4                          NOISE Impact

4.1                    Introduction

4.1.1               This section presents an assessment on the potential noise impacts arising from the proposed Project. During the Stage 1 works period before 2012, based on the latest available information, the existence of planned noise sensitive receivers (NSRs) at the former Kai Tak Airport runway would not be expected. Cumulative daytime construction noise impacts due to nearby construction activities are also assessed for the Stage 2 works in this EIA study.  With reference to the latest information on construction programme, the construction working hours of the Project would be from 0700 to 1900 hours and 6 days a week (not including Sunday and Public Holiday).  In other words, construction activities during restricted hours are not anticipated and noise impact assessment for restricted hours is therefore not included in this assessment.  Noise impact arising from regular maintenance dredging is also assessed.    

4.2                    Environmental Legislation, Policies, Plans, Standards and Criteria

General

4.2.1               Noise impacts have been assessed in accordance with the criteria and methodology given in the Technical Memoranda (TMs) under the Noise Control Ordinance (NCO), and the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).

4.2.2               The NCO and EIAO provide the statutory framework for noise control.  Assessment procedures and standards are set out in five TMs listed below:

l              EIAO-TM

l              TM on Noise from Construction Work other than Percussive Piling (GW-TM)

l              TM on Noise from Percussive Piling (PP-TM)

l              TM on Noise from Construction Work in Designated Areas (DA-TM) 

l              TM on Noise from Places other than Domestic Premises, Public Places or Construction Sites (IND-TM)

Construction Noise – General Construction

4.2.3               The NCO provides the statutory framework for noise control of construction work other than percussive piling using powered mechanical equipment (PME) between the hours of 1900 and 0700 hours or at any time on Sundays and general holiday (that is, restricted hours).  Noise control on construction activities taking place at other times is subject to the Criteria for Evaluating Noise Impact stated in Table 1B of Annex 5 in the EIAO-TM.  The noise limit is Leq (30 minutes) 75 dB(A) at the façades of dwellings and 70 dB(A) at the façade of schools (65 dB(A) during examinations).

4.3                    Project Description and Construction Activities

4.3.1               The Project involves dredging at the existing seawall at the southern tip of the former Kai Tak Airport runway for construction of a quay deck structure for two berths, and dredging the seabed fronting the new quay to provide the necessary manoeuvring basin. 

4.3.2               In accordance with the construction programme of the Project, dredging works would be carried out in two stages covering different areas as indicated in Figure 4.1A.

4.3.3               The construction activities under Stage 1 would be completed before Year 2012.  The construction activities under Stage 2 (dredging activities for the second berth) are currently tentatively scheduled to commence in Year 2012 or later.  The programme for Stage 2 dredging is indicative only and the actual programme would depend on the commissioning programme for the second berth.

4.3.4               As mentioned in Section 2, maintenance dredging is required once every 5 to 10 years during the operation stage of the proposed cruise terminal.

4.4                    Noise Sensitive Receivers

4.4.1               In order to evaluate the construction noise impacts from the Project, representative Noise Sensitive Receivers (NSRs) within the Study Area are identified for assessment.  The area for the noise impact assessment includes all areas within 300 m from the Project boundary.  There are no existing NSRs identified within 300 m from the boundary of the proposed dredging areas.  Based on the latest available information, existence of planned NSRs at the former Kai Tak Airport runway would not be expected before Year 2012. 

4.4.2               As there is no available information on the commissioning year of the planned residential developments at the former Kai Tak Airport runway, as a conservative assumption for the purpose of this assessment, a planned hotel and two planned residential R3 sites which are located within 300m from the dredging works area are assumed to be occupied during the dredging period.  The two planned residential R3 sites are the nearest residential sites to the Stage 2 dredging area.  As the planned hotel would be provided with central air conditioning and would not rely on openable windows for ventilation, adverse construction noise impact at the planned hotel is not anticipated.  Therefore, only the two planned residential sites are taken as NSRs during the dredging works period for the purpose of a conservative assessment.  Table 4.1 summarises the representative NSRs for construction noise impact assessment for the Stage 2 dredging.  The locations of the assessment points for these NSRs are shown in Figure 4.1.   These two selected assessment points have been agreed with EPD on 14 March 2007 according to Section 3.4.6.2 item (iii) (b) of the EIA Study Brief No. ESB-159/2006.

Table 4.1                        RepresentativeNoise Sensitive Receivers for Construction Noise Impact Assessment for Stage 2 Dredging

NSR

Description

Use

Maximum Height* (mPD)

N1

Planned Residential Development (R3 site)

Residential

45

N2

Planned Residential Development (R3 site)

Residential

55

Note: * Information on the number of floors of the planned development is not available at this stage, only maximum height of the development is provided.

 

4.5                    Assessment Methodology

4.5.1               The proposed dredging works is scheduled to be commenced in Year 2009 and to be completed in 2013.  According to the construction programme, there are two work stages.  Stage 1 works (Year 2009 – Year 2011) include dredging activities to facilitate the operation of the first berth.  Stage 2 works (Year 2012 – Year 2013) include dredging activities for the second berth.  The programme for Stage 2 dredging is indicative only and the actual programme would depend on the commissioning programme for the second berth.  The locations of dredging areas are indicated in Figure 4.1. 

4.5.2               All dredging activities including maintenance dredging are planned to be carried out during 0700 to 1900 hours (Monday to Saturday excluding general holidays).  No dredging works would be carried out during restricted hours.

4.5.3               Any construction activities taking place concurrently within 300m of a given NSR are considered to contribute to the cumulative impact at that NSR.  With regard to concurrent projects, the construction works for two building sites of the Kai Tak Development might occur simultaneously with the Stage 2 dredging activities.  One building site would be in the immediately south of NSR N1 namely the Tourism Node at the southern tip of the former Kai Tak Airport runway and one building site immediately north of NSR N2.  Construction activities including basement excavation, bored piling, concreting and superstructure construction were assumed for the purpose of this assessment.  These construction activities are considered to contribute to the cumulative impact at the NSRs and are also included in the assessment.  Noise sources from the areas greater than 300m of a given NSR are excluded from the assessment.  Based on the latest available information, the construction of cruise terminal building would be completed before Year 2012 and therefore would not cause cumulative noise impacts to the representative NSRs during the Stage 2 dredging period.

4.5.4               In accordance with the EIAO-TM, the methodology outlined in the GW-TM has been used for the assessment of construction noise (excluding percussive piling).  Sound Power Levels (SWLs) of the equipment were taken from Table 3 of this TM.  Schedules of powered mechanical equipment (PME) for different construction tasks of the Project and other concurrent construction activities of other projects during normal daytime working hours are presented in Appendix 4.1.  As a worst case scenario, on-time percentage for all PME of each construction activity is assumed to be 100%.  Letter from Project Proponent confirming that the plant inventory is valid for the Project works is attached in Appendix 4.3.

4.5.5               It was assumed that all PME items required for a particular construction activity would be located at the notional or probable source position of the segment where such activity is to be performed.  The assessment is based on the cumulative SWL of PME likely to be used for each location, taking into account the construction period in the vicinity of the receiver location.  To predict the noise level, PME was divided into groups required for each discrete construction task.  The objective was to identify the worst case scenario representing those items of PME that would be in use concurrently at any given time.  The sound pressure level of each construction task was calculated, depending on the number of plant and distance from receivers.  The noise levels at NSRs are then predicted by adding up the SWLs of all concurrent construction tasks.

4.5.6               A positive 3 dB(A) façade correction was added to the predicted noise levels in order to account for the facade effect at each NSR.

4.6                    Identification of Environmental Impacts

4.6.1               In order to evaluate the construction noise impacts from the Project, representative NSRs within the Study Area are identified for assessment.  As mentioned in Section 4.4 above, there are no existing NSRs or planned NSRs located within 300m from the Project boundary during the Stage 1 works period.  The nearest NSRs are located at more than 500m away from the Stage 1 work site, therefore, no adverse impact arising from the Stage 1 dredging works and seawall reconstruction would be expected.

4.6.2               During the Stage 2 works period, potential construction noise impact arising from the Project on the two planned residential developments at the former Kai Tak Airport runway would be expected in additional to the cumulative noise impacts from nearby building construction works.

4.6.3               During operation stage of the proposed cruise terminal, regular maintenance dredging would be carried out once every 5 to 10 years.  Potential noise impact arising from dredging would be expected on the nearest noise sensitive receivers.

4.7                    Prediction and Evaluation of Environmental Impacts

4.7.1               During the Stage 2 works period, no exceedance of the construction noise criteria         (Leq(30 minutes) 75 dB(A)) for residential uses are predicted at the representative NSRs in the absence of mitigation measures during normal daytime working hours.  Details of the construction noise calculations and results are presented in Appendix 4.1.  Results show that the predicted noise levels related to the concurrent construction works of the Project and two building construction projects are in the range of 72 to 74 dB(A).  A summary of the unmitigated construction noise levels at the representative NSRs during normal daytime working hours within the construction period of the Project is listed in Table 4.2.

Table 4.2                        UnmitigatedConstruction Noise Levels at Representative NSRs during Normal Daytime Working Hours for Stage 2 Dredging 

Representative NSRs

Predicted Unmitigated Construction Noise Levels during Normal Daytime Working Hour (dB(A))

N1

73 – 74

N2

72 – 73

 

4.7.2               During operation stage of the proposed cruise terminal, maintenance dredging would be carried out once every 5 to 10 years.  As a conservative impact assessment, maintenance dredging is assumed to be carried out at the manoeuvre basin for berth 2 which is nearer to the NSRs.  The plant to be used in maintenance dredging would include one grab dredger, one derrick lighter and one tug boat.  Details of noise calculation and results are presented in Appendix 4.2.  Results indicate that the predicted noise levels would be in the range of 59 – 60 dB(A) during maintenance dredging.  The NSRs are expected to comply with the construction noise criterion of 75 dB(A).  

 

4.8                    Evaluation of Residual Environmental Impacts

4.8.1               The construction noise levels at all representative residential NSRs are predicted to comply with the noise standards stipulated in the EIAO-TM without implementation of mitigation measures.

4.8.2               In order to further ameliorate the construction noise impacts, good site practices listed below should be adopted by all the Contractors as far as practicable.  Although the noise mitigating effects are not easily quantifiable and the benefits may vary with the site conditions and operating conditions, good site practices are easy to implement and do not impact upon the works schedule.

l          Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction program.

l          Mobile plant, if any, should be sited as far away from nearby NSRs as possible.

l          Machines and plant (such as trucks) that may be in intermittent use should be shut down between works periods or should be throttled down to a minimum.

l          Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from nearby NSRs.

l          Material stockpiles and other structures should be effectively utilised, wherever practicable, in screening noise from on-site construction activities.

4.9                    Environmental Monitoring and Audit

4.9.1               If there are any planned NSRs within 300 m from the works area occupied during the dredging period, an EM&A programme should be implemented during the period(s) with predicted occurrence of noisy activities.  All the recommended mitigation measures for daytime normal working activities should be incorporated into the EM&A programme for implementation during dredging.  Details of the EM&A requirement are provided in the EM&A Manual.

4.10                 Summary

4.10.1           This assessment has predicted the construction noise impacts of the Project during normal daytime working hours, taking into account other concurrent projects within a 300m study area.  Based on the latest available information, there are no existing NSRs identified within 300m from Project boundary and only two representative planned NSRs are identified for assessment during the Stage 2 dredging period as a conservative approach.  Under the unmitigated scenario, the noise levels at all the representative planned residential NSRs would comply with the construction noise standard, and therefore no adverse noise impact is expected.  Good site practices are recommended to further ameliorate the impacts.  A construction noise EM&A programme is recommended to check the compliance of the noise criteria during normal daytime working hours if any planned NSRs within the 300m study area are occupied during the proposed dredging works.

4.10.2           Assessment on noise impact from maintenance dredging was also conducted.  Results indicated that the predicted noise at the nearest NSRs would comply with the construction noise criterion of 75 dB(A).