2.             Project Description

Purpose and Objective of the Project

2.1          A key aspect of the construction of Shatin to Central Link - Hung Hom to Admiralty Section (hereafter known as SCL (HUH-ADM)) inside the CBTS will be the coordination of the interfaces with the CWB project.  The CWB will be constructed in cut-and-cover tunnel from temporary reclamation in the CBTS.  Construction of the CWB will tentatively start in the third quarter of 2010 and will overlap with the target construction period of the SCL.  There is a need to address how the SCL can be integrated with the proposed CWB project to minimize the extent and duration of reclamation for both projects in the CBTS.

2.2          The purpose of the SCL Protection Works and associated works (which is the Project being considered in this EIA Report) is to temporarily reclaim land for construction of a section of tunnel box for SCL by cut-and-cover method at the crossing above the CWB tunnels within the CBTS. The Protection Works is limited to civil and structural elements and cannot serve to function for any railway service or operation. The prime objectives of the Project are:

·               To avoid repeated temporary reclamation and minimize the extent and duration of reclamation in the CBTS by constructing the SCL Protection Works together with the main CWB works that is undertaken by Highway Department.

·               To ensure future construction of the SCL on both sides of the CWB tunnels is protected and ensure its feasibility without damaging or unduly affecting the CWB tunnels which could be operational by then.

 

Brief Description of the Project

2.3          The Project involves the construction of a section of the twin track railway tunnel box (the SCL Protection Works) by cut-and-cover method at the crossing above the CWB tunnels. The length of the SCL Protection Works is approximately 160m long and it is located entirely offshore within the CBTS. Upon implementation of the SCL in the future, the south end of the Protection Works will be extended from the temporary reclamation to connect with the South Ventilation Building (SOV) at the existing Police Officers’ Club and the north end of the Protection Works will be continued in cut and cover construction to connect to an Immersed Tube Tunnel (IMT) beneath the harbour.

2.4          Temporary reclamation is required for the construction of the Protection Works and will be authorized under the Foreshore and Sea-bed (reclamations) Ordinance. The temporary reclamation will be removed once the Protection Works is completed except a small area at the southwest corner of the reclamation which will be retained to enable construction of the future SCL tunnels connecting to the proposed SOV (the Police Officer Club site). This section of the temporary reclamation will be removed by the SCL project.

2.5          Due to the temporary reclamation for the SCL Protection Works, vessels in the southwest corner will be affected. Hence, the southeast corner of the CBTS will need to be dredged to provide sufficient water depth to allow the relocation of moorings. The temporary reclamation for the Protection Works will also require relocation of the temporary RHKYC jetty within the CWB temporary reclamation to a new location.

2.6          Location, boundary and general layout of the Project are illustrated in Figure Nos. NEX2213/C/331/ENS/M50/501 to NEX2213/C/331/ENS/M50/503.

 

Project Scope

2.7          The Project comprises the following key elements:

·               Temporary reclamation, which occupies about 0.7ha of Government foreshore and sea-bed (of which 0.3ha is already authorized under CWB project, i.e. additional reclamation of 0.4ha is required).

 

·               Dredging works at the southeast corner of the CBTS to provide space for temporary relocation of anchorage area due to the additional temporary reclamation for the Project.

 

·               Construction of a section of the twin track railway tunnel structure (approximately 160m long) above the proposed CWB located entirely offshore within the CBTS.

 

·               Relocation of the temporary RHKYC jetty within the CWB temporary reclamation to a new location.

 

·               Removal of the temporary reclamation, except the small area at the southwest corner of the reclamation (which will be removed by the SCL project upon completion of the future SCL tunnels connecting to the proposed SOV). 

 

2.8          All of the above construction works, including the dredging work at the southwest corner of the temporary reclamation area, would be entrusted to the CWB project and hence carried out by the CWB Contractor. The only exception is the removal of temporary reclamation at the southwest corner, which would be performed under the SCL (HUH-ADM) when the future SCL tunnel is connected to the shoreline at the proposed SOV. 

 

Need for the Project

Benefits of the Project

2.9          Since the Project will interface with CWB project at the CBTS, there is a need to address how the two projects can be integrated, not only to optimize the use of temporary reclamation provided by CWB but also to minimize the impacts on the users of the CBTS. Based on feedback from consultation with stakeholders and users of the CBTS, they opined that there should be a better coordination with the CWB project to minimize disturbance to the moorings and operations of the typhoon shelter and expedite the works to avoid prolongation of the impacts.

2.10        The Project is a win-win option to both SCL and CWB projects in terms of project costs and risks during construction. It allows optimum usage of the temporary reclamation provided by CWB for the construction of SCL, so that future temporary reclamation due to SCL works in the interfacing region can be avoided. On one hand it reduces the extent of temporary reclamation area required for future SCL works which in turn facilitates the allocation of resources, on the other hand it as well shortens the duration of temporary reclamation within the CBTS and hence the impacts on the users of CBTS. Despite that temporary reclamation additional to that proposed in the CWB project is required, it would be significantly reduced in terms of size and duration in comparison to that which would be required if the Protection Works is undertaken after completion of the CWB.

2.11        As CWB would be operational during the construction of the SCL, the Project will allow the future construction of the SCL on both sides of the CWB tunnels without damaging or unduly affecting the CWB tunnel. The risks of both SCL construction and CWB tunnel operation are therefore minimized.

2.12        In environmental terms, the following potential benefits would likely be achieved with the implementation of the Project:

·               Repeated dredging could be avoided at the interfacing area of the two tunnels when future SCL tunnel works are constructed by cut-and-cover method. The seabed in the interfacing region would not be disturbed once again, and additional release of suspended solids (SS) and sediment-bound contaminants such as heavy metals and nutrients, if present, into the water column, can be avoided. The overall water quality impact in the CBTS due to dredging is thus minimized in absolute terms.

 

·               In a similar fashion, repeated temporary reclamation following the dredging operation could be made unnecessary in the interfacing area. Duration of temporary embayment due to the partially reclaimed land for SCL tunnel works in the southwest part of the CBTS would be shortened and hence potential accumulation of pollutants from contaminated stormwater runoff can be minimized. Moreover, loss of fill materials into the water column due to filling activities for the temporary reclamation can also be limited as a result of the minimized extent of temporary reclamation.

 

·               Besides, the amount of waste including Construction and Demolition (C&D) materials would be reduced, which would otherwise be increased due to the repetition of dredging and temporary reclamation at the interfacing area.

Without Project Scenario (Not constructed under the CWB project)

2.13        If the SCL Protection Works is not proceeded, temporary reclamation will be required in future construction of SCL at the interfacing area of the two projects. The construction may risk the operation of the CWB tunnel as the closest distance between the crown of the CWB tunnel and the SCL tunnels is merely around 3m. From the perspective of cost-effectiveness, both the higher construction risks and larger temporary reclamation area will result in a bigger project cost compared to the scenario which the Protection Works is constructed under the CWB project,

2.14        While the temporary reclamation will be carried out after the completion of CWB project, the size and duration of the temporary reclamation in the CBTS will be significantly more than that of having the Protection Works constructed under the CWB project, leading to a prolongation of impacts to the users of CBTS, disturbance to the moorings and operations of the typhoon shelter.

 

Consideration of Alternatives/Options 

Introduction

2.15        The engineering design, location and scale of the Project are governed by the alignment scheme of the SCL (HUH-ADM). Different alignment options and construction methods of the SCL (HUH-ADM) would have direct implication on the design of the Project in various aspects, including the location and size of works area, extent of dredging and temporary reclamation, works sequence and phase implementation and even the necessity of the Project. It is essential to apprehend different alternative options of the SCL (HUH-ADM) and to acknowledge the preferred scheme of the alignment which fundamentally defines the scope and need of the Project. 

Compliance with the Protection of The Harbour Ordinance (PHO) 

2.16        The PHO Cap 531 recognises the harbour as a special public asset and a natural heritage of Hong Kong to be protected and preserved. Judicial reviews on other projects have further clarified the legal principles behind the PHO and have established a presumption against reclamation within Victoria Harbour, irrespective if the reclamation is permanent or temporary.

2.17        The presumption against reclamation can only be rebutted by establishing an overriding public need for the reclamation work. Guidance for addressing the public need for reclamation (referred to as “the overriding public need test”) is provided in the Housing, Planning and Lands Bureau Technical Circular No. 1/04 (HPLB TC 1/04). This applies to all reclamations within the boundaries of Victoria Harbour and cogent and convincing materials are required to support and justify the overriding public need for reclamation.

2.18        The HPLB TC No. 1/04 states that a “no reclamation” scenario must be taken as the starting point in considering alternatives and that it is imperative to examine if an overriding public need can be met without reclamation through a reasonable alternative. It further states that all circumstances should be considered in determining whether there is a reasonable alternative to reclamation, including the economic, social and environmental implications, cost and time incurred, and other relevant considerations, including technical feasibility and safety considerations.

2.19        A detailed examination of the SCL needs and constraints, including an exhaustive investigation into the need for reclamation for the SCL (HUH-ADM) construction and of alternative schemes that might do away with reclamation or, at least, minimise reclamation, has been carried out. A “Cogent and Convincing Materials to Demonstrate Compliance with the Overriding Public Need Test” (CCM Report for SCL), which set out the findings of the investigations and the conclusions regarding the need for reclamation and the minimum extent of reclamation has been prepared. The CCM Report can be viewed at the website: http://www.mtr-shatincentrallink.hk/en/construction/work-in-victoria-harbour.html.

2.20        As detailed in the CCM Report, the three tests in rebutting the presumption against the reclamation as set out in the PHO have been satisfied:

·                     In facilitating the construction of the SCL and therefore in meeting the overriding public need for the railway, there is consequently a compelling and present need for the reclamation in the CBTS and adjacent to Hung Hom landfalls. All of the reclamation is essentially temporary and will be removed upon completion of construction, with the seabed reinstated to the original level.

·                     No reasonable alternative to temporary reclamation is found for constructing the SCL (HUH-ADM) (known as SCL Cross Harbour Section in the CCM Report).

·                     The extent of reclamation has been determined to be the minimum required.

 

SCL (HUH-ADM) Alignment Options

2.21        In general, two broad groups of engineering design have been considered for the SCL (HUH-ADM), namely the “No Reclamation Options” and “Alternative Options Requiring Reclamation” and are described in the sections below. Details of the options are described in the CCM Report.

Alternatives of SCL (HUH-ADM) - “No Reclamation” Options

2.22        Three “no-reclamation” options have been investigated as a part of the engineering design of the SCL (HUH-ADM), however each of these options are considered to be either not viable or not a reasonable alternative to reclamation. These options include:

·                     Bridge Option;

·                     Shallow Bored Tunnel Options; and

·                     Deep Tunnel Option.

Bridge Option

2.23        The Bridge Option would have huge impacts on existing infrastructure and buildings on both sides of the harbour as well as significant visual impact. The problems arise from the need to provide sufficient navigation clearance under the bridge deck and the limiting 3% gradient for the railway. The approach ramps on other side of the harbour would have to be 1km long for every 30m of clearance.

2.24        On the Kowloon side the approach ramps would impact on the East Rail Line, existing roads and other infrastructure. The Coliseum would require being demolished and the resulting HUH Station would provide for an unacceptable interchange due to significant level differences between the east-west and north-south corridors.

2.25        On the Hong Kong side the approach ramp would have to extend a significant distance along the north shore on Hong Kong Island, including sections at grade and in trough and would fail to provide acceptable interchange stations at Exhibition and Admiralty because of the significant level differences involved. This option is therefore not considered to be viable.

Shallow Bored Tunnel Options

2.26        The Shallow Bored Tunnel Options would have to be constructed by Tunnel Boring Machine (TBM) in view of the anticipated ground conditions along the alignment corridor (Figure 2.1 of Appendix 2.1). The alignment of these options is driven by the need to pass under the CWB tunnels with adequate clearance to avoid damaging the CWB tunnels during SCL tunnel construction and also to maintain adequate cover under the seabed, particularly below a large depression in the seabed near the HUH seawall in order to allow the TBM to operate.

2.27        In order to adopt the Shallow TBM Tunnel Option, sufficient ground cover is required over the TBM to enable ground control and steering so as to meet safety requirements. The absolute minimum ground cover above the tunnel is generally one TBM diameter and preferably two diameters. It is expected for an internal diameter of 9m would be required for a single track SCL tunnel with ventilation duct. The external diameter of the TBM would be about 10.35m. Accordingly, to allow for sufficient ground cover, the tunnel would require an absolute minimum depth below seabed of 10.35m and preferably more than 20m clearance from the top of the tunnel to the seabed.

2.28        Due to these constraints, this option would involve twin bored TBM tunnel which would require an invert level of approximately -50 mPD, at the lowest point under the CWB tunnel, and a general depth below -44 mPD within the remaining areas of the Harbour. At these levels the tunnel would pass in and out of rockhead several times and significantly increase both the likelihood of corestones being encountered and the general engineering difficulty of the alignment.

2.29        The particularly onerous tunnelling conditions demand the TBM to be capable of operating in mixed face conditions at deep tunnel depths. Based on previous experience, and in view of the expected high cutter wear and risk of damage to the cutterhead, daily interventions would be required at the tunnel face for inspection, maintenance and repair. These works would require workers to enter the pressurised cutterhead via air locks in the pressure bulkhead of the TBM, and would be undertaken in a small and confined space at deep tunnel depths under the harbour at pressures exceeding 50 pounds per square inch (psi) (approximately 3.45 bar) (Figure 2.2 of Appendix 2.1).

2.30        In Hong Kong any works using compressed air is regulated by the Factories and Industrial Undertakings Ordinance (Cap. 59) (F&IUO), which provides for the safety and health protection to workers in the industrial sector. According to the current regulations “no person shall be employed in compressed air at a pressure exceeding 50 psi without permission from the Commissioner, except in the case of an emergency.”

2.31        This option therefore associates with high engineering difficulties in relation to the requirements on the ground cover and stability of the tunnel face, as well as the significant risks to health and regulatory requirements associated with working under high pressures. Moreover, this option also bears very high cost and can only provide a considerably poorer interchange arrangement to rail users due to large vertical separation between the east-west and north-south corridor platforms, which in return lengthens the interchange times. Therefore the Shallow TBM Tunnel Option is not considered to be a viable alternative option.

Deep Tunnel Options

2.32        There are a number of constraints associated with the Deep TBM Tunnel Option. One is the proximity of the alignment to the Hong Kong Coliseum (HKC) foundations.  The SCL tunnels must be constructed through or below the limited space between the existing HKC foundations, significantly increasing construction difficulty. Ensuring that construction tolerances, therefore, become more critical.

2.33        An alignment under the HKC foundations but above the rockhead is preferred in order to avoid undermining the existing foundations and limit the volume of rock to be excavated.  However, the Deep TBM Tunnel Option is expected to have cost and programme implications and cause disruption to the community and environment in the area surrounding the HKC.

2.34        Figure 2.3 of Appendix 2.1 illustrates that the Deep TBM Tunnel Option also results in a deeper HUH such that the SCL cannot connect into the existing alignment south of Tunnel 1A (approximately 800 m north of HUH) given the limiting 3% rail gradient requirements. The rail level at HUH would be required to be lowered from the preferred level of -10 mPD to approximately -25mPD, requiring the installation of two escalators and an intermediate platform, which would increase interchange time by approximately 40 seconds.  The line would also have to be extended almost 2km to the north to join with the existing East Rail Line. This additional section of rail would require design and construction 2 km of tracks and other associated rail infrastructure, significantly increasing the environmental impacts, cost and engineering difficulty of the SCL.

2.35        The Deep TBM Tunnel Option also has similar engineering and safety difficulties relating to working at depth as the Shallow TBM Tunnel Option.  The requirement to undertake daily interventions at the tunnel face for inspection, maintenance and repair requiring man entry into the pressurised cutterhead via air locks would be required to be undertaken at pressures far exceeding 50psi.  This again would exceed the current regulated level and must be supported by argument that there is no reasonable, safer way to carry out the construction. Similar to the Shallow TBM Tunnel Option, compressed air is not considered to be practical for face interventions due to the limited working time available at the face at such high pressures and difficulties in using compressed air under F&IUO.

2.36        Given the constraints in relation to working under high pressures at depth, the engineering difficulties in working around the HKC foundations and the less favourable interchanges provided by the deeper HUH and EXH, the Deep TBM Option is deemed not able to meet the SCL project objectives.

2.37        To conclude, there is no acceptable “no-reclamation” option for the SCL (HUH-ADM). It must be accepted that some reclamation will be required to enable its construction.

Alternatives of SCL (HUH-ADM) - Options Requiring Reclamation

2.38        The Immersed Tube Tunnel (IMT) construction method has been adopted for all existing cross-harbour transport tunnels in Hong Kong, including the Eastern Harbour Crossing, Western Harbour Crossing and Central Harbour Crossing transport tunnels across Victoria Harbour. The construction process and technology for this method is well established with relatively little risk involved. Both local and overseas contractors have the skills to undertake this type of construction and the construction plant and materials are locally available.

2.39        The standard practice for IMT construction is to dredge a trench in the seabed to remove soft materials, provide a foundation base within the trench, float in precast tube tunnels in sections, sink the precast units into place within the seabed using a floating pontoon system or from a barge and finally connect and backfill the tunnel with a rock blanket or other suitable material to protect and anchor the tunnels. This approach would raise some sections of sea-bed but does not result in any dry surface or land formed. Nonetheless, the raising of the sea-bed level would not affect the use or access to that part of the harbour.

2.40        The maximum depth and portion of IMT extending above the seabed is generally dictated by marine clearance requirements. The top level of the IMT will be slightly above the Cross Harbour Tunnel located at the north of the CBTS but the slightly reduced water depth should have no impact to the marine users and it will not affect the main fairway.

2.41        An envelope covering various alignment options of the SCL (HUH-ADM) is shown on Figure 2.4 of Appendix 2.1. This is bounded by the existing Cross Harbour Tunnel on the west and the need to identify a suitable landfall on Hong Kong Island which is not constrained by existing buildings or infrastructure. The IMT must be kept as shallow as possible and, therefore, must pass above the CWB tunnels.

Eastern and Western Corridor Options

2.42        On the Hong Kong Island, the central alignment of corridor, the SCL tunnels would clash with CWB Slip Road No. 8, which extends above the main CWB Tunnel Box. Therefore, alignment options along the central part of the corridor on Hong Kong Island are not feasible.  Two alternative alignment corridors are therefore considered, namely an Eastern Corridor and a Western Corridor which both pass through the CBTS.

2.43        For both the Eastern and Western Alignment Corridors, the requirements at the Hung Hom landfall are common. At the Hung Hom landfall, the SCL tunnel would need to pass under the Hung Hom Bypass. During construction of the SCL tunnels, some of the fender piles for protecting the Hung Hom Bypass would need to be removed and reprovisioned in a slightly different form. The reprovisioned fender piles are considered to be permanent reclamation but are not considered to affect the use or enjoyment of the Harbour.

Eastern Corridor Options

2.44        The Eastern Corridor options are shown on Figures 2.5 to 2.8 of Appendix 2.1 and the key characteristics are summarised below:

·          Option 1A: Alignment runs under CWB tunnels along the same corridor as far as possible.

·          Option 1B: Alignment runs partly under the CWB tunnels and then to the south of the tension anchor zone at the Cross Harbour Tunnel and then parallel to and just to the south of the CWB tunnels.

·          Option 1C non-stacked: This is a similar alignment to Option 1B through the CBTS but then follows a non-stacked inland alignment to EXH to provide cross platform interchange. A similar alignment option to provide a cross platform at EXH was also considered but found to be unfeasible.                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                  

·          Option 1D: Shallow alignment above the CWB tunnels.

 

2.45        Options 1A to 1C would require construction of the SCL tunnels beneath the CWB tunnels within the CBTS. These works would have to be carried out under the CWB contract. Due to the extra depth of construction and complexity, completion of the CWB tunnels is expected to be delayed for 3 years, which hence prolongs the period of disruption in the CBTS.  Other problems associated with these options include increased construction risk, in particular to the construction of the combined CWB and SCL tunnels under the Cross Harbour Tunnel.

2.46        The assessment of Option 1D has shown that the currently proposed CWB tunnels would have to be lowered to avoid the SCL tunnels from either clashing with the CWB Slip Road No. 8 or protruding above the seabed at this location, and in the eastern part of CBTS as shown on Figure 2.8 of Appendix 2.1.  The Highways Department has advised that deeper CWB alignment would result in the CWB tunnel portal being moved further east towards North Point. This would increase the permanent reclamation in North Point from 3.3 hectares to approximately 10 hectares.

2.47        All options would require temporary reclamation of up to 2ha while Option 1B would also require additional permanent reclamation to allow the SCL to be constructed parallel to the CWB tunnels adjacent to the Wanchai East Screening Plant and Hong Kong Electric Sub-station.

2.48        The Eastern Alignment Options are therefore not favoured because of a combination of the need for permanent reclamation and the prolonged period of construction required in CBTS. In addition, the route length for the alignment within the Eastern Corridor would be extended resulting in greater construction impacts and longer journey times during operation.


Western Corridor Options

2.49        The horizontal alignment of the Western Corridor Options is shown on Figure 2.9 of Appendix 2.1. At the location where the SCL crosses the CWB, the SCL tunnels will pass over the CWB tunnels.

2.50        After passing through the Hung Hom landfall section, the alignment will run in a southerly direction towards the CBTS, to the east and generally parallel to the existing Cross Harbour Tunnel. South of the CBTS breakwater, the alignment will then run in a south westerly direction towards the Police Officers’ Club site where a ventilation building will be located.

2.51        The tunnel between the Hung Hom landfall and a point approximately 72m north of the breakwater will be constructed using the IMT method. South of the IMT section, the cut and cover construction method will be adopted. The cut-and-cover section requires temporary reclamation, with a total area of approximately 2.2ha, including the temporary reprovisioned jetty for the Royal Hong Kong Yacht Club.

2.52        The existing breakwater will be removed after the surround area has been temporarily reclaimed. The breakwater will be reinstated at the existing location and in a similar form after completion of the SCL tunnels below. The typhoon shelter will be protected at all times by the temporary seawalls and reclamation provided while the existing breakwater is removed for the SCL tunnel construction.

2.53        There are several challenges with constructing the cross-harbour SCL tunnel through the CBTS section, these include:

·          The need to reduce disturbance to the moorings and operations of the typhoon shelter as much as possible and ensuring the works are undertaken as quickly as possible to avoid prolongation of any impacts, particularly as this area will be affected by the CWB tunnel construction.

·          Ensuring the tunnels are placed at a sufficient depth to reduce the potential risk of damage from ship impact, anchors, etc. and are not exposed, whilst minimising the amount of materials to be dredged from within the typhoon shelter during construction, due to the expected high levels of contaminants in the sediment, and ensuring that contaminants are contained as best as possible when removed.

·          Interfacing with the CWB project construction at this area.

2.54        The above requirements contribute to the need for temporary reclamation to be undertaken for construction works. In particular, the most significant implication to the project is the interface requirements with CWB.

Other Alternative Considerations

2.55        Other alternative alignment options to the west of the Cross Harbour Tunnel and to the east of CBTS were studied but considered not preferable for the reasons given below.

Alternative Alignment to West of Cross Harbour Tunnel

2.56        These options would require the SCL tunnels to pass under the Cross Harbour Tunnel on the Kowloon side of the tunnel and run along Salisbury Road before crossing to the ex-Public Cargo Working Area in Wanchai. The SCL tunnels would pass under the CWB tunnels before entering EXH located adjacent to the CWB tunnels to the north of the Harbour Road Sports Centre.

2.57        There are a number of major challenges with this alignment which renders it unfeasible. These include conflicts with the Coliseum foundations, retaining structures or footings for the East Rail tunnels and the adjacent flyover. Mined tunnelling under the existing Cross Harbour Tunnel on Kowloon side would be particularly risky as the existing structure is sensitive to movements.

2.58        The tunnel across the harbour would be particularly deep (approximately 40m below sea level) as it would have to pass below the CWB tunnels. This would lead to excessive dredging and significant areas of temporary reclamation. EXH Station would have to be much deeper and a cross platform interchange could not be provided.

2.59        The risks associated with this alignment, the impacts of construction and less favourable EXH Station interchange mean that this option is unacceptable.

Alternative Alignment to East of CBTS

2.60        This alignment option will shift towards Eastern side of Hong Kong Island which terminate at North Point and Fortress Hill Stations. Due to the insufficient capacity at these existing stations, they would need to be totally reconstructed. Therefore, there would be space, cost and programme implications.

Conclusions of Options Reviewed

2.61        A number of “no-reclamation” options have been investigated and are considered to be not viable or not a reasonable alternative to reclamation. These options include: (i) Bridge Option; (ii) Shallow Bored Tunnel Option; and (iii) Deep Tunnel Option.

2.62        The Bridge Option would cause very significant adverse impacts on both sides of the Harbour. It is not possible to engineer a scheme which meets the SCL project objective. This option is therefore rejected. The Deep Tunnel Option is considered not viable because of the impractical interchanges created and the need for tunnelling at pressures greater than 50psi. The Shallow Bored Tunnel Option would require working in high pressures exceeding the statutory limit of 50psi. The MTR are not prepared to accept the risks to health, life and the project with this option when there is an acceptable alternative option available which avoids these risks. Also, the poor interchange arrangement would not meet the SCL Project objective.

2.63        For the “Options Requiring Reclamation”, the Immersed Tube and Cut-and-Cover Tunnel option has been adopted as the approach for the construction of tunnels, thanks to the well established technology and construction process for this method and the relatively little risk involved.

2.64        Based on the analysis of the alignment options for the IMT, it has been concluded that the IMT alignment should follow the Western Corridor option as it minimizes interfaces with CBTS and is the most direct railway alignment. The Eastern alignments have more significant impacts on reclamation durations and greater construction risks.

2.65        Permanent reclamation would not be required under the Western Corridor option by the IMT and cut-and-cover tunnel, as all permanent works would be below seabed or lowest astronomic tide level, other than the reprovisioned fender piles for the Hung Hom Bypass. However, temporary reclamation will be required to construct the cut-and-cover tunnel to connect with the IMT and inside the CBTS.

2.66        It is thus concluded that there is no reasonable alternative to the IMT tunnel option which requires temporary reclamation for construction at the Hung Hom landfall and adjacent to and in the CBTS and replacement of the fender piles for the Hung Hom Bypass (which is considered as permanent reclamation.) This option is the most appropriate option that can achieve the project needs and benefits to the public and be constructed with proven technology, with lower costs and less risk to programme.

2.67        A comparison of the key aspects of each alignment is presented in Table 2.1 below.

2.68         Based on feedback from the public consultation process particularly from the Professional Forum and taking into account construction risks and programme, the Western Corridor option is considered to be a better option than the Eastern Corridor options.

 

 


Table 2.1           Comparison of Alignment Design Options for Cross Harbour Tunnel

Construction alignments/ Aspects

“No Reclamation” Options

Alternative Options Requiring Reclamation

Bridge Option

Deep TBM Tunnel Option

Shallow TBM Tunnel Option

IMT Eastern Corridor

IMT Western Corridor

Option 1A

(below CWB)

Option 1B

(below CWB)

Option 1C

(below CWB)

Option 1D

(above CWB)

Engineering Factors

Implementation Programme

-

+ 2 further years as compared to IMT.

+ 2 further years as compared to IMT.

Extended 3 years of works in CBTS & cause delay to CWB

Extended 3 years of works in CBTS & cause delay to CWB

Extended 3 years of works in CBTS & cause delay to CWB

Extended 3 years of works in CBTS & cause delay to CWB

Extended 1.5 years of

works in CBTS but no delay to CWB

Interface with Existing Facilities

Major impact on the East Rail Line, existing roads and other infrastructure on Kowloon side.

Major resumption of land on Hong Kong Island would be required.

The Hong Kong Coliseum would also have to be demolished.

-

-

Prolonged occupation of moorings at CBTS and major interaction with CWB.

Limited mooring affected.

Construction/ Operation Safety, Flexibility and Maintainability

Shipping at the busy Victoria Harbour would be difficult since sufficient navigation clearance will be needed under deck.

Use of face interventions at greater than the maximum 50 psi pressure as currently set in the Factories and Industrial Undertakings Ordinance (Cap 59). It is considered that the Health & Safety risks associated with these options cannot be justified.

Increased construction complexity and risk,

particularly for the construction under the

Cross Harbour Tunnel,

Adverse impact on interchange at EXH

Increased construction complexity and risk,

particularly for the construction of the combined CWB and SCL tunnels under the

Cross Harbour Tunnel,

More simple construction method. Size and duration of temporary reclamation would be significantly reduced. All permanent works would be below seabed or lowest astronomic tide level

 

High risk

High risk

High risk

Medium risk

Low risk

Temporary / Permanent Reclamation

Nil

Nil

Nil

0.6ha

Temporary Reclamation

+

 Permanent reclamation required for the reprovision of fender pier piles for Hung Hom Bypass (not considered to affect the enjoyment of the Harbour)

2ha

Temporary Reclamation +  Permanent reclamation required for the reprovision of fender pier piles for Hung Hom Bypass

2ha

Temporary Reclamation

+

Permanent reclamation required  for the reprovision of fender pier piles for Hung Hom Bypass

 

0.6ha

Temporary Reclamation required  for the reprovision of fender pier piles for Hung Hom Bypass

+

additional  6.7ha Permanent reclamation for CWB.

2.2ha

Temporary Reclamation

Required.

+

Permanent

Reclamation required for the reprovision of fender pier piles for Hung Hom Bypass. 

Land Acquisition & Railway Operation

Bridge extends a significant distance along the North shore of Hong Kong Island and Kowloon.

Cross-platform interchange not engineered practical at the stations.

80m below sea level in bedrock;

HUH Station at 50m deep and EXH at 43m deep

Cross-platform interchange not possible and unacceptable level of service for passenger entering or leaving stations.

Deep Station;

Cross--platform interchange not OK.

Longer tunnels;

Cross-platform interchange at EXH not OK.

Longer tunnels;

Cross-platform interchange at EXH not OK.

Longer tunnels;

Cross-platform interchange at EXH not OK.

Longer tunnels;

Cross-platform interchange at EXH not OK.

Min length;

Cross-platform interchange at EXH OK.

Environmental Factors

Environmental Considerations

·  Significant visual impact

·  Water and ecology/fishery impacts would be concerns.

 

·  Much more sediment/C&D will be generated due to a longer alignment.

 

·  Much more sediment/C&D will be generated due to a longer alignment.

·  Construction noise and dust would be a concern at the cut-and-cover section at the landing points only.

·  Water and ecology/fishery impacts would be concerns.

 

·  Localised construction noise and dust impact at the cut-and-cover section at the landing points.

·  Water and ecology / fishery impacts would be concerns.

 

Other Factors

Avoidance of Issues/Constraints

SCL (HUH-ADM) would be a major concern on marine traffic.

Tunnelling for the SCL (HUH-ADM) would be a major concern on Health & Safety risks.

Engineering constraints cannot be resolved.

Avoidance of engineering and environmental constraints has largely been investigated and resolved.

Disruption to the Community

Due to the longer time span and larger works area, a larger disruption to the community would be expected.

-

-

Long interfacing/ disruption at CBTS.

Limited interfacing/ disruption at CBTS.


Preferred Option 

2.69        As discussed, the IMT along the Western Corridor option is considered as the most appropriate option that can both achieve the needs of the SCL project and benefit to the public and be constructed with proven technology, at lower costs and less risk to the programme.

2.70        Under this preferred option, temporary reclamation will be required to construct the portion of the SCL tunnel running through the existing CBTS breakwater and inside the CBTS by cut-and-cover method.  This method is similar to that of the CWB project, which involves cut-and-cover construction, temporary reclamation and seawalls. It is thereby proposed that the section of SCL tunnel above the CWB tunnel will be constructed in conjunction with the CWB tunnel under the Project.

2.71        This scheme of the SCL (HUH-ADM) has essentially defined the scope and components of the Project as described in Section 2.7, since the design of the Project is aimed to tied in with and meet the requirements of the preferred option of the SCL (HUH-ADM). This, on the other hand, has imposed more constrains on possible alternatives in terms of feasible engineering design, size and location requirements.

 

Construction Methods

2.72        As aforementioned, the preferred scheme of the SCL (HUH-ADM), which was found to be the most all-rounded option that can achieve the project needs and benefit to the public at the least expense of cost and risk, has largely defined the scope and design of this Project.

2.73        The section of SCL within the CBTS will be constructed using the cut-and-cover method thus requiring temporary reclamation; relocation of the temporary RHKYC jetty and dredging at the southeast corner of the CBTS to provide space for temporary relocation of anchorage area for the vessels.  A small fraction at the southwest corner of the temporary reclamation will be retained until the completion of the SCL tunnel works scheduled in 2017. Detailed descriptions on each activity are given below.  

Cut-and-Cover Tunnel Construction

2.74        Temporary reclamation will be required to construct the SCL Protection Works inside the CBTS using cut-and-cover method. The temporary reclamation would be located on the western side of the CBTS.

2.75        The cut-and-cover method would involve constructing a temporary reclamation area to provide a dry working platform and the installation of temporary walls propped by steel struts. The soil between the temporary walls would then be excavated and a reinforced concrete tunnel box would be constructed to form the permanent structure. Backfilling would then be undertaken on top of the tunnel and followed by the removal of temporary reclamation. Certain provisions would be built into the end of the tunnel to enable subsequent extension of the tunnel by the SCL project. This approach is similar to that adopted by the CWB tunnels for construction within the CBTS.

2.76        Based on feedback from consultation with stakeholders and users of the CBTS and taking into account constraints on availability of off-site reprovisioning, the general view is that no additional moorings (i.e. over what CWB has proposed) should be relocated outside of the CBTS to facilitate SCL construction.  For vessels to be relocated to other locations within the CBTS to suit the construction works, buoy and sinker moorings and/or pontoons could be used. It is therefore proposed that the section of SCL tunnel above the CWB tunnel will be constructed in conjunction with the CWB tunnel under the CWB project.

2.77        The CWB project would construct the SCL tunnels from adjacent to the shoreline to just north of the CWB tunnel.  This will require some modification to the limits of temporary reclamation carried out under the CWB project on authorisation of the SCL scheme under the Foreshore and Sea-bed (Reclamation) Ordinance upon approval of EIA report. A small part of the temporary reclamation would be left in place adjacent to the shoreline to allow the SCL project to construct the SCL tunnels through the seawall.  This temporary reclamation would be removed by the SCL (HUH-ADM).

Area of Temporary Reclamation

2.78        The width of the temporary reclamation is driven by the following requirements:

·                Working space for construction of tunnels;

·                Temporary walls;

·                The need to minimize conflicts between the seawall foundation and temporary wall construction.

2.79        The total area of temporary reclamation (measured as the area within the copelines of the vertical seawall) including the reclamation outside the CBTS is approximately 2.2ha in addition to that required for CWB construction. To be specific, the Protection Works would require 0.7ha of temporary reclamation, of which 0.3ha has been authorized under the CWB project and the remaining 0.4ha being additional. This 0.4ha area is the minimum extent for temporary reclamation required to allow the construction of the 160m Protection Works on top of the CWB tunnel.

2.80        However, this is not the extent of temporary reclamation at any one time. The staging of the works will have a significant effect on the extent of temporary reclamation at any one time.

Options to reduce temporary reclamation in CBTS

2.81        Alternatives to reduce temporary reclamation as a result of cut-and-cover tunnel have been considered, such as the use of a pipe piled cofferdam without temporary seawalls and reclamation, for the section of SCL works adjacent to the breakwater. However, these were rejected due to the risks associated with the depth of the piles and excavation, and also the risk of marine collisions.

2.82        An option of extending the immersed tube tunnel into the CBTS was also considered with the aim to reduce the extent of temporary reclamation required. However, during consultation with the users of the CBTS, clear views have been expressed that there should be no reduction in the protection provided to their moorings by the existing breakwater. Construction of IMT through the breakwater would require a significant section of the breakwater to be removed. The extent of mooring area affected in the CBTS would also be similar to the proposed cut-and-cover option.

Dredging for Temporary Mooring Space

2.83        Due to the increase in the temporary reclamation area required for the SCL Protection Works, vessels within the increased reclamation area as well as those in the southwest corner will be affected. The southeast corner of the CBTS will therefore need to be dredged to provide sufficient water depth to allow the relocation of moorings.

2.84        The anchorage area of the CBTS will be expanded into the southeast corner underneath the existing Island East Corridor. The extent of dredging in the southeast corner is around 1ha, which is already the minimum extent for dredging the seabed to a level of -3.5m to -4.0mCD, which is sufficient for temporary anchorage and at the same time maintaining a navigation channel of not less than 20m wide. Temporary use of this area for anchorage will not affect the future permanent use of the site to its immediate east for the reprovisioning of the Tin Hau Temple Boat.

Relocation of RHKYC Jetty

2.85        Certain facilities required for operation of the Royal Hong Kong Yacht Club will be affected by the SCL and CWB construction works. These will require temporary reprovisioning during SCL construction and reinstatement at its original position upon completion of the project. These include the pontoon and the jetty for hoisting boats from the water for maintenance etc. The jetty will require to be piled both in its temporary location and when reinstated in its permanent position. The temporary reprovisioning of the jetty is considered to be temporary reclamation. The floating pontoon system will not be piled and this is not considered to involve either temporary or permanent reclamation.

Retaining of Temporary Reclamation

2.86        While most of the temporary reclamation will be removed after the completion of the Project, a small area (approximately 0.26ha) in the southwest of the temporary reclamation will be retained in order to enable the construction of future SCL tunnels to connect with the proposed SOV. This part will be removed upon completion of the concerned tunnel works by 2017.

Option without retaining the southwest corner of the temporary reclamation

2.87        Option without retaining this small area of temporary reclamation has been considered in view of the extended occupancy of the Victoria Harbour which is a highly sensitive issue. The key purpose of retaining this part of temporary reclamation, as mentioned, is to facilitate the connection between the SCL tunnel box laid under the Project and the land-based tunnel section starting at the proposed SOV, where a small harbour section of the tunnel needs to be installed by cut-and-cover method. Therefore if all temporary reclamation including the southwest area section is removed upon completion of the Project, repeated temporary reclamation (including seawall construction, associated dredging and filling) will be required for this small section when future SCL tunnel construction is ready to extend from the Protection Works to the proposed SOV. Moreover, the size of the retaining area is considered to be minimum which is capable of accommodating future construction works for the connection of SCL tunnel to the SOV with minimal disturbance induced to the CBTS stakeholder.

2.88        In environmental terms, the extent of temporary reclamation and dredging will be increased under this option. Additional Impacts on water quality and extra waste materials which could otherwise be avoided will arise as a result of the repeated reclamation works. While on the contrary, retainment of temporary reclamation in this small area will not cause any adverse environmental impacts to the surroundings. No construction activities will be carried out throughout this period until future SCL tunnel construction has reached this section.

2.89        In terms of programme implementation, repeated temporary reclamation under this option will lengthen the project duration of the SCL (HUH-ADM) within the CBTS and hence the associated impacts to the sensitive receivers will be prolonged. All these programme and environmental implications due to this option have drawn to the conclusion that, the retaining of temporary reclamation option would minimize the environmental impacts to the CBTS not only by keeping the extent of temporary reclamation and dredging at a minimum level, but also at best shortening the duration of SCL works within the CBTS and fulfil the requirements of the Protection of the Harbour Ordinance by minimizing the extent of reclamation. For the benefits of users in CBTS and surrounding environment, this option is not reckoned as the most environmentally beneficial one. 

Other Alternatives besides retaining the southwest corner of the temporary reclamation

2.90        An option of encompassing the construction of the SCL tunnel to SOV section into the scope of the Project was considered. Under this option, no reclaimed area would need to be retained after the completion of the Project. Whilst efficient integration of the two projects is aimed to minimize duration and disruption to the CBTS users, it was emphasized by HyD that the entrusted SCL works should not delay the completion date for the CWB project. In this connection, this option may lengthen the duration of the Project and hence the scheduled completion of the CWB project. The original length of SCL tunnel structure to be constructed under the CWB project is considered to be at an optimum extent without adversely affecting the CWB project, both in the sense of construction programme and engineering risks associated with future construction of SCL tunnel above the CWB tunnel. This option is therefore not recommended.

2.91        On the other hand, re-arranging the sequence of construction work of SCL (HUH-ADM) to shorten the retaining time of the temporary reclamation at the said location has been considered. It should be noted that if the SCL (HUH-ADM) construction works, particularly those within the CBTS, are to be conducted earlier to trim the period of retaining the reclamation area, cumulative environmental impacts especially on air and water quality will likely be intensified. In addition, this option will further diminish the available area for temporary mooring in the CBTS and reprovision of mooring site outside the CBTS will be unavoidable which the CBTS users have expressed strong opposition to such arrangement. Above all, this is again not a preferable option to go for. 

Environmental Consideration of Alternative Construction Methods

2.92        Potential environmental issues associated with alternative construction methods for the Project have been considered and a summary of the benefits and dis-benefits of the construction methods is presented in Table 2.2 below.

Table 2.2           Benefits and Dis-benefits of Construction Methods

 

Construction Method

 

Benefits

Dis-benefits

Construction of Protection Works

Cut-and-Cover Tunnel

·         Protection to the moorings/anchorage vessels in CBTS is maintained.

 

·         Same construction method as CWB tunnel allowing integration of the two projects and hence shorter construction period.

 

·         Temporary reclamation and associated dredging will be required that would give rise to potential water quality impact and sediment disposal issue.

·         Potential dust impact from the construction activities, such as seawall construction, excavation, backfill, material handling, etc.

·         Potential noise impact from the use of powered mechanical equipment (PME) during the construction activities.

Immersed Tunnel

·         No temporary reclamation is required and hence lesser construction dust impact is anticipated compared to cut-and-cover tunnel.

·         Significant section of the breakwater needs to be removed thus impede the protection provided to the moorings in CBTS.

·         Dredging operation is required that would give rise to potential water quality impact and sediment disposal issue.

·         Potential noise impact from the use of PME during the construction activities.

Pipe piled cofferdam

·         No filling, dredging and seawalls construction are required and hence impact on water quality and sediment disposal issue are not anticipated.

·         No potential construction dust impact

·         Potential risk of marine collision

·         Risks associated with the depth of the piles and excavation.

·         Potential noise impact from the use of PME during the piling activities.

 

Retaining the southwest corner of temporary reclamation

Retainment Option

·         Repeated temporary reclamation can be avoided.

·         Reduce potential water quality impact and sediment disposal issue

·         Temporary occupancy of the harbour

No Retainment option

·         Temporary occupancy of the harbour can be avoided.

 

 

·         Repeated temporary reclamation and associated dredging will be required that would result in potential water quality impact and sediment disposal issue.

 

·         Project duration will be lengthened and hence longer disturbance to the users of CBTS and the public.

Including the construction of the tunnel to SOV into the scope of the Project

·         Temporary occupancy of the harbour can be avoided.

 

·         May cause delay to the CWB project

·         May increase engineering risks to future construction of SCL tunnels in CBTS

 

Re-arranging sequence of SCL (HUH-ADM) construction works

·         Temporary occupancy of the harbour can be avoided.

 

·         Cumulative environmental impacts especially on water and air quality could be intensified.

·         Available area for mooring in the CBTS will be diminished, resulting in reprovision of temporary mooring site outside CBTS.

 

Sequences of Works

2.93        In determining the staging for construction of the SCL works adjacent to and within the CBTS, due consideration has been taken of views expressed in consultation with the District Councils, the public and affected stakeholders. The principal concerns were:

·                The SCL works should be integrated with the CWB works where possible with a view to minimizing the duration of construction.

·                Stakeholders do not want to have any more moorings reprovisioned out of the CBTS (i.e. over what CWB has already proposed).

·                Adequate separation should be provided between moorings and the construction equipment for the required marine works. The level of protection provided by the existing breakwater should be maintained.

2.94        The construction of the SCL tunnels through the CBTS would be carried out in stages, using the same approach to dealing with the moorings as developed under the CWB project.  Whilst it is envisaged that the SCL works within the CBTS can be completed within 18 months of completion of the CWB works within the CBTS, the full area of temporary reclamation would not be in place up until that time. Illustrative construction staging plans for the works through the CBTS are shown in Appendix 2.2.

2.95        Key aspects of the staging are:

·                The section of SCL tunnels which run above the CWB tunnel and to the south of the CWB tunnel within the CBTS will be constructed under the CWB construction contract.

·                Construction of the SCL tunnels immediately to the north of the existing breakwater will commence during Stage 3 of the CWB construction to allow the connection between the immersed tube tunnel and the cut-and cover-tunnel to be completed.

·                Construction of the SCL tunnels through the breakwater and into the northern part of the CBTS would commence once the CWB Stage 3 works are completed.  These works will extend as far as possible into the CBTS without affecting CWB construction or requiring additional moorings to be relocated out of CBTS. Earlier commencement of these works is not possible without additional moorings being relocated out of CBTS.

·                The final stage of SCL construction would commence once all of the CWB works within the CBTS are completed.  These would take a further 18 months to complete.

2.96        The durations of the temporary reclamation stages for SCL works from the time of starting seawall construction and filling above the seabed to the time when the temporary reclamation is removed and the seabed reinstated will vary from 15 months to 28 months, except for a small area near the shoreline (Area SCL 1.4 in Appendix 2.2) which will stay for a longer period. 

2.97        Upon completion of each stage, the temporary reclamation would be removed and the seabed reinstated.  There would be some overlapping of temporary reclamation between stages.  At any one time the maximum area of temporary reclamation for SCL would be around 1.6ha (excluding temporary reclamation for CWB).

2.98        Therefore, whilst the overall area of temporary reclamation required for SCL construction at the CBTS is approximately 2.2ha, the additional affected area of the harbour in respect of temporary reclamation in the CBTS will only be around 1.6ha for approximately 8 months.  This would be reduced to approximately 0.8ha for the final 10 months of SCL construction after completion of the CWB.

Environmental Consideration of Alternative Sequences of Construction

2.99        Environmental issues arising from alternative sequences of construction have been reviewed. The relative benefits and dis-benefits of the different sequences of construction for the Project are summarised in Table 2.3 below.

Table 2.3        Benefits and Dis-benefits of Construction Sequences

 

Construction Sequence

 

Benefits

Dis-benefits

Construction of Protection Works together with CWB works

·         Significantly minimize the extent and duration of disturbance to the users of CBTS and the public

·         Avoid potential dust, noise, waste and water quality impacts due to repeat temporary reclamation.

·         Potential cumulative construction noise and dust impacts from the construction of CWB project to local communities

Construction of Protection Works upon completion of CWB works

·         Reduce potential cumulative construction dust and noise impacts from the CWB project to local communities

·         Potential dust, noise, waste, water quality impacts due to repeat temporary reclamation and prolonged construction period

·         Longer duration of disturbance to the users of CBTs and the public  

 

 

Construction Programme

2.100      The construction of the Project is anticipated to commence in 2012 and be substantially completed by 2013. A tentative construction programme for the Project is presented in Appendix 2.3. The small reclaimed area at the southwest corner that will be retained to enable the construction of future SCL tunnels to connect with the proposed SOV will be removed in 2017 under the SCL (HUH-ADM).

 

Concurrent Projects

2.101      Concurrent projects in the vicinity of the Project which would likely interact with this Project include:

·                Wan Chai Development Phase II (WDII); and

·                Central-Wanchai Bypass including its road tunnel and slip roads for Island Eastern Corridor Link (CWB)

2.102      In terms of water quality assessment, the assessment area covers the Victoria Harbour Water Control Zone (WCZ) and hence concurrent projects within this WCZ are identified. They are:

·          Dredging Works for Proposed Cruise Terminal at Kai Tak (CT Dredging);

·          Public Landing Steps cum Fireboat Berth under the KTD Project;

·          Runway Opening under the KTD Project;

·          Disused Fuel Dolphin under the KTD Project;

·          Installation of Submarine Gas Pipelines from Ma Tau Kok to North Point for Former Kai Tak Airport Development (New Submarine Gas Main);

·          Road T2 and Central Kowloon Route (CKR); and

·          Lei Yue Mun Waterfront Enhancement.

2.103      The potential cumulative environmental impacts of the identified concurrent projects during the construction of the Project are summarised in Table 2.4 below.


Table 2.4           Summary of Concurrent Projects

Project

Tentative Start

Tentative Finish

 

Potential Cumulative Environmental Impact

WDII

2010

2016

·         Cumulative dust impact at Causeway Bay area

·         Cumulative water quality issue

CWB

2009

2017

·         Cumulative dust, water quality and air-borne noise impact at Causeway Bay area

CT Dredging

2013

2015

·         Cumulative water quality issue

Public Landing Steps cum Fireboat Berth under the KTD Project

2010

unknown

·         Cumulative water quality issue

Runway Opening under the KTD Project

2014

unknown

·         Small-scale dredging at 2km away, cumulative  impact no anticipated

Disused Fuel Dolphin under the KTD Project

unknown

unknown

·         no dredging work, cumulative  impact not anticipated

Installation of New Submarine Gas Main

2012

2012

·         Cumulative water quality issue

Road T2 and Central Kowloon Route (CKR)

2012

2013

·         Cumulative water quality issue

Lei Yue Mun Waterfront Enhancement

unknown

unknown

·         8km away, cumulative impact not anticipated

 

Continuous Public Involvement

2.104      Public consultation activities were conducted to brief the public on the issues associated with the proposed SCL (HUH-ADM) works in the harbour and seek their views. These included public forums, professional forums and seminars, presentations to and discussions with District Councils and Harbour-front Enhancement Committee. Table 2.5 summaries the meeting the public consultation activities.


Table 2.5           Summary of Public Consultation Activities

Date

Public Consultation Activity

16 June 2009

First Professional Forum

6 July 2009

CBTS Stakeholder Briefing cum Forum

21 July 2009

Presentation to Wan Chai District Council

23 July 2009

Presentation to Eastern District Council

5 August 2009

Seminar for The Hong Kong Institute of Planners (HKIP)

17 August 2009

Presentation to Harbour-front Enhancement Committee (HEC)

18 August 2009

Seminar for The Chartered Institute of Logistics and Transport in Hong Kong (CILTHK)

19 August 2009

Seminar for The Hong Kong Institute of Architects (HKIA)

24 August 2009

Public Forum – The New Territories

29 August 2009

Public Forum – Kowloon

1 September 2009

Public Forum – Hong Kong Island

10 September 2009

Presentation to Yau Tsim Mong District Council

14 September 2009

Presentation to North District Council

29 September 2009

Presentation to Kwun Tong District Council

9 November 2009

CBTS Stakeholder Briefing cum Forum (PMA users)

20 November 2009

Seminar for Hong Kong Construction Association (HKCA)

30 November 2009

Presentation to Southern District Council

4 December 2009

Second Professional Forum

17 June 2010

Presentation to Eastern District Council

16 July 2010

Presentation to Eastern District Council

 

2.105      Detailed public’s feedbacks and recommendations on the SCL (HUH-ADM) works in the harbour are presented in the CCM Report. Table 2.6 summaries the key public views on this Project.

Table 2.6           Summary of Key Public Views on the Project

Concern Groups

Major Public Views Sought

Professional Institutes / Harbour Protection Concern Groups

 

·         In the first Professional Forum and subsequent seminars, most of the participants agreed that there was an overriding public need for SCL. It was recognised that it could not only relieve congestion of existing lines, but also increase mobility especially for those from the New Territories and older urban districts in East Kowloon.

·         Most of them supported the finding that there was no reasonable “no reclamation” option.

·         It was generally agreed that the Western Alignment was a better option as it would cause less disruption to the CBTS than the Eastern Alignment, and was a more direct route.

·         There was a view expressed that the extent of the proposed temporary reclamation in the CBTS should be minimised.  As explained in Chapter 6 of the CCM Report, the SCL works have been integrated with the CWB project to optimise the use of temporary reclamation formed under that project for SCL tunnel construction. Other areas of temporary reclamation required for SCL construction have been minimised and presented at the second Professional Forum.

·         In response to suggestions by the public, including one raised at the HKIA seminar, alternative alignments which avoided passing through the CBTS were investigated as discussed in Chapter 5 of the CCM Report. These options were found to be unacceptable.

·         There was a view expressed that the SCL and CWB projects teams should work closely together to avoid repeated temporary reclamation and also if possible to reduce the period of construction to minimize disruption to the stakeholders and the public. As described in Chapter 6 of the CCM Report, this close liaison has taken place with the result that it is now intended approximately 160m of the SCL tunnel be constructed under the CWB project subject to the timely authorisation of the SCL project.

·         The second Professional Forum was held in December 2009 to report the public consultation activities conducted, to update the design development and to explain how the reclamation would be minimized. The invitees were the same as those for the first Professional Forum, plus the non-official members of the Harbour-front Enhancement Committee. Participants recognized the coordination work undertaken between the SCL and CWB projects and supported the findings on the duration and the extent of temporary reclamation.

Harbour-front Enhancement Committee (HEC)

 

·         Most of the HEC members supported the SCL project. They opined that the option that would be completed in the shortest period of time should be pursued, and coordination with the CWB project should be necessary. They were concerned about the temporary occupation of the harbour-front areas by different railway projects and asked for mitigation measures to be implemented.

·         Suggestions were offered that the temporary reclamation at CBTS could be further reduced by extending the immersed tube tunnel method into the CBTS or by moving the breakwater outward to provide more sheltered space and allow the SCL construction to be expedited. However, as described in Paragraphs 6.3.15 and 6.3.16 of the CCM Report, the former impacted a similar extent of mooring area in the CBTS and the latter option contravened the requirements of the PHO.  These findings were reviewed and supported at the second Professional Forum.

District Councils

 

·         An information paper on the SCL (HUH-ADM) was sent to all 18 District Councils. Presentations were given to Wan Chai, Eastern, Yau Tsim Mong, North, Kwun Tong and Southern District Councils as requested to introduce the scheme.

·         Most of the District Councillors considered that there is an overriding public need for the SCL. Many District Councils urged for its early implementation. There was no specific view on the findings that there would be no reasonable “no reclamation” option but there was a preference for the Western Alignment.

·         Eastern District Councillors expressed objection to any SCL works being carried out in the CBTS, unless the agreement from all stakeholders of CBTS was obtained. Follow-up meetings with the key Councillors representing the fishermen were held to further explain the need for SCL to pass through CBTS, and a written reply was subsequently sent to the District Council. As noted above it was concluded in Chapter 5 of the CCM Report that the alignment must pass through the CBTS.

·         Follow-up meeting with Eastern District Council was held in July 2010 and the Councillor’s view to obtain agreement from all stakeholders of CBTS was maintained. On-going discussion with stakeholders in the CBTS will be carried out.

Stakeholders at CBTS

 

·         A Stakeholder Briefing cum Forum for CBTS users, except those in the Private Mooring Area (PMA), who would be affected by the construction of SCL was held in early July 2009. Another briefing specifically for PMA users in CBTS was organised in early November 2009.

·         Meetings with individual stakeholders were held from June 2009 onwards in order to better understand their concerns. Their views are summarised in the followings:

-    RHKYC did not object to the construction of the SCL. They had a number of principal concerns and requirements including: the moorings that they had should remain in CBTS; facilities for their operational and sailing activities should be reprovisioned; the protection level offered by the existing breakwater should not be compromised; and, sufficient depth should be provided at reprovisioned locations for their moorings. These issues have been considered in the development of the proposed construction approach described in Chapter 6 of the CCM Report.

-    The anchorage users preferred that the SCL be realigned to avoid passing through the CBTS.  However, on the understanding that the SCL would pass through the CBTS, their primary concerns were: on the duration of the works; the existing breakwater would be removed exposing their moorings to risk, and, dredging would affect the marine ecology and in turn their catches. The alternative alignment has been reviewed and is not considered viable, as explained in Annex A and Chapters 4 and 5 of the CCM Report. Protection to the vessels in the CBTS has been a major factor considered in developing the SCL scheme. The preferred scheme has ensured that the level of protection will not be undermined during construction of SCL. The impact due to dredging will be addressed in the SCL EIA report and where necessary mitigation measures will be proposed.

-    The PMA users expressed no particular strong views on the possible postponement of their return to the CBTS for a period of up to 18 months after completion of the CWB but were concerned about whether they would be able to moor in the same location if they were able to return to the CBTS within the 18-month period. Further discussions with the PMA users will be held to address their concerns.

-    The commercial boat operators did not object to the SCL and the possible postponement of their return to the CBTS for a period of up to 18 months after completion of CWB works in CBTS.  Some requested to reprovision their moorings temporarily within the harbour to accommodate their operational requirements. They were concerned about the lack of sufficient protection during typhoon if the moorings were to be reprovisioned at non-typhoon shelter areas and asked for earlier completion of the works in the CBTS. The approach adopted for the CWB project will continue to be followed for the integrated CWB and SCL works.

Public Forums

 

·         At the three public forums held from late August to early September, most of the participants showed strong support for the SCL project and many urged for earlier completion of the SCL. The general view was that reclamation should be minimized and close coordination with interfacing projects would be necessary. There was a preference that the duration of construction be minimised through close integration with the CWB project but there was recognition that impacts on existing moorings also be mitigated. These issues have been addressed in this Report, i.e. the extent of reclamation and duration minimized.

·         Throughout the forums, no disagreement with the findings that there was no reasonable ‘no-reclamation’ option was raised. 

2.106      To conclude, the majority of the public agreed that there is an overriding public need for the SCL and urged for early completion of this infrastructure.  They supported the finding that there is no reasonable “zero reclamation” option, and preferred the Western Alignment as it requires a shorter construction period and provides a shorter routing between HUH and EXH. Moreover, many people opined that there should be better coordination with the CWB project to minimize disturbance to the CBTS. Having considered the views of the public, as well as all other engineering and environmental factors, it is proposed that the Project is to be implemented as described above.