5                                            PROJECT DESCRIPTION

5.1                                      The Project

This section of the EIA Report presents the details of the proposed development against which environmental impacts have been addressed.  The construction, operation and maintenance phases are described in terms of the likely component options and their installation and use.  In summary, the key components of the project include the following:

·            The construction of around 35 nos. of 2.3 to 3.6MW class wind turbine units including seabed works required for foundation emplacement.  Should 3.6MW class wind turbine be selected, the number of wind turbines would be reduced to around 28 to 30 in order to maintain the wind farm capacity of around 100MW.

·            The installation of interconnecting submarine electricity cables between turbine units, to the offshore substation and to grid.

·            Construction of an offshore substation.  There may, however, be an option for the offshore substation to be replaced by an onshore one subject to detailed engineering design.

·            Development of an onshore lay down area and quayside for material storage and pre-assembly works.

·            Development of an offshore wind monitoring mast.

5.2                                      Project Design

The components for the wind farm will not be procured until the Detailed Design Phase, which will commence once the EIA has been approved.  Therefore a description of the likely components and their installation is provided in this EIA Report together with any alternatives (if necessary) and corresponding methods of installation.  The assessment of environmental impacts will correspond to the component or process option giving rise to the maximum perceived impact.

The preferred scenario/alternatives for development of the wind farm and installation of the submarine and terrestrial cables to be taken forward in this EIA are described in Section 4.  On the basis of the alternatives selection, the layout plan for the proposed development is shown in Figure 5.1.  The turbine layout and cable route shown in Figure 5.1 are indicative only and will be confirmed during the Detailed Design Phase of the Project. 


The key elements of the Project are as follows:

·           Wind turbine construction;

·           Offshore substation construction;

·           Offshore wind monitoring mast construction;

·           Submarine cable installation; and

·           Onshore cable installation.

A general summary of each of these key elements is presented followed by a description of the key construction and operational activities.

5.2.1                                Wind Turbine Design and Construction

Foundation Design & Ancillary Features

Foundations

Foundations are required to support turbine towers, nacelles and blades and also to provide a platform above sea level for ongoing maintenance access.  In addition foundations will also need to be constructed for the offshore wind monitoring mast and offshore substation.  Three types of wind turbine foundation have been considered for this Project and these are discussed in Section 4 of this EIA Report.  Of those options assessed only the tripod / tetrapod and monopile foundations were considered to be technically feasible and environmentally acceptable with proven mitigation.  The monopile foundation has been identified as potentially having the worst case scenario impacts given the relatively larger footprint and also the potential need to incorporate scour protection material.  This foundation is therefore taken forward for the EIA.  The monopile for this size of turbine is anticipated to have a diameter of 5 to 7 m which will lead to a physical footprint of approximately 38.5 m2 with a pile wall thickness of approximately 80 mm.  However, impacts associated with the use of tripod / tetrapod foundations are covered by the assessment of monopile foundations.  As the wind monitoring mast will be constructed much earlier than the rest of the wind farm equipment, deployment of special duty plant from overseas, which are not commonly used for marine structures in Hong Kong, such as large jack up (with long legs) vessels and, heavy duty hammer, dedicated for monopile foundation and wind turbine installations solely for the purpose of wind monitoring mast monopile foundation construction would be unfeasible.  It is, therefore, expected that adoption of monopile foundation for the wind monitoring mast similar to that for the wind turbines will be highly unlikely.  Alternative foundation design for the wind monitoring mast will therefore be adopted.  Based on the preliminary engineering design conducted by HK Electric’s consultant, the foundation of the wind monitoring mast will be made up of a lattice of 8 piles, each expected to be of 1.6m diameter (See Section 4).

Turbine Ancillary Features

Each turbine foundation will have a platform, which is required for maintenance access (see Section 4).  This platform will be lifted into place using a crane barge.

As discussed in more detail below, the wind turbines will be inter-connected by submarine cables to provide both power and telemetry links (see Figure 5.1).  Provision is therefore made for the entry and protection of the cables.  The cables are most likely to be installed in a “J-tube” arrangement, a steel tube of approximately 250-350 mm diameter attached to the side of the turbine support structure extending from above the high tide level to the seabed.  Each structure will have between two and five J-tubes.  The cable entry and protection will be pre-installed at the quayside.

Scour Protection

As discussed in Section 4, rock scour protection will be constructed at the base of the monopile foundation.  It is assumed that this scour protection will have an overall width of 30m and length of 30 m and overall area of 900 m2.  The height of the scour protection is expected to be 0.5 m above the seabed.  It is proposed that stability calculations will be undertaken during pre-contract engineering to ensure stability of the material and that suitable rock sizes be identified during the Detailed Design.

Wind Turbines

Wind Farm and Wind Turbine Dimensions

In order to prevent wake loss, the preliminary separation distance of the turbines for the EIA is 650m East-West and 360 m North-South.  However, this layout is subject to further detailed engineering design and consideration of impacts, e.g. visual impacts (see Section 11).  Preliminary dimensions are not expected to exceed a tip height of +125mPD.  In the event the wind turbine model with a maximum rotor diameter of 111m be adopted, the maximum tip height would be +136mPD.  The area of development for the turbine site is approximately 6 km2 (see Figure 5.1).  Figure 5.2 shows a typical offshore wind turbine structure.

Figure 5.2       Offshore Wind Turbine


The diameter of the tower base will be approximately 5 - 6 m, tapering to approximately 4 m at the hub.  The tower of each turbine will be made of tubular steel, and the blades of composite material, which consists of fibre glass and epoxy resin.  Each blade is protected from lightning damage by means of a receptor system.  The turbines will each have three blades.

Operation parameters

The turbines will have a rotational speed of between 9 and 19 revolutions per minute (rpm) and have weights of between 220 - 480 tonnes.  The wind turbines will generate power when the wind speed at the hub height is between 2 - 5 ms-1 (metres per second) and will have a full generation potential at wind speeds of about 14 ms-1.  Once erected, the turbines will operate automatically using remote diagnostics and control systems.  These systems will require ongoing maintenance during the operational period whenever necessary.  The turbines will also be serviced at regular intervals following the manufacturer’s requirements. 

The turbines will have a “fail-safe” operation in that if wind speeds greater than 25 ms-1 occur for extended periods the turbines will shut down automatically.  The maximum tolerable wind speeds for the structural integrity of the turbines is approximately 70 ms-1.

All rotors will rotate clockwise when viewed from the windward direction.  This will ensure that there will be some conformity in how the wind farm is seen from Visually Sensitive Receiver’s (see Section 11). 

Colour

The final decision on the colour of the turbine mast and blades will be made during the Detailed Design Phase.  However, it is currently assumed to be the “standard” colour for offshore wind turbines, a semi-matt pale grey colour RAL 7035.  Marking requirements for aviation and navigation are discussed separately below.

Corrosion Protection

Corrosion protection on the steel structure will be achieved by a combination of a protective paint coating and installation of sacrificial anodes on the submarine structure.  The anodes are standard products for offshore structures and are welded onto the steel structures.  The anodes typically consist of zinc and aluminium, and are connected to the structure via doubler plates to ensure the integrity of the primary structure is maintained in the unlikely failure of an anode connection.  The number and size of anodes would be confirmed during the Detailed Design phase.

Lighting and Marking

Minimum marking requirements for offshore wind farms are as follows (see Figure 5.3), which has been agreed with the Civil Aviation Department ([1]):

For those turbines at the periphery of the wind farm:

·           The blade tips and the top of the nacelle and the part of the Supporting tower corresponding to the marked portion of the blade tip when the blade is pointing downwards should be marked in orange; and

For all other turbines:

·           Only the blade tips and the top of the nacelle should be marked in orange.

The minimum extent of markings on blade and tower is that each band should have a width approximately one-seventh of the longest dimension of the wind turbine, i.e. its tip height (see Figure 5.3).

Figure 5.3      Marking and Aviation Lighting Requirements for Offshore Wind Farms

 


Aviation lights will be required for the offshore structures.  For structures at the periphery of the wind farm, the offshore substation and monitoring mast, lighting will be required at the highest practical point on the nacelle and on an intermediate point on the supporting tower.  This should consist of low intensity continuous red lights.  In addition for turbines within the wind farms site, only the highest practical point on the supporting tower should be lighted in low intensity steady red light ([2]).   

In addition, there will also be a need for navigation marking and lighting, which should comply with the International Association of Marine Aids to Navigation and Lighthouse Authorities (IALA) Recommendation 0-117 of May 2000 ([3]).  In general, there will be a need for navigation lights placed on each corner of the wind farm development, and mid-way along each side of the wind farm.  The corner lights will be yellow flashing Morse ‘U’ code lights (5 second interval) visible for 5 nautical miles (9.3 km), located at least +12mPD with radar reflectors situated beside them.  The intermediate (mid-way) lights will flash at 2.5 seconds and will be visible for 2 nautical miles (3.7 km).  There will need to be two lights on each lit turbine so that the light is visible through 360°.   Each tower should also be marked by a unique number or code, clearly visible from a position mid-way between adjacent towers such that any vessel in difficulty can easily report its exact position within the wind farm and that any emergency service vessel can locate a casualty with equal ease.

During construction, the offshore working area will need to be established and marked in accordance with Marine Department Notice No. 23 (2009).  A safety / exclusion zone of 500 m will be closed to all vessels around the area of works. The purpose of this area will be to protect the safety of construction plant and personnel and also third parties who may wish to navigate through this area.  This safety zone will cover the whole wind farm area, but the extent of the safety zone will change as per the rolling construction programme.

Oils and Fluids

Each of the turbines will contain lubricants and hydraulic oils (nominally 100 l of gearbox oil, 250 l of hydraulic oil, 20 l of motor oil, 2,500 l of transformer oil and potentially limited quantities of coolant depending on design).  Discharges of contaminants from wind turbines or other installations (e.g. offshore sub-stations) are anticipated to be extremely unlikely due to oils and fluids from gearboxes, hydraulics and pitch drive and yaw drive systems being mechanically contained ([4]) ([5]).

Noise Emission

The wind turbines will generate aerodynamic and mechanical ambient noise during their construction and operation.  The major ambient noise sources are expected to come from crane operation, vessel movement and percussive piling during the construction phase and from the wind turbines during the operational phase. 

Aerodynamic noise generated during operation of the turbines is broad-band in nature, relatively unobtrusive and is dependent upon wind speeds prevalent at the site of development.  Studies from offshore wind farms in the UK suggest that receptors beyond 500 m from the wind farm are not significantly affected for wind turbines of similar size to that being considered by this Project (1) (2).  Mechanical noise is generated from moving components in the nacelle and can be radiated through the structure, which can be mitigated through good design (e.g. anti-vibration techniques). 

Mechanical noise during operation can be successfully controlled at the design stage of the turbine, using advanced gearbox design and anti-vibration techniques.  The present generation of turbines considered for this Project incorporate design features which ensure that such tonal noise emissions are not considered significant.

Based on a total of 35 wind turbines to be installed for the Project and a sound power level of 109.4 dB(A) for each wind turbine at a wind speed of 9 ms-1 at 10m above ground level, which is typical of 3.0MW wind turbines, the nearest sensitive receivers at Lamma Island and Cheung Chau would likely experience a noise level of about 35 dB(A) and 38 dB(A), respectively (estimated in accordance with the procedures outlined in the ISO 9613-1 ([6]) and ISO 9613-2 ([7])) (Annex 5A).  The operational noise levels anticipated at the nearest sensitive receivers are well within the specified noise criterion (ie 43 dB(A) and 45 dB(A) for the sensitive receivers at Lamma Island and Cheung Chau, respectively), and therefore not expected to cause any significant impact.

The site is a significant distance from the nearest sensitive receivers (NSR), with Yung Shue Wan and Lo So Shing being at least 4 km away.  In view of the considerable separation distances between the NSRs and the site, the noise generated during the construction and operational phases is not expected to be a concern.  In accordance with the EIA Study Brief ESB-151/2006, quantitative construction and operational noise impact assessments are therefore not required.  However, underwater sound generation is discussed with respect to impacts on marine ecology in Section 9 and fisheries in Section 10.

The normal working hours of the contractor will be between 0700 and 1900 hours from Monday to Saturday (except public holidays).  Should percussive piling and any construction works during evening and night works between 1900 and 0700 hours or on public holidays (including Sunday) be required, the contractor should submit a Construction Noise Permit (CNP) application and the application would be assessed by the Noise Control Authority.  Conditions stipulated in CNP should be strictly followed.

Wind Farm Layout

As discussed in Section 4, in order to inform the EIA an interim geometric design is considered as being indicative of how the wind turbines will be arranged with two distinct circuits within the turbine array.  This is shown in Figure 5.1.

5.2.2                                Offshore Substation

For the purposes of this EIA, the base case design of the wind farm includes for an offshore sub-station to transform the voltage of the electricity generated at the wind turbine to a high voltage suitable for transmission of power ashore.  22kV, 33kV or other voltage rating according to the proprietary design of wind turbine manufacturer’s will be used for the wind farm internal grid and connection to the offshore substation where the electricity voltage will be stepped up to 132 kV for transmission to HK Electric’s grid at the Lamma Power Station Extension.  The substation is expected to be a steel platform with an area of about 200 m2 and a height of > +20mPD.  The offshore sub-station platforms will have boat access points to assist operations and maintenance or emergency evacuation.  A model of a typical offshore substation is shown in Figure 5.4 below.

Figure 5.4       Indicative Model of an Offshore Substation at Horns Rev Offshore Wind Farm (Demark) ([8])


It should be noted, however, that as mentioned in Section 5.1 there may be an option for the offshore substation to be replaced by an onshore one subject to detailed engineering design.  For this case, a network of six cables (22kV, 33kV or other voltage rating according to the proprietary design of wind turbine manufacturers) from the wind farm internal grid will be connected to HK Electric’s grid at the Lamma Power Station Extension. 

5.2.3                                Offshore Wind Monitoring Mast

A monitoring mast will be required to measure wind, wave and current information for operational purpose.  The structure will consist of a steel lattice tower erected on top of a foundation (see Section 4, and Figure 4.10 for the indicative foundation design). Anemometry equipment will be installed on the mast and wave and current sensors installed on the foundation structure.  A model of a typical offshore monitoring mast is shown in Figure 5.5 below. 

Figure 5.5       Indicative Monitoring Mast


 

5.3                                      Offshore Wind Farm Construction

5.3.1                                General Construction Sequence

The general construction sequence is presented below.  It should be noted that this sequence may be subject to refinement and potentially further study at the Detailed Design Phase.

1.        Site preparation will compose the creation of a delineated Lay Down area.

2.        Support vessels for foundation construction (monitoring mast, offshore substation and turbines) will need to be mobilised to the site.

3.        The offshore monitoring mast will be constructed before the construction of the wind turbines so that data can be collected at the site.

4.        Foundations will be constructed for the offshore monitoring mast first at the area shown in Figure 5.1.

5.        If required, scour protection will be installed at the base of the monitoring mast foundation prior to installation of the foundation.

6.        The Offshore monitoring mast will be delivered to the quayside at Lamma Power Station Extension with a lay down area located adjacent to the quay.  This will then be transferred offshore so that it can be fixed to the foundation structure.

7.        Once approval is obtained for marine works, dredging and jetting will be undertaken to install the submarine cables.  It is possible that this could occur in parallel to the construction of foundations and/or turbine installations.

8.        Foundations will be constructed for each turbine site and substation at the locations shown in Figure 5.1.

9.        Again, if required, scour protection will be installed at the base of each turbine foundation and the offshore substation prior to installation of the foundation.

10.    The turbine components will be delivered to the quayside at Lamma Power Station Extension with a lay down area located adjacent to the quay.  The turbine mast sections (number yet to be determined) will be pre-mounted in a vertical position onshore and left in this position until being transferred offshore once foundations are in place. 

11.    Turbine and substation components will be transferred from the Lamma Power Station Extension for fixing to the foundation support structure.

12.    Dredged material would be removed to approved disposal/storage sites by barge.

13.    Once submarine cables have been installed and landed through the seawall, the cable will be installed to the Switching Station on the Lamma Power Station Extension.

A more detailed description of the construction activities is presented below.

5.3.2                                Marine Works

Marine works associated with the offshore wind farm development will be divided into the following works:

·            Installation of key wind farm components; and

·            Submarine cable circuit and crossings.

A description of the works associated with each of the above activities is presented below.  It should be noted that the information included here is taken from preliminary design and will be subject to further study at the Detailed Design stage.


Installation of Key Wind Farm Components

Foundations

The percussive piling method will be used for the construction of the wind turbine, wind monitoring mast and offshore substation foundations (see Section 4 for a comparison of alternative installation methods).

This technique involves the driving a hollow steel pile into the seabed, relying on the frictional properties of the seabed sediments and the underlying in-situ materials for support.  The installation of a driven pile will also take place from a jack-up barge or from a floating barge.  Once at the turbine location, the jack-up barge will jack its legs down onto the seabed to create a stable platform.  The jack-up barge or the floating platform will have 1 - 2 mounted marine cranes, a piling frame adjustable to different degrees, and a hammer.  A support jack-up barge or floating barge, support barge, tug, safety vessel and personnel transfer vessel may also be required. 

Once the platform is stable or when the floating barge has been anchored, the pile is driven into the seabed.  Pile driving will commence with low energy impulses until the pile is stable (free standing).  An alternative method is to vibrate the pile downwards until the free standing state is achieved.  The pile is then driven until the target penetration is achieved. 

Since the pile is driven, the top of the pile can become distorted during the driving process, and a transition piece may be required to make the connection with the wind turbine tower.  This transition piece is generally fabricated from steel, and is subsequently attached to the pile head using grout. 

Potential impacts of underwater sounds and the need or otherwise for mitigation measures is discussed are discussed in the Marine Ecological Assessment (Section 9 of this EIA Report).

Scour Protection

If scour protection is required, this is likely to comprise a rock structure at the base of the foundation.  Suitable graded rock will be loaded onto a rock-dumping vessel at the Lamma Power Station Extension and transferred to the foundation site.  Scour protection will be established after installing the foundations.  After the scour protection is constructed a further layer of cover stones will be placed around the foundation.

Rock dumping is based on the use of typical Hong Kong Lighters (1,800 – 3,000T), configured to place rocks using grabs.  These units have the capacity to place 2,400/3,600 T/day of graded rock.  It is likely that the Contractor will manipulate the numbers of units working in any area depending upon the available equipment at any time and on its actual progress vs. that planned.

Turbine Installation Approach

The turbine components will be delivered to the quayside at Lamma Power Station Extension with a lay down area located adjacent to the quay.  The turbine mast sections (number yet to be determined) will be pre-mounted in a vertical position onshore and left in this position until being transferred offshore.  On another part of the quay, the nacelles will be mounted on transportation frames and nose cones attached.  Two of the three blades will then be fixed to cones.

Once assembled, the turbine masts will be transferred to an installation vessel using the vessel’s onboard crane and onshore trailing crane.  Once the masts are secured onboard, the nacelles will be loaded onto the vessel, followed by the remaining blades.  For marine installation, support vessels will again be required, which will comprise similar vessels to that required for foundation construction.

Once all components are secured, they are transferred to the site ready for installation.  Upon arrival to site, the installation vessel will approach the intended location for each single turbine.  It will then position itself next to the foundation within a distance of 20 to 25 m.  After positioning the vessel, the legs will be lowered to the seabed and the vessel will jack itself to a stable position.

The tower will then be installed first followed by the nacelle, taking approximately fours hours to complete per turbine.  The third blade is then attached to the nose cone. The final phase of the turbine installation is the establishment of the electrical and mechanical connections.

Grouting will be required to fix transition pieces (i.e. fixing the foundation to the turbine).  As per grouting proposals for foundations, the grout will either be mixed in large tanks aboard the jack-up platform, or mixed ashore and transported to site.  The grout is also likely to be pumped through a series of grout tubes previously installed in the pile, so that the grout is introduced directly between the pile and the walls of the transition piece.  The level of grout in each tube is monitored during pumping by a grout probe unit so that the flow can be switched off once the required levels have been reached. 

Offshore Substation and Monitoring Mast Installation

The wind monitoring mast is comprised of 8 nos. of 1.6m diameter steel tubular piles fixed into seabed in which each pile individually can be considered as a small monopile.  An indicative drawing of the wind monitoring mast design is presented in Figure 4.10.  The mast pile will be installed at an above sea level of approx. 18 mPD on a concrete deck platform on-top of the underwater steel substructure.  Percussive piling using a hydraulic hammer from a piling barge will be used to install the tubular piles.  A description of the works associated with marine piling is presented above.

The offshore substation is expected to be a steel platform also set on tubular piles with an area of about 200 m2 and a height of > +20mPD.  The substation platforms will have boat access points to assist operations and maintenance or emergency evacuation.  Percussive piling using a hydraulic hammer from a piling barge will be used to install the tubular piles.  A description of the works associated with marine piling is presented above.

Submarine Cable Installation

As discussed in Section 4, submarine power cables are required to connect the wind farm to the electricity distribution system (see Figure 5.1).  These cables will also comprise fibre optic communication links for wind farm control processes.  Curved pipe ducts will be provided at the foundation of the wind turbines and Offshore Substation for submarine cable landing.  The provisions would be included in the civil foundation for wind turbine and offshore substation. 

Figure 5.6 shows the proposed layout of existing submarine cables, the proposed cable circuit for this Project and the location of crossing points.  The selection of installation method and sequencing activities for the cable circuit has been discussed in Section 4.  Grab dredging is the preferred installation technique at nearshore area to the Lamma Power Station Extension and jetting is preferred elsewhere. 

Seawall Removal and Reinstatement

In order to connect the submarine cable to land, the existing rubble mounted seawall at the west shore of the Lamma Power Station Extension will be exposed for installation of a duct bank (2 m internal steel slipway with concrete lining).  Approximately 2,145 m3 of existing seawall will be removed and reinstated as part of the works.  All removed seawall material will be reused to reinstate the seawall back to the existing condition.  Figure 5.7 shows the proposed area of seawall disturbance.  Figure 5.8 provides a cross section showing the area of seawall removal.

In the event that an onshore substation is selected during the detailed design, approximately 3,400 m3 of existing seawall material would be removed and reinstated as part of the works.  All removed seawall material will be reused to reinstate the seawall back to the existing condition.

Dredging

Grab dredgers will be utilised in the nearshore cable landing area to construct a short underwater trench.  For submarine utility installations, dredging involves the removal of marine sediments from the seabed to form the trench, into which the cable is laid. 

For the base case design, ie offshore substation, the cable trench will be trapezium shape with bottom width of 5 m.  The upper width shall be 8 to 12 m and the trench depth of 1.5 – 3.5 m deep.  It is assumed that the trench length will be a maximum of 100 m.  Figure 5.9 shows the proposed nearshore dredging works.  The expected maximum amount of sediment to be dredged is 3,000 m3.

For the alternative design, ie onshore substation, the cable trench will be trapezium shape with bottom width of 9 m.  The upper width shall be 12 to 16 m and the trench depth of 1.5 – 3.5 m deep.  It is assumed that the trench length will be a maximum of 300 m.  The expected maximum amount of sediment to be dredged is 13,125 m3.

The Water Quality Impact Assessment (Section 6) has examined the effects of dredging on water quality and should be referred to for further details.

Jetting

Offshore of the grab dredging area, cable installation will be undertaken using jetting methods.  The maximum burial depth for the base case design, ie offshore substation, will be 5 m and have a cross-sectional area of 0.75 m² (0.5 x 5 m x 0.3 m). 

Based on a total cable trench of 17.3 km (13 km for the internal turbine array and 4.3 km from the offshore substation to the grab dredging area), the approximate volume of sediment to be disturbed will be approximately 13,000 m3.  The internal turbine array cables will be laid in a loop within the trench.  This will mean that the overall cable length will be approximately 35 km, but the length of seabed disturbance will be only 17.3 km.

For the onshore substation design, a total cable trench of 48.3 km (14.6 km for the internal turbine array and 33.7 km for the six cables to the grab dredging area), the approximate volume of sediment to be disturbed will be approximately 37,000 m3. 

The submarine cable laying can start either from Lamma Extension or from the Offshore Substation [hereinafter named as Point (A)].  Initially the submarine cables will be laid out from the laying barge and buoys will be attached to the cable at about 1m intervals to allow the cable to float on the sea surface.  The cable is then pulled to Point (A) by means of a winch. 

After pulling to Point A, submarine cables will be set in the plough of the burying machine which is outfitted with the following typical equipment:

·            A towing wire rope;

·            A cable for power supply to the water pump cable;

·            A control cable for monitoring the working conditions of the burying machine;

·            One high pressure jet delivery hose; and

·            A hydraulic hose for control of the nozzle frame.

Cable guide equipment will be attached to the towing wire rope between the burying machine and the laying barge, so that the submarine cables are supported and guided into the burying machine. The burying machine will then be lowered into the sea using a crane.  By winding the anchor wire ropes, the cable laying barge will move forward and tow the burying machine at the same time.

As the burying machine advances, a small trench will be ploughed by fluidizing the seabed using water jetting method and the cable(s) will be laid onto the trench simultaneously.  Only a small amount of sediment will be disturbed at the seabed and the majority will subsequently settle over the cables.

Jetting speeds have been taken as 360 m hr-1 for cable circuit installation.  This rate relates to typical practices by contractors in Hong Kong that would be involved in these works ([9]) ([10]).  Each journey of laying operation, with a maximum of one power and one communication cables, will last for approximately one week.  There will be a maximum of three cable laying journeys, depending on the final system design.

Upon reaching the opposite landing point [hereinafter named as Point (B)], the submarine cables will be detached from the burying machine and laid out from the cable laying barge to form a loop line on the sea surface.  Buoys will be attached to the cables in the same manner as at Point A.  The cable will be pulled to Point B by winch and then lowered to the seabed by detaching the buoys one by one.

Within the turbine site area, typically an underwater trench shall be formed at the Offshore Substation and at each wind turbine for 22kV, 33kV or other voltage rating according to the proprietary design of wind turbine manufacturer’s cable landing. 

The Water Quality Impact Assessment (Section 6) has examined the effects of jetting on water quality and should be referred to for further details.

Cable Crossings

The new 22kV, 33kV or other voltage rating according to the proprietary design of wind turbine manufacturer’s and 132k V submarine cables will have to cross over some existing submarine communication cables. 

The submarine cable will be laid by simultaneously laying and burial method.  Before cable crossing, a short section of cable trench (~30 m) will be formed at each side of the crossing point.  During cable crossing, the burial machine will be temporarily lifted up and the submarine cable will be laid directly on the seabed/trench.  After cable laying, the cable trench will be backfilled with marine sand. 

The typical crossing method is to lower the existing communication cable by water jet method to about 3~5m depth, depending on their burial depth and available slack length.  The submarine cable will then be laid and buried at 2~3m at the cross over point.  Since portion of the submarine cable at the cable crossing point will be at shallow burial depth (e.g. 3 m for water depth > -18mCD and 5 m for water depth < -18mCD).  Figure 5.10 shows the typical design details for cable crossings that may be adopted for this Project.

A number of alternatives have been considered to provide protection to the above-bed (surface laid) cable at the pipeline crossing point should it be required, including the use of rock armour, pre-cast concrete mattresses or grout filled bags known as ‘fill in situ’ mattresses.  Should cable protection be required the preferred method of installation will comprise the development of a Reinforced Concrete (RC) cover at the crossing or other locations, which will be precast and delivered to site or be formed in situ.

In the worst case the existing submarine cable cannot be lowered down and laid at seabed surface, the following typical cable crossing method will be adopted:

·            A 0.3 m thick concrete mattress (about 30 m long) or 0.3 - 0.5 m thick aggregates will be laid on top of the existing cable to provide a partition at the crossing point;

·            The submarine cable will be laid on top of the concrete mattress;

·            After cable laying, for the cable portion above seabed level, a 0.5m thick fill in-situ concrete mattress will be installed on top of the cables for cable protection and to present a smooth top profile that does to hamper fishing gear.   The highest point of the concrete mattress will be 0.8 m above seabed level; and

·            For the cable portion below the seabed with a shallow burial depth, RC covers will be installed.

5.3.3                                Land Based Works

The land based works would be expected as follows:

·            Cable connection to grid

·            Development of a Laydown Area

Each of these proposed works are discussed below.

Cable Connection to Grid

The submarine cable will be landed at the west side of Lamma Extension and then connected to Lamma Extension 275 kV Switching Station by 132 kV land cable, 132/275 kV step up transformer and 275 kV cable via preformed RC cable troughs.  Similar to conventional trenching work on land, a 1 m wide x 1 m depth x 250 m long RC cable trough will be constructed from the submarine cable landing point to the 275 kV Switching Station Compound. Figure 5.11 shows the location of the onshore cable route.  The trench will be 1 m wide x 1 m depth x 250 m long.

Figure 5.11     Preliminary onshore cable route


 

Laydown Area

It is proposed that the Lamma Power Station Extension quayside will be used for the Laydown area and pre-assembly area during the construction phase (see Figure 5.12). 

5.4                                      Operation and Maintenance of the Offshore Wind Farm Components

There will be an ongoing requirement to maintain the wind turbines, monitoring mast and offshore substation during their design lifetime, which is expected to be 20-25 years.

The wind turbines will be configured so that they operate with a minimum of supervision.  The turbines are monitored and controlled by microprocessors installed within the turbine tower.  This system detects faults, and if necessary, the turbine is automatically shut down for safety purposes.

All information relating to on-site conditions, turbine status and generated output will be held within a central Supervisory Control and Data Acquisition (SCADA) system linked to each individual turbine microprocessor.  This will be controlled by an operational base at the Lamma Power Station, which will provide the remote control of individual turbines (or a number of turbines) should it be needed.

The wind farm will be serviced as per the manufacturer’s requirements. It is anticipated that ongoing maintenance will be required as necessary.  Inspections of support structures and submarine cables will also be performed regularly as will ad hoc visits for surveillance.  Should inspections show that cables have been un-earthed, then these will be re-buried using jetting techniques as discussed above.  Maintenance crew will use vessels to access the turbines via the platforms already constructed.  There will be an inbuilt crainage system within the turbine nacelle, which allows heavy equipment to be lowered to sea level should major work be needed.

An operational safety zone of 50 m radius will be in force from the substation, turbine and monitoring mast.  This will apply to non-Project vessels (excluding fishery vessels) throughout the operational period regardless of other exclusion arrangements.  No fishing activity or anchoring will be allowed within the wind turbine array or within 500 m of any turbine, offshore substation or offshore monitoring mast (the impacts of such an exclusion have been discussed in Section 10).  It is expected that during maintenance work exclusion from access to the wind farm is likely to be required in accordance with Marine Department Notice No. 23 (2009).

5.5                                      Decommissioning

Decommissioning is a term describing all the stages of the process implemented when an installation approaches the end of its useful life.  The process can generally be categorized into three key phases as follows (see Figure 5.13):

·           Pre-decommissioning activities: includes the detailed planning (development of the decommissioning plan) and approval procedures;

·           Decommissioning activities: removal and re-use, recycling, leaving in-situ, or disposal of all, or part, of the installation; and

·           Post-decommissioning activities: site survey, close-out report and field monitoring as necessary.

 

Figure 5.13     Stages of Decommissioning


The activities involved during decommissioning and abandonment phase include decommissioning of the wind farm facilities.  The facilities will, however, only be decommissioned when it is no longer economical to operate the facility. 

Decommissioning Plan

The decommissioning plan will realistically only be developed during the latter stages of the production life of the facilities.  The assessment of environmental impacts associated with the decommissioning will need to be conducted once the decommissioning plan is finalized and the marine works/ operations are defined. 

A detailed decommissioning plan will be developed taking into account of the most cost effective and best practicable methods, legal requirements and industry practices at the time of field abandonment.  To ensure that due consideration is given to all the relevant issues it is recommended that a detailed evaluation of decommissioning options is carried out.  The evaluation should consider environmental issues in conjunction with technical, safety and cost implications to establish the best practicable environmental options (BPEO) for the decommissioning of the wind farm.  A risk assessment will also be conducted to ensure that nothing which could be constituted as a hazard for other users of the area or for the environment in general will be left at the site.  The site will be left in a safe and environmentally acceptable condition. 

In addition to any Hong Kong abandonment regulations in force at the time decommissioning studies for the wind farm may also be based on International Maritime Organization (IMO) guidelines and standards – Guidelines and Standards for the Removal of Offshore Installations and Structures on the Continental Shelf and in the Exclusive Economic Zone.

Typically, offshore wind farms are designed with an appreciation of decommissioning in mind.  In general terms, the turbines are designed so that they can be cut and lifted off in steps which are in reverse of the installation procedure.  The piles are typically cut flush to the seabed to leave no obstruction following abandonment. 

At the end of the project activities, the decommissioning shall be treated as a standalone project.  The following points should be considered during planning: cessation plan, installation cold phase, cleaning operations, hazardous products elimination, pieces of equipment and facilities which will be dismantled and removed, environmental surveys and impact assessment studies.  On this basis, the assessment of impacts related to decommissioning are not presented herein, but will be conducted once the detailed decommissioning plan has been developed.

5.6                                      Project Summary

Table 5.1 presents the summary of the Project details.

Table 5.1        Summary of Project Description

Detail

Preliminary Design Information

Wind farm site area

600 ha

Submarine cable route trench (inter-array)

Approximately 13 km

Submarine cable route trench (offshore sub station to landing point)

Approximately 4.3 km

Submarine cable route length (inter-array loop)

Approximately 26 km

Submarine cable route length (offshore sub station to landing point loop)

Approximately 9 km

Grab dredging volume

3000 m3

Jetting area/volume

13,000 m3

Turbine foundation footprint area

38.5 m2

Scour protection footprint area

900 m2

Volume of grab dredging arisings for disposal

3000 m3

Volume of excavated C& D material

Seawall = 2,145 m3

 

Onshore cable trench = 250 m3

Volume of excavated C&D material for disposal

0 m3

Volume of grout per turbine

70 m3

Lay down area

2.73 ha

5.7                                      Project Programme

The preliminary programme for the Detailed Design and Construction Phases is presented in Figure 5.14. 

Figure 5.14    Construction Programme

5.8                                      Concurrent Projects

At present the identified potential concurrent projects are the marine dumping activities near South Cheung Chau.  Consideration will be given to potential cumulative impacts wherever appropriate in the EIA.  



([1])     Written correspondence from CAD to Hong Kong Electric dated 25 April 2007.

([2])     Written correspondence from CAD to Hong Kong Electric dated 25 April 2007.

([3])      IALA (2004) – O-117. The Marking of Offshore Windfarms (Edition 2).

([4])     Airtricity (2005). Greater Gabbard Offshore Wind Farm – Environmental Statement. Image provided by Global Scour Control Systems Ltd

([5])     National Wind Power (2002). North Hoyle Offshore Wind Farm Environmental Statement, UK. National Wind Power Ltd.

([6])      ISO 9613-1 Acoustics - Attenuation of Sound during Propagation Outdoors – Part 1: Calculation of the absorption of sound by the atmosphere.

([7])      ISO 9613-2 Acoustics - Attenuation of Sound during Propagation Outdoors – Part 2: General method of calculation.

([8])     Airtricity (2005). Greater Gabbard Offshore Wind Farm – Environmental Statement. Image provided by Global Scour Control Systems Ltd

([9])     ERM – Hong Kong, Ltd (2002)  EIA for the Proposed Submarine Gas Pipeline from Cheng Tou Jiao Liquefied Natural Gas Receiving Terminal, Shenzhen to Tai Po Gas Production Plank, Hong Kong.  Final EIA Report.  For the Hong Kong and China Gas Co., Ltd.

([10])    ERM - Hong Kong, Ltd (2007) Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities.  For CAPCO.  Final EIA Report. December 2006