3                                            Project Description

3.1                                      The Project

The Project is classified as a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO).  The works that are the subject of the EIA Study include the construction and operation phases of the Project.  The key components of the Project include the following:

·            Installation of submarine gas pipelines connecting the proposed Gas Receiving Stations (GRSs) at the Black Point Power Station (BPPS) and gas export facilities in southern Guangdong Province (Item H.2 of Part I of Schedule 2 of EIAO); and

·            Dredging operation exceeding 500,000 m3 for the reclamation and pipeline trenches (Item C.12 of Part I of Schedule 2 of EIAO).

3.2                                      Project Design

The proposed Project involves the construction of two submarine gas pipelines and the associated GRSs.  The first pipeline and GRS (i.e. First Phase) must be completed in 2012 to provide facilities to accommodate a timely replacement for the Yacheng 13-1 gas supply.  It is expected that the Second Phase could commence construction within 24 months of commissioning of the First Phase.  The information presented in this section is taken from the existing preliminary design and will be subject to further study at the detailed design phase.

The preferred scenario for the Project to be taken forward in this EIA has been described in Section 2.  On the basis of this selection, the preliminary layout plans for the proposed Project are presented in Figure 3.1.

The construction and operation of the two submarine pipelines and the two associated GRSs will involve the following key work elements:

·            Marine sediment dredging;

·            Seawall construction and land reclamation;

·            Submarine gas pipeline installation, testing, commissioning and operation; and

·            GRS construction, testing, commissioning and operation.

A general summary of each of these key elements is presented below.

3.2.1                                Marine Sediment Dredging

Dredging of marine sediments will be required for:

·            Construction of seawalls and reclamation for the GRS; and

·            Pre-trenching for submarine gas pipeline installation at the shore approach and for crossing the Urmston Road.

Dredging requirements for each of the above are discussed in the following sections.

3.2.2                                Seawall Construction & Land Reclamation

A new reclamation area to the north of the BPPS will be required to provide approximately 0.5 ha of land as the platform area for one of the proposed GRSs.  Permanent vertical seawalls will be constructed around the seaward boundaries of the reclamation to protect it from wave and tidal action.  The vertical seawall option will result in a smaller seabed area affected and smaller volume of dredged sediment than that for sloping seawall, and is suitable in areas where spatial constraints exist.  The preliminary layout of the proposed seawalls together with typical sections is shown in Figure 3.2.  The total length of vertical seawalls to be built along the reclamation is approximately 200 m.

Dredging will be undertaken to remove the soft material beneath the seawalls to ensure that these structures are stable to enable construction of GRS facilities immediately after reclamation.  Approximately 0.108 Mm3 of soft marine sediments (in situ volume) will be dredged (Table 3.1).  Minor dredging works (about 0.012 Mm3 in situ volume) will also be required to provide sufficient depth for the construction barges ([1]).  A small amount of rock trimming may be required to provide a level platform for seawall construction, which may be undertaken using a hydraulic breaker.

Rock fill is placed into the seawall trenches up to the existing seabed level to provide a foundation for the seawall blocks.  Sand fill is placed into the reclamation area to initially raise the ground level to +2.5 mPD after which, public fill is compacted in layers to the finished level of +6 mPD.  An extended period of consolidation or settlement of fill materials, and ground improvement works ([2]) such as the installation of vertical drain with surcharge pre-loading, are not anticipated using this method given the small size of the proposed reclamation.

At this stage it is expected that the seawall trenches and reclamation will be formed using sand/ rock/ public fill sourced locally or within the Pearl River Delta region.  The total volume of fill material needed is expected to be about 0.17 Mm3.

3.2.3                                Submarine Gas Pipeline Installation

The installation of two submarine natural gas pipelines connecting the new gas export facilities in southern Guangdong Province to the new GRSs at the BPPS will be required to deliver natural gas to fuel the power generation plant at Black Point.  The pipelines, in a size range of 32” – 42” (about 813 mm – 1067 mm) diameter, will have around 5 km in HKSAR waters.  According to the preliminary design the pipelines will be installed in two separate trenches about 100 m apart (distance between pipeline centrelines). 

The design of the submarine gas pipelines is described in Section 3.3.3.  Dredging of marine sediments and jetting will be required to bury the gas pipelines to a safe depth.  Dredging will be required for the shore approach and crossing the Urmston Road and will be undertaken in soft marine sediments with an approximate in situ quantity of 0.194 Mm3 for each pipeline trench required to be removed.  The remaining sections of the pipelines will be installed by jetting.

Approximately 0.329 Mm3 of rock and sand fill material shall be required to protect each pipeline from anchor drop and drag.

A summary of dredging and filling requirements for this Project is provided in Table 3.1.

Table 3.1        Summary of Dredging (in situ) and Filling (Bulk) Quantities of this Project

 

Pipeline 1

Pipeline 2

Reclamation with Vertical Seawall

Reclamation Land Area

N/A

N/A

0.5 ha

Affected Seabed Footprint Area

7.8 ha

7.8 ha

1.35 ha

Dredging Volume

0.194 Mm3

0.194 Mm3

0.108 Mm3

Additional Dredging for Construction Barge

N/A

N/A

0.012 Mm3

Total Fill Required

0.329 Mm3

0.329 Mm3

0.170 Mm3

 

3.2.4                                GRS Construction

To accommodate the two GRSs at the BPPS, a total area of approximately 1.5 ha of land is needed.  Whilst about 0.5 ha of reclaimed land will be needed for the Second Phase GRS, the remaining 1 ha for the First Phase GRS will be from existing land within the site boundary of BPPS.  This piece of land is located next to the existing GRS of the BPPS.  The preliminary layout of the proposed reclamation is shown in Figure 3.3.

Facilities at the existing GRS of the BPPS will need to be modified or relocated to accommodate the First Phase GRS, referred to as the co-located GRS.  Such modification works will be undertaken prior to, and will continue in parallel with, the construction of the GRSs.  Details of the GRS construction works are described in Section 3.3.2.

3.3                                      Project Construction

3.3.1                                General Construction Sequence

The Project will involve two phases of construction works:

·            First Phase: installation of the first pipeline (Pipeline 1) and construction of the co-located GRS; and

·            Second Phase: installation of the second pipeline (Pipeline 2) and construction of the reclamation and the associated GRS.

The construction of the two phases is expected to be separate with the First Phase construction commencing in 2011 in order to receive the replacement gas in 2012.  The Second Phase of construction is expected to commence within 24 months following commissioning of the First Phase.

The conceptual construction sequence is presented below.  It should be noted that this sequence has been based on the preliminary design and will be subject to further study at the detailed design stage.

1.         Site preparation for co-located GRS and construction within BPPS site boundary.

2.         Once approval is obtained to undertake marine works, dredging of the shore approach and Urmston Road crossing pipeline sections will be undertaken at the proposed locations for the installation of Pipeline 1 leading to the co-located GRS.

3.         Dredged material will be removed to approved disposal sites by barge.

4.         Use of suitable fill material for the bedding of the submarine gas pipeline, followed by pipeline laying and jetting (of applicable sections) and subsequent rock-filling as armour rock protection.

5.         Commissioning of Pipeline 1 and the co-located GRS.

6.         Once approval is obtained to undertake marine works, dredging will be undertaken at the proposed locations for seabed formation and seawall construction for the second GRS, as well as for the installation of Pipeline 2 leading to the reclamation.

7.         Dredged material will be removed to approved disposal sites by barge.

8.         Backfilling works to commence behind partially-completed seawalls to form the GRS reclamation.  A sand blanket layer followed by rock fill and soft soil materials, of suitable size and grading, will be deposited into the reclamation area until the required level is reached.

9.         Vertical seawall construction to commence, followed by backfilling to the formation level and the completion of the seawalls.

10.     Use of suitable fill material for the bedding of the submarine gas pipeline, followed by pipeline laying and jetting (of applicable sections) and subsequent rock-filling as armour rock protection.

11.     Construction of the GRS on the newly reclaimed land.

12.     Commissioning of Pipeline 2 and the associated GRS.

3.3.2                                GRS Construction

Design Basis

To accommodate the necessary gas receiving facilities of the GRS at least 0.5 ha of land is needed.  Facilities associated with the GRS are not complex and the site area requirements are small, generally comprising:

·           Emergency Shutdown valves;

·           PIG receiver, with associated service piping;

·           Station inlet header;

·           Inlet filter-separators (duty and standby runs);

·           Metering runs (duty and standby runs);

·           Pipeline gas heaters (duty and standby runs);

·           Pressure control runs (duty and standby runs);

·           Vent stack; and

·           Station export header.

Piping and equipment will generally be skid-mounted (size permitting) and placed on prepared concrete footings.  Larger piping and equipment assemblies will be delivered to site as discreet subassemblies and assembled on-site.  Sensitive instrumentation will be housed in air-conditioned instrument enclosures that are commonly prefabricated portable buildings.

Gas will be received via the offshore pipeline and the first major piece of equipment in the station will be an Emergency Shutdown (ESD) valve, which can be closed by means of the station ESD system in the event of an emergency, isolating the GRS from the source of gas.

Downstream of the ESD valve will be the station inlet header that will distribute the gas to inlet filter units.  Parallel to the inlet filters oriented inline with the incoming pipeline will be a pig receiver, enabling the running of cleaning and inspection pigs in the pipeline.  A schematic process flow diagram for the proposed new facilities is presented in Figure 3.4.

Downstream of the Gas Inlet filters, the gas passes through the metering skid and into the gas heaters, for gas conditioning, before the pressure of the gas is letdown at the pressure reduction station and supplied to the station export header.

Land Based Works for Co-located GRS (First Phase)

Co-location of the new GRS with the existing GRS of BPPS will require land clearance within the existing GRS site boundary to accommodate the new GRS facility.  To provide the required land area for the proposed new GRS, the existing vent stack is to be decommissioned and a new vent stack will be constructed to the northeast corner of the facility.  The existing GRS will be connected to the new vent stack.

Construction of the co-located GRS next to the existing GRS of BPPS will involve the following stages of modification and construction works (Figures 3.5a, b and c):

·            Stage 1: a new vent stack, which will be built on a structural tower support, will be constructed at the northeast corner of the GRS site.  New independent pipe racks that run adjacent to the current existing pipe rack will be constructed.  Minor preparation works will be undertaken at the vent header for tie-ins.  The existing vent stack will be decommissioned and removed from site.  New fences will be constructed at the boundary of the new GRS site.  Minor fencing modification works will also be undertaken at the existing GRS for accommodating the proposed future mixing facility.

·            Stage 2: the pipeline shore approach would be erected by breaking the existing seawall, trenching, installing a box culvert followed by the installation of the pipeline and riser.  Once the pipeline has been installed the trench would be backfilled and the seawall would be reinstated to its original condition.

·            Stage 3: all new pipe racks and pipe rack modification would be erected along side the existing GRS facilities.

·            Stage 4: New gas receiving facility (e.g. heating station, metering station, filtering station, pressure reduction facility and pig receiving station) will be constructed at the new GRS site, and the new pipeline will be connected to the new GRS.  Provision for a future mixing facility tie-in would be provided at the proposed location.

Marine Works for GRS on Reclamation (Second Phase)

The reclamation at BPPS will include the construction of permanent, vertical seawalls around the seaward boundaries of the reclamation.  Backfilling works for the reclamation are assumed to commence behind partially-completed seawalls.

Reclamation activities will include:

·            Dredging of sediments in the area where the seawall will be located.  A small amount of rock trimming may be required to provide a level platform for seawall construction;

·            Placement of sand and rock fill material and concreting works to construct the seawall; and

·            Infill of the area behind the seawall with sand and public fill materials to create the formed site.

The rock or public fill material will be brought in to the site by split-bottom or derrick barges.  These barges have been widely used in reclamation works throughout Hong Kong.  The rock filling or public filling will continue to be undertaken by derrick barges through end tipping, after the fill has reached a level of +6 mPD and treated with vibro-compaction.  The fill materials will be placed by truck and compacted by bulldozer in layer increments of 300 mm thickness or less.

The public fill materials could be obtained from existing fill banks, such as those located at Tuen Mun Area 38.  Transportation of materials from the fill bank will be the Contractor’s responsibility.  It could also be obtained from the public filling barging points at different locations around Hong Kong although the quality of the fill is difficult to control.

It is assumed that no marine borrow area would be allocated by the government within Hong Kong waters for sourcing sand for backfilling.  It is considered that the sand material can be readily sourced from the suppliers within the Pearl River Delta area, which has provided a steady supply of sand material to Hong Kong projects over the last few decades.  Assuming that sand may be sourced from these areas then the sand fill material will be brought in to the site by self-propelled pelican barges.

Pelican barges have been widely used in reclamation works as its application would not be limited by water depth.  With the aid of a conveyor belt installed at the front of the vessel, the sand material could be deposited up to a level of +2.5 mPD.  Marine access would be maintained throughout the construction period through good sequence planning such that the pelican barges can deposit the sand fill material at the designated deposition area.

3.3.3                                Submarine Natural Gas Pipeline Installation

Design Basis

The two proposed pipelines will be installed in two separate trenches (Figure 3.6).  The preferred alignment avoids direct impacts to ecologically sensitive habitats within the Sha Chau and Lung Kwu Chau Marine Park.  The alignment is also located at a sufficient distance from marine ecological sensitive receivers, such as mud flats, seagrass beds and areas of highest density of dolphin sightings.

Due to the relatively short construction time and proven installation methods, impacts to marine traffic are expected to be minimal.

The pipelines will have a design life of 25 years and will be situated below the seabed to a depth that would be dependent on the conditions and location of the area to be traversed.  The preliminary construction methodology for the pipelines is presented below covering both the onshore and submarine works.

Onshore Section of Pipeline

The land-based construction works associated with the Project would include laying the pipelines into open trenches followed by direct burial.  The pipelines would, typically, be buried at about 1 m below ground level within separate trenches a few metres wide.  An open cut method of construction would be used.  The pipelines would be coated with a protective coating and provided with cathodic protection.  Onshore works would be within the BPPS boundary.

Offshore Section of Pipeline: Pipeline Protection

The marine-based burial depth would typically be up to 5 m below the existing seabed level to the top of the pipe.  Typical cross sections of the trench designs that may be used for the submarine pipelines are shown in Figure 3.7.  For marine areas that are considered to pose a threat to the integrity of the pipeline system through anchor drop/drag, additional protective measures would be required and may include rock armouring.  The pipelines would be coated externally with an anti-corrosion coating and wrap and, would have an outer layer of steel reinforced concrete weight coating.  There are three types of protection proposed for the pipelines, as follows:

·            Type 1: 1.5 m burial with 0.5 m sand bedding and 1.5 m Armour Rock Protection;

·            Type 2: 5 m natural fill burial with 1 m Armour Rock Protection; and

·            Type 3: 3 m burial with 3 m Armour Rock Protection.

Trench Types 1 and 2 (Figure 3.7) are designed for Type 1 hazards (i.e., trawling and small anchors), with additional protection against dropped objects and small (2 – 5 MT) anchors within the landfall approaches of Black Point.  Protection measures will also prevent damage to the pipelines through any potential future dredging works.  Type 2 protection is applied for the majority of the route selection.

Trench Type 3 (Figure 3.7) provides maximum protection to the pipelines.  It is designed to protect against both Type 1 and Type 2 hazards, with additional protection against accidental anchor drop (up to 19 MT anchors) and drag by seagoing vessels.  This protection is provided at the location where the pipelines cross high density shipping areas (Urmston Road).

Pipe-laying

The lay-barge method is the most common form of pipeline installation.  It is a process whereby individual pipe lengths (usually 40 ft) are systematically welded on the lay-barge.  In the pipe-lay operation, the lay-barge winches itself forward after welding is completed.  In relative terms, the pipes, after welding, continue along a ramp for the checking of welds and to the field joint coating station.  The pipes then leave the barge and typically, go over a curved ramp known as a stinger before going into a suspended span in the water prior to touching down on the seabed.  The curvature of the pipeline in the suspended span is controlled by tension, applied through a tracked or wheeled tensioner system after the welding stations.

Dredging & Jetting

The proposed pipeline design requires a burial depth of 1.5 m to 5 m.  For submarine utility installations, dredging or jetting involves the removal/ displacement of marine sediments from the seabed to form the trench, into which the pipeline is laid.  Dredging/ jetting can be a comparatively fast way to construct a pipeline trench and is necessary in areas where extra pipeline protection is required (e.g. rock armour protection).  Many dredging techniques, such as grab, trailing suction hopper and cutter suction dredging are available and chosen depending on the prevailing environmental conditions (e.g. shear strength of marine deposits).  The selection of installation method for the gas pipelines has been discussed in Section 2 and depicted in Figure 3.6.

Dredging is planned to be carried out by grab dredgers, while jetting will be done by a jetting machine.  The potential impacts of these methods are discussed further in the Water Quality Impact Assessment (Section 6).

A summary of dredging requirements for different sections of the pipelines is provided in Table 3.2.  Pipeline sections are defined based on marine traffic pattern and the associated level of anchor drop/ drag risk for determining the pipeline protection requirements.

Table 3.2        Summary of Dredging Volume (in situ) for Different Sections for One Submarine Gas Pipeline

Pipeline Section

Approximate Length (m)

Approximate Trench Width (m)

Approximate Affected Seabed Area (ha)

Dredging Volume

Section 1

110

3

0.03

0.001 Mm3

Section 2

2,400

5

1.20

--

Section 3

1,800

35

6.19

0.193 Mm3

Section 4

750

5

0.38

--

Total

5,060

-

7.8

0.194 Mm3

Note: Sections 2 and 4 of the pipelines will be installed by jetting.

 

Armour Rock Placement

Rock armour is necessary to achieve adequate protection against anchor drop and drag.  The vessel will manoeuvre to the designated area where the rocks will be placed on top of the pipelines.  A barge will transport rocks from a quarry to the material storage barge. 

Rock dumping is based on the use of typical Hong Kong Derrick Lighters (1,800 – 3,000 T) configured to place rocks using grabs (as has been adopted in previous projects in Hong Kong).  These units have the capability to place 2,400/3,600 T/day of graded rock.  It is possible that the Contractor may elect to utilize specialized side-dump equipment for some of the deeper water areas (e.g. Trench Type 3).  It is also likely that the Contractor will manipulate the numbers of units working in any area depending on the equipment available at any time and on its actual progress vs planned.

Black Point Power Station Landfall

Upon arrival of the pipelines at BPPS the existing seawall will need to be opened to allow the pipelines to land.  In order to reduce the amount of demolition and later reinstatement works of the seawall structure it is proposed that a cofferdam shall be provided for the shore approach works.  Initially, the rock armour of the existing seawall will be removed across the width of the proposed cofferdam using a crane barge with a grab.

The cofferdam comprising parallel rows of sheet piles will then be installed through the seawall.  The cofferdam shall be formed perpendicular to the shoreline out to sea to a sufficient distance beyond the existing seawall.  Any remaining marine deposits within the shore approach cofferdam will be removed using grab dredgers.  The grab dredgers will also similarly be used in conjunction with onshore backhoes in the near shore areas to form the required approach profile through the BPPS seawall.  The excavated rockfill material from the seawall will be stored for later reinstatement works.

Once complete, the pipeline initiation operation will commence by winching the pipeline to shore through the pre-formed trench within the cofferdam structure.  Following installation of the pipeline the section of seawall within the pipeline trench will be reinstated by backfilling with the stored rockfill material previously removed from the BPPS seawall.  The sheet piles will be subsequently removed and the rock armour reinstated over the front of the seawall and around the pipeline structure.

3.4                                      Project Operation

Operation of the facilities will include the following aspects:

·           Receipt of natural gas via pipelines; and

·           Send out for use by the Black Point Power Station.

The proposed Project facilities are expected to be automated and unmanned during the operation phase.  However it is expected that during the early operation phase a few personnel will work at the GRSs.  It is also envisaged that maintenance activities will be scheduled and will be routine in nature.  As part of the EIA, hydrocarbon hazards have been identified and quantified for this specific project (Section 12). 

3.5                                      Project Summary

Table 3.3 presents a summary of the project details.  The proposed Project requires approximately 0.5 ha of reclaimed land, resulting in the construction of 200 m of new artificial coastline.  A maximum total dredged volume of 0.508 Mm3 (in situ volume) of marine sediments will be generated over the two phases of construction.  It is noted that First Phase Construction is expected to generate no more than 0.194 Mm3 (in situ volume) of marine sediments for off-site disposal.

 


Table 3.3        Summary Table of Key Issues

Issue

Summary

First Phase Construction – Pipeline 1 & Co-located GRS

Area of Seabed Affected by Pipeline Footprint

7.8 ha

Dredging Volume (in situ volume)

0.194 Mm3 for Submarine Gas Pipeline Trench

Length of Submarine Pipeline (km)

About 5 km in HKSAR waters

 

 

Second Phase Construction – Pipeline 2 & GRS on Reclamation

Reclaimed Land (ha)

0.5 ha

Area of Seabed Affected by Reclamation Footprint

1.35 ha

Area of Seabed Affected by Pipeline Footprint

7.8 ha

Length of New Artificial Seawall

200 m

Length of Existing Seawall Lost due to Reclamation

100 m

Dredging Volumes (in situ volume)

Gas Receiving Stations & Associated Seawalls

= 0.12 Mm3

 

Submarine Gas Pipeline Trench

= 0.194 Mm3

Length of Submarine Pipeline (km)

About 5 km in HKSAR waters

 

3.6                                      Project Programme

Depletion of the Yacheng 13-1 field is expected to start as early as 2012 and hence there is an urgent need for a replacement gas supply, and the timely permitting and construction of associated pipelines and facilities to bring this gas to Hong Kong is of prime importance.  The planning stage of the Project, including the EIA, engineering design and statutory permitting, has commenced in mid 2009.  The construction works of the Project should commence in 2011, dependent on timely receipt of various regulatory permits, in order to receive replacement gas in 2012.

The preliminary construction programme is provided in Figure 3.8.  As noted in the programme the present plan is that the Project will be constructed in phases.  The first pipeline and GRS (i.e. First Phase) must be completed in 2012 to provide facilities to accommodate a timely replacement for the Yacheng 13-1 gas supply. 

It is expected that the Second Phase could commence construction within 24 months of commissioning of the First Phase.  Whilst the construction of each of the submarine gas pipelines is expected to be completed in approximately 10 months, site formation works for the reclamation (Second Phase) would be expected to take 8 months. 

3.7                                      Concurrent Projects

3.7.1                                Installation of Submarine Gas Pipeline(s) in PRC Waters

Installation of Pipeline 1 in PRC waters is expected to follow the broad construction programme of First Phase construction of this Project to allow gas delivery.  In the absence of detailed implementation schedule it is conservatively assumed that dredging works in PRC waters may be concurrent with those in HKSAR waters.

Given that Second Phase construction of this Project is expected to commence within 24 months following commissioning of the first pipeline and GRS, installation of Pipeline 2 in PRC waters is expected to take place within the same timeframe.

3.7.2                                Other Concurrent Construction Projects

At present the only known projects that is planned to be constructed in sufficient proximity of the proposed GRSs at BPPS and the submarine gas pipelines are the following HKSAR Government projects:

·            Sludge Treatment Facilities, which have been proposed to be located at Tsang Tsui (i.e. east of the existing CAPCO Ash Lagoons at Tsang Tsui and west of the WENT Landfill) at > 1.2 km from the proposed reclamation and pipelines; and

·            West New Territories (WENT) Landfill Extensions, which have been proposed to extend to the hilly terrain next to the BPPS and the areas of the existing CLP Ash Lagoons at Tsang Tsui.

The Sludge Treatment Facilities are currently scheduled to commence construction in early 2010 for completion by the end of 2012.  However, given the separation distance cumulative impacts are unlikely to occur.  The WENT Landfill Extensions are scheduled to commence its first phase construction in 2016 when this Project is expected to be in operation.  Cumulative impacts are therefore also unlikely to occur.

Information from the Shenzhen Port Tonggu Channel Developing Office indicates that maintenance dredging of the Tonggu Waterway may take place annually.  Updated information to determine if there is any overlap with the construction for this Project is not available and this will be reviewed at a later stage.

Various activities have been proposed for the Nim Wan and Tsang Tsui areas including an Animal Carcass Treatment Facility and Waste-to-energy Facility.  The programmes for these projects remain uncertain.  Nevertheless, the separation distance from this Project (at least 2 km from Black Point) is such that cumulative impacts are unlikely to occur. 

Latest information ([3]) ([4]) ([5]) has suggested that the HK-Zhuhai-Macau Bridge (HZMB) is targeted to be commissioned by 2015.  The construction schedules of the HZMB and associated facilities are as follows:

·            Construction of the Hong Kong Link Road (HKLR) will start in 2011, for completion in 2015, with a construction period of 4 years;

·            Construction of the Hong Kong Boundary Crossing Facilities (HKBCF) will start in the 3rd quarter of 2010, for first phase completion by End 2015, and second (final) phase completion by End 2016.

·            Construction for the Tuen Mun - Chek Lap Kok Link (TM-CLKL) will commence in late 2011, with a target opening date for the entire road link at the end of 2016.  However, the part of the southern reclamation may be carried out in conjunction with the reclamation for HKBCF which will commence earlier and in the 3rd quarter of 2010.

Therefore, these projects may be constructed concurrently with the construction works of the submarine pipelines.  No other projects are presently planned to be constructed in sufficient proximity to the Project to cause cumulative effects.  Cumulative assessments where applicable have been conducted and are presented in the relevant technical section in the remainder of this EIA Report.

 

 



([1])         Electromagnetic survey data and results of geotechnical investigation revealed that the seabed is dipping down from the existing shoreline towards the sea.  The seabed level at the far edge of the reclamation is approximately -3 mPD.  Assuming the low tide water level to be at +0 mPD and the minimum water depth required for construction barge is 4 m, minor additional dredging may be required to allow marine access during the construction stage.

([2])         Typically ground improvement works are required to reduce the differential settlement occurred within the marine mud layer.

([3])         AECOM (2009) Tuen Mun - Chek Lap Kok Link: EIA Report. Prepared for Highways Department

([4])         ARUP (2009) Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities: EIA Report. Prepared for Highways Department

([5])         ARUP (2009) Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road: EIA Report. Prepared for Highways Department