9              Environmental outcomes and Impact Summary

Introduction

9.1          The Project is a Designated Project (DP) under Item C.12 (b), Part I of Schedule 2 of the EIAO (Cap. 499) – “A dredging operation which is less than 100m from a seawater intake point”. The Project will be undertaken together by the CWB contractor.  The temporary reclamation in the Project together with that in the CWB project will be another designated project under Item C.1, Part 1, Schedule 2 of the EIAO. This EIA report has provided an assessment of the potential environmental impacts associated with the Project, and taken into consideration the potential cumulative impacts from other concurrent projects.

9.2          During the EIA process, specific environmental control and mitigation measures have been identified and incorporated into the planning and design of the Project in order to achieve compliance with environmental legislation and standards. An environmental monitoring and audit (EM&A) programme has also been developed during the assessment of the Project. The key assessment assumptions, limitation of assessment methodologies and all relevant prior agreements with the EPD on assessment of different environmental aspects are given in Appendix 9.1. The implementation schedule listing the recommended mitigation measures is presented in Section 8. A summary of the key environmental outcomes arising from the EIA study and the environmental impacts are presented in the sections below.

Environmental Outcomes

9.3          A summary of the key environmental outcomes arising from the EIA study and the environmental benefits of the environmental protection measures recommended are tabulated in Table 9.1 below:

 

Table 9.1           Summary of Key Environmental Outcomes / Benefits

Area / Issue

Environmental Outcomes / Benefits and Mitigation Measures

The Project

Requirements:

 

The Project comprises the following key elements:

 

·         Temporary reclamation, which occupies about 0.7ha of Government foreshore and sea-bed (of which 0.3ha is already authorized under CWB project, i.e. additional reclamation of 0.4ha is required).

 

·         Dredging works at the southeast corner of the CBTS to provide space for temporary relocation of anchorage area due to the additional temporary reclamation for the Project.

 

·         Construction of a section of the twin track railway tunnel structure (approximately 160m long) above the proposed CWB located entirely offshore within the CBTS.

 

·         Relocation of the temporary RHKYC jetty within the CWB temporary reclamation to a new location.

 

·         Removal of the temporary reclamation, except the small area at the southwest corner of the reclamation (which will be removed by the SCL project upon completion of the future SCL tunnels connecting to the proposed SOV). 

 

 

Benefits:

 

With the presence of the Project, future construction of the SCL on both sides of the CWB tunnels is protected and ensured feasible without damaging or unduly affecting the CWB tunnels which could be operational by then. This arrangement will also minimize public nuisance and impact to the surrounding environment as it can reduce the reclamation area for subsequent construction of the SCL after CWB is completed. 

 

Potential Consequences without the Project:

 

Temporary reclamation will be required in future construction of the Protection Works at the interfacing area with the CWB. The construction may risk the operation of the CWB tunnel as the closest distance between the crown of the CWB tunnel and the SCL tunnels is merely around 3m. The higher construction risks and larger temporary reclamation area will result in a bigger project cost compared to the scenario which the Protection Works is constructed under the CWB project.

 

While the temporary reclamation will be carried out after the completion of CWB project, the size and duration of the temporary reclamation in the CBTS will be significantly more than that of having the Protection Works constructed under the CWB project, leading to a prolongation of impacts to the users of CBTS, disturbance to the moorings and operations of the typhoon shelter.

 

Environmental Friendly Designs Recommended to Avoid Environmental Problems

This Project allows the SCL Protection Works to be constructed together with the CWB works within the CBTS to achieve the following merits:  

·         Use of the temporary reclamation area provided by CWB to avoid the repeated temporary reclamation at the interfacing area of the two projects.  

·         Minimize the extent and duration of temporary reclamation required for the construction of the SCL tunnels.

·         Minimize waste generation during the construction by avoiding the repeated temporary reclamation and hence minimize the potential impact to the existing public fills and landfills in Hong Kong.

·         Minimize disturbance to the moorings and operations of the typhoon shelter and expedite the works to avoid prolongation of environmental impacts.

Water Quality

 

Environmental benefits of environmental protection measures recommended:

Marine Construction

The worst-case scenario during the marine construction period, taking into account the cumulative effects from other concurrent marine works has been assessed. It was predicted that, with the implementation of the recommended mitigation measures, there would be no unacceptable water quality impacts due to the construction of the SCL Protection Works and due to the cumulative effects from other concurrent marine construction activities.

 

Land-based Construction

Potential water quality impact due to land-based construction would arise from the release of sediment-laden water from surface works areas and discharge of construction site effluent.  Water quality deterioration could be minimized through the implementation of adequate mitigation measures. No unacceptable residual impact on water quality is anticipated.

 

Compensation areas included:

N/A.

 

Population and environmental sensitive receivers protected:

Water sensitive receivers along the coastlines of Wan Chai, Causeway Bay, North Point and Kowloon Pennisula.

 

Construction Noise

Environmental benefits of environmental protection measures recommended:

All NSRs in the vicinity of the Project would be protected from construction noise through the implementation of recommended noise mitigation measures including the use of quieter plants and movable noise barrier. There would be no exceedance throughout the Project construction period and no residual impacts are expected.

 

Compensation areas included:

N/A

 

Population and environmental sensitive receivers protected:

Existing NSRs including residential blocks along Gloucester Road and southeast corner of the typhoon shelter.

 

Construction Dust

Environmental benefits of environmental protection measures recommended:

All representative ASRs within 500m of the Project Boundary would be protected from the construction dust impact with the implementation of recommended mitigation measures, which include watering once every working hour on temporary reclamation area of the Project, covering/paving the retained area at the southwest of temporary reclamation and the implementation of good site practices.

 

Compensation areas included:

N/A

 

Population and environmental sensitive receivers protected:

Identified ASRs along Gloucester Road and near the typhoon shelter including existing commercial, residential and recreational developments.

 

Waste Management Implication

Environmental benefits of environmental protection measures recommended:

The proposed waste control and mitigation measures could avoid the potential water quality, dust and noise impacts associated with the handling, transportation and disposal of the identified wastes arising from the construction of the Project.

 

It is estimated that approximately 14,400m3 of inert C&D materials and 300 m3 of non-inert materials would be generated during the construction phase of the Project which would be reused (i.e. other concurrent projects) as far as practicable before off-site disposal. Opportunities in minimization of generation and maximization of reuse would be continually investigated during the detailed design and construction phases.  The remainder of materials would be disposed of to designated outlets.

 

The total volume of dredged sediment generated from the Project is estimated to be approximately 38,200m3. Based on the results of the chemical and biological screening, approximately 9,000m3 sediment is suitable for Type 1 – Open Sea Disposal, 18,700m3 sediment requires Type 2 – Confined Marine Disposal and 10,500m3 sediment requires Type 3 – Special Treatment/Disposal in accordance with ETWB TC(W) No.34/2002.

 

The proposed handling method of dredged Type 3 sediments should adhere to the CWB project under which geosynthetic containment would be employed as disposal method. A proposal for the use of geosynthetic containers on Type 3 sediment should be submitted to TCO/EPD for agreement at a later stage of the Project and prior to the dredging works.

 

With the implementation of the recommended mitigation measures in accordance with the requirements of ETWB TC(W) No.34/2002, no adverse environmental impacts would be expected.

 

Compensation areas included:

N/A

 

Population and environmental sensitive receivers protected:

Water quality, air and noise sensitive receivers at or near the Project Site, the waste transportation routes and the waste disposal site.

 

Impact Summary

Water Quality Impact

Marine Construction

9.4          The water quality impacts during the marine construction works have been quantitatively assessed by numerical modelling. Suspended solids were identified as the most significant water quality parameter during the marine construction works. The worst-case scenario during the marine construction period, taking into account the cumulative effects from other concurrent marine works has been assessed. It was predicted that, with the implementation of the recommended mitigation measures, there would be no unacceptable water quality impacts due to the construction of the SCL Protection Works and due to the cumulative effects from other concurrent marine construction activities. A water quality monitoring and audit programme would be implemented to check the effectiveness of the proposed water quality mitigation measures.

Land-based Construction

9.5          The key issue from the land-based construction activities would be the potential water quality impact due to the release of sediment-laden water from surface works areas and discharge of construction site effluent.  Water quality deterioration could be minimized through the implementation of adequate mitigation measures. Regular site inspections should be undertaken to inspect the construction activities and works areas in order to ensure the recommended mitigation measures are properly implemented.

Noise Impact

9.6          The noise impact assessment in this EIA Study has predicted the construction noise impacts of the Project during normal daytime working hours, taking into account all other concurrent projects within a 300m assessment area. Night-time work would not be involved in this Project. Based on the latest available information, six representative NSRs were identified within 300m from Project Boundary. The assessment result has revealed that noise arising from the construction activities of the Project would have unavoidable potential impact on the NSRs located in the vicinity of the works areas. Unmitigated construction noise levels at the representative NSRs have been predicted, which were found to be in the range of 63 to 84 dB(A).

9.7          Mitigation measures including good site practices, quieter plant and movable noise barrier were recommended to reduce the noise levels so as to meet the EIAO-TM noise criterion.  With the recommended mitigation measures in place, noise levels due to the Project and the cumulative impact with the CWB project at all representative NSRs were predicted to comply with the EIAO-TM daytime construction noise criterion. No residual impact would be envisaged. An EM&A programme was also recommended to be established according to the predicted occurrence of noisy activities.

Construction Dust Impact

9.8          Potential dust impact associated with the construction of the Project has been assessed in this EIA Study. A total of 6 representative ASRs are identified for this assessment within 500m from the boundaries of all associated works areas under the Project in accordance with the criteria set out in the EIAO-TM. Under the Project, potential sources of dust impact would include dredging, temporary seawall construction, filling, installation of diaphragm walls, excavation, placing a reinforced concrete tunnel box and removal of temporary reclamation.

9.9          Under the unmitigated scenario, the predicted cumulative maximum hourly, daily and annual average TSP levels at most of the representative ASRs would exceed the criteria of EIAO-TM and AQO. Proper dust mitigation measures, including watering once every working hour on temporary reclamation area of the Project, covering/paving the retained area at the southwest of temporary reclamation and the implementation of good site practices, were thus proposed.

9.10        With the implementation of the recommended dust mitigation measures, the predicted cumulative maximum hourly, daily and annual TSP levels at all representative ASRs would comply with the criteria in EIAO-TM and AQO. No adverse dust impacts on the ASRs in the vicinity of the construction sites were anticipated.

Waste Management Implications         

9.11        Different types of potential wastes likely to be generated by the Project have been identified in this EIA Study. C&D materials (from construction of railway tunnel structure and relocation of temporary of RHKYC jetty), sediment, general refuse (from workforce) and chemical waste (from maintenance of construction plant and equipment) would be generated during the construction phase.  Provided that these wastes are handled, transported and disposed of using approved methods and that the recommended good site practices are strictly followed, adverse environmental impacts would not be expected.

9.12        Reduction measures have been recommended to minimise the amount of materials generated in the Project.  Approximately 14,400m3 of inert materials and 300 m3 of non-inert materials would be generated during the construction phase of the Project which would be reused (i.e. other concurrent projects) as far as practicable before off-site disposal.  Opportunities in minimisation of generation and maximisation of reuse would be continually investigated during the detailed design and construction phases.  The remainder of materials would be disposed of to designated outlets.

9.13        The total volume of dredged sediment generated from the Project is estimated to be approximately 38,200m3. Based on the results of the chemical and biological screening, approximately 9,000m3 sediment is suitable for Type 1 – Open Sea Disposal, 18,700m3 sediment requires Type 2 – Confined Marine Disposal and 10,500m3 sediment requires Type 3 – Special Treatment/Disposal in accordance with ETWB TC(W) No.34/2002.

9.14        It is proposed that the handling method of dredged Type 3 sediments should adhere to the CWB project under which geosynthetic containment would be employed as disposal method. The sediment should be sealed in geosynthetic containers and disposed of at the designated contaminated mud pit.  The pit would be subsequently capped thereby meeting the requirements for fully confined mud disposal. A proposal for the use of geosynthetic containers on Type 3 sediment should be submitted to TCO/EPD for agreement at a later stage of the Project and prior to the dredging works.

9.15        With the implementation of the recommended mitigation measures and in accordance with the requirements of ETWB TC(W) No.34/2002, no adverse environment impacts would be expected from dredging, transportation and disposal of marine sediment.

Overall Summary

9.16        This EIA has been conducted based on the best and latest information available during the course of the EIA study. The findings of this EIA have provided information on the nature and extent of environmental impacts arising from the Project. The EIA has, where appropriate, identified mitigation measures to ensure compliance with environmental legislation and standards.

9.17        Overall, this EIA has demonstrated the general acceptability of the residual impacts and that the population and environmental sensitive resources in the vicinity of the Project will be sufficiently protected. Environmental monitoring and audit mechanisms have been recommended before and during the construction of the Project, where necessary, to verify the accuracy of the EIA predictions and the effectiveness of recommended mitigation measures. A summary of the environmental impacts associated with the Project is presented in Table 9.2.

 

 


      Table 9.2     Summary of Environmental Impacts associated with the Project             

Sensitive Receivers / Assessment Points

Impact Prediction Results

Relevant Standards / Criteria

Extents of Exceedances

Impact Avoidance Measures / Mitigation Measures

Residual Impacts (After Implementation of Mitigation Measures)

Water Quality Impact

Coral communities and seawater intakes along the coastlines of Wan Chai, Causeway Bay, North Point and Kowloon Pennisula (refer to Figures Nos. NEX2213/C/331/ENS/M59/501 – 503)

·      The model results indicate that full compliance with SS criterion at all the cooling water intakes and WSD flushing water intakes would be achieved.

·      At the far-field coral communities, both the predicted SS elevations and sedimentation rates would comply with the relevant criteria.

1.   WSD’s Water Quality Criteria for Flushing Water at Sea Water Intakes for SS: <10 mg/l.

2.  Target water quality objectives at coral sites for SS elevations: <30% of the mean SS level. 

·      Full compliance would be achieved with the implementation of all recommended mitigation measures.

·      Deployment of silt curtains at appropriate dredging areas to control sediment plume dispersion away from the site.

·      Use of closed grab dredger to minimize the release of sediment and other contaminants during dredging.

·      Silt screens will be installed at the cooling water intakes within the CBTS during the temporary reclamation period.

·      No more than two dredgers (of about 8m3 capacity each) should be operated for dredging within the typhoon shelter at any time of the Project. The combined dredging rate for all concurrent works within the CBTS shall not exceed 6,000 m3 per day throughout the entire construction period.

 

None

Noise Impact (Construction Phase)

Existing residential blocks along Gloucester Road and near the southeast corner of the typhoon shelter.

Six assessment points (refer to Figure Nos. NEX2213/C/331/ENS/M52/ 501502)

 

Predicted noise levels would range from 63 to 84 dB(A)

 

EIAO-TM assessment criterion for works during non-restricted hours for domestic premises: 75dB(A)

 

Exceed the EIAO-TM noise criterion by up to 9 dB(A)

 

Adoption of good site practices, quiet equipment and movable noise barriers to minimise construction noise impact

None

Construction Dust Impact

Existing commercial, residential and recreational developments along Gloucester Road and near the typhoon shelter.

Five assessment points (refer to Figure No. NEX2213/C/331/ENS/M60/ 501)

 

1-hour Average TSP Conc.: 370 – 1969 µg/m3

24-hour Average TSP Conc.: 206 – 894 µg/m3

Annual Average TSP Conc: 77.0 – 84.5 µg/m3

 

EIAO-TM (hourly): 500 mg/m3 

AQO (daily): 260 µg/m3

AQO (annual): 80 µg/m3    

Exceed EIAO-TM (hourly) criterion by up to 1469 µg/m3

Exceed AQO (daily) by up to 634µg/m3

Exceed AQO (annual by up to 4.5 µg/m3

 

 

·      Watering once on the temporary reclamation area of the Protection Works for every working hour

·      Covering/paving the southwest retained area of temporary reclamation once filling is completed

·      Dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation and good site practices would be carried out to further minimize construction dust impact.

None

Waste Management Implications

Water quality, air and noise sensitive receivers at or near the Project Site, the waste transportation routes and the waste disposal site.

Main waste: Dredged marine sediment with a total volume of approximately 38,200 m3

Other wastes:

·   C&D Materials from demolition and excavation works with a total volume of approximately 14,400 m3

·   300 m3 of non-inert C&D material  

·   General refuse from workforce

·   Chemical waste from plant and equipment maintenance

·      Waste Disposal Ordinance (Cap. 354);

·      Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354C);

·      Land (Miscellaneous Provisions) Ordinance (Cap. 28);

·      Public Health and Municipal Services Ordinance (Cap. 132) - Public Cleansing and Prevention of Nuisances Regulation;

·      Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N); and

·      Dumping at Sea Ordinance (Cap. 466).

 

Not applicable.

·      C&D wastes would be reused (i.e. other concurrent projects) as far as practicable before off-site disposal

·      Contaminated dredged sediment (Category M and H) would require either Type 1 – Open Sea Disposal (Dedicated Sites) or Type 2 – Confined Marine Disposal at contaminated mud pit allocated by MFC. Category L sediment is suitable for Type 1 – Open Sea Disposal at gazetted marine disposal ground allocated by MFC.

·      The handling method of dredged Type 3 sediments should adhere to the CWB project under which geosynthetic containment would be employed as disposal method. The sediment should be sealed in geosynthetic containers and disposed of at the designated contaminated mud pit.  The pit would be subsequently capped thereby meeting the requirements for fully confined mud disposal.

·      Other waste reduction measures and good site practices to achieve avoidance and minimization of waste generation from the Project are discussed in detail in Section 6.60 to 6.92.  

None