
audit findings, the Contractor carried out corrective actions.
6.25
A summary of the Implementation
Schedule of Mitigation Measures (EMIS) is presented in Appendix C. Most of the
necessary mitigation measures were implemented properly.
Summary of Exceedances of the Environmental Quality
Performance Limit
6.26
All 1-hour TSP, 24-hour TSP
and noise monitoring results complied with the Action / Limit levels.
6.27
No exceedance was recorded
in the reporting month.
Summary of Complaints, Notification of Summons and
Successful Prosecutions
6.28
The Environmental Complaint
Handling Procedure is annexed in Figure 6.1.
6.29
No environmental complaint, notification of summons
and successful prosecutions was received in the reporting month.
Construction Programme for the Coming Months
7.1
The construction programme
for the Project is provided in Appendix B.
7.2
The major construction work
in January 2009 will be:
-
Soil nailing
works at Portion B2;
-
Construction
of soil nail heads at Portion A1 and Portion A2; and
-
Rock
slope stabilization works at Portion B2 and Portion C.
7.3
Key issues to be considered
in the coming month included:
-
Sufficient dust suppression
measures should be maintained;
-
Collection of construction
waste should be carried out regularly;
-
Site runoff should be
properly collected and treated prior to discharge;
-
Construction activities
should avoid causing damage to the trees and to plants species of conservation
interest; and
-
Quieter powered mechanical
equipment should be used.
7.4
The following mitigation
measures are required:
Air Quality Impact
-
Regular watering should be
used during soil nailing;
-
Dusty material stockpiled
should be completely covered;
-
Dusty activities should be
re-scheduled if high-wind conditions encountered;
-
Open burning should be
strictly prohibited;
-
All dusty vehicle loads
transporting to, from and between site locations should be covered with
tarpaulin;
-
Vehicle wheel and body
washing facilities should be used at all exit points of the site;
-
Wind shield, dust
extraction units or water spraying should be used at the loading points.
Construction Noise Impact
-
Quieter powered mechanical
equipment should be used;
-
Insulating fabric should be
used for drill rigs during drilling process;
-
Noise generating construction
works should be carried out during daytime only;
-
Noise barriers or other
measures should be used to minimize disturbance to the bat roost;
-
Plant on site should be
properly maintained and serviced regularly;
-
Mobile plants should be
sited as far from NSRs as possible;
-
Machines and plant in
intermittent use should be throttled down;
-
Strong noise emitting
plants, wherever possible, should be oriented so that noise is directed away
from the nearby NSRs;
-
Material stockpiles,
wherever possible, should be effectively utilized to screen noise from
construction activities;
-
Movable noise barrier with
surface mass in excess of 7kg/m2 should be used for PME wherever
possible;
-
Noise insulating fabric
should be adopted for drill rig operating in Works Area E.
Water Quality Impact
-
Prevent runoff water from
entering the nearby water-bodies;
-
Silt traps and oil / grease
separators should be regularly cleaned and maintained;
-
Outlet pipe extending above
the slope surface should be installed;
-
Air should be used as the
flushing medium of the drilling equipment;
-
Earth bunds or sand bag
barriers should be provided on-site to direct storm water to silt removal
facilities;
-
Exposed slope / soil
surface and opened stockpile of more than 50m3 should be covered
with tarpaulin;
-
Oils and fuels should be
used and stored in designated area.
Chemical and Waste Management
-
Debris and rubbish on-site
should be collected, handled and disposed of properly;
-
Waste skips should be
provided to collect general refuse and construction wastes;
-
Soil contamination with
fuel leaked from construction plants should be removed off-site;
-
Sufficient waste disposal
points with regular collection should be provided;
-
Appropriate measures should
be provided to minimize windblown litter and dust during transportation of
waste;
-
Different containers should
be used to segregate and store different types of waste;
-
Encourage collection of aluminum
cans, PET bottles and paper by providing separate bins;
-
Unused chemicals should be
recycles wherever possible;
-
Proper storage and site
practices should be adopted to minimize the potential for damage and
contamination of construction materials;
-
Oils and fuels should be
stored in designated area;
-
Plan and stock construction
materials carefully to minimize waste generation.
Ecological Impact
-
Soil nail installation
should avoid / minimize damage of root system to the existing plants;
-
Fences should be erected
along the boundary of the works area
-
Disturbance to the natural
woodland and shrubland habitats should be minimized by preventing tipping,
vehicle movements and encroachment of personnel onto the adjacent area;
-
Permanent casing should be
provided to the drillhole of soil nail;
-
Placement of equipment or
stockpile should be located in designated areas to minimize disturbance to natural
or moderate-high ecological value habitats;
-
Construction activities
should be restricted to works areas;
-
Disturbance to existing
vegetation should be minimized wherever possible.
Landscape and Visual Impact
-
Designation of
“no-intrusion zones” and record any trespass and damage to existing vegetation;
-
Soil nails on site should
avoid tree trunks and tree roots;
-
Dust and erosion control
should be provided for exposed soil;
-
For tree planting
operations, method statement should be checked against specification
requirements;
-
All retained trees within
the working boundary should be checked regularly;
-
Control over appearance of
hoarding, construction plants / machines;
-
Security floodlights should
be carefully selected to avoid light pollution.
Monitoring Schedule for the Coming Months
7.5
The tentative schedule for
environmental monitoring in January 2009 is provided in Appendix L.
8.1
The construction phase of
the project commenced in April 2008.
8.2
1-hour TSP and 24-hour TSP
monitoring was carried out in the reporting month. All monitoring results
complied with the action / limit level. No exceedance was recorded.
8.3
All impact daytime noise
monitoring results complied with the limit level in the reporting month.
8.4
Environmental site inspections were carried out 5
times in December 2008. Recommendations on remedial actions were given to the
Contractor for the deficiencies identified during the site audit.
8.5
Three landscape and visual
audits were carried out in the reporting month. The Contractor was advised
prevent damage to tree barks and provide better protection to existing trees before carrying
out of works in the vicinity. The
Contractor was also reminded that Engineer’s
agreement should be sought prior to tree pruning works.
8.6
Two ecological audits were
carried out in the reporting month. The
Contractor was reminded to take all necessary actions to prevent grout leakage
to the surrounding natural environment.
The Contractor was requested to investigate the cause(s) of the grout
leakage case and take remedial measures to preserve the identified vegetation
of conservation interest and propose preventive measures to avoid re-occurrence
of similar cases. All tagged plants of
conservation interest in the affected area should be located and fenced off
properly with clear sign to avoid any further damage and restrict any
unauthorized access of site workers to the area. The fabric shields for soil nailing works
should be replaced regularly to ensure they function properly. All site access should be clearly demarcated
and no excessive removal of vegetation in natural areas adjacent to the site
access should be allowed.
8.7
No environmental complaint,
notification of summons and prosecution was received in the reporting month.
8.8
According to the
environmental site inspections performed in the reporting month, the following
recommendations were provided:
Air Quality Impact
-
Soil nail workstations on
site should be properly enclosed.
Construction Noise Impact
-
Nil
Water Quality Impact
-
Sedimentation tanks on site
should be properly maintained;
-
Site effluent must be collected
and treated prior to discharge to public drain;
-
U-channels should be kept
clear of mud, debris, leaves, construction waste and materials; and
-
Soil and exposed earth at
all working platforms and slopes should be cleaned up.
Chemical and Waste Management
-
Drip trays should be provided
to all plants and chemical containers on site;
-
Oils and fuels should be
stored in designated area;
-
Empty chemical containers
should be disposed of as chemical waste;
-
C&D waste, debris and general
refuse on-site should be collected, handled and disposed of properly; and
-
Waste skips should be
provided to collect general refuse and construction wastes.
Ecological Impact
-
The Contractor was reminded
to take all necessary actions to prevent grout leakage to the surrounding
natural environment;
-
The fabric shields for soil
nailing works should be replaced regularly to ensure they function properly;
-
Regular watering should be
carried out to wash dust covered on leaves of vegetation;
-
All site access should be
clearly demarcated and no excessive removal of vegetation in natural areas
adjacent to the site access should be allowed; and
-
All plant species of
conservation interest should be fenced off properly with clear sign, especially
for those located near major access road and areas likely to be impacted by
construction activities.
Landscape and Visual Impact
-
Dead / rotten trees should
be removed from site for safety. The Contractor was also reminded to record and
report all dead trees as found on site to the Engineer for record.
-
All ineligible tree
identification numbers should be rectified for all existing trees.
-
The status of missing trees
should be clarified as soon as possible.
-
Engineer’s agreement on the
replacement planting for dead tree should be sought.
-
Excavated rocks should be
kept clear from existing tree and should not be placed against trees in future.
-
Engineer’s agreement prior
to carry out tree pruning works should be sought and tree pruning works should only
be carried out by approved landscape contractor in future.
-
Damage to tree barks should
be avoided and better tree protections should be provided while carried out
works near vicinity of existing trees.
-
The pipe stockpile should
be kept away from existing tree, and materials and equipment should not be
stockpiled against trees on site.