Monthly EM&A Report
(May 2023)
Contract No. : DPW
01/2020
Contract Name : Environmental
Team for Drainage
Improvement
Works at Ngong Ping
(Contract No.
DC/2019/06)
Report No. : 0118/20/ED/0595A
EP No. : EP-456/2013/B
Prepared by : Michelle
Shum
Reviewed by : Rex
Chow
_____________________________
Certified by : Calvin
M.P. Leung
Environmental
Team Leader
Project Title |
Drainage Improvement Works at Ngong Ping |
Document Title |
Monthly
EM&A Report (May 2023) |
Fugro Project No. |
0118/20 |
Fugro Document No. |
0118/20/ED/0595 |
Issue Number |
1 |
Client |
Drainage Services Department |
Client Address |
45/F, Revenue Tower, 5
Gloucester Road, Wan Chai, Hong Kong |
Client Contact |
Mr. Dave Choi |
01 |
Rev.
0 |
Michelle
Shum |
Rex
Chow |
Calvin M.P. Leung |
12
June 2023 |
02 |
Rev.
A |
Michelle
Shum |
Rex
Chow |
Calvin M.P. Leung |
14
June 2023 |
Issue |
Document Status |
Prepared
by |
Reviewed
by |
Certified
by |
Date |
1.2 Project Organization and Management Structure
1.3 Construction Programme and Activities
1.4 Works Undertaken During the Month
3.2 Environmental Quality Performance Limits (Action
and Limit Levels)
3.4 Environmental Mitigation Measures as Recommended
in the EIA Report
3.5 Environmental Requirements in Contract Documents
3.8 Landscape and Visual Impact
5.2 Laboratory and Equipment Used and Calibration
5.3 Parameters, Monitoring Date, Time, Frequency and
Duration
5.6 Comparisons of Monthly EM&A Data with the EIA
Predictions
6.1 Non-compliance (Exceedances)
6.3 Notification of Summons and Successful Prosecution
7.1 Construction Works for Next Three Month
7.2 Monitoring Schedules for Next Three Month
Appendix A Project Organization and Management Structure
Appendix B1 Construction Programme
Appendix B2 Works undertaken Illustrations
Appendix B3 Proactive Environmental Protection or Control Measures for
Next Three Month
Appendix C1 EP-456/2013/B Conditions
Appendix C2 Mitigation Measures Implementation (Construction Phase)
Appendix C3 Summary of Site Inspection
Appendix D Monitoring Parameters Action and Limit Levels
Appendix E Event and Action Plans
Appendix F1 Equipment Calibration Certificates (Noise Monitoring)
Appendix F2 Equipment Calibration Certificates (Water Quality Monitoring)
Appendix G Environmental Monitoring Schedules
Appendix H1 Noise Monitoring Data and Graphical Presentations
Appendix H2 Water Quality Monitoring Data and Graphical Presentations
Appendix I Statistics on Exceedances, Complaints, Notifications of
Summons and Prosecutions Appendix J Weather Condition
Appendix I2 Investigation Report on Limit Level of Non-compliance
i.
This is the 29th monthly EM&A Report which summaries
the results and findings of the EM&A programme required for the Project
from 1 May to 31 May 2023.
Breaches of Action and Limit
Levels
Noise
ii.
No Action or Limit Level Exceedance of monitoring was recorded in
the reporting period.
Water Quality
iii.
2 Limit Level Exceedance of Total Suspended solid was recorded at
WS5-I4 and WS6-I5 on 25 May 2023 and 2 Limit Level Exceedance of Total
Suspended solid was recorded at WS5-I4 and WS6-I5 on 27 May
2023. The
exceedance cases on both 25 and 27 May was considered as project non-related.
Exceedance summary and investigation report are shown in Section 6.1.2 and
Appendix I2 respectively.
Complaint log
iv.
No Complaint was recorded in the reporting period.
Notifications of Summons and
Successful Prosecutions
v.
No notifications of Summon and Successful Prosecution was recorded
in the reporting period.
Reporting Change
vi.
There was no reporting change required in the reporting period.
Future Key Issues
vii.
During the next three month reporting period, the principal work
activities within the site included:
Portion A
-
Receiving Pit excavation
-
TBM operation
Portion B
-
Excavation of box culvert
-
Launching pit excavation
-
TBM operation
viii.
The ET will continue to implement the environmental monitoring
& audit programme in accordance with the EM&A Manual and Environmental
Permit requirements. The recommended environmental mitigation measures shall be
implemented on site and regular inspections as required will be carried out to
ensure that the environmental conditions are acceptable.
Table 1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Drainage
Services Department, HKSAR (DSD) |
Engineer |
Mr. Dave Choi |
2594 7348 |
Acuity
Sustainability Consulting Limited (ASC) |
IEC |
Mr. F.C.
Tsang |
2698 8060 |
Contractor
(Ming Hing) |
Environmental
Officer |
Mr. Jason
Wong |
9744 2390 |
Fugro
Technical Services Limited (FTS) |
ET Leader |
Mr. Calvin
Leung |
3565 4441 |
Portion A
-
Receiving Pit excavation
-
TBM operation
Portion B
-
Excavation of box culvert
-
Launching pit excavation
-
TBM operation
EP No. EP-456/2013/B Conditions
Mitigation Measures
Implementation
Environmental Licences, Notification
and Permits
Table
2.1 Environmental
Licences, Notification and Permits
Summary
Permit / Notification / License |
Ref No |
Valid From |
Valid Till |
Environmental
Permit |
EP-456/2013/B |
26/08/2021 |
N/A |
Wastewater
Discharge License |
EP/RS0000458474 |
23/9/2022 |
30/9/2027 |
Notification
pursuant to Air Pollution
(Construction Dust) Regulation |
462432 |
01/12/2020 |
N/A |
Billing Account |
7038098 |
26/08/2020 |
N/A |
Chemical
Waste Producer |
5213-941-M2935-04 |
05/05/2021 |
N/A |
Project Area, Environmental
Sensitive Receivers and Locations of Monitoring and Control Stations
Table
3.1 ET¡¦s
vetting Contract Documents Summary
ET¡¦s vetting Contract Documents |
Status |
NIL |
|
Table
3.2 Site
Inspection Date Summary
Inspection Date |
Weekly Site Inspection |
02/05/2023 |
09/05/2023 |
16/05/2023 |
23/05/2023 |
30/05/2023 |
Landscape and Visual |
02/05/2023 |
16/05/2023 |
30/05/2023 |
Cultural Heritage |
23/05/2023 |
Post-transplantation Works |
-- |
Floral Protection Measures |
16/05/2023 |
~ Weekly audit of
Enhancement planting and construction run-off.
~ Monthly audit of the
implementation of Floral Protection Plan.
~ Monthly audit of the
transplanted species for the first 12 months after the transplantation.
~ Quarterly audit the
transplanted species between months 12 to 24 after the transplantation.
Noise
¡P
The monitoring station will set at a point 1m from the exterior of the sensitive
receivers building façade and set at a position 1.2m above the ground.
¡P
The battery condition will check to ensure good functioning of the meter.
¡P
Parameters such as frequency weighting, the time weighting and the
measurement time will set as follows:
¡± frequency weighting : A
¡± time weighting : Fast
¡± measurement time : continue
5 minutes interval
¡P
Prior to and after noise measurement, the meter will be calibrated using
the calibrator for 94.0 dB at 1000 Hz. If the difference in the calibration
level before and after measurement is more than 1.0 dB, the measurement will be
considered invalid and repeat of noise measurement is required after
re-calibration or repair of the equipment.
¡P
The wind speed at the monitoring station will check with the portable wind
meter. Noise monitoring shall be cancelled in the presence of fog, rain, and
wind with a steady speed exceeding 5 m/s, or wind with gusts exceeding 10 m/s.
¡P
Noise measurement shall be paused during periods of high intrusive noise
if possible and observation shall be recorded when intrusive noise is not
avoided.
¡P
The supplementary information for data auditing and statistical results
(e.g. L10 and L90), shall be obtained for reference.
Maintenance /
Calibration
¡P
The microphone head of the sound level meter and calibrator should be
cleaned with a soft cloth at quarterly intervals.
¡P
The sound level meter and calibrator should be calibrated annually by a
HOKLAS laboratory or the manufacturer.
Water Quality
Noise
Table
5.1a Noise
Monitoring Equipment
Manufacturer/ Brand |
Model |
Equipment |
Quantity |
Casella |
CEL-63X Series |
Sound Level
Meter |
3 |
CEL-120/1 |
Sound Calibrator |
3 |
Table
5.1b Water
Quality Monitoring Equipment
Manufacturer/ Brand |
Model |
Equipment |
Quantity |
In-Situ |
YSI EXO-3 |
Multi-parameter
Water Quality Meter |
1 |
Noise
Table
5.2 Monitoring
Parameters and Frequencies of Noise Monitoring
Parameter |
Frequency and Period |
LAeq
(30 min) in normal weekdays and (L10 and L90 will
be recorded for reference) |
0700-1900 on
normal weekdays at a frequency of once a week |
Noise
Table
5.3 Noise Monitoring Locations and Type of Measurement
NSRs* |
Monitoring Location |
Type of Measurement# |
NSR1 |
Columbarium of
Po Lin Monastery |
Free-field |
NSR5 |
Village House
No. 49A |
Free-field |
NSR8 |
Village House
No. 34 |
Façade |
* NSRs: Noise Sensitive
Receivers
#For Free-field measurement, +3dB(A) should be added to the measured results.
Water Quality
Table
5.4 Water Quality Monitoring Locations
Station |
Type |
Easting |
Northing |
Relevant Works
Section* |
Remark |
WS1-R1 |
Upstream
reference |
808664 |
813130 |
WS1/SA1 |
R2 in EIA |
WS1-I1 |
Downstream
impact |
808535 |
813094 |
WS1/SA1 |
|
WS1-R2 |
Upstream
reference |
808524 |
813134 |
WS1 |
W2 in EIA |
WS1-I2 |
Downstream
impact |
808528 |
813101 |
WS1 |
|
WS4-R3 |
Upstream
reference |
808214 |
813003 |
WS4/SA2 |
|
WS4-I3 |
Downstream
impact |
808196 |
813042 |
WS4/SA2 |
|
WS5-R4 |
Upstream
reference |
808096 |
813076 |
WS5/SA3 |
|
WS5-I4 |
Downstream
impact |
808055 |
813115 |
WS5/SA3 |
|
WS6-R5 |
Upstream
reference |
807983 |
813158 |
WS6/WA3 |
|
WS6-I5 |
Downstream
impact |
807919 |
813155 |
WS6/WA3 |
|
WS6-C1 |
Intermediate
Control |
807813 |
813214 |
WS6/SA4 |
W8 in EIA |
WS6-R6 |
Upstream
reference |
807727 |
813249 |
WS6/WA4 |
|
WS6-I6 |
Downstream
impact |
807762 |
813285 |
WS6/WA4 |
W9 in EIA |
* Please refer to Figures 2.9a-2.9g
of the EIA Report for the relevant Works Section (WS), and/or designated works
area (WA) and stockpiling area (SA).
Noise
Table 5.5
Summary of Noise Monitoring Results
NSR |
Monitoring
Results (Range)(2)(3) |
Action
Level |
Limit
Level(1) |
||||
Columbarium of Po Lin Monastery |
61.4 |
- |
65.3 |
dB(A) |
When one documented complaint is
received. |
70 dB(A) |
|
NSR5 Village House No. 49A |
49.4 |
- |
65.4 |
dB(A) |
75 dB(A) |
||
NSR8 Village House No. 34 |
52.2 |
- |
57.1 |
dB(A) |
75 dB(A) |
||
Note:
(1)
75 dB(A) for residential premises and 70 dB(A) for educational
institutions, kindergartens, nurseries and all others where voice
communication.
(2)
Leq(30min) in dB(A), 0700-1900 hrs in
normal weekdays.
(3)
Free-field correction applied at NSR1 & NSR5.
Water Quality
Table 5.6 Summary of Water Quality Monitoring Results
Parameter(s) Station(s) |
DO
in mg/L |
Turbidity
in NTU |
pH |
Suspended
Solids in mg/L |
||||||||||||||||||||
Min |
- |
Max |
( |
Mean |
) |
Min |
- |
Max |
( |
Mean |
) |
Min |
- |
Max |
( |
Mean |
) |
Min |
- |
Max |
( |
Mean |
) |
|
WS1-R1 |
7.82 |
- |
7.82 |
( |
7.82 |
) |
6.60 |
- |
6.60 |
( |
6.60 |
) |
7.00 |
- |
7.00 |
( |
7.00 |
) |
8.50 |
- |
8.50 |
( |
8.50 |
) |
WS1-I1 |
7.39 |
- |
8.86 |
( |
8.12 |
) |
1.00 |
- |
6.90 |
( |
3.13 |
) |
6.80 |
- |
7.00 |
( |
6.90 |
) |
1.00 |
- |
13.50 |
( |
4.36 |
) |
WS1-R2 |
7.22 |
- |
8.67 |
( |
7.89 |
) |
0.75 |
- |
9.70 |
( |
3.38 |
) |
6.70 |
- |
7.00 |
( |
6.86 |
) |
1.00 |
- |
15.00 |
( |
6.04 |
) |
WS1-I2 |
7.51 |
- |
7.51 |
( |
7.51 |
) |
6.40 |
- |
6.40 |
( |
6.40 |
) |
7.10 |
- |
7.10 |
( |
7.10 |
) |
5.00 |
- |
5.00 |
( |
5.00 |
) |
WS4-R3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
WS4-I3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
WS5-R4 |
6.76 |
- |
7.71 |
( |
7.14 |
) |
1.80 |
- |
20.50 |
( |
9.80 |
) |
7.00 |
- |
7.10 |
( |
7.07 |
) |
1.00 |
- |
24.00 |
( |
6.64 |
) |
WS5-I4 |
6.75 |
- |
7.25 |
( |
6.88 |
) |
5.90 |
- |
22.60 |
( |
15.03 |
) |
7.00 |
- |
7.20 |
( |
7.13 |
) |
2.00 |
- |
145.00 |
( |
56.63 |
) |
WS6-R5 |
6.40 |
- |
6.40 |
( |
6.40 |
) |
10.30 |
- |
10.30 |
( |
10.30 |
) |
7.00 |
- |
7.00 |
( |
7.00 |
) |
21.50 |
- |
21.50 |
( |
21.50 |
) |
WS6-I5 |
6.32 |
- |
7.44 |
( |
6.75 |
) |
1.30 |
- |
12.30 |
( |
6.58 |
) |
6.90 |
- |
7.10 |
( |
6.98 |
) |
2.00 |
- |
135.00 |
( |
38.60 |
) |
WS6-C1 |
4.00 |
- |
7.30 |
( |
6.21 |
) |
0.10 |
- |
37.30 |
( |
4.33 |
) |
6.10 |
- |
7.60 |
( |
6.82 |
) |
1.00 |
- |
16.50 |
( |
2.65 |
) |
WS6-R6 |
6.50 |
- |
7.90 |
( |
7.08 |
) |
1.00 |
- |
19.90 |
( |
5.13 |
) |
6.90 |
- |
7.20 |
( |
7.01 |
) |
1.00 |
- |
42.50 |
( |
8.64 |
) |
WS6-I6 |
6.60 |
- |
7.80 |
( |
7.11 |
) |
1.00 |
- |
20.50 |
( |
5.31 |
) |
6.90 |
- |
7.20 |
( |
7.03 |
) |
1.00 |
- |
40.00 |
( |
6.18 |
) |
Remark:
1)
Monitoring location dried up and detailed refer to Appendix H2.
Other factor influencing the
monitoring results
Water Quality
Noise
Table 5.7
Comparison of Noise Monitoring Data with EIA Predictions
NSR |
Predicted
Mitigated Construction Noise Levels (1) |
Monitoring
Results (Range) |
||||
NSR1 Columbarium of Po Lin Monastery |
55
- 70 |
dB(A) |
61.4 |
- |
65.3 |
dB(A) |
NSR5 Village House No. 49A |
48
- 86 |
dB(A) |
49.4 |
- |
65.4 |
dB(A) |
NSR8 Village House No. 34 |
51
- 73 |
dB(A) |
52.2 |
- |
57.1 |
dB(A) |
Note
(1)
Predicted Mitigated Construction Noise Levels refer to EIA Report Table
4.11.
Water Quality
Portion A
-
Receiving Pit excavation
-
TBM operation
Portion B
-
Excavation of box culvert
-
Launching pit excavation
-
TBM operation
Effectiveness and Efficiency
of Mitigation Measures
Improvement in the EM&A
Programme
Conclusions
Noise
Water Quality
Figure 2a Noise Monitoring Locations (Part 1)
Figure 2b Noise Monitoring Locations (Part 2)
NSRs* |
Monitoring Location |
Type of Measurement# |
NSR1 |
Columbarium of
Po Lin Monastery |
Free-field |
NSR5 |
Village House
No. 49A |
Free-field |
NSR8 |
Village House
No. 34 |
Façade |
Figure 2c Water Quality
Monitoring Locations
Station |
Type |
WS1-R1 |
Upstream
reference |
WS1-I1 |
Downstream
impact |
WS1-R2 |
Upstream
reference |
WS1-I2 |
Downstream
impact |
WS4-R3 |
Upstream
reference |
WS4-I3 |
Downstream
impact |
WS5-R4 |
Upstream
reference |
WS5-I4 |
Downstream
impact |
WS6-R5 |
Upstream
reference |
WS6-I5 |
Downstream
impact |
WS6-C1 |
Intermediate
Control |
WS6-R6 |
Upstream
reference |
WS6-I6 |
Downstream
impact |
Appendix A Project Organization and Management
Structure
Note:
Detailed key personnel contact names and telephone numbers refer to Table 1.1.
Appendix
B1 Construction Programme
Appendix B2 Works Undertaken
Illustrations
Portion A |
Portion
B |
|
|
- TBM operation (L305A) |
- Excavation
Works (Bay 9) |
Portion C |
|
|
|
- Excavation Works (Intake No.1) |
|
Appendix B3 Proactive
Environmental Protection or Control Measures for Next Three Month
Activity Impact |
Excavation of Trench or Pit |
Pipe Lining |
Installation of Drainage
Pipe |
Box culvert |
TBM |
Control Measures |
Air Pollution Nuisance |
✓ |
✓ |
✓ |
✓ |
✓ |
− Use of regular watering to reduce dust emissions − Open stockpiles shall be avoided or covered. |
Noise Nuisance |
✓ |
✓ |
✓ |
|
✓ |
− Use of quieter plant
(QPME) − Use suitable acoustic
enclosure. − Installation of a fixed
noise barrier. |
Water Nuisance |
|
✓ |
|
✓ |
✓ |
− Intercept the surface runoff by sand bag or etc. − Treat the wastewater before discharge. |
Waste Nuisance |
|
✓ |
✓ |
|
✓ |
− The site and surroundings
shall be kept tidy and litter free. − General refuse arising
on-site should be stored in enclosed bins separately from C&D and
chemical wastes − Recycle as many C&D
materials as possible on-site |
Ecology |
✓ |
✓ |
✓ |
✓ |
|
− avoid damage and disturbance to the remaining and surrounding
natural habitat − construction activities should be restricted to the proposed
works boundary |
Moreover, the ET will continue to implement the environmental
monitoring & audit programme in accordance with the EM&A Manual and
Environmental Permit requirements. The recommended environmental mitigation
measures shall be implemented on site and regular inspections as required will
be carried out to ensure that the environmental conditions are acceptable.
Appendix C1 EP-456/2013/B Conditions
Summary Table for Status of Compliance /
Required Submission
EP Conditions |
Submission(s) |
Submission Date |
Approval Status |
2.6 |
Landscape
Plan (Rev. G) |
02/03/2021 |
Approved on 23/03/2021 |
2.7 |
Landscape
as-built drawing(s) |
At
least one month before the Project commences operation |
* |
2.8 |
Updated
Baseline Vegetation Survey Report (Rev. E) |
19/02/2021 |
* |
Floral
Protection Plan (Rev. J) |
04/04/2021 |
* |
|
Floral
Transplantation Plan (Rev. E) |
11/12/2020 |
* |
|
2.10 |
Aquatic
Fauna Translocation Plan (Rev. H) |
24/12/2020 |
* |
2.11 |
Aquatic
Fauna Translocation Survey
Report (Rev. B) |
02/03/2021 |
* |
4.3 |
Noise
Baseline Monitoring Report (Rev. A) |
30/10/2020 |
* |
Water
Quality Baseline Monitoring Report (Rev. D) |
29/01/2021 |
* |
|
4.4 |
Monthly
EM&A Report (April 2023) |
09/05/2023 |
* |
Remarks: * Approval not required in
EP-456/2013/B
Appendix C2 Mitigation
Measures Implementation (Construction Phase)
Environmental Protection Measures
(Construction Phase) (1) |
Status |
A) Air Quality |
-- |
Watering once per hour for 12 hours a day at
exposed soil in all active works areas
and paved haul roads to reduce dust emissions by 91.7%. The amount of
water to be applied would be 0.25L/m2 for the respective watering
frequency. |
^ |
Dust suppression measures stipulated in the
Air Pollution Control (Construction Dust) Regulation and good site practices: |
-- |
¡½ Use of regular watering to reduce dust emissions from exposed
site surfaces and unpaved roads, particularly during dry weather; |
^ |
¡½ Use of frequent watering for particularly dusty construction
areas and areas close to ASRs; |
^ |
¡½ Side enclosure and covering of any aggregate or dusty material
storage piles to reduce emissions. Where this is not practicable owing to
frequent usage, watering shall be applied to aggregate fines; |
^ |
¡½ Open stockpiles shall be avoided or covered. Prevent placing
dusty material storage piles near ASRs; |
^ |
¡½ Tarpaulin covering of all dusty vehicle loads transported to,
from and between site locations; |
^ |
¡½ Establishment and use of vehicle wheel and body washing
facilities at the exit points of the site; |
^ |
¡½ Imposition of speed controls for vehicles on unpaved site roads,
8 km per hour is the recommended limit; |
^ |
¡½ Routing of vehicles and position of construction plant should be
at the maximum possible distance from ASRs; |
^ |
¡½ Every stock of more than 20 bags of cement or dry pulverised fuel
ash (PFA) should be covered entirely by impervious sheeting or placed in an
area sheltered on the top and the 3 sides; |
^ |
¡½ Cement or dry PFA delivered in bulk should be stored in a closed
silo fitted with an audible high level alarm which is interlocked with the
material filling line and no overfilling is allowed; and ¡½ Loading, unloading, transfer, handling or storage of bulk cement
or dry PFA should be carried out in a totally enclosed system or facility,
and any vent or exhaust should be fitted with an effective fabric filter or
equivalent air pollution control system. |
N/A |
N/A |
|
B) Noise |
-- |
The use of quieter plant (QPME) is specified
for the list of equipment: |
-- |
¡½ Tracked excavator fitted with hydraulic rock breaker; ¡½
Concrete lorry mixer; ¡½
Tracked mobile crane
(132kW, 55t); |
^ |
¡½ Dump Truck; ¡½ Tracked excavator (14t); ¡½ Generator, Super Silenced, 70 dB(A) at 7m; ¡½
Poker vibratory; |
|
¡½ Hand Held Electric Circular Saw, 150mm Blade with SWL of 103dB(A)
or less; |
|
¡½ Electric Chain-Saw, Hand-held; and ¡½ Water Pump, Submersible (Electric). |
|
For the Columbarium
(NSR1), the vertical gaps along of edge of the solid boundary wall facing the
works area WA4 should be covered with acoustic fabric or small barrier for
noise screening. |
^ |
The use of temporary noise barrier /
enclosure are specified for the list of equipment: |
-- |
¡½ Bar Bender and Cutter (Electric) - Noise Enclosure |
^ |
¡½ Tracked excavator fitted with hydraulic rock breaker - Temporary
Noise barrier; |
|
¡½ Tracked excavator (14t) - Temporary Noise barrier |
|
¡½ Generator, Super Silenced, 70 dB(A) at 7m - Noise Enclosure; and |
|
¡½ Hand Held Electric Circular Saw, 150mm Blade - Noise Enclosure. |
|
Installation of a fixed
noise barrier of 3m in height between the NSR5 and the open cut trench
(Activities 4 and 4+ at Works Section 5) |
N/A (Works is ended in that section) |
Implementation of further good site
practices: |
-- |
¡½ Only well-maintained plant should be operated on- site and PME
should be serviced regularly during the construction programme; |
^ |
¡½ Silencers or mufflers on construction equipment should be
utilised and properly maintained throughout the construction programme; |
^ |
¡½ Any mobile PME should be sited as far from NSRs as possible; |
^ |
¡½ Machines and PME that may be in intermittent use should be shut
down between work periods or should be throttled down to a minimum; |
^ |
¡½ PME known to emit noise strongly in one direction should be
orientated to direct away from the nearby NSRs; |
^ |
¡½ Material stockpiles and other structures should be effectively
utilised, wherever practicable, in screening noise from on-site construction
activities; |
^ |
¡½ Use of acoustic enclosure, in accordance with EPD's A Practical
Guide for the Reduction of Noise from Construction Works; and |
^ |
¡½ Re-scheduling of works should be considered to ameliorate the
residual impact. |
^ |
C) Water Quality |
-- |
In accordance with the Practice Note for
Professional Persons on Construction Site Drainage, Environmental Protection
Department, 1994 (ProPECC PN 1/94), construction
phase mitigation measures shall include the following: |
^ |
¡½
At the establishment of Site Office (SO), works area (WA1 and
WA2) and stockpiling areas (SA1,
SA2, SA3 and SA4; |
^ |
¡½
Dikes or embankments for flood protection should be implemented around
the boundaries of earthwork areas. Temporary ditches should be provided to facilitate
the runoff discharge into an appropriate watercourse, through a site/sediment
trap. Sediment/silt traps should be incorporated in the permanent drainage
channels to enhance deposition rates; |
^ |
¡½ While ProPECC PN 1/94 requires
construction works should be programmed to minimise surface excavation works
during rainy seasons (April to
September). By the nature of the pipe laying works, it is considered not
practicable to avoid excavation works in the wet season as this would
substantially affect the overall construction programme. However, for works
at areas that directly interface with the existing watercourses, excavation
works shall avoid the rainy season as far as possible. These include Intake A interfacing the stream, Intake B interfacing the U channel, Outfall A interfacing the gabion
channel, Intake C/RP3 interfacing
the gabion channel and Outfall B/RP4
interfacing Ngong Ping Stream |
^ |
¡½ Exposed slope surfaces should be covered by tarpaulin or other
means during the rainy season; |
^ |
¡½ The design of efficient silt removal facilities should be based on
the guidelines in Appendix A1 of ProPECC PN 1/94,
which states that the retention time for silt/sand traps should be 5 minutes
under maximum flow conditions. The sizes may vary depending upon the flow
rate, but for a flow rate of 0.1m3/s, a sedimentation basin of 30m3
would be required and for a flow rate of 0.5m3/s the basin would
be 150m3. The detailed design of the sand/silt traps should be
undertaken by the contractor prior to the commencement of construction; |
^ |
¡½ The overall slope of works sites should be kept to a minimum to
reduce the erosive potential of surface water flows, and all trafficked areas
and access roads should be protected by coarse stone ballast. An additional
advantage accruing from the use of crushed stone is the positive traction
gained during the prolonged periods of inclement weather and the reduction of
surface sheet flows; |
^ |
¡½ All drainage facilities and erosion and sediment control
structures should be regularly inspected and maintained to ensure their
proper and efficient operation at all times particularly following
rainstorms. Deposited silts and grits should be removed regularly and
disposed of proper waste receiving facilities. As the area is within the
water gathering grounds, on-site disposal of silts/grits shall not be
allowed; |
^ |
¡½ Measures should be taken to minimise the ingress of site drainage
into excavations. If the excavation of trenches in wet season is inevitable,
they should be dug and backfilled in short sections wherever practicable. The
water pumped out from trenches or foundation excavations should be discharged
into storm drains via silt removal facilities; |
^ |
¡½ Manholes (including newly constructed ones) should always be
adequately covered and temporarily sealed so as to prevent silt, construction
materials or debris being washed into the drainage system and storm runoff
being directed into foul sewers; |
^ |
¡½ Precautions to be taken at any time of the year when rainstorms
are likely, actions to be taken when a rainstorm is imminent or forecasted
and during or after rainstorms, are summarised in Appendix A2 of ProPECC PN 1/94. Particular attention should be paid to
the control of silty surface runoff during storm events, especially for areas
located near steep slopes; |
^ |
¡½ All vehicles and plant should be cleaned before leaving a
construction site to ensure no earth, mud, debris and the like is deposited
by them on roads. An adequately designed and sited wheel washing facilities
should be provided at the exit of every construction site where practicable.
Wash-water should have sand and silt settled out and removed at least on a
weekly basis to ensure the continued efficiency of the process. The section
of access road leading to, and exiting from, the wheel- washing bay to public
roads should be paved with sufficient backfall toward the wheel-washing bay
to prevent vehicle tracking of soil and silty water to public roads and
drains; |
^ |
¡½ Oil interceptors should be provided in the drainage system
downstream of any oil/fuel pollution sources. Oil interceptors should be
emptied and cleaned regularly to prevent the release of oil and grease into
the storm water drainage system after accidental spillage. A bypass should be
provided for oil interceptors to prevent flushing during heavy rain; |
N/O |
¡½ Stockpiled material shall be covered by tarpaulin and /or watered
as appropriate to prevent windblown dust and surface run off. Measures should
be taken to prevent the washing away of construction materials, soil, silt or
debris into any drainage system; |
^ |
¡½ Major stockpiled areas shall be sited outside of the country
parks area (Works Section 6) and away from stream courses as far as
practicable. For the stockpiling area SA4 within the country park area,
stockpiling of earthed material shall be minimised and excavated soil from
Works Section 6 shall be delivered to the Site Office as soon as possible. Similarly,
overnight stockpiling of earthed material along the exposed trench shall be
minimised as far as possible and the excavated soil shall be transferred to
the designated stockpiling area as soon as possible; |
^ |
¡½ The Contractor shall comply with WSD's General Conditions for
Working within Water Gathering Grounds as applicable; |
^ |
¡½ The construction solid waste, debris and rubbish on-site should
be collected, handled and disposed of properly to avoid causing any water
quality impacts. The requirements for solid waste management are detailed in
Section 9 of this EIA report; and |
^ |
¡½ All fuel tanks and chemical and bentonite storage areas should be
provided with locks and sited on sealed areas, within bunds of a capacity
equal to 110% of the storage capacity of the largest tank to prevent spilled
fuel oils from reaching the nearby WSRs. |
^ |
There is a need to apply
to the EPD for a discharge licence for discharge of effluent from the
construction site under the WPCO. The discharge quality must meet the
requirements specified in the discharge licence. All the runoff and
wastewater generated from the works areas should be treated so that it
satisfies all the standards listed in the TM-DSS. It should particularly noted that the TM-DSS specifically prohibits the discharge of the following substances into the
inland waters: |
N/A |
¡½ polychlorinated biphenyls (PCB); ¡½ polyaromatic hydrocarbon (PAH); ¡½ fumigant, pesticide or toxicant ; |
|
¡½ radioactive substances ; ¡½ chlorinated hydrocarbons; ¡½ flammable or toxic solvents ; |
|
¡½ petroleum oil or tar; ¡½ calcium carbide; ¡½ wastes liable to form scum, deposits or
discoloration; |
|
¡½ sludge or solid refuse of any kind; and ¡½ detergents in Group A inland waters only. |
|
The beneficial uses of the
treated effluent for other on- site activities such as dust suppression,
wheel washing and general cleaning etc, can minimise water consumption and
reduce the effluent discharge volume and shall be encouraged. If monitoring
of the treated effluent quality from the works areas is required during the
construction phase of the Project, the monitoring should be carried out in
accordance with the WPCO license. |
^ |
In addition to compliance
with the discharge licence requirement, to prevent bank side erosion, the
discharge of site effluents shall be either at existing storm drains or
artificial channels. No effluent or treated surface runoff shall be allowed
to discharge at natural stream course. |
N/A |
The use of bentonite
slurries shall be minimised as far as possible. In addition to the
requirement of a peripheral bunds and drainage system for the WA4 and SO,
where the bentonite slurries will be used, to prevent any accidental release
of bentonite slurry from getting into the surrounding environment, the
following specific control measures shall be followed to reduce the risk and
impacts of accidental spillage: |
-- |
¡½
All bentonite slurry should be stored in a container that
resistant to corrosion, maintained in good conditions and securely closed; |
^ |
¡½ The container should be labelled in English and Chinese and note
that the container is for storage of bentonite slurry only; |
^ |
¡½ The storage container should be placed on an area of impermeable flooring
and bunded with capacity to accommodate 110% of the volume of the container
size or 20% by volume stored in the area and enclosed with at least 3 sides;
and |
^ |
¡½ Sufficiently covered to prevent rainfall entering the container
or bunded area (water collected within the bund must be tested and disposed
of as chemical waste, if necessary). |
^ |
In order to reduce the
possibility of frac-out, detailed ground investigation shall be undertaken to
evaluate the likelihood of frac-out and if necessary advanced ground
treatment applied before the commencement of the pipe jacking works. A member
of the Contractor's site staff shall, also, be dedicated to closely monitor
the ground surface above the pipe jacking head for any frac-outs release. The
pipe jacking works and application of bentonite shall immediately stop if
frac- outs are observed. Any frac-out shall be immediately cleaned or bunded
to prevent spreading of the bentonite slurry. The Contractor shall
immediately notify the Engineer and propose rectification measures to prevent
further frac-out to the satisfaction of the Engineer before pipe jacking
works resume. An emergency clean up kit shall be readily available at Works
Section 2 and 6 where pipe jacking will be undertaken. |
^ |
The handling and disposal
of bentonite slurries should be undertaken in accordance within ProPECC PN 1/94. Surplus bentonite slurries used in
construction works shall be reconditioned and reused wherever practicable.
Residual bentonite slurry shall be disposed of from the site as soon as
possible as stipulated in Clause 8.56 of the General Specification for Civil
Engineering Works. The Contractor should explore alternative disposal outlets
for the residual bentonite slurry (dewatered bentonite slurry to be disposed
to a public filling area and liquid bentonite slurry if mixed with inert fill
material to be disposed to a public filling area) and disposal at landfill
should be the last resort. |
^ |
The contractor must register as a chemical
waste producer if chemical wastes would be produced from the construction
activities. The Waste Disposal Ordinance (Cap 354) and its subsidiary
regulations in particular the Waste Disposal (Chemical Waste) (General)
Regulation should be observed and complied with for control of chemical
wastes. |
^ |
Any maintenance facilities should be located
outside Works Section 6 in the Lantau North Country Park. Such facilities
should be located on hard standings within a bunded area, and sumps and oil
interceptors should be provided. Maintenance of vehicles and equipment
involving activities with potential for leakage and spillage should only be
undertaken within the areas appropriately equipped to control these
discharges. All maintenance activities which may generate chemical waste
shall be undertaken in the Site Office area, as far as possible. |
^ |
Disposal of chemical wastes should be
carried out in compliance with the Waste Disposal Ordinance. The Waste
Disposal Ordinance (Cap 354) and its subsidiary regulations in particular the
Waste Disposal (Chemical Waste) (General) Regulation should be observed and
complied with for control of chemical wastes. The Code of Practice on the
Packaging, Labelling and Storage of Chemical Wastes published under the Waste
Disposal Ordinance details the requirements to deal with chemical wastes.
General requirements are given as follows: |
-- |
¡½
Suitable containers should
be used to hold the chemical wastes to avoid leakage or spillage during
storage, handling and transport; |
^ |
¡½ Chemical waste containers should be suitably labelled, to notify
and warn the personnel who are handling the wastes, to avoid accidents; and |
^ |
¡½ Storage area should be selected at a safe location on site and
adequate space should be allocated to the storage area. |
^ |
In order to minimise the risk of accidental
spillage, the use and storage of oils/chemicals/waste should be limited to
absolute minimum volume and are to be removed from sites at the earliest
opportunity. However, all chemical waste, fuels and oils shall be stored at
the Site Office (SO), to minimise impact to the Lantau North Country Park and
water gathering grounds. |
^ |
In order to protect against an accidental
spillage of fuel or oil, the Contractor will be required to prepare a spill response plan to the satisfaction
of AFCD, EPD, FSD, HyD, Police, TD and WSD to
define procedures for the control, containment and clean-up of any spillage
that could occur on the construction site. |
^ |
At all times, the Contractor shall comply
with WSD's General Conditions for Working within Water Gathering Grounds as
applicable. |
^ |
The sewage of the site
office will be connected the existing sewer networks and be treated at the
Ngong Ping STW. Portable chemical toilets and sewage holding tanks are
recommended for the handling of the construction sewage generated by the
workforce at other works area. The use of temporary toilets within the water
gathering ground, however, is also subject to the approval of Water Services
Department. A licensed contractor
should be employed to provide appropriate and adequate portable toilets and
be responsible for appropriate disposal and maintenance |
^ |
The Outfall A and Intake C
and associated works areas are within the gabion channel, the construction
and operation of which was previously governed by the Environmental Permit
EP-192/2004. While the EP was surrendered in May 2007, the currently proposed
works at these locations shall, also, comply with the specific conditions of
the EP |
^ |
D) Ecology |
-- |
Good construction practice measures which
should be implemented and should include: |
-- |
¡½ avoid damage and disturbance to the remaining and surrounding
natural habitat; |
^ |
¡½ placement of equipment in designated areas within the existing
disturbed land; |
^ |
¡½ spoil heaps should be covered at all times; |
^ |
¡½ construction activities should be restricted to the proposed
works boundary; and |
^ |
¡½ disturbed areas to be reinstated immediately after completion of
the works. |
^ |
Landscape compensatory planting is
recommended as mitigation for the loss of landscape and habitat. Recommended
Planting Species included: |
-- |
Tree |
-- |
Cinnamomum burmannii, |
N/A |
Minimisation mitigation measures required to
protect water quality and the three aquatic faunal species of conservation
would comprise controlling surface runoff: |
-- |
¡½ All works on the banks of the natural stream should be undertaken
within the dry season, where practical; |
N/A |
¡½ Perimeter cut-off drains to direct off-site water around the site
should be constructed with internal drainage works and erosion and
sedimentation control facilities implemented; |
N/A |
¡½ Channels (both temporary and permanent drainage pipes and
culverts), earth bunds or sand bag barriers should be provided to divert the
stormwater to silt removal facilities; |
^ |
¡½ Oil interceptors should be provided in the drainage system
downstream of any oil/fuel pollution sources; |
N/A |
¡½ Stockpiled material shall be covered by tarpaulin and /or watered
as appropriate to prevent windblown dust and surface run off; |
^ |
¡½ Overnight stockpiling of earthed material along the exposed
trench shall be minimised as far as possible and excavated soil shall be
transferred to the designated stockpiling area as soon as possible; |
^ |
¡½ All bentonite slurry shall be suitably stored in accordance with
Section 5.8.8 of this EIA Report to minimise the chance of spillage; |
^ |
¡½ All fuel tanks and storage areas should be provided with locks
and sited on sealed areas, within bunds of a capacity equal to 110% of the
storage capacity of the largest tank to prevent spilled fuel oils; and |
^ |
¡½ Pipe jacking areas shall be closely monitored for frac-outs
release of bentonite and frac-out area immediately cleaned if they occur. |
^ |
The particular measures to protect the
ecology of the Lantau North Country Park are summarised below: |
-- |
¡½ Major stockpiled areas shall be sited outside of the country
parks area (Works Section 6) and away from stream courses as far as
practicable; |
^ |
¡½ All backfilling material and cement required for this Works
Section 6 shall be delivered daily and only the quantity required; |
^ |
¡½ No storage of chemicals and waste in Works Section 6; and |
^ |
¡½ No construction plant maintenance facilities in Works Section 6. |
^ |
Treated site drainage shall be discharged
via the existing drainage system or diverted to the artificial channel to
prevent stream bank erosion and directly affect the stream ecology. No site
drainage shall be allowed to be discharged at the natural stream bank. |
^ |
E) Landscape and Visual |
-- |
To maximize protection of existing resources
including watercourses existing trees, ground vegetation and the associated
understory habitats a "No-intrusion Zone" will be designated to various
areas within and along the site boundary with rigid and durable fencing for
each individual no-intrusion zone. Regular checks will be carried out to
ensure that the work site boundaries are not exceeded, hoarding is properly
maintained and that no damage is being caused to these protected areas. |
^ |
A temporary screen hoarding shall be erected
around the north side of the Site Office (SO) area to screen activities from
local receivers. It shall be designed and to be compatible with the existing
rural context, with visually unobtrusive design and colours where
appropriate. |
^ |
No night time work shall be programmed
avoiding light pollution to visual receivers. |
^ |
F) Cultural Heritage |
-- |
Four built heritage resources have been
identified as being located in close proximity to the proposed works areas,
namely, NP-19, NP-20, NP-21 and NP-26, as detailed in Appendix G1 and shown
in Figures 8.12, 8.13 and 8.15 of the EIA Report. The structures may be
damaged by contact with machinery and equipment. The recommended mitigation
measures for each resource are as follows: |
-- |
¡½
A buffer zone of a minimum of 5 metres in size (or if due to
site/engineering constraints, as large as possible buffer zone should be
provided) should be marked out for NP-19, NP-20, NP-21 and NP-26 by temporary
fencing and placed around the structures 2 weeks prior to the construction
works commencing. |
^ |
Three built heritage resources have been
identified as being in close proximity to an excavation area (NP-10, NP-11
and NP-19), a condition survey must be carried out by a qualified building
surveyor or engineer one month in advance of works commencing near the
buildings that may be affected by ground borne vibration. The Condition
Survey Report should contain descriptions of the structure, identification of
fragile elements, an appraisal of the condition and working methods for any
proposed monitoring (including frequency of monitoring) and precautionary
measures that are recommended. The Contractor must implement the approved
monitoring and precautionary measures. |
^ |
¡½
Vibration monitoring should be undertaken for the duration of the
construction works based upon the recommendations of the approved Condition
Survey Report, which will also define the frequency of monitoring required.
The maximum acceptable level of vibration will be set at 15 mm/s. Based upon
the findings of the condition survey, this limit may be revised for sensitive
structures. The location of monitoring points should be situated on the
structure closest to the construction works, unless the maximum level is set
lower than the standard 15 mm/s, in which case monitoring points should be
located on each affected structure. Installation of monitoring points must
not damage the historic building fabric. The location of monitoring points
(and access to the property for purposes of measurement) must be agreed with
the property owner prior to installation. |
^ |
G) Waste Management |
-- |
The requirements as
stipulated in the ETWB TC(W) No.19/2005 Environmental Management on
Construction Sites and the other relevant guidelines should be included in
the Particular Specification for the Contractor as appropriate. |
^ |
¡½ Waste management policy; ¡½ Record of generated waste; ¡½ Waste reduction target; ¡½ Waste reduction programme; |
|
¡½ Role and responsibility of waste management team; ¡½ Benefit of waste management; ¡½ Analysis of waste materials; |
|
¡½ Reuse, recycling and disposal plans; ¡½ Transportation process of waste products;
and ¡½ Monitoring and action plan. |
|
A trip-ticket system
should be established in accordance with DevB TC(W)
No. 6/2010 and Waste Disposal (Charges for Disposal of Construction Waste)
Regulation to monitor the disposal of public fill and solid wastes at public
filling facilities and landfills, and to control fly-tipping. A trip-ticket
system would be included as one of the contractual requirements for the
Contractor to strictly implement. The Engineer would also regularly audit the
effectiveness of the system. |
^ ^ ^ |
Recommendations for good site practices: |
-- |
¡½ The site and surroundings shall be kept tidy and litter free; |
^ |
¡½ No waste shall be burnt on-site; |
^ |
¡½ Make provisions in contract documents to allow and promote the
use of recycled aggregates where appropriate; |
^ |
¡½ The Contractor will be prohibited to dispose of C&D materials
within the proposed site and at any sensitive locations including Lantau
North Country Park, the Lantau South Country Park, the Ngong Ping Site of
Special Scientific Interest, the Lantau Peak Special Area and Site of Special
Scientific Interest and the Conservation Area, etc. The Contractor should
propose the final disposal sites in the EMP and WMP for approval before
implementation; |
^ |
¡½
Stockpiled material shall be covered by tarpaulin and /or watered as
appropriate to prevent windblown dust and surface run off; |
^ |
¡½ Major stockpiled areas shall be sited outside of the country
parks area (Works Section 6) and away from stream courses as far as
practicable. For the stockpiling area SA4 within the country park area,
stockpiling of earthed material shall be minimised and excavated soil from
Works Section 6 shall be delivered to the Site Office as soon as possible.
Similarly, overnight stockpiling of earthed material along the exposed trench
shall be minimised as far as possible and the excavated soil shall be
transferred to the designated stockpiling area as soon as possible; |
^ |
¡½ Excavated material in trucks shall be covered by tarpaulins to
reduce the potential for spillage and dust generation; |
^ |
¡½ Wheel washing facilities shall be used by all trucks leaving the
site to prevent transfer of mud onto public roads; |
^ |
¡½ Standard formwork or pre-fabrication should be used as far as
practicable so as to minimise the C&D materials arising. The use of more
durable formwork or plastic facing for construction works should also be
considered. The use of wooden hoardings should be avoided and metal hoarding
should be used to facilitate recycling. Purchasing of construction materials
should be carefully planned in order to avoid over-ordering and wastage; |
^ |
¡½ The Contractor should recycle as many C&D materials as
possible on-site. The public fill and C&D waste should be segregated and
stored in separate containers or skips to facilitate the reuse or recycling
of materials and proper disposal. Where practicable, the concrete and masonry
should be crushed and used as fill materials. Steel reinforcement bar should
be collected for use by scrap steel mills. Different areas of the sites
should be considered for segregation and storage activities; and ¡½ Subject to agreement with Water Service Department, adequate
numbers of portable toilets should be provided for on-site workers. Portable
toilets should be maintained in reasonable states, which will not deter the
workers from utilising them. Night soil should be regularly collected by
licensed collectors. |
^ |
^ |
|
Recommendations for waste reduction
measures: |
-- |
¡½ General refuse arising on-site should be stored in enclosed bins
or compaction units separately from C&D and chemical wastes. General
refuse shall be removed from Works Section 6 within the country park on the
regular basis. Sufficient dustbins shall be provided for storage of waste as
required under the Public Cleansing and Prevention of Nuisances By-laws. In addition,
general refuse shall be cleared regularly and shall be disposed of to the
nearest licensed landfill or refuse transfer station. Burning of refuse on
construction sites is prohibited; |
^ |
¡½ All waste containers shall be in a secure area on hardstanding; |
^ |
¡½ Aluminium cans are usually collected and recovered from the waste
stream by individual collectors if they are segregated and easily accessible.
Separately labelled bins for their deposition should be provided as far as
practicable; |
^ |
¡½ Office wastes can be reduced by recycling of paper if such volume
is sufficiently large to warrant collection. Participation in a local
collection scheme by the Contractor should be advocated. Waste separation
facilities for paper, aluminium cans, plastic bottles, etc should be provided
on- site; and |
^ |
¡½ Training shall be provided to workers about the concepts of site
cleanliness and appropriate waste management procedure, including waste
reduction, reuse and recycling. |
^ |
Chemical
waste producers should register with the EPD. Chemical waste should be handled in accordance with the Code of
Practice on the Packaging, Handling and Storage of Chemical Wastes as
follows: |
-- |
¡½ Suitable for the substance to be held, resistant to corrosion,
maintained in good conditions and securely closed; |
^ |
¡½ Having a capacity of <450L unless the specifications have been
approved by the EPD; |
N/A |
¡½ Displaying a label in English and Chinese according to the
instructions prescribed in Schedule 2 of the Regulations; |
^ |
¡½ Clearly labelled and used solely for the storage of chemical
wastes; |
^ |
¡½ Enclosed with at least 3 sides; |
^ |
¡½ Impermeable floor and bund with capacity to accommodate 110% of
the volume of the largest container or 20% by volume of the chemical waste
stored in the area, whichever is greatest; |
^ |
¡½ Adequate ventilation; |
^ |
¡½ Sufficiently covered to prevent rainfall from entering (water
collected within the bund must be tested and disposed of as chemical waste,
if necessary); |
^ |
¡½ Incompatible materials are adequately separated; |
^ |
¡½ All chemical waste, fuels and oils shall be stored at the Site
Office area, to minimise impacts to the Country Park and water gathering
grounds; |
^ |
¡½ All maintenance activities which may generate chemical waste
shall be undertaken in Site Office area, as far as possible; |
^ |
¡½ The Contractor shall comply with WSD's General Conditions for
Working within Water Gathering Grounds as applicable; and |
^ |
¡½ Waste oils, chemicals or solvents shall not be disposed of to
drain. |
^ |
Remark:
^ |
Compliance of
mitigation measure in the reporting period. |
# |
Recommendations were
made in the reporting period but has not yet been improved/rectified by the
Contractor. |
X |
Non-compliance of
mitigation measure in the reporting period. |
N/A |
Not Applicable in the
reporting period. |
N/O |
Not observed in the
reporting period. |
(1) |
Detailed EIA report and
EM&A Manual reference refer to the Appendix A of approved EM&A
Manual. |
Appendix C3 Summary of Site Inspection
Inspection Date |
Observations/ Reminders/ Recommendations |
Follow Up Action |
Completion Date |
Follow Up action(s) of last reporting month |
NIL. |
N.A |
N.A |
Weekly
Site Inspection |
|||
02/05/2023 |
Observation |
|
|
1) The NRMM Label of the excavator should be replaced
(L305). |
1) New NRMM label have been replaced at L305 |
02/05/2023 |
|
09/05/2023 |
Reminder |
|
|
1) Broken
sandbag should be replaced (Bay 4). |
-- |
-- |
|
16/05/2023 |
Observation |
|
|
1) Stagnant water in the drip tray should be cleared (L301). |
1) Stragnant water have been removed. |
23/05/2023 |
|
2) Stagnant water should be removed (L304). |
2) Stagnant water have been removed. |
23/05/2023 |
|
Reminder |
|
|
|
1) Broken sandbag should be replaced (L304). |
-- |
-- |
|
23/05/2023 |
Reminder |
|
|
1)
Broken samdbag should be replaced (L303). |
-- |
-- |
|
2)
Sand should cleared nearby the river. |
-- |
-- |
|
3)
General refuse should be cleared (Outfall2) |
-- |
-- |
|
30/05/2023 |
Observation |
|
|
1)
Water spray should be provided at the main haul road as dust control measures
(Bay 9). |
1) The observation will be followed up by the
Contractor |
-- |
|
Landscape
and Visual |
|||
02/05/2023 |
-- |
-- |
-- |
16/05/2023 |
-- |
-- |
-- |
30/05/2023 |
-- |
-- |
-- |
Cultural
Heritage |
|||
23/05/2023 |
-- |
|
|
Quarterly Post-transplantation
Works |
|||
-- |
-- |
||
Monthly
Floral Protection Measures |
|||
16/05/2023 |
Reminder |
|
|
1) From previous audit were not followed; posts to be replaced or
repaired were not fixed |
-- |
-- |
|
2) Replace the posts that are no loger found as indicated |
-- |
-- |
|
3) Repair the posts that have fallen down as indicated. |
-- |
-- |
Cultural Heritage
Monthly Floral Protection Measures
Appendix D Monitoring
Parameters Action and Limit Levels
Noise
Action and
Limit Levels for Impact Monitoring
Time Period |
Monitoring Location No. |
Action Level |
Limit Level* |
Leq),dB(A) (0700-1900
hrs in normal weekdays)(1) |
NSR1 Columbarium of Po Lin Monastery |
When one documented complaint is received. |
70 dB(A) |
NSR5 Village House No. 49A |
When one documented complaint is received. |
75 dB(A) |
|
NSR8 Village House No. 34 |
When one documented complaint is received. |
75 dB(A) |
Note:
*75 dB(A) for residential
premises and 70 dB(A) for educational institutions, kindergartens, nurseries
and all others where voice communication
(1) Any general construction
work carried out during restricted hours is controlled by Construction Noise
Permit (CNP) under the NCO.
Water Quality
Action and Limit Levels for
Impact Monitoring
Parameter(s) Station(s) |
DO
in mg/L |
Turbidity
in NTU |
pH |
Suspended
Solids in
mg/L |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
|||||
WS1-R1 |
|
|
|
|
|
|
|
|
|
|
|
|
WS1-I1 |
7.36 |
7.32 |
15.8(5) |
17.3(6) |
< |
6.5(3) |
or |
> |
6.9(4) |
<6.5
or >8.5 |
14(5) |
14(6) |
WS1-R2 |
|
|
|
|
|
|
|
|
|
|
|
|
WS1-I2 |
7.19 |
7.11 |
16.4(5) |
18.4(6) |
< |
6.5(3) |
or |
> |
6.9(4) |
<6.5
or >8.5 |
10(5) |
14(6) |
WS4-R3 |
|
|
|
|
|
|
|
|
|
|
|
|
WS4-I3 |
7.29 |
7.28 |
22.9(5) |
31.2(6) |
< |
6.9(3) |
or |
> |
7.2(4) |
<6.5
or >8.5 |
13(5) |
13(6) |
WS5-R4 |
|
|
|
|
|
|
|
|
|
|
|
|
WS5-I4 |
6.75 |
6.64 |
24.7(5) |
28.2(6) |
< |
6.6(3) |
or |
> |
7.1(4) |
<6.5
or >8.5 |
9(5) |
9(6) |
WS6-R5 |
|
|
|
|
|
|
|
|
|
|
|
|
WS6-I5 |
6.31 |
6.23 |
12.6(5) |
13.2(6) |
< |
6.6(3) |
or |
> |
7.0(4) |
<6.5
or >8.5 |
10(5) |
10(6) |
WS6-C1 |
|
|
|
|
|
|
|
|
|
|
|
|
WS6-R6 |
|
|
|
|
|
|
|
|
|
|
|
|
WS6-I6 |
6.57 |
6.38 |
21.7(5) |
23.7(6) |
< |
6.9(3) |
or |
> |
7.1(4) |
<6.5
or >8.5 |
12(5) |
13(6) |
Note:
AL: Action Level, LL: Limit
Level
(3)
Or 80% of upstream control station.
(4)
Or 110% of upstream control station.
(5)
Or 120% of upstream control station of the same day.
(6)
Or 130% of upstream control station of the same day.
Appendix E Event and Action
Plans
Event and Action Plan for Construction
Noise Monitoring
EVENT |
ACTION |
|||
ET(1) |
IEC(1) |
Engineer |
Contractor |
|
Action Level |
1. Notify the IEC and
Contractor. 2. Carry out investigation. 3. Report the results of
investigation to the IEC and Contractor. 4. Discuss with the Contractor
and formulate remedial measures. 5. Increase monitoring frequency
to check mitigation effectiveness. |
1. Review the analysed results
submitted by the ET. 2. Review the proposed remedial
measures by the Contractor and advise the Engineer accordingly. 3. Supervise the implementation
of remedial measures. |
1. Confirm receipt of
notification of failure in writing. 2. Notify the Contractor. 3. Require the Contractor to
propose remedial measures for the analysed noise problem. 4. Ensure remedial measures are
properly implemented. |
1. Submit noise mitigation
proposals to the IEC. 2. Implement noise mitigation
proposals. |
Limit Level |
1. Notify the IEC, Engineer, EPD
and Contractor. 2. Identify sources. 3. Repeat measurements to
confirm findings. 4. Increase monitoring
frequency. 5. Carry out analysis of the
Contractor's working procedures to determine possible mitigation to be implemented. 6. Inform the IEC, Engineer and
EPD the causes and action taken for the exceedances. 7. Assess the effectiveness of
the Contractor's remedial action and keep the IEC, EPD and Engineer informed
of the results. 8. If exceedance stops, cease
additional monitoring. |
1. Discuss amongst the Engineer,
ET and Contractor on the potential remedial action. 2. Review the Contractor's
remedial action whenever necessary to assure their effectiveness and advise
the Engineer accordingly. 3. Supervise the implementation
of remedial measures. |
1. Confirm receipt of
notification of failure in writing. 2. Notify the Contractor. 3. Require the Contractor to
propose remedial measures for the analysed noise problem. 4. Ensure remedial measures are
properly implemented. 5. If exceedance continues,
consider what portion of work is responsible and instruct the Contractor to
stop that portion of works until the exceedance is abated. |
1. Take immediate action to
avoid further exceedance. 2. Submit proposals for remedial
action to the IEC within 3 working days of notification. 3. Implement the agreed
proposals. 4. Resubmit proposals if
problems still not under control. 5. Stop the relevant portion of
works as determined by the Engineer until the exceedance is abated. |
Note: (1) ET -
Environmental Team, IEC - Independent Environmental Checker;
(2) According to
EM&A Manual Table 3.4.
Event and Action Plan for Water Quality
Monitoring (Part 1)
EVENT |
ACTION |
|||
ET(1) |
IEC(1) |
ER(1) |
Contractor |
|
Action Level being exceeded by one sampling day |
1. Repeat in-situ measurement to
confirm findings; 2. Identify source(s) of impact; 3. Inform the IEC and the
Contractor; 4. Check monitoring data, all
plant, equipment and the Contractor's working methods; 5. Discuss mitigation measures
with the IEC and the Contractor; 6. Repeat measurement on next
day of exceedance. |
1. Discuss with the ET and the
Contractor on the mitigation measures; 2. Review proposals on
mitigation measures submitted by the Contractor and advise the ER
accordingly; 3. Access the effectiveness of
the implemented mitigation measures |
1. Discuss with the IEC on the
proposed mitigation measures; 2. Make agreement on the
mitigation measures to be implemented. |
1. Inform the ER and confirm
notification of the non- compliance in writing; 2. Rectify unacceptable
practice; 3. Check all plant and
equipment; 4. Consider changes of working
methods; 5. Discuss with the ES and the
IEC and propose mitigation measures to the IEC |
Action Level being exceeded by more than one consecutive sampling days |
1. Repeat in-situ measurement to
confirm findings; 2. Identify source(s) of impact; 3. Inform the IEC and the
Contractor; 4. Check monitoring data, all
plant, equipment and Contractor's working methods; 5. Discuss mitigation measures
with the IEC and the Contractor; 6. Ensure mitigation measures
are implemented; 7. Prepare to increase the
monitoring frequency to daily; |
1. Discuss with the ET and the
Contractor on the mitigation measures; 2. Review proposals on
mitigation measures submitted by the Contractor and advise the ER
accordingly; 3. Access the effectiveness of
the implemented mitigation measures |
1. Discuss with IEC on the
proposed mitigation measures; 2. Make agreement on the
mitigation measures to be implemented; 3 Access the effectiveness of
the implemented mitigation measures. |
1. Inform the ER and confirm
notification of the non- compliance in writing; 2. Rectify unacceptable
practice; 3. Check all plant and
equipment; 4. Consider changes of working
methods; 5. Discuss with the ES and the
IEC and propose mitigation measures to the IEC and ER within 3 working days; 6. Implement the agreed
mitigation |
Event and Action Plan for Water Quality
Monitoring (Part 2)
EVENT |
ACTION |
|||
ET(1) |
IEC(1) |
ER(1) |
Contractor |
|
Limit Level being exceeded by one consecutive sampling day |
1. Repeat in-situ measurement to
confirm findings; 2. Identify source(s) of impact; 3. Inform the IEC, the
Contractor and the DEP; 4. Check monitoring data, all
plant, equipment and the Contractor's working methods; 5. Discuss mitigation measures
with the IEC, the ER and the Contractor; 6. Ensure mitigation measures
are implemented; 7. Increase the monitoring
frequency to daily until no exceedance of Limit Level. |
1. Discuss with the ES and the
Contractor on the mitigation measures; 2. Review proposals on
mitigation measures submitted by the Contractor and advise the ER
accordingly; 3. Access the effectiveness of
the implemented mitigation measures. |
1. Discuss with the IEC, the ES
and the Contractor on the proposed mitigation measures; 2. Request the Contractor to
critically review the working methods; 3. Make agreement on the
mitigation measures to be implemented; 4. Access the effectiveness of
the implemented mitigation measures. |
1. Inform the Engineer and
confirm notification of the non-compliance in writing; 2. Rectify unacceptable
practice; 3. Check all plant and
equipment; 4. Consider changes of working
methods; 5. Discuss with the ES, the IEC
and the ER and propose mitigation measures to the IEC and the ER within 3
working days; 6. Implement the agreed
mitigation measures. |
Limit Level being exceeded by more than one consecutive sampling days |
1. Repeat in-situ measurement to
confirm findings; 2. Identify source(s) of impact; 3. Inform the IEC, the
Contractor and DEP; 4. Check monitoring data, all
plant, equipment and Contractor's working methods; 5. Discuss mitigation measures
with the IEC, the ER and the Contractor; 6. Ensure mitigation measures
are implemented; 7. Increase the monitoring
frequency to daily until no exceedance of Limit Level for two consecutive
days. |
1. Discuss with ET and
Contractor on the mitigation measures; 2. Review proposals on
mitigation measures submitted by the Contractor and advise the ER accordingly; 3. Access the effectiveness of
the implemented mitigation measures. |
1. Discuss with the IEC, the ES
and the Contractor on the proposed
mitigation measures; 2. Request Contractor to
critically review the working methods; 3. Make agreement on the mitigation
measures to be implemented; 4. Access the effectiveness of
the implemented mitigation measures; 5. Consider and instruct, if
necessary, the Contractor to slow down or to
stop all or part of the works until no exceedance of Limit Level. |
1. Inform the ER and confirm
notification of the non- compliance in writing; 2. Rectify unacceptable
practice; 3. Check all plant and
equipment; 4. Consider changes of working
methods; 5. Discuss with the ES, the IEC
and the ER and propose mitigation measures to the IEC and the ER within 3
working days; 6. Implement the agreed
mitigation measures; 7. As directed by the ER, slow
down or stop all or part of the construction activities. |
Note: (1) ET -
Environmental Team, IEC - Independent Environmental Checker;
(2) According to
EM&A Manual Table 4.4.
Event / Action Plan for Ecological
Monitoring
Action Level |
ET(1) |
IEC(1) |
ER(1) |
Contractor |
Non-conformity
on one occasion |
Identify
Source Inform
the IEC and the ER Discuss
remedial actions with the IEC, the ER and the Contractor Monitor
remedial actions until rectification has been completed |
Check
report Check
the Contractor's working method Discuss
with the ET and the Contractor on possible remedial measures Advise
the ER on effectiveness of proposed remedial measures. Check
implementation of remedial measures. |
Notify
Contractor Ensure
remedial measures are properly implemented Consider
and instruct, if necessary, the Contractor to slow down or to stop all
or part of the works in the case of a serious non-conformity until situation
rectified. |
Amend
working methods Rectify
damage and undertake any necessary replacement |
Repeated
Non conformity |
Identify
Source Inform
the IC(E) and the ER Increase
monitoring frequency Discuss
remedial actions with the IC(E), the ER and the Contractor Monitor
remedial actions until rectification has been completed If
exceedance stops, cease additional monitoring |
Check
monitoring report Check
the Contractor's working method Discuss
with the ES and the Contractor on possible remedial measures Advise
the ER on effectiveness of proposed remedial measures Supervise
implementation of remedial measures |
Notify
the Contractor Ensure
remedial measures are properly implemented Consider
and instruct, if necessary, the Contractor to slow down or to stop all
or part of the works in the case of a serious non-conformity until situation
rectified. |
Amend working
methods Rectify
damage and undertake any necessary replacement |
Note: (1) ET -
Environmental Team, IEC - Independent Environmental Checker;
(2) According to
EM&A Manual Table 5.4.
Event / Action Plan for Construction/Operational
Phase for Ecology Issues (Landscape and Visual)
Action Level |
ET(1) |
IEC(1) |
ER(1) |
Contractor |
Non-conformity
on one occasion |
1. Identify
Source 2. Inform
the IEC and the ER 3. Discuss
remedial actions with the IEC, the ER and the Contractor 4. Monitor
remedial actions until rectification has been completed |
1. Check
report 2. Check
the Contractor's working method 3. Discuss
with the ET and the Contractor on possible remedial measures 4. Advise the
ER on effectiveness of proposed remedial measures. 5. Check implementation of
remedial measures. |
1. Notify
Contractor 2. Ensure
remedial measures are properly implemented |
1. Amend
working methods 2. Rectify
damage and undertake any necessary replacement |
Repeated
Non-conformity |
1. Identify
Source 2. Inform
the IEC and the ER 3. Increase
monitoring frequency 4. Discuss
remedial actions with the IEC, the ER and the Contractor 5. Monitor
remedial actions until rectification has been completed 6. If exceedance stops,
cease additional monitoring |
1. Check
monitoring report 2. Check
the Contractor's working method 3. Discuss
with the ET and the Contractor on possible remedial measures 4. Advise
the ER on effectiveness of proposed remedial measures 5. Supervise
implementation of remedial measures. |
1. Notify
the Contractor 2. Ensure
remedial measures are properly implemented |
1. Amend
working methods 2. Rectify
damage and undertake any necessary replacement |
Note: (1) ET -
Environmental Team, IEC - Independent Environmental Checker;
(2) According to
EM&A Manual Table 6.4.
Event / Action Plan for Construction
Phase for Heritage Issue
Action
Level |
ET(1) |
IEC(1) |
ER(1) |
Contractor |
Non-conformity
on one occasion |
1. Identify
Source 2. Inform
the IEC and the ER 3. Discuss
remedial actions with the IEC, the ER and the Contractor 4. Monitor
remedial actions until rectification has been completed |
1. Check
report 2. Check
the Contractor's working method 3. Discuss
with the ES and the Contractor on possible remedial measures 4. Advise
the ER on effectiveness of proposed remedial measures. 5. Check
implementation of remedial measures. |
1. Notify Contractor 2. Ensure remedial
measures are properly implemented |
1. Amend working
methods 2. Rectify damage and
undertake any necessary replacement |
Repeated
Non-conformity |
1. Identify
Source 2. Inform
the IEC and the ER 3. Increase
monitoring frequency 4. Discuss
remedial actions with the IEC, the ER and the Contractor 5. Monitor
remedial actions until rectification has been completed 6. If
exceedance stops, cease additional monitoring |
1. Check
monitoring report 2. Check
the Contractor's working method 3. Discuss
with the ES and the Contractor on possible remedial measures 4. Advise
the ER on effectiveness of proposed remedial measures 5. Supervise
implementation of remedial measures. |
1. Notify the Contractor 2. Ensure remedial
measures are properly implemented |
1. Amend working
methods 2. Rectify damage and
undertake any necessary replacement |
Note: (1) ET -
Environmental Team, IEC - Independent Environmental Checker;
(2) According to
EM&A Manual Table 7.
Appendix F1 Equipment Calibration
Certificates (Noise Monitoring)
Noise Monitoring
Equipment Record
Monitoring
Date |
Model |
Equipment |
Serial
No. |
02
May 2023 |
CEL-63X
Series |
Sound
Level Meter |
1488306 |
CEL-120/1 |
Sound Calibrator |
2525984 |
|
09
May 2023 |
CEL-63X
Series |
Sound
Level Meter |
1488314 |
CEL-120/1 |
Sound Calibrator |
5230950 |
|
16
May 2023 |
CEL-63X
Series |
Sound
Level Meter |
1488314 |
CEL-120/1 |
Sound Calibrator |
5230950 |
|
23 May 2023 |
CEL-63X
Series |
Sound
Level Meter |
1488306 |
CEL-120/1 |
Sound Calibrator |
2383707 |
|
30 May 2023 |
CEL-63X
Series |
Sound
Level Meter |
1488306 |
CEL-120/1 |
Sound Calibrator |
2383707 |
Appendix F2 Equipment Calibration Certificates (Water Quality
Monitoring)
Appendix G Environmental
Monitoring Schedule
Sun |
Mon |
Tue |
Wed |
Thu |
Fri |
Sat |
|
1 |
2 |
3 |
4 |
5 |
6 |
|
|
W
& N |
|
W |
|
W |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
|
|
W
& N |
|
W |
|
W |
14 |
15 |
16 |
17 |
18 |
19 |
20 |
|
|
W
& N |
|
W |
|
W |
21 |
22 |
23 |
24 |
25 |
26 |
27 |
|
|
W
& N |
|
W |
|
W |
28 |
29 |
30 |
31 |
|
|
|
¡@ |
¡@ |
W
& N |
|
|
|
|
Sun |
Mon |
Tue |
Wed |
Thu |
Fri |
Sat |
|
|
|
|
1 |
2 |
3 |
|
|
|
|
W |
|
W |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
|
|
W
& N |
|
W |
|
W |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
|
|
W
& N |
|
W |
|
W |
18 |
19 |
20 |
21 |
22 |
23 |
24 |
|
|
W
& N |
|
W |
|
W |
25 |
26 |
27 |
28 |
29 |
30 |
|
|
|
W
& N |
|
W |
|
|
Sun |
Mon |
Tue |
Wed |
Thu |
Fri |
Sat |
|
|
|
|
|
|
1 |
|
|
|
|
|
|
W |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
|
|
W
& N |
|
W |
|
W |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
|
|
W
& N |
|
W |
|
W |
16 |
17 |
18 |
19 |
20 |
21 |
22 |
|
|
W
& N |
|
W |
|
W |
23/30 |
24/31 |
25 |
26 |
27 |
28 |
29 |
|
|
W
& N |
|
W |
|
W |
Sun |
Mon |
Tue |
Wed |
Thu |
Fri |
Sat |
|
|
1 |
2 |
3 |
4 |
5 |
|
|
W
& N |
|
W |
|
W |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
|
|
W
& N |
|
W |
|
W |
13 |
14 |
15 |
16 |
17 |
18 |
19 |
|
|
W
& N |
|
W |
|
W |
20 |
21 |
22 |
23 |
24 |
25 |
26 |
|
|
W
& N |
|
W |
|
W |
27 |
28 |
29 |
30 |
31 |
|
|
|
|
W
& N |
|
W |
|
|
Remarks
1.
W:
Impact Water Quality Monitoring.
2.
N:
Impact Noise Monitoring.
3.
Actual
monitoring may be subjected to change due to any safety concern or adverse
weather condition, etc.
Appendix H1 Noise Monitoring Data and Graphical Presentations
Monitoring Location : |
NSR1 Columbarium of Po Lin Monastery |
|||||
Date |
Weather |
Wind Speed |
Start Time |
Noise
Monitoring (in dB(A)) |
||
Leq(30 min) |
L90(30 min) |
L10(30 min) |
||||
02-05-2023 |
Fine |
0.2 |
11:45 |
63.2 |
61.5 |
66.5 |
09-05-2023 |
Cloudy |
0.5 |
11:06 |
61.4 |
60.5 |
62.5 |
16-05-2023 |
Fine |
0.3 |
12:41 |
65.3 |
60.0 |
70.5 |
23-05-2023 |
Cloudy |
0.3 |
11:48 |
63.9 |
63.5 |
65.0 |
30-05-2023 |
Fine |
0.2 |
11:50 |
64.3 |
61.5 |
67.0 |
Monitoring Location : |
NSR5 Village House No. 49A |
|||||
Date |
Weather |
Wind Speed |
Start Time |
Noise
Monitoring (in dB(A)) |
||
Leq(30 min) |
L90(30 min) |
L10(30 min) |
||||
02-05-2023 |
Fine |
0.2 |
10:10 |
57.7 |
50.5 |
59.0 |
09-05-2023 |
Cloudy |
0.4 |
9:47 |
49.4 |
48.5 |
50.0 |
16-05-2023 |
Fine |
0.5 |
11:20 |
57.6 |
56.0 |
59.0 |
23-05-2023 |
Cloudy |
0.3 |
10:05 |
64.6 |
62.0 |
66.5 |
30-05-2023 |
Fine |
0.3 |
9:56 |
65.4 |
62.5 |
66.5 |
Monitoring Location : |
NSR8 Village House No. 34 |
|||||
Date |
Weather |
Wind Speed |
Start Time |
Noise
Monitoring (in dB(A)) |
||
Leq(30 min) |
L90(30 min) |
L10(30 min) |
||||
02-05-2023 |
Fine |
0.3 |
9:13 |
53.1 |
49.5 |
55.0 |
09-05-2023 |
Cloudy |
0.8 |
9:10 |
52.2 |
43.5 |
55.5 |
16-05-2023 |
Fine |
0.4 |
10:22 |
54.0 |
48.0 |
56.0 |
23-05-2023 |
Cloudy |
0.2 |
9:00 |
56.6 |
54.5 |
60.0 |
30-05-2023 |
Fine |
0.3 |
9:00 |
57.1 |
55.0 |
60.5 |
|
Noise
Monitoring (in dB(A)) |
|
|
Min |
Max |
NSR1 |
61.4 |
65.3 |
NSR5 |
49.2 |
65.4 |
NSR8 |
52.2 |
57.1 |
Remarks:
1) NSR1 & NSR5 noise results were
calculated by +3 dB (A) correction for free-field measurement.
Note: 1) Major
activities being carried out on site during the reporting period refer to
section 1.4. 2) The
other factors influencing the monitoring results refer to section 5.5.3. 3) The
QA/QC procedures and detection Limits refer to section 5.1 and 5.2. |
Appendix H2 Water
Quality Monitoring Data and Graphical
Presentations
Monitoring
Results Summary
Parameter(s) Station(s) |
DO
in mg/L |
Turbidity
in NTU |
pH |
Suspended
Solids in mg/L |
||||||||||||||||||||
Min |
- |
Max |
( |
Mean |
) |
Min |
- |
Max |
( |
Mean |
) |
Min |
- |
Max |
( |
Mean |
) |
Min |
- |
Max |
( |
Mean |
) |
|
WS1-R1 |
7.82 |
- |
7.82 |
( |
7.82 |
) |
6.60 |
- |
6.60 |
( |
6.60 |
) |
7.00 |
- |
7.00 |
( |
7.00 |
) |
8.50 |
- |
8.50 |
( |
8.50 |
) |
WS1-I1 |
7.39 |
- |
8.86 |
( |
8.12 |
) |
1.00 |
- |
6.90 |
( |
3.13 |
) |
6.80 |
- |
7.00 |
( |
6.90 |
) |
1.00 |
- |
13.50 |
( |
4.36 |
) |
WS1-R2 |
7.22 |
- |
8.67 |
( |
7.89 |
) |
0.75 |
- |
9.70 |
( |
3.38 |
) |
6.70 |
- |
7.00 |
( |
6.86 |
) |
1.00 |
- |
15.00 |
( |
6.04 |
) |
WS1-I2 |
7.51 |
- |
7.51 |
( |
7.51 |
) |
6.40 |
- |
6.40 |
( |
6.40 |
) |
7.10 |
- |
7.10 |
( |
7.10 |
) |
5.00 |
- |
5.00 |
( |
5.00 |
) |
WS4-R3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
WS4-I3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
WS5-R4 |
6.76 |
- |
7.71 |
( |
7.14 |
) |
1.80 |
- |
20.50 |
( |
9.80 |
) |
7.00 |
- |
7.10 |
( |
7.07 |
) |
1.00 |
- |
24.00 |
( |
6.64 |
) |
WS5-I4 |
6.75 |
- |
7.25 |
( |
6.88 |
) |
5.90 |
- |
22.60 |
( |
15.03 |
) |
7.00 |
- |
7.20 |
( |
7.13 |
) |
2.00 |
- |
145.00 |
( |
56.63 |
) |
WS6-R5 |
6.40 |
- |
6.40 |
( |
6.40 |
) |
10.30 |
- |
10.30 |
( |
10.30 |
) |
7.00 |
- |
7.00 |
( |
7.00 |
) |
21.50 |
- |
21.50 |
( |
21.50 |
) |
WS6-I5 |
6.32 |
- |
7.44 |
( |
6.75 |
) |
1.30 |
- |
12.30 |
( |
6.58 |
) |
6.90 |
- |
7.10 |
( |
6.98 |
) |
2.00 |
- |
135.00 |
( |
38.60 |
) |
WS6-C1 |
4.00 |
- |
7.30 |
( |
6.21 |
) |
0.10 |
- |
37.30 |
( |
4.33 |
) |
6.10 |
- |
7.60 |
( |
6.82 |
) |
1.00 |
- |
16.50 |
( |
2.65 |
) |
WS6-R6 |
6.50 |
- |
7.90 |
( |
7.08 |
) |
1.00 |
- |
19.90 |
( |
5.13 |
) |
6.90 |
- |
7.20 |
( |
7.01 |
) |
1.00 |
- |
42.50 |
( |
8.64 |
) |
WS6-I6 |
6.60 |
- |
7.80 |
( |
7.11 |
) |
1.00 |
- |
20.50 |
( |
5.31 |
) |
6.90 |
- |
7.20 |
( |
7.03 |
) |
1.00 |
- |
40.00 |
( |
6.18 |
) |
Laboratory Duplicate, Quality Assurance/Quality Control Summary extract
form Lab test report
Total suspended solids
dried at 103oC ¡V 105oC |
||||||
Sampling Date |
Detection Limit |
Blank |
Spike recovery (%) |
Original result |
Duplicate result |
RPD% |
02/05/2023 |
1mg/L |
<1 |
101.60 |
8.68 |
7.72 |
11.71 |
04/05/2023 |
1mg/L |
<1 |
97.77 |
1.02 |
1.07 |
4.78 |
06/05/2023 |
1mg/L |
<1 |
102.10 |
3.30 |
3.40 |
2.99 |
09/05/2023 |
1mg/L |
<1 |
101.75 |
0.90 |
1.08 |
18.18 |
11/05/2023 |
1mg/L |
<1 |
104.20 |
0.52 |
0.56 |
7.41 |
13/05/2023 |
1mg/L |
<1 |
98.80 |
1.16 |
1.20 |
3.39 |
16/05/2023 |
1mg/L |
<1 |
98.65 |
2.95 |
2.70 |
8.85 |
18/05/2023 |
1mg/L |
<1 |
97.43 |
0.58 |
0.69 |
17.76 |
20/05/2023 |
1mg/L |
<1 |
101.62 |
1.62 |
1.53 |
5.77 |
23/05/2023 |
1mg/L |
<1 |
95.80 |
17.10 |
16.50 |
3.57 |
1 mg/L |
<1 |
98.80 |
13.50 |
11.90 |
12.60 |
|
25/05/2023 |
1mg/L |
<1 |
98.55 |
1.02 |
1.00 |
1.98 |
27/05/2023 |
1mg/L |
<1 |
99.62 |
0.42 |
0.49 |
15.38 |
30/05/2023 |
1mg/L |
<1 |
97.90 |
46.63 |
44.12 |
5.53 |
Parameter Exceedance Summary
Monitoring Date |
Monitoring Location |
Exceedance Parameter |
Monitoring Results |
Action Level(AL) |
Limit Level(LL) |
Project-related? |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
Monitoring Location Dried up Summary
Date /
Location |
WS1-R1 |
WS1-I1 |
WS1-R2 |
WS1-I2 |
WS4-R3 |
WS4-I3 |
WS5-R4 |
WS5-I4 |
WS6-R5 |
WS6-I5 |
WS6-C1 |
WS6-R6 |
WS6-I6 |
2 May 2023 |
Dried Up |
Dried Up |
|
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
|
|
|
4 May 2023 |
Dried Up |
Dried Up |
|
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
|
Dried Up |
Dried Up |
6 May 2023 |
Dried Up |
Dried Up |
|
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
|
Dried Up |
Dried Up |
9 May 2023 |
Dried Up |
|
|
Dried Up |
Dried Up |
Dried Up |
|
Dried Up |
Dried Up |
|
|
|
|
11 May 2023 |
Dried Up |
Dried Up |
|
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
|
|
|
13 May 2023 |
Dried Up |
Dried Up |
|
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
|
|
|
16 May 2023 |
Dried Up |
Dried Up |
|
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
|
|
|
18 May 2023 |
Dried Up |
|
|
Dried Up |
Dried Up |
Dried Up |
|
|
Dried Up |
|
|
|
|
20 May 2023 |
Dried Up |
|
|
Dried Up |
Dried Up |
Dried Up |
|
Dried Up |
Dried Up |
Dried Up |
|
|
|
23 May 2023 |
|
|
|
|
Dried Up |
Dried Up |
|
|
|
|
|
|
|
25 May 2023 |
Dried Up |
|
|
Dried Up |
Dried Up |
Dried Up |
|
|
Dried Up |
|
|
|
|
27 May 2023 |
Dried Up |
|
|
Dried Up |
Dried Up |
Dried Up |
|
|
Dried Up |
|
|
|
|
30 May 2023 |
Dried Up |
Dried Up |
|
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
Dried Up |
|
|
|
Note:
1) Major
activities being carried out on site during the reporting period refer to
section 1.4.
2) The
other factors influencing the monitoring results refer to section 5.5.4.
3) The
QA/QC procedures and detection Limits refer to section 5.1 and 5.2.
Appendix I Statistics on
Exceedances, Complaints, Notifications of Summons and Prosecutions
Statistics on Monitoring Exceedance (Reporting Month)
Reporting Period |
No. of Exceedance |
|||
AL |
LL |
|||
No. of Exceedance This Month |
Noise |
0 |
0 |
|
Water Quality |
pH |
0 |
0 |
|
DO |
0 |
0 |
||
Turbidity |
0 |
0 |
||
Suspended Solids |
0 |
4 |
Statistics on Complaints, Notifications of Summons and Successful
Prosecutions
Reporting Period |
Complaints |
Notifications of Summons |
Successful Prosecutions |
No. of Complaints , Notifications of Summons and
Successful Prosecutions This Month |
0 |
0 |
0 |
Cumulative
Project-to-Date |
0 |
0 |
0 |
Environmental Complaints Log
Complaint Log No. |
Date of Complaint
Received |
Received From |
Received By |
Nature of Complaint |
Investigation/Mitigation Action |
Status |
NIL |
-- |
-- |
-- |
-- |
-- |
-- |
Remark:
(1)
No Complaints,
Notifications of Summons or Successful Prosecutions was received in the
reporting period.
Appendix I2 Investigation
Report on Limit Level of Non-compliance
Date |
Mean Pressure
(hPa) |
Air Temperature |
Mean Dew Point
(deg. C) |
Mean Relative
Humidity (%) |
Mean Amount of Cloud (%) |
Total Rainfall
(mm) |
||
Absolute Daily
Max (deg. C) |
Mean (deg. C) |
Absolute Daily
Min (deg. C) |
||||||
May 2023 |
||||||||
1 |
1014.2 |
26.1 |
24.1 |
23.0 |
19.9 |
78 |
87 |
0.3 |
2 |
1015.2 |
26.9 |
24.1 |
22.7 |
19.1 |
74 |
81 |
0.0 |
3 |
1013.4 |
29.1 |
25.4 |
23.6 |
22.5 |
84 |
79 |
0.1 |
4 |
1008.8 |
31.0 |
27 |
25.4 |
23.9 |
84 |
74 |
0.0 |
5 |
1005.8 |
30.2 |
27.5 |
25.5 |
23.7 |
80 |
66 |
0.0 |
6 |
1004.4 |
29.7 |
28.2 |
26.9 |
24.8 |
82 |
85 |
0.0 |
7 |
1006.0 |
30.3 |
26.6 |
23.4 |
24.0 |
86 |
88 |
35.5 |
8 |
1011.0 |
24.8 |
23.2 |
21.9 |
21.1 |
88 |
88 |
39.2 |
9 |
1013.2 |
26.5 |
23.8 |
22.3 |
19.7 |
78 |
82 |
0.1 |
10 |
1013.7 |
25.3 |
23.9 |
23.0 |
18.1 |
70 |
88 |
0.0 |
11 |
1014.7 |
25.8 |
23.9 |
22.2 |
19.2 |
76 |
88 |
0.5 |
12 |
1014.8 |
25.7 |
24.4 |
23.8 |
20.0 |
77 |
88 |
Trace |
13 |
1013.8 |
25.3 |
23.5 |
22.3 |
20.8 |
85 |
89 |
9.5 |
14 |
1011.6 |
23.1 |
21.3 |
20.2 |
20.2 |
93 |
94 |
39.9 |
15 |
1010.4 |
27.1 |
24.3 |
21.9 |
21.4 |
84 |
83 |
0.1 |
16 |
1009.6 |
27.3 |
25.2 |
23.1 |
22.9 |
87 |
81 |
0.4 |
17 |
1007.9 |
28.9 |
26.9 |
23.7 |
24.9 |
89 |
88 |
32.7 |
18 |
1006.9 |
31.4 |
28.9 |
27.5 |
25.7 |
83 |
63 |
0.0 |
19 |
1007.7 |
31.3 |
29.1 |
27.4 |
25.6 |
82 |
67 |
0.0 |
20 |
1008.5 |
32.7 |
29.7 |
28.0 |
25.9 |
80 |
76 |
Trace |
21 |
1009.0 |
32.2 |
29.7 |
28.0 |
25.6 |
79 |
78 |
1.5 |
22 |
1008.1 |
33.0 |
30 |
28.1 |
25.2 |
76 |
83 |
0.0 |
23 |
1009.1 |
29.2 |
26.9 |
24.4 |
24.7 |
88 |
93 |
8.3 |
24 |
1010.5 |
28.2 |
24.9 |
23.3 |
22.7 |
88 |
93 |
14.5 |
25 |
1012.0 |
26.9 |
26.1 |
24.9 |
24.0 |
89 |
88 |
Trace |
26 |
1011.9 |
30.9 |
27.8 |
26.4 |
25.3 |
87 |
85 |
0.2 |
27 |
1010.4 |
32.3 |
28.8 |
26.7 |
25.1 |
81 |
60 |
0.0 |
28 |
1009.8 |
32.5 |
28.7 |
27.0 |
23.7 |
75 |
47 |
Trace |
29 |
1008.0 |
32.3 |
28.9 |
26.3 |
23.5 |
73 |
18 |
0.0 |
30 |
1004.0 |
34.6 |
31.2 |
28.0 |
25.9 |
74 |
14 |
0.0 |
31 |
1002.1 |
34.7 |
31.4 |
29.6 |
26.8 |
77 |
37 |
Trace |
Trace means rainfall less than 0.05 mm |
Source: Hong Kong Observatory