4                          Water Quality Impact

4.1                    Introduction

4.1.1               Water quality impact during the proposed dredging works will be minimized through implementation of the mitigation measures recommended in the EIA study.  Implementation of regular site audits is recommended to ensure that the recommended mitigation measures are to be properly undertaken during the proposed dredging works.  It can also provide an effective control of any malpractices and therefore achieve continual improvement of environmental performance on site. 

4.1.2               The EIA Report has identified that suspended solids (SS) would be the most critical water quality parameter during the dredging operations.  Marine water quality monitoring for SS and turbidity is therefore recommended to be carried out at selected WSD flushing water intakes.  The monitoring should include baseline and impact monitoring.  The impact monitoring should be carried out during the proposed dredging works for cruise terminal construction.  Monitoring programme to be implemented for protection of the coral communities are provided in Section 7.

4.2                    Monitoring Schedule and Stations

4.2.1               The proposed water quality monitoring stations are shown in Table 4.1 and Figure 4.1.  The monitoring stations proposed in this section are indicative subject to further review before commencement of the water quality monitoring works.  The status and locations of water sensitive receivers and the marine activities may change after issuing this Manual.  If such case exists, the ET Leader shall propose updated monitoring locations and seek approval from the IEC and EPD.

4.2.2               It is proposed to monitor the water quality at seven WSD flushing water intakes along the seafront of the Victoria Harbour.

Table 4.1   Proposed Marine Water Quality Stations for Baseline and Impact Monitoring

Station

WSD Flushing Water Intake

Easting

Northing

WSD9

Tai Wan

838132.71

817798.61

WSD10

Cha Kwo Ling

841528.70

817713.39

WSD15

Sai Wan Ho

841194.35

816520.20

WSD17

Quarry Bay

839863.48

817077.46

WSD21

Wan Chai

836242.94

815999.00

WSD19

Sheung Wan

832488.01

816911.92

 

4.3                    Baseline Monitoring

4.3.1               Baseline conditions for marine water quality should be established and agreed with EPD prior to the commencement of marine works.  The purpose of the baseline monitoring is to establish ambient conditions prior to the commencement of the dredging works and to demonstrate the suitability of the proposed monitoring stations.

4.3.2               The baseline conditions should be established by measuring turbidity and suspended solids (SS) levels at the seven selected monitoring stations.  The baseline monitoring schedule should be submitted to EPD at least 4 weeks before commencement of monitoring for agreement.  EPD should also be notified immediately for any changes in schedule.

4.3.3               The measurements should be taken at all designated monitoring stations, 3 days per week, at mid-flood and mid-ebb tides, for at least 4 weeks prior to the commencement of dredging works.  There should not be any marine construction activities in the vicinity of the stations during the baseline monitoring.  The interval between 2 sets of monitoring should not be less than 36 hours.  Duplicate in-situ measurements and water sampling should be carried out in each sampling event.  For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5 m.

4.3.4               The baseline monitoring report should be submitted to EPD at least 4 weeks before the commencement of the dredging works for agreement.  The baseline monitoring report should be certified by the IEC before submission to EPD.

4.4                    Impact Monitoring

4.4.1               During the period of dredging, monitoring should be undertaken three days per week, at mid-flood and mid-ebb tides, with sampling / measurement at the designated monitoring stations as shown in Table 4.1.  Silt screens are recommended to be deployed at these intakes during the dredging period.  It is recommended to conduct the monitoring behind the silt screens and at the appropriate vertical levels of the abstraction points of these intakes to collect information on the mitigated water quality condition if practicable.

4.4.2               The interval between two sets of monitoring should not be less than 36 hours except where there are exceedances of Action and/or Limit Levels, in which case the monitoring frequency will be increased.  Table 4.2 shows the proposed monitoring frequency and water quality parameters.  Duplicate in-situ measurements and water sampling should be carried out in each sampling event.  For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5 m.

Table 4.2   Proposed Marine Water Quality Monitoring Frequency and Parameters

Activities

Monitoring Frequency Note 1

Key Parameters Note 2

During the 4-week baseline monitoring period

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS)

During dredging works for proposed cruise terminal at Kai Tak

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS)

Notes:               

1.      For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5 m.

2.      Turbidity should be measured in situ whereas SS should be determined by laboratory. 

 

4.4.3               The proposed water quality monitoring schedule should be submitted to EPD at least 1 week before the first day of the monitoring.  EPD should also be notified immediately for any changes in schedule.  If the monitoring data collected at the flushing water intakes indicate that the Action or Limit Levels as shown in Table 4.4 are exceeded, appropriate actions should be taken in accordance with the Event and Action Plan in Table 4.5.

Regular Maintenance of Silt Screens

 

4.4.4               Silt screens are recommended to be deployed at the WSD flushing water intakes during the dredging period.  Installation of silt screens at the seawater intake points may cause a potential for accumulation and trapping of pollutants, floating debris and refuse behind the silt screens and may lead to potential water quality deterioration at the seawater intake points.  Major sources of pollutants and floating refuse include the runoff and storm water discharges from the nearby coastal areas.  As a mitigation measure to avoid the pollutant and refuse entrapment problems and to ensure that the impact monitoring results are representative, regular maintenance of the silt screens and refuse collection should be performed at the monitoring stations at regular intervals on a daily basis.  The Contractor should be responsible for keeping the water behind the silt screen free from floating rubbish and debris during the impact monitoring period. 

4.5                    Site Audits

4.5.1               Implementation of regular site audits is to ensure that the recommended mitigation measures are to be properly undertaken during the proposed dredging works.  It can also provide an effective control of any malpractices and therefore achieve continual improvement of environmental performance on site.

4.5.2               Site audits should be carried out by the ET and should be based on the mitigation measures for water pollution control recommended in Appendix C.  In the event that the recommended mitigation measures are not fully or properly implemented, deficiency should be recorded and reported to the site management.  Suitable actions are to be carried out to:

·    investigate the problems and the causes;

·    issue action notes to the Contractor who is responsible for the works;

·    implement remedial and corrective actions immediately;

·    re-inspect the site conditions upon completion of the remedial and corrective actions; and

·    record the event and discuss with the Contractor for preventive actions.

4.6           Field Log

4.6.1               Other relevant data should also be recorded, including monitoring location / position, time, water depth, sampling depth, pH, salinity, DO saturation, water temperature, tidal stages, weather conditions and any special phenomena or work underway nearby. 

4.6.2               A sample data record sheet is shown in Appendix B for reference.

4.7           Monitoring Equipment

Dissolved Oxygen and Temperature Measuring Equipment

 

4.7.1               The instrument should be a portable and weatherproof DO measuring instrument complete with cable and sensor, and use a DC power source.  The equipment should be capable of measuring:

·    a DO level in the range of 0 ‑ 20 mg L-1 and 0 ‑ 200% saturation; and

·    a temperature of 0 ‑ 45 degree Celsius.

 

4.7.2               It should have a membrane electrode with automatic temperature compensation complete with a cable (for example, YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved similar instrument).  Sufficient stocks of spare electrodes and cables should be available for replacement where necessary.

4.7.3               Should salinity compensation not be built-in to the DO equipment, in-situ salinity should be measured to calibrate the DO equipment prior to each DO measurement.

Turbidity Measurement Instrument

 

4.7.4               Turbidity should be measured in situ by the nephelometric method.  The instrument should be portable and weatherproof using a DC power source complete with cable, sensor and comprehensive operation manuals.  It should have a photoelectric sensor capable of measuring turbidity between 0 - 1000 NTU (for example, Hach model 2100P or an approved similar instrument).  The cable should not be less than 25m in length.  The meter should be calibrated in order to establish the relationship between NTU units and the levels of suspended solids.  The turbidity measurement should be carried out on split water sample collected from the same depths of suspended solids samples.

Sampler

 

4.7.5               A water sampler is required.  It should comprise a transparent PVC cylinder, with a capacity of not less than 2 litres, which can be effectively sealed with latex cups at both ends.  The sampler should have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (for example, Kahlsico Water Sampler or an approved similar instrument).

Water Depth Detector

 

4.7.6               A portable, battery-operated echo sounder should be used for the determination of water depth at each designated monitoring station.  This unit can either be hand held or affixed to the bottom of the work boat, if the same vessel is to be used throughout the monitoring programme.

Salinity

 

4.7.7               A portable, salinometer capable of measuring salinity in the range 0 – 40 mg/L shall be provided for measuring salinity of the water at each monitoring location.

Sample Containers and Storage

 

4.7.8               Water samples for SS should be stored in high density polythene bottles, packed in ice (cooled to 4°C without being frozen) and delivered to the laboratory and analysed as soon as possible after collection.  Sufficient volume of samples should be collected to achieve the detection limit.

Monitoring Position Equipment

 

4.7.9               A hand-held or boat-fixed type digital Differential Global Positioning System (DGPS) with way point bearing indication or other equipment instrument of similar accuracy, should be provided and used during water quality monitoring to ensure the monitoring vessel is at the correct location before taking measurements.  DGPS or the equivalent instrument, calibrated at appropriate checkpoint (e.g. Quarry Bay Survey Nail at Easting 840683.49, Northing 816709.55) should be provided and used to ensure the monitoring station is at the correct position before taking measurement and water samples.

Calibration of In-Situ Instruments

 

4.7.10           All in-situ monitoring instruments should be checked, calibrated and certified by a laboratory accredited under HOKLAS or any other international accreditation scheme before use and subsequently re-calibrated at three monthly intervals throughout all stages of the water quality monitoring programme.  Responses of sensors and electrodes should be checked with certified standard solutions before each use.  Wet bulb calibration for a DO meter should be carried out before measurement at each monitoring location.

4.7.11           For the on site calibration of field equipment, the BS 127:1993, Guide to Field and On-Site Test Methods for the Analysis of Water should be observed.

4.7.12           Sufficient stocks of spare parts should be maintained for replacements when necessary. Backup monitoring equipment should also be made available so that monitoring can proceed uninterrupted even when some equipment is under maintenance, calibration, etc.

4.8                    Laboratory Measurement / Analysis

4.8.1               Analysis of SS level should be carried out in a HOKLAS or other international accredited laboratory.  Sufficient water samples of not less than 1 liter should be collected at the monitoring stations for carrying out the laboratory SS determinations.  The suggested testing method and lowest detection limit are provided in Table 4.3.

Table 4.3       Analytical Methods to be applied to Marine Water Quality Samples

 

Determinant

Suggested Method

Suggested Detection Limit

Suspended solids

APHA 2540D*

1 mg L-1

* APHA American Public Health Association Standard Methods for the Examination of Water and Wastewater

 

4.8.2               The testing of SS should be HOKLAS accredited (or if not, approved by EPD) and comprehensive quality assurance and control procedures in place in order to ensure quality and consistency in results.

4.8.3               The ET should provide the Contractor with on copy of the relevant chapters of the “Standard Methods for the Examination of Water and Wastewater” updated edition and any other relevant document for his reference.

4.8.4               Detailed testing methods, pre-treatment procedures, instrument use, Quality Assurance / Quality Control (QA/QC) details (such as blank, spike recovery, number of duplicate samples per batch, etc.), detection limits and accuracy should be submitted to EPD for approval prior to the commencement of monitoring programme.  EPD may also request the laboratory to carry out analysis of known standards provided by EPD for quality assurance. The QA/QC should be in accordance with the requirement of HOKLAS or international accredited scheme.  The QA/QC results should be reported.  The testing methods and related proposal should be checked and certified by IEC before submission to EPD for approval.

4.8.5               Additional duplicate samples may be required by EPD for inter laboratory calibration. Remaining samples after analysis should be kept by the laboratory for 3 months in case repeat analysis is required.  If in-house or non-standard methods are proposed, details of the method verification may also be required to submit to EPD.  In any circumstance, the sample testing should have comprehensive quality assurance and quality control programmes.  The laboratory should prepare to demonstrate the programmes to EPD or EPD’s representatives when requested.

4.9                    Event and Action Plan

4.9.1               The water quality assessment criteria, namely Action and Limit Levels are shown in Table 4.4.  If the monitoring results of the water quality parameters at any designated monitoring stations indicate that the water quality assessment criteria are exceeded, the actions in accordance with the Event and Action Plan in Table 4.5 should be carried out. 

4.9.2               The ET Leader should assess the potential dredging impacts on the seawater intakes based on the monitoring data.  The performance of the environmental management system (i.e. of the overall EM&A programme) should be reviewed by the ET Leader on a quarterly basis.  The findings of this review should be included in the quarterly EM&A summary reports, together with any recommendations to improve the performance of the EM&A programme.

Table 4.4  Action and Limit Levels for Marine Water Quality at the WSD Flushing Water Intakes

Parameters

Action

Limit

SS in mg L-1

95 percentile of baseline data See Note 1 or 10 mg/l

99 percentile of baseline data See Note 1 or 10 mg/l

Turbidity in NTU

95 percentile of baseline data See Note 1

99 percentile of baseline data See Note 1

Remarks:  1.      It is recommended to conduct the monitoring behind the silt screens and at the   appropriate vertical levels of the abstraction points of these intakes.

2.          For turbidity and SS, non-compliance of the water quality limits occurs when monitoring result is higher than the limits. 

3.          All the figures given in the table are used for reference only and EPD may amend the figures whenever it is considered as necessary.

Note 1:      More than 1 set of baseline data should be derived to take account the seasonal fluctuation of the background SS level (refer to Section 4.9.3).

 

4.9.3               The proposed dredging works would likely cover both dry and wet seasons. Given the rather short duration for baseline data collection (refer to Section 4.3), it is recommended that the EPD routine marine water quality monitoring data at the relevant stations should be used to determine the monthly variation of the SS level in the Victoria Harbour.  The monthly SS pattern derived from the EPD monitoring data should be used to adjust the baseline data collected at the intake points to take account the seasonal fluctuation in the background SS level. At least two sets of Action and Limit levels (for dry and wet seasons respectively) should be derived for each intake. The ET should approach the Water Quality Assessment Section of EPD for the data.

4.10                 Mitigation of Adverse Environmental Impacts

4.10.1           Mitigation measures for water quality control have been recommended in the EIA Report.  The Contractor should be responsible for the design and implementation of these measures.

4.10.2           Recommended mitigation measures to minimize the adverse impacts on water quality during the proposed dredging are listed in the implementation schedule given in Appendix C.


Table 4.5  Event and Action Plan for Marine Water Quality

EVENT

ACTION

 

ET

IEC

ER

CONTRACTOR

Action level being exceeded by one sampling day

 

1.   Repeat in-situ measurement to confirm findings;

2.   Identify source(s) of impact;

3.   Inform IEC and Contractor;

4.   Check monitoring data, all plant, equipment and Contractor's working methods;

5.   Discuss mitigation measures with IEC and Contractor;

6.   (The above actions should be taken within 1 working day after the exceedance is identified)

7.   Repeat measurement on next day of exceedance.

1.   Discuss with ET and Contractor on the mitigation measures;

2.   Review proposals on mitigation measures submitted by Contractor and advise the ER accordingly;

3.   Assess the effectiveness of the implemented mitigation measures.

4.   (The above actions should be taken within 1 working day after the exceedance is identified)

 

1.   Discuss with IEC on the proposed mitigation measures;

2.   Make agreement on the mitigation measures to be implemented.

3.   (The above actions should be taken within 1 working day after the exceedance is identified)

 

1.  Inform the ER and confirm notification of the non-compliance in writing;

2.  Rectify unacceptable practice;

3.  Check all plant and equipment;

4.  Review the working methods and consider additional measures such as use of frame-type silt curtain, deployment of double silt curtains, slowing down, or rescheduling of works;

5.  Discuss with ET and IEC and propose mitigation measures to IEC and ER;

6.  Implement the agreed mitigation measures.

7.  (The above actions should be taken within 1 working day after the exceedance is identified)

Action level being

exceeded by more

than one

consecutive

sampling days

 

1.   Identify source(s) of impact;

2.   Inform IEC and Contractor;

3.   Check monitoring data, all plant, equipment and Contractor's working methods;

4.   Discuss mitigation measures with IEC and Contractor;

5.   Ensure mitigation measures are implemented;

6.   Prepare to increase the monitoring frequency to daily;

7.   (The above actions should be taken within 1 working day after the exceedance is identified)

8.   Repeat measurement on next working day of exceedance.

 

1.   Discuss with ET and Contractor on the mitigation measures;

2.   Review proposals on mitigation measures submitted by Contractor and advise the ER accordingly;

3.   Assess the effectiveness of the implemented mitigation measures.

4.   (The above actions should be taken within 1 working day after the exceedance is identified)

 

1.   Discuss with IEC on the proposed mitigation measures;

2.   Make agreement on the mitigation measures to be implemented;

3.   Assess the effectiveness of the implemented mitigation measures.

4.   (The above actions should be taken within 1 working day after the exceedance is identified)

 

1.  Inform the Engineer and confirm notification of the non-compliance in writing;

2.  Rectify unacceptable practice;

3.  Check all plant and equipment;

4.  Review the working methods and consider additional measures such as use of frame-type silt curtain,  deployment of double silt curtains, slowing down, or rescheduling of works;

5.  Discuss with ET and IEC and propose mitigation measures to IEC and ER within 3 working days;

6.  Implement the agreed mitigation measures.

7.  (The above actions should be taken within 1 working day after the exceedance is identified)

Limit level being

exceeded by one sampling day

 

1.  Repeat in-situ measurement to confirm findings;

2.  Identify source(s) of impact;

3.  Inform IEC, Contractor and EPD;

4.  Check monitoring data, all plant, equipment and Contractor's working methods;

5.  Discuss mitigation measures with IEC, ER and Contractor;

6.  Ensure mitigation measures are implemented;

7.  Increase the monitoring frequency to daily until no exceedance of Limit Level.

8.  (The above actions should be taken within 1 working day after the exceedance is identified)

 

 

1.   Discuss with ET and Contractor on the mitigation measures;

2.   Review proposals on mitigation measures submitted by Contractor and advise the ER accordingly;

3.   Assess the effectiveness of the implemented mitigation measures.

4.   (The above actions should be taken within 1 working day after the exceedance is identified)

 

1.   Discuss with IEC, ET and Contractor on the proposed mitigation measures;

2.   Request Contractor to critically review the working methods;

3.   Make agreement on the mitigation measures to be implemented;

4.   Assess the effectiveness of the implemented mitigation measures.

5.   (The above actions should be taken within 1 working day after the exceedance is identified)

 

1.  Inform the Engineer and confirm notification of the non-compliance in writing;

2.  Rectify unacceptable practice;

3.  Check all plant and equipment;

4.  Review the working methods and consider additional measures such as use of frame-type silt curtain, deployment of double silt curtains, slowing down, or rescheduling of works;

5.  Discuss with ET, IEC and ER and propose mitigation measures to IEC and ER within 3 working days;

6.  Implement the agreed mitigation measures.

7.  (The above actions should be taken within 1 working day after the exceedance is identified)

Limit level being exceeded by more than one consecutive sampling days

1.   Identify source(s) of impact;

2.   Inform IEC, Contractor and EPD;

3.   Check monitoring data, all plant, equipment and Contractor's working methods;

4.   Discuss mitigation measures with IEC, ER and Contractor;

5.   Ensure mitigation measures are implemented;

6.   Increase the monitoring frequency to daily until no exceedance of Limit level for two consecutive days.

7.   (The above actions should be taken within 1 working day after the exceedance is identified)

 

 

1.   Discuss with ET and Contractor on the mitigation measures;

2.   Review proposals on mitigation measures submitted by Contractor and advise the ER accordingly;

3.   Assess the effectiveness of the implemented mitigation measures.

4.   (The above actions should be taken within 1 working day after the exceedance is identified)

 

1.   Discuss with IEC, ET and Contractor on the proposed mitigation measures;

2.   Request Contractor to critically review the working methods;

3.   Make agreement on the mitigation measures to be implemented;

4.   Assess the  effectiveness of the implemented mitigation measures;

5.   Consider and instruct, if necessary, the Contractor to slow down or to stop all or part of the marine work until no exceedance of Limit level.

6.   (The above actions should be taken within 1 working day after the exceedance is identified)

 

1.  Inform the ER and confirm notification of the non-compliance in writing;

2.  Rectify unacceptable practice;

3.  Check all plant and equipment;

4.  Review the working methods and consider additional measures such as use of frame-type silt curtain,  deployment of double silt curtains, slowing down, or rescheduling of works;

5.  Discuss with ET , IEC and ER and propose mitigation measures to IEC and ER within 3 working days;

6.  Implement the agreed mitigation measures;

7.  As directed by the Engineer, to slow down or to stop all or part of the marine work or construction activities.

8.  (The above actions should be taken within 1 working day after the exceedance is identified)