In accordance with
the requirements of Section 3.3 of
the EIA Study Brief, this Section
describes the need for the Project and the consideration of alternative
construction methods and work sequence.
As highlighted in Section 1, traffic queues are already
observed on the northern and southern approaches of POR during the evening peak
period. The situation will likely
deteriorate further when the nearby development is in place. The tailback of traffic on the
southbound carriageway of the northern approach may block the through traffic
from Tai Lam Tunnel / NT North to Tuen Mun / Tin Shui Wai / the
The objective of
the Project is to relieve the traffic pressure and traffic queues of the
existing POR so that its design flow / capacity ratio can be maintained at a
reasonable value acceptable to the Transport Department (TD).
In accordance with
the Traffic Impact Assessment Report([1]), the Ratios of
Flow to Capacity (RFC) of POR are 0.84 and 0.99 during AM and PM Peaks for the
Year 2006, respectively. As
demonstrated by the RFC, POR has almost reached its capacity in Year 2006. With the proposed improvement works, the
RFC could be reduced from 1.05 to 0.57 and 1.22 to 0.78 in Year 2011 for the AM
and PM Peaks, respectively.
The proposed improvement works were shown to be capable of relieving the
queuing problem at POR.
3.3
Considerations of Alternative Construction Methods and Work
Sequence
Different construction methods for the
foundation works, erection of the new flyover deck and retaining structures are
examined based on the following criteria:
·
Severity
and duration of the construction impacts on the nearby environmental sensitive
receivers;
·
Traffic
impacts on the existing carriageways;
·
Site
constraints, such as limited working spaces, unforeseen ground conditions and
potential impacts on the existing structures;
·
Satisfaction
to the design requirements, such as loading requirements and retained heights;
and
·
Tight
construction programme.
3.3.1
Options for Piling
Four piling options have been assessed during
preliminary design, namely,
·
Option
A: Continuous Flight
Auger Piles;
·
Option
B: Large Diameter
Bored Piles;
·
Option
C: Pre-bored Concrete
Piles; and
·
Option
D: Driven Steel
H-piles.
The above options are considered common
piling methods in Hong Kong and therefore the required machinery should be
available in the
Option A:
Continuous Flight Auger (CFA) Piles
In this
construction method, continuous flight auger is used to form the pile holes,
which will be infilled with concrete or grout after the placing of steel
reinforcement which would either be steel H-piles or rebar cages. The sizes of CFA piles range from 300mm
to 700mm in diameter and the most common pile size is 610mm in diameter.
Benefits
·
Piles can be installed without appreciable noise and
vibration;
·
Generally ground loss/disturbance is minimal during
pile hole excavation and therefore less disturbance on the adjacent structures
and piles;
·
Compared with Options B and C, it is a more economic
pile construction method under suitable ground condition (i.e. for cohesive
soils) and satisfying load requirements;
·
Less working spaces are required compared with Option
B;
·
Construction time is relatively fast; and
·
There is no restriction on the normal working hours.
Drawbacks
·
Pre-excavation or pre-boring may be required to cope
with any underground obstruction such as boulders within the soil matrix;
·
Compared
with Option B, this pile type has less structural capacities to resist lateral
and vertical loads;
·
Specialist
contractor may be required to ensure workmanship; and
·
Designed
pile length is limited by the construction plants and it is generally less than
40m.
Option B: Large Diameter Bored Piles
Shafts of the large diameter bored piles
are constructed by traditional boring machines with temporary steel casings or
drilling fluid as a supporting system. Chisel and grab system with casings, and
Reverse Circulation Drilling (RCD) are the common large bored pile construction
plants. Typical sizes of large diameter bored piles range from 1m to 3m in
diameter. In
Benefits
·
Extensive experience of using this type of
construction method has been developed in
·
Compared with Options C and D, less noise and vibration
will be generated during pile installation;
·
It is relatively easy to overcome underground
obstructions;
·
Compared with Option A, this construction method has
higher flexibility in designing
longer piles to suit design requirements;
·
This pile type has larger structural capacities to
cater for lateral and vertical loads; and
·
With provision of temporary casings during pile
excavation, shaft collapse and over-excavation can be minimized.
Drawbacks
·
Comparatively larger working spaces are required due to
larger piling plants required;
·
It
may be susceptible to bulging or necking during pile concreting in unstable
ground due to the larger pile size;
·
Compared
with Options A and C, risk of loosening of surrounding soil is higher, causing ground
movement and structural impacts on the adjacent structures; and
·
Extension
of working hours to the restricted hours may be required for concreting of very
long piles.
Option C: Pre-bored Concrete Pile
Pile shafts are formed by drilling rigs
with the use of down-the-hole hammers.
Pre-bored concrete piles are considered as small diameter bored
piles. Therefore, similar to the
large diameter bored pile construction, the pre-bored holes will be inserted
with rebar cages and in-filled with concrete. Shaft-grouting can also be provided for
enhancing shaft resistance for friction piles.
Benefits
·
It is relatively easy to overcome underground
obstructions by down-the-hole
hammers;
·
Compared with Option A, this construction method has higher
flexibility in designing longer piles to suit design requirements;
·
Compared with Option D, less ground borne vibration
will be induced;
·
With provision of temporary casings during pile
excavation, shaft collapse and over-excavation can be minimized.
Drawbacks
·
Pile excavation by down-the-hole (DTH) hammer will
cause disturbance affecting the adjacent
structures and foundations;
·
Construction
Noise Permit (CNP) under the Noise Control Ordinance (NCO) will be required for
the use of DTN hammer. Longer construction period may be required due to the
restricted working hours imposed by the Authority;
·
It
may be susceptible to bulging or necking during pile concreting in unstable
ground; and
·
Possible
collapse of the annulus space (over-cut) between the side wall and temporary
casing before pile concreting would reduce the skin friction.
Option D: Driven Steel H-Pile
This construction method is to pitch
H-piles using percussion method until final sets are achieved. A hydraulic hammer is commonly used for pile
driving in
Benefits
·
Pile installation method is relatively simple and
degree of redundancy can be easily incorporated to provide flexibility to deal
with any unexpected ground condition;
·
Extensive experiences of driving H-piles within marble
areas in
·
Installation is generally unaffected by groundwater
conditions;
·
Compared with Options A and C, this pile type can be
designed to withstand high bending and tensile stresses; and
·
Compared with Option A, this construction method has
higher flexibility to design longer piles to suit design requirement.
Drawbacks
·
The driving operation will generate relatively high
noise and vibration levels, affecting the nearby environmental sensitive
receivers;
·
Construction
Noise Permit (CNP) under the Noise Control Ordinance (NCO) will be required for
percussion pile installation. Longer construction period may be required due to
the restricted working hours imposed by the Authority;
·
Higher
ground borne vibration and movement induced from the driving operation may
cause damage to the adjacent piles, structures and utilities installations;
·
Pre-boring
may be required to overcome underground obstructions and require longer
construction period.
3.3.2
Selection of Pile Construction Method
By comparing the above
four options, Option A - Continuous Flight Auger (CFA) Pile is preferable in
view of the following:
·
Relatively less noise and vibration impacts;
·
No restriction on normal working hours;
·
Relatively fast construction rate;
·
Less impacts to existing structures; and
·
Satisfying the loading and ground condition
requirements.
Table 3.3a Comparison
of Alternative Pile Construction Methods
Options |
Alternative Construction
Methods |
Benefits |
Drawbacks |
A |
Continuous Flight Auger Pile |
·
Piles
can be installed without appreciable noise and vibration; ·
Generally
ground loss/disturbance is minimal during pile hole excavation and therefore
less disturbance on the adjacent structures and piles; ·
Compared
with Options B and C, it is a more economic pile construction method under
suitable ground condition (i.e. for cohesive soils) and satisfying load
requirements; ·
Less
working spaces are required compared with Option B; ·
Construction
time is relatively fast; and ·
There
is no restriction on the normal working hours. |
·
Pre-excavation
or pre-boring may be required to cope with any underground obstruction such
as boulders within the soil matrix; ·
Compared
with Option B, this pile type has less structural capacities to resist
lateral and vertical loads; ·
Specialist
contractor may be required to ensure the pile construction workmanship; and ·
Designed
pile length is limited by the construction plants and it is generally less
than 40m. |
B |
Large Diameter Bored
Pile |
·
Extensive
experience of using this type of construction method has been developed in ·
Compared
with Options C and D, less noise and vibration will be generated during pile
installation; ·
It
is relatively easy to overcome underground obstructions; ·
Compared
with Option A, this construction method has higher flexibility in designing
longer piles to suit design requirement; ·
This
pile type has larger structural capacities to cater for lateral and vertical
loads; and ·
With
provision of temporary casings during pile excavation, shaft collapse and
over-excavation can be minimized. |
·
Comparatively
larger working spaces are required due to larger piling plants required; ·
It
may be susceptible to bulging or necking during pile concreting in unstable
ground due to the larger pile size; Compared with Options A and C, risk of
loosening of surrounding soil is higher, causing ground movement and
structural impacts on the adjacent structures; and ·
Extension
of working hours to the restricted hours may be required for concreting of
very long piles. |
C |
Pre-bored
Concrete Pile |
·
It
is relatively easy to overcome underground obstructions by down-the-hole
hammers; ·
Compared
with Option A, this construction method has higher flexibility in designing
longer piles to suit design requirements; ·
Compared
with Option D, less ground borne vibration will be induced; ·
With
provision of temporary casings during pile excavation, shaft collapse and
over-excavation can be minimized. |
·
Pile
excavation by down-the-hole (DTH) hammer will cause disturbance affecting the
adjacent structures and foundations; ·
Construction
Noise Permit (CNP) under the Noise Control Ordinance (NCO) will be required
for the use of DTN hammer. Longer construction period may be required due to
the restricted working hours imposed by the Authority; ·
It
may be susceptible to bulging or necking during pile concreting in unstable
ground; and ·
Possible
collapse of the annulus space (over-cut) between the side wall and temporary
casing before pile concreting would reduce the skin friction. |
D |
Driven Steel
H-Pile |
·
Pile
installation method is relatively simple and degree of redundancy can be
easily incorporated to provide flexibility to deal with any unexpected ground
condition; ·
Extensive
experiences of driving H-piles within marble areas in ·
Installation
is generally unaffected by groundwater conditions; ·
Compared
with Options A and C, this pile type can be designed to withstand high
bending and tensile stresses; and ·
The
pile installation method has less settlement concern, which is essential for
bridge structures. |
·
The
driving operation will generate relatively high noise and vibration levels,
affecting the nearby environmental sensitive receivers; ·
Construction
Noise Permit (CNP) under the Noise Control Ordinance (NCO) will be required
for percussion pile installation. Longer construction period may be required
due to the restricted working hours imposed by the Authority; ·
Higher
ground borne vibration and movement induced from the driving operation may
cause damage to the adjacent piles, structures and utilities installations; ·
Pre-boring
may be required to overcome underground obstructions and require longer
construction period. |
3.3.3
Options for Construction of New Flyover Deck
Three methods for construction of the new
flyover deck have been examined. The benefits and drawbacks
of each method are discussed below and summarised in Table 3.3b:
Option 1: Precast Segmental Balanced Cantilever Box
Girder
Due to limited working areas on site
and heavy traffic flows at the existing interchange, concrete box girder
segments is likely to be used for construction of the flyover. They are usually
cast in casting yards in Mainland
Benefits
·
Conventional falseworks and formworks are not required
and therefore extensive temporary road closures/diversions at the interchange
can be avoided;
·
In-situ concreting works are significantly reduced compared
with the other methods, minimizing the potential impacts to the environment,
such as noise and air quality. In addition,
the
operation is quieter compared with other methods;
·
Construction time is shorter and better construction
planning can be achieved;
·
Although not labour intensive as most of the works can
be achieved off site. Even so, more experience and mature skilled labourers
have been developed in recent years in
Drawbacks
·
Construction cost is relatively high for an
approximately 140m long bridge; and;
·
The gantry girder cannot be very long thus
restricting the span length to a maximum of around 60m currently in
·
Worldwide specialist contractors may be required.
Option 2: Cast In-situ Deck with Conventional
Temporary Works
Falseworks/scaffolding will be erected across the
existing carriageway for placement of formworks. Rebar fixing will be subsequently
carried out before in-situ concreting of the deck structure.
Benefits
·
It is a simple and straight forward construction
method;
·
Extensive experiences have been gained among the local
contractors.
Drawbacks
·
Temporary road closure is necessary for erection of
falseworks and during concreting, causing significant impacts to the existing
traffic;
·
Construction time may be taken longer for the
span-by-span construction method;
·
More working areas are required; and
·
More construction plants will be involved for the
in-situ works and the longer construction period will induce higher
environmental impacts to the surroundings, such as noise and air quality
impacts.
Option 3: Cast In-situ Balanced Cantilever Box Girder
by Form Travellers
This construction method is a combination of Options 1
and 2. First pair of the box girder
segments will be cast in-situ symmetrically about the pier head by conventional
falseworks and formworks. Form
travellers will be launched and anchored on the previously cast segments for
rebar fixing and concreting of the subsequent pair of segments. After stressing the new segments to the
deck structure, the travelling formworks will be moved forward and the
construction procedures will be repeated until completion of the bridge deck.
Benefits
·
Requirements of the conventional falseworks and
formworks is greatly reduced; and
·
Heavy lifting operations are minimised.
Drawbacks
·
It is time consuming for steel fixing, concreting of
segments and adjustment of the form travellers as compared with the other two
options, causing longer construction period and higher environmental impacts;
·
Comparatively, more construction plants will be
involved for the in-situ works, which will also induce higher environmental
impacts on the surroundings, such as noise and air quality impacts.
·
Temporary road closure during day-time cannot be
avoided, particularly for concreting above existing carriageway, which cause
disturbances to the traffic;
·
There is limited experiences for highways construction
using form travellers in
·
Worldwide specialist contractors may be required.
3.3.4
Selection of Construction Method for New Flyover Deck
The potential environmental impacts to the NSRs in the
vicinity, disturbance to existing traffic flows and construction speed are all
important factors in the selection of a preferred construction method for the
new flyover deck. Option 3 is
considered to be inferior in all the above aspects, and therefore has not been
considered further. Both Options 1
- Precast Segmental Balanced Cantilever Box Girder and Option 2 - Cast In-situ
Deck with Conventional Temporary Works are found to be acceptable in terms of
the potential construction noise impacts, as demonstrated in Section 4. Option 1 is a common method for the
construction of flyovers/viaducts in
Table
3.3b Comparison of Alternative
Construction Methods for New Flyer Deck
Options |
Alternative Construction Methods |
Benefits |
Drawbacks |
1 |
Precast Segmental
Balanced Cantilever Box Girder |
· Conventional falseworks and formworks
are not required and therefore extensive temporary road closures/diversions
at the interchange can be avoided; · In-situ concreting works are
significantly reduced compared with the other methods, minimizing the
potential impacts to the environment, such as noise and air quality; In
addition, the operation is quiet compared with other methods. · Construction time is shorter and better
construction planning can be achieved; · Although not labour intensive as most of
the works can be achieved off site.
Even so, more experience and mature skilled labourers have been
developed in recent years in |
· Construction cost is relatively high for
an approximately 140m long bridge; · The gantry girder cannot be very long
thus restricting the span length to a maximum of around 60m currently in Hong
Kong; and · Worldwide specialist contractors may be
required. |
2 |
Cast In-situ Deck with Conventional Temporary Works
|
· It is a simple and straight forward
construction method; · Extensive experiences have been gained
among the local contractors. |
· Temporary road closure is necessary for
erection of falseworks and during concreting, causing significant impacts to
the existing traffic; · Construction time may be taken longer
for the span-by-span construction method; · More working areas are required; and · More construction plants will be involved for the in-situ
works and the longer construction period will induce higher environmental
impacts to the surroundings, such as noise and air quality impacts. |
3 |
Cast In-situ Balanced Cantilever Box Girder by Form
Travellers |
· Requirements of the conventional
falseworks and formworks is greatly reduced; and · Heavy lifting operations are minimised. |
· It is time consuming for steel fixing,
concreting of segments and adjustment of the form travellers as compared with
the other two options, causing longer construction period and higher
environmental impacts; · Comparatively, more construction plants
will be involved for the in-situ works, which will also induce higher environmental
impacts on the surroundings, such as noise and air quality impacts; · Temporary road closure during day-time
can not be avoided, particularly for concreting above existing carriageway,
which cause disturbances to the traffic; · There is limited experiences for
highways construction using form travellers in · Worldwide specialist contractors may be
required. |
3.3.5
Options for Construction of Retaining Structures
Three
types of retaining structures are considered for the formation of road
embankments, namely reinforced concrete (RC) cantilever wall, piled wall and
reinforced earth (RE) wall. As these are widely adopted as solutions for
retaining structures in
Construction
of RC cantilever walls involves excavation, formwork erection, rebar fixing,
placing of wall drainage system, in-situ concreting, temporary works removal
and backfilling of the walls. It is
a relatively straight forward construction method and extensive project
experiences have been gained in
Piled
wall utilizes the lateral resistance of the piles for earth retaining
purpose. It is commonly used in areas
where excavation for RC wall construction is difficult or technically
infeasible. Piled wall construction involves pile shaft excavation using piling
plants, placing of rebar cages/H-piles, in-situ shaft concreting/grouting,
excavation and construction of lagging between piles. The retained height would generally be
higher than the RC wall, and excavation works would be much less. However, pile
installation usually induces noise and vibration with higher degree of
environmental concerns. Moreover,
for the works immediately adjacent to the existing carriageways, temporary road
closure or traffic diversion may be required to provide larger working spaces
required for the piling plants.
Construction
works for RE wall comprises excavation, and placing of fill materials and
reinforcements in compacted backfill layers until the design road formation
level is reached. The construction
sequences are relatively simple and construction rate is usually faster than
the conventional RC retaining wall construction. Experiences in the use of RE
wall have been gained in recent years to form embankment slopes for highway
projects in
By
comparing the above three construction method of retaining structures, it is
considered that the RE wall option is more preferable in terms of environmental
consideration, construction speed and flexibility. However, RC cantilever walls at some
areas are still required due to small retaining height required or site constraints,
such as tie-in issues with the proposed/existing RC structures.
In
conclusion, the optimum solution of retaining structures is provision of RE
walls, associated with RC walls, where appropriate.
3.3.6
Consideration of Construction Sequences
The
interchange improvement works are broadly grouped into three main tasks as
follows:
Task
1: Provision of southbound carriageways, including construction works for Road
Resurfacing & Remarking A, Left-turn Lane A and Slip Road C; and
Task
2: Provision of northbound carriageways, including construction works for Slip
Roads A and B, new flyover and Road Resurfacing & Remarking B.
Task
3: Earmark an approximate 200m long and 2.5m high vertical noise barrier along
the southern arm of the northbound carriageway of Yuen Long Highway to the east
of the planned schools (refer to Annex
C11-2
for noise barrier location).
Overall Planning
Task
2 is scheduled to start following the commencement of Task 1 for alleviating
the cumulative environmental impacts to the surroundings and to enable early
handover of the carriageway.
Construction
sequences are also highly dependent on the selection of construction
methods. Consideration of different
construction methods for piling works, erection of the new flyover deck and
retaining walls has already been discussed in above sections. However, one of key approaches is to
maximize the use of pre-cast units, and therefore minimise in-situ works and
the consequential environmental impacts on the Project site. Other preferences in the construction
methods include fast construction progress and the use of relatively silent
plant.
Construction
Works for Task 1
The
existing alignment of the Road Resurfacing & Remarking A is to be locally
adjusted to increase the number of carriageway lanes from three to four. Works
include resurfacing of the existing carriageway and reprovision of road
markings.
Construction
of Slip Road C involves retaining walls construction, re-profiling of the
existing fill embankment slopes, construction of pavement and the associated
drainage, watermain, utilities and landscaping works.
As
shown on the construction programme in Annex
C2,
it is anticipated that construction of Task 1 will take around one and half
year. Other than the construction
methods and sequences described above, there are limited alternatives due to
the relatively straight-forward works sequences and the tight construction
programme.
Construction
Works for Task 2
Construction
of the new flyover involves pile installations, construction of pilecaps and
piers/columns, erection of deck, installation of parapets and planters,
pavement works and the associated drainage, watermain, utilities and
landscaping works.
Similar
to the construction of Slip Road C, works for Slip Roads A and B comprise
construction of retaining walls or formation fill embankment slopes,
installation of parapets, construction of pavement and the associated drainage,
watermain, utilities and landscaping works.
The
existing alignment of Road Resurfacing & Remarking B is to be slightly
shifted westward to accommodate the additional lane at the northbound
carriageway. Works mainly consist
of road formation and re-surfacing, and reprovision of existing drainage and
road furniture along the realigned carriageway.
Noise
induced from piling works is one of the major concerns; construction works for
Slip Roads A and B are therefore planned to commence after the completion of
the pile installation works. Moreover, pavement construction of Slip Roads A
and B, the new flyover and Road Resurfacing & Remarking B is planned to be
conducted in a similar period so that paving of the southbound carriageway can
be carried out within the same time frame. Consequently, it can reduce the
numbers of overlapping joints and mobilization of construction plants. In
addition, it can mitigate the overall level of disturbance to the environment and
traffic.
Construction
Works for Task 3
Construction
of the proposed noise barrier will be earmarked as a provisional work of the
Project as the construction schedule of the planned schools has not yet been
confirmed. Moreover, it is anticipated that the noise barrier will be designed
in form of a retaining structure with an extended wall plinth for the noise
barrier. Therefore, construction of the noise barrier will involve site
formation, retaining wall construction, backfilling works and reinstatement of
the existing street furniture. Furthermore, the noise barrier will be
positioned at the crest of existing fill embankment slope of Yuen Long Highway,
and therefore re-profiling /reinstatement of the existing fill slopes may be
required during the noise barrier construction.
([1])
Traffic
Impact Assessment Report prepared under the Agreement No. WD 3/2006 for
Improvement to Pok Oi Interchange - Traffic Impact Assessment and Alignment
Design Study dated July 2007.