TABLE OF CONTENT
Purpose of the Manual
Project Description
Environmental Monitoring and Audit Requirements
Project Organisation
Introduction
Construction Noise Monitoring
Operational Phase Noise Monitoring
Mitigation Measures
Introduction
Air Quality Parameters
Monitoring Equipment
Laboratory Measurement / Analysis
Monitoring Locations
Baseline Monitoring
Monitoring of Construction Air Quality Impact
Environmental Quality Performance Limits
Event and Action Plan for Construction Air Quality
Construction Dust Mitigation Measures
Introduction
Water Quality Parameters
Monitoring Equipment
Laboratory Measurement / Analysis
Monitoring Locations
Baseline Monitoring
Impact Monitoring
Event and Action Plan for Water Quality
Water Quality Mitigation Measures
Introduction
Waste Control and Mitigation Measures
Introduction
Ecological Mitigation Measures
Introduction
Baseline Monitoring
Construction and Operational stage Audit
Introduction
Land Contamination Assessment
Mitigation Measures
Site Inspection
Compliance with Legal and Contractual Requirements
Environmental Complaints
General
Baseline Monitoring Report
Monthly EM&A Reports
Quarterly EM&A Summary Reports
Final EM&A Summary Reports
Data Keeping
Interim Notifications of Environmental Quality Limit Exceedances
LIST OF TABLES
Table 2.1 Noise Monitoring Stations during Construction Phase
Table 2.2 Action and Limit Levels for Construction Noise
Table 2.3 Event / Action Plan for Construction Noise
Table 2.4 Noise Monitoring Stations during Operational Phase
Table 3.1 Baseline Monitoring Location
Table 3.2 Action / Limit Levels for Air Quality
Table 3.3 Event / Action Plan for Air Quality
Table 4.1 Action and Limit Levels for Water Quality
Table 4.2 Event and Action Plan for Water Quality
Table 6.1 Examples of Plant Species of Conservation Value to Wildlife for Landscaping Works
Table 7.1 Summary of Disturbance to Landscape Character Units
Table 7.2 Summary of Disturbance to Landscape Elements
Table 7.3 Summary of Landscape Impact (Without Mitigation Measures)
Table 7.4 Summary of Residual Landscape Impacts (With Mitigation Measures)
LIST OF FIGURES
Figure 1.2 Preliminary Construction Programme
Figure 1.3 Project Organisation
Figure 2.1 Locations of Representative Noise Sensitive Receivers
Figure 2.2 Locations of Construction Noise Monitoring Stations
Figure 2.3 Locations of Operational Noise Monitoring Stations
Figure 3.1 Locations of Baseline Monitoring Stations
Figure 4.1 Locations of Water Quality Monitoring Stations
Figure 8.1 Locations of Proposed Zones for Contamination Investigation Work
LIST OF APPENDICES
Appendix A Implementation Schedule
Appendix B Sample Data Sheet for Dust, Noise and Water Quality Monitoring
Appendix C Sample Template for the Interim Notification