Submission Checking Record_01

L-0188 Hyder-Verification of QEM&A Report for Nov 2013 - Jan 2014_01

TABLE OF CONTENTS

Page

EXECUTIVE SUMMARY  1

1       introduction  3

2       Environmental Monitoring and Audit Requirements  6

3       Air Quality Monitoring   7

4       Construction Noise MONITORING   8

5       ENVIRONMENTAL SITE INSPECTION AND AUDIT  9

6       Advice on the Solid and Liquid Waste Management Status  11

7       Summary of Non-compliance (Exceedances) of the Environmental Quality  11

8       Environmental Complaints, Notification of Summons and Successful Prosecutions  11

9       Comments, recommendations and Conclusions  17

 

List of Tables

 

Table 1.1       Contact Information of Key Personnel

Table 3.1       Summary of Number of Monitoring Events for 1-hr & 24-hr TSP Concentration

Table 3.2       Summary of Number of Exceedances for 1-hr & 24-hr TSP Monitoring

Table 4.1       Summary of Number of Monitoring Events for Construction Noise

Table 4.2       Summary of Number of Monitoring Exceedances for Construction Noise

 

Figures

 

Figure 1.1      General Project Layout Plan

Figure 2.1      EM&A Monitoring Locations

 

List of Appendices

 

Appendix A       Project Organization Structure

Appendix B       Construction Programmes

Appendix C       Implementation Schedule of Environmental Mitigation Measures (EMIS)

Appendix D      Summary of Action and Limit Levels

Appendix E       Graphical Presentation of Impact Air Quality Monitoring Results

Appendix F       Graphical Presentation of Impact Daytime Construction Noise Monitoring Results

Appendix G      Cumulative Statistics on Complaints, Notifications of Summons and Successful Prosecutions

 

 


EXECUTIVE SUMMARY

The proposed widening of Tolo Highway and Fanling Highway between Island House Interchange and Fanling (the Project) is a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) and is governed by an Environmental Permit (EP-324/2008)(EP) issued by EPD on 23 December 2008. Subsequently, EPD issued a Variation of Environmental Permit (EP-324/2008/A) (VEP) on 31 January 2012.

The Project aims to widen Tolo Highway and Fanling Highway to dual 4-lane carriageway in order to alleviate the current traffic congestion problems and to cope with the increasing transport demands to and from the urban areas and also cross boundary traffic.

The construction works for this Project will be delivered in 2 stages i.e. Stage 1 (between Island House Interchange and Tai Hang) and Stage 2 (between Tai Hang and Wo Hop Shek Interchange). The construction works of Stage 1 commenced on 23 November 2009 and will tentatively be completed in March 2014. This report focuses on Stage 1 of the Project only.

The construction phase of Stage 1 under the EPs and the Environmental Monitoring and Audit (EM&A) programme for Stage 1 of the Project commenced on 23 November 2009. The impact environmental monitoring and audit includes air quality and noise monitoring.

This report documents the findings of EM&A works conducted in the period between 1 November 2013 and 31 January 2014. As informed by the Contract 1 Contractor (CSHK), construction activities in the reporting period were:-

 

-        Temporary shoring, sheetpiling and excavation;

-        At-grade road construction;

-        Widening and demolition of central dividers;

-        Retaining wall construction;

-        Noise barrier footing construction;

-        Noise barrier panels installation;

-        Asphalt laying;

-        Installation of Drainage Pipes; and

-        Modification of Edge coping.

 

 

The construction works carried out by the Contract 2 Contractor (GCL) in the reporting period were:-

 

-        Condition survey of existing structures;

-        Setting up the temporary traffic arrangement;

-        Excavation of trial trenches to locate existing utilities;

-        Construction of haul road;

-        Construction of concrete profile barrier and beam barrier;

-        Construction of Pilecap / Spread footing of Noise Barrier / Semi Noise Enclosure;

-        Slope works, including installation of soil nails;

-        NTHA mitigation works;

-        Construction of retaining walls;

-        Noise barrier construction;

-        Modification of existing bridge structures;

-        Entrusted watermains works;

-        Sewer Installation;

-        Road and drainage works; and

-        Landscaping works.

-           


Environmental Monitoring Works

 

A summary of monitoring and audit activities conducted in the reporting quarter is listed below:-

 

24-hour TSP monitoring

17 sessions

1-hour TSP monitoring  

51 sessions

Daytime Noise monitoring

13 regular sessions

Environmental Site inspection

13 sessions (Contract 1) / 13 sessions (Contract 2)

 

                                                                       

Breaches of Action and Limit Levels for Air Quality

No exceedance of Action and Limit Level was recorded for 1-hour TSP monitoring in the reporting quarter.

 

No exceedance of Action and Limit Level was recorded for 24-hour TSP monitoring in the reporting quarter.

 

Breaches of Action and Limit Levels for Noise

No exceedance of Limit and Action Levels was recorded for noise monitoring in the reporting quarter.

 

Complaint, Notification of Summons and Successful Prosecution

There were four (4) complaints (including one (1) air-related complaint, one (1) air-and-water-related complaint and two (2) noise-related complaints) followed up by the Environmental Team (ET) in the reporting quarter.

There was one (1) follow-up complaint (including one (1) air-related complaint) followed up by the ET in the reporting quarter.

Investigations were carried out. Findings and proposed mitigation measures of the complaints were submitted to all relevant parties.  

No notifications of summons and successful prosecutions was received in the reporting quarter.


 

1              introduction

Background

 

1.1.         Tolo Highway and Fanling Highway are expressways in the North East New Territories connecting Sha Tin, Tai Po and Fanling. These highways form a vital part of the strategic Route 9, which links Hong Kong Island to Shenzhen. At present, this section of Route 9 is dual 3-lane carriageway. However, at several major interchanges along this section of Route 9, the highway is only dual-2 lane. Severe congestion is a frequent occurrence during peak periods, particularly in the Kowloon bound direction.

 

1.2.         The objective of the Project “Widening of Tolo Highway / Fanling Highway between Island House Interchange and Fanling” is to widen Tolo Highway and Fanling Highway to dual 4-lane carriageway in order to alleviate the current traffic congestion problems and to cope with the increasing transport demands to and from the urban areas and also cross boundary traffic.

 

1.3.         The Project is a designated project and is governed by an Environmental Permit (EP-324/2008)(EP) issued by EPD on 23 December 2008. Subsequently, EPD issued a Variation of Environmental Permit (EP-324/2008/A) (VEP) on 31 January 2012.

 

1.4.         The scope of the Project comprises mainly:

 

(i)

Widening of a 5.7 km section of Tolo Highway and 3.0 km section of Fanling Highway between Island House Interchange and Wo Hop Shek Interchange from the existing dual 3-lane to dual 4-lane, including construction of new vehicular bridges;

(ii)

Widening of interchange sections at Island House Interchange, Tai Po North Interchange, and Lam Kam Road Interchange from dual 2-lane to dual 3-lane, except Sha Tin bound carriageway at Tai Po North Interchange, which is widened from 3-lane to 4-lane, including realignment of various slip roads;

(iii)

Modification and reconstruction of highways, vehicular bridges, underpasses and footbridges.

 

1.5.         The construction works for this Project will be delivered in 2 stages i.e. Stage 1 (between Island House Interchange and Tai Hang) and Stage 2 (between Tai Hang and Wo Hop Shek Interchange). The construction works of Stage 1 commenced on 23 November 2009 and will tentatively be completed in March 2014. This report focuses on Stage 1 of the Project only.

 

1.6.         The construction works for Stage 1 of the Project will be implemented under 2 works contracts (Contract 1 and Contract 2).  Contract 1 covers the section of Tolo Highway between Island House Interchange and Ma Wo, Contract 2 covers the section of Tolo Highway between Ma Wo and Tai Hang.

 

1.7.         Hyder-Arup-Black and Veatch Joint Venture (HABVJV) are appointed by Highways Department (HyD) as the consultants for the design and construction assignment for the Tolo project under Agreement No. CE 58/2000 Supplementary Agreement No. 3 (SA3) (i.e. the Engineer for the Contracts).

 

1.8.         China State Construction Engineering (Hong Kong) Ltd. (CSHK) was commissioned as the Contractor of Contract 1 of Stage 1 of the Project, while Gammon Construction Limited (GCL) was commissioned as the Contractor of Contract 2 of Stage 1 of the Project.

 

1.9.         AECOM Asia Co. Ltd. was employed by Highways Department as the Environmental Team (ET) to undertake the Environmental Monitoring and Audit (EM&A) works for Stage 1 of the Project and Mott MacDonald Hong Kong Ltd. acts as the Independent Environmental Checker (IEC) for the Contracts.

 

1.10.       The construction phase of Stage 1 under the EPs commenced on 23 November 2009.

 

1.11.       According to the updated EM&A Manual of Stage 1 of the Project, there is a need of an EM&A programme including air quality and noise monitoring. The EM&A programme for Stage 1 of the Project commenced on 23 November 2009.

 


Scope of Report

 

1.12.       This is the seventeenth Quarterly EM&A Summary Report under the Agreement No. CE 20/2009 (EP) - Widening of Tolo Highway between Island House Interchange and Tai Hang – Investigation.  This report presents a summary of the environmental monitoring and audit works, list of activities and mitigation measures proposed by the ET for Stage 1 of the Project between 1 November 2013 and 31 January 2014.

 

 

Project Organization

 

1.13.       The project organization structure is shown in Appendix A. The key personnel contact names and numbers are summarized in Table 1.1.

 

              Table 1.1          Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

ER of Stage 1, Contract 1

(Hyder-Arup-Black & Veatch Joint Venture)

Chief Resident Engineer /TOLO1

James Tsang  

9038 8797

2667 4000

ER of Stage 1, Contract 2

(Hyder-Arup-Black & Veatch Joint Venture)

Chief Resident Engineer /TOLO2

Paul Appleton

9097 5833

2653 2348

IEC of Stage 1

 (Mott MacDonald Hong Kong Limited)

Independent Environmental Checker

Terence Kong

2828 5919

2827 1823

Contractor of    Stage 1, Contract 1

 

(China State Construction Engineering (Hong Kong) Limited)

Site Agent

Eddie Tang

9863 7686

2667 5666

Environmental Officer

Michael Tsang

9277 4956

2667 5666

Contractor of    Stage 1, Contract 2

 

(Gammon Construction Limited)

Site Agent

John Chan

3126 1202

2559 3410

Environmental Officer

Thomson Chang

9213 6569

2559 3410

Crispin Ao

9223 8773

2559 3410

Jason Cheng

9837 9323

2559 3410

ET of Stage 1

 (AECOM
Asia Company Limited)

ET Leader

Y T Tang

3922 9393

3922 9797

 

Summary of Construction Works

1.14.       The construction phase of Stage 1 under the EPs commenced on 23 November 2009. Details of the construction works carried out by the Contract 1 Contractor (CSHK) in this reporting period are listed below:-

 

-   Temporary shoring, sheetpiling and excavation;

-   Pile cap construction (Noise Barrier);

-   At-grade road construction;

-   Widening and demolition of central dividers;

-   Retaining wall construction;

-   Noise barrier footing construction;

-   Noise barrier panels installation;

-   Asphalt laying;

-   Installation of Drainage Pipes; and

-   Modification of Edge coping.

 

 

1.15.       The construction works carried out by the Contract 2 Contractor (GCL) in the reporting period were:-

 

-   Condition survey of existing structures;

-   Setting up the temporary traffic arrangement;

-   Excavation of trial trenches to locate existing utilities;

-   Construction of haul road;

-   Construction of concrete profile barrier and beam barrier;

-   Construction of Pilecap / Spread footing of Noise Barrier / Semi Noise Enclosure;

-   Slope works, including installation of soil nails;

-   NTHA mitigation works;

-   Construction of retaining walls;

-   Noise barrier construction;

-   Modification of existing bridge structures;

-   Entrusted watermains works;

-   Sewer Installation;

-   Road and drainage works; and

-   Landscaping works.

 

 

1.16.       The Construction Programmes are shown in Appendix B.

 

1.17.       The general layout plan of the Project site showing the contract areas is shown in Figure 1.1.

 

1.18.       The environmental mitigation measures implementation schedule are presented in Appendix C.

 

 

 


2              Environmental Monitoring and Audit Requirements

Monitoring Parameters

2.1.         The updated EM&A Manual designated 4 air quality monitoring stations and 7 noise monitoring stations to monitor environmental impacts on air quality and noise due to Stage 1 of the Project.

2.2.         For air quality, monitoring locations AM2 (Shan Tong New Village) and AM3 (Riverain Bayside) were set up at the proposed locations in accordance with updated EM&A Manual. However, for monitoring locations: Dynasty View and Tai Po Garden, proposed in the updated EM&A Manual, as approval could not be obtained from the owner’s corporation of the premises, impact air quality monitoring was conducted at alternative monitoring locations: AM1 (Ha Wun Yiu) and AM4 (Tai Kwong Secondary School). The monitoring station at 13 Ha Wun Yiu (AM1) was relocated to Fan Sin Temple, 3 Sheung Wun Yiu (AM1A) in February 2010.

2.3.         For noise, monitoring stations NM3 (Wong Shiu Chi Middle School), NM6 (PLK Tin Ka Ping Primary School) and NM7 (Riverain Bayside) were set up at the proposed locations in accordance with updated EM&A Manual. However, for monitoring locations: Tai Po Garden, Dynasty View, Hong Kong Teachers’ Association Lee Heng Kwei Secondary School and Grand Palisades, proposed in the updated EM&A Manual, as approval of access could not be obtained from the owner’s corporation of the premises or the principal of the education institutes, impact noise monitoring was conducted at alternative monitoring locations: NM1 (Tai Kwong Secondary School), NM2 (Ha Wun Yiu), NM4 (Uptown Plaza) and NM5 (The Paragon).

2.4.         As Tai Kwong Secondary School was closed down with effect from 1 September 2011, air quality (AM4) and noise (NM1) monitoring stations were relocated to 168 Shek Kwu Lung Village, naming AM4A and NM1A respectively, starting from 1 September 2011. The same air quality Action and Limit of AM4 were adopted for AM4A. For the measured construction noise level, the same noise Action Level of NM1 was adopted for NM1A, whereas Limit Level for residential noise sensitive receiver was adopted for NM1A.

2.5.         The monitoring locations used during the reporting period are depicted in Figure 2.1.

2.6.         The updated EM&A Manual also required environmental site inspections for air quality, noise, water quality, chemical, waste management, ecology and landscape and visual impact.

Environmental Quality Performance Limits (Action/Limit Levels)

2.7.         The environmental quality performance limits (i.e. Action/Limit Levels) of air quality monitoring were derived from the baseline air quality monitoring results at the respective monitoring stations (AM1, AM2, AM3 and AM4), while the environmental quality performance limits of noise monitoring were defined in the EM&A Manual.

2.8.         The environmental quality performance limits of air quality and noise monitoring and are given in Appendix D.

Environmental Mitigation Measures

2.9.         Relevant environmental mitigation measures were stipulated in the Particular Specification and EPs (EP-324/2008 and EP-324/2008/A) for the Contractor to adopt. A list of environmental mitigation measures and their implementation statuses are given in Appendix C.


 

3              Air Quality Monitoring

3.1.         Air quality monitoring, including 1-hour and 24-hour TSP, was conducted at least 3 times every 6 days and at least once every 6 days respectively at the 4 monitoring stations (AM1A, AM2, AM3 and AM4A), in accordance with the updated EM&A Manual.

 

3.2.         The weather was mostly sunny, with several fine, cloudy and rainy days in the reporting quarter. The major dust source in the reporting period included construction activities from Stage 1 of the Project, as well as nearby traffic emissions.

 

3.3.         The number of monitoring events and exceedances recorded in each month of the reporting quarter are presented in Table 3.1 and Table 3.2 respectively.

Table 3.1            Summary of Number of Monitoring Events for 1-hr & 24-hr TSP Concentration

Monitoring Parameter

Location

No. of monitoring events

Nov 13

Dec 13

Jan 14

1-hr TSP

AM1A

15

18

18

AM2

15

18

18

AM3

15

18

18

AM4A

15

18

18

24-hr TSP

AM1A

5

6

6

AM2

5

6

6

AM3

5

6

6

AM4A

5

6

6

 

Table 3.2            Summary of Number of Exceedances for 1-hr & 24-hr TSP Monitoring

Monitoring Parameter

Location

Level of Exceedance

Level of Exceedance

Nov 13

Dec 13

Jan 14

1-hr TSP

AM1A

Action

0

0

0

Limit

0

0

0

AM2

Action

0

0

0

Limit

0

0

0

AM3

Action

0

0

0

Limit

0

0

0

AM4A

Action

0

0

0

Limit

0

0

0

 

Total

0

0

0

24-hr TSP

AM1A

Action

0

0

0

Limit

0

0

0

AM2

Action

0

0

0

Limit

0

0

0

AM3

Action

0

0

0

Limit

0

0

0

AM4A

Action

0

0

0

Limit

0

0

0

 

Total

0

0

0

 

3.4.         All 1-hour TSP results were below the Action and Limit Level at all monitoring locations in the reporting quarter.

 

3.5.         All 24-hour TSP results were below the Action and Limit Level at all monitoring locations in the reporting period.

 

 

3.6.         The graphical plots of the impact air quality monitoring results are provided in Appendix E.


4              Construction Noise MONITORING

4.1.         Construction noise monitoring was conducted at the 7 monitoring stations (NM1A, NM2, NM3, NM4, NM5, NM6 and NM7) for at least once per week during 07:00 – 19:00 in the reporting quarter.

 

4.2.         The major noise sources during the noise monitoring included construction activities of Stage 1 of the Project and nearby traffic noise. In addition, for NM3 and NM6, general school activities are also a major noise source during the noise monitoring.

 

4.3.         The number of construction noise monitoring events and exceedances are summarized in Table 4.1 and Table 4.2 respectively. 

Table 4.1            Summary of Number of Monitoring Events for Construction Noise

Monitoring Parameter

Location

No. of monitoring events

Nov 13

Dec 13

Jan 14

NM1A

4

5

4

NM2

4

5

4

NM3

4

5

4

NM4

4

5

4

NM5

4

5

4

NM6

4

5

4

NM7

4

5

4

Table 4.2            Summary of Number of Monitoring Exceedances for Construction Noise

Monitoring Parameter

Location

Level of Exceedance

Level of Exceedance

Nov 13

Dec 13

Jan 14

NM1A

0

0

0

NM2

0

0

0

NM3

0

0

0

NM4

0

0

0

NM5

0

0

0

NM6

0

0

0

NM7

0

0

0

 

Total

0

0

0

 

4.4.         All measured construction noise levels were below the Limit level and the graphical plots of the trends of the monitoring results are provided in Appendix F. No Limit and Action level exceedance of construction noise monitoring was recorded in the reporting quarter.


 

5              ENVIRONMENTAL SITE INSPECTION AND AUDIT

5.1.         Site Inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures for Stage 1 of the Project. In the reporting quarter, 13 site inspections were carried out for Contract 1 and 13 site inspections were carried out for Contract 2 of the Project.

5.2.         Particular observations and reminder during the site inspections for Contract 1 are described below:-

 

Air Quality

 

5.2.1.     Dry soil surface was observed on access roads and the Contractor was reminded to spray the access road with water or dust suppression chemicals to maintain the entire surface wet.

5.2.2.     Dry surfaces were observed on access roads near the site exit. The Contractor was reminded to spray water to maintain the entire surface wet and wash the wheels of vehicles before leaving the construction site.

 

Noise

 

5.2.3.     No adverse observation was identified in the reporting quarter.

 

Water Quality

 

5.2.4.     No adverse observation was identified in the reporting quarter .

 

Chemical and Waste Management

5.2.5.      

5.2.6.     The Contractor was reminded to provide a drip tray to hold the oil can.

5.2.7.     Oil drums were observed without drip tray and the Contractor was reminded to provide trays to oil drums as a mitigation measure.

5.2.8.     The Contractor was reminded to clear the construction waste at the waste skip.

 

Landscape and Visual Impact

 

5.2.9.     No adverse observation was identified in the reporting quarter.

 

Miscellaneous

 

5.2.10.   The Contractor was reminded to clear the stagnant water at the drip tray so as to prevent mosquito breeding.

 

5.3.         Particular observations during the site inspections for Contract 2 are described below:-

 

 

Air Quality

 

5.3.1.     The Contractor was reminded to cover the exposed slope at Gate 48 with tarpaulin sheets.

5.3.2.     Mud was observed at the edge of the footpath at NLKP3. The Contractor was reminded to clear the mud and increase the height of sand bags to prevent the overflow of sand from the construction site.

 

Noise

 

5.3.3.     The Contractor was reminded to wrap the breaker properly with sound-absorptive materials.

 

Water Quality

 

5.3.4.     The Contractor was reminded to provide a drip tray to hold the oil can or remove the oil can.

5.3.5.     Oil leakage was observed under the generator. The Contractor was reminded to clear the oil stain, and identify and eliminate the source of leakage.

5.3.6.     Muddy water was observed at the edge of the road at W74. The contractor was reminded to direct the water to an appropriate discharge point so that it will not mix with sand to produce muddy water.

5.3.7.     The Contractor was reminded to clear the muddy water at the wheel-washing facilities in Shek Kwu Lung.

 

Chemical and Waste Management

 

5.3.8.     The Contractor was reminded to cover the stockpiles at Gate 7B.

5.3.9.     The Contractor was reminded to clear the general refuse at Bridge 13.

5.3.10.   The Contractor was reminded to provide a drip tray to oil cans at Gate 2 or remove the oil cans.

5.3.11.   The Contractor was reminded to clear the refuse at the waste skip at G40A.

5.3.12.   The Contractor was reminded to provide a drip tray to the chemical container on Lam Kam Flyover or remove the chemical container.

5.3.13.   The Contractor was reminded to clear the general refuse inside and next to the rubbish bin

 

Landscape and Visual Impact

 

5.3.14.   No adverse observation was identified in the reporting quarter.

 

Miscellaneous

           

5.3.15.   No adverse observation was identified in the reporting quarter.

6              Advice on the Solid and Liquid Waste Management Status

6.1.1       The Contract 1 Contractor (CSHK) and the Contract 2 Contractor (GCL) are registered as chemical waste producers for Stage 1 of the Project. C&D material sorting was carried out on site. Sufficient numbers of receptacles were available for general refuse collection.

6.1.2      As advised by the Contract 1 Contractor (CSHK), 677m3 of inert C&D material was disposed as public fill to Tuen Mun 38(of which 146m3 was broken concrete), while 410m3 of general refuse were disposed at NENT landfill. 36,741kg of metal, 286kg of paper/cardboard and 8,852kg of plastic were collected by recycling contractor in the reporting quarter. 4,653m3 and 2,556m3 of inert C&D materials were reused on site and in NENT for backfilling respectively. On the other hand, 0kg of chemical waste was collected by licensed contractor in the reporting period.

6.1.3       As advised by the Contract 2 Contractor (GCL), 590m3 of inert C&D material were disposed to Tuen Mun 38 and 680m3 of general refuse was disposed to NENT landfill in the reporting period. 0m3 of  paper/cardboard packaging was collected by the recycling contractor in the reporting period. 0kg of plastics and 0kg of metals were collected by the recycling contractor in the reporting period. No inert C&D materials was reused on site. 260m3 of inert C&D materials was reused in other projects. No chemical waste was collected by the licensed contractor in the reporting period.

6.1.4       The Contract 1 Contractor (CSHK) and the Contract 2 Contractor (GCL) are advised to maintain on site waste sorting and recording system and maximize reuse / recycle of C&D wastes.

7              Summary of Non-compliance (Exceedances) of the Environmental Quality

7.1.         All 1-hour TSP monitoring results complied with the Action / Limit Levels in the reporting period.

7.2.         All 24-hour TSP monitoring results complied with the Action / Limit Levels in the reporting period.

7.3.         No Limit and Action Level exceedance of construction noise monitoring was recorded in the reporting period.

8              Environmental Complaints, Notification of Summons and Successful Prosecutions

8.1.         A 24-hour complaint hotline at 6628 8366 has been established for Stage 1 (both Contract 1 and Contract 2) of the Project. Also a 24-hour hotline at 8201 6669 is established for Contract 1 of the Project. The hotline numbers are displayed at the site entrances, fencings and project signboards, as well as printed on publications for the public, such as newsletters.

8.2.         No notifications of summons and prosecutions was received in the reporting quarter.

8.3.         There were four (4) complaints (including one (1) air-related complaint, one (1) air-and-water-related complaint and two (2) noise-related complaints) followed up by the Environmental Team (ET) in the reporting quarter.

8.4.         There was one (1) follow-up complaint (including one (1) air-related complaint) followed up by the ET in the reporting quarter.

8.5.         The investigation details are given below:

-           

 

 

 

 

 

 


8.1.1       Environmental Enquiry No.: EC-34

8.6.         One (1) noise-related complaint was received on 4 November 2013 and followed up by the Environmental Team in November and December 2013.

8.7.         EPD referred a noise complaint from a resident living near Uptown Plaza at Tai Po on 4 November 2013. The complainant expressed that the construction work between late-night hours on 2 November and early morning of 3 November at Tolo Highway disturbed the resident’s sleep.

8.8.         According to the information provided by the Contractor (China State Construction Engineering (HK) Ltd.) and confirmed by the Engineer of the Project, road marking alternation works was carried out at Tolo Highway between 23:00 on 2 November 2013 and 05:00 on 3 November 2013. The permitted works area and the exact working area for road marking alternation are indicated in the site location plan.

8.9.         A valid Construction Noise Permit (CNP no.: GW-RN0607-13) has been obtained for the use of certain specified Powered Mechanical Equipments (PMEs) and carrying out of certain prescribed construction work at Tolo Highway (Shatin Bound) between Grand Dynasty View and the Paragon between 23:00 on Saturdays and 05:00 on Sundays, subject to the conditions imposed in the CNP. The numbers and types of PMEs operated between 23:00 on 2 November 2013 and 05:00 on 3 November 2013 complied with the CNP. The list of plants used during the construction works (provided by the Contractor and confirmed by the Engineer) on 2 and 3 November 2013 was also checked for verification.

8.10.      Notification was sent to EPD at 13:18 hours on 1 November 2013 prior to the commencement of the construction work but the notification period was less than the required 48 hours before the said works carried out at 23:00 on 2 November 2013.

8.11.      The Contractor notified the nearby residents in advance of the construction work by disseminating a public notice to the estates management offices of the affected residential buildings on 1 November 2013.

8.12.      However, the noise complaint is considered project-related.

8.13.      Upon the receipt of the complaint, the Contractor stopped the road works as soon as practicable as determined by The Highways Department. A safety net had been set up to cover the skip of dump trucks to reduce the dropping height of milling materials (rubbles) to reduce the impact noise for any future works conducted under CNP no.: GW-RN0607-13, but the results were not satisfactory. Hence, this measure will not be implemented. However, the Contractor was urged to shorten the time of handling rubbles as much as possible to minimize the nuisance caused to the nearby residents. Additionally, the Contractor has shut off idling plants at once. The Contractor also wrapped up the reversing alarm of the PMEs with sound-absorbing materials to reduce noise generated from similar works so as to minimize the impacts to nearby residents.

8.14.      The Contractor has been setting up permanent noise barriers at both sides of the section of the road where road marking alternation works were carried out. Most of the noise barriers have been erected and the Contractor will install all the remaining noise barrier panels by January 2014. The Contractor was prompted to install the remaining permanent noise barriers as soon as it can.

8.15.      The Contractor also visited the Management Offices of nearby estates thereafter to introduce them about its works programme and night works of the coming two months. Meanwhile, a public notice was disseminated to the estates on 6 November 2013 and is displayed at the lift lobby of the estates to inform the residents about its works.

8.16.      According to the Contractor, no further works in relation to CNP no.: GW-RN0607-13 is scheduled before the CNP expires at 05:00 on 22 December 2013, even though the CNP permits such prescribed use of the specified PMEs for a total of 10 nights during its validity period. However, the Contractor was urged to comply with conditions of this and subsequent CNPs for future works and make advance notifications to the EPD at least 48 hours before the scheduled commencement of works. The Contractor was prompted to improve their management and schedule night works as early as possible to prevent late notification. The Contractor was reminded to review the current working method and implement noise mitigation measures so as to minimize nuisance caused to sensitive receivers.

8.17.      In addition, the Contractor is advised to implement the mitigation measures as stated in “Recommended Mitigation Measures” below:

-          Strictly comply with the requirements of the approved CNP for works carried out in restricted hours;

-          Have better scheduling of works to minimize noise nuisance;

-          Instruct the site workers to keep the noise in minimum during construction works in restricted hours; and

-          Foster better public relations with the sensitive receivers nearby.

 

Environmental Enquiry No.: EC-35

 

8.18.      One (1) air-related complaint was received on 13 December 2013 and followed up by the Environmental Team in December 2013.

8.19.      EPD referred a complaint from a resident of Ma Wo Tsuen about the dust emission at the construction site of the Tolo Highway widening construction works at Ma Wo on 13 December 2013. The complainant has complained about the air pollution problem for three years and that no improvement has been seen.

8.20.      The complainant stated that there are no water sprinklers in the construction site and the residents of Ma Wo Tsuen have requested the Contractor to use tarpaulin sheets.

8.21.      As informed by the Contractor (Gammon Construction Ltd) and confirmed by the Engineer of the Project, catchment drain, backfilling and compaction work of general fill materials at W38 and delivery of fill materials from W48 to W38 by dump truck on 12 December 2013 (Thursday) and 13 December 2013 (Friday) were carried out at the work areas near the residential flat of the complainant.

8.22.      Mitigation measures, including water spraying by sprinklers on haul roads and exposed slopes, covering non-working slopes by tarpaulin sheets at a sight distance from the complainant before the complete construction of permanent footpath, full-time manual water spraying, and the tarpaulin dust screen of appropriately 1.8 m in height set on the top of W45-47 which is along W44 and NB31, and a section of footpath on W38, were taken by the Contractor. As shown in Figure 4B, water is sprayed manually to the leaves of the trees to minimize the emitted dust from dropping to the complainant’s house and Ma Wo Tsuen through the trees. As shown in Figure 5, the loading and unloading height of general fill materials at W38 was kept to a minimum. Besides, in case any dump truck passes through W45-47, the mechanical covering will not open until they reach the unloading point.

8.23.      Wheel washing has been carried out at the site entrance. The dump truck responsible for the delivery of fill materials for W38 only moved within W48 and W38, which was not exiting from the site entrance on 12 and 13 December 2013.

8.24.      With reference to the monitoring results recorded on the day closest to the day of complaint at the nearest EM&A monitoring station (AM1A- Sheung Wun Yiu), the 24-hour TSP level on 10 December 2013 was 133.8 ug/m3, which was below the action level of 176.6 ug/m3. Besides, the average 1-hour TSP 10 December 2013 at the nearest EM&A monitoring station (AM1A- Sheung Wun Yiu) was 83.5 ug/m3, which was also below the action level of 302.3ug/m3.

8.25.      Nevertheless, the complaint was considered project-related.

8.26.       Therefore, the Contractor is reminded to enhance the dust mitigation measures as stated in the “Recommended Mitigation Measures” below:

-   Confirm the implementation of dust mitigation measures (erection of tarpaulin dust screens along the work areas W38-48, spraying water manually by workers and sprinkler systems for the haul roads and exposed slopes at work areas W38-48, covering non-working slopes by tarpaulin sheets within work areas, covering dusty materials carried in dump trucks within work areas W38-48) during all construction and dusty activities to minimize fugitive dust generation;

-   Increase the frequency of watering in the work areas (specially at the entrance of the construction site, and on site haul roads and exposed slopes / areas in the work areas W38-48), so that site haul roads and exposed surfaces are in a wet condition;

-   Cover the backfilling surface after work;

-   Keep soil surfaces wet before loading and unloading activities;

-   Maintain the frequency of the environmental supervision (by the Contractor) to regularly review the adequacy and effectiveness of dust suppression measures to suit the construction progress;

-   Inform the complainant before dusty activities (e.g. rock breaking, excavation, grouting and backfilling) are carried out; and

-   Foster better public relations with the sensitive receivers and complainants nearby.

 

Environmental Enquiry No.: EC-35 (Follow-up)

8.27.      One (1) air-related follow-up complaint was received on 22 January 2014 and followed up by the Environmental Team in January 2014.

8.28.      EPD referred a follow-up complaint from a resident of Ma Wo on 22 January 2014. The complaint is about the dust emission at the construction site of the Tolo Highway widening construction works at Ma Wo on 21 January 2014 afternoon and 22 January 2014 morning. The complainant complained that there was insufficient water spraying and tarpaulin sheets were not used. He expressed that the air pollution problem has caused nuisance to him for three years. He requests improvements by the Contractor and follow-up by the EPD.

8.29.      As informed by the Contractor (Gammon Construction Ltd) and confirmed by the Engineer of the Project, slope trimming and U-channel construction were carried out in work area W36, and slope trimming was carried out in work areas W39-W40 on 21 and 22 January 2014.

8.30.      The following mitigation measures have been done by the Contractor. The loading and unloading height of general fill materials was kept to a minimum. Wheel washing has been carried out at the site entrance. There have been water spraying by sprinklers on haul roads and exposed slopes, covering non-working slopes by tarpaulin sheets at a sight distance from the complainant before the complete construction of permanent footpath, full-time manual water spraying, and the tarpaulin dust screen of appropriately 1.8 m in height set on the top of W45-47 which is along W44 and NB31, and a section of footpath on W38. Water is sprayed manually to the leaves of the trees to minimize the emitted dust from dropping to the complainant’s house and Ma Wo Tsuen through the trees. Besides, in case any dump truck passes through W45-47, the mechanical covering will not open until they reach the unloading point.

8.31.      With reference to the monitoring results recorded on the day closest to the day of complaint at the nearest EM&A monitoring station (AM1A- Sheung Wun Yiu), the 24-hour TSP level on 21 January 2014 was 123.0 ug/m3, which was below the action level of 176.6 ug/m3. Besides, the average 1-hour TSP level 21 January 2014 at AM1A- Sheung Wun Yiu was 87.3 ug/m3, which was also below the action level of 302.3ug/m3.

8.32.      Nevertheless, the complaint was considered project-related.

8.33.       Therefore, the Contractor is reminded to enhance the dust mitigation measures as stated in the “Recommended Mitigation Measures” below:

-   Confirm the implementation of dust mitigation measures (erection of tarpaulin dust screens along the work areas W38-48, spraying water manually by workers and sprinkler systems for the haul roads and exposed slopes at work areas W38-48, covering non-working slopes by tarpaulin sheets within the work areas, covering dusty materials carried in dump trucks within work areas W38-48) during all construction and dusty activities to minimize fugitive dust generation;

-   Increase the frequency of watering in the work areas (specially at the entrance of the construction site, and on site haul roads and exposed slopes / areas in the work areas W38-48), so that site haul roads and exposed surfaces are in a wet condition;

-   Cover the backfilling surface after work;

-   Keep soil surfaces wet before loading and unloading activities;

-   Maintain the frequency of the environmental supervision (by the Contractor) to regularly review the adequacy and effectiveness of dust suppression measures to suit the construction progress;

-   Inform the complainant before dusty activities (e.g. rock breaking, excavation, grouting and backfilling) are carried out; and

-   Foster better public relations with the sensitive receivers and complainants nearby.

 

 

Environmental Enquiry No.: EC-36

8.34.      One (1) noise-related complaint was received on 13 January 2014 and followed up by the Environmental Team in January 2014. The summary of investigation is described in Sections 4.6.3 to 4.6.5.

8.35.      EPD referred a noise complaint on 13 January 2014 from a resident living in Grand Palisades at Tai Po. The complainant complained about the persistent construction noise emitted between late-night hours on Saturdays and early morning of Sundays at Tolo Highway.

8.36.      According to the information provided by the Contractor (China State Construction Engineering (HK) Ltd.) and confirmed by the Engineer of the Project, road resurfacing works were carried out at Tolo Highway over Shan Tong Road between 23:00 on 11 January 2014 and 07:00 on 12 January 2014.

8.37.      A valid Construction Noise Permit (CNP no.: GW-RN0815-13) has been obtained for the use of certain specified Powered Mechanical Equipments (PMEs) and carrying out of certain prescribed construction work at Tolo Highway (Fanling Bound) between The Balmoral and The Paragon near Tat Wan Road between 23:00 on Saturdays and 07:00 on Sundays, subject to the conditions imposed in the CNP. All restricted hours works were supervised by senior staff of the Contractor and Representatives of the Engineer to ensure all CNP conditions were complied with. The list of plants used during the construction works (provided by the Contractor and confirmed by the Engineer) on 11 and 12 January 2014 was checked for verification.

8.38.      Notification had been sent to the EPD on 9 January 2014 prior to the commencement of construction works before the said works was carried out at 23:00 on 11 January 2014.

8.39.      Other Advance Notifications of Restricted-hour Construction Work to the EPD have also been attached since the complaint is concerned with persistent construction noise emitted. The notifications were sent to the EPD 2 days prior to the commencement of the said works.

8.40.      The Contractor notified the nearby residents in advance of the construction work by disseminating a public notice to the estates management offices of the affected residential buildings on 6 November 2013.

8.41.      The warning buzzer of the road miller used between 23:00 on 11 January 2014 and 00:30 on 12 January 2014 was enclosed that night to reduce noise impacts from the road resurfacing works.

8.42.      However, the noise complaint is considered project-related.

8.43.      Upon the receipt of the complaint, there has not been road resurfacing works under the CNP no.: GW-RN0815-13 being arranged at the same location at night since 11 and 12 January 2014.

8.44.      Moreover, the Contractor was urged to shorten the time of handling rubbles as much as possible to minimize nuisance caused to the nearby residents. The Contractor has been setting up permanent noise barriers at both sides of the section of the road where road resurfacing works were carried out. Most of the noise barriers have been erected. The Contractor was prompted to install the remaining permanent noise barriers as soon as it can.

8.45.      The Contractor met Mr Chan Siu-kuen, The Tai Po District Council Member, in the morning of 13 January 2014 to explain their works and progress. Mr Chan agreed to contact the complainant and the complainant has been satisfied with Mr Chan’s explanations.

8.46.      According to the Contractor, no further works in relation to CNP no.: GW-RN0607-13 is scheduled before the CNP expires at 07:00 on 23 February 2014, even though the CNP permits such prescribed use of the specified PMEs for a total of 6 nights during its validity period.

8.47.      There are still outstanding works to be carried out at night in the coming months before the South Bound of Tolo Highway is open. However, the works will be less frequent and cause less impacts compared to those in previous months. The Contractor was urged to comply with conditions of existing and subsequent CNPs for future works and make advance notifications to the EPD at least 48 hours before the scheduled commencement of works. The Contractor was prompted to improve their management and schedule night works as early as possible to prevent late notification. The Contractor was reminded to review the current working method and implement noise mitigation measures so as to minimize nuisance caused to sensitive receivers.

8.48.       In addition, the Contractor is advised to implement the mitigation measures as stated in “Recommended Mitigation Measures” below:

-   Strictly comply with the requirements of the approved CNP for works carried out in restricted hours;

-   Have better scheduling of works to minimize noise nuisance;

-   Instruct the site workers to keep the noise in minimum during construction works in restricted hours; and

-   Foster better public relations with the sensitive receivers nearby.

Environmental Enquiry No.: EC-37

8.49.      One (1) air-and–water-related complaint was received on 21 January 2014 and followed up by the Environmental Team in January 2014.

8.50.      EPD referred a complaint on 21 January 2014.The complainant drove via Tai Po Tai Wo Road section of Tolo Highway on 21 January 2014 morning. He observed a lot of muddy water generated from the Tolo Highway widening construction works. Besides, he saw from Google Earth Image Satellite that a pipe was used to draw water for ground washing, causing the outflow of muddy runoff. As the mud on the road becomes dry, dust is generated when vehicles are passing by.

8.51.      The complainant requests follow-up as soon as possible.

8.52.      As informed by the Contractor (Gammon Construction Ltd) and confirmed by the Engineer of the Project, concrete breaking at Bridge 15A North abutment was carried out at the work areas from 8:30am to 5:30pm on 21 January 2014.

8.53.      Mitigation measures have been implemented in relation to water quality impact when construction activities are carried out. The measures include ensuring the works areas are well paved by concrete and keeping the paved area clean by sweeping to prevent mud and debris from depositing on the paved area. Besides, temporary channels are set up to control runoff.

8.54.       Mitigation measures have been implemented in relation to dust control when construction activities are carried out. The measures include ensuring the works areas are well paved by concrete, wetting the breaking surfaces regularly for dust suppression of concrete breaking works and providing wheel washing of vehicles before vehicles leave the construction site.

8.55.      With reference to the monitoring results recorded on the day closest to the day of complaint at the nearest EM&A monitoring station (AM4A- 168 Shek Kwu Lung Village), the 24-hour TSP level on 22 January 2014 was 96.1 ug/m3, which is below the action level of 176.6 ug/m3. Besides, the average 1-hour TSP level on 22 January 2014 at AM4A was 85.8 ug/m3, which is also below the action level of 302.3ug/m3.

8.56.      The complaint was received by the Contractor at around 2:15pm on 21 January 2014 and site inspection was immediately carried out at 3 pm on the same day. Inspection was conducted along the concerned carriageway and no muddy water or mud trails were observed on both the carriageway and access gates. Moreover, referring to the complainant’s description, the Google earth image was capturing the condition in April 2011, which is deviated from the current site situation. Although no muddy water was observed on 21 January 2014 afternoon, the Contractor was urged to monitor the road surfaces regularly and rectify whenever muddy water is observed by sweeping to prevent mud and debris from depositing on paved road areas.

8.57.      Nevertheless, the complaint was considered project-related.

8.58.       Therefore, the Contractor is reminded to enhance the water quality impacts and dust mitigation measures as stated in the “Recommended Mitigation Measures” below:

-   Rectify the muddy water overflowing and propose preventive measures for muddy runoff;

-   Review the methodology of collecting the wheel washing water to prevent recurrence in the future;

-   Confirm the implementation of dust mitigation measures during all construction and dusty activities to minimize fugitive dust generation;

-   Maintain the frequency of environmental supervision (by the Contractor) to regularly review the adequacy and effectiveness of dust suppression measures to suit the construction progress;

-   Inform the complainant before dusty activities are carried out; and

-   Foster better public relations with the sensitive receivers and complainants nearby.

 

8.59.      Cumulative statistics on complaints, notifications of summons and successful prosecutions are summarized in Appendix G.

9              Comments, recommendations and Conclusions

Comments on Mitigation Measures

9.1.         According to the environmental site inspections performed in the reporting quarter, the following recommendations were provided:-

Air Quality Impact

l  All plants on site should be properly maintained to avoid dark smoke emission.

l  All vehicles should be washed to remove any dusty materials before leaving the site.

l  Haul roads should be sufficiently dampened to minimize fugitive dust generation.

l  Wheel washing facilities should be properly maintained to ensure properly functioning.

l  Temporary exposed slopes and open stockpiles should be properly covered.

l  Enclosure should be erected for cement mixing operations.

l  Provide water spraying to suppress fugitive dust for any dusty construction activity.

l  Exposed cemented bags should be covered.

Construction Noise Impact

l  Properly erect the temporary noise barriers in accordance with the Environmental Permit requirement.

l  Noise barriers should be closely packed and properly aligned to ensure effective noise reduction.

l  Noisy operations should be oriented to a direction away from sensitive receivers as far as possible.

l  Sound insulation materials shall be wrapped at the breaker tip for concrete breaking works.

l  Noise Emission Label (NEL) shall be affixed to the air compressor and hand-held breaker operating within works area.

l  Better scheduling of construction works to minimize noise nuisance.

Water Quality Impact

l  Silt, debris and leaves accumulated at public drains, wheel washing bays and perimeter u-channels and desilting facilities should be cleaned up regularly.

l  Silty effluent should be treated/desilted before discharged. Untreated effluent should be prevented from entering public drain channel.

l  Proper drainage channels/bunds should be provided at the site boundaries to collect/intercept the surface run-off from works areas.

l  Exposed slopes and stockpiles should be covered up properly during rainstorm.

l  Stagnant water accumulated within works area should be removed.

Chemical and Waste Management

l  C&D materials and wastes should be sorted, recycled/treated and removed timely.

l  All chemical containers and oil drums should be properly stored.

l  All plants and vehicles on site should be properly maintained to prevent oil leakage.

l  All drain holes of the drip trays utilized within works areas should be properly plugged to avoid any oil leakage.

l  Oil stains on soil surface and empty chemical containers should be cleared and disposed of as chemical waste.

l  Only the recycling materials should be dumped into the recycling bins.

l  Refuse should not be placed near the retained trees.

Landscape and Visual Impact

l  All retained trees should be properly fenced off at the works area.

Recommendations on EM&A Programme

9.2.         The impact air quality and noise monitoring programme ensured that any deterioration in environmental condition was readily detected and timely actions taken to rectify any non-compliance. Assessment and analysis of monitoring results collected demonstrated the environmental acceptability of Stage 1 of the Project. The weekly environmental site inspections ensured that all the environmental mitigation measures recommended in the ERR were effectively implemented.

9.3.         The EM&A programme effectively monitored the environmental impacts from the construction activities and no particular recommendation was advised for the improvement of the programme.

Conclusions

9.4.         Air quality and noise monitoring, weekly site inspections were carried out in the reporting quarter, in accordance with the updated EM&A manual.

9.5.         All 1-hour TSP monitoring results complied with the Action / Limit Level in the reporting quarter.

9.6.         All 24-hour TSP monitoring results complied with the Action / Limit Level in the reporting quarter.

9.7.         No Action and Limit Level exceedance of construction noise monitoring was recorded in the reporting period.

9.8.         There were four (4) complaints (including one (1) air-related complaint, one (1) air-and-water-related complaint and two (2) noise-related complaints) followed up by the Environmental Team (ET) in the reporting quarter.

9.9.         There was one (1) follow-up complaint (including one (1) air-related complaint) followed up by the ET in the reporting quarter.

9.10.      Investigations were carried out. Findings and proposed mitigation measures of the complaints were submitted to all relevant parties. 

9.11.      No notifications of summons and successful prosecutions was received in the reporting quarter.