This section identifies the potential wastes arising from
the construction and operation of the two proposed submarine gas pipelines and
Gas Receiving Stations (GRSs) to the north of the
Black Point Power Station (BPPS), and assesses the environmental impacts
associated with waste handling and disposal. The main issues are:
·
Management
of dredged marine sediment;
·
Handling
and disposal of contaminated soil/sediments;
·
Handling
and disposal of construction and demolition (C&D) materials ([1])
arising from the reclamation
works; and
·
Chemical
wastes, sewage, general refuse and industrial wastes from work vessels and
equipment.
7.2
Relevant Legislation & Assessment Criteria
The following discussion on legislative requirements
and evaluation criteria applies to both the construction and operation phases
of the proposed Project.
The criteria and guidelines for evaluating potential
waste management implications are laid out in Annexes 7 and 15 of the EIAO TM under the EIAO (Cap 499). The
following legislation covers, or has some bearing upon the handling, treatment
and disposal of the wastes generated from the construction and operation of the
proposed Project.
·
Waste Disposal Ordinance (Cap 354);
·
Waste Disposal (Chemical Waste) (General)
Regulation (Cap 354C);
·
Land (Miscellaneous Provisions) Ordinance (Cap
28);
·
Public Health and Municipal Services
Ordinance (Cap 132) - Public Cleansing and Prevention of Nuisances Regulation; and
·
Dumping at Sea Ordinance (Cap 466).
Details on each of the above are presented below.
7.2.1
Waste Disposal Ordinance (Cap 354)
The Waste
Disposal Ordinance (WDO) prohibits the unauthorised disposal of wastes,
with waste defined as any substance or article, which is abandoned. Construction waste is not directly
defined in the WDO but is considered to fall within the category of ‘trade waste’. Trade waste is defined as waste from any
trade, manufacturer or business or any wasted building, or civil engineering
materials, but does not include animal waste.
Under the WDO, wastes can only be disposed of at a
licensed site. The WDO provides for
the issuing of licences for the collection and transport of wastes. Licences are not, however, currently
issued for the collection and transport of construction waste or trade waste.
The Waste
Disposal (Charges for Disposal of Construction Waste) Regulation defined
construction waste as any substance, matters or things that is generated from
construction work and abandoned, whether or not it has been processed or
stockpiled before being abandoned.
It does not include any sludge, screening or matter removed in or
generated from any desludging, desilting
or dredging works.
The Construction Waste Disposal Charging Scheme
entered into operation on 1 December 2005.
From that time, the main contractor who undertakes construction work
under a contract with value of HK$1 million or above is required to open a
billing account solely for the contract for waste disposal. Application shall be made within 21 days
after the contract is awarded.
For construction work under a contract with value
less than $1 million, such as minor construction or renovation work, any person
such as the owner of the premises where the construction work takes place or
his/her contractor can open a billing account; the account can also be used for
contracts each with value less than $1 million. The premises owner concerned may also
engage a contractor with a valid billing account to make arrangement for
disposal of construction waste.
Under the Construction Waste Disposal Charging Scheme,
charging for disposal of construction waste started on 20 January 2006 and
therefore will apply to this Project.
Depending on the percentage of inert materials in the
construction waste, inert construction waste can be disposed of at public fill
reception facilities. However mixed
construction waste can be disposed of at construction waste sorting facilities,
landfills and outlying islands transfer facilities which have different
disposal costs. The scheme
encourages reducing, reusing and sorting of construction waste such that the
waste producer can reduce their disposal fee. Table
7.1 summarises the government construction waste disposal facilities, types
of waste accepted and disposal cost.
Table 7.1 Government
Facilities for Disposal of C&D Materials
Government Waste Disposal Facilities |
Type of Construction Waste Accepted |
Charge (HK$/ Tonne) |
Public Fill
Reception Facilities |
Consisting
entirely of inert construction waste |
$27 |
Sorting Facilities |
Containing more
than 50% by weight of inert construction
waste |
$100 |
Landfills |
Containing not
more than 50% by weight of inert construction
waste |
$125 |
Outlying Facilities |
Containing any percentage
of inert construction waste |
$125 |
7.2.2
Waste Disposal (Chemical Waste) (General)
Regulation (Cap 354C)
Chemical waste as defined under the Waste Disposal (Chemical Waste) (General)
Regulation includes any substance being scrap material, or unwanted
substances specified under Schedule 1
of the Regulation, if the specified
substance or chemical occurs in such a form, quantity or concentration so as to
cause pollution or constitute a danger to health or risk of pollution to the
environment.
A person should not produce, or cause to be produced,
chemical wastes without registration with the EPD. Chemical wastes must either be treated
using on-site facility licensed by EPD or be collected by a licensed collector
for off-site treatment at a licensed facility. Under EPD regulations, the waste
producer, collector and disposal facility must sign all relevant parts of a
computerised trip ticket for each consignment of waste. The computerized system is designed to
allow the transfer of wastes to be traced from cradle-to-grave.
The EPD Regulation
prescribes storage facilities to be provided on site which include labelling
and warning signs. To reduce the
risks of pollution and danger to human health or life, the waste producer is
required to prepare and make available written emergency procedures for
spillage, leakage or accidents arising from the storage of chemical
wastes. They must also provide
their employees with training on such procedures.
7.2.3
Land (Miscellaneous Provisions) Ordinance
(Cap 28)
The inert portion of C&D materials (also called
public fill) may be taken to public fill reception facilities. Public fill reception facilities usually
form part of land reclamation schemes and are operated by the Civil Engineering
and Development Department (CEDD) and others. The Land
(Miscellaneous Provisions) Ordinance requires that individuals or companies
who deliver public fill to the public fill reception facilities to obtain a Dumping Licence from the CEDD. Individual licences and windscreen
stickers are issued for each vehicle involved.
Under the licence conditions, public fill reception
facilities will only accept earth, soil, sand, rubble, brick, tile, rock,
boulder, concrete, asphalt, masonry or used bentonite. In addition, in accordance with Paragraph 11 of the ETWBTC(W) No. 31/2004 ([2]), Public Fill Committee will advise on the
acceptance criteria (e.g. no mixing of construction waste, nominal size of the
materials less than 250 mm, etc).
The material should, however, be free from marine mud, household refuse,
plastic, metal, industrial and chemical wastes, animal and vegetable matter and
any other materials considered unsuitable by the public fill reception facility
supervisor.
7.2.4
Public Health and Municipal Services
Ordinance (Cap 132) - Public Cleansing and Prevention of Nuisances Regulation
This Regulation provides a further control on the
illegal dumping of wastes on unauthorised (unlicensed) sites.
7.2.5
Dumping at Sea Ordinance (Cap 466)
The Dumping at
Sea Ordinance (DASO) came into
operation in April 1995 and empowers the Director of Environmental Protection
(DEP) to control the disposal and incineration of substances and articles at
sea for the protection of the marine environment. Under the DASO, a permit from the DEP is required for the disposal of
regulated substances within and outside the waters of the Hong Kong SAR. The permit contains terms and conditions
that includes the following specifications:
·
Type
and quantity of substances permitted to be dumped;
·
Location
of the disposal grounds;
·
Requirement
of equipment for monitoring the disposal operations; and
·
Environmental
monitoring requirements.
Management of Dredged/ Excavated Sediments for Marine Disposal
Marine disposal of any dredged/excavated sediment is
subject to control under the Dumping at
Sea Ordinance (DASO). Dredged/
excavated sediment destined for marine disposal is classified based on its
contaminant levels with reference to the Chemical Exceedance
Levels (CEL), as stipulated in PNAP 252:
Management Framework for Disposal of Dredged/ Excavated Sediment ([3]).
This practice note includes a set of sediment quality criteria, as
presented in Table 7.2, which
includes heavy metals and metalloids, organic pollutants and a class of
contamination level for highly contaminated sediment not suitable for marine
disposal.
Table 7.2 Dredged/
Excavated Sediment Quality Criteria for the Classification under the PNAP 252
Contaminant |
Lower Chemical Exceedance Level (LCEL) |
Upper Chemical Exceedance Level (UCEL) |
Metal (mg kg-1
dry weight) |
||
Cadmium (Cd) |
1.5 |
4 |
Chromium (Cr) |
80 |
160 |
Copper (Cu) |
65 |
110 |
Mercury (Hg) |
0.5 |
1 |
Nickel (Ni) (a) |
40 |
40 |
Lead (Pb) |
75 |
110 |
Silver (Ag) |
1 |
2 |
Zinc (Zn) |
200 |
270 |
Metalloid (mg kg-1
dry weight) |
||
Arsenic (As) |
12 |
42 |
Organic-PAHs (mg
kg-1 dry weight) |
||
Low Molecular Weight (LMW) PAHs |
550 |
3,160 |
High Molecular Weight (HMW) PAHs |
1,700 |
9,600 |
Organic-non-PAHs (mg
kg-1 dry weight) |
||
Total PCBs |
23 |
180 |
Organometallics
(mg
TBT l-1 in interstitial water) |
||
Tributyl-tin (a) |
0.15 |
0.15 |
(a) The contaminant level is considered to have exceeded
the UCEL if it is greater than the value shown.
The DEP, as the Authority under the DASO, will classify sediments based on their
contaminant levels with reference to the CEL laid down in Table 7.2. In
accordance with PNAP 252, the
sediment is classified into three categories based on its contamination levels:
Category L: Sediment with all
contaminant levels not exceeding the LCEL.
The material must be dredged, transported and disposed of in a manner
which reduces the loss of contaminants either into solution or by
re-suspension.
Category M: Sediment with any one or more
contaminants in the sediment exceeding the LCEL with none exceeding the
UCEL. The material must be dredged
and transported with care, and must be effectively isolated from the
environment upon final disposal unless appropriate biological tests demonstrate
that the material will not adversely affect the marine environment.
Category H: Sediment with any one or more
contaminants in the sediment exceeding the UCEL. The material must be dredged and
transported with great care, and must be effectively isolated from the
environment upon final disposal.
Figure 7.1 summarises the sediment classification and disposal arrangements. EPD
will use the sediment and biological test results to determine the most
appropriate disposal site (e.g. open sea or confined marine disposal site).
In addition, in accordance with Building Ordinance Office Practice Note for
Authorised Persons and Registered Structural Engineers No 155, any proposal
to remove more than 500,000 m3 of clean mud or any quantity of
contaminated mud must be justified on both cost and environmental grounds. The rationale for such removal will also
be provided to enable an allocation for disposal to be considered. Therefore it is desirable to demonstrate
that any proposed mud dredging has been reduced as far as reasonably and safely
practicable and to obtain, in-principle, an agreement from the Secretary of the
Marine Fill Committee (MFC) of the CEDD at an early stage.
7.2.6
Other Relevant Guidelines
Other guideline documents which detail how the Contractor
will comply with the WDO and its associated regulations include:
·
Waste Disposal Plan for Hong Kong (December 1989), Planning, Environment
and Lands Branch Government Secretariat,
·
Chapter 9 - Environment (1999), Hong Kong Planning Standards and
Guidelines,
·
New Disposal Arrangements for Construction
Waste (1992), EPD &
CED,
·
Code of Practice on the Packaging,
Labelling and Storage of Chemical Wastes (1992), EPD,
·
Works Branch Technical Circular (WBTC) No.
32/92, The Use of Tropical Hard Wood on Construction Site, Works Branch,
·
WBTC No. 2/93, Public Dumps, Works Branch,
·
WBTC No. 2/93B, Public Filling Facilities, Works Branch,
·
WBTC No. 16/96, Wet Soil in Public Dumps, Works Branch,
·
WBTC Nos. 4/98 and 4/98A, Use of Public
Fill in Reclamation and Earth Filling Projects, Works Bureau,
·
Waste Reduction Framework Plan, 1998 to
2007, Planning,
Environment and Lands Bureau, Government Secretariat, 5 November 1998;
·
WBTC Nos. 25/99, 25/99A and 25/99C,
Incorporation of Information on Construction and Demolition Material Management
in Public Works Subcommittee Papers; Works Bureau,
·
WBTC No. 12/2000, Fill Management, Works Bureau,
·
WBTC No. 19/2001, Metallic Site Hoardings
and Signboards, Works
Bureau,
·
WBTC Nos. 6/2002 and 6/2002A, Enhanced
Specification for Site Cleanliness and Tidiness, Works Bureau,
·
WBTC No. 11/2002, Control of Site Crusher, Works Bureau,
·
WBTC No. 12/2002, Specification
Facilitating the Use of Recycled Aggregates. Works Bureau,
·
ETWBTC(W) No. 33/2002, Management of
Construction and Demolition Material Including Rock; Environment, Transport and Works Bureau,
·
PNAP 252 (ADV-21), Management Framework
for Disposal of Dredged/ Excavated Sediment; Buildings Department,
·
ETWBTC(W) No. 31/2004, Trip Ticket System
for Disposal of Construction & Demolition Materials, Environment, Transport and Works Bureau,
Hong Kong SAR Government; and
·
ETWBTC(W)
No. 19/2005, Environmental Management of Construction Site, Environment, Transport and Works Bureau,
7.3.1
Construction Phase
Optioneering has been conducted to try to avoid waste generation
and reuse and recycling of waste generated from the construction of the
proposed facilities. During the
planning and design stages, options for layout, construction methods and
programme have been considered and the proposed scheme comprises the proposed
best balance. Section 2 contains more discussion on the alternatives that were
considered to reduce the volumes of dredged mud generated by this Project.
During the construction phase, the main activities
that will result in generation of waste include dredging, reclamation, seawall
construction, filling and concreting.
The typical waste types associated with these activities include:
·
Dredged
marine sediment;
·
C&D
materials;
·
Chemical
wastes;
·
Sewage;
and
·
General
refuse.
7.3.2
Operation Phase
The proposed Project facilities are expected to be
automated and unmanned during the operation phase. However it is expected that during the
early operation phase a few personnel will work at the GRSs
and thus a small amount of solid wastes/ by-products and sewage may be
generated.
It is also envisaged that a very small amount of
wastes, primarily industrial wastes and chemical wastes, will be generated from
routine maintenance activities.
7.4
Waste Management
Assessment
7.4.1
Assessment Methodology
The potential environmental impacts associated with
the handling and disposal of waste arising from the construction and operation
of the Project facilities at BPPS were assessed in accordance with the criteria
presented in Annexes 7 and 15 of the EIAO-TM and summarised as follows:
·
Estimation
of the types (i.e. quality), timing and quantities of the wastes to be
generated based on information provided by the engineering design team and the
relevant researches and studies on waste generation;
·
Assessment
of the secondary environmental impacts due to the management of waste with
respect to potential hazards, air and odour emissions, noise, wastewater
discharges and traffic; and
·
Assessment
of the potential impacts on the capacity of waste collection, transfer and
disposal facilities.
7.4.2
Construction Phase Impact Assessment
Dredged Marine Sediment
Marine dredging will be required for the construction
of the submarine pipelines and the GRS reclamation (see Section 3.2 for further details). The quantities of sediment to be dredged
are considered as the best estimate based on the preliminary engineering design
and available geotechnical investigation data (e.g. depth of marine deposits)
(see Table 3.1).
The first pipeline and GRS (i.e. First Phase) must be
completed in 2012 to provide facilities to accommodate a timely replacement for
the Yacheng 13-1 gas supply. It is expected that the Second Phase
could commence construction within 24 months of commissioning of the First
Phase.
For the construction of submarine gas
pipelines (approximately 5 km in HKSAR waters) dredging will be required for
certain sections of the pipeline alignment for trenching to provide the
necessary burial depths (1.5 m to 3 m below the existing seabed level to the
top of the pipe; see Section 3.3.3). Approximately 0.194 Mm3 (in situ volume, 0.253 Mm3 for
bulk volume) of marine sediment will be dredged for each pipeline (Table 7.3).
Approximately 0.5 ha of land will be
reclaimed next to the BPPS to provide land for a GRS. Works will also include the construction
of an approximately 200 m long vertical seawall. The seawall trenches will be constructed
with minimal dredging (see Section 2.2),
and a total of approximately 0.12 Mm3 of marine sediment (in situ volume) will be dredged (Table 7.3). The dredging work will be carried out
for approximately two months, not expected to commence earlier than the second
half of 2013 during the Second Phase construction ([4])
(Table 7.4, Figure 3.8).
The dredging work for the first pipeline (Pipeline 1)
will commence in 2011 during the First Phase Construction, while that for the
second pipeline (Pipeline 2) is expected to commence at the same time as the
dredging work for the reclamation, i.e. no earlier than the second half of 2013
during the Second Phase construction (Table
7.4). Dredging work for each
pipeline is expected to be completed within three months.
Table 7.3 Summary
of Dredging Volume of this Project (Phased Construction)
Proposed Facility |
Estimated Dredging Volume (Mm3) |
|
|
In situ |
Bulk * |
Reclamation with Vertical Seawall |
0.108 |
0.140 |
Additional Dredging for Reclamation Construction
Barge |
0.012 |
0.016 |
Pipeline 1 |
0.194 |
0.253 |
Pipeline 2 |
0.194 |
0.253 |
Total Volume |
0.508
|
0.662 |
*Bulk Factor: 1.3
Table 7.4 Summary
of Dredged Material Arisings of this Project (Phased
Construction)
Year |
Sediment disposal requirement as per PNAP 252 (in Mm3) |
|
|
In situ |
Bulk * |
1st Half of 2011 (First Phase
Construction) |
0.194 |
0.253 |
2nd Half of 2011 |
-- |
-- |
1st Half of 2012 |
-- |
-- |
2nd Half of 2012 |
-- |
-- |
1st Half of 2013 |
-- |
-- |
2nd Half of 2013 (Second Phase
Construction) |
0.314 |
0.409 |
Total Volume |
0.508 |
0.662 |
*Bulk Factor: 1.3
Contaminated Dredged Marine Sediment
A marine sediment sampling programme has been undertaken
as part of this EIA Study to provide an indication of the quality of the
sediment and the volumes of different types of sediment to be dredged. The sediment sampling programme
(including the sampling stations, the chemical analysis suite and the
biological testing programmes) was developed based on the guidelines described
in PNAP 252 ([5]).
The contaminants tested include all the contaminants stated in Table
1 - Analytical Methodology in Appendix B of PNAP 252, and all
sediment samples were evaluated for sediment quality parameters as listed in
the Appendix A of the PNAP 252.
The sampling and testing programmes are summarised in
Table 7.5 and the sampling locations
presented in Figure 7.2.
A combination of grab samples and vibrocore
samples were taken within the proposed Project area. Whilst grab samples were
taken from the seabed, vibrocore samples were taken
vertically either down to the proposed dredging depth (i.e. at seabed, 0.9 m,
1.9 m, 2.9 m below the seabed, every 3 m thereafter and at the end of the vibrocore sampling) or upon refusal, or when encountering
rock head in order to determine the depth of contaminated marine deposit. The grab sampling programme was
conducted in March 2009, whereas the vibrocore
sampling programme was conducted in July-August 2009.
Table 7.5 Marine
Sediment Sampling and Testing Programme
Sampling Location |
PNAP 252 Grab (March 2009 – Chemical Screening only)(a) |
PNAP 252 Vibrocore (July-August 2009 – Chemical & Biological Screening) (b) |
Pipeline Corridor |
|
|
GS 09-01 |
ü |
|
GS 09-02 |
ü |
|
GS 09-03 |
ü |
|
GS 09-04 |
ü |
|
GS 09-05 |
ü |
|
GS 09-06 |
ü |
|
GS 09-07 |
ü |
|
GS 09-08 |
ü |
|
GS 09-09 |
ü |
|
GS 09-10 |
ü |
|
|
ü |
|
GSVB2 |
|
ü |
GSVB3 |
|
ü |
GSVB4 |
|
ü |
GSVB5 |
|
ü |
GSVB6 |
|
ü |
GSVB7 |
|
ü |
GSVB8 |
|
ü |
GSVB9 |
|
ü |
GSVB10 |
|
ü |
Proposed
GRS Reclamation |
|
|
GSVB11 |
|
ü |
GSVB12 |
|
ü |
Notes:
(a) All
sediment grab samples were analysed for sediment quality parameters as listed
in the Appendix A of the PNAP 252.
(b) Vibrocore samplings were conducted and samples analysed for
sediment quality parameters as listed in the Appendix A of the PNAP 252
at these locations.
Results of the grab sampling programme indicated that
all 10 grab samples tested have negligible concentration of toxic organics
since they were all below the detection limits of the chemical analysis (Table
7.6). Heavy metal concentrations, aside from
the arsenic metalloid, in sediment samples obtained in all 10 locations (GV
09-01 to GV 09-10) within the proposed dredging areas were below the LCEL. Concentrations of arsenic
in all 10 samples exceeded the LCEL but were below the UCEL.
Similarly, results of the vibrocore
sampling programme showed that all 50 vibrocore
samples tested have negligible concentration of toxic organics (Table 7.6). Sediment from 9 of the 50 samples tested
were found to be uncontaminated (i.e. sediment with all contaminant levels not
exceeding the LCEL). Concentrations
of arsenic in the remaining 41 samples tested, exceeded the LCEL but were below
the UCEL. All other heavy metal
concentrations in these sediment samples were below the LCEL, except in three
samples in which the copper (GSBV9 1.9-2.9m) and lead (GSBV5 0.0-0.9m and
GSBV10 2.9-3.9m) concentrations exceeded the LCEL but were below the UCEL. Sediment from these locations and depths
were thus classified as Category M contaminated materials.
Table 7.6 Results
of Marine Sediment Testing in March and July/ August2009
Heavy Metals (mg kg-1) |
Organics (mg kg-1) |
Organo-metallics (mg TBT l-1) |
Biological Sample No. |
Failed Biological Test |
Sediment Category |
Disposal Option |
||||||||||||||
Sample ID |
Depth (m) From-To |
Silver (Ag) |
Arsenic (As) |
Cadmium (Cd) |
Chromium (Cr) |
Copper (Cu) |
Nickel (Ni) |
Lead (Pb) |
Zinc (Zn) |
Mercury (Hg) |
Total PCB |
LMW PAHs |
HMW PAHs |
Tributyl-tin (TBT) |
Amphipod |
Bivalve |
Polychaete |
|||
Reporting Limits |
0.1 |
1 |
0.2 |
1 |
1 |
1 |
1 |
1 |
0.05 |
3 |
550 |
1700 |
0.005 |
|
|
|
|
|
|
|
LCEL |
1 |
12 |
1.5 |
80 |
65 |
40 |
75 |
200 |
0.5 |
23 |
550 |
1700 |
0.15 |
|
|
|
|
|
|
|
UCEL |
2 |
42 |
4 |
160 |
110 |
40 |
110 |
270 |
1 |
180 |
3160 |
9600 |
0.15 |
|
|
|
|
|
|
|
GS
09-01 |
|
0.5 |
15 |
< 0.2 |
54 |
63 |
37 |
55 |
155 |
0.14 |
< 3 |
< 550 |
< 1700 |
-- |
- |
|
|
|
M |
- |
GS
09-02 |
|
0.3 |
14 |
< 0.2 |
41 |
41 |
26 |
42 |
134 |
0.09 |
< 3 |
< 550 |
< 1700 |
-- |
- |
|
|
|
M |
- |
GS
09-03 |
|
0.3 |
13 |
< 0.2 |
35 |
34 |
23 |
41 |
122 |
0.08 |
< 3 |
< 550 |
< 1700 |
-- |
- |
|
|
|
M |
- |
GS
09-04 |
|
0.1 |
24 |
< 0.2 |
28 |
17 |
21 |
72 |
126 |
< 0.05 |
< 3 |
< 550 |
< 1700 |
-- |
- |
|
|
|
M |
- |
GS
09-05 |
|
0.1 |
16 |
< 0.2 |
28 |
12 |
14 |
29 |
70 |
< 0.05 |
< 3 |
< 550 |
< 1700 |
-- |
- |
|
|
|
M |
- |
GS
09-06 |
|
0.4 |
20 |
0.2 |
47 |
45 |
29 |
40 |
128 |
0.10 |
< 3 |
< 550 |
< 1700 |
-- |
- |
|
|
|
M |
- |
GS
09-07 |
|
0.2 |
14 |
< 0.2 |
29 |
23 |
18 |
28 |
80 |
0.06 |
< 3 |
< 550 |
< 1700 |
-- |
- |
|
|
|
M |
- |
GS
09-08 |
|
0.1 |
14 |
< 0.2 |
39 |
16 |
22 |
34 |
92 |
< 0.05 |
< 3 |
< 550 |
< 1700 |
-- |
- |
|
|
|
M |
- |
GS
09-09 |
|
0.2 |
18 |
< 0.2 |
41 |
22 |
25 |
40 |
107 |
< 0.05 |
< 3 |
< 550 |
< 1700 |
-- |
- |
|
|
|
M |
- |
GS
09-10 |
|
0.2 |
18 |
< 0.2 |
43 |
26 |
28 |
40 |
111 |
0.08 |
< 3 |
< 550 |
< 1700 |
-- |
- |
|
|
|
M |
- |
GSVB1 |
0.1-0.9m |
0.4 |
18 |
0.2 |
51 |
43 |
32 |
57 |
135 |
0.15 |
< 3 |
< 550 |
< 1700 |
-- |
1 |
|
|
|
M |
Type 1
Dedicated |
|
0.9-1.9m |
0.4 |
22 |
0.3 |
57 |
56 |
35 |
59 |
147 |
0.18 |
< 3 |
< 550 |
< 1700 |
-- |
2 |
|
|
|
M |
Type 1
Dedicated |
|
1.9-2.9m |
0.3 |
18 |
< 0.2 |
53 |
46 |
30 |
66 |
132 |
0.16 |
< 3 |
< 550 |
< 1700 |
-- |
3 |
|
|
|
M |
Type 1
Dedicated |
|
6.0-6.9m |
0.3 |
18 |
< 0.2 |
49 |
40 |
30 |
52 |
124 |
0.11 |
< 3 |
< 550 |
< 1700 |
-- |
4 |
|
|
|
M |
Type 1
Dedicated |
|
6.9-7.9m |
< 0.1 |
11 |
< 0.2 |
25 |
12 |
15 |
28 |
53 |
0.07 |
< 3 |
< 550 |
< 1700 |
-- |
5 |
|
|
|
L |
Type 1 |
GSVB2 |
0.5-0.9m |
0.3 |
17 |
< 0.2 |
51 |
46 |
31 |
50 |
124 |
0.13 |
< 3 |
< 550 |
< 1700 |
-- |
6 |
|
|
|
M |
Type 1
Dedicated |
|
0.9-1.9m |
0.2 |
15 |
< 0.2 |
46 |
36 |
26 |
54 |
107 |
0.12 |
< 3 |
< 550 |
< 1700 |
-- |
7 |
|
|
|
M |
Type 1
Dedicated |
|
1.9-2.9m |
0.1 |
17 |
< 0.2 |
34 |
21 |
19 |
41 |
76 |
0.14 |
< 3 |
< 550 |
< 1700 |
-- |
8 |
x |
|
|
Mfail |
Type 2 |
|
6.0-6.4m |
< 0.1 |
14 |
< 0.2 |
40 |
17 |
18 |
34 |
67 |
< 0.05 |
< 3 |
< 550 |
< 1700 |
-- |
9 |
|
|
|
M |
Type 1
Dedicated |
GSVB3 |
0.8-0.9m |
0.3 |
14 |
< 0.2 |
41 |
42 |
25 |
38 |
104 |
0.14 |
< 3 |
< 550 |
< 1700 |
-- |
-+ |
|
|
|
M |
Type 1
Dedicated |
|
0.9-1.9m |
0.1 |
18 |
< 0.2 |
37 |
23 |
22 |
43 |
87 |
0.11 |
< 3 |
< 550 |
< 1700 |
-- |
10 |
x |
|
|
Mfail |
Type 2 |
|
1.9-2.9m |
0.1 |
14 |
< 0.2 |
41 |
17 |
27 |
30 |
94 |
0.07 |
< 3 |
< 550 |
< 1700 |
-- |
11 |
|
|
|
M |
Type 1
Dedicated |
|
2.9-3.9m |
0.1 |
14 |
< 0.2 |
44 |
18 |
29 |
33 |
98 |
0.07 |
< 3 |
< 550 |
< 1700 |
-- |
12 |
x |
|
|
Mfail |
Type 2 |
GSVB4 |
0.1-0.9m |
0.1 |
10 |
< 0.2 |
30 |
12 |
17 |
40 |
80 |
0.08 |
< 3 |
< 550 |
< 1700 |
-- |
13 |
x |
|
|
Mfail |
Type 2 |
|
0.9-1.9m |
0.1 |
16 |
< 0.2 |
40 |
15 |
25 |
34 |
94 |
0.09 |
< 3 |
< 550 |
< 1700 |
-- |
14 |
x |
|
|
Mfail |
Type 2 |
|
1.9-2.9m |
0.1 |
14 |
< 0.2 |
39 |
16 |
25 |
34 |
93 |
0.09 |
< 3 |
< 550 |
< 1700 |
-- |
15 |
x |
|
|
Mfail |
Type 2 |
|
2.9-3.9m |
0.2 |
17 |
< 0.2 |
44 |
16 |
26 |
35 |
96 |
0.07 |
< 3 |
< 550 |
< 1700 |
-- |
16 |
x |
|
x |
Mfail |
Type 2 |
GSVB5 |
0.0-0.9m |
0.2 |
27 |
< 0.2 |
32 |
19 |
22 |
81 |
111 |
0.06 |
< 3 |
< 550 |
< 1700 |
-- |
17 |
|
|
|
M |
Type 1
Dedicated |
|
0.9-1.9m |
0.1 |
16 |
< 0.2 |
45 |
18 |
30 |
35 |
105 |
0.09 |
< 3 |
< 550 |
< 1700 |
-- |
18 |
x |
|
|
Mfail |
Type 2 |
|
1.9-2.9m |
0.1 |
14 |
< 0.2 |
38 |
16 |
25 |
29 |
89 |
0.07 |
< 3 |
< 550 |
< 1700 |
-- |
19 |
|
|
x |
Mfail |
Type 2 |
|
2.9-3.9m |
0.1 |
18 |
< 0.2 |
39 |
16 |
25 |
29 |
88 |
0.09 |
< 3 |
< 550 |
< 1700 |
-- |
20 |
|
|
|
M |
Type 1
Dedicated |
GSVB6 |
0.1-0.9m |
0.1 |
15 |
< 0.2 |
29 |
12 |
17 |
55 |
78 |
< 0.05 |
< 3 |
< 550 |
< 1700 |
-- |
21 |
|
|
|
M |
Type 1
Dedicated |
|
0.9-1.9m |
< 0.1 |
7 |
< 0.2 |
29 |
7 |
15 |
44 |
71 |
< 0.05 |
< 3 |
< 550 |
< 1700 |
-- |
22 |
|
|
|
L |
Type 1 |
|
1.9-2.9m |
< 0.1 |
7 |
< 0.2 |
32 |
8 |
17 |
34 |
73 |
< 0.05 |
< 3 |
< 550 |
< 1700 |
-- |
23 |
|
|
|
L |
Type 1 |
|
2.9-3.9m |
0.1 |
15 |
< 0.2 |
38 |
15 |
24 |
33 |
90 |
0.08 |
< 3 |
< 550 |
< 1700 |
-- |
24 |
|
|
|
M |
Type 1
Dedicated |
GSVB7 |
0.1-0.9m |
0.1 |
13 |
< 0.2 |
30 |
14 |
14 |
28 |
62 |
0.06 |
< 3 |
< 550 |
< 1700 |
-- |
25 |
|
|
|
M |
Type 1
Dedicated |
|
0.9-1.9m |
0.1 |
14 |
< 0.2 |
43 |
16 |
24 |
42 |
96 |
0.06 |
< 3 |
< 550 |
< 1700 |
-- |
26 |
|
|
|
M |
Type 1
Dedicated |
|
1.9-2.9m |
0.1 |
12 |
< 0.2 |
40 |
15 |
23 |
32 |
83 |
0.07 |
< 3 |
< 550 |
< 1700 |
-- |
27 |
|
|
|
L |
Type 1 |
|
2.9-3.9m |
0.1 |
14 |
< 0.2 |
40 |
16 |
23 |
33 |
83 |
0.07 |
< 3 |
< 550 |
< 1700 |
-- |
28 |
x |
|
|
Mfail |
Type 2 |
GSVB8 |
0.5-0.9m |
0.2 |
13 |
< 0.2 |
40 |
38 |
24 |
48 |
128 |
0.13 |
< 3 |
< 550 |
< 1700 |
-- |
29 |
x |
|
|
Mfail |
Type 2 |
|
0.9-1.9m |
0.5 |
17 |
0.2 |
47 |
44 |
27 |
43 |
135 |
0.13 |
< 3 |
< 550 |
< 1700 |
-- |
30 |
|
|
|
M |
Type 1
Dedicated |
|
1.9-2.9m |
0.2 |
19 |
0.3 |
40 |
26 |
24 |
36 |
97 |
0.11 |
< 3 |
< 550 |
< 1700 |
-- |
31 |
|
|
|
M |
Type 1
Dedicated |
|
2.9-3.9m |
0.2 |
16 |
< 0.2 |
47 |
30 |
29 |
39 |
107 |
0.09 |
< 3 |
< 550 |
< 1700 |
-- |
32 |
|
|
|
M |
Type 1
Dedicated |
GSVB9 |
0.3-0.9m |
< 0.1 |
9 |
< 0.2 |
32 |
10 |
17 |
25 |
60 |
0.06 |
< 3 |
< 550 |
< 1700 |
-- |
33 |
|
|
|
L |
Type 1 |
|
0.9-1.9m |
< 0.1 |
13 |
< 0.2 |
23 |
22 |
11 |
25 |
79 |
0.08 |
< 3 |
< 550 |
< 1700 |
-- |
34 |
|
|
|
M |
Type 1
Dedicated |
|
1.9-2.9m |
0.5 |
26 |
0.4 |
65 |
81 |
38 |
52 |
163 |
0.18 |
< 3 |
< 550 |
< 1700 |
-- |
35 |
|
|
|
M |
Type 1
Dedicated |
|
2.9-3.9m |
0.5 |
22 |
0.2 |
53 |
55 |
32 |
48 |
142 |
0.2 |
< 3 |
< 550 |
< 1700 |
-- |
36 |
|
|
|
M |
Type 1
Dedicated |
GSVB10 |
0.3-0.9m |
0.1 |
13 |
< 0.2 |
31 |
13 |
18 |
29 |
70 |
0.07 |
< 3 |
< 550 |
< 1700 |
-- |
37 |
|
|
|
M |
Type 1
Dedicated |
|
0.9-1.9m |
0.2 |
13 |
< 0.2 |
43 |
18 |
26 |
38 |
88 |
0.06 |
< 3 |
< 550 |
< 1700 |
-- |
38 |
|
|
|
M |
Type 1
Dedicated |
|
1.9-2.9m |
0.6 |
29 |
0.4 |
55 |
48 |
35 |
60 |
169 |
0.22 |
< 3 |
< 550 |
< 1700 |
-- |
39 |
|
x |
|
Mfail |
Type 2 |
|
2.9-3.9m |
0.4 |
38 |
1.2 |
60 |
52 |
38 |
76 |
192 |
0.24 |
< 3 |
< 550 |
< 1700 |
-- |
40 |
|
|
|
M |
Type 1
Dedicated |
GSVB11 |
0.0-0.9m |
0.6 |
19 |
0.2 |
57 |
52 |
34 |
54 |
151 |
0.13 |
< 3 |
< 550 |
< 1700 |
-- |
41 |
|
|
|
M |
Type 1
Dedicated |
|
0.9-1.9m |
0.3 |
18 |
0.3 |
58 |
44 |
34 |
60 |
152 |
0.14 |
< 3 |
< 550 |
< 1700 |
-- |
42 |
|
|
|
M |
Type 1
Dedicated |
|
1.9-2.9m |
0.3 |
18 |
0.2 |
52 |
51 |
29 |
59 |
129 |
0.12 |
< 3 |
< 550 |
< 1700 |
-- |
43 |
|
|
|
M |
Type 1
Dedicated |
|
6.0-6.9m |
0.1 |
2 |
< 0.2 |
28 |
14 |
10 |
26 |
38 |
0.12 |
< 3 |
< 550 |
< 1700 |
-- |
44 |
|
x |
|
Mfail |
Type 2 |
|
6.9-7.4m |
< 0.1 |
< 1 |
< 0.2 |
8 |
10 |
2 |
24 |
7 |
0.09 |
< 3 |
< 550 |
< 1700 |
-- |
45 |
x |
|
|
Mfail |
Type 2 |
GSVB12 |
0.1-0.9m |
0.5 |
19 |
< 0.2 |
57 |
52 |
35 |
55 |
152 |
0.15 |
< 3 |
< 550 |
< 1700 |
-- |
46 |
|
|
|
M |
Type 1
Dedicated |
|
0.9-1.9m |
0.5 |
20 |
0.2 |
58 |
52 |
35 |
55 |
150 |
0.15 |
< 3 |
< 550 |
< 1700 |
-- |
47 |
|
|
|
M |
Type 1
Dedicated |
|
1.9-2.9m |
0.2 |
15 |
< 0.2 |
39 |
34 |
23 |
50 |
104 |
0.1 |
< 3 |
< 550 |
< 1700 |
-- |
48 |
|
|
|
M |
Type 1
Dedicated |
|
6.0-6.8m |
0.1 |
3 |
< 0.2 |
13 |
8 |
6 |
61 |
33 |
0.09 |
< 3 |
< 550 |
< 1700 |
-- |
49 |
|
|
|
L |
Type 1 |
Notes:
(a) Shaded Cell = Exceeding
LCEL, classified as Category M, which requires biological screening to
determine the types of disposal site (i.e. Type 1 Dedicated or Type 2
Disposal).
(b) Shaded Cell and underlined = Exceeding UCEL, classified as Category H, Type 3 Disposal.
(c) Type 1 Disposal = open sea disposal.
(d) Type 1 (Dedicated) Disposal = disposal at dedicated site.
(e) Type 2 Disposal = disposal at confined marine disposal site.
(f)
L: Category L material; M: Category Mpass material; Mfail: Category Mfail material
+ Not tested for biological screening
due to insufficient sample as a result of significant core loss
Tier III biological screening was required to
identify the most appropriate disposal option for the Category M contaminated
materials arising from this Project.
This consisted of ecotoxicological testing
programmes on three phylogenetically distinct species
(amphipod, polychaete and bivalve larvae), which was
undertaken to determine if there are any potential risks of toxicological
impacts from the sediment to the marine biota, and whether there is any
difference in the toxicity of the sediment samples taken from the Project site
and the reference station (collected from a clean area in Port Shelter, New
Territories).
Results of the biological screening indicated that of
the 49 vibrocore sediment samples tested ([6]), sediment from 14 samples failed in at
least one of the three toxicity tests and sediment from these locations are thus
regarded as Category Mfail material (Table 7.6). These 14 samples were from different
sections of the proposed pipelines and also from the proposed reclamation
site. Sediments from the remaining
samples have passed the biological screening tests and are regarded as either
Category L or Category Mpass material (Table 7.6).
In summary, a total of 0.508 Mm3
(in situ volume) of marine sediments
would be dredged. This assumes that
dredging will be required for suitable sections of the pipeline route and
jetting will be adopted for the remaining sections of the route. About 0.044 Mm3 (in situ volume) would be Category L
sediment. About
0.312 Mm3 (in situ volume)
would be Category M contaminated marine sediments (passed biological
screening), whereas about 0.152 Mm3 (in situ volume) would be Category M contaminated (failed biological
screening) sediments. The
detailed breakdown of estimated quantities of different types of marine sediments
to be dredged from this Project is summarised in Table 7.7.
Table 7.7 Estimated
Quantities of Different Types of Marine Sediment to be Dredged
Sediment Type |
In situ Volume (Mm3) |
Bulk Volume (Mm3) |
First Phase Construction |
||
Category L |
0.022 |
0.029 |
Category M pass |
0.126 |
0.164 |
Category M fail |
0.046 |
0.060 |
Sub-Total |
0.194 |
0.253 |
Second Phase Construction |
||
Category L |
0.022 |
0.029 |
Category M pass |
0.186 |
0.242 |
Category M fail |
0.106 |
0.138 |
Sub-Total |
0.314 |
0.409 |
Total |
0.508 |
0.662 |
The testing results presented in this Report are for
EIA purposes only. The procedures detailed
below will be followed prior to applying for a marine dumping permit. A proposal for sampling and chemical
testing of the sediment will be prepared and submitted to the EPD for approval. The approved detailed sampling and
chemical testing will be carried out prior to the commencement of the dredging
activities to confirm the sediment disposal method. After carrying out the sampling and
testing, a Sediment Quality Report (SQR) will be prepared for EPD
approval as required under the Dumping at Sea Ordinance. The SQR will include the sampling
details, chemical testing results, quality control records, proposed
classification and delineation of sediment according to the requirements of the
Appendix A of PNAP 252 ([7]).
At present, the East of Sha Chau Mud Pits are designated for confined marine disposal of contaminated
sediment. For the First Phase of
this Project, MFC has no objection in-principle to allocating disposal space
for the Mfail sediment dredged from
Sections 1 and 3 of the pipeline route (Figure 3.6), subject to the
availability of disposal space at the time of CAPCO's
application and at the proposed programme for disposal. The actual quantity and disposal site(s)
to be allocated will be based on the results of the SQR to be approved by DEP. The project proponent will implement the
project in accordance with the DASO
and the requirements as stipulated in the PNAP
252, prior to the application and allocation of space for dredging and
disposal of sediment arising from the project. The proposed disposal options for the
respective categories of marine sediment arising from the First Phase of this
Project are presented in Table 7.8.
Table 7.8 Proposed
Disposal Options for Different Types of Marine Sediment to be Dredged along the Alignment of Pipeline 1
Sediment Type |
In situ Volume (Mm3) |
Bulk Volume (Mm3) |
Proposed Disposal Option |
Category L |
0.022 |
0.029 |
Type 1 Open Sea Disposal to the areas
managed by the CEDD |
Category M pass |
0.126 |
0.164 |
To the extent accepted and approved by
the local authorities, Cross Boundary Disposal to Mainland |
Category M fail |
0.046 |
0.060 |
Type 2 Confined Marine Disposal to the
facilities managed by the CEDD |
Total |
0.194 |
0.253 |
|
Note:
(a) At
the time of reporting CAPCO is liaising with relevant authorities for the
preparation of a submission to the PRC
Due to the size of the East of Sha
Chau mud pits as well as ongoing re-evaluations of project
priorities by Government, it is noted that capacity may not be available for
the Second Phase material at the time of disposal. In view of such a situation, an
alternative site(s) / option(s) for contaminated sediment disposal for the
Second Phase mud arisings would be identified in
consultation with the MFC and the EPD.
The feasibility of the use of these alternatives site(s) / option(s
)(for Second Phase) has not been confirmed at the time of writing this report and
hence further study may be involved prior to confirmation of a disposal site(s)
/ alternative option(s) as suitable.
It is important to note that at this stage, the
construction of the two phases is expected to be separate. Such a Phased Construction approach is a
result of an optimisation of the Project’s implementation schedule to resolve
potential concerns regarding dredged material management. Other possibilities of reducing dredged
mud volumes by optimisation of project design, including the use of jetting for
installing suitable pipeline sections, have also been explored and discussed
(see Section 2 and Table 3.2). The present proposed work scheme
represents a concerted effort to reduce and manage dredged material
generation. Also, it is noted that
the First Phase Construction is expected to generate no more than 0.253 Mm3
(bulk volume) of contaminated marine sediments for off-site disposal.
The dredging works for the proposed Second
Phase reclamation (bulk volume of approximately 0.156 Mm3) will take
about two months with an estimated approximate maximum of 10 barge trips per
day ([8]).
For the dredging works for the submarine pipelines (bulk volume of 0.253
Mm3 for each pipeline), they will take about three months with
approximately 5 to 10 barge trips per day ([9]).
The dredged marine sediments will be loaded onto
barges and transported to the appropriate disposal site depending on their
level of contamination. In
accordance with the requirements of PNAP
252, Category M sediment will be dredged and transported with care in order
to avoid leakage of contaminated sediment into the sea. With the implementation of the
mitigation measures recommended in Section 7.5, sediment disposal at the designated disposal sites is not
expected to cause adverse environmental impacts.
The potential water quality impacts due to the
dredging of these sediments have been assessed and are presented in Section 6 Water Quality Impact Assessment. The assessment concluded that the
dredging works will meet the relevant water quality assessment criteria in the EIAO-TM
with the implementation of
mitigation measures recommended in Section 6.
C&D Materials
For the new reclamation adjacent to the
BPPS, approximately 0.17 Mm3 of suitable inert fill materials
(primarily sand, rock and public fill) will be required for backfilling at the
reclamation. The backfilling work
for the reclamation is expected to commence in early 2014 for approximately
four months.
For the backfilling of submarine gas
pipelines using armour rock and other suitable fill materials, the backfilling
work is expected to be completed within four months starting in 2011 for
Pipeline 1. Backfilling of the
trench of Pipeline 2 is expected to commence within 24 months of commissioning
of Pipeline 1. Approximately, 0.329
Mm3 of rock/ inert fill materials will be used for backfilling of
one pipeline.
A total bulk volume of 0.828 Mm3
of fill materials are, therefore, required for this Project. A breakdown of the quantities of fill
materials is presented in Table 7.8. The quantities of materials to be used
for backfilling are considered as the best estimate based on the available site
investigation data.
Table 7.9 Summary
of Quantity of Fill Materials (Bulk Volume) *
Fill Material |
First Phase |
Second Phase |
Total (Mm3) |
|
|
Pipeline 1 (Mm3) |
Pipeline 2 (Mm3) |
Reclamation (Mm3) |
|
Rock Fill |
0.319 |
0.319 |
0.115 |
0.905 |
Sand Fill |
0.010 |
0.010 |
0.035 |
0.035 |
Public Fill |
-- |
-- |
0.020 |
0.020 |
Total |
0.329 |
0.329 |
0.170 |
0.828 |
* Bulk Factor: Rock Fill = 1.2; Public Fill = 1.2;
Sand Fill = 1.3
Since blasting / land excavation works are not needed
during GRS and onshore pipeline construction, excavated materials are not
anticipated to arise from this Project for disposal or for reuse as backfilling
materials and potential concern for contaminated soil excavation is not
expected. At this stage it is
assumed that materials for backfilling will either be suitable sorted public
fill materials obtained from Fill Bank, or will be marine sand sourced within
the Pearl River Delta region. Fill
materials will be brought in to the site by self-propelled pelican barges when
needed. Rock and soil may be
excavated from minor site formation works and that will be reused as fill
material for the reclamation within the Project as far as practicable. Surplus fill material is not
anticipated.
C&D materials arising from this
Project will be sorted on site into inert waste (public fill) and non-inert
waste (construction waste). Public
fill will either be reused or be disposed of at public fill reception
facilities (e.g. Tuen Mun
Area 38 or other locations as agreed with CEDD). Construction waste, such as timber,
paper, plastics and general refuse, cannot be reused and need to be disposed of
at the
With proper implementation of standard construction
site practices and the mitigation measures recommended in Section 7.5, the handling and transportation of C&D materials
to the disposal sites will not cause adverse dust, noise or water quality
impacts.
Chemical wastes
Chemical waste, as defined under the Waste Disposal (Chemical Waste) (General)
Regulation, includes any substance being scrap material, or unwanted
substances specified under Schedule 1
of the Regulation. A complete list of such substances is
provided under the Regulation;
however, substances likely to be generated from the construction of this
Project will, for the most part, arise from the equipment and vessels
associated with the dredging works.
These may include, but not limited to the following:
·
Scrap
batteries or spent acid/alkali from their maintenance;
·
Used
engine oils, hydraulic fluids and waste fuel;
·
Spent
mineral oils/cleaning fluids from mechanical machinery; and
·
Spent
solvents/solutions from equipment cleaning activities.
Chemical wastes may pose environmental, health and safety
hazards if not stored and disposed of in an appropriate manner as outlined in
the Waste Disposal (Chemical Waste)
(General) Regulation and the Code of
Practice on the Packaging, Labelling and Storage of Chemical Wastes. These hazards may include:
·
Toxic
effects to workers;
·
Adverse
effects on air, water and land from spills; and
·
Fire
hazards.
The amount of chemical waste that will arise from the
construction activities will be highly dependent on the Contractor’s on-site
maintenance activities and the quantity of plant and equipment utilized. With respect to the nature of
construction works and the number of vessels and equipment to be used on site,
it is estimated that about a few hundred litres of used lubricant oil will be
generated per month during the construction period. It is anticipated that the quantities of
waste solvent and wasted oils will be minimal.
With the incorporation of suitable arrangements for
the storage, handling, transportation and disposal of chemical wastes under the
requirements stated in the Code of
Practice on the Packaging, Labelling and Storage of Chemical Waste, no
adverse environmental and health impacts, and hazards will result from the
handling, transportation and disposal of chemical waste arising from the
Project.
Sewage
Sewage will arise from the construction workforce,
portable toilets and sanitary facilities from the barges/ dredgers. If not properly managed, these materials
could cause odour and potential health risks to the workforce by attracting
pests and other disease vectors.
It is conservatively estimated that up to
100 construction workers, including both land- and marine-based workforce, will
be involved in the construction of the proposed Project. With a sewage generation rate of 0.15 m3/worker/day ([11]), about 15 m3 of sewage will be
generated per day. The sewage
generated is expected to be either conveyed to sewage treatment works (STW) at
BPPS (for land-based site work at BPPS) or collected in the onboard sewage tank
in the case of barges/ dredgers for off-site disposal. Given the small quantity of sewage
generated the sewage treatment works of the BPPS will be able to handle the
additional sewage flow from the construction work force at the GRS site. Therefore no adverse water quality
impacts are envisaged.
General refuse
The presence of a construction site with workers and
associated site facilities will result in the generation of general refuse
(mainly consist of food waste, aluminium cans and waste paper) which requires
off-site disposal. The storage of
general refuse has the potential to give rise to adverse environmental
impacts. These include odour if the
waste is not collected frequently (for example, daily), windblown litter, water
quality impacts if waste enters water bodies, and visual impact.
It is conservatively estimated that up to 100
construction workers will be working on site at any one time, with a general
refuse generation rate of 0.65 kg per worker per day ([12]), the amount of general refuse to be
generated will only be about 65 kg per day.
Recyclable materials such as paper and aluminium cans
will be separated and delivered to the recyclers. The non-recyclable waste will be
collected and disposed of together with the general waste arising from the
operation of the BPPS at the WENT Landfill on daily basis. With respect to the small quantity of
additional general refuse to be transferred to the WENT Landfill, it is not
anticipated that it will cause adverse operational impact to these facilities.
Provided that the mitigation measures recommended in Section 7.5 are adopted, no adverse environmental impacts caused by the storage,
handling, transport and disposal of general refuse are expected.
7.4.3
Operation Phase Impact Assessment
As discussed in Section
7.3.2, it is expected that during the early operation phase a few personnel
will work at the GRSs and thus a small amount of
solid wastes/ by-products and sewage may be generated. Whilst solid wastes will be disposed
properly with the existing waste management practices at BPPS, sewage is
expected to be treated by the sewage treatment works of the BPPS.
Industrial Waste
Industrial waste will arise from the maintenance
activities at the GRSs. The materials may include very small
quantities of scrap materials from maintenance of gas metering/ treatment
facilities and equipment and cleaning materials. Provided the scrap materials are
collected regularly for recycling, it is not expected that storage, handling,
transport and disposal of industrial waste will cause any adverse environmental
impacts. General industrial waste
such as plastic, metal cans and waste paper, will be disposed of together with
the general waste arising from the operation of the BPPS at the WENT Landfill.
Chemical Waste
With respect to the operation activities of the GRSs, it is anticipated that chemical waste will be
generated from maintenance activities anticipated to be conducted once a
year. The quantity of the chemical
wastes to be generated is very small.
The chemical waste will be collected by a licensed chemical waste
collector for disposal at the Chemical Waste Treatment Centre at Tsing Yi. The
handling, storage, collection and transportation of chemical waste will be
undertaken in accordance with requirement stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical
Waste, and no adverse environmental impacts and hazards are anticipated.
This Section
recommends the mitigation measures to avoid or reduce potential adverse environmental
impacts associated with handling, collection and disposal of waste arising from
the construction and operation of the proposed Project.
The Contractors will incorporate these
recommendations into a Waste Management Plan for the construction works. The Contractors will submit the plan to CAPCO’s Engineer Representative for endorsement prior to
the commencement of the construction works. Such plan will incorporate site-specific
factors, such as the designation of areas for the segregation and temporary
storage of reusable and recyclable materials.
It is the Contractor’s responsibility to confirm that
only reputable licensed waste collectors are used and that appropriate measures
to reduce adverse impacts, including windblown litter and dust from the
transportation of these wastes, are employed. In addition, the Contractor must confirm
that all the necessary permits or licences required under the Waste Disposal Ordinance are obtained for the construction and operation
phases.
7.5.1
Waste Management Hierarchy
The various waste management options are categorised
in terms of preference from an environmental viewpoint. The options considered to be most
preferable have the least environmental impacts and are more sustainable in the
long term. The hierarchy is as
follows:
·
Avoidance
and reduction;
·
Reuse
of materials;
·
Recovery
and recycling; and,
·
Treatment
and disposal.
The above hierarchy has been used to evaluate and
select waste management options.
The aim has been to reduce waste generation and reduce waste handling
and disposal costs.
CAPCO will confirm that their contractors consult the
EPD for the final disposal of wastes and as appropriate implement the standard
site practices and mitigation measures recommended in this Study and those
given below.
·
Nomination
of approved personnel to be responsible for standard site practices,
arrangements for collection and effective disposal to an appropriate facility
of all wastes generated at the site;
·
Training
of site personnel in proper waste management and chemical handling procedures;
·
Provision
of sufficient waste disposal points and regular collection for disposal;
·
Appropriate
measures to reduce windblown litter and dust transportation of waste by either
covering trucks or by transporting wastes in enclosed containers;
·
Separation
of chemical wastes for special handling and appropriate treatment at the
Chemical Waste Treatment Centre at Tsing Yi.;
·
Regular
cleaning and maintenance programme for drainage systems, sumps and oil
interceptors; and
·
A
recording system for the amount of wastes generated/ recycled and disposal
sites.
7.5.2
Waste Reduction Measures
Good management and control can prevent generation of
significant amount of waste. Waste reduction
is best achieved at the planning and design stage, as well as by ensuring the
implementation of standard site practices.
Recommendations to achieve waste reduction include:
·
Segregation
and storage of different types of waste in different containers, skips or
stockpiles to enhance reuse or recycling of material and their proper disposal;
·
Encourage
collection of aluminium cans and waste paper by individual collectors during
construction with separate labelled bins provided to segregate these wastes
from other general refuse by the workforce;
·
Any
unused chemicals and those with remaining functional capacity will be recycled
as far as possible;
·
Use
of reusable non-timber formwork to reduce the amount of C&D materials;
·
Prior
to disposal of construction waste, wood, steel and other metals will be
separated to the extent practical, for re-use and/or recycling to reduce the
quantity of waste to be disposed of to landfill;
·
Proper
storage and site practices to reduce the potential for damage or contamination
of construction materials; and
·
Plan
and stock construction materials carefully to reduce amount of waste generated
and avoid unnecessary generation of waste.
7.5.3
Dredged Materials
For sediments dredged during the construction of the
GRS reclamation and submarine pipelines, their disposal will be as indicated in
Section 7.4.2, and in accordance with the requirements of the PNAP 252.
Detailed sampling and chemical testing will be
carried out prior to the commencement of the dredging activities to confirm the
sediment disposal method. The final
disposal site will be determined by the MFC and a dumping licence will be
obtained from EPD prior to the commencement of the dredging works. Uncontaminated sediments will be
disposed of at open sea disposal sites designated by the MFC. For contaminated sediments requiring
Type 2 confined marine disposal, CAPCO will confirm that the relevant contract
documents will specify the allocation conditions of the MFC and EPD.
7.5.4
Excavated Materials
Management of Waste Disposal
The contractor will open a billing account with EPD
in accordance with the Waste Disposal
(Charges for Disposal of Construction Waste) Regulation for the payment of
disposal charges. Every waste load transferred
to Government waste disposal facilities such as public fill, sorting
facilities, landfills or transfer station will require a valid “Chit” which
contains the information of the account holder to facilitate waste transaction
recording and billing to the waste producer. A trip-ticket system will be established
in accordance with ETWBTC(W) No. 31/2004 to monitor the reuse of
surplus excavated materials off-site and disposal of construction waste and
general refuse at transfer stations/ landfills, and to control
fly-tipping. The billing “chit” and
trip ticket system will be included as one of the contractual requirements and
implemented by the contractor.
CAPCO will also conduct regular inspection of the waste management
measures implemented on site as described in the Waste Management Plan to be
prepared before commencement of construction.
A recording system (similar to summary table as shown
in Annex 5 and Annex 6 of Appendix G of ETWBTC(W)
No. 19/2005) for the amount of waste generated, recycled and disposed of
(including the disposal sites) will be established during the construction
stage.
Measures for the Reduction of C&D Materials Generation
Majority of the inert C&D materials (rock and
soil) will be reused within the Project.
Public fill and construction waste shall be segregated and stored in
different containers or skips to facilitate reuse or recycling of materials and
their proper disposal. Specific
areas of the work site will be designated for such segregation and storage if
immediate use is not practicable.
To reduce the potential dust and water quality impacts
of site formation works, C&D materials will be wetted as quickly as
possible to the extent practice after filling.
7.5.5
Chemical Waste
Chemical waste producers will be registered with the
EPD.
Chemical waste, as defined by Schedule 1 of the Waste
Disposal (Chemical Waste) (General) Regulation, will be handled in
accordance with the Code of Practice on
the Packaging, Handling and Storage of Chemical Wastes as follows. Containers used for storage of chemical
wastes will:
·
Be
suitable for the substance they are holding, resistant to corrosion, maintained
in a good condition, and securely closed;
·
Have
a capacity of less than 450 L unless the specifications have been approved by the
EPD; and
·
Display
a label in English and Chinese in accordance with instructions prescribed in Schedule 2 of the Regulations.
The storage area for chemical wastes will:
·
Be
clearly labelled and used solely for the storage of chemical waste;
·
Be
enclosed on at least 3 sides;
·
Have
an impermeable floor and bunding, of capacity to
accommodate 110% of the volume of the largest container or 20% by volume of the
chemical waste stored in that area, whichever is the greatest;
·
Have
adequate ventilation;
·
Be
covered to prevent rainfall entering (water collected within the bund must be
tested and disposed of as chemical waste, if necessary); and
·
Be
arranged so that incompatible materials are appropriately separated.
Chemical waste will be disposed of:
·
Via a
licensed waste collector; and
·
To a
facility licensed to receive chemical waste, such as the Chemical Waste
Treatment Facility which also offers a chemical waste collection service and
can supply the necessary storage containers.
7.5.6
Sewage
Sanitary facilities, such as portable toilets, will
be provided for the on-site construction workforce. The sewage generated from the
construction works will either be conveyed to sewage treatment works (STW) at
BPPS or collected in the onboard sewage tank in the case of barges/ dredgers
for off-site disposal. The small
amount of sewage generated during the operation phase is also expected to be
conveyed to the STW at BPPS.
7.5.7
General Refuse
General refuse will be stored in enclosed bins or compaction
units separately from construction and chemical wastes. Adequate number of waste containers will
be provided to avoid over-spillage of waste. A reputable waste collector will be
employed by the Contractor to remove general refuse from the site, separately
from construction and chemical wastes, on a daily basis to minimise odour, pest
and litter impacts. The burning of
refuse on construction sites is prohibited by law.
Recycling bins will be provided at strategic
locations to facilitate recovery of aluminium can and waste paper from the
site. Materials recovered will be
sold for recycling.
7.5.8
Industrial Wastes
Industrial waste arising from maintenance activities
will be segregated. It is
recommended to send scrap metals for recycling to reduce the overall quantity
of waste disposed from these activities.
7.5.9
Staff Training
Training will be provided to workers on the concepts
of site cleanliness and appropriate waste management procedures, including waste
reduction, reuse and recycling at the beginning of the construction works.
7.6
Residual
Environmental Impacts
With the implementation of the recommended mitigation
measures no adverse residual impacts are anticipated from the construction and
operation of the GRSs and submarine gas pipelines.
7.7
Environmental
Monitoring & Audit
7.7.1
Construction Phase
To facilitate monitoring and control over the
contractors’ performance on waste management, a waste monitoring and audit programme
will be implemented throughout the construction phase. The aims of the monitoring and audit
programme are:
·
To
review the Contractor’s Waste Management Plan (WMP) including the quantities
and types of C&D materials generated, reused and disposed of off-site; the
amount of fill materials exported from/imported to the site and the quantity of
timber used in temporary works construction for each process/activity;
·
To
monitor the implementation and achievement of the WMP on site to assess its effectiveness;
and
·
To
monitor the follow-up action on deficiencies identified.
Joint site inspections by CAPCO and the contractor
will be undertaken each month.
Particular attention will be given to the contractor’s provision of
sufficient spaces, adequacy of resources and facilities for on-site sorting and
temporary storage of C&D materials.
The C&D materials to be disposed of from the site will be visually
inspected. The public fill for
delivery to the off-site stockpiling area will contain no observable non-inert
materials (e.g. general refuse, timber, etc). Furthermore, the waste to be disposed of
at refuse transfer stations or landfills will as practicable contains no
observable inert or reusable/recyclable C&D materials (e.g. soil, broken
rock, metal, and paper/cardboard packaging, etc). Any irregularities observed during the
site inspections will be raised promptly to the contractor for rectification.
The findings of the waste inspections will be
reported in the Environmental Monitoring and Audit Reports.
7.7.2
Operation Phase
As the operation of the GRSs
will generate minimal quantity of waste and no adverse environmental impacts
will arise with the implementation of standard waste management practices,
waste monitoring and audit programme for the operation
phase of the facilities is not required.
7.8.1
Construction Phase
Optioneering has been conducted to try to avoid waste
generation and reuse and recycling of waste generated from the construction of the
proposed Project during the planning and design stages and consideration of
options for layout, construction methods and programme, and the proposed scheme
comprises the proposed best balance.
The key potential impacts during the construction phase are related to
wastes generated from dredging, reclamation, seawall
construction, filling and concreting.
The Project is planned to take place in
phases. For the First Phase of the
Project, Sections 1 and 3 of the pipeline would be installed by dredging while
Sections 2 and 4 of the pipeline would be installed by jetting. About 0.253 Mm3 (bulk volume)
sediment will be generated from Sections 1 and 3 of the pipeline. The final volumes will be subject to
detailed sediment sampling, testing and analysis in accordance with the PNAP 252 and disposal method reviewed
prior to the commencement of the dredging activities. About 0.029 Mm3 (bulk volume)
of the dredged sediment is expected to be Category L sediment. MFC has no objection in-principle to
allocating disposal space for the Mfail
sediment dredged from Sections 1 and 3 of the pipeline route (about 0.060 Mm3
bulk volume), subject to the availability of disposal space at the time of CAPCO's application and at the proposed programme for
disposal. CAPCO is exploring
alternative disposal sites (such as cross boundary disposal to Mainland
The Second Phase of the Project is
expected to also generate approximately 0.253 Mm3 (bulk volume) from
the installation of the submarine pipeline. At present the dredging works for the
reclamation for the second GRS are expected to give rise to a bulk volume of
0.156 Mm3 of contaminated mud.
As for C&D materials, they will be sorted on site
into inert waste (public fill) and non-inert waste (construction waste). Public fill will either be reused or be
disposed of at public fill reception facilities (e.g. Tuen
Mun Area 38 or other locations as agreed with
CEDD). Construction waste, such as
timber, paper, plastics and general refuse, cannot be reused and need to be
disposed of at the
The construction programme is preliminary and subject
to reduce, therefore, the Contractor's programme will be reviewed by CAPCO when
the construction programme is finalized.
A few hundred litres of used lubrication oil is
expected to be generated per month and a maximum of about 65 kg of general
refuse will be generated each day.
In view of the small quantity of waste generated, the handling and
disposal of the waste generated from construction activities, chemical wastes
and general refuse will not cause any significant environmental impacts. With the implementation of the
recommendations in Section 7.5, the
potential environmental impacts arising from storage, handling, collection,
transport and disposal of wastes is expected to meet the criteria specified in
the EIAO TM. No adverse waste management impact is
anticipated based on the information available. No residual and cumulative environmental
impacts and hazards associated with handling and disposal of wastes arising
from the construction of the proposed Project are anticipated.
A Waste Management Plan will be prepared by the
Contractors and will be audited through the environmental monitoring and
auditing (EM&A) programme recommended in Section 7.7 to reduce the potential environmental impact arising
from waste management.
7.8.2
Operation Phase
With standard site practice, the potential environmental
impacts associated with the storage, handling, collection, transport and
disposal of a small quantity of industrial and chemical wastes arising from the
operation of the GRSs at BPPS will meet the criteria
specified in the EIAO TM and no unacceptable
waste management impact is anticipated.
No residual and cumulative environmental impacts and
hazards associated with handling and disposal of wastes arising from the
operation of the GRSs at BPPS are anticipated.