5                          Waste Management Implications

5.1                    Introduction

5.1.1               Waste management will be the Contractor’s responsibility to ensure that all wastes produced during the dredging operation are handled, stored and disposed of in accordance with good waste management practices and EPD’s regulations and requirements.  The Contractor will be required to ensure that loss of dredged material does not take place during transportation of the material in barges to the designated marine disposal ground.

5.1.2               Other waste materials generated during the dredging operation, such as construction and demolition (C&D) material and chemical wastes, are recommended to be audited at regular intervals (at least quarterly) to ensure that proper storage, transportation and disposal practices are being implemented.  This audit will ensure that solid and liquid wastes are not disposed of into the surrounding marine waters.  The Contractor will also be responsible for the implementation of mitigation measures to minimise waste or redress problems arising from the waste materials.

5.2                    Waste Control and Mitigation Measures

5.2.1               Table 5.1 provides a summary of the various waste types likely to be generated during the dredging operation, together with the recommended handling and disposal methods.  The implementation schedule of the recommended waste control and mitigation measures is presented in Appendix C.

Table 5.1                        Summary of Waste Handling Procedures and Disposal Routes 

Waste Type

Generated from Works Item

Total Quantity Generated

Quantity to be disposed off-site / re-used

Handling

Disposal

Capital Dredging

C&D Material 

 

Removal of existing seawall by dredging

 

 

322,300 m3  rock fill / rock armour / general fill

 

322,300 m3  of C&D material to be disposed off-site

C&D material should be reused as far as practicable

Dust and water quality mitigation measures

(Appendix C)

Inert C&D material to be disposed off-site to the designated public fill reception facility

C&D material should be reused as far as practicable

Dredged Sediment

Dredging of seabed in the proposed manoeuvring basin (Category H and Category M sediment)

430,000 m3

Stage 1: 210,000 m3 & Stage 2: 220,000m3

430,000 m3

(Stage 1: 210,000m3 & Stage 2: 220,000m3)

Dust, odour, noise , water quality mitigation measures

(Appendix C)

Type 1 – Open Sea Disposal (Dedicated Sites) or Type 2 - Confined Marine Disposal at disposal site(s) to be allocated by MFC

Dredging of seabed in the proposed manoeuvring basin (Category L sediment)

950,000 m3

Stage 1: 490,000m3 (including 20,000m3 from removal of the Kai Tak Runway submarine outfall) &

Stage 2: 460,000m3

950,000 m3

(Stage 1: 490,000m3 & Stage 2: 460,000m3)

Type 1 - Open Sea Disposal - gazetted marine disposal ground allocated by MFC

Removal of existing seawall by dredging

None

None

-

-

Chemical Wastes

Cleansing fluids, solvent, lubrication oil and fuel from construction plant and equipment

Few cubic metres per month (preliminary estimate)

Few cubic metres per month (preliminary estimate)

Recycle by licensed companies

Stored on-site within suitably designed containers

(Appendix C)

Chemical Waste Treatment Facility or other licensed facility

General Refuse

Waste paper, discarded containers, etc. generated from workforce

Approx. 13 kg per day (preliminary estimate based on workforce of 20)

Approx. 13 kg per day

Provide on-site refuse collection points (Appendix C)

Refuse station for compaction and containerisation and then to landfill

Maintenance Dredging

Dredged Sediment

Sediment quality to be determined by sediment sampling and testing under the requirements of the ETWB TCW No. 34/2002 

Approx. 350,000 m3 every 5 to 10 years

Approx. 350,000 m3 every 5 to 10 years

Dust, odour, noise , water quality mitigation measures

(Appendix C)

 

MFC would formally allocate marine disposal space in accordance with ETWB TCW No. 34/2002.

Chemical Wastes

Cleansing fluids, solvent, lubrication oil and fuel from construction plant and equipment

Few cubic metres per month (preliminary estimate)

Few cubic metres per month (preliminary estimate)

Recycle by licensed companies

Stored on-site within suitably designed containers

(Appendix C)

Chemical Waste Treatment Facility or other licensed facility

General Refuse

Waste paper, discarded containers, etc. generated from workforce

Approx. 13 kg per day (preliminary estimate based on workforce of 20)

Approx. 13 kg per day

Provide on-site refuse collection points (Appendix C)

Refuse station for compaction and containerisation and then to landfill