Environmental Impact Assessment (EIA) for
Route 9 between Tsing Yi and Cheung Sha Wan

Reference of the EIA Report in the Register: AEIAR018/1999
Condition of Approval under Section 8(3) of the EIA Ordinance

  1. The recommendation of the EIA Report, as exhibited in accordance with section 7(1) of the Ordinance, shall be properly implemented.

  2. To deal with key project changes after the approval of the EIA report, the applicant or the person in charge of the project shall seek written agreement from the Director on those project changes that would affect the findings and recommendations of the approved EIA report, and shall demonstrate to the satisfaction of the Director that the same environmental performance requirements in the approved EIA report can be met by equivalent or additional measures. Such information shall be made available to the public, as directed by the Director.

  3. The approval of the EIA report shall not remove any person's responsibility to comply with other legislation or to obtain other government approvals.

 

Environmental Protection Department
October 1999


Supplementary EIA Information persuant to (2) above