3.                         NOISE

3.1                      Introduction

Yau Tong Bay Development Reclamation

3.1.1                 Westwood Hong & Associates Ltd (WHA) was commissioned to conduct an environmental noise impact assessment on the proposed Yau Tong Bay Development Reclamation.

3.1.2                 This report presents the assessment criteria, methodology and results for the noise impact as per the requirements stipulated in the relevant Technical Memorandums (TMs) issued under the Noise Control Ordinance (NCO)[1] : the TM on EIA Process (EIA-TM)[2], the TM on Noise from Construction Work other than Percussive Piling (GW-TM)[3] , the TM on Noise from Construction Work in Designated Areas (DA-TM)[4] and the TM on Noise from Percussive Piling (PP-TM)[5].

Scope and Objectives of the EIA (noise)

3.1.3                 The scope of the EIA will cover all works proposed within the Study Area and any other works associated with these developments outside the Study Area. The EIA study will cover the combined impacts of all these works on the Noise Sensitive Receivers (NSRs) in the vicinity in accordance with the requirements laid down in the TM. The scope includes the following key work elements of the project:-

i)     Reclamation of Yau Tong Bay

ii)   Construction of seawall

iii)  Diversion of existing drainage outfall and provision of new stormwater drainage system

iv)   Provision of new sewerage system

v)    Decommissioning of all the marine lots which have the potential history of land contamination due to ship building and repairing facilities

vi)   Demolition of existing building structures; and

vii) Provision of infrastructure (e.g. access roads, waterworks, services and utilities, etc.)

3.1.4                 The potential noise sources from the site are identified as the following:-

·       Construction noise (including reclamation works and demolition of existing buildings)

·       Vehicular movement on haul roads.


3.2                      Reclamation Site Location

3.2.1                 The reclamation site for the CDA (Comprehensive Development Area) adjoins Cha Kwo Ling Road to the north and east and, Ko Fai Road to the south.  The future Western Coast Road (WCR) will be located to the west of the site and MTR Yau Tong Station to the east (Figures 3.1 and 3.2).  The reclamation works cover about 18 hectares comprising 14.2 hectares of Yau Tong Bay and 3.8 hectares seabed areas of the existing Marine Lots.  Should the coastal alignment of the WCR eventually be revised, the EIA reports need to be revised.

3.3                      Assessment Criteria

3.3.1                 Construction work should comply with the requirements of the “Noise Control Ordinance” (NCO), the “Technical Memorandum on Environmental Impact Assessment Process” (EIA-TM), “Technical Memorandum on Noise from Construction Work other than Percussive Piling” (GW-TM) and the “Technical Memorandum on Noise from Construction Work in Designated Areas” (DA-TM). However, the entire reclamation site lies outside the Designated Area and construction activities during restricted hours will need to comply with EIA-TM only. 

3.3.2                 Noise standards for daytime construction activities are given in Table 1B of the “Technical Memorandum on Environmental Impact Assessment Process” (EIA-TM).  The noise standards are dependent on the uses of the NSRs. The day-time construction noise (on any day not being a Sunday or general holiday) should be limited to 75dB(A) (Leq, 30-mins) at the sensitive residential buildings with opened windows and, 70dB(A) and 65dB(A) (during examinations) at the school and educational buildings in the neighbourhood, as given in Table 3.1. EIA-TM states that the noise criteria for construction or decommissioning of designated projects, shall be met as far as practicable. All practicable mitigation measures shall be exhausted and the residual impacts are minimized.

Table 3.1              Acceptable Noise Levels For Day, Evening and Night Periods


Noise Standards, dB(A), Leq (30 mins)

Uses

0700 to 1900 hours on any day not being a Sunday or general holiday

1900 to 0700 hours or any time on Sundays or general holiday

All domestic premises including temporary housing accommodation

75

(see Note 3)

Hotels and hostels

75

(see Note 3)

Educational institutions including kindergartens, nurseries and all others where unaided voice communication is required

70

 

65

(during exam.)

 

 

(see Note 3)

Note 3: The criteria laid down in the relevant technical memoranda under the Noise Control Ordinance for designated areas and construction works other than percussive piling may be used for planning purpose. A Construction Noise Permit (CNP) shall be required for the carrying out of the construction work during the period.

3.3.3                 GW-TM will cover the use of specified powered mechanical equipment (PME) including barge mounted cranes, barges, grab dredgers, dumpers, excavators, hydraulic rock drills, tug boats, etc.

3.3.4                 DA-TM governs construction works to be carried out within a Designated Area during restricted hours. It covers Prescribed Construction works including erection or dismantling of formwork or scaffolding; loading, unloading or handling of rubble, wooden boards, steel bars, wood or scaffolding material; and hammering. As the entire reclamation site lies outside the Designated Areas, DA-TM does not apply. Construction activities during restricted hours will need to comply with GW-TM only.

3.3.5                 A Construction Noise Permit (CNP) is required for any construction work carried out during the night-time (2300 to 0700 hours), evening (1900 to 2300 hours) and any time on general holidays, including Sunday.

3.3.6                 The control of percussive piling is governed at all times by “Technical Memorandum on Noise From Percussive Piling” (PP-TM).

3.3.7                 The NCO requires that the construction noise level to comply with the specified Acceptable Noise Level (ANL) as given in GW-TM and DA-TM. The ANL is dependent on the Area Sensitivity Rating for the NSR, as listed in Tables 3.2 and 3.3. For this assessment, it is anticipated that construction works may be carried for the MTRC Yau Tong Station such that ANLs are equal to the BNLs - 3.

3.3.8                 The ANLs from GW-TM for Construction other than Percussive Piling are given in Table 3.2 with no correction applied to allow for noise contribution from construction work associated with more than one CNP.  The Authority should be approached for clarification of an appropriate correction for multiple permit situations.

Table 3.2              Acceptable Noise Levels for Construction other than Percussive Piling, dB(A)

Time Period

ASR “A”

ASR “B”

ASR “C”

All days during the evening (1900 to 2300 hours), and general holidays (including Sundays) during the day-time and evening (0700 to 2300 hours)

 

60

 

65

 

70

All days during the night-time (2300 to 0700 hours)

45

50

55

 

3.3.9                 In addition, other noise regulations, Noise Control (Hand held percussive breakers) Regulations and Noise Control (Air Compressors) Regulations govern the noise from hand held breakers and air compressors on compliance with the relevant noise emission standards and the fixing of noise emission labels.

3.4                      Methodology

Construction Noise Assessment Methodology

3.4.1                 The methodology for assessing the construction noise other than percussive piling is based on GW-TM, as summarised in the following:-

i)      To identify the affected NSRs within the Study Area;

ii)     To determine the Area Sensitivity Rating (ASR) of NSRs for construction work;

iii)    To identify the phasing of construction work and, locations and required number of the construction plant items;

iv)    To obtain the sound power levels in dB(A) of the construction equipment from the TM;

v)      To determine the distance and distance attenuations (from geometric spreading and other absorption effects where appropriate), barrier corrections from a notional noise point source and reflection corrections at the NSR;

vi)    To calculate the Corrected Noise Level (CNL) which will be generated by the construction work at the NSRs;

vii)   To correct for multiple site situations; and

viii)  To propose direct mitigation measures, if necessary, to minimise the impact by the construction work in order to comply with the stipulated noise limits.

3.4.2                 Appropriate mitigation measures have been evaluated and recommended in cases where the stipulated noise criteria are exceeded at the NSRs.  A systematic approach to the evaluation of the mitigation measures has been adopted with the following three levels of mitigation :-

·       Level One – use of quiet plant and construction methods

·       Level Two – erection of temporary noise screens and barriers

·       Level Three – reduction in plant items

3.4.3                 The use of quiet plant for the reclamation is encouraged as some models of plant are commercially available with sound power levels lower than that of the standard types specified in the GW-TM.

3.4.4                 Noise barriers of 3 to 5 m high site hoarding can be erected at the site boundary with a 5dB(A) reduction achievable from screening noisy construction activities from the NSRs. Location of site access should be carefully chosen without significantly compromising the effectiveness of the site barriers.  Stationary PME including generators and compressors can be fitted with acoustic enclosures to achieve a noise reduction of 10dB(A) or more. Movable barriers erected close to a noisy plant are also found to be effective in reducing noise emission.

3.4.5                 The Contractor has to make the choice of the number and types of construction equipment taking into account the use of quiet plant while devising a feasible work programme.

3.4.6                 The tentative programme for the whole development has been prepared by MCAL.

3.4.7                 The reclamation scheme phasing and Construction Programme have been prepared by MGS, the specialist consultant on reclamation construction, to cover construction work tasks to be carried out within different work areas.  The construction programme is divided into phases as described in the following and shown in Figure 3.2.

·          Seawall Construction - this phase of the reclamation will require temporary edge structures or seawalls to be formed.

·          Phase 1 works will form the main body of the reclamation. The extent will cover sites 1a to 1d with the reclamation work progressing from the landside towards the sea. 

·          Phase 2 works will take place above the pipe reserve and will be formed by a piled deck.

3.4.8                 Details of the Construction Programme are given in Appendix 3A. Construction of Seawall will commence in January 2004 and end in February 2004. Phase 1 works for Main Reclamation will commence in May 2004 and end in February 2007.  Phase 2 works for bored pile will commence in April 2004 and end in October 2007.

3.4.9                 The Schedule of Plant for reclamation has been provided by the MGS, the specialist consultant on reclamation construction (Appendix 3B).  The types of construction plant that may be required for the reclamation works, together with the sound power levels extracted from GW-TM, are given in Table 3.3.  These sound power levels are likely to result in the worst case noise prediction as quiet models of plant are now commercially available.

Table 3.3              Listing of PME items for Reclamation Works

DA-TM CNP Reference


Powered Mechanical Equipment (PME)

Maximum SWL

dB(A)

CNP048

Crane, mobile / barge mounted

112

CNP061

Derrick barge

104

CNP063

Dredger, grab

112

CNP066

Dumper

106

CNP067

Dump truck

117

CNP081

Excavator

112

CNP164

Piling, bored, grab & chisel

115

CNP165

Piling, bored, oscillator

115

CNP166

Piling, bored, reverse circulation drill

100

CNP021

Bar bender & cutter

90

CNP044

Concrete lorry mixer

109

CNP047

Concrete pump

109

CNP170

Poker

113

CNP101

Generator

108

CNP003

Air compressor

104

CNP282

Water pump

103

CNP221

Tug boat

110

 

3.4.10              The notional source position at each site has been taken in accordance with GW-TM to calculate the noise contribution from the site. The total noise level due to reclamation works is obtained by summing up contributions from all sites.

3.4.11              Computer analysis models will be employed to assess the noise impact, taking into consideration the NSR and source location, noise barriers, NSR orientation, contribution from various phases and construction sites.

Noise Assessment of Demolition Works

3.4.12              Demolition works are scheduled to be carried out for a duration of 2 months starting from July 2005 to August 2005 (Appendix 3A).

3.4.13              The types of PME plant that may be required for the demolition works, together with the sound power levels, are given in Table 3.4.

Table 3.4              Listing of PME items for Demolition Works

DA-TM CNP Reference

Powered Mechanical Equipment (PME)

Maximum SWL dB(A)

CNP081

Excavator

112

CNP023

Breaker

108

CNP101

Generator

108

CNP003

Air compressor

104

CNP067

Dump truck

117

CNP021

Bar bender & cutter

90

 

3.4.14              Demolition works will be carried out to three main areas with shipyard buildings or structures lying to the north, east and south of Yau Tong Bay.  The notional source position at each site has been taken in accordance with GW-TM to calculate the contribution from the site due to the demolition works.  The total noise level is obtained by summing up contributions from all three areas.

Noise Assessment of Vehicular Movement on Haul Roads

3.4.15              The assessment of noise from the movement of vehicles on-site shall be based on the methodology recommended in the British Standard BS 5228 Part I, Noise Control on Construction and Open Site, 1984 (BS).


3.5                      Baseline Conditions and Noise Sensitive Receivers

Yau Tong Area

3.5.1                 The existing NSRs have been located through site visits. For planned developments, representative NSRs have been identified by reference to Outline Zoning Plan and, information from MTRC, Housing Department and Planning Department.

3.5.2                 The major residential developments in the Yau Tong area are Yau Tong Centre, Yau Tong Estate and East Harbour Crossing (EHC) site.  The Yau Tong Estate is being redeveloped to have residential blocks and two new schools to replace the two existing schools, namely, Po Chiu College and St. Antonius Primary School.  These new schools have started operation in September 1999 and they are located close to the Yau Tong MTR Station. Noise mitigation measures with upgraded glazing and air-conditioners have been provided to these schools for reducing noise impacts from the Station Construction (Appendix 3C).

3.5.3                 Located to the northwest of the site are a few 1- to 2-storey village houses of Cha Kwo Ling.

3.5.4                 The other buildings in the Yau Tong area are industrial buildings, located south of Ko Fai Road and along Cha Kwo Ling Road.  As industrial buildings are not considered as NSRs, the noise impacts from the reclamation construction works do not need to cover these industrial buildings.

3.5.5                 In addition, the other major housing development and three new schools at EHC Site located to the north and north-west of Yau Tong Estate are scheduled to complete construction in September 2004 for EHC Phases 1, February 2005 for EHC Phase 2 and in September 2004 for the schools, (Appendix 3D).  Noise mitigation measures are expected to be provided by the Government to protect the schools from the significant traffic noise impact from heavily trafficked Cha Kwo Ling Road and that the development will make provision to provide the required noise mitigation measures if necessary.

Ambient Noise Condition

3.5.6                 The existing ambient noise climate of the representative NSRs is dominated by traffic noise from Cha Kwo Ling Road, Ko Fai Road and Lei Yue Mun Road, the distant Eastern Harbour Crossing and local roads.  The industrial noise also contributes to the overall ambient noise levels in the Yau Tong area. 

Representative NSRs

3.5.7                 The NSRs (planned and existing) closest to the reclamation have been identified as representative NSRs and are shown in Table 3.5 and Figure 3.3. The information on the completion year of each NSRs is extracted from the letter prepared by Hong Kong Housing Authority (Appendix 3D).


3.5.8                 For the Yau Tong Estate and Yau Tong Centre, the NSRs are assumed to have open windows and a direct line of sight to the appropriate construction site. Inspection conducted in Dec 98 has confirmed that the Cha Kwo Ling school was no longer in use. For the Cha Kwo Ling village houses closest to site, the topography and existing screening available from the ventilation shaft structure and industrial buildings along Cha Kwo Ling Road provide noise screening to the majority of the construction sites. Hence, the NSRs are assumed to have a direct line of sight to the construction site (Site 1a) but to have a 10dB(A) barrier effect for the other construction sites screened from sight.

3.5.9                 Yau Tong Estate Phases 3 and 5, which have completion year later than Phases 1 and 2, will be screened by Phases 1 and 2 so that the occupants will not be adversely affected by the construction noise.

3.5.10              The phasing of reclamation work makes it practical to divide the reclamation area into smaller construction sites, as advised by MGS, the specialist consultant on reclamation construction.  For each site, the Notional Source Position (NSP) has been determined in accordance with the guidelines given in DA-TM.

Table 3.5              Noise Sensitive Receivers closest to reclamation site

 

 

 

Distance to Worksite (m)

NSRs

Representative NSRs

Completion Year

Seawall Construction

1a

1b

1c

1d

2

RYTE1

Yau Tong Estate (Phase 1)

08/2000

830

714

245

420

570

690

RYTE2

Yau Tong Estate (Phase 2)

10/2001

850

740

245

415

580

610

RYCT

Yau Tong Centre

existing

759

759

371

470

576

746

RCKL

Cha Kwo Ling

existing

405

405

539

397

422

321

REHC1

East Harbour Crossing Housing Estates (Phase 1)

09/2004

825

700

255

400

560

525

REHC2

East Harbour Crossing Housing Estates (Phase 2)

02/2005

660

540

195

365

405

345

RSCH1

New School 1 at YTE (North)

09/1999

870

745

270

435

600

600

RSCH2

New School 2 at YTE (South)

09/1999

840

745

245

415

585

615

RSCH3

New Schools at EHC

09/2004

615

495

105

190

350

320

 


3.6                      Prediction of Construction Noise Impacts

Prediction of noise due to Reclamation

3.6.1                 The construction noise levels are predicted at the representative NSRs using the methodology described in Section 3.4, the sound power levels of plant items listed in Table 3.3 and the reclamation programme and anticipated plant schedule given in Appendices 3A and 3B.

Construction Noise affecting Domestic Premises

3.6.2                 The results of the noise prediction for domestic premises are presented in Figures 3.4a – 3.4f and Appendix 3E. The predicted facade noise levels are within the 75dB(A) criterion for domestic premises over the whole period of reclamation.

Construction Noise affecting Schools

3.6.3                 The noise prediction results for schools are presented in Figures 3.4g – 3.4i and Appendix 3E. The predicted noise levels exceed the 70dB(A) criterion for schools and the 65dB(A) criterion during school examinations during Jan 2005 and Jul 2005 to Sep 2005.

3.6.4                 Noise mitigation measures as described in Section 3.7 should be adopted to mitigate the noise impact due to the reclamation works.

Prediction of noise due to Demolition Works

3.6.5                 The plant noise levels due to the demolition works on the existing boatyard/ industrial buildings are in the range of 58 - 76dB(A) at the NSRs (Table 3.6).  Details of calculations are given in Appendix 3F. The noise prediction results at the NSRs are also presented in Figures 3.4a to 3.4i.

Table 3.6              Predicted Noise Levels in dB(A) Leq due to demolition works at NSR locations


NSR locations

Predicted Noise Levels, dB(A) Leq  *

Noise Criteria dB(A)

Compliance

RYTE1

71

75

Yes

RYTE2

71

75

Yes

RYCT

58

75

Yes

RCKL

58

75

Yes

REHC1

68

75

Yes

REHC2

72

75

Yes

RSCH1

69

65/70

No/Yes

RSCH2

72

65/70

No/No

RSCH3

76

65/70

No/No

* Note : Predicted noise levels include facade effect but exclude contributions from background.

 

3.6.6                 The predicted noise levels at the residential NSRs are well within the stipulated limit as stated in Section 3.3. However, the predicted noise levels at the schools exceed the noise criteria. Noise mitigation measures as described in Section 3.7 should be adopted to mitigate the noise impact due to the demolition works.

Prediction of noise due to vehicular movement on haul roads

3.6.7                 According to MGS, the anticipated heavy vehicle/ PME movement on haul roads will be about a vehicle every 2 to 5 minutes in and out of the site, i.e. an additional traffic flow of 30 vehicles per hour. This flow is insignificant as compared to the 2,450 - 3,700 vehicles per hour on Cha Kwo Ling Road and 850 - 1650 vehicles on Ko Fai Road.

3.6.8                 As the exact routes for access roads in and around the sites are not available, the access roads are assumed to cover all the boundaries of each reclamation areas so as to be conservative in the noise prediction.

3.6.9                 The predicted noise levels at the NSRs due to movement of heavy vehicles / PME items within the reclamation sites are shown in Table 3.7.  Calculations of the noise prediction are given in Appendix 3G.

Table 3.7        Predicted Noise Levels in dB(A) Leq due to vehicular movement on haul roads at NSR locations


NSR locations

Predicted Noise Levels, dB(A) Leq  *

RYTE1 (Yau Tong Estate, Phase 1)

49

RYTE2 (Yau Tong Estate, Phase 2)

49

RYCT (Yau Tong Centre)

38

RCKL (Village at Cha Kwo Ling)

43

REHC1 (EHC Phase 1)

49

REHC2 (EHC Phase 2)

51

RSCH1 (School at north of YTE)

49

RSCH2 (School at south of YTE)

49

RSCH3 (3 Schools at EHC site)

53

* Note :      Predicted noise levels include facade effect but exclude contributions from background.

3.6.10              The predicted noise levels at all of the NSRs are well within the stipulated limit as stated in Section 3.3.  As compared with the PME noise levels, the predicted levels due to vehicular movement on haul roads are insignificant as these are lower than the predicted PME noise by about 20 dB(A).

3.6.11              The background noise levels measured at the NSRs due to road traffic and industrial activities were in the range of 68 - 75dB(A).  The predicted levels due to vehicular movement on haul roads are insignificant and, therefore, the haul road movement is unlikely to cause any noise nuisance to the NSRs.

3.7                      Mitigation Measures for Construction Noise

3.7.1                 The predicted daytime construction noise levels exceed the criteria stipulated in the EIA-TM for schools during January 2005 and July 2005 to September 2005. The following mitigation measures are recommended to reduce further the construction noise impact:-

·          Scheduling of work

·          Siting of facilities

·          Reduction of operating time

·          Use of Quiet Powered Mechanical Equipment (PME)

·          Use of temporary noise barriers

·          Use of movable noise barriers

·          Adopt good site practice

Scheduling of Work

3.7.2                 The Contractor has to make the choice of the number and types of construction equipment taking into account the use of quiet plant while devising a feasible work programme.

3.7.3                 This includes minimizing noisy operations during examination periods; avoiding simultaneous operation of noisy equipment; retaining existing features that can act as a noise barrier until the last phase; and erecting, as early as possible, any new structures which will have the effect of screening noise sources.  Such screens can reduce noise levels by 15dB(A) or more.

Siting of Facilities

3.7.4                 Noisy equipment, such as emergency generators and water pumps, should always be sited as far as possible from noise sensitive receivers.  Consideration should also be given to the use of structures such as site offices and stores as noise barriers.

Reduction of Plant Operating Time

3.7.5                 The activity sound power levels could be reduced by limiting the plant operating time.  For a 30-minute noise exposure time specified for the noise criteria, reducing the total operating time to 70% (i.e. 21 minutes) would result in a 1.5dB(A) reduction of the noise exposure.  The operating time of breakers is recommended to be reduced to 70% during the demolition works.

Use of Quiet Powered Mechanical Equipment (PME)

3.7.6                 The contractor should be requested to use quiet PME during reclamation and demolition works, whose actual SWL is less than the value specified in GW-TM.  This is one of the most effective measures and is increasingly practicable because of the availability of quiet equipment.  Examples of SWLs for specific silenced PME are given in the following Table 3.8.


Table 3.8              Listing of Quiet PME items


Powered Mechanical Equipment (PME)

Reference

(GW-TM and BS)

Maximum SWL, dB(A)

Crane, mobile

BS Table C.7, 110

106

Dumper

BS Table C.7, 81

96

Dump truck

BS Table C.9, 19

102

Excavator

BS Table C.6, 28

102

Truck mixer

BS Table C.6, 23

100

Concrete pump

BS Table C.6, 36

106

Generator

TM CNP103

95

Air compressor

TM CNP001

100

 

Use of Temporary Noise Barriers

3.7.7                 It is recommended to erect a noise barrier of 3m to 5m high along the site boundary adjoining Cha Kwo Ling Road and Ko Fai Road during the construction phase.  The noise barrier should be constructed of impervious material with minimum 15kg/m2 surface density.  The noise barrier would provide screening losses of 3 to 5 dB(A) and reduce the construction noise impact on the NSRs.  Location of site access should be carefully chosen without significantly compromising the effectiveness of the site barriers.

Use of Movable Noise Barriers

3.7.8                 Movable noise barriers can be very effective at screening NSRs from noisy plant.  A 8m high movable barrier with skid footing and a small cantilevered upper portion can be located within a few metres of static plant and within about 5m of mobile plant.  It is estimated that movable noise barriers of this type can produce 10dB(A) of screening for static plant and 5dB(A) for mobile plant.  Movable noise barriers are recommended in this study for grab & chisel bored piling and oscillator bored piling since Jan 2005 which can provide 10dB(A) of screening benefits to the NSRs.

Adopt Good site practice

3.7.9                 Good site practice and noise management can considerably reduce the impact of the construction sites’ activities on nearby NSRs.  The following measures should be followed during each phase of construction:

·          only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction programme;

·          machines and plant (such as trucks) that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum;

·          plant known to emit noise strongly in one direction, should, where possible, be orientated so that the noise is directed away from nearby NSRs;

·          silencers or mufflers on construction equipment should be utilised and should be properly maintained during the construction period;

·          mobile plant should be sited as far away from NSRs as possible; and

·          material stackpiles and other structures should be effectively utilised, where practicable, to screen noise from on-site construction activities.

3.8                      Evaluation of Residual Impacts

Reclamation

3.8.1                 With the implementation of quiet plants and movable noise barriers for grab and chisel bored piling and oscillator bored piling, the noise levels at the NSRs were predicted. Details of predicted noise levels are given in Appendix 3H.

Demolition Works

3.8.2                 With the implementation of quiet plants and reduction of operating time for breakers, the noise levels at the NSRs were predicted. The results are summarised in the following Table 3.9.  Details of calculation are given in Appendix 3I.

Table 3.9              Predicted Noise Levels in dB(A) Leq due to demolition works at NSR locations


NSR Locations

Predicted Noise Levels, dB(A) Leq  *

Noise Criteria dB(A)

Compliance

RYTE1

63

75

Yes

RYTE2

63

75

Yes

RYCT

49

75

Yes

RCKL

50

75

Yes

REHC1

60

75

Yes

REHC2

64

75

Yes

RSCH1

61

65/70

Yes/Yes

RSCH2

64

65/70

Yes/Yes

RSCH3

68

65/70

No/Yes

 

3.8.3                 The predicted noise levels due to the reclamation and demolition works are presented in Figures 3.5a to 3.5i.  Results indicate that the mitigated noise levels at RSCH1 and RSCH2 comply with the 65dB(A) noise criterion over the whole period of reclamation.

3.8.4                 RSCH3 will have cumulative noise levels up to 70dB(A) for a short period due to the demolition works during the summer vocation period from July 2005 to August 2005.  The cumulative noise level during September 2005 is 66dB(A), which is well within the 70dB(A) criterion for normal school days.  As no examination will be held during September, there is no residual noise impact at RSCH3.


3.9                      Cumulative Impacts

3.9.1                 During the construction period of the reclamation works, other concurrent construction activities will be carried out in the vicinity, such as, for the Yau Tong Bay Development (Package 2), Yau Tong Estate Development and the East Harbour Crossing Housing Estates.  The cumulative construction noise impacts at the NSRs from the overall construction works in Yau Tong area are presented in the following.

3.9.2                 The possibility of a tunnel alignment option for the proposed Western Coast Road (WCR) project was made known to the public in March 2000, given the strong public objections on the coastal alignment.  Since the alignment has not been finalised at the time of preparing this report, the construction of WCR is likely not to be started and overlapped with the programme of the reclamation.

Yau Tong Bay Development (Package 2)

3.9.3                 The construction programme for the foundation/superstructure works at the Yau Tong Bay Development is scheduled from October 2005 to September 2015, which will overlap with the construction period of reclamation works for approximately two years.

3.9.4                 With reference to the EIA Report titled “Yau Tong Bay Development – Engineering Feasibility Study for the Comprehensive Development at Yau Tong Bay”, the mitigated construction noise levels at all NSRs due to the foundation/superstructure works are in the range of 58 - 69 dB(A), which comply with the stipulated noise criteria. The predicted noise levels are summarised in the following Table 3.10.

Table 3.10            Predicted Construction Noise levels at NSRs due to the foundation/ superstructure works of Yau Tong Bay Development (Package 2)

 

Distance to Notional Source

Predicted Mitigated CNLs (dB(A))

 

Criteria

Representative NSRs

Position (m)

Foundation

Superstructure

(dB(A))

RYTE1

180

67

67

75

RYTE2

216

65

65

75

RYCT

300

52

52

75

RCKL

236

60

60

75

REHC1

228

65

65

75

REHC2

156

68

68

75

RSCH1

276

58

58

65/70

RSCH2

190

61

61

65/70

RSCH3

76

69

69

65/70

 


3.9.1                 The cumulative impacts at the NSRs due to the overlap period of the Yau Tong Bay reclamation works and construction works for the Yau Tong Bay Development are presented in Figures 3.6a to 3.6i.  Results indicate that the cumulative noise levels at all of the residential NSRs and RSCH 1 and 2 comply with the construction noise criteria for domestic premises and school during examination over the whole period of reclamation.

3.9.2                 RSCH3 will have cumulative noise levels greater than 65dB(A) after July 2005 and the start of construction of Package 2.  Since the predicted noise levels are within the 70dB(A) criterion for normal school days and noise mitigation measures in the form of upgraded glazing and air-conditioner units are expected to be provided to RSCH3 (Section 3.5.5), the roomside noise levels of the school are considered as acceptable.

Other Developments in Yau Tong Area

3.9.3                 There are a number of planned and committed housing developments in Yau Tong Area, including Yau Tong Estate Development and East Harbour Crossing Housing Estates.  The completion years for the developments are given in Appendix 3D. 

3.9.4                 Noise levels have been predicted at the NSRs based on a sound power level of 121dB(A) for the construction activities at each development. The cumulative construction noise impacts caused by the reclamation of Yau Tong Bay, the construction of Yau Tong Bay Development and the construction of nearby developments are shown in Figures 3.7a – 3.7i and summarised in Appendix 3J.  Results indicate that the predominant noise impact will be caused by the construction activities at the other developments rather than due to the reclamation of Yau Tong Bay.

3.10                   Environmental Monitoring and Audit Requirements

3.10.1              The Environmental Monitoring and Audit (EM&A) programme should include the following:

i)                the collection of noise data;

ii)              the organization and interpretation of the environmental monitoring data to establish a record of change associated with the implementation of the project;

iii)            the verification that the noise levels measured by an environmental monitoring programme in compliance with the regulatory requirements, standards and established environmental quality performance limits;

iv)             the comparison of project impact predictions with actual impacts for the purpose of assessing the accuracy of predictions at the NSRs;

v)               the assessment of the effectiveness of the environmental management systems, practices and procedures;

vi)             event and action plans shall be included and linked to the environmental quality performance.  The determination of the degree and scope of any necessary remedial measures in case of exceedance of compliance, for which environmental monitoring forms the basis, or the recommendation of environmental controls and operations in the event that the organisation’s environmental objectives are not achieved. 


3.10.2              The EM&A Manual will provide a description of the organisational arrangements for the EM&A programme and will stipulate the details of the construction monitoring required and actions to be taken in the event of exceedances.

3.11                   Conclusion

3.11.1              An environmental noise impact assessment on the proposed Yau Tong Bay Development Reclamation has been conducted to predict the future construction noise impacts at the noise sensitive receivers in the Yau Tong neighbourhood.

3.11.2              With the proposed use of quiet plants, reduction of plant operating time and use of movable noise barriers for the reclamation and demolition works, the nearby NSRs will not be adversely affected.

3.11.3              The cumulative assessment indicate that the predominant noise impact will be caused by the construction activities at the other developments rather than due to the reclamation of Yau Tong Bay.

3.12                   References

[1]            Noise Control Ordinance (NCO).

[2]            Environmental Protection Department "Technical memorandum on EIA Process", Sep 1997 (EIA-TM).

[3]            Environmental Protection Department "Technical memorandum on noise from construction work other percussive piling", July 1991 (GW-TM).

[4]            Environmental Protection Department "Technical memorandum on noise from construction work in designated areas", March 1996 (DA-TM).

[5]            Environmental Protection Department "Technical memorandum on noise from percussive piling", June 1997 (PP-TM).