TABLE OF CONTENTS
Page
EXECUTIVE
SUMMARY............................................................................................................................ 1
1. INTRODUCTION............................................................................................................................ 2
Background................................................................................................................................... 2
Scope of
Report............................................................................................................................. 2
Project
Organization...................................................................................................................... 2
Summary of
Construction Works................................................................................................. 332
Summary of EM&A Programme
Requirements.............................................................................. 332
2. AIR QUALITY............................................................................................................................. 442
Monitoring Requirements............................................................................................................ 442
Monitoring Equipment................................................................................................................. 442
Monitoring Parameters,
Frequency and Duration........................................................................... 442
Monitoring Locations.................................................................................................................. 442
Monitoring Methodology.............................................................................................................. 552
Monitoring Results..................................................................................................................... 662
3. NOISE MONITORING................................................................................................................. 772
Monitoring Requirements............................................................................................................ 772
Monitoring Equipment................................................................................................................. 772
Monitoring Locations.................................................................................................................. 772
Monitoring Parameters................................................................................................................ 772
Monitoring Methodology.............................................................................................................. 772
Monitoring Results..................................................................................................................... 882
4. VEGETATION MONITORING....................................................................................................... 992
Monitoring Requirement.............................................................................................................. 992
Monitoring Location.................................................................................................................... 992
Monitoring Methodology.............................................................................................................. 992
Monitoring Results..................................................................................................................... 992
5. LANDSCAPE AND VISUAL..................................................................................................... 10102
Monitoring Requirement........................................................................................................... 10102
Summary of Inspection – 7
April 2009....................................................................................... 10102
Summary of Inspection – 21
April 2009...................................................................................... 11112
Next Landscape and Visual
Audit Schedule............................................................................... 11112
6. ENVIRONMENTAL SITE INSPECTION
AND AUDIT................................................................... 12122
Site Inspection....................................................................................................................... 12122
Assessment of Environmental
Monitoring Results...................................................................... 13132
Advice on the Solid and Liquid
Waste Management Status......................................................... 13132
Environmental Licenses and
Permits........................................................................................ 13132
Implementation Status of
Environmental Mitigation Measures...................................................... 14142
Summary of Exceedances of the
Environmental Quality Performance Limit.................................. 14142
Summary of Complaints,
Notification of Summons and Successful Prosecutions.......................... 14142
7. FUTURE KEY ISSUES........................................................................................................... 15152
Construction Programme for the
Coming Months....................................................................... 15152
Key Issues for Coming Month.................................................................................................. 15152
Monitoring Schedule for the
Coming Months.............................................................................. 16162
8. CONCLUSIONS AND
RECOMMENDATIONS............................................................................ 17172
Conclusions........................................................................................................................... 17172
Recommendations.................................................................................................................. 17172
Summary of EM&A Programme
Requirements
Monitoring Parameters, Frequency and
Duration
Summary of
Inspection – 7 April 2009
Summary of
Inspection – 21 April 2009
Next
Landscape and Visual Audit Schedule
6. ENVIRONMENTAL SITE INSPECTION
AND AUDIT
Assessment of
Environmental Monitoring Results
Advice on the
Solid and Liquid Waste Management Status
Environmental
Licenses and Permits
Implementation
Status of Environmental Mitigation Measures
Summary of
Exceedances of the Environmental Quality Performance Limit
Summary of
Complaints, Notification of Summons and Successful Prosecutions
Construction
Programme for the Coming Months
Monitoring
Schedule for the Coming Months
8. CONCLUSIONS AND RECOMMENDATIONS
List of Tables
Table 1.1 Contact Information of Key Personnel....................................................................... 332
Table 2.1 Air Quality Monitoring Equipment............................................................................. 442
Table 2.2 Air Quality Monitoring Parameters, Frequency and
Duration....................................... 442
Table 2.3 Locations of Air Quality Monitoring Stations.............................................................. 442
Table 2.4 Summary of 1-hour TSP Monitoring Results in the
Reporting Period............................ 662
Table 2.5 Summary of 24-hour TSP Monitoring Results in the
Reporting Period.......................... 662
Table 3.1 Noise Monitoring Equipment.................................................................................... 772
Table 3.2 Locations of Noise Monitoring Stations..................................................................... 772
Table 3.3 Summary of Noise Monitoring Results in the
Reporting Period.................................... 882
Table 6.1 Summary of Environmental Licensing and Permit
Status........................................ 13142
Table 1.1 Contact Information of Key
Personnel
Table 2.1 Air Quality Monitoring Equipment
Table 2.2 Air Quality Monitoring
Parameters, Frequency and Duration
Table 2.3 Locations of Air Quality
Monitoring Stations
Table 2.4 Summary of 1-hour TSP
Monitoring Results in the Reporting Period
Table 2.5 Summary of 24-hour TSP
Monitoring Results in the Reporting Period
Table 3.1 Noise Monitoring Equipment
Table 3.2 Locations of Noise Monitoring
Stations
Table 3.3 Summary of Noise Monitoring
Results in the Reporting Period
Table 6.1 Summary of Environmental
Licensing and Permit Status
List
of Figures
Figure 2.1 Locations
of Air Quality and Noise Monitoring Stations
Figure 6.1 Environmental Complaint Handling
Procedures
List
of Appendices
Appendix A Project
Organization Structure
Appendix B Construction
Programme
Appendix
C Implementation Schedule of
Mitigation Measures (EMIS)
Appendix D Action
and Limit Levels for Air Quality and
Noise
Appendix E Calibration
Certificates
Appendix F Air
Quality Monitoring Results and Graphical Presentation
Appendix I Noise Monitoring Results and Graphical
Presentation
Appendix
J Detailed Landscape and Visual
Monitoring Report
Appendix K ET’s
Site Inspection Summaries
Appendix L Monitoring
Schedules
The Project
“Landslide Preventive Works at Po Shan, Mid-levels – Design and Construction
(Natural Terrain Risk Mitigation Works)” (hereafter called “the Project”)
includes the installation of about 700 numbers of soil nails and about 60
numbers of raking drains on the natural terrain within the concerned area.
The impact environmental
monitoring and audit for the Project includes the air quality, noise, ecology, landscape
and visual monitoring. The construction of the Project and the EM&A
programme commenced on 1 April 2008.
This report
documented the findings of EM&A works conducted in the period between 1 and
30 April 2009. As informed by the Contractor, construction activities in the
reporting period were:
-
Soil nailing works at Portion B2;
-
Soil nail head construction at Portion B1 and Portion C;
and
-
Rock slope stabilization works at Portion B2 and
Portion D.
Breaches of Action and Limit Levels
There was no action
/ limit level exceedance recorded for 1-hour and 24-hour TSP monitoring.
In the reporting
month, all noise level recorded complied with the limit level.
Complaint, Notification of Summons and Successful
Prosecution
There was no
complaint, notification of summons and successful prosecution received in the
reporting month.
Reporting Change
There was no
reporting change required in the reporting month.
Future Key Issues
The weather in the
forthcoming month is expected to be wet and windy. The Contractor should
provide preventive measures to prevent any muddy runoff, such as proper
collection and treatment of the runoff and provide a functional temporary
drainage system in site.
It is also
recommended to implement all necessary preventive measures to avoid oil leakage
on ground / soil, such as provision of drip trays for all oil drums / chemical
containers. In the event of oil leakage, the Contractor should properly remove
the contaminated soil and dispose of as chemical waste. Construction waste and
general refuse should be properly collected and disposed of.
1.1
The
project site is located at the mostly undeveloped hillside above the
residential development at
1.2
The
objective of the Project “Landslide Preventive Works at Po Shan, Mid-levels –
Design and Construction (Natural Terrain Risk Mitigation Works)” under Contract
CE 28/2004 (GE) is to carry out detailed design and supervision of landslide
preventive works on local repair of the hillside to minimize slope
deterioration and shallow instability.
1.3
The
proposed landslide preventive works would be constructed to protect the
existing residential developments at the toe of the project site.
1.4
The
scope of works of this Project includes the installation about 700 numbers of
soil nails and about 60 numbers of raking drains on the natural terrain within
the concerned area. The length of the soil nails is about
1.5
The
Project is anticipated to complete in 10 months after the commencement of
construction.
1.6
According
to the Environmental Permit (EP-235/2005/B) and the EM&A Manual of the Project,
there is a need of an EM&A programme including air quality, noise, ecology,
and landscape and visual monitoring.
1.7
ENSR
Asia (HK) Ltd., which
was
integrated into AECOM Asia Company Limited as of 1 May 2009, was employed by the Contractor,
1.8
This
is the thirteenth monthly Environmental Monitoring and Audit (EM&A) Report
under the Contract CE 28/2004 (GE) – Landslide Preventive Works at
1.9
The project organization is shown in Appendix A. The
key personnel contact names and numbers are summarized in Table 1.1
.
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
CEDD |
Senior
Engineer |
H.
W. Sun |
2762
5375 |
2714
0247 |
ER
(MGS) |
Resident
Engineer |
Freddie
Chan |
3188
0400 |
3188
0775 |
Assistant
Resident Engineer |
S.
F. Chau |
3188
0400 |
3188
0775 |
|
IEC (ENVIRON) |
Independent Environmental
Checker |
David Yeung |
3743 0788 |
3548 6988 |
Contractor (CCJV) |
Project Manager |
C. Y. Mak |
3188 0538 |
3188 1710 |
Safety and Environmental
Officer |
Brian Wong |
3188 0538 |
3188 1710 |
|
ET (ENSR) |
ET Leader |
Edith Ng |
3105 8525 |
2891 0305 |
1.10
The Contactor has carried out major activities in the
reporting month. Details of the works undertaken in this reporting period are
listed below:
-
Soil nailing works at Portion
B2;
-
Soil nail head construction at Portion B1 and Portion
C; and
-
Rock slope stabilization works at Portion B2 and
Portion D.
1.11
The general layout plan of the Project site showing the
contract area is shown in Figure 1.1. The construction programme is provided in
Appendix B.
1.12
The mitigation measures implementation schedule are
presented in Appendix C.
Summary
of EM&A Programme Requirements
1.13
The EM&A programme required environmental
monitoring for air quality, noise, ecology and landscape and visual and
environmental site inspections for air quality, noise, ecology, landscape and
visual and waste management. The EM&A requirements for each parameter
described in the following sections include:
-
All monitoring parameters;
-
Monitoring schedules for the reporting month and
forthcoming months;
-
Action and Limit levels for all environmental
parameters;
-
Event / Action Plan;
-
Environmental mitigation measures, as recommended in
the Project EIA study final report; and
-
Environmental requirement in contract documents.
2.1
In
accordance with the EM&A Manual, 1-hour and 24-hour TSP levels at 2 air
quality monitoring stations were established. Impact 1-hour and 24-hour TSP
monitoring was conducted for at least once every 7 days during the construction
phase of the Project. The Action and Limit level of the air quality monitoring
is provided in Appendix D.
2.2
24-hour
TSP air quality monitoring was performed using High Volume Sampler (HVS)
located at each designated monitoring station. The HVS meets all the
requirements of the EM&A Manual. Portable direct reading dust meters were
used to carry out the 1-hour TSP monitoring. Table 2.1 summarises the equipment
used.
Table 2.1 Air Quality Monitoring Equipment
Equipment |
Model |
High Volume Sampler |
GS 2310 Accu-vol system |
Calibrator |
GMW 25 |
1-hour TSP Dust Meter |
Laser Dust Monitor – Model LD-3 |
Monitoring
Parameters, Frequency and Duration
2.3
Table
2.2 summarizes the monitoring parameters, frequency and duration of impact TSP
monitoring.
Table 2.2 Air
Quality Monitoring Parameters, Frequency
and Duration
Parameter |
Frequency and
Duration |
|
CA1 & CA2 |
24-hour TSP |
At least once every 7 days |
1-hour TSP |
At least 3 times every 7 days |
2.4
Both
monitoring stations were set up at the proposed locations in accordance with
EM&A Manual. Table 2.3 describes details of the two monitoring stations.
The monitoring locations are shown in Figure 2.1.
Table 2.3 Locations of Air Quality Monitoring
Stations
Monitoring
Station |
Identity
/ Description |
CA1 |
Access road to Po Shan
Mansions |
CA2 |
Podium of |
24-hour TSP
Monitoring
Installation
2.5
The
HVS was installed in the vicinity of the air sensitive receivers. The following criteria were considered in the
installation of the HVS.
·
A
horizontal platform with appropriate support to secure the sampler against
gusty wind was provided.
·
The
distance between the HVS and any obstacles, such as buildings, was at least
twice the height that the obstacle protrudes above the HVS.
·
A
minimum of 2 meters separation from walls, parapets and penthouse was required
for rooftop sampler.
·
No
furnace or incinerator flues were nearby.
·
Airflow
around the sampler was unrestricted.
·
Permission
was obtained to set up the samplers and to obtain access to the monitoring
stations.
·
A
secured supply of electricity is needed to operate the samplers.
Preparation
of Filter Papers
·
Glass fibre
filters, G810 were labeled and sufficient filters that were clean and without
pinholes were selected.
·
All filters were
equilibrated in the conditioning environment for 24 hours before weighing. The conditioning environment temperature was
around
·
ALS Technichem (HK) Pty Ltd. has comprehensive quality assurance and quality control
programmes.
Field
Monitoring
·
The power supply
was checked to ensure the HVS works properly.
·
The filter holder
and the area surrounding the filter were cleaned.
·
The filter holder
was removed by loosening the four bolts and a new filter, with stamped number
upward, on a supporting screen was aligned carefully.
·
The filter was
properly aligned on the screen so that the gasket formed an airtight seal on
the outer edges of the filter.
·
The swing bolts
were fastened to hold the filter holder down to the frame. The pressure applied should be sufficient to
avoid air leakage at the edges.
·
Then the shelter
lid was closed and was secured with the aluminum strip.
·
The HVS was warmed-up
for about 5 minutes to establish run-temperature conditions.
·
A new flowrate
record sheet was set into the flow recorder.
·
The range specified
in the EM&A Manual was between 0.6
·
The programmable
timer was set for a sampling period of 24 hrs + 1 hr, and the starting
time, weather condition and the filter number were recorded.
·
The initial elapsed
time was recorded.
·
At the end of
sampling, the sampled filter was removed carefully and folded in half length so
that only surfaces with collected particulate matter were in contact.
·
It was then placed
in a clean plastic envelope and sealed.
·
All
monitoring information was recorded on a standard data sheet.
·
Filters
were sent to ALS Technichem (HK) Pty
Ltd. for analysis.
Maintenance
and Calibration
·
The HVS and its
accessories are maintained in good working condition, such as replacing motor
brushes routinely and checking electrical wiring to ensure a continuous power
supply.
·
HVSs are calibrated
using GMW-25 Calibration Kit prior to the commencement of baseline air quality
monitoring, and will be calibrated at bi-monthly intervals throughout all
stages of the impact monitoring.
·
Calibration records
are shown in Appendix E.
1-hour TSP
Monitoring
Measuring
Procedures
2.6
The
measuring procedures of the 1-hour dust meter are in accordance with the
Manufacturer’s Instruction Manual as follows:
·
Set POWER to “ON”,
push
·
Push the knob at
MEASURE position.
·
Push “O-ADJ”
button. (Then meter’s indication is 0).
·
Push the knob at
SENSI ADJ position and set the meter’s indication to S value described on the
Test Report using the trimmer for SENSI ADJ.
·
Pull out the knob
and return it to MEASURE position.
·
Push “START”
button.
Maintenance
and Calibration
·
The 1-hour TSP
meter would be checked at 3-month intervals and calibrated at 1-year intervals
throughout all stages of the air quality baseline monitoring. Calibration
records are shown in Appendix E.
2.7
The
monitoring results for 1-hour TSP and 24-hour TSP are summarized in Table 2.4
and 2.5 respectively and the monitoring results are provided in Appendix F.
Table 2.4 Summary
of 1-hour TSP Monitoring Results in the Reporting Period
|
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
CA1 |
76.4 |
69.5
– 85.9 |
309.3 |
500 |
CA2 |
73.2 |
67.6
– 83.3 |
319.6 |
500 |
Table 2.5 Summary
of 24-hour TSP Monitoring Results in the Reporting Period
|
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
CA1 |
56.3 |
15.2
– 101.1 |
166.8 |
260 |
CA2 |
54.4 |
22.6
– 74.2 |
187.0 |
260 |
2.8
Air quality monitoring was carried out for both 1-hour
TSP and 24-hour TSP at all the monitoring stations in the reporting month.
2.9
The
air quality monitoring results, in terms of 1-hour TSP and 24-hour TSP, were below
the action and limit level at both monitoring locations in the reporting month.
The event action plan is annexed in Appendix G.
2.10
Weather
information including wind speed and wind direction is annexed in Appendix H.
The information was obtained from Hong Kong Observatory Victoria Peak Automatic
Weather Station and Central Pier Anemometer Station.
3.1
In accordance with
the EM&A Manual, impact noise levels should be obtained at 2 noise
monitoring stations. Impact noise monitoring was conducted for at least once
per week during the construction phase of the Project. The Action and Limit
level of the noise monitoring is provided in Appendix D.
3.2
Integrating Sound
Level Meter was employed for noise monitoring.
They were Type 1 sound level meters capable of giving a continuous
readout of the noise level readings including equivalent continuous sound
pressure level (Leq) and percentile sound pressure level (Lx). They
comply with International Electrotechnical Commission Publications 651:1979
(Type 1) and 804:1985 (Type 1). Portable
electronic wind speed indicator capable of measuring wind speed in m/s was
employed to check the wind speed. Table
3.1 details the noise monitoring equipment used.
Table 3.1 Noise Monitoring Equipment
Equipment |
Model |
Integrating Sound Level Meter |
Rion NL-31 |
Calibrator |
Rion NC-73 |
3.3
Two
monitoring stations were set up in accordance with EM&A Manual. Table 3.2
describes details of the two monitoring stations. The monitoring locations are
shown in Figure 2.1.
Table 3.2 Locations of Noise Monitoring Stations
Monitoring
Station |
Identity / Description |
CN1 |
Block A, |
CN2 |
Block A, |
3.4
One set of 30-mins measurement
at each monitoring station between 0700 and 1900 on normal weekdays at a
frequency of once per week was required to determine the impact noise level. Leq,
L10 and L90 would be recorded.
Monitoring Procedures
·
The
Sound Level Meter was set on a tripod at a height of
·
Façade
measurements were made at all three monitoring locations.
·
The
battery condition was checked to ensure the correct functioning of the meter.
·
Parameters
such as frequency weighting, the time weighting and the measurement time were
set as follows:
-
frequency
weighting: A
-
time
weighting: Fast
-
time
measurement: Leq(30 minutes) during non-restricted hours i.e.
between 07:00 and 19:00 on normal weekdays
·
Prior
to and after each noise measurement, the meter was calibrated using a
Calibrator for 94 dB at 1000 Hz. If the
difference in the calibration level before and after measurement was more than
1 dB(A), the measurement would be considered invalid and repeat of noise
measurement would be required after re-calibration or repair of the equipment.
·
The
wind speed was frequently checked with a portable wind meter.
·
During
the monitoring period, the Leq , L10 and L90
were recorded. In addition, site
conditions and noise sources were recorded on a standard record sheet.
·
Noise
measurement was paused during periods of high intrusive noise (e.g. dog
barking, helicopter noise) if possible. Observations were recorded when
intrusive noise was unavoidable.
·
Noise
monitoring was cancelled in the presence of fog, rain, wind with a steady speed
exceeding
Maintenance and Calibration
·
The
microphone head of the sound level meter and calibrator is cleaned with soft
cloth at quarterly intervals.
·
The meter should be
checked and calibrated at yearly intervals.
·
Calibration details
for the sound level meter and calibrator are provided in Appendix E.
3.5
The
monitoring results for noise are summarized in Table 3.3 and the monitoring
data is provided in Appendix I.
Table 3.3 Summary of Noise Monitoring Results in the Reporting Period
|
Average, dB(A), Leq (30
mins) |
Range, dB(A), Leq (30
mins) |
Limit Level, dB(A), Leq
(30 mins) |
CN1 |
60.9 |
60.6
– 61.4 |
75.0 |
CN2 |
60.1 |
59.9
– 60.3 |
75.0 |
3.6
There was no noise
complaint received in the reporting month, hence, no action level exceedance
was recorded. At both monitoring locations, CN1 and CN2, all the monitoring
results (daytime) were below the limit level of 75 dB(A).
3.7
All the monitoring
results lied within the range of the predicted noise levels in the EIA report.
3.8
Major noise sources
during the noise monitoring included the construction activities from the
Project and another project under the same contract (concurrent project)
carried out in the vicinity and nearby traffic noise.
4.1
As required under
Environmental Permit No. EP-235/2005/B, the Permit Holder is required to carry
out monitoring of the plant species of conservation interest to check on the
health and condition of the plants twice a month during the construction period
of the Project.
4.2
It is required to
undertake the ecological tasks to fulfill the requirements of the Environmental
Permit (EP). As required by Conditions 2.11
and 3.5 of the EP, a suitably qualified ecologist
with 7 or more years of relevant experience shall be employed to conduct the
ecological monitoring.
4.3
The ecological
monitoring was carried out for plant individuals of conservation interest
identified within the proposed works area.
4.4
The ecological
monitoring was conducted twice in the reporting month on 7 and 28 April 2009 by Ms. Gigi C C Lam, who had over 7
years of relevant ecological experience.
4.5
The plants of
conservation interest, which were tagged during the baseline survey, were
checked during each monitoring.
4.6
Site clearance, sSoil
nailing and
scaffolding works were in progress during the monitoring
visits.
4.7
Three individuals of vegetation of conservation
interest in
Group V015, V016 and to V0187 had been identified and tags tied back during the 28 April 2009
visit. The Contractor agreed to fence off two of the individuals which were located
outside the existing fence-off area. The Contractor was also
advise to erect a clear sign
notable to all the construction workers and restrict any unauthorized
entry to the area.
4.8
Another
two vegetation of conservation V018 and V035 could not be located during the monitoring
visits, The Contractor advised the
concerned vegetation were probably covered
up under the temporary storage platform and scaffolding, the Contractor agreed to identify the missing
individual once the platform has been removed from the
site. and the plant species V035 were missing.
4.84.1Part of the
plant species of conservation interest and three identified vegetation of
conservation interest (V015 to V017) were not properly fenced off. The
Contractor was advised to fence off
the vegetation properly with a
clear sign notable to all the construction workers and
restrict any unauthorized access to the area.
4.1
4.9
Vegetation and
plant species of conservation interest located near soil nailing work areas
were densely covered with soil and dust.
4.10
Hardened grout was
found in the natural habitat near the Project area. To prevent the plant from being affected by
grout leakage and muddy site run-off, the Contractor was reminded to remove any
grout from the natural habitat as soon as possible and add sand bags around the
hardened grout.
4.11
Sign of oil /
lubricant spillage was observed from soil nailing machine on the nearby
vegetation. The Contractor was
recommended to remove any soil nailing machine from the vegetation.
5.1
During the construction phase of the Project, landscape
and visual monitoring should be carried out bi-weekly by a Registered Landscape
Architect (RLA) to check if the design, implementation and maintenance of the
landscape and visual mitigation measures are fully realized. A detailed report
is annexed in Appendix J.
Summary
of Inspection – 7 April 2009
Matters
Arising from Previous Inspections
5.2
The Contractor had cleared away the soil bags and small
boulder previously found stockpiled against existing tree.
5.3
It was still observed that the termite infected dead
tree T511 at the corner of footpath stair was still not removed. The Resident Engineer advised that
instruction will be given to the Contractor to urgently remove the infected
dead tree for consideration of safety of the workers and the public in future.
5.4
It was still observed that the Contractor had not
removed the dead trees, including a tree with rotten trunk at the base located
near existing tree T534. The Resident
Engineer requested RLA to prepare a separate letter recommendation for the
removal of the tree which is in poor condition for his follow up actions.
5.5
It was observed that Contractor had commenced the
rectification of many of the tree identification numbers for the existing
retained trees at the lower portion. The
Contractor further advised that rectification of the tree numbers on the
remaining existing trees shall be completed as soon as possible.
5.6
It was noted that compensatory planting proposal for
the replacement of dead tree T611 was outstanding. The Contractor was recommended to seek
Engineer’s agreement on the replacement planting as soon as possible.
5.7
It was noted that the Contractor’s clarification of the
status of existing trees T516, T517, T666, and T698 located immediately outside
of the works boundary was outstanding.
The Contractor was reminded to provide necessary information as soon as
possible.
Protection
of Existing Trees
5.8
It was again observed that construction materials were
stock piled against the trunks of 2 existing trees. The Contractor was requested to clear the
material away from the tree as soon as possible.
Recommendations
5.9
The Contractor was recommended to remove dead / rotten
trees from site for safety, especially T511 which was now found infected by
termite. The Contractor was also
reminded to record and report all dead trees as found on site to the Engineer
for record.
5.10
The Contractor was reminded to rectify all remaining
ineligible tree ID numbers for all existing trees.
5.11
The Contractor was recommended to clarify the status of
missing trees as soon as possible.
5.12
The Contractor was recommended to seek Engineer’s
agreement on the replacement planting for dead tree.
5.13
The Contractor was recommended to clear the construction
materials away from existing trees and not to stockpile materials against trees
in future.
Summary
of Inspection – 21 April 2009
Matters
Arising from Previous Inspections
5.14
The Contractor had removed the termite infected dead
tree T511 at the corner of footpath stair.
The Contractor had also removed the tree with rotten trunk base located
near existing tree T534. However,
removal of dead tree T534 itself was outstanding, which was also infected by
termites. The Contractor was also reminded to remove the dead tree T534 which
had leaned against existing tree T538.
5.15
The Contractor had cleared the construction materials
previously observed stock piled against the trunks of 2 existing trees.
5.16
It was observed that no further rectification of tree
ID numbers was carried out since the last inspection. The Contractor was reminded to rectify the
missing tree ID numbers on the remaining existing trees as soon as possible.
5.17
It was noted that compensatory planting proposal for
the replacement of dead tree T611 was outstanding. The Contractor was recommended to seek
Engineer’s agreement on the replacement planting as soon as possible.
5.18
It was noted that the Contractor’s clarification of the
status of existing trees T516, T517, T666, and T698 located immediately outside
of the works boundary was outstanding.
The Contractor was reminded to provide necessary information as soon as
possible.
Protection
of Existing Trees
5.19
It was noted that no particular new observations
regarding the protection of existing trees was made during this inspection.
Recommendations
5.20
The Contractor was recommended to remove the dead tree
T534 from site for safety considerations, especially the tree was found
infected by termite. The Contractor was
also reminded to record and report all dead trees as found on site to the
Engineer for record.
5.21
The Contractor was reminded to rectify all remaining
ineligible / missing tree ID numbers for all existing trees.
5.22
The Contractor was recommended to clarify the status of
missing trees as soon as possible.
5.23
The Contractor was recommended to seek Engineer’s
agreement on the replacement planting for dead trees.
Next
Landscape and Visual Audit Schedule
5.24
The landscape and visual audits in the next reporting
month was tentatively scheduled to 5 and 19 May 2009.
6.1
Site Inspections were carried out on a weekly basis to
monitor the implementation of proper environmental pollution control and
mitigation measures for the Project. In the reporting month, 4 site inspections
were carried out on 7, 14, 21 and 28 April 2009. The detail findings of the
landscape and visual audits in the reporting month are presented separately in
Section 5. The environmental site inspection summaries are attached in Appendix
K. Particular observations are described below.
Air Quality
6.2
No adverse observation was identified in the reporting
month.
Noise
6.3
No adverse observation was identified in the reporting
month.
Water Quality
6.4
Loose sediment was observed on the slope above Row AI.
The Contractor was reminded to clear up the sediment as soon as the operation
is completed.
Chemical and Waste Management
6.5
A chemical container was observed placed on ground
without drip tray at Row AF. While immediate action was taken by the Contractor,
the Contractor was still reminded to provide drip tray to all chemical
containers on site.
6.6
Stagnant water was observed inside an uncovered
chemical container at Row AF. The Contractor was advised to pour off the
stagnant water and dispose of as chemical waste, and properly cover all
chemical containers on site.
Ecology
6.76.1Three individuals of vegetation
of conservation interest in Group V015 to V018 and the plant species V035 were missing.
6.86.7
Part of the plant species of
conservation interest and the identified vegetation of conservation interest
(V015 to V017) were not properly fenced off.
6.96.8
Vegetation and plant species of
conservation interest located near soil nailing work areas were densely covered
with soil and dust.
6.106.9
Hardened grout was found in the
natural habitat near the Project area.
6.116.10
Sign of oil / lubricant spillage
was observed from soil nailing machine on the nearby vegetation.
Landscape and Visual
6.126.11
It was observed that Contractor
had commenced the rectification of many of the tree identification numbers for
the existing retained trees at the lower portion. The Contractor further advised that
rectification of the tree numbers on the remaining existing trees shall be
completed as soon as possible.
6.136.12
It was noted that compensatory
planting proposal for the replacement of dead tree T611 was outstanding. The Contractor was recommended to seek
Engineer’s agreement on the replacement planting as soon as possible.
6.146.13
It was noted that the
Contractor’s clarification of the status of existing trees T516, T517, T666,
and T698 located immediately outside of the works boundary was
outstanding. The Contractor was reminded
to provide necessary information as soon as possible.
6.156.14
It was observed that
construction materials were stock piled against the trunks of 2 existing
trees. The Contractor was requested to
clear the material away from the tree as soon as possible.
6.166.15
The Contractor had removed the
termite infected dead tree T511 at the corner of footpath stair. The Contractor had also removed the tree with
rotten trunk base located near existing tree T534. However, removal of dead tree T534 itself was
outstanding, which was also infected by termites. The Contractor was also
reminded to remove the dead tree T534 which had leaned against existing tree
T538.
Assessment
of Environmental Monitoring Results
6.176.16
All monitoring results were
audited against the Action / Limit levels and any exceedance would be validated
and issued when necessary.
6.186.17
The monitoring results in the
reporting period were comparable with the EIA predictions. Detailed discussions
are given in Section 2 and 3.
Advice
on the Solid and Liquid Waste Management Status
6.196.18
The Contractor is registered as
a chemical waste producer for this Project. The Chemical Waste Storage Area
located at the Contractor’s site office area was properly maintained in the
reporting month.
6.206.19
As advised by the Contractor, 33.06
ton of non-inert C&D waste and 9.38 ton of inert C&D waste were
disposed offsite to SENT landfill and Chai Wan respectively in the reporting
month. C&D waste generated was reused on site as much as possible.
Environmental
Licenses and Permits
6.216.20
The environmental licenses and
permits for this Project and valid in the reporting month is summarized in Table
6.1.
Table 6.1 Summary of Environmental Licensing and
Permit Status
Description |
Permit
No. |
Valid
Period |
Remarks |
|
From |
To |
|||
Environmental Permit |
EP-235/2005/B |
|
-- |
- Installation of
about 700 nos. of soil nails and about 60 nos. of raking drains in the
natural terrain; - Rock slope
stabilisation works at upper portion of the natural terrain; and - Other associated
works. |
Registration as a Chemical
Waste Producer |
5213-141-C3250-02 |
|
-- |
Spent lubricating oil and
mineral oil |
Effluent Discharge License |
EP880/W10/XX0261 |
|
|
-- |
Notification of Constriction
Work under APCO (Construction Dust) |
001012125 |
|
-- |
-- |
Implementation
Status of Environmental Mitigation Measures
6.226.21
In response to the site audit
findings, the Contractor carried out corrective actions.
6.236.22
A summary of the Implementation
Schedule of Mitigation Measures (EMIS) is presented in Appendix C. Most of the
necessary mitigation measures were implemented properly.
Summary
of Exceedances of the Environmental Quality Performance Limit
6.246.23
All 1-hour TSP, 24-hour TSP and
noise monitoring results complied with the Action / Limit levels.
6.256.24
No exceedance was recorded in
the reporting month.
Summary
of Complaints, Notification of Summons and Successful Prosecutions
6.266.25
The Environmental Complaint
Handling Procedure is annexed in Figure 6.1.
6.276.26
No
environmental complaint, notification of summons and successful prosecutions
was received in the reporting month.
Construction
Programme for the Coming Months
7.1
The construction programme for the Project is provided
in Appendix B.
7.2
The major construction work in May 2009 will be:
-
Rock
slope stabilization works at Portion D;
-
Soil nail heads construction at
Portion B2 and Portion C;
-
Soil nailing works at Portion
B2; and
-
Backfilling of hessian
fertilized soil bags to soil nail heads and lying of erosion control mat to
soil nail heads at Portion A1 and Portion A2.
7.3
Key issues to be considered in the coming month
included:
-
Sufficient dust suppression measures should be maintained;
-
Collection of construction waste should be carried out
regularly;
-
Site runoff should be properly collected and treated
prior to discharge;
-
Construction activities should avoid causing damage to
the trees and to plants species of conservation interest; and
-
Quieter powered mechanical equipment should be used.
7.4
The following mitigation measures are required:
Air
Quality Impact
-
Regular watering should be used during soil nailing;
-
Dusty material stockpiled should be completely covered;
-
Dusty activities should be re-scheduled if high-wind
conditions encountered;
-
Open burning should be strictly prohibited;
-
All dusty vehicle loads transporting to, from and
between site locations should be covered with tarpaulin;
-
Vehicle wheel and body washing facilities should be
used at all exit points of the site;
-
Wind shield, dust extraction units or water spraying
should be used at the loading points.
Construction
Noise Impact
-
Quieter powered mechanical equipment should be used;
-
Insulating fabric should be used for drill rigs during
drilling process;
-
Noise generating construction works should be carried
out during daytime only;
-
Noise barriers or other measures should be used to
minimize disturbance to the bat roost;
-
Plant on site should be properly maintained and
serviced regularly;
-
Mobile plants should be sited as far from NSRs as
possible;
-
Machines and plant in intermittent use should be
throttled down;
-
Strong noise emitting plants, wherever possible, should
be oriented so that noise is directed away from the nearby NSRs;
-
Material stockpiles, wherever possible, should be
effectively utilized to screen noise from construction activities;
-
Movable noise barrier with surface mass in excess of
-
Noise insulating fabric should be adopted for drill rig
operating in Works Area E.
Water
Quality Impact
-
Prevent runoff water from entering the nearby
water-bodies;
-
Silt traps and oil / grease separators should be
regularly cleaned and maintained;
-
Outlet pipe extending above the slope surface should be
installed;
-
Air should be used as the flushing medium of the
drilling equipment;
-
Earth bunds or sand bag barriers should be provided
on-site to direct storm water to silt removal facilities;
-
Exposed slope / soil surface and opened stockpile of
more than
-
Oils and fuels should be used and stored in designated
area.
Chemical
and Waste Management
-
Debris and rubbish on-site should be collected, handled
and disposed of properly;
-
Waste skips should be provided to collect general refuse
and construction wastes;
-
Soil contamination with fuel leaked from construction
plants should be removed off-site;
-
Sufficient waste disposal points with regular
collection should be provided;
-
Appropriate measures should be provided to minimize
windblown litter and dust during transportation of waste;
-
Different containers should be used to segregate and
store different types of waste;
-
Encourage collection of aluminum cans, PET bottles and
paper by providing separate bins;
-
Unused chemicals should be recycles wherever possible;
-
Proper storage and site practices should be adopted to
minimize the potential for damage and contamination of construction materials;
-
Oils and fuels should be stored in designated area;
-
Plan and stock construction materials carefully to
minimize waste generation.
Ecological
Impact
-
Soil nail installation should avoid / minimize damage
of root system to the existing plants;
-
Fences should be erected along the boundary of the
works area
-
Disturbance to the natural woodland and shrubland habitats
should be minimized by preventing tipping, vehicle movements and encroachment
of personnel onto the adjacent area;
-
Permanent casing should be provided to the drillhole of
soil nail;
-
Placement of equipment or stockpile should be located
in designated areas to minimize disturbance to natural or moderate-high
ecological value habitats;
-
Construction activities should be restricted to works
areas;
-
Disturbance to existing vegetation should be minimized
wherever possible.
Landscape
and Visual Impact
-
Designation of “no-intrusion zones” and record any
trespass and damage to existing vegetation;
-
Soil nails on site should avoid tree trunks and tree
roots;
-
Dust and erosion control should be provided for exposed
soil;
-
For tree planting operations, method statement should
be checked against specification requirements;
-
All retained trees within the working boundary should
be checked regularly;
-
Control over appearance of hoarding, construction
plants / machines;
-
Security floodlights should be carefully selected to avoid
light pollution.
Monitoring
Schedule for the Coming Months
7.5
The tentative schedule for environmental monitoring in May
2009 is provided in Appendix L.
8.1
The construction phase of the project commenced in
April 2008.
8.2
1-hour TSP and 24-hour TSP monitoring was carried out
in the reporting month. All monitoring results complied with the action / limit
level. No exceedance was recorded.
8.3
All impact daytime noise monitoring results complied
with the limit level in the reporting month.
8.4
Environmental
site inspections were carried out 4 times in April 2009. Recommendations on
remedial actions were given to the Contractor for the deficiencies identified
during the site audit.
8.5
Two landscape and visual audits were carried out in the
reporting month. Construction materials were observed placed against existing
trees. The Contractor was reminded to keep construction materials away from the
trees.
8.6
Two ecological audits were carried out in the reporting
month. The Contractor was reminded
to preserve the identified vegetation of conservation interest. All tagged plants of conservation
interest in the affected area should be located and fenced off properly with
clear sign to avoid any further damage and restrict any unauthorized access of
site workers to the area. The leaves of
vegetation within works areas should be washed regularly to avoid excessive
dust deposition. To further protect the other vegetation/tree, the Contractor
was recommended to remove any grout and soil nailing machine from the natural
habitat as well as add sand bags around the hardened grout.
8.7
No environmental complaint, notification of summons and
prosecution was received in the reporting month.
8.8
According to the environmental site inspections
performed in the reporting month, the following recommendations were provided:
Air
Quality Impact
-
Soil nail workstations on site should be properly enclosed.
Construction
Noise Impact
-
Nil
Water
Quality Impact
-
Sedimentation tanks on site should be properly
maintained;
-
Site effluent must be collected and treated prior to
discharge to public drain;
-
U-channels should be kept clear of mud, debris, leaves,
construction waste and materials; and
-
Soil and exposed earth at all working platforms and
slopes should be cleaned up.
Chemical
and Waste Management
-
Drip trays should be provided to all plants and chemical
containers on site;
-
Oils and fuels should be stored in designated area;
-
Empty chemical containers should be disposed of as
chemical waste;
-
C&D waste, debris and general refuse on-site should
be collected, handled and disposed of properly; and
-
Waste skips should be provided to collect general
refuse and construction wastes.
Ecological
Impact
-
The Contractor was reminded to take all necessary
actions to prevent grout leakage and muddy run-off to the surrounding natural
environment;
-
All identified vegetation of conservation interest
should be preserved;.
-
All site access should be clearly demarcated and no
excessive removal of vegetation in natural areas adjacent to the site access
should be allowed;
-
All plant species of conservation interest should be
fenced off properly with clear sign, especially for those located near major
access road and areas likely to be impacted by construction activities; and.
-
The
Contractor was recommended to take necessary measures to prevent damage to all vegetation
within the construction site.
Landscape
and Visual Impact
-
The Contractor was recommended to remove the dead tree
T534 and T511 from site for safety considerations, especially the tree was
found infected by termite. The
Contractor was also reminded to record and report all dead trees as found on
site to the Engineer for record;.
-
The Contractor was reminded to rectify all remaining
ineligible / missing tree ID numbers for all existing trees;.
-
The Contractor was recommended to clarify the status of
missing trees as soon as possible;.
-
The Contractor was recommended to seek Engineer’s
agreement on the replacement planting for dead trees; and.
-
The Contractor was recommended to clear the
construction materials away from existing trees and not to stockpile materials
against trees in future.