5                                            Water Quality

5.1                                      Introduction

This Section addresses the potential impacts on water quality from the construction and operation of the Designated and Potentially Designated Elements of the Project.

 

 

5.2                                      Relevant Legislation and Guidelines

The following relevant pieces of legislation and associated guidance are applicable to the evaluation of water quality impacts associated with the construction and operation of the Designated and Potentially Designated Elements of the Project.

 

·       Water Pollution Control Ordinance (WPCO);

 

·       Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems Inland and Coastal Waters; and

 

·       Environmental Impact Assessment Ordinance (Cap. 499. S.16), Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM), Annexes 6 and 14.

 

Apart from the above statutory requirements, the Practice Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94), issued by ProPECC in 1994, also provides useful guidelines on the management of construction site drainage and prevention of water pollution associated with construction activities.

 

5.2.1                                Water Pollution Control Ordinance

The WPCO is the legislation for the control of water pollution and water quality in Hong Kong.  Under the WPCO, Hong Kong waters are divided into 10 Water Control Zones (WCZs).  Each WCZ has a designated set of statutory Water Quality Objectives (WQOs).  The WQOs set limits for different parameters that should be achieved in order to maintain the water quality within the WCZs.  The Project is wholly located within the Deep Bay WCZ, the boundaries of which are shown on Figure 5.2a.  The WQOs for the Deep Bay WCZ, which are presented in Table 5.2a, are applicable as evaluation criteria for assessing compliance of any effects from the construction and operation of the Project.

 

Table 5.2a       Water Quality Objectives for the Deep Bay Water Control Zone

Water Quality Objectives

Part or parts of Zone

A.    AESTHETIC APPEARANCE

 

a)     Waste discharges shall cause no objectionable odours or discolouration of the water.

 

 

Whole zone

 

b)    Tarry residues, floating wood, articles made of glass, plastic, rubber or of any other substances should be absent.

Whole zone

c)     Mineral oil should not be visible on the surface.  Surfactants should not give rise to a lasting foam.

Whole zone

d)    There should be no recognisable sewage-derived debris.

Whole zone

e)     Floating, submerged and semi-submerged objects of a size likely to interfere with the free movement of vessels, or cause damage to vessels, should be absent.

Whole zone

f)      Waste discharges shall not cause the water to contain substances which settle to form objectionable deposits.

Whole zone

 

B.     BACTERIA

 

 

a)     The level of Escherichia coli should not exceed 610 per 100 mL, calculated as the geometric mean of all samples collected in one calendar year.

b)    The level of Escherichia coli should be zero per 100 mL, calculated as the running median of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days.

c)     The level of Escherichia coli should not exceed 1,000 per 100 mL, calculated as the running median of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days.

d)    The level of Escherichia coli should not exceed 180 per 100 mL, calculated as the geometric mean of all samples collected from March to October inclusive in one calendar year.  Samples should be taken at least 3 times in a calendar month at intervals of between 3 and 14 days.

Secondary Contact Recreation Subzone and Mariculture Subzone.

 

Yuen Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones.

Yuen Long & Kam Tin (Lower) Subzone and other inland waters.

 

 

Yung Long Bathing Beach Subzone.

 

C.    COLOUR

 

 

a)     Waste discharges shall not cause the colour of water to exceed 30 Hazen units.

 

 

b)    Waste discharges shall not cause the colour of water to exceed 50 Hazen units.

Yuen Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones.

Yuen Long and Kam Tin (Lower) Subzone and other inland waters.

 

D.    DISSOLVED OXYGEN

 

 

a)     Waste discharges shall not cause the level of dissolved oxygen to fall below 4 mg per litre for 90% of the sampling occasions during the year; values should be taken at 1 metre below surface.

b)    Waste discharges shall not cause the level of dissolved oxygen to fall below 4 mg per litre for 90% of the sampling occasions during the year; values should be calculated as water column average (arithmetic mean of at least 2 measurements at 1 metre below surface and 1 metre above seabed).  In addition, the concentration of dissolved oxygen should not be less than 2 mg per litre within 2 metres of the seabed for 90% of the sampling occasions during the year.

c)     The dissolved oxygen level should not be less than 5 mg per litre for 90% of the sampling occasions during the year; values should be taken at 1 metre below surface.

d)    Waste discharges shall not cause the level of dissolved oxygen to be less than 4 mg per litre.

Inner Marine Subzone excepting Mariculture Subzone.

 

 

Outer Marine Subzone excepting Mariculture Subzone.

 

 

 

 

 

 

 

 

Mariculture Subzone.

 

 

 

Yuen Long & Kam Tin (Upper and Lower) Subzones, Beas Subzone, Indus Subzone, Ganges Subzone, Water Gathering Ground Subzones and other inland waters of the Zone.

E.     PH

 

 

a)     The pH of the water should be within the range of 6.5 - 8.5 units.  In addition, waste discharges shall not cause the natural pH range to be extended by more than 0.2 units.

b)    Waste discharges shall not cause the pH of the water to exceed the range of 6.5 - 8.5 units.

 

 

c)     The pH of the water should be within the range of 6.0 - 9.0 units.

d)    The pH of the water should be within the range of 6.0 - 9.0 units for 95% of samples.  In addition, waste discharges shall not cause the natural pH range to be extended by more than 0.5 units.

 

Marine waters excepting Yung Long Bathing Beach Subzone.

 

 

Yuen Long & Kam Tin (Upper and Lower) Subzones, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones.

Other inland waters.

 

Yung  Long Bathing Beach Subzone.

 

 

F.     TEMPERATURE

 

 

Waste discharges shall not cause the natural daily temperature range to change by more than 2.0 oC.

 

Whole zone

G.    SALINITY

 

 

Waste discharges shall not cause the natural ambient salinity level to change by more than 10%.

Whole zone

 

H.   SUSPENDED SOLIDS

 

 

a)     Waste discharges shall neither cause the natural ambient level to be raised by 30% nor give rise to accumulation of suspended solids which may adversely affect aquatic communities.

b)    Waste discharges shall not cause the annual median of suspended solids to exceed 20 mg per litre.

Marine waters.

 

 

 

Yuen Long & Kam Tin (Upper and Lower) Subzones, Beas Subzone, Indus Subzone, Ganges Subzone, Water Gathering Ground Subzones and other inland waters.

I.      AMMONIA

 

 

The un-ionized ammoniacal nitrogen level should not be more than 0.021 mg per litre, calculated as the annual average (arithmetic mean).

 

Whole zone

J.      NUTRIENTS

 

 

a)     Nutrients shall not be present in quantities sufficient to cause excessive or nuisance growth of algae or other aquatic plants.

b)    Without limiting the generality of objective (a) above, the level of inorganic nitrogen should not exceed 0.7 mg per litre, expressed as annual mean.

c)     Without limiting the generality of objective (a) above, the level of inorganic nitrogen should not exceed 0.5 mg per litre, expressed as annual water column average (arithmetic mean of at least 2 measurements at 1 metre below surface and 1 metre above seabed).

 

 

Inner and Outer marine Subzones.

 

 

Inner Marine Subzone.

 

 

Outer Marine Subzone.

K.    5-DAY BIOCHEMICAL OXYGEN DEMAND

 

 

a)     Waste discharges shall not cause the 5-day biochemical oxygen demand to exceed 3 mg per litre.

 

b)    Waste discharges shall not cause the 5-day biochemical oxygen demand to exceed 5 mg per litre.

 

Yuen Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones.

Yuen Long and Kam Tin (Lower) Subzone and other inland waters.

L.     CHEMICAL OXYGEN DEMAND

 

 

a)     Waste discharges shall not cause the chemical oxygen demand to exceed 15 mg per litre.

 

 

b)    Waste discharges shall not cause the 5-day chemical oxygen demand to exceed 30 mg per litre.

 

Yuen Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones.

Yuen Long and Kam Tin (Lower) Subzone and other inland waters.

M.   TOXINS

 

 

a)     Waste discharges shall not cause the toxins in water to attain such levels as to produce significant toxic, carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms, with due regard to biologically cumulative effects in food chains and to interactions of toxic substances with each other.

b)    Waste discharges shall not cause a risk to any beneficial uses of the aquatic environment.

Whole zone

 

 

 

 

 

 

Whole zone

 

N.   PHENOLS

 

Phenols shall not be present in such quantities as to produce a specific odour, or in concentration greater than 0.05 mg per litre as C6H5OH.

 

Yung  Long Bathing Beach Subzone.

O.    TURBIDITY

 

 

Waste discharges shall not reduce light transmission substantially from the normal level.

Yung  Long Bathing Beach Subzone.

 

5.2.2                                Technical Memorandum for Effluent Discharges

All discharges during both the construction the operational phases of the Project are required to comply with the Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM) issued under Section 21 of the WPCO.  The TM defines discharge limits to different types of receiving waters.  Under the TM, effluents discharged into the drainage and sewerage systems, inshore and coastal waters of the WCZs are subject to pollutant concentration standards for particular discharge volumes.  Any new discharges within a WCZ are subject to licence conditions and the TM acts as a guideline for setting discharge standards for the licence.  The current discharge licence standards for the Yuen Long STW are shown in Table 5.2b.


Table 5.2b       Current Discharge Licence Standards for the Yuen Long STW

Licence No.

Licence Expiry Date

Flow Rate

(m3 day-1)

SS Concentration

(mg L-1)

BOD Concentration (mg L-1)

3L1/4

30 November 2004

210,000

30

20

 

In addition to the provisions of the TM, the ‘Deep Bay Zero Discharge Policy’ aims to provide protection to the inland and marine water quality of the Deep Bay WCZ.  The policy requires that developments within the Deep Bay catchment areas do not result in an increase in pollution loads to the inland and marine waters.

 

5.2.3                                EIAO-TM

Annexes 6 and 14 of the EIAO-TM provide general guidelines and criteria to be used in assessing water quality issues.

 

 

5.3                                      Existing Environment/Sensitive Receivers

5.3.1                                Inland Waters

The construction and operation of the proposed works for the Project have the potential to affect a number of inland watercourses within the Deep Bay WCZ.  There are two EPD routine water quality monitoring stations along these inland watercourses, one along the Kam Tin River (Station KT2) and one in the Tin Shui Wai Nullah (TSR1), the locations of which are shown in Figure 5.3a. A summary of water quality data for these stations is presented in Table 5.3a.  These data were measured in 1999 and are the most recently published data ([1]).

Table 5.3a       EPD Routine River Water Quality Monitoring Data in the Vicinity of the Project Area

Parameter

Station KT2

Station TSR1

Dissolved Oxygen (mg L-1)

5.5 (1.9 - 14.4)

7.9 (1.4 - 11.6)

PH

7.3 (6.9 - 8.2)

7.7 (7.3 - 8.9)

Suspended Solids (mg L-1)

65 (21 – 100)

29 (6 – 72)

5-day Biochemical Oxygen Demand (mg L-1)

22 (9 - 190)

19 (5 – 41)

Chemical Oxygen Demand (mg L-1)

57 (31 -240)

35 (8 – 56)

Oil & Grease (mg L-1)

1.2 (0.5 -3.0)

0.8 (0.5 - 4.6)

E. coli (cfu 100mL-1)

9,680 (900 - 260,000)

3,590,000 (310,000 - 67,000,000)

Ammonia-nitrogen (mg L-1)

14.00 (2.30 – 21.00)

4.50 (1.40 - 25.00)

Nitrate-nitrogen (mg L-1)

0.27 (0.01 - 2.00)

0.79 (0.01 - 3.00)

Total Kjeldahl Nitrogen (mg L-1)

17.00 (4.50 – 27.00)

7.05 (2.20 – 30.00)

Ortho-phosphate (mg L-1)

0.67  (0.06 - 5.20)

0.63 (0.21 - 3.20)

Total Phosphorous (mg L-1)

1.80 (0.96 -6.50)

1.15 (0.29 - 4.00)

Notes:

1.     Data presented are annual medians of monthly samples, except for E. coli which are in annual geometric means.

2.     Figures in brackets are annual ranges.

3.     Shaded cells indicate exceedance of the WQOs.

 

The above data show that there are a number of breaches of the WQOs for dissolved oxygen, chemical oxygen demand, 5-day biochemical oxygen demand, suspended solids and E. coli  for both monitoring stations.  The main factor contributing to the poor water quality at these two stations is uncontrolled discharges of livestock wastes.  Improvements may be expected in the future due to greater enforcement of livestock waste control measures.

 

In addition to determining compliance with the WQOs, EPD also compiles a Water Quality Index (WQI).  The WQI is based on the key parameters of dissolved oxygen saturation, 5-day biochemical oxygen demand and ammonia-nitrogen.  The river water quality at KT2 was found to be in the WQI category of ‘bad’ for 1999, which is an improvement from 1998, while at Station TSR1 the quality was defined as ‘bad’, which is consistent with earlier years.

 

5.3.2                                Marine Waters

The streams within the Study Area discharge into inner Deep Bay, along the shallow southern shoreline of Deep Bay where there are extensive mud flats.  Tidal current speeds in the area are extremely low, resulting in long residence times for the marine waters.  There is one routine EPD water quality monitoring station located in the vicinity of the discharge locations for the streams which may be affected by the works and the location of the station is shown in Figure 5.3a.  A summary of water quality data for this station is presented in Table 5.3b.  These data were measured in 1999 and are the most recently published data ([2]).

Table 5.3b       EPD Routine Marine Water Quality Monitoring Data in the Vicinity of the Project Area

Water Quality Parameter

Monitoring Station DM1

Temperature (°C)

24.7 (16.1 – 31.7)

Salinity (ppt)

18.0 (5.5 - 26.4)

Dissolved Oxygen (mg L-1)

4.6 (1.8 - 7.7)

5-day Biochemical Oxygen Demand (mg L-1)

3.8 (1.9 - 6.6)

Suspended Solids (mg L-1)

70.8 (19.0 - 180.0)

Total Inorganic Nitrogen (mg L-1)

4.12 (1.28 - 7.95)

Unionised Ammonia (mg L-1)

0.040 (0.01 - 0.071)

Chlorophyll-a (mg L-1)

7.0 (0.2 – 31.0)

E. coli (cfu 100mL-1)

700 (16 - 14,000)

Notes:

1.     Data presented are depth averaged, except as specified.

2.     Data presented are annual arithmetic mean except for E. coli, which are geometric mean values.

3.     Data enclosed in brackets indicate the ranges.

4.     Shaded cells indicate non-compliance with the WQOs for a parameter.

 

In 1999 there were exceedances of the WQOs for dissolved oxygen, total inorganic nitrogen and unionised ammonia.  These measurements reflect the poor state of the water quality in the inner part of Deep Bay, which prompted the implementation of the ‘Deep Bay Zero Discharge Policy’.  A significant trend of increasing nutrient (total inorganic nitrogen and ammonia) and decreasing dissolved oxygen levels has been observed over the last ten years.

 

The marine waters of Deep Bay are heavily affected by discharges from rivers in both Hong Kong and Shenzhen.  The values of suspended sediment concentrations are high compared to other parts of Hong Kong, which may be attributed to the presence of shallow areas with mud flats and the discharges from the rivers.  The relatively high E. coli values (up to 14,000 cfu 100mL-1) show that there is a strong influence from sewage discharges.  Despite the nutrient enrichment of the marine waters at Station DM1, as shown by the high total inorganic nitrogen levels, the concentrations of chlorophyll-a are not shown to be particularly high.  The data for salinity show that during the wet summer months the marine waters are dominated by freshwater discharges and the salinity declines rapidly.

 

5.3.3                                Sensitive Receivers

Inland Waters

There are no specific water quality sensitive receivers identified for the inland waters.  However, the poor quality of these waters, as discussed above, means that the majority of the stream courses would be termed as ‘stressed’ and as such measures should be taken to prevent any impacts from the construction and operation of the Project.  In particular, the sewerage pipes will cross streams or pumping stations and will be built in the immediate vicinity of streams at the following locations, which are shown on Figure 5.3b.

 

·       Shui Tsan Tin;

·       Kam Tsin Wai;

·       Ng Ka Tsuen;

·       Kam Hing Wai; and

·       Nam Sang Wai.

 

It is to be expected that the operation of the project will result in an improvement to the quality of the inland waters by connecting unsewered areas to the Yuen Long STW, where the sewage effluent will be treated prior to discharge.

 

Marine Waters

The closest marine sensitive area which may be affected by the construction and operation of the project works are the Mai Po and Inner Deep Bay Ramsar Site and the Mai Po Marshes and Inner Deep Bay Sites of Special Scientific Interest (SSSI), as shown on Figure 5.3b.  It is to be expected that the Project will result in improvements to the quality of the marine waters in these areas by improving the quality of the inland watercourses which discharge into them.

 

 

5.4                                      Assessment Methodology

5.4.1                                Construction Phase

The assessment of the potential water quality impacts of the various construction activities has been undertaken in a qualitative manner.  Consideration has been given to controlling potentially harmful impacts from the site works and to the use of ‘best practice’ measures to minimise the potential for discharges of pollutants to water courses in the vicinity of the works areas.  The construction activities which have been considered include the construction of pumping stations (site formation and building works), the laying of sewerage pipelines (site formation and trenching) and pipeline crossings of streams.

 

5.4.2                                Operation Phase

The operation of the sewerage mains and pumping stations will result in a reduction of pollution loads to the inland watercourses, through the connection of unsewered areas to the sewerage system and subsequent transport to the Yuen Long STW.  The magnitude of the reduction has been estimated through an analysis of the designs of the sewerage main and pumping stations, which provided information on the quantities of sewage to be transported.  This analysis then enabled a qualitative assessment of the potential improvements to water quality in the affected inland watercourses.

 

The connection of the unsewered areas will result in an increase in the treated sewage effluent flows from the Yuen Long STW to the Shan Pui River, which discharges into inner Deep Bay.  There will be a net decease in the total load to Deep Bay as the increase in treated effluent flows will be offset by the reduction in untreated sewage effluent discharges to the inland watercourses, which are in the upstream/catchment areas of the Shan Pui River.

 

The effects of the increased flows from the Yuen Long STW and the overall reduction in pollutant load on water quality have been quantified using water quality modelling.  The modelling has been undertaken using the Delft 3D water quality model, which was set up and calibrated for Deep Bay as part of the study Deep Bay Water Quality Regional Control Strategy Study.  This detailed model covers the whole of Deep Bay and extends beyond the mouth of the bay, as shown in Figure 5.4a.  Data on pollution loads into Deep Bay are contained within the Pollution Load Inventory from the study Update on Cumulative water Quality and Hydrological Effect of Coastal Development and Upgrading Assessment Tool.  The locations of the sources of polluting discharges to Deep Bay and the surrounding area contained in the Pollution Load Inventory are shown in Figure 5.4b.  The implementation of the Project will result in changes in the loading input at source YL2 (due to connection of unsewered areas to the Yuen Long STW and increasing discharges from the Yuen Long STW).

 

The water quality model has been used to simulate two scenarios:

 

·       A Commissioning Scenario, which simulated the pollution loads following implementation of the Stage 1 works in 2007; and

 

·       A Non-Commissioning Scenario, which simulated the pollution loads in 2007 if the Stage 1 works were not implemented.

 

These two scenarios allowed the water quality conditions after completion of the works and the differences in water quality prior to the construction of the works to be quantified.  Both of these scenarios have been simulated for representative wet and dry season conditions, in order to simulate the seasonal variation in the hydrodynamic/oceanographic conditions in Deep Bay.

 

The loadings for source YL2 (see Figure 5.4b) in the Commissioning Scenario have been derived as part of this Study.  In order to define the future loads the areas to be connected to the Yuen Long STW have been represented by the pumping stations that will transport the flows, the locations of which are shown on Figure 5.4c.  Sources of wastewater discharges include domestic, commercial and industrial effluents.  Data on the future flows and loads transported by the pumping stations to the Yuen Long STW have been

provided by DSD.  The data also include a breakdown of the future domestic, commercial and industrial flows that will not be connected to the STW.  It has been assumed that these flows will be discharged to inland waterways.  In the case of the commercial and industrial flows, it has been assumed that those flows not connected to the STW will undergo treatment prior to discharge to inland waterways.

 

The loadings for source YL2 (see Figure 5.4b) in the Non-Commissioning Scenario have been derived as part of this Study.  In this scenario only the domestic, commercial and industrial effluent discharges from the existing Yuen Long Town cathchment will be connected to the STW.  All other wastewaters will be discharges to inland waterways.  Domestic sewage effluents are assumed to be untreated, while commercial and industrial effluents will receive treatment prior to discharge.

 

There may be a concern arising from the potential for a shut-down of the pumping stations, either through mechanical breakdown or failure of the power supply, to result in a short term discharge of untreated sewage effluent to surface waters.  The designs of the pumping stations, particularly of backup/redundant systems, will be reviewed to determine the potential for failures and, if necessary, additional design features defined to minimise the risk.  In addition, a series of measures will be defined to minimise the duration of untreated sewage effluent discharges, in the unlikely event that a failure were to occur and hence reduce the potential impacts to water quality.

 

5.5                                      Identification of Potential Impacts

5.5.1                                Construction Phase

During construction of the sewers and pumping stations the primary sources of potential impacts to water quality will be from pollutants in site run-off, which may enter surface waters directly or enter storm drains discharging into these waters.  Pollutants, mainly suspended sediments, may also enter these waters if pumped groundwater is not adequately controlled.

 

Wastewater from temporary site facilities should be controlled to prevent direct discharge to surface waters.  Such wastewater may include sewage effluent from toilets.  Water from plant servicing facilities may be contaminated with oil and other petroleum products and would have the potential to discharge to surface waters if spillages are not contained.

 

For the sewer crossings of the Yuen Long and Kam Tin Main Drainage Channels, the sewers will be laid using the trenchless pipe jacking method.  This method avoids direct disturbance of any sediments on the bed of the channels.  However, in the event of malfunction of the tunnelling machine, a rescue pit would be sunk, which would require dredging works.  This could potentially cause localised impacts to water quality, particularly if the sediments are contaminated.  Mitigation measures may be necessary to prevent the transport of sediment in suspension away from the works area.  In addition, embankments along the sides of the channels will need to be removed and reinstated once the sewers have been laid, which could result in spillage of material to the channels.  There may also be the potential for adverse impacts to surface water quality if pumped groundwater is not controlled.

 

At smaller, natural streams (see Figure 5.3b) the sewers will be laid using the open trench method.  In order to allow this work to be undertaken in dry conditions two possible methodologies will be used, as follows:

 

·         For low flows, submersible pumps will be used to bypass the works area; and

·         For higher flows, temporary diversion of the stream will be required, either along a temporary channel or through pipes.

 

These methods of construction will result in minimal impacts to water quality in the streams.  However, there may be the potential for adverse impacts to surface water quality if pumped groundwater is not controlled.

 

5.5.2                                Operation Phase

The operation of the works will result in an improvement to the quality of inland waters through the connection of unsewered areas to sewer mains, thereby removing sources of polluting discharges to streams/watercourses.  The sewer mains will then be connected to the Yuen Long STW, where the effluents will be treated and discharged to the Shan Pui River.  This will result in an increase in treated sewage effluent discharges from the Yuen Long STW, but will not increase the total pollutant load to Deep Bay.  The potential improvements to water quality in Deep Bay, where the affected streams discharge, was demonstrated through the use of water quality modelling.

 

In order to prevent the uncontrolled discharge of untreated sewage effluent to surface waters there will be a need to minimise the risk of failure of the pumping stations.  Measures to minimise the risk could include the provision of standby/redundant pumps and the provision of a back-up power supply.  Despite the provision of such measures the potential for failure may still exist and procedures should be put in place to reduce the duration of the discharge of untreated sewage effluent in order to prevent adverse impacts to surface waters.  Such procedures could include the setting up of a system for early reporting of failures, possibly through the use of telemetry systems to monitor the pumps, and the actioning of timely repairs.

 

 

5.6                                      Assessment of Environmental Impacts

5.6.1                                Construction Phase

The potential impacts of land based construction activities on water quality, as described in Section 5.5.1 may be readily controlled by appropriate on-site measures.  These measures are described in Section 5.7.1 and, as such, no further assessment of impacts has been carried out.  The measures described in Section 5.7.1 are not only sufficient to control/prevent impacts to the water sensitive receivers in the vicinity of the works area, but such controls will also prevent adverse downsteam impacts to both the fresh and marine waters of the Deep Bay WCZ.

 

The methods of construction for the crossings of the main drainage channels and smaller streams will prevent the majority of potential impacts to water quality, as discussed in Section 5.5.1.  However, specific mitigation measures may be required to minimise smaller scale impacts, which are discussed in Section 5.7.1.

 

5.6.2                                Operation Phase

The detailed derivation of the input parameters for the water quality modelling was presented in a Technical Note on Water Quality Modelling Methodology (1), which is contained in Annex B1.

 

The modelling results have been produced as a series of contour plots and statistical analyses of key parameters at selected points.  The contour plots and statistical analyses have been presented in the following formats:

 

·       dissolved oxygen – depth averaged values which are exceeded for 90% of the simulation time;

·       dissolved oxygen – bottom values which are exceeded for 90% of the simulation time;

·       5-day biochemical oxygen demand – depth averaged mean values;

·       total inorganic nitrogen – depth averaged mean values;

·       unionised ammonia – depth averaged mean values;

·       chlorophyll-a – depth averaged mean values;

·       E. coli – depth averaged geometric mean values; and

·       suspended sediment – depth averaged mean values.

 

The above presentation of modelling results will allow a comparison to be made with the relevant Water Quality Objectives for both the Commissioning and Non-Commissioning Scenarios.  The selected output locations are shown in Figure 5.6a and represent the marine waters of Deep Bay and the identified sensitive receivers.

 

The results of the water quality modelling at the selected points are contained in Tables 5.6a and 5.6b for the wet and dry seasons respectively.

 

The data in Tables 5.6a and 5.6b illustrate that the main effects of the commissioning of the works will be in the immediate vicinity of the discharge point YL2 (Station 11).  Further afield the effects of the works are predicted to be minimal, as shown by the lack of difference between the Pre-Commissioning and Commissioning scenarios.  The modelling predicts that there will be increases in dissolved oxygen concentrations and decreases in BOD, E. coli and SS concentrations in the vicinity of the discharge point YL2 at Station 11 in the wet season.  The greatest improvement is in E. coli concentrations, which decrease from a geometric mean of 159,000 to 143,000 cfu 100mL-1.  In the dry season similar improvements in water quality are predicted, although the magnitude of the improvements is generally less, reflecting the lower loads in the dry season.

 


.3b                   Table 5.6a  Wet Season Water Quality Modelling Results

Station

DO (mg L-1)

DO (Bottom) (mg L-1)

BOD (mg L-1)

TIN (mg L-1)

NH3-N (mg L-1)

Chlorophyll-a (µg L-1)

E. coli (cfu 100mL-1)

SS (mg L-1)

 

Base

Comp

Base

Comp

Base

Comp

Base

Comp

Base

Comp

Base

Comp

Base

Comp

Base

Comp

1

4.9

4.9

4.9

4.9

0.7

0.7

1.8

1.8

0.009

0.009

2.1

2.1

129

125

19.1

19.1

2

4.2

4.2

4.1

4.1

1.0

1.0

2.4

2.4

0.017

0.017

2.3

2.4

203

200

23.9

23.9

3

4.0

4.0

3.9

3.9

1.4

1.4

3.3

3.3

0.024

0.024

2.6

2.6

251

249

30.4

30.4

4

2.9

2.9

2.8

2.8

2.6

2.6

5.8

5.8

0.054

0.054

1.9

1.9

1,170

1,170

49.1

49.1

5

5.3

5.3

5.2

5.2

0.6

0.6

1.5

1.5

0.006

0.006

2.1

2.1

85

84

17.3

17.3

6

5.1

5.1

5.0

5.0

0.8

0.8

1.6

1.6

0.008

0.008

2.2

2.2

297

292

18.8

18.8

7

4.5

4.5

4.5

4.5

1.2

1.2

2.2

2.2

0.015

0.015

2.2

2.2

1,730

1,690

23.2

23.2

8

3.7

3.7

3.6

3.6

1.8

1.8

3.1

3.1

0.024

0.024

2.0

2.0

3,560

3,450

29.9

29.9

9

1.4

1.4

1.3

1.3

2.7

2.7

5.4

5.4

0.054

0.054

1.7

1.7

3,100

3,050

47.4

47.4

10

0.0

0.0

0.0

0.0

8.8

8.8

15.3

15.3

0.170

0.170

1.1

1.1

18,700

18,700

127.0

127.0

11

1.6

1.7

1.6

1.7

4.8

4.5

4.5

4.5

0.028

0.028

0.9

0.9

159,000

143,000

33.8

32.8

Notes:

1.        Base refers to the Pre-Commissioning scenario, and Comp refers to the Commissioning scenario.

2.        All values are depth averaged, unless otherwise specified.

3.        DO values are 10%ile.

4.        BOD, TIN, NH3-N, Chlorophyll-a and SS are arithmetic mean values.

5.        E. coli are geometric mean values.

 


Table 5.6b     Dry Season Water Quality Modelling Results

 

Station

DO (mg L-1)

DO (Bottom) (mg L-1)

BOD (mg L-1)

TIN (mg L-1)

NH3-N (mg L-1)

Chlorophyll-a (µg L-1)

E. coli (cfu 100mL-1)

SS (mg L-1)

 

Base

Comp

Base

Comp

Base

Comp

Base

Comp

Base

Comp

Base

Comp

Base

Comp

Base

Comp

1

7.4

7.4

7.4

7.4

2.1

2.1

1.2

1.2

0.004

0.004

16.4

16.5

211

200

18.4

18.4

2

6.9

6.9

7.0

7.0

2.9

2.9

1.8

1.8

0.007

0.007

22.9

22.9

441

428

23.1

23.1

3

6.4

6.4

6.4

6.4

3.8

3.8

2.9

2.9

0.012

0.012

26.3

26.3

1,530

1,520

31.9

31.9

4

3.9

3.9

3.9

3.9

5.7

5.7

5.7

5.7

0.029

0.029

19.3

19.3

9,240

9,220

55.2

55.2

5

7.2

7.2

7.2

7.2

1.9

1.9

1.2

1.2

0.005

0.005

14.3

14.3

227

215

18.1

18.1

6

7.0

7.0

7.0

7.0

2.4

2.4

1.6

1.6

0.007

0.007

17.0

17.0

764

721

20.6

20.6

7

6.3

6.3

6.2

6.3

3.4

3.4

2.4

2.4

0.012

0.012

20.4

20.5

4,390

4,140

27.0

26.9

8

5.1

5.1

5.1

5.1

3.8

3.8

3.0

3.0

0.014

0.014

18.9

18.9

6,570

6,330

32.0

32.0

9

3.8

3.8

3.8

3.8

5.1

5.1

4.8

4.8

0.025

0.025

17.1

17.1

12,100

12,000

47.7

47.7

10

2.2

2.2

2.5

2.5

8.3

8.3

8.6

8.6

0.048

0.048

11.7

11.7

58,700

58,600

83.4

83.3

11

3.1

3.1

3.4

3.4

5.2

5.0

3.7

3.7

0.013

0.013

10.5

10.6

170,000

153,000

31.5

31.0

Notes:

1.        Base refers to the Pre-Commissioning scenario, and Comp refers to the Commissioning scenario.

2.        All values are depth averaged, unless otherwise specified.

3.        DO values are 10%ile.

4.        BOD, TIN, NH3-N, Chlorophyll-a and SS are arithmetic mean values.

5.        E. coli are geometric mean values.

 


Contour plots of the water quality parameters are contained in Annex B2.   The plots show that the major contributor to the water quality conditions in the inner part of Deep Bay is the outflow from the Shenzhen River.  In general, water quality conditions within Deep Bay are worse in the wet season, compared to the dry season.  The contour plots show that there are minimal differences between the Pre-Commissioning and Commissioning scenarios, which reflects the results shown in Tables 5.6a and 5.6b.

 

Overall, the results of the water quality modelling predict that there will be small improvements in the water quality of Deep Bay in the vicinity of the discharge point YL2, which is at the mouth of the Shan Pui River.

 

The operation of the Stage 1 works will result in an improvement in the water quality within the streams and watercourses adjacent to the areas to be connected to the new sewerage system.  This is because currently untreated sewage effluent discharges will be connected to the Yuen Long STW.  Based on the data contained in the Technical Note on Water Quality Modelling Methodology, contained in Annex B1, the reductions in pollutant loads due to the connection of currently unsewered domestic premises are estimated to be as follows:

 

·         Suspended solids – 320 kg day-1;

·         BOD – 340 kg day-1;

·         COD – 730 kg day-1;

·         TKN – 70 kg day-1;

·         Ammonia – 40 kg day-1; and

·         E. coli – 3.5x1014 cfu day-1.

 

These loads represent approximately 10% of the total pollutant loads to the inland waterways.  It may thus be expected that there will be at least a 10% improvement in water quality within the affected waterways.

 

Impacts to water quality may occur due to the uncontrolled discharge of untreated effluent to inland waterways in the event of failure of the pumping stations.  As discussed in Section 5.5.2, the risk of potential impacts may be minimised through the implementation of mitigation measures in the design and operation of the pumping stations.  These measures, which would serve to minimise the risk of failure and facilitate a rapid response in the event of failure, are described in Section 5.7.2.

 

 

5.7                                      Mitigation of Adverse Environmental Impacts

5.7.1                                Construction Phase

Construction phase mitigation measures to prevent the uncontrolled discharge of wastewater from the construction site, in accordance with Practice Note for Professional Persons on Construction Site Drainage, Professional Persons Environmental Protection Department, 1994 (ProPECC PN 1/94) include the use of sediment traps, wheel washing facilities for vehicles leaving the site, adequate maintenance of drainage systems to prevent flooding and overflow, sewage collection and treatment, and comprehensive waste management (collection, handling, transportation, disposal) procedures.

 

Construction Runoff and Drainage

The following measures are recommended for reducing the potential for impacts to water quality from construction run off and site drainage:

 

·                At the start of site establishment, perimeter cut-off drains to direct off-site water around the site should be constructed and internal drainage works and erosion and sedimentation control facilities implemented.  Channels, earth bunds or sand bag barriers should be provided on site to direct stormwater to silt removal facilities.  The design of the temporary on-site drainage system will be undertaken by the contractor prior to the commencement of construction.

 

·                The design of efficient silt removal facilities should be based on the guidelines in Appendix A1 of ProPECC PN 1/94, which states that the retention time for silt/sand traps should be 5 minutes under maximum flow conditions.  Sizes may vary depending upon the flow rate, but for a flow rate of 0.1 m3 s-1 a sedimentation basin of 30m3 would be required and for a flow rate of 0.5 m3 s-1 the basin would be 150 m3.  The detailed design of the sand/silt traps will be undertaken by the contractor prior to the commencement of construction.

 

·                Ideally, construction works should be programmed to minimise surface excavation works during the rainy season (April to September).  All exposed earth areas should be completed and vegetated as soon as possible after earthworks have been completed, or alternatively, within 14 days of the cessation of earthworks where practicable.  If excavation of soil cannot be avoided during the rainy season, or at any time of year when rainstorms are likely, exposed slope surfaces should be covered by tarpaulin or other means.

 

·                The overall slope of the site should be kept to a minimum to reduce the erosive potential of surface water flows, and all trafficked areas and access roads protected by coarse stone ballast.  An additional advantage accruing from the use of crushed stone is the positive traction gained during prolonged periods of inclement weather and the reduction of surface sheet flows.

 

·                All drainage facilities and erosion and sediment control structures should be regularly inspected and maintained to ensure proper and efficient operation at all times and particularly following rainstorms.  Deposited silt and grit should be removed regularly and disposed of by spreading evenly over stable, vegetated areas.

 

·                Measures should be taken to minimise the ingress of site drainage into excavations.  If the excavation of trenches in wet periods is necessary, they should be dug and backfilled in short sections wherever practicable.  Water pumped out from trenches or foundation excavations should be discharged into storm drains via silt removal facilities.

 

·                Open stockpiles of construction materials (for example, aggregates, sand and fill material) of more than 50 m3 should be covered with tarpaulin or similar fabric during rainstorms.  Measures should be taken to prevent the washing away of construction materials, soil, silt or debris into any drainage system.

 

·                Manholes (including newly constructed ones) should always be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris being washed into the drainage system and storm runoff being directed into foul sewers.

 

·                Precautions to be taken at any time of year when rainstorms are likely, actions to be taken when a rainstorm is imminent or forecasted, and actions to be taken during or after rainstorms are summarised in Appendix A2 of ProPECC PN 1/94.  Particular attention should be paid to the control of silty surface runoff during storms events, especially for areas located near steep slopes.

 

·                All vehicles and plant should be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads.  An adequately designed and sited wheel washing bay should be provided at every site exits and wash-water should have sand and silt settled out and removed at least on a weekly basis to ensure the continued efficiency of the process.  The section of access road leading to, and exiting from, the wheel-wash bay to the public road should be paved with sufficient backfall toward the wheel-wash bay to prevent vehicle tracking of soil and silty water to public roads and drains.

 

·                On-site drainage system should be equipped with oil interceptors to separate oil / fuel from contaminated storm water.

 

General Construction Activities

The following measures are recommended for reducing the potential for general construction waste impacts to water quality:

 

·                Construction solid waste, debris and rubbish on site should be collected, handled and disposed of properly to avoid water quality impacts.  Requirements for solid waste management are detailed in Section 6.7 of this Report.

 

·                All fuel tanks and storage areas should be provided with locks and sited on sealed areas, within bunds of a capacity equal to 110% of the storage capacity of the largest tank to prevent spilled fuel oils from reaching water sensitive receivers nearby.

 

Sewage Effluent from Construction Work Force

The following measures are recommend for reducing the potential for impacts to water quality from sewage effluent from construction work force.

 

Construction work force sewage should be handled by portable chemical toilets or sewage holding tanks with the sewage regularly collected by a reputable sewage collector for disposal at for example, Shek Wu Hui STW. 

 

MDC and Stream Crossings

 

The methods of construction of the crossings of the main drainage channels and small streams will prevent adverse impacts to water quality, as discussed in Section 5.5.1.  However, if there are equipment malfunction with the tunnelling machine when crossings of the main drainage channels then a rescue pit may need to be excavated, which could have potential impacts to water quality.  If a rescue pit is necessary then the following mitigation measures should be implemented during excavation.

 

·         Excavation should be undertaken during periods of low tide, when the water level within the main drainage channel is at it lowest; and

 

·         If excavation during periods of high rainfall and/or at times other than low tide is unavoidable then silt curtains should be deployed around the excavation machine to prevent the transport of sediment in suspension beyond the works area.

 

At smaller stream crossings where diversion of the existing flows is required through a temporary channel it is recommended that the temporary channel be lined with shotcrete in order prevent erosion of the channel introducing increased suspended solids into downstream stretches of the stream.  Diversion through temporary pipes would prevent potential impacts of this form.  Diversion of low flows by submersible pumps would not cause adverse impacts as it would simply mean bypassing of the existing stream water around the works area, without introducing additional pollutants.  It is recommended, on a precautionary principal, that silt traps be installed either at the inlets or outlets of the submersible pumps to prevent any suspended solids generated in the vicinity of the works area being introduced into the downstream stretches of the stream.

 

Material excavated from the open trench crossings of streams and from any rescue pits is likely to be stockpiled for disposal.  This material should be covered with impermeable material and placed on an impermeable liner in order to prevent rainfall eroding the material leading to stormwater runoff with high suspended sediment concentrations.  The disposal of excavated materials are discussed in Section 6.5.2.

 

5.7.2                                Operation Phase

The normal operation of the Stage 1 works has been shown to result in an improvement in water quality in both the inland and marine waters of the Deep Bay WCZ and thus no mitigation measures will be required.

 

The following measures should be implemented to reduce the risk of failure of the pumping stations which would result in an emergency discharge of untreated sewage effluent.  Should a failure occur the intention is to minimise the duration.

 

·         The overflow bypass should be operated only in an emergency, such as prolonged power failure.  Overflow must not occur on a regular basis such as to facilitate routine maintenance.

·         Standby pump should be provided to facilitate maintenance and repairing of equipment;

·         Dual (back-up) power supply should be provided.  Dual power supply could be in the format of ring main, or an automatic-operated emergency generator with sufficient capacity to cope with the demand loading of the essential plant equipment;

·         If the pumping station is unmanned, a telemetry system should be provided to the nearest manned station/plant so that swift actions could be taken in the case of malfunction of the unmanned facilities;

·         Hand-cleaned screens should be provided at the overflow bypass to prevent the discharge of floating solids into receiving water bodies.  The clear spacing of the bar screen should normally be about 25mm;

·         The discharge point of the overflow bypass should be below the low water mark; and

·         The discharge point of the overflow bypass should be away from sensitive receivers such as gazetted beaches, mariculture zones, seawater intakes, water gathering grounds, country parks, marinas, boat parks, nature reserves, sites of special scientific interest, marine parks/marine reserves, streams with water for human consumption…etc, and water with low assimilative capacity such as typhoon shelter or embayed water.  In this connection, the location of the overflow bypass should be provided by the project proponent at detail design stage for DEP approval.

 

 

5.8                                      Residual Environmental Impacts

5.8.1                                Construction Phase

No residual water quality impacts were predicted to occur due to construction of the Stage 1 works provided the above described mitigation measures are implemented.

 


5.8.2                                Operation Phase

The operation of the Stage 1 works was predicted to result in improvements to the water quality within the Deep Bay WCZ.  Residual water quality impacts due to uncontrolled discharge of effluents from pumping station failure were not predicted, provided the mitigation measures described in Section 5.7.2 are implemented.

 

 

5.9                                      Environmental Monitoring and Audit

5.9.1                                Construction Phase

The majority of construction of sewers/rising mains and pumping stations will be land based activities.  Any construction activities across natural streams will be several km away from Deep Bay.  Construction activities across the MDC will use the pipe jacking method ie boring a tunnel for the sewers underneath the river bed of the MDC.  Unlike the conventional dredging method for laying the sewers, this method will avoid the release of river sediments under normal operating conditions.  It is not envisaged that adverse water quality impacts will arise, especially with the implementation of the recommended mitigation measures.   No monitoring of water quality would be required during the construction phase.  It is recommended that regular audits of the implementation of the specified mitigation measures, as described in Section 5.7.1, be carried out during the construction phase.

 

Any wastewater discharges from the construction sites will require a WPCO discharge licence to be issued.  It may be that there will be a requirement for monitoring the quality/quantity of the discharges to show compliance with the conditions of the licence.  Such monitoring, however, would not form part of the EM&A programme.

 

5.9.2                                Operation Phase

No monitoring of water quality would be required during the operational phase of the Designated and Potentially Designated Elements.

 

Routine monitoring of the quality of the treated sewage effluent from the Yuen Long STW is currently being carried out by the Drainage Services Department (DSD) in order to satisfy the conditions of the WPCO discharge licence.  Such monitoring would continue following the upgrade/expansion of the STW.  It should be noted that prior to the operation of the Stage 1 works a new discharge licence will be required.  Such monitoring, however, would not form part of the EM&A programme for the Stage 1 works.

 

 

5.10                                  Summary and Conclusions

This Section has addressed the potential impacts on water quality from the construction and operation of the Designated and Potentially Designated Elements of the Project.

 

The construction phase assessment considered the following aspects.

 

·         the potential impacts to inland water quality from the land based construction activities; and

·         the potential impacts to inland water quality from crossings of the main drainage channels and streams.

 

Potential impacts to surface water quality due to land based construction activities would primarily occur due to surface run-off and wastewater generation from within the construction sites, including sewage effluent from the workforce.  The potential impacts may be readily controlled by on-site mitigation measures, which were specified in detail.

 

The proposed construction methods for the crossings of the main drainage channels and streams would be sufficient to avoid adverse impacts to water quality.  However, in case of the possibility of excavation works in the main drainage channel mitigation measures were specified to prevent adverse impacts to water quality.

 

The operation phase assessment considered the following aspects.

 

·         The potential impacts to inland and marine water quality due to the connection of currently unsewered areas to the Yuen Long STW; and

 

·         The potential impacts to inland and marine water quality due to uncontrolled effluent discharges due to failure of pumping stations.

 

Detailed water quality modelling was undertaken to determine the effects on marine water quality of decreasing the discharge of untreated sewage effluent to inland waterways through connection to the Yuen Long STW and the subsequent increases in the treated effluent flows from the Yuen Long STW.  The results of the water quality modelling determined that there would be improvements in marine water quality in the vicinity of the mouth of the Shan Pui River, where the Yuen Long STW discharges.  An assessment of the impacts of the Stage 1 works on inland water quality determined that there would be a 10% reduction in polluting discharges to the inland waterways and that there would thus be an improvement in water quality.

 

Mitigation measures were defined to reduce the risks of failure of pumping stations and to ensure that timely responses are initiated in cases of failure in order to prevent adverse impacts to water quality due to the discharge of untreated sewage effluent.

 

No monitoring of water quality would be required during either the construction or operation phases.  It was recommended that regular audits of the implementation of the specified mitigation measures be carried out during the construction of the Project.

 

                                                                                               Back to Contents



([1]) EPD (2000).  River Water Quality in Hong Kong in 1999.

([2]) EPD (2000).  Marine Water Quality in Hong Kong in 1999.