No unacceptable residual impacts are predicted for the construction and operation of the Designated and Potentially Designated Elements of this Project. Table 3.1a summarises the findings of the environmental assessments.
Table 3.1a Summary of Environmental Assessments
|
Construction |
Operation |
Residual Impact |
Project
Description |
· Construction
10km of trunk sewers/rising mains and 7 sewage pumping stations |
· Operations of 7
SPSs · The expansion of
sewers/rising mains networks under the Stage 1 works of this Project to
deliver domestic sewage for treatment at Yuen Long Sewage Treatment Works
will extend coverage area of sewage collection and thus will allow 33% more
sewage flow to be treated.
Untreated sewage would otherwise be discharged to inland waters. |
n/a |
Air
Quality |
With
the implementation of mitigation measures, no adverse construction dust
impacts are envisaged. |
With
the installation of odour removal systems at the sewage pumping stations, no
adverse odour nuisance is envisaged. |
No
adverse residual impact is expected. |
Noise |
The
construction noise assessment indicated that unmitigated sources of
construction noise associated with the proposed development and projects in
the vicinity (ie the non designated elements of this project and Kam Tin Bypass; Yuen Long Bypass Floodway;
Yuen Long, Kam Tin, Ngau Tam Mei and Tin Shui Wan Drainage Improvement Works
Stage 1) would cause exceedances of the daytime construction noise criteria at
the majority of the nearby NSRs.
Mitigation measures such as quiet plant, limiting the use of PME and
movable noise barriers/enclosures have been recommended where appropriate. In view of the close proximity of
some NSRs to the sewer laying works, exceedances are still predicted even
allowing for all practical mitigation measures being implemented. |
Noise impacts due to the proposed sewage pumping stations would not be insurmountable provided that the planning recommendations described in this report are followed. |
Exceedances
of the daytime construction noise criteria are predicted at the following
NSRs: · Scattered House near Kam Tin Shi (D1) · Yuk Yat Garden
Phases II (D4) · Scattered House
in Nam Sang Wai (D12) · Kam Tin Shi
North (D22) · Scattered House
beside Kam Sheung Life Lutheran Church (D30) · Ng Ka Tsuen
(D33) · Planned
Residential Development beside Kam Tsin Wai (A-YL-KTS-174) (D36) · Kam Tsin Wai
(D38) · Kam Kong Villa
(D39) · Planned
Residential Development near Shui Tsan Tin (DPA/YL-KTS/-YL-KTS-82) (D40) |
Water
Quality |
With
the implementation of mitigation measures, no adverse water quality impacts
are envisaged. |
Reductions in
pollutant loads to the streams and watercourses adjacent to the areas to be
connected to the new sewerage system are estimated as follows: · Suspended solids
– 320 kg day-1; · BOD – 340 kg day-1; · COD – 730 kg day-1; · TKN – 70 kg day-1; · Ammonia – 40 kg
day-1; and · E. coli – 3.5x1014 cfu day-1. These
loads represent approximately 10% of the total pollutant loads to the inland
waterways. |
No
residual impact is expected. |
Waste |
With
the implementation of good waste management practices, no adverse waste
management impact is envisaged. |
With
the implementation of good waste management practices, no adverse waste
management impact is envisaged. |
No
residual impact is expected. |
Land
Contamination |
Based
on the available information and the findings of the site inspections, there
is no evidence to suggest that the potentially contaminated sites identified
in this study will be the source of significant off-site migration of
contaminants to the proposed alignment of the sewer and locations of the
pumping stations. |
No
operational impact is expected. |
No
residual impact is expected. |
Ecology |
Direct habitat loss of approximately 0.26 ha cultivated lands of
moderate ecological value, including the proposed location of pumping
stations P4 (0.09 ha), P6 (0.07 ha) and P7 (0.10 ha), approximately 0.15 ha
of abandoned fishpond (P2) and approximately 1.02 ha of urbanised/developed
areas as a result of landtake for the construction and related temporary
storage areas. |
No
operational impact is expected. |
There
will be the loss of 0.15 ha of abandoned and partially filled fishpond with
low impact and other low quality habitats including 0.26 ha of cultivated
land and 1.02 ha of urbanised/disturbed area. No adverse residual impact (direct or indirect) is
expected due to the construction and operation of the sewerage system and
pumping stations after the implementation of the proposed mitigation
measures. |
|
Indirect
impact to the associated fauna, in the sections that the sewer crosses over
the MDC. |
|
|
|
Indirect
impact to the birds inside WCA and WBA due to the increased noise impact,
human activities and disturbance such as storage or dumping of construction
material and construction site runoff. |
|
|
|
Indirect
impact to the surrounding habitats and associated wildlife arising from
increased noise impact, human activities and disturbance such as storage or
dumping of construction material and construction site runoff. |
|
|
Fisheries |
It
is estimated that approximately 0.15 ha of the abandoned fish pond will be
lost through construction of pumping station P2. This impact is not expected
to be of concern as the fish pond is inactive and currently abandoned. |
No
operational impact is expected. |
There
are no residual impacts expected to occur to aquaculture fisheries resources
and operations as a result of the construction and operation of the proposed
sewerage system and pumping stations. |
|
|
|
|
Cultural
Heritage |
No
direct impact to the identified historical buildings or features is expected.
|
No
operational impact is expected. |
No
residual impact is expected. |
|
Set
back of construction works to avoid encroachment of safe margins, attention
of site works to remove underlying obstructions,
careful selection of construction plant and
construction method, structure survey of Ng Ka Tsuen historic compound and vibration monitoring have been
recommended to ensure that the structural integrity of the historic compound
at Ng Ka Tsuen would not be affected by the construction of the Ng Ka Tsuen
Sewage Pumping Station.
Precaution on start up and stopping of pumps and noise radiation is
also recommended to ensure any operational vibration impact is kept to a
minimum. |
|
|
|
No
significant archaeological deposits would be impacted by most of the proposed
sewerage facilities, except Shui Tsan Tin, Ng Ka Tsuen and Pang Ka Tsuen
Sewage Pumping Stations. A six
month period has been recommended to allow for an archaeological field
investigation to be undertaken at each of these proposed pumping station
sites and once the land is resumed and access is gained, but before any
construction takes place.
Mitigation measures agreed with the AMO, should be implemented to
mitigate any potential impacts.
Before undertaking any fieldwork, a qualified archaeologist should
obtain a Licence from the Authority under the Antiquities and Monuments Ordinance (Cap. 53). |
|
|
Landscape
and Visual |
“Significant”
visual impact is predicted at the historic house at Ng Ka Tsuen (1C). “Moderate adverse” landscape impact
is predicted to the Village Development LCU during construction.
“Slight/Moderate Adverse” visual impacts to viewer groups at Sensitive Visual
Receivers (SVR) during construction, at the following locations. ·
Sha Po Tsuen Residential Development (1A); ·
Kam Tin Shi Residential Development (1B); ·
Residential Developments near Shui Tsan Tin SPS (1D); ·
Residential Developments near Pang Ka Tsuen SPS (1E); ·
Residential Development near Leung Uk Tsuen SPS (2A); and ·
Residential Developments west of Pang Ka Tsuen (3D). |
“Significant”
visual impact is predicted at
the historic house at Ng Ka Tsuen (SVR-1C) due to the close proximity
to Ng Ka Tsuen SPS. “Slight/Moderate
Adverse” visual impacts are predicted to those viewer groups at SVRs
identified for the construction phase. The source of the visual impact is
SPSs in proximity to residents during the operation phase of these SPSs. |
The
incorporation of mitigation measures into the Project will be effective in
reducing “Moderate/Significant Adverse” construction impacts in the Village
Development LCU to “Slight Adverse”. The
incorporation of mitigation measures into the Project will be effective in
reducing “Significant” to “Moderate” visual impacts to SVR-1C during
construction and from “Significant” to “Moderate” and “Negligible” visual
impacts at “Day 1” and “Year 10”, respectively during operations. The
incorporation of mitigation measures into the Project will be effective in
reducing “Slight/Moderate Adverse” to “Slight Adverse” visual impacts to
SVRs-1A, 1B and 3D and to “Negligible” to SVRs- 1D, 1E and 2A during
construction and from “Slight/Moderate Adverse” to “Slight adverse” and
“Negligible” visual impacts at “Day 1” and “Year 10”, respectively during
operations. |