Chapter Title Page
Figures
Figure 10.1 Study Area for the Air
Quality Impact Assessment
Figure 10.2 Locations of Air
Sensitive Receivers in Admiralty
Figure 10.3 Locations of Air
Sensitive Receivers at
Figure 10.4 Locations of Air
Sensitive Receivers in Wong Chuk Hang
Figure 10.5 Locations of Air
Sensitive Receivers in Lei Tung
Figure 10.6 Locations of Air
Sensitive Receivers in South Horizons and
Figure 10.7 Locations of Air
Sensitive Receivers at Chung Hom Shan Magazine Site and
Figure
10.8 Zoning
for Site Formation Works and Structure/ Fitting Out Works at WCH Depot
Figure 10.9 Locations of Dust
Emission Sources in Admiralty (1) (Tier 1)
Figure 10.10 Locations of Dust Emission
Sources in Admiralty (2) (Tier 1)
Figure 10.11 Locations of Dust Emission
Sources in
Figure 10.12 Locations of Dust Emission
Sources in Wong Chuk Hang (Tier 1)
Figure 10.13 Locations of Dust Emission
Sources in Ap Lei Chau and Lei Tung (Tier 1)
Figure 10.14 Locations of Dust Emission
Sources in South Horizons (Tier 1)
Figure 10.15 Locations of Dust Emission
Sources at
Figure 10.16 Locations of Dust Emission
Sources at Chung Hom Shan Magazine Site and
Figure
10.17 Locations of Dust Emission Sources in Wong Chuk Hang (Tier 2 for ASR –
WCH14)
Figure
10.18 Locations of Dust Emission Sources in Wong Chuk Hang (Tier 2 for ASR –
WCH2)
Figure
10.19 Locations of Dust Emission Sources in Wong Chuk Hang (Tier 2 for ASR –
WCH3)
Figure
10.20 Locations of Dust Emission Sources in Wong Chuk Hang (Tier 2 for ASR –
WCH5)
Figure
10.21 Locations of Dust Emission Sources in Wong Chuk Hang (Tier 2 for ASR –
WCH6)
Figure
10.22 Cumulative
Result - Contours of tier 1 hourly TSP Concentration (mg/m3) at 1.5m above G/F during Construction Phase
(Include Background Concentration = 77.4mg/m3, AQO = 500mg/m3) -
Admiralty
Figure
10.23 Cumulative
Result - Contours of tier 1 hourly TSP Concentration (mg/m3) at 1.5m above G/F during Construction Phase
(Include Background Concentration = 73.2mg/m3, AQO = 500mg/m3) - Nam Fung Portal and
Figure
10.24 Cumulative
Result - Contours of tier1 hourly TSP Concentration (mg/m3) at 1.5m above G/F during Construction Phase
(Include Background Concentration = 73.2mg/m3, AQO = 500mg/m3) – Wong Chuk Hang
Figure
10.25 Cumulative
Result - Contours of tier 1 hourly TSP Concentration (mg/m3) at 1.5m above G/F during Construction Phase
(Include Background Concentration = 73.2mg/m3, AQO = 500mg/m3) – Lei Tung
Figure
10.26 Cumulative
Result - Contours of tier 1 hourly TSP Concentration (mg/m3) at 1.5m above G/F during Construction Phase
(Include Background Concentration = 73.2mg/m3, AQO = 500mg/m3) – South Horizons and Lee Nam Barging Point
Figure
10.27 Cumulative
Result - Contours of tier1hourly TSP Concentration (mg/m3) at 1.5m above G/F (Include Background
Concentration = 73.2mg/m3, AQO = 500mg/m3) - Telegraph Bay
Figure
10.28 Cumulative
Result - Contours of tier 1hourly TSP Concentration (mg/m3) at 1.5m above G/F during Construction Phase
(Include Background Concentration = 73.2mg/m3, AQO = 500mg/m3) - Chung Hom Shan
Figure
10.29 Cumulative
Result - Contours of tier 2 hourly
Figure
10.30 Cumulative
Result - Contours of tier 2 hourly
Figure
10.31 Cumulative
Result - Contours of tier 2 hourly
Figure
10.32 Cumulative
Result - Contours of tier 2 hourly
Figure
10.33 Cumulative
Result - Contours of tier 2 hourly
Figure
10.34 Cumulative
Result - Contours of tier 1daily
Figure
10.35 Cumulative
Result - Contours of tier 1 daily
Figure
10.36 Cumulative
Result - Contours of tier 1 daily
Figure
10.37 Cumulative
Result - Contours of tier 1 daily
Figure
10.38 Cumulative
Result - Contours of tier 1 daily
Figure
10.39 Cumulative
Result - Contours of tier 1 daily
Figure
10.40 Cumulative
Result - Contours of tier 1 daily
Figure
10.41 Not used.
Figure
10.42 Not used.
Figure
10.43 Cumulative
Result - Contours of tier 2 daily
Figure
10.44 Not used.
Figure
10.45 Cumulative
Result - Contours of tier 2 daily
Figure
10.46 Cumulative
Result - Contours of annual
Figure
10.47 Cumulative
Result - Contours of annual
Figure
10.48
Cumulative Result - Contours of annual
Figure
10.49 Cumulative
Result - Contours of annual
Figure
10.50 Cumulative
Result - Contours of annual
Figure
10.51 Cumulative
Result - Contours of annual
Figure
10.52 Cumulative
Result - Contours of annual
Appendices
Appendix 10.1 The construction programme of
the concurrent projects
Appendix 10.2 Detailed Calculations of
Emission Factors for FDM Model
Appendix 10.3 Input information of dust
sources
Appendix 10.4 Calculations for percentage active
area and watering efficiency
This section
assesses the potential air quality impacts associated with construction of the
Project. Dust emission in the processes of construction of stations and
viaducts, material handling, storage of materials, spoil disposal, crushing,
concrete batching and barging activities are the major sources of dust emission
during the construction phase. Representative Air Sensitive Receivers (ASRs)
within 500m of the study area have been identified and extended to include
those areas that are potentially affected along the proposed
In accordance with
the Section 3.4.7 of the EIA Study Brief, the air quality impact in the
construction phase has been assessed. Air quality impact assessment in
operation phase is not required. Similar to other existing electricified
railways in
10.2
Environmental Legislations, Standards and
Guidelines
10.2.1 Technical Memorandum on Environmental Impact Assessment Ordinance (EIAO-TM)
Assessment criteria for aerial emission is based on the Hong Kong Air Quality Objectives (“AQO”) for air pollutants given in Chapter 9, "Environment", of the Hong Kong Planning Standards and Guidelines (HKPSG) for air pollution control and are listed in Table 10.1.
Table 10.1: Hong Kong Air Quality Objectives
Pollutant |
Concentration
in micrograms per cubic metre (i) |
||||
Averaging Time |
|||||
|
1 hour (ii) |
8 hours (iii) |
24 hours (iii) |
3 Months (iv) |
1 year (iv) |
|
800 |
N.A. |
350 |
N.A. |
80 |
Total Suspended Particulates |
500* |
N.A. |
260 |
N.A. |
80 |
Respirable (v) Suspended
Particulates |
N.A. |
N.A. |
180 |
N.A. |
55 |
Nitrogen Dioxide |
300 |
N.A. |
150 |
N.A. |
80 |
Carbon Monoxide |
30000 |
10000 |
N.A. |
N.A. |
N.A. |
Photochemical Oxidants (as
Ozone) (vi) |
240 |
N.A. |
N.A. |
N.A. |
N.A. |
Lead |
N.A. |
N.A. |
N.A. |
1.5 |
N.A. |
Legend:
(i) Measured at 298K (25oC) and 101.325 kPa (one atmosphere).
(ii) Not to be exceeded more than three times per year;
(iii) Not to be exceeded more than once per year;
(iv) Arithmetic means
(v) Respirable suspended particulates means suspended particles in air with a nominal aerodynamic diameter of 10 micrometres and smaller.
(vi) Photochemical oxidants are determined by measurement of ozone only.
* Acceptable criteria under the EIAO-TM for construction dust impact assessment.
For impacts during the construction phase, fugitive dust in
particular, Section 1, Annex 4 of EIAO-TM stipulates the hourly average Total
Suspended Particulate (“
10.2.2 Air Pollution Control (Construction Dust) Regulation
The APCO’s subsidiary regulation Air Pollution Control (Construction Dust) Regulation defines notifiable and regulatory works activities that are subject to construction dust control.
10.2.2.1 Notifiable Works:
1. Site formation
2. Reclamation
3. Demolition of a building
4. Work carried out in any part of a tunnel that is within 100 m of any exit to the open air
5. Construction of the foundation of a building
6. Construction of the superstructure of a building or
7. Road construction work
10.2.2.2 Regulatory Works:
8. Renovation carried out on the outer surface of the external wall or the upper surface of the roof of a building
9. Road opening or resurfacing work
10. Slope stabilisation work or
11. Any work involving any of the following activities:
¡ Stockpiling of dusty materials
¡ Loading, unloading or transfer of dusty materials
¡ Transfer of dusty materials using a belt conveyor system
¡ Use of vehicles
¡ Pneumatic or power-driven drilling, cutting and polishing
¡ Debris handling
¡ Excavation or earth moving
¡ Concrete production
¡ Site clearance or
¡
Blasting
Notifiable works require that advance notice of activities be
given to
10.2.3 Air Pollution Control (Specified Processes) Regulations
A stringent emission control for the operation of the following facility, which is classified as Specified Processes (SP) in the APCO.
¡ Operation of Cement Works in which the total silo capacity exceeds 50 tonnes and in which cement is handled or in which argillaceous and calcareous materials are used in the production of cement clinker, and works in which cement clinker is ground.
¡ Operation of Minerals Works in which the processing capacity exceeds 5000 tonnes per annum and in which stones are subjected to any size reduction or grading by a process giving rise to dust, not being any works described in any other specified process.
A licence is required for the operation of
the concrete batching plant and stone crushing plant under Part IV of the
Ordinance. Application for licence shall be made to
10.3
Assessment Area and Air Sensitive Receivers
The assessment area within 500m of the proposed
10.3.2 Representative Air Sensitive Receivers
Representative ASRs
have been selected in the vicinity of the identified works areas and barging
points according to Annex 12 of EIAO-TM through the on-site inspection and a
review of the latest land use plans. Lists of selected ASRs along the proposed
Table 10.2: Representative Air Sensitive Receivers in the Vicinity of Work Sites in Admiralty
|
Description |
Type of Use |
Existing/ Planned ASRs |
Separation
Distance between |
Fresh Air Intake Height/Sensitive Use Above Ground Level (m) |
|
Island Shangri-La Hotel |
Hotel |
Existing |
18 |
>20 |
|
Tennis Court |
Recreational |
Existing |
5 |
N/A |
|
Jockey Club New Life Hostel |
Residential |
Existing |
76 |
Approximately 1.5 |
|
|
Open Space |
Existing |
11 |
N/A |
|
United Centre |
Office |
Existing |
74 |
>20 |
|
Admiralty Centre – Office Tower II |
Office |
Existing |
5 |
>20 |
|
Arsenal House (West Wing) |
G/IC |
Existing |
3 |
>20 |
|
Caine House |
G/IC |
Existing |
21 |
>5 |
|
|
G/IC |
Existing |
42 |
Approximately 1.5 |
ADM13 |
British Council |
G/IC |
Existing |
9 |
>5 |
ADM14 |
Conrad Hotel |
Hotel |
Existing |
28 |
>20 |
ADM15 |
|
G/IC |
Existing |
9 |
>20 |
ADM16 |
Fleet |
Commercial |
Existing |
45 |
>10 |
ADM17 |
Citic Tower |
Office |
Existing |
70 |
>20 |
ADM18 |
Queensway Government Office |
G/IC |
Existing |
21 |
>20 |
ADM19 |
Regent on the Park |
Residential |
Existing |
56 |
Approximately 1.5 |
ADM20 |
|
Office |
Existing |
107 |
Approximately 1.5 |
ADM21 |
Office of
Ministry of Foreign Affairs of |
G/IC |
Existing |
123 |
>20 |
Table 10.3: Representative
Air Sensitive Receivers in the Vicinity of Work Sites at
|
Description |
Type of Use |
Existing/ Planned ASRs |
Separation Distance between |
NFP1 |
|
Educational |
Existing |
55 |
NFP2 |
|
Educational |
Existing |
26 |
NFP3 |
Wong Chuk Hang Services for the Elderly |
Elderly Centre |
Existing |
38 |
NFP4 |
|
Hospital |
Existing |
79 |
NFP5 |
Wong Chuk Hang Complex for the Elderly |
Convalescent Home |
Existing |
16 |
NFP6 |
Wong Chuk Hang San Wai – No. 4C |
Residential |
Existing |
4 |
NFP7 |
Country Villa |
Residential |
Existing |
87 |
NFP8 |
|
Residential |
Existing |
109 |
NFP9 |
Shouson
Hill Nursery |
Open
space |
Existing |
80 |
Table 10.4: Representative Air
Sensitive Receivers in the Vicinity of Work Sites in
|
Description |
Type of Use |
Existing/ Planned ASRs |
Separation
Distance between |
OCP1 |
|
Hospital |
Existing |
157 |
OCP2 |
Wong Chuk Hang Sport Centre |
Open Space |
Existing |
8 |
OCP3 |
|
Open Space |
Existing |
11 |
OCP4 |
|
Educational |
Existing |
1 |
OCP6 |
|
Recreation |
Existing |
80 |
OCP7 |
|
Recreation |
Planned |
31 |
OCP8 |
Operational
Force Training Area |
Open Space |
Existing |
1 |
Table 10.5: Representative Air
Sensitive Receivers in the Vicinity of Work Sites in Wong Chuk Hang and Viaduct
Section
|
Description |
Type of Use |
Existing/ Planned ASRs |
Separation
Distance between |
Fresh Air Intake Height/Sensitive Use Above Ground Level (m) |
WCH1 |
|
Educational |
Existing |
21 |
Approximately 1.5 |
WCH2 |
|
Residential |
Existing |
22 |
Approximately 1.5 |
WCH3 |
San Wui
Commercial Society of |
Educational |
Existing |
17 |
Approximately 1.5 |
WCH4 |
Little Sisters of the Poor St. Mary’s Home for the Aged – Chapel |
Worship |
Existing |
52 |
Approximately 1.5 |
WCH5 |
Tai Wong
Ye |
Worship |
Existing |
1 |
Approximately 1.5 |
WCH6 |
Gee |
Industrial |
Existing |
3 |
Approximately 1.5 |
WCH7 |
|
Industrial |
Existing |
6 |
>5 |
WCH8 |
TWGHs Jockey Club Rehabilitation Complex – Block A |
Convalescent Home |
Existing |
3 |
Approximately 1.5 |
WCH9 |
|
Industrial |
Existing |
17 |
>5 |
WCH10 |
Holy Spirit Seminary – Chapel |
Worship |
Existing |
28 |
Approximately 1.5 |
WCH11 |
Holy Spirit Seminary |
Educational |
Existing |
3 |
Approximately 1.5 |
WCH12 |
|
Residential |
Existing |
55 |
Approximately 1.5 |
WCH13 |
|
Recreational |
Existing |
32 |
N/A |
WCH14 |
(Planned)
|
School |
Planned |
19 |
Approximately 1.5 |
WCH16 |
|
Residential |
Existing |
52 |
>10 |
WCH17 |
Pao Yue Kong Swimming Pool Complex |
Recreational |
Existing |
17 |
N/A |
WCH18 |
|
Open Space |
Existing |
1 |
Approximately 1.5 |
WCH21 |
|
Open Space |
Existing |
21 |
N/A |
WCH22 |
|
G/IC |
Existing |
40 |
Approximately 1.5 |
Table 10.6: Representative
Air Sensitive Receivers in the Vicinity of Work Sites in Ap
|
Description |
Type of Use |
Existing/ Planned ASRs |
Separation
Distance between |
LET1 |
Ap |
Open Space |
Existing |
21 |
LET2 |
Sham Wan Towers – Tower |
Residential |
Existing |
13 |
LET3 |
|
Residential |
Existing |
42 |
LET4 |
The |
Worship |
Existing |
35 |
LET5 |
Shan On House |
Residential |
Existing |
4 |
LET6 |
Tung Sing House |
Residential |
Existing |
5 |
LET7 |
Tung Mau House |
Residential |
Existing |
1 |
LET8 |
Sunny Court |
Residential |
Existing |
3 |
LET9 |
|
Residential |
Existing |
8 |
LET10 |
Lei Tung Comercial Centre (Phase 1) |
Shopping Centre |
Existing |
1 |
LET11 |
Lei Tung Comercial Centre (Phase 2) |
Shopping Centre |
Existing |
1 |
LET12 |
|
Educational |
Existing |
126 |
LET13 |
Tung Hing House |
Residential |
Existing |
50 |
LET14 |
Ap Lei Chau Service Reservoir Playground |
Recreational |
Existing |
32 |
LET15 |
Sham Wan
|
Residential |
Existing |
25 |
LET19 |
Yue On
Court - Pik On House |
Residential |
Existing |
28 |
LET20 |
St.
Peter's |
School |
Existing |
102 |
LET21 |
Ap |
Recreational |
Existing |
46 |
Table 10.7: Representative
Air Sensitive Receivers in the Vicinity of Work Sites in South Horizons
|
Description |
Type of Use |
Existing/ Planned ASRs |
Separation
Distance between |
SOH1 |
South
Horizons Phase 3 – Block 23A |
Residential |
Existing |
3 |
SOH2 |
South
Horizons Phase 4 (The Oasis) – Block |
Residential |
Existing |
3 |
SOH3 |
South
Horizons Phase 3 – Block |
Residential |
Existing |
3 |
SOH4 |
South
Horizons Phase 4 (The Oasis) – Block 33A |
Residential |
Existing |
1 |
SOH5 |
Marine Square (East Wing) |
Shopping Centre |
Existing |
3 |
SOH6 |
|
Educational |
Existing |
46 |
SOH8 |
South Horizons Phase 3 Block |
Residential |
Existing |
14 |
SOH9 |
South Horizons Phase 3 Block |
Residential |
Existing |
21 |
SOH11 |
South Horizons Phase 4 Block |
Residential |
Existing |
21 |
SOH13 |
|
School |
Existing |
81 |
SOH14 |
Ap Lei Chau Fire Station |
G/IC |
Existing |
46 |
SOH15 |
Lei Fook
House |
Residential |
Existing |
61 |
SOH16 |
Yuk Kwai Shan
Service Reservoir Sitting Area |
Open
Space |
Existing |
105 |
Table 10.8: Representative
Air Sensitive Receivers in the Vicinity of
|
Description |
Type of Use |
Existing/ Planned ASRs |
Separation
Distance between |
TGB1 |
Magnolia Villas |
Residential |
Existing |
268 |
TGB2 |
|
Residential |
Existing |
316 |
TGB3 |
|
Educational |
Existing |
232 |
TGB4 |
Aegean
Terrace House K |
Residential |
Existing |
156 |
TGB5 |
Le
Meridien Cyberport |
Hotel |
Existing |
84 |
TGB6 |
The
Cyberport Arcade |
Shopping Centre |
Existing |
108 |
Table 10.9: Representative
Air Sensitive Receivers in the Vicinity of
|
Description |
Type of Use |
Existing/ Planned ASRs |
Separation Distance
between |
Fresh Air Intake Height/ Sensitive Use Above Ground Level (m) |
LNB1 |
Oceanic Industrial Centre |
Industrial |
Existing |
11 |
>5 |
LNB2 |
Harbour Industrial Centre |
Industrial |
Existing |
11 |
>5 |
LNB3 |
Dah Chong Hong (Motor Service Centre) Ltd. |
Industrial |
Existing |
63 |
>5 |
LNB4 |
|
Office |
Existing |
39 |
Approximately 1.5 |
LNB5 |
HK |
Office |
Existing |
23 |
Approximately 1.5 |
LNB6 |
HK |
Office |
Existing |
17 |
Approximately
1.5 |
Table 10.10: Representative Air
Sensitive Receivers in the Vicinity of Chung Hom Shan Magazine Site
|
Description |
Type of Use |
Existing/ Planned ASRs |
Separation Distance between |
|
Cheshire Home Chung Hom Shan |
Residential |
Existing |
500 |
|
The Jockey Club Cheshire Home |
Residential |
Existing |
524 |
|
|
Residential |
Existing |
240 |
CHK5 |
|
open
space |
Existing |
300 |
10.4
Description of the Environment/ Background Air
Quality
The proposed
There are currently
11 general and 3 roadside air quality monitoring stations operated by
The background
concentrations of major air pollutants in the previous five years were recorded
and the latest 5-year-averaged annual concentration from 2005 to 2009 at the
monitoring stations is presented in Table 10.11. It is noted that the annual background TSP
level adopted for Admiralty approaches the annual AQO.
Table 10.11: 5-Year-Averaged
Annual Background Air Quality
Pollutants |
5-year-averaged Annual Background Concentration (μg/m3) |
HKAQO (μg/ m3) |
TSP (adopted in Admiralty) |
77.4 |
80 |
TSP (adopted in Island South) |
73.2 |
80 |
10.1.1 Potential Sources of Environmental Impact
The construction
work for the proposed
There are also other
construction activities associated with the construction of the proposed
Table 10.12 Potential Emission Sources from Works Sites
Location |
Works Areas |
Construction Activities |
Admiralty |
|
¡ Heavy construction activities including the open excavation on the cut-and-cover station, ventilation shafts and station entrance ¡ Material handling and temporary stockpiles ¡ Wind erosion of open active area ¡ Spoil
transportation to the temporary stockpile area within the site |
|
|
¡ Heavy construction on ventilation shaft and ancillary building ¡ Wind erosion of open active area |
|
ex-Canadian Hospital site |
¡ Heavy construction on tunnel excavation, construction of ventilation building and tunnel box ¡ Wind erosion of open active area ¡ Operation of rock crushing plant ¡ Loading of crushed materials to the temporary stockpile ¡ Slope stabilization works |
|
Nam Fung
portal to |
¡ Heavy construction on viaduct sections ¡ Wind erosion of open active area |
|
|
¡ Heavy construction on station ¡ Wind erosion of active area |
|
|
¡ Heavy construction on viaduct section ¡ Wind erosion of open active area |
Wong Chuk Hang |
Wong Chuk Hang station |
¡ Heavy construction on station ¡ Wind erosion of open active area |
|
Wong Chuk Hang depot* |
¡ Heavy construction of site formation by open excavation and foundation work (installation of a mixture of pipe piles and bored piles or pad footing) ¡ Heavy construction of station depot, ventilation shafts and cooling towers ¡ Operation of rock crushing plant ¡ Loading of crushed materials to the temporary stockpiles ¡ Spoil transportation within the site (i.e. earth moving activity) ¡ Wind erosion of active area ¡ Concrete batching activity |
|
Wong Chuk Hang viaduct |
¡ Heavy construction on pier and viaduct sections ¡ Wind erosion of active area |
Lei Tung |
Channel bridge |
¡
Heavy construction of ¡ Wind erosion of active area |
|
Lei Tung tunnel |
¡ Heavy construction of cut-and-cover tunnel including open excavation and ventilation facilities ¡ Wind erosion of active area |
|
Lei Tung station |
¡ Heavy construction of station entrances ¡ Slope stabilization work ¡ Wind erosion of active area |
South Horizons |
South Horizon station |
¡ Heavy construction of station, entrances and ventilation building including excavation and foundation work ¡
Site formation and slope stabilization work at
the existing hillside facing the ¡ Wind erosion of active area |
|
|
¡ Material handling and stockpiling ¡ Unloading of spoils to barge |
|
|
¡ Heavy construction of ventilation building ¡ Slope stabilization works ¡ Transportation of spoil materials to barge at Barging Point 6 (Figure 10.15) ¡ Material handling and wind erosion of open active area ¡ Construction of berths and tipping halls |
Chung Hom Shan |
Magazine site |
¡ Slope stabilization works |
* The paved road
dust emissions were considered insignificant because of the high frequency of
watering exercise in the construction area. All construction vehicles should pass
through the wheel-washing facility at site exit(s). See mitigation measure in Section 10.6.2 for details.
The construction
activities that are subject to dust emissions from the proposed stations,
barging points and magazine site are described below:
10.1.1.1
Admiralty (
Two major work
sites, namely
Most areas of the
A site access road connecting Rodney Street and
Two sites would also
be assigned for the shaft construction. The main ventilation shaft for the
tunnel would be constructed at the works site at
10.1.1.2
The ex-Canadian
Hospital site at
Due to the large amount
of rock generated from the tunnel, a rock crushing plant would be operated in
the site near the Nam Fung Portal, and the crushed rocks would be transported
to barging point for disposal. Crushing activities include the crushing
loading, secondary crushing, screening and unloading from crushing plant to the
stockpile area. Licence for Specified Processes as described in Section 10.2.3 is required if the
capacity of the crushing plant exceeds the capacity as described in Section 10.2.3. There are also slope stabilization works
behind the
The viaduct section
between OCP Station and the former
10.1.1.3
The proposed
development site would be a major works site for the construction of the OCP
station. Most of the site area would be used for site office, plant and
material storage, and the remaining areas would be occupied for the
construction of viaduct sections. The major construction activities include the
installation of bored piles, construction of viaduct sections.
Access to the works
site would be along the
10.1.1.4 Wong Chuk Hang (WCH) Station
WCH Station would be
situated to the north of the WCH Depot. The proposed construction work includes
the construction of the station and the approaching viaducts.
The construction of
the station would interface with the re-construction works of Staunton Creek
Nullah in Wong Chuk Hang, where a section of about 600m between the Ocean Park
Road Roundabout and Tai Wong Ye Temple will be decked.
Viaduct section between
The construction of
the piers and foundation for the viaduct will divert existing roads and
footpaths and will need to slightly modify building structures such as Nam Long
Shan Road Cooked Food Market, Nam Long Shan Road Children’s Playground.
10.1.1.5 Wong Chuk Hang (WCH) Depot
The majority of Wong
Chuk Hang Estate works site would be excavated for the construction of the WCH
station and the depot. A number of the major construction works including site
formation, piling, piling caps and footings and structure work is found within
Zone A to Zone E of the depot, with similar works undertaken within each zone.
According to the construction programme, the construction works would be
carried out simultaneously at each zone. The worst case scenario, based on the
construction programme, is that three zones (Zones C, D and E) are for site
formation, one zone (Zone A) is for piling, one zone (Zone E) is for crushing
works and no major construction works in Zone B, since these works would occupy
the largest works areas and thus are of the largest dust emissions in the
modelling exercise. Details on zoning for
site formation and structure/ fitting out works are shown in Figure 10.8.
Minor blasting
activities for site formation would be carried out at the ground level of the
depot, once per day. Dust generation from the minor blasting works was
considered as one of the activities of the “heavy construction work” assumed in
the modelling exercise as for the minor blasting at WCH Depot, tarpaulin
covers would be provided on wire mesh covered steel cages to contain the dust. Rock crushing would be carried out in the
works site to crush the larger rock fragments produced from blasting process
and the rocks would be moved to the stockpiles for temporary storage and then
transported to the barging point for disposal. Licence for Specified Processes
as described in Section 10.2.3 is
required if the capacity of the
crushing plant exceeds the capacity as described in Section 10.2.3.
A small concrete
batching plant (production rate approximately 500 tons/hr) is also located in
the depot. However, it would be only operating during the construction of the
super structure, i.e. after the completion of site formation and piling works.
As its operation would not be cumulated with other dusty construction works,
site formation and piling works, the dust contribution / impact would be
minimal. The assessment results presented in the later Sections are already
represented the worst case scenario. Licence for Specified Processes as
described in Section 10.2.3 is
required if the capacity of the concrete batching plant exceeds the capacity as
described in Section 10.2.3. If
license is applied and granted, relevant conditions as imposed by the license
will be followed.
10.1.1.6 Lei Tung (LET) Station
Lei Tung would be a
deep underground station with entrances, vent shafts and fireman’s access
provided at ground level. After passing through the Ap Lei Chau Bridge, the
viaducts section would enter to the cut-and-cover tunnel at Ap Lei Chau Drive.
A fan chamber will be situated adjacent to
The construction of
the cut-and-cover tunnel and the portal would be carried out in two stages. The
first stage would be carried out within the work site at the existing
Table 10.13: Major Construction Works at Lei Tung Portal & Tunnel
Construction Stage |
Construction Works |
Stage 1 |
Demolition of Excavation of for construction of cut-and-cover tunnel Clearance of existing planter area |
Stage 2 |
Installation of pipe pile wall Excavation for construction of remaining cut-and cover tunnel Installation of bored piles |
There are also a few works sites for the construction of the entrances and the stabilization of slope work.
10.1.1.7 South Horizon (SOH) Station
The SOH station
would be underground and constructed by the cut-and-cover method, while the section
under Yuk Kwai Shan would be constructed by drill and blast method. The
proposed works areas would be founded by mini-bored piles socketed in rock and
bounded by screen walls. There would also be construction of the entrances at
the works areas at
A Lee Wing Street
Plant building will be constructed at the existing slope along
There are also some
modification works to the existing deck structure at the east of South Horizon
and the widening of the footpath at all three entrances, however, dust emission
is considered to be insignificant.
Major mucking out activities
would be carried out via the construction adit at the portal connecting the
tunnel and the spoils would be further transported to the
10.1.1.8
Telegraph Bay
Barging Point is situated on the seafront, where barging activities will mainly
be carried out for the eastern portion of the site. The site would mainly handle the spoil
materials transported from WCH depot and Nam Fung portal.
Major construction
activities that would generate adverse dust impacts include the material
handling in the stockpile areas, road traffic within the site and the unloading
activities to the barge.
10.1.1.9
The spoil generated
by the excavation of LET station and the approach tunnel could be disposed from
an access adit at Lee Wing Street to the barging point via a temporary conveyor
belt. Spoil generated from the works sites at South Horizons and tunnel section
at
Major construction
activities from the site include the temporary spoil disposal, and road traffic
within the site and unloading activities to the barges from the trucks and the
conveyor belt.
10.1.1.10 Chung Hom Shan Magazine Site
The area is located to the south of Chung Hom Shan, in a
disused quarry located at the end of a road that passes a PCCW satellite
receiving station. Paved access
road with slight overgrowth is closed to the public from Chung
Hom Shan. The site is situated at a disused platform at the
end of the road.
10.1.1.11
Concurrent
Projects
There is also a
number of Essential Public Infrastructure Works (EPIW) to be carried out during
the construction of the subject Project. They were all considered as concurrent
works and included in the dust impact assessment. Construction activities are
described in Table 10.14. The construction
programme of the concurrent projects was given in Appendix 10.1.
Dust source from the
Wan Chai Development Phase II and Central-Wan Chai Bypass project and Harbour
Area Treatment Scheme Stage 2A project were included. Another project, Shatin
to Central Link (SCL), is also proposed by the Project Proponent. The enabling
works of SCL at Admiralty will be carried out under SIL(E) at the time of the
ADM construction. All plants to be involved in the ADM construction have been
included in the dust impact assessment. It is considered that the cumulative
impact from the SCL project had been taken into account in the assessment.
For the Central
Reclamation Phase III project, according to the latest project programme
available from the project website (http://www.criii-cedd.com/),
the progress of reclamation works which may potentially cause dust emissions
have been completed at least 95% in mid 2009. The construction of the Central
Reclamation Phase III project will cease in November 2011. The concurrent
period between the subject Project and Central Reclamation Phase III project is
about 6 months only which is considered to be short. The remaining works in
these 6 months will only include finishing works which would not include heavy
construction and are therefore unlikely to be dusty. As such, the Central
Reclamation Phase III project was not included in the quantitative dust
assessment since dust emissions from the Central Reclamation Phase III project
contribute insignificantly when the subject Project commences.
The Tamer
Development project adjacent to Admiralty Station will be completed in May
2011. The Tamar Development project would unlikely be a concurrent project with
the subject Project. According to the latest available construction works
programme as presented in the Paper “Legislative Council Panel on Development Progress
Report on the Tamar Development Project”, the remaining works will only include
snagging inspection and handover upon commencement of the subject Project. As
such, dust emission from this work will not be anticipated. Therefore the
cumulative dust impact due to the Tamar Development project is considered to be
insignificant.
For the Drainage Improvement in
Table 10.14: Potential Emission Sources from EPIW and Concurrent Projects
Location |
Construction Activities |
EPIW |
|
Wong Chuk Hang |
¡
Widening of ¡ Public Transport Interchange (PTI) underneath Wong Chuk Hang (WCH) Station; ¡
Footbridge connecting to |
Ap Lei Chau |
¡ Footbridge connecting to Ap Lei Chau Estate. |
Other
Concurrent Projects |
|
Admiralty |
¡ Wan Chai Development Phase II and Central-Wan Chai Bypass ¡
Drainage
Improvement in Northern |
|
¡ Harbour Area Treatment Scheme (HATS) Stage 2A ¡
Drainage
Improvement in Northern |
Wong Chuk Hang |
¡ Re- provisioning of PTI |
The assessment of construction dust impacts has been carried out based on the following assumptions of the general construction activities:
§ All construction activities at all work sites and areas would be undertaken concurrently in order to assess the worst case situation
§ Heavy construction activities would include site clearance, excavation, foundation works, cut and cover operations, construction of the associated facilities, slope stabilization works, and construction traffic and hauling over the sites
§ For the minor blasting at WCH Depot, tarpaulin covers would be provided on wire mesh covered steel cages to contain the dust. Therefore, the heavy construction emission factor is considered adequate for the Fugitive Dust Model (FDM) in the air quality assessment to address the dust generated from this activity
§ Wind erosion area of 30% has been assumed at any time for the hourly and daily TSP predictions and 6% at any time for annual TSP. However, to be conservative a 100% active area screening test has been undertaken initially for the short term hourly and daily TSP assessment as detailed in Section 10.5.6
§ Active operating areas of 30% have been assumed at any time for the hourly and daily TSP predictions and 6% active operating area at any time for annual TSP predictions for all sites. However, to be conservative a 100% active area screening test has been undertaken initially for the short term hourly and daily TSP assessment as detailed in Section 10.5.6
§ Construction periods are assumed to be 26 working days per month and 12 operation hours per day from 0700 to 1900. as the worst case scenario
Dust emission factors for different construction activities had been extracted from the USEPA “Compilation of Air Pollution Emission Factors (AP-42)”, 5th edition. The key assumptions for the calculation of dust emission factors are summarised in Table 10.15 below.
Table 10.15: Assumptions
for Calculation of Dust Emission Factors
Activities |
Reference [1] |
Operating Sites |
Equations and Assumptions [1] |
Heavy construction activities including site clearance, excavation, foundation works, cut and cover operations, construction of the associated facilities, slope stabilization works, and construction traffic and hauling over the sites [2] |
S.13.2.3.3 |
All above ground and open construction and excavation sites |
E=1.2tons/acre/month of activity or 2.69Mg/hectare/month of activity |
Wind erosion |
S11.9. Table 11.9.4 |
Area of 30% for the hourly and daily TSP prediction and 6% for annual TSP |
E = 0.85 Mg/hectare/yr (24 hour emission) |
Loading and unloading at barging point |
S.13.2.4 |
Barging
point |
E=k*0.0016*(U/2.2)^1.3/(M/2)^1.4
kg/Mg k is
particle size multiplier U is
average wind spped M is
material moisture content |
Unloading of rock materials at the receiving point of rock
crushing facilities |
S11.19.2,
Table 11.19.2-1 |
Rock
crushing facilities |
E=
0.000008 kg/Mg |
Crushing at rock crushing facilities |
S11.19.2,
Table 11.19.2-1 |
Rock
crushing facilities |
E = 0.0027
kg/Mg |
Screening at rock crushing facilities |
S11.19.2,
Table 11.19.2-1 |
Rock
crushing facilities |
E =
0.0125 kg/Mg |
[1] USEPA Compilation of Air Pollution Emission Factors (AP-42)
[2] For the minor blasting at WCH Depot, tarpaulin covers would be provided on wire mesh covered steel cages to contain the dust and therefore, the emission factors associated with heavy construction has been used for the modelling.
The emission factors used for each scenario in the FDM model
were provided in Appendix 10.2. The potential dust emission sources are
shown in Figures 10.9 to 10.16.
The major dust
generating activities at the rock crushing facilities at Nam Fung Portal and
Wong Chuk Hang Depot would be assumed to mainly originate from the unloading of
rock materials, crushing and screening processes. The rock crushing facilities
are assumed to have maximum daily output of over 1000m3 per day and
would be assumed to be equipped with the following measures:
¡ A dust enclosure with fabric baghouse/cartridge filter type dust extraction and collection system or equivalent system with 99% or more dust removal efficiency for the rock crushing facilities including unloading location.
The air pollutant concentrations were assessed in accordance
with the Guidelines for Choice of Models
and Model Parameters in Air Quality Assessment published by
Emission factors for various fugitive dust sources were determined based on the USEPA Compilation of Air Pollutant Emission Factors, 5th Edition (AP-42), Sections 11.9 and 13.2.3. Calculation of the emission factors was detailed in Appendix 10.2. The input information of dust sources were detailed in Appendix 10.3.
10.1.4 Particle Size Distribution
In the FDM model runs, the particle size distribution was made reference to the USEPA Compilation of Air Pollutant Emission Factors 5th Edition, Section 13.2.4 November 2006.
Sequential meteorological data includes wind speed, wind
direction, Pasquill stability class, temperature and mixing height from
meteorological stations for the year 2008
were used in the FDM model to obtain hourly, daily and annual average
It is noted that
valid data was found to be less than 90% in 2008 (and 2007) for the original
WCH meteorology dataset. As such, treatment has been made for those hourly
meteorology data with missing/invalid wind direction recorded. The treatment
method was made reference to Air
Dispersion Modelling Guideline for
According to the
guideline, the missing wind direction found in WCH station was filled with data
from a nearby station with similar climatology.
In this case, Cheung Chau station was selected. Missing wind directions
last longer than six consecutive hours have been left as "missing"
data. Hours with calm or very low wind speeds (<1 m/s) were set to a minimum
speed of 1m/s.
For hourly and daily TSP, it is assumed that 30% of total works area would be active at any one time. Detailed calculation of the assumed percentage of active area is provided in Appendix 10.4. As active construction activities would be undertaken at moving multiple works faces spread across the site, works activities would not be concentrated in certain areas of the site close to ASRs at any time. However, notwithstanding that such a scenario would not be expected to occur, for hourly and daily TSP predictions, to be conservative, a hypothetical Tier 1 screening that assumes 100% active area of construction site with mitigation measures in place was carried out. The purpose is to highlight the ASRs where construction dust may potentially become an issue. However, it should be emphasized that Tier 1 scenario (i.e. assuming 100% active area for the subject Project and all other concurrent projects) is a hypothetical one which does not occurred in reality.
The Tier 1 results have allowed a more focused Tier 2 assessment to be undertaken at specific ASRs with TSP non-compliance in the Tier 1 screening. For each of these selected ASRs, it is assumed that 30% active area for the subject Project and other concurrent projects are located closest to the particular ASR. The TSP level at the particular ASR is subsequently predicted and presented. The Tier 2 assessment is also a very conservative approach as it assumed 30% active area for the subject Project and all concurrent projects located closest to the particular ASR at any one time, which as noted above, is unlikely to occur in reality
For annual TSP, 6% of active area for the subject Project and all concurrent projects has been assumed. Detailed calculation of the assumed percentage of active area is provided in Appendix 10.4.
The highest 1-hour, highest daily and annual
10.2 Identification, Prediction and Evaluation of Environmental Impact
The predicted unmitigated hourly, daily and annual average
Table 10.16: Predicted
Cumulative Hourly Average TSP Concentrations in Admiralty (Unmitigated)
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
|
- |
- |
- |
- |
217 |
|
1056 |
535 |
394 |
296 |
215 |
|
459 |
458 |
382 |
297 |
224 |
|
603 |
582 |
448 |
316 |
219 |
|
- |
- |
- |
- |
226 |
|
- |
- |
- |
- |
240 |
|
- |
- |
- |
- |
224 |
|
- |
1044 |
481 |
313 |
196 |
|
1602 |
834 |
461 |
285 |
225 |
ADM13 |
- |
522 |
410 |
297 |
211 |
ADM14 |
- |
- |
- |
- |
212 |
ADM15 |
- |
- |
- |
- |
192 |
ADM16 |
- |
- |
358 |
252 |
190 |
ADM17 |
- |
- |
- |
- |
205 |
ADM18 |
- |
- |
- |
- |
215 |
ADM19 |
432 |
421 |
336 |
249 |
194 |
ADM20 |
411 |
412 |
351 |
281 |
218 |
ADM21 |
- |
- |
- |
- |
228 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.17: Predicted
Cumulative Hourly Average TSP Concentrations in
ASRs |
Cumulative
Hourly Average |
||||
1.5m
|
5m |
10m
|
15m
|
20m
|
|
NFP1 |
1530 |
1224 |
906 |
784 |
669 |
NFP2 |
977 |
1019 |
909 |
770 |
623 |
NFP3 |
1101 |
1150 |
1032 |
883 |
724 |
NFP4 |
1144 |
1191 |
1062 |
903 |
735 |
NFP5 |
1561 |
1561 |
1281 |
1022 |
810 |
NFP6 |
3377 |
2440 |
1490 |
1047 |
781 |
NFP7 |
1333 |
1330 |
1076 |
874 |
715 |
NFP8 |
1353 |
1356 |
1113 |
896 |
726 |
NFP9 |
1343 |
1339 |
1083 |
873 |
713 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.18: Predicted
Cumulative Hourly Average TSP Concentrations in
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
OCP1 |
1438 |
1462 |
1237 |
970 |
712 |
OCP2 |
2041 |
2016 |
1600 |
1181 |
839 |
OCP3 |
3651 |
2714 |
1680 |
1112 |
781 |
OCP4 |
3957 |
2051 |
1586 |
1101 |
714 |
OCP6 |
1159 |
1200 |
1050 |
866 |
677 |
OCP7 |
1753 |
1645 |
1204 |
944 |
739 |
OCP8 |
3156 |
1768 |
1303 |
997 |
712 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.19: Predicted
Cumulative Hourly Average TSP Concentrations in Wong Chuk Hang (Unmitigated)
ASRs |
Cumulative
Hourly Average |
||||
1.5m
|
5m |
10m
|
15m
|
20m
|
|
WCH1 |
4039 |
3310 |
1770 |
1126 |
826 |
WCH2 |
6024 |
3038 |
1637 |
1030 |
749 |
WCH3 |
6983 |
3259 |
1686 |
1080 |
845 |
WCH4 |
4760 |
3592 |
1705 |
1146 |
782 |
WCH5 |
5441 |
3301 |
1602 |
1052 |
773 |
WCH6 |
7692 |
3060 |
1558 |
997 |
767 |
WCH7 |
- |
2760 |
1436 |
1048 |
742 |
WCH8 |
3961 |
2834 |
1752 |
1040 |
789 |
WCH9 |
- |
2861 |
1690 |
1024 |
773 |
WCH10 |
2293 |
2194 |
1651 |
1141 |
754 |
WCH11 |
3069 |
2197 |
1651 |
1145 |
766 |
WCH12 |
1639 |
1646 |
1361 |
1055 |
787 |
WCH13 |
2120 |
1976 |
1443 |
1030 |
742 |
WCH14 |
5929 |
3003 |
1599 |
1049 |
825 |
WCH16 |
- |
- |
1720 |
1092 |
837 |
WCH17 |
5934 |
3530 |
1709 |
1071 |
853 |
WCH18 |
6547 |
3304 |
1579 |
1052 |
812 |
WCH21 |
3784 |
2884 |
1582 |
1037 |
805 |
WCH22 |
1918 |
1871 |
1457 |
1034 |
692 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average TSP levels criterion, i.e. 500 μg/m3
Table 10.20: Predicted Cumulative Hourly Average TSP Concentrations in Lei
Tung (Unmitigated)
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
LET1 |
2246 |
1442 |
1025 |
813 |
655 |
LET2 |
2015 |
1358 |
977 |
849 |
711 |
LET3 |
1825 |
1484 |
1097 |
843 |
673 |
LET4 |
2664 |
2064 |
1220 |
868 |
688 |
LET5 |
3427 |
1232 |
852 |
752 |
642 |
LET6 |
1192 |
773 |
716 |
643 |
561 |
LET7 |
1127 |
779 |
693 |
622 |
543 |
LET8 |
2167 |
1080 |
951 |
801 |
656 |
LET9 |
1622 |
1122 |
982 |
822 |
670 |
LET10 |
1858 |
793 |
735 |
663 |
582 |
LET11 |
1621 |
817 |
758 |
682 |
596 |
LET12 |
1036 |
951 |
684 |
609 |
538 |
LET13 |
1009 |
848 |
708 |
639 |
563 |
LET14 |
1226 |
762 |
710 |
643 |
567 |
LET15 |
3501 |
1140 |
1027 |
886 |
732 |
LET19 |
2515 |
1759 |
857 |
750 |
642 |
LET20 |
1331 |
1150 |
690 |
617 |
536 |
LET21 |
1568 |
1365 |
1047 |
815 |
648 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.21: Predicted
Cumulative Hourly Average TSP Concentrations in South Horizons (Unmitigated)
ASRs |
Cumulative
Hourly Average |
||||
1.5m
|
5m |
10m
|
15m
|
20m
|
|
SOH1 |
3608 |
1264 |
632 |
552 |
489 |
SOH2 |
3529 |
1126 |
590 |
531 |
472 |
SOH3 |
2778 |
1436 |
646 |
544 |
481 |
SOH4 |
3628 |
1133 |
621 |
561 |
497 |
SOH5 |
2805 |
1203 |
639 |
584 |
521 |
SOH6 |
1851 |
914 |
653 |
599 |
538 |
SOH8 |
1760 |
1137 |
715 |
544 |
485 |
SOH9 |
2824 |
1366 |
731 |
579 |
504 |
SOH11 |
1926 |
889 |
654 |
598 |
535 |
SOH13 |
1194 |
941 |
678 |
609 |
534 |
SOH14 |
922 |
840 |
730 |
624 |
522 |
SOH15 |
866 |
786 |
726 |
651 |
568 |
SOH16 |
1916 |
1229 |
710 |
637 |
564 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.22: Predicted
Cumulative Hourly Average TSP Concentrations at
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
TGB1 |
198 |
218 |
211 |
204 |
195 |
TGB2 |
226 |
249 |
241 |
231 |
220 |
TGB3 |
192 |
211 |
204 |
197 |
189 |
TGB4 |
204 |
224 |
217 |
209 |
200 |
TGB5 |
321 |
246 |
238 |
229 |
219 |
TGB6 |
236 |
261 |
252 |
242 |
231 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.23: Predicted
Cumulative Hourly Average TSP Concentrations at
ASRs |
Cumulative
Hourly Average |
||||
1.5m
|
5m |
10m
|
15m
|
20m
|
|
LNB1 |
- |
655 |
492 |
421 |
381 |
LNB2 |
- |
751 |
528 |
445 |
405 |
LNB3 |
- |
918 |
560 |
515 |
465 |
LNB4 |
1829 |
1188 |
624 |
565 |
502 |
LNB5 |
1883 |
1234 |
626 |
543 |
483 |
LNB6 |
1891 |
1283 |
610 |
555 |
495 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.24: Predicted
Cumulative Hourly Average TSP Concentrations at Chung Hom Shan Magazine Site
(Unmitigated)
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
|
310 |
309 |
263 |
209 |
194 |
|
298 |
300 |
258 |
209 |
183 |
|
564 |
530 |
380 |
239 |
184 |
CHK5 |
528 |
501 |
371 |
243 |
183 |
Table 10.25: Predicted
Cumulative Daily Average TSP Concentrations in Admiralty (Unmitigated)
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
|
- |
- |
- |
- |
108 |
|
296 |
178 |
144 |
125 |
109 |
|
132 |
132 |
123 |
111 |
101 |
|
153 |
151 |
134 |
116 |
102 |
|
- |
- |
- |
- |
109 |
|
- |
- |
- |
- |
117 |
|
- |
- |
- |
- |
103 |
|
- |
366 |
220 |
140 |
118 |
|
331 |
263 |
153 |
122 |
104 |
ADM13 |
- |
185 |
160 |
134 |
114 |
ADM14 |
- |
- |
- |
- |
113 |
ADM15 |
- |
- |
- |
- |
103 |
ADM16 |
- |
- |
156 |
118 |
103 |
ADM17 |
- |
- |
- |
- |
104 |
ADM18 |
- |
- |
- |
- |
104 |
ADM19 |
168 |
164 |
145 |
127 |
112 |
ADM20 |
125 |
126 |
118 |
109 |
100 |
ADM21 |
- |
- |
- |
- |
102 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.26: Predicted
Cumulative Daily Average TSP Concentrations in
ASRs |
Cumulative
Hourly Average |
||||
1.5m
|
5m |
10m
|
15m
|
20m
|
|
NFP1 |
378 |
287 |
203 |
176 |
158 |
NFP2 |
239 |
239 |
214 |
188 |
166 |
NFP3 |
268 |
261 |
229 |
199 |
174 |
NFP4 |
306 |
288 |
230 |
200 |
175 |
NFP5 |
530 |
340 |
263 |
211 |
177 |
NFP6 |
684 |
484 |
313 |
235 |
193 |
NFP7 |
260 |
249 |
221 |
194 |
168 |
NFP8 |
284 |
279 |
234 |
197 |
168 |
NFP9 |
263 |
249 |
223 |
195 |
169 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.27: Predicted
Cumulative Daily Average TSP Concentrations in
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
OCP1 |
293 |
280 |
246 |
213 |
181 |
OCP2 |
480 |
392 |
302 |
246 |
205 |
OCP3 |
791 |
563 |
379 |
283 |
216 |
OCP4 |
763 |
455 |
354 |
281 |
220 |
OCP6 |
259 |
246 |
220 |
198 |
175 |
OCP7 |
413 |
316 |
260 |
217 |
186 |
OCP8 |
567 |
355 |
300 |
252 |
208 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.28: Predicted
Cumulative Daily Average TSP Concentrations in Wong Chuk Hang (Unmitigated)
ASRs |
Cumulative
Hourly Average |
||||
1.5m
|
5m |
10m
|
15m
|
20m
|
|
WCH1 |
793 |
684 |
445 |
286 |
205 |
WCH2 |
1320 |
835 |
456 |
302 |
224 |
WCH3 |
2030 |
1078 |
476 |
295 |
227 |
WCH4 |
891 |
711 |
469 |
301 |
240 |
WCH5 |
1131 |
792 |
431 |
298 |
246 |
WCH6 |
2119 |
1062 |
443 |
310 |
237 |
WCH7 |
- |
720 |
444 |
301 |
222 |
WCH8 |
999 |
568 |
399 |
282 |
216 |
WCH9 |
- |
509 |
380 |
283 |
224 |
WCH10 |
405 |
379 |
322 |
262 |
211 |
WCH11 |
711 |
420 |
335 |
267 |
214 |
WCH12 |
306 |
309 |
272 |
232 |
197 |
WCH13 |
472 |
406 |
308 |
247 |
205 |
WCH14 |
1463 |
880 |
433 |
280 |
219 |
WCH16 |
- |
- |
469 |
281 |
219 |
WCH17 |
1224 |
820 |
425 |
284 |
219 |
WCH18 |
1974 |
1083 |
474 |
321 |
249 |
WCH21 |
781 |
576 |
388 |
295 |
230 |
WCH22 |
403 |
327 |
268 |
222 |
194 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average TSP levels criterion, i.e. 500 μg/m3
Table 10.29: Predicted Cumulative Daily Average TSP Concentrations in Lei Tung
(Unmitigated)
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
LET1 |
725 |
311 |
194 |
160 |
142 |
LET2 |
449 |
253 |
173 |
139 |
125 |
LET3 |
404 |
286 |
199 |
156 |
136 |
LET4 |
383 |
292 |
194 |
154 |
130 |
LET5 |
447 |
293 |
172 |
138 |
126 |
LET6 |
270 |
165 |
139 |
131 |
123 |
LET7 |
202 |
151 |
138 |
130 |
121 |
LET8 |
494 |
201 |
168 |
149 |
134 |
LET9 |
541 |
199 |
163 |
146 |
133 |
LET10 |
454 |
203 |
145 |
132 |
124 |
LET11 |
380 |
190 |
142 |
135 |
126 |
LET12 |
177 |
173 |
149 |
128 |
121 |
LET13 |
204 |
165 |
147 |
136 |
126 |
LET14 |
212 |
162 |
141 |
131 |
122 |
LET15 |
727 |
313 |
177 |
143 |
126 |
LET19 |
261 |
218 |
170 |
144 |
128 |
LET20 |
162 |
157 |
141 |
132 |
123 |
LET21 |
407 |
278 |
204 |
164 |
142 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.30: Predicted
Cumulative Daily Average TSP Concentrations in South Horizons (Unmitigated)
ASRs |
Cumulative
Hourly Average |
||||
1.5m
|
5m |
10m
|
15m
|
20m
|
|
SOH1 |
891 |
382 |
197 |
143 |
122 |
SOH2 |
1031 |
384 |
197 |
143 |
123 |
SOH3 |
663 |
408 |
218 |
157 |
125 |
SOH4 |
927 |
348 |
223 |
164 |
130 |
SOH5 |
687 |
328 |
213 |
169 |
138 |
SOH6 |
408 |
248 |
184 |
149 |
133 |
SOH8 |
347 |
255 |
188 |
147 |
123 |
SOH9 |
551 |
344 |
197 |
156 |
132 |
SOH11 |
441 |
283 |
196 |
153 |
133 |
SOH13 |
233 |
210 |
156 |
142 |
128 |
SOH14 |
249 |
231 |
173 |
141 |
130 |
SOH15 |
184 |
174 |
158 |
142 |
128 |
SOH16 |
359 |
285 |
175 |
142 |
127 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.31: Predicted
Cumulative Daily Average TSP Concentrations at
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
TGB1 |
90 |
91 |
90 |
89 |
88 |
TGB2 |
91 |
93 |
92 |
92 |
91 |
TGB3 |
90 |
93 |
92 |
91 |
90 |
TGB4 |
92 |
91 |
90 |
89 |
89 |
TGB5 |
126 |
109 |
91 |
90 |
89 |
TGB6 |
94 |
94 |
92 |
90 |
89 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.32: Predicted
Cumulative Daily Average TSP Concentrations at
ASRs |
Cumulative
Hourly Average |
||||
1.5m
|
5m |
10m
|
15m
|
20m
|
|
LNB1 |
- |
138 |
124 |
111 |
104 |
LNB2 |
- |
153 |
131 |
116 |
107 |
LNB3 |
- |
209 |
164 |
132 |
115 |
LNB4 |
378 |
308 |
193 |
140 |
124 |
LNB5 |
278 |
242 |
179 |
143 |
129 |
LNB6 |
433 |
342 |
216 |
150 |
122 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.33: Predicted
Cumulative Daily Average TSP Concentrations at Chung Hom Shan Magazine Site
(Unmitigated)
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
|
104 |
104 |
99 |
93 |
87 |
|
94 |
94 |
90 |
86 |
83 |
|
98 |
97 |
90 |
87 |
86 |
CHK5 |
114 |
112 |
100 |
89 |
84 |
Table 10.34: Predicted
Cumulative Annual Average TSP Concentrations in Admiralty (Unmitigated)
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
|
- |
- |
- |
- |
78 |
|
79 |
78 |
78 |
78 |
78 |
|
79 |
79 |
78 |
78 |
78 |
|
78 |
78 |
78 |
78 |
78 |
|
- |
- |
- |
- |
79 |
|
- |
- |
- |
- |
79 |
|
- |
- |
- |
- |
78 |
|
- |
82 |
80 |
79 |
79 |
|
79 |
79 |
79 |
79 |
78 |
ADM13 |
- |
79 |
78 |
78 |
78 |
ADM14 |
- |
- |
- |
- |
78 |
ADM15 |
- |
- |
- |
- |
78 |
ADM16 |
- |
- |
79 |
79 |
78 |
ADM17 |
- |
- |
- |
- |
78 |
ADM18 |
- |
- |
- |
- |
78 |
ADM19 |
78 |
78 |
78 |
78 |
78 |
ADM20 |
78 |
78 |
78 |
78 |
78 |
ADM21 |
- |
- |
- |
- |
78 |
Note: The background
Bold: The predicted
value exceeds the annual average
Table 10.35: Predicted
Cumulative Annual Average TSP Concentrations in
ASRs |
Cumulative
Hourly Average |
||||
1.5m
|
5m |
10m
|
15m
|
20m
|
|
NFP1 |
83 |
79 |
75 |
75 |
74 |
NFP2 |
86 |
83 |
78 |
76 |
75 |
NFP3 |
83 |
80 |
77 |
75 |
75 |
NFP4 |
84 |
81 |
78 |
76 |
75 |
NFP5 |
85 |
81 |
77 |
76 |
75 |
NFP6 |
96 |
81 |
77 |
75 |
75 |
NFP7 |
78 |
77 |
76 |
75 |
75 |
NFP8 |
76 |
76 |
75 |
75 |
74 |
NFP9 |
78 |
77 |
76 |
75 |
75 |
Note: The background
Bold: The predicted
value exceeds the annual average
Table 10.36: Predicted
Cumulative Annual Average TSP Concentrations in
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
OCP1 |
78 |
78 |
77 |
76 |
75 |
OCP2 |
82 |
81 |
78 |
76 |
75 |
OCP3 |
83 |
80 |
78 |
76 |
75 |
OCP4 |
87 |
79 |
77 |
76 |
75 |
OCP6 |
77 |
77 |
76 |
75 |
74 |
OCP7 |
79 |
78 |
76 |
75 |
75 |
OCP8 |
81 |
78 |
76 |
75 |
75 |
Note: The background
Bold: The predicted
value exceeds the annual average
Table 10.37: Predicted
Cumulative Annual Average TSP Concentrations in Wong Chuk Hang (Unmitigated)
ASRs |
Cumulative
Hourly Average |
||||
1.5m
|
5m |
10m
|
15m
|
20m
|
|
WCH1 |
82 |
80 |
78 |
76 |
75 |
WCH2 |
84 |
81 |
78 |
76 |
75 |
WCH3 |
101 |
92 |
82 |
77 |
76 |
WCH4 |
100 |
94 |
85 |
80 |
77 |
WCH5 |
125 |
110 |
92 |
83 |
79 |
WCH6 |
107 |
94 |
83 |
78 |
76 |
WCH7 |
- |
100 |
89 |
83 |
79 |
WCH8 |
93 |
87 |
82 |
79 |
77 |
WCH9 |
- |
84 |
81 |
79 |
77 |
WCH10 |
81 |
80 |
78 |
77 |
76 |
WCH11 |
85 |
80 |
78 |
77 |
76 |
WCH12 |
77 |
77 |
77 |
76 |
75 |
WCH13 |
80 |
79 |
77 |
76 |
75 |
WCH14 |
89 |
84 |
79 |
76 |
75 |
WCH16 |
- |
- |
80 |
77 |
75 |
WCH17 |
101 |
94 |
83 |
78 |
76 |
WCH18 |
191 |
136 |
93 |
82 |
78 |
WCH21 |
91 |
87 |
83 |
80 |
78 |
WCH22 |
80 |
80 |
78 |
77 |
76 |
Note: The background
Bold: The predicted
value exceeds the annual average TSP levels criterion, i.e. 80 μg/m3
Table 10.38: Predicted Cumulative Annual Average TSP Concentrations in Lei
Tung (Unmitigated)
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
LET1 |
82 |
78 |
76 |
75 |
75 |
LET2 |
78 |
76 |
75 |
75 |
74 |
LET3 |
80 |
78 |
76 |
75 |
74 |
LET4 |
80 |
78 |
76 |
75 |
74 |
LET5 |
77 |
75 |
75 |
74 |
74 |
LET6 |
75 |
75 |
74 |
74 |
74 |
LET7 |
75 |
75 |
74 |
74 |
74 |
LET8 |
78 |
75 |
75 |
74 |
74 |
LET9 |
82 |
76 |
75 |
74 |
74 |
LET10 |
83 |
75 |
74 |
74 |
74 |
LET11 |
76 |
75 |
74 |
74 |
74 |
LET12 |
74 |
74 |
74 |
74 |
74 |
LET13 |
75 |
75 |
74 |
74 |
74 |
LET14 |
75 |
75 |
74 |
74 |
74 |
LET15 |
81 |
77 |
75 |
75 |
74 |
LET19 |
75 |
75 |
75 |
74 |
74 |
LET20 |
75 |
75 |
74 |
74 |
74 |
LET21 |
80 |
78 |
76 |
75 |
75 |
Note: The background
Bold: The predicted
value exceeds the annual average
Table 10.39: Predicted
Cumulative Annual Average TSP Concentrations in South Horizons (Unmitigated)
ASRs |
Cumulative
Hourly Average |
||||
1.5m
|
5m |
10m
|
15m
|
20m
|
|
SOH1 |
91 |
81 |
76 |
75 |
74 |
SOH2 |
87 |
79 |
76 |
75 |
74 |
SOH3 |
87 |
79 |
76 |
75 |
74 |
SOH4 |
84 |
78 |
76 |
75 |
74 |
SOH5 |
84 |
77 |
75 |
75 |
74 |
SOH6 |
79 |
76 |
75 |
74 |
74 |
SOH8 |
78 |
77 |
76 |
75 |
74 |
SOH9 |
82 |
79 |
76 |
75 |
74 |
SOH11 |
78 |
76 |
75 |
75 |
74 |
SOH13 |
77 |
77 |
75 |
75 |
74 |
SOH14 |
76 |
75 |
75 |
74 |
74 |
SOH15 |
76 |
75 |
75 |
74 |
74 |
SOH16 |
77 |
76 |
75 |
75 |
74 |
Note: The background
Bold: The predicted
value exceeds the annual average
Table 10.40: Predicted
Cumulative Annual Average TSP Concentrations at
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
TGB1 |
74 |
74 |
74 |
74 |
74 |
TGB2 |
74 |
74 |
74 |
74 |
74 |
TGB3 |
74 |
74 |
74 |
74 |
74 |
TGB4 |
75 |
75 |
74 |
74 |
74 |
TGB5 |
76 |
75 |
74 |
74 |
74 |
TGB6 |
75 |
75 |
74 |
74 |
74 |
Note: The background
Bold: The predicted
value exceeds the annual average
Table 10.41: Predicted
Cumulative Annual Average TSP Concentrations at
ASRs |
Cumulative
Hourly Average |
||||
1.5m
|
5m |
10m
|
15m
|
20m
|
|
LNB1 |
- |
77 |
74 |
74 |
74 |
LNB2 |
- |
77 |
74 |
74 |
74 |
LNB3 |
- |
76 |
75 |
74 |
74 |
LNB4 |
78 |
76 |
75 |
74 |
74 |
LNB5 |
79 |
78 |
76 |
75 |
74 |
LNB6 |
85 |
77 |
75 |
74 |
74 |
Note: The background
Bold: The predicted
value exceeds the annual average
Table 10.42: Predicted
Cumulative Annual Average TSP Concentrations at Chung Hom Shan Magazine Site
(Unmitigated)
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
|
73 |
73 |
73 |
73 |
73 |
|
73 |
73 |
73 |
73 |
73 |
|
73 |
73 |
73 |
73 |
73 |
CHK5 |
73 |
73 |
73 |
73 |
73 |
Note: The background
Bold: The predicted value
exceeds the annual average
The following specific mitigation measures and proposed dust removal efficiencies that have been assumed in the modelling exercise to reduce dust generation from the Project to comply with the 1-hour, 24-hour and annual TSP AQO criteria of 500μg/m3, 260 μg/m3 and 80 μg/m3 at ASRs have been applied for both Tier 1, Tier 2 and annual TSP predictions:
¡ For the unloading of spoil from trucks at barging point, installation of 3-sided screen with top and the provision of water sprays at the discharge point would be provided for an assumed 50% dust suppression. This assumption is based upon USEPA AP-42 Control Techniques for Particulate Emissions from Stationary Sources Part 2 which states that watering alone would have 50% dust removal efficiency. This is considered to be very conservative as the barging point would also be provided with a 3 sided-enclosure, which would provide additional dust containment and control
¡ Watering every working hour for 12 hours a day on exposed soil areas on active works areas and paved haul roads to reduce dust emissions by 91.7%, which is with reference to the “Control of Open Fugitive Dust Sources” (USEPA AP-42). It is assumed that the amount of water to be applied would be 1.8L/m2; and
¡ The rock crushing facilities with maximum daily output of over 1000m3 per day would be enclosed including unloading locations and a fabric baghouse/cartridge filter type dust extraction and collection system or equivalent system with 99% or more dust removal efficiency would be installed for the treatment of the emissions from rock crushing and screening processes. The dust removal efficiency of fabric baghouse/cartridge filter type dust extraction and collection system or equivalent for rock crushing activities within an enclosure is assumed to be 99%, with reference to USEPA AP-42 Control Techniques for Particulate Emissions from Stationary Sources – Volume 2, Section 9.7.1.2.1 Emission Control Techniques – Dry Collection on page 9.7-18.
In addition to those measures mentioned above under the auspices of the Air Pollution Control (Construction Dust) Regulation, the Contractor would be required to ensure that dust control measures stipulated in the Regulation should be implemented to control dust emissions.
Disturbed Parts of the Roads
¡ Each and every main temporary access should be paved with concrete, bituminous hardcore materials or metal plates and kept clear of dusty materials; or
¡ Unpaved parts of the road should be sprayed with water or a dust suppression chemical so as to keep the entire road surface wet.
Exposed Earth
¡ Exposed earth should be properly treated by compaction, hydroseeding, vegetation planting or seating with latex, vinyl, bitumen within six months after the last construction activity on the site or part of the site where the exposed earth lies.
Loading, Unloading or Transfer of Dusty Materials
¡ All dusty materials should be sprayed with water immediately prior to any loading or transfer operation so as to keep the dusty material wet.
Debris Handling
¡ Any debris should be covered entirely by impervious sheeting or stored in a debris collection area sheltered on the top and the three sides.
¡ Before debris is dumped into a chute, water should be sprayed so that it remains wet when it is dumped.
¡ For the minor blasting at WCH Depot, tarpaulin covers would be provided on the steel screens to prevent the dust from spreading out.
Transport of Dusty Materials
¡ Vehicle used for transporting dusty materials/spoils should be covered with tarpaulin or similar material. The cover should extend over the edges of the sides and tailboards.
Wheel washing
¡ Vehicle wheel washing facilities provided at each construction site exit.
Stone crushing plants
¡ The control measures listed in EPD’s A Guidance Note on the Best Practicable Means for Mineral Works (Stone Crushing Plants) (BPM 11/1) should be followed, where appropriate.
Concrete Batching Plant
¡ The loading, unloading, handling, transfer or storage of dusty materials shall be carried in a totally
¡ enclosed system. All dust-laden air or waste gas generated by the process operations should be properly extracted and vented to fabric filtering system. The control measures listed in EPD’s A Guidance Note on the Best Practicable Means for Cement Works (Concrete Batching Plant) (BPM 3/2) should be followed, where appropriate.
Good Site Practices
¡ Good site management is important to help reducing potential air quality impact down to an acceptable level. As a general guide, the Contractor should maintain high standard of housekeeping to prevent emission of fugitive dust. Loading, unloading, handling and storage of raw materials, wastes or by-products should be carried out in a manner so as to minimize the release of visible dust emission. Any piles of materials accumulated on or around the work areas should be cleaned up regularly. Cleaning, repair and maintenance of all plant facilities within the work areas should be carried out in a manner minimizing generation of fugitive dust emissions. The material should be handled properly to prevent fugitive dust emission before cleaning.
The mitigation measures as specified above are also detailed in the Implementation Schedule of Mitigation Measures in Section 14.
The predicted mitigated
hourly average
Table 10.43: Predicted
Cumulative Hourly Average TSP Concentrations in Admiralty (Tier 1)
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
|
- |
- |
- |
- |
150 |
|
263 |
219 |
194 |
171 |
148 |
|
224 |
229 |
210 |
186 |
162 |
|
254 |
257 |
229 |
197 |
167 |
|
- |
- |
- |
- |
174 |
|
- |
- |
- |
- |
174 |
|
- |
- |
- |
- |
157 |
|
- |
345 |
268 |
202 |
172 |
|
419 |
407 |
322 |
234 |
177 |
ADM13 |
- |
241 |
216 |
187 |
160 |
ADM14 |
- |
- |
- |
- |
163 |
ADM15 |
- |
- |
- |
- |
192 |
ADM16 |
- |
- |
356 |
252 |
190 |
ADM17 |
- |
- |
- |
- |
205 |
ADM18 |
- |
- |
- |
- |
169 |
ADM19 |
217 |
221 |
203 |
180 |
157 |
ADM20 |
215 |
221 |
203 |
182 |
160 |
ADM21 |
- |
- |
- |
- |
-155 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.44: Predicted
Cumulative Hourly Average TSP Concentrations in
ASRs |
Cumulative
Hourly Average |
||||
1.5m
|
5m |
10m
|
15m
|
20m
|
|
NFP1 |
208 |
179 |
150 |
138 |
128 |
NFP2 |
158 |
162 |
152 |
139 |
125 |
NFP3 |
168 |
172 |
161 |
147 |
132 |
NFP4 |
172 |
176 |
164 |
150 |
134 |
NFP5 |
210 |
210 |
184 |
160 |
140 |
NFP6 |
380 |
292 |
204 |
162 |
138 |
NFP7 |
190 |
190 |
166 |
148 |
133 |
NFP8 |
192 |
191 |
169 |
148 |
133 |
NFP9 |
191 |
191 |
167 |
147 |
133 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.45: Predicted
Cumulative Hourly Average TSP Concentrations in
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
OCP1 |
201 |
204 |
182 |
157 |
133 |
OCP2 |
254 |
252 |
213 |
174 |
143 |
OCP3 |
403 |
317 |
221 |
167 |
139 |
OCP4 |
435 |
256 |
212 |
168 |
132 |
OCP6 |
174 |
178 |
164 |
147 |
129 |
OCP7 |
229 |
219 |
178 |
154 |
135 |
OCP8 |
361 |
231 |
187 |
159 |
132 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.46: Predicted
Cumulative Hourly Average TSP Concentrations in Wong Chuk Hang (Tier 1)
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
WCH1 |
438 |
370 |
228 |
170 |
142 |
WCH2 |
637 |
353 |
220 |
162 |
136 |
WCH3 |
738 |
373 |
227 |
169 |
146 |
WCH4 |
483 |
383 |
220 |
170 |
139 |
WCH5 |
574 |
373 |
216 |
163 |
137 |
WCH6 |
791 |
351 |
212 |
159 |
137 |
WCH7 |
- |
321 |
200 |
162 |
135 |
WCH8 |
435 |
327 |
227 |
162 |
139 |
WCH9 |
- |
332 |
222 |
160 |
138 |
WCH10 |
278 |
268 |
218 |
171 |
136 |
WCH11 |
352 |
270 |
219 |
172 |
137 |
WCH12 |
219 |
219 |
193 |
164 |
139 |
WCH13 |
263 |
250 |
200 |
162 |
135 |
WCH14 |
619 |
351 |
217 |
164 |
143 |
WCH16 |
- |
- |
229 |
169 |
145 |
WCH17 |
657 |
407 |
225 |
169 |
147 |
WCH18 |
655 |
374 |
211 |
161 |
140 |
WCH21 |
424 |
331 |
212 |
162 |
141 |
WCH22 |
245 |
241 |
202 |
163 |
131 |
Note: The
background
Bold:
The predicted value exceeds the 1-hour average TSP levels criterion, i.e. 500
μg/m3
Table 10.47: Predicted Cumulative Hourly Average TSP
Concentrations in Lei Tung (Tier 1)
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
LET1 |
276 |
200 |
161 |
142 |
127 |
LET2 |
254 |
193 |
158 |
146 |
133 |
LET3 |
237 |
205 |
168 |
145 |
129 |
LET4 |
315 |
259 |
180 |
147 |
130 |
LET5 |
386 |
181 |
146 |
137 |
127 |
LET6 |
178 |
138 |
133 |
126 |
119 |
LET7 |
171 |
139 |
131 |
124 |
117 |
LET8 |
268 |
167 |
155 |
141 |
127 |
LET9 |
219 |
171 |
158 |
143 |
129 |
LET10 |
240 |
140 |
135 |
128 |
121 |
LET11 |
193 |
143 |
137 |
130 |
122 |
LET12 |
135 |
138 |
130 |
123 |
116 |
LET13 |
160 |
146 |
132 |
126 |
119 |
LET14 |
181 |
138 |
133 |
126 |
119 |
LET15 |
393 |
173 |
162 |
149 |
135 |
LET19 |
301 |
230 |
147 |
137 |
126 |
LET20 |
190 |
174 |
131 |
124 |
117 |
LET21 |
213 |
193 |
164 |
142 |
126 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.48: Predicted
Cumulative Hourly Average TSP Concentrations in South Horizons (Tier 1)
ASRs |
Cumulative
Hourly Average |
||||
1.5m
|
5m |
10m
|
15m
|
20m
|
|
SOH1 |
352 |
171 |
125 |
118 |
112 |
SOH2 |
396 |
172 |
121 |
116 |
110 |
SOH3 |
304 |
180 |
123 |
117 |
111 |
SOH4 |
405 |
172 |
124 |
119 |
113 |
SOH5 |
328 |
179 |
126 |
121 |
115 |
SOH6 |
239 |
152 |
127 |
122 |
117 |
SOH8 |
231 |
159 |
125 |
117 |
112 |
SOH9 |
284 |
185 |
134 |
120 |
113 |
SOH11 |
246 |
149 |
128 |
122 |
116 |
SOH13 |
178 |
154 |
130 |
123 |
116 |
SOH14 |
149 |
143 |
135 |
125 |
115 |
SOH15 |
144 |
140 |
134 |
127 |
119 |
SOH16 |
245 |
181 |
132 |
126 |
119 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.49: Predicted
Cumulative Hourly Average TSP Concentrations at
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
TGB1 |
100 |
98 |
89 |
85 |
85 |
TGB2 |
101 |
99 |
90 |
88 |
87 |
TGB3 |
118 |
112 |
95 |
85 |
84 |
TGB4 |
141 |
124 |
92 |
86 |
85 |
TGB5 |
309 |
162 |
106 |
88 |
87 |
TGB6 |
163 |
134 |
93 |
89 |
88 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.50: Predicted
Cumulative Hourly Average TSP Concentrations at
ASRs |
Cumulative
Hourly Average |
||||
1.5m
|
5m |
10m
|
15m
|
20m
|
|
LNB1 |
- |
145 |
109 |
106 |
102 |
LNB2 |
- |
131 |
111 |
108 |
104 |
LNB3 |
- |
131 |
119 |
114 |
110 |
LNB4 |
199 |
150 |
125 |
119 |
113 |
LNB5 |
188 |
152 |
125 |
117 |
111 |
LNB6 |
196 |
146 |
123 |
118 |
113 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
Table 10.51: Predicted
Cumulative Hourly Average TSP Concentrations at Chung Hom Shan Magazine Site
(Tier 1)
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
|
95 |
95 |
91 |
86 |
85 |
|
94 |
94 |
90 |
86 |
83 |
|
119 |
116 |
102 |
89 |
84 |
CHK5 |
116 |
113 |
101 |
89 |
83 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
The results showed that under Tier 1 screening, a number of sensitive receivers at Wong Chuk Hang could be subject to construction dust impacts. The sensitive receivers with non-compliance under Tier 1 screening were selected to undergo Tier 2 testing. Although the contour plot in Figure 10.22 for the Admiralty works area showed exceedance of cumulative hourly average TSP levels at 1.5 above ground level at ADM15, 16 and 17 and area to the east of ADM16 when compared with the AQO criteria, as the use of these ASRs and other ASRs if any in the area to the east of ADM16 are mainly hotels, office, G/IC or commercial which are dependent on central air conditioning and their fresh air intakes are located at specific height above 5m, adverse impacts to these ASRs were therefore not anticipated.
Construction works in Wong Chuk Hang are divided into several phasing and zones as indicated in Figure 10.8. According to the construction programme, the construction works would be carried out simultaneously at each zone. The locations of the 30% of active area nearest to the ASRs with non-compliance under Tier 1 screening for each zone which represents the worst case scenario are shown in Figures 10.17 to 10.21.
The assessment results of Tier 2 are summarized in the Tables 10.52.Tier 2 Contours of cumulative hourly
Table 10.52: Predicted
Cumulative Hourly Average TSP Concentrations in Wong Chuk Hang at 30% active
area nearest to selective ASR (Tier 2)
ASRs |
Cumulative Hourly Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
WCH2 |
444 |
236 |
127 |
111 |
100 |
WCH3 |
467 |
234 |
151 |
115 |
104 |
WCH5 |
293 |
219 |
146 |
116 |
100 |
WCH6 |
436 |
206 |
133 |
110 |
99 |
WCH14 |
406 |
210 |
139 |
111 |
99 |
WCH16 |
- |
- |
145 |
116 |
98 |
WCH17 |
391 |
219 |
144 |
113 |
102 |
WCH18 |
479 |
238 |
143 |
118 |
104 |
Note: The background
Bold: The predicted
value exceeds the 1-hour average
The results showed that under Tier 2 testing, the predicted cumulative hourly average TSP concentrations at all ASRs complied with the 1-hour Average TSP levels criterion even assuming a conservative scenario.
The predicted mitigated
daily average
Table 10.53: Predicted Cumulative Daily Average TSP
Concentrations in Admiralty (Tier 1)
ASRs |
Cumulative
Daily Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
|
- |
- |
- |
- |
94 |
|
118 |
107 |
102 |
97 |
93 |
|
99 |
99 |
97 |
94 |
91 |
|
103 |
104 |
100 |
96 |
92 |
|
- |
- |
- |
- |
94 |
|
- |
- |
- |
- |
94 |
|
- |
- |
- |
- |
103 |
|
- |
157 |
139 |
119 |
103 |
|
131 |
129 |
118 |
105 |
95 |
ADM13 |
- |
114 |
108 |
102 |
96 |
ADM14 |
- |
- |
- |
- |
98 |
ADM15 |
- |
- |
- |
- |
103 |
ADM16 |
- |
- |
156 |
118 |
103 |
ADM17 |
- |
- |
- |
- |
104 |
ADM18 |
- |
- |
- |
- |
92 |
ADM19 |
110 |
111 |
107 |
102 |
97 |
ADM20 |
97 |
98 |
96 |
93 |
90 |
ADM21 |
- |
- |
- |
- |
90 |
Note: The background
Bold: The predicted
value exceeds the 24-hour Average TSP levels criterion, i.e. 260 μg/m3
Table 10.54: Predicted
Cumulative Daily
Average TSP
Concentrations in
ASRs |
Cumulative Daily Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
NFP1 |
100 |
94 |
87 |
84 |
82 |
NFP2 |
90 |
90 |
87 |
85 |
82 |
NFP3 |
92 |
92 |
89 |
86 |
83 |
NFP4 |
95 |
94 |
89 |
86 |
83 |
NFP5 |
119 |
100 |
92 |
86 |
83 |
NFP6 |
135 |
114 |
97 |
89 |
85 |
NFP7 |
91 |
90 |
87 |
85 |
83 |
NFP8 |
94 |
93 |
88 |
85 |
82 |
NFP9 |
92 |
91 |
88 |
85 |
83 |
Note: The background
Bold: The predicted
value exceeds the 24-Hour Average TSP levels criterion, i.e. 260 μg/m3
Table 10.55: Predicted
Cumulative Daily
Average TSP
Concentrations in
ASRs |
Cumulative Daily Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
OCP1 |
95 |
94 |
91 |
87 |
84 |
OCP2 |
114 |
105 |
95 |
90 |
86 |
OCP3 |
145 |
120 |
103 |
94 |
87 |
OCP4 |
141 |
110 |
101 |
94 |
87 |
OCP6 |
92 |
91 |
87 |
85 |
83 |
OCP7 |
107 |
98 |
91 |
87 |
84 |
OCP8 |
121 |
102 |
96 |
91 |
86 |
Note: The background
Bold: The predicted
value exceeds the 24-Hour Average TSP levels criterion, i.e. 260 μg/m3
Table 10.56: Predicted
Cumulative Daily
Average TSP
Concentrations in Wong Chuk Hang (Tier
1)
ASRs |
Cumulative Daily Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
WCH1 |
146 |
135 |
110 |
94 |
86 |
WCH2 |
199 |
151 |
110 |
95 |
88 |
WCH3 |
271 |
173 |
114 |
95 |
88 |
WCH4 |
160 |
140 |
113 |
96 |
89 |
WCH5 |
180 |
142 |
109 |
95 |
90 |
WCH6 |
275 |
169 |
109 |
96 |
89 |
WCH7 |
- |
138 |
109 |
95 |
88 |
WCH8 |
163 |
121 |
105 |
94 |
88 |
WCH9 |
- |
117 |
103 |
94 |
89 |
WCH10 |
108 |
103 |
97 |
91 |
86 |
WCH11 |
136 |
107 |
98 |
92 |
87 |
WCH12 |
96 |
96 |
92 |
89 |
85 |
WCH13 |
112 |
105 |
96 |
90 |
86 |
WCH14 |
218 |
156 |
109 |
94 |
87 |
WCH16 |
- |
- |
113 |
94 |
87 |
WCH17 |
195 |
150 |
108 |
94 |
87 |
WVH18 |
249 |
169 |
112 |
97 |
90 |
WCH21 |
146 |
123 |
105 |
96 |
89 |
WCH22 |
107 |
99 |
93 |
88 |
86 |
Note: The background
Bold: The predicted
value exceeds the 24-Hour Average TSP levels criterion, i.e. 260 μg/m3
Table 10.57: Predicted Cumulative Daily Average TSP
Concentrations in Lei Tung (Tier 1)
ASRs |
Cumulative
Daily Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
LET1 |
135 |
96 |
85 |
82 |
80 |
LET2 |
111 |
92 |
83 |
80 |
78 |
LET3 |
106 |
95 |
86 |
82 |
79 |
LET4 |
105 |
95 |
85 |
81 |
79 |
LET5 |
113 |
96 |
83 |
79 |
78 |
LET6 |
93 |
82 |
80 |
79 |
78 |
LET7 |
84 |
81 |
80 |
79 |
78 |
LET8 |
118 |
86 |
83 |
81 |
79 |
LET9 |
119 |
86 |
82 |
81 |
79 |
LET10 |
112 |
86 |
80 |
79 |
78 |
LET11 |
101 |
82 |
80 |
79 |
78 |
LET12 |
80 |
80 |
79 |
79 |
78 |
LET13 |
86 |
82 |
81 |
79 |
78 |
LET14 |
86 |
82 |
80 |
79 |
78 |
LET15 |
140 |
98 |
83 |
80 |
78 |
LET19 |
92 |
87 |
82 |
80 |
78 |
LET20 |
82 |
82 |
80 |
79 |
78 |
LET21 |
108 |
94 |
86 |
82 |
80 |
Note: The background
Bold: The predicted
value exceeds the 24-Hour Average TSP levels criterion, i.e. 260 μg/m3
Table 10.58: Predicted Cumulative Daily Average TSP Concentrations in South Horizons (Tier 1)
ASRs |
Cumulative Daily Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
SOH1 |
155 |
101 |
84 |
79 |
77 |
SOH2 |
165 |
100 |
84 |
79 |
77 |
SOH3 |
129 |
103 |
86 |
80 |
78 |
SOH4 |
154 |
98 |
85 |
80 |
78 |
SOH5 |
131 |
96 |
84 |
81 |
78 |
SOH6 |
104 |
88 |
81 |
79 |
78 |
SOH8 |
100 |
90 |
83 |
80 |
78 |
SOH9 |
118 |
97 |
84 |
80 |
78 |
SOH11 |
111 |
89 |
81 |
79 |
78 |
SOH13 |
89 |
85 |
80 |
79 |
78 |
SOH14 |
86 |
84 |
81 |
79 |
79 |
SOH15 |
83 |
82 |
81 |
79 |
78 |
SOH16 |
99 |
91 |
81 |
78 |
77 |
Note: The background
Bold: The predicted
value exceeds the 24-Hour Average TSP levels criterion, i.e. 260 μg/m3
Table 10.59: Predicted
Cumulative Daily
Average TSP
Concentrations at
ASRs |
Cumulative Daily Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
TGB1 |
79 |
79 |
77 |
76 |
75 |
TGB2 |
77 |
77 |
76 |
75 |
75 |
TGB3 |
78 |
78 |
76 |
75 |
75 |
TGB4 |
81 |
80 |
77 |
75 |
75 |
TGB5 |
108 |
92 |
79 |
77 |
75 |
TGB6 |
82 |
80 |
77 |
75 |
75 |
Note: The background
Bold: The predicted
value exceeds the 24-Hour Average TSP levels criterion, i.e. 260 μg/m3
Table 10.60: Predicted
Cumulative Daily
Average TSP
Concentrations at
ASRs |
Cumulative Daily Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
LNB1 |
- |
87 |
77 |
76 |
76 |
LNB2 |
- |
88 |
78 |
77 |
76 |
LNB3 |
- |
83 |
79 |
78 |
77 |
LNB4 |
94 |
87 |
80 |
78 |
77 |
LNB5 |
88 |
85 |
81 |
79 |
78 |
LNB6 |
99 |
91 |
82 |
78 |
77 |
Note: The background
Bold: The predicted
value exceeds the 24-Hour Average TSP levels criterion, i.e. 260 μg/m3
Table 10.61: Predicted
Cumulative Daily
Average TSP
Concentrations at Chung Hom Shan Magazine Site (Tier 1)
ASRs |
Cumulative Daily Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
|
76 |
76 |
76 |
75 |
75 |
|
75 |
75 |
75 |
74 |
74 |
|
76 |
76 |
75 |
75 |
74 |
CHK5 |
78 |
77 |
76 |
75 |
74 |
Note: The background
Bold: The predicted
value exceeds the 24-Hour Average TSP levels criterion, i.e. 260 μg/m3
The results showed that under Tier 1 screening, a two sensitive receivers at Wong Chuk Hang could be subject to construction dust impacts. The sensitive receivers with non-compliance under Tier 1 screening were selected to undergo Tier 2 testing. Although the contour plot in Figure 10.34 for the Admiralty works area showed exceedance of cumulative daily average TSP levels at 1.5 above ground level at ADM 16 and area to the east of ADM16 when compared with the AQO criteria, as the use of this ASR and other ASRs if any in the area to the east of ADM16 are mainly hotels, office, G/IC or commercial which are dependent on central air conditioning and their fresh air intakes are located at specific height above 5m, adverse impacts to these ASRs were therefore not anticipated.
Construction works in Wong Chuk Hang are divided into several phasing and zones as indicated in Figure 10.8. According to the construction programme, the construction works would be carried out simultaneously at each zone. The locations of the 30% of active area nearest to the ASRs with non-compliance under Tier 1 screening for each zone which represents the worst case scenario are shown in Figures 10.17 to 10.21.
The assessment results of Tier 2 are summarized in the Table 10.62. Tier 2 contours of cumulative daily
Table 10.62: Predicted
Cumulative Daily Average TSP Concentrations in Wong Chuk Hang at 30% active
area nearest to selective ASR (Tier 2)
ASRs |
Cumulative Daily Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
WCH3 |
181 |
126 |
91 |
83 |
79 |
WCH6 |
141 |
106 |
87 |
81 |
78 |
Note: The background
Bold: The predicted
value exceeds the 24-hour average
The results showed that under Tier 2 testing, the predicted cumulative daily average TSP concentrations at all ASRs complied with the 24-hour Average TSP levels criterion even assuming a conservative scenario.
The predicted mitigated
annual average
Table
10.63:
Predicted Cumulative Annual Average TSP Concentrations in Admiralty (Mitigated)
ASRs |
Cumulative Annual Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
|
- |
- |
- |
- |
78 |
|
78 |
78 |
78 |
78 |
78 |
|
78 |
78 |
78 |
78 |
78 |
|
78 |
78 |
78 |
78 |
78 |
|
- |
- |
- |
- |
78 |
|
- |
- |
- |
- |
78 |
|
- |
- |
- |
- |
78 |
|
- |
79 |
79 |
78 |
78 |
|
79 |
79 |
79 |
78 |
78 |
ADM13 |
- |
78 |
78 |
78 |
78 |
ADM14 |
- |
- |
- |
- |
78 |
ADM15 |
- |
- |
- |
- |
78 |
ADM16 |
- |
- |
79 |
79 |
78 |
ADM17 |
- |
- |
- |
- |
78 |
ADM18 |
- |
- |
- |
- |
78 |
ADM19 |
78 |
78 |
78 |
78 |
78 |
ADM20 |
78 |
78 |
78 |
78 |
78 |
ADM21 |
- |
- |
- |
- |
78 |
Note: The background
Bold: The predicted
value exceeds the annual average
Table 10.64: Predicted
Cumulative Annual Average TSP Concentrations in
ASRs |
Cumulative
Annual Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
NFP1 |
74 |
73 |
73 |
73 |
73 |
NFP2 |
74 |
74 |
74 |
73 |
73 |
NFP3 |
74 |
74 |
73 |
73 |
73 |
NFP4 |
74 |
74 |
73 |
73 |
73 |
NFP5 |
74 |
74 |
73 |
73 |
73 |
NFP6 |
76 |
74 |
73 |
73 |
73 |
NFP7 |
74 |
74 |
73 |
73 |
73 |
NFP8 |
73 |
73 |
73 |
73 |
73 |
NFP9 |
74 |
74 |
73 |
73 |
73 |
Note: The background
Bold: The predicted
value exceeds the annual average
Table 10.65: Predicted
Cumulative Annual Average TSP Concentrations in
ASRs |
Cumulative Annual Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
OCP1 |
74 |
74 |
74 |
73 |
73 |
OCP2 |
74 |
74 |
74 |
73 |
73 |
OCP3 |
74 |
74 |
74 |
73 |
73 |
OCP4 |
75 |
74 |
74 |
73 |
73 |
OCP6 |
74 |
74 |
73 |
73 |
73 |
OCP7 |
74 |
74 |
73 |
73 |
73 |
OCP8 |
74 |
74 |
73 |
73 |
73 |
Note: The background
Bold: The predicted
value exceeds the annual average
Table 10.66: Predicted
Cumulative Annual Average TSP Concentrations Wong Chuk Hang (Mitigated)
ASRs |
Cumulative
Annual Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
WCH1 |
74 |
74 |
74 |
73 |
73 |
WCH2 |
74 |
74 |
74 |
73 |
73 |
WCH3 |
76 |
75 |
74 |
74 |
73 |
WCH4 |
75 |
75 |
74 |
74 |
74 |
WCH5 |
76 |
75 |
74 |
74 |
74 |
WCH6 |
76 |
75 |
74 |
74 |
73 |
WCH7 |
- |
75 |
74 |
74 |
74 |
WCH8 |
75 |
74 |
74 |
74 |
74 |
WCH9 |
- |
74 |
74 |
74 |
74 |
WCH10 |
74 |
74 |
74 |
74 |
73 |
WCH11 |
74 |
74 |
74 |
73 |
73 |
WCH12 |
74 |
74 |
74 |
73 |
73 |
WCH13 |
74 |
74 |
74 |
73 |
73 |
WCH14 |
75 |
74 |
74 |
73 |
73 |
WCH16 |
- |
- |
74 |
73 |
73 |
WCH17 |
76 |
75 |
74 |
74 |
73 |
WCH18 |
78 |
76 |
74 |
74 |
74 |
WCH21 |
75 |
74 |
74 |
74 |
74 |
WCH22 |
74 |
74 |
74 |
74 |
73 |
Note: The background
Bold: The predicted
value exceeds the annual average
Table 10.67: Predicted Cumulative Annual Average TSP
Concentrations in Lei Tung (Mitigated)
ASRs |
Cumulative Annual Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
LET1 |
74 |
74 |
73 |
73 |
73 |
LET2 |
74 |
74 |
73 |
73 |
73 |
LET3 |
74 |
74 |
73 |
73 |
73 |
LET4 |
74 |
74 |
73 |
73 |
73 |
LET5 |
74 |
73 |
73 |
73 |
73 |
LET6 |
73 |
73 |
73 |
73 |
73 |
LET7 |
73 |
73 |
73 |
73 |
73 |
LET8 |
74 |
73 |
73 |
73 |
73 |
LET9 |
74 |
73 |
73 |
73 |
73 |
LET10 |
74 |
73 |
73 |
73 |
73 |
LET11 |
74 |
73 |
73 |
73 |
73 |
LET12 |
73 |
73 |
73 |
73 |
73 |
LET13 |
74 |
73 |
73 |
73 |
73 |
LET14 |
73 |
73 |
73 |
73 |
73 |
LET15 |
74 |
74 |
73 |
73 |
73 |
LET19 |
73 |
73 |
73 |
73 |
73 |
LET20 |
73 |
73 |
73 |
73 |
73 |
LET21 |
74 |
74 |
73 |
73 |
73 |
Note: The background
Bold: The predicted
value exceeds the annual average
Table 10.68: Predicted Cumulative Annual Average TSP
Concentrations in South Horizons (Mitigated)
ASRs |
Cumulative
Annual Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
SOH1 |
75 |
74 |
74 |
73 |
73 |
SOH2 |
75 |
74 |
74 |
73 |
73 |
SOH3 |
75 |
74 |
74 |
73 |
73 |
SOH4 |
74 |
74 |
74 |
73 |
73 |
SOH5 |
74 |
74 |
74 |
73 |
73 |
SOH6 |
74 |
74 |
73 |
73 |
73 |
SOH8 |
74 |
74 |
73 |
73 |
73 |
SOH9 |
74 |
73 |
73 |
73 |
73 |
SOH11 |
74 |
74 |
74 |
73 |
73 |
SOH13 |
74 |
74 |
74 |
73 |
73 |
SOH14 |
74 |
74 |
73 |
73 |
73 |
SOH15 |
73 |
74 |
73 |
73 |
73 |
SOH16 |
74 |
73 |
73 |
73 |
73 |
Note: The background
Bold: The predicted
value exceeds the annual average
Table 10.69: Predicted Cumulative Annual
Average TSP Concentrations at
ASRs |
Cumulative Annual Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
TGB1 |
74 |
74 |
73 |
73 |
73 |
TGB2 |
73 |
73 |
73 |
73 |
73 |
TGB3 |
73 |
73 |
73 |
73 |
73 |
TGB4 |
74 |
74 |
73 |
73 |
73 |
TGB5 |
74 |
74 |
74 |
73 |
73 |
TGB6 |
74 |
74 |
73 |
73 |
73 |
Note: The background
Bold: The predicted
value exceeds the annual average
Table 10.70: Predicted Cumulative Annual
Average TSP Concentrations at
ASRs |
Cumulative Annual Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
LNB1 |
- |
75 |
74 |
73 |
73 |
LNB2 |
- |
75 |
73 |
73 |
73 |
LNB3 |
- |
74 |
74 |
73 |
73 |
LNB4 |
74 |
74 |
74 |
73 |
73 |
LNB5 |
74 |
74 |
74 |
74 |
73 |
LNB6 |
75 |
74 |
74 |
73 |
73 |
Note: The background
Bold: The predicted
value exceeds the annual average
Table 10.71: Predicted Cumulative Annual Average TSP
Concentrations at Chung Hom Shan Magazine Site (Mitigated)
ASRs |
Cumulative Annual Average |
||||
1.5m |
5m |
10m |
15m |
20m |
|
CHK1 |
73 |
73 |
73 |
73 |
73 |
|
73 |
73 |
73 |
73 |
73 |
|
73 |
73 |
73 |
73 |
73 |
CHK5 |
73 |
73 |
73 |
73 |
73 |
Note: The background
Bold: The predicted
value exceeds the annual average
With the implementation of the mitigation measures, the results in Table 10.63 and Table 10.71 indicated that there is no TSP exceedance at all assessment levels for all identified ASRs. As such, no adverse dust impact was predicted at all the ASRs. The contour plot in Figure 10.46 for the Admiralty works area and Figure 10.50 for the South Horizons and Lee Nam Road Barging Point works area showed exceedance of cumulative annual average TSP levels at 1.5 above ground level at ADM 16 and area to the east of ADM16 and LNB 1 respectively when compared with the AQO criteria.
For Admiralty, however, as the use of this ASR and other ASRs if any in the area to the east of ADM16 are mainly hotels, office, G/IC or commercial which are dependent on central air conditioning and their fresh air intakes are located at specific height above 5m, adverse impacts to these ASRs were therefore not anticipated.
For Lee Nam Road Barging Point, however, as the use of this ASR is an industrial building in which sensitive use are located at a height of above 5m, adverse impact to this ASR is therefore not anticipated.
10.3
Evaluation of Residual Impact
With the implementation of the appropriate mitigation measures and good site practice as stipulated in the Air Pollution Control
(Construction Dust) Regulation, the predicted cumulative 1-hour, 24-hour and
annual average
10.4 Environmental Monitoring and Audit
The predicted TSP levels at all works sites compiled with the hourly, daily and annual average TSP criteria with the implementation of dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation. Dust monitoring is considered necessary during the construction phase and regular site audits are required to ensure that the dust control measures are properly implemented.
During construction, it is anticipated that the construction activities should be controlled in accordance with appropriate mitigation measures stipulated under the Air Pollution Control (Construction Dust) Regulations. With the proper implementation of dust suppression measures, adverse dust impacts would not be anticipated.