§ Environmental
Impact Assessment Ordinance (Cap.499.S.16) Technical Memorandum on EIA
Process (EIAO-TM), particularly Annexes 10 and 18;
§ EIAO
Guidance Note (GN) No. 8/2010;
§ Town
Planning Ordinance (Cap.131);
§ ETWB
TC (Works) No. 29/2004 - Registration of Old and Valuable Trees, and Guidelines
for their Preservation;
§ Lands
Administration Office Practice Note No. 7/2007;
§ Hong
Kong Planning Standards and Guidelines, particular Chapter 4, Chapter 8 and
Chapter 11; and
§ Study
on Landscape Value Mapping of Hong Kong.
In accordance with
EIAO GN No. 8/2010 and Clause 3.4.12.2 of the EIA Study Brief No. ESB-261/2013,
the Landscape Impact Assessment Area includes all areas within 500m extended
from the boundary of the Project area.
The Landscape Assessment Area is shown in Figure 12.1.
Visual Impact Assessment
Area
The Visual Impact Assessment Area is identified by the
visual envelope of this Project and its associated works as specified in Clause
3.4.12.2 of the EIA Study Brief No. ESB-261/2013. By definition of EIAO GN No. 8/2010, the
visual envelope (zone of visual influence) is generally the viewshed formed by
natural or manmade features such as ridgeline or building blocks. It contains areas which are fully, partially
visible or unseen from this Project and its associated works. The Visual Impact Assessment Area is
illustrated in Figure 12.2.
The landscape and visual impact assessment (LVIA) is based
on the criteria and guidelines stated in Annexes 10 and 18 of the EIAO-TM and
covered in the scope outlined in Section 3.4.12 and Appendix H of the EIA Study
Brief No. ESB-261/2013. The main
elements include:
§ Identification
of the scope of works
§ Review
of relevant planning and development control framework
§ Baseline
study of LRs, LCAs and VSRs
§ Identification
of potential landscape and visual impacts during the construction and operation
phases
§ Recommendation
on mitigation measures
§ Identification
of residual impacts during the construction and operation phases
§ Assessment
on acceptability according to the criteria set out in Annex 10 of the EIAO-TM
The LVIA makes reference to the EIAO GN No. 8/2010
Preparation of Landscape and Visual Impact Assessment under the EIAO for
evaluation of the landscape and visual impact significance from the
construction and operation of the Project.
Chapter 2 of this EIA report
describes the details of the Project and this section assesses the landscape
and visual impacts that may arise from the Project. The methodology for the
LVIA is described in the following sub-sections.
Review
of Planning and Development Control Framework
§
Plan title/number;
§
Land use zonings;
§
Potential impacts and approximate area of the
land use zones to be affected by the Project;
§
Design and conservation intention; and
§
Mitigation measures and future outlook of the
area.
Landscape
Impact Assessment
Landscape impacts are quantified
as much as possible to predict the magnitude and significance of impacts
arising from this Project and its associated works. LRs and LCAs identified are numbered and
assessed by a combination of desktop studies and site surveys. The difference between mitigated and
unmitigated conditions is properly highlighted to demonstrate the effectiveness
of recommended mitigation measures.
Landscape elements that are in
consideration include:
§ Local
topography;
§ Woodland
extent and type;
§ Other
vegetation types;
§ Built
form;
§ Patterns
of settlement;
§ Land
use;
§ Scenic
spots;
§ Details
of local materials, styles, streetscapes, etc.;
§ Prominent
watercourses; and
§ Cultural
and religious identity.
After identification of baseline
LRs and LCAs, each of the LRs and LCAs is analyzed and evaluated by the
following factors:
Sensitivity of landscape framework
To analyze sensitivity, a number
of factors need to be evaluated. These factors include:
§ the
quality, maturity, condition and value of LRs or LCAs
§ importance
and rarity of LRs or LCAs
§ whether
the site is considered to be of local, regional, national or global
significance
§ any
statutory or regulatory limitations or requirements relating to the LRs or LCAs
on this site
§ ability
of LRs and LCAs to accommodate change
The above factors are considered
and analyzed before each of the LRs and LCAs is classified into the following
three categories:
High: LR
or LCA has a distinctive character or is of high importance and sensitive to
relatively small changes.
Medium: LR
or LCA has a moderately valued landscape character that is reasonably tolerant
to change.
Low: LR
or LCA has a low-valued landscape character that is highly tolerant to change.
Magnitude of change on landscape impact arising from this
Project
A number of factors can
influence the magnitude of change on landscape impact. They are as follows:
§ duration
of impact, i.e. whether it is temporary or long-term
§ scale
of impact
§ reversibility
of change
§ compatibility
of the Project and associated works with existing and planned landscape
The above factors will be
analyzed carefully and the results of each of the LRs and LCAs will be
classified into four different categories.
They are as follows:
Large: Landscape
resource or area will suffer a major change.
Intermediate: Landscape
resource or area will suffer a moderate change.
Small: Landscape
resource or area will suffer a slight change.
Negligible: Landscape
resource or area will suffer no discernible change.
It should be noted that the
landscape impact assessment for construction phase and operation phase is
conducted separately due to the different potential sources affecting the
magnitude of change on landscape impacts.
Evaluation of the sensitivity
and magnitude of change on various LRs and LCAs is conducted in a logical,
reasonable and consistent manner for both construction and operation phases.
Each of the LRs and LCAs is given a degree of impact significance depending on
the severity of sensitivity and magnitude. Table 12.1 illustrates the underlying principle for each of the four significance
thresholds.
Table 12.1: Sensitivity
and Magnitude of Change on the Degree of Impact Significance
|
Sensitivity
|
|
Magnitude
of Change
|
Low
|
Medium
|
High
|
Large
|
Moderate
|
Moderate / Significant
|
Significant
|
Intermediate
|
Slight / Moderate
|
Moderate
|
Moderate /
Significant
|
Small
|
Slight
|
Slight /
Moderate
|
Moderate
|
Negligible
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
Note: Significant
Adverse / beneficial impact where the Project would cause significant
deterioration or improvement.
Moderate
Adverse / beneficial impact where the Project would cause noticeable
deterioration or improvement.
Slight
Adverse / beneficial impact where the Project would cause barely noticeable
deterioration or improvement.
Insubstantial
The Project would cause no discernible change.
|
In accordance with
Lands Administration Office Practice Note No. 7/2007, all existing trees with
trunk diameter measuring 95mm or more at a height of 1.3m above ground level
within the Landscape Impact Assessment Area were included in the tree survey.
Every tree surveyed
is recorded with the following information:
§
Species botanical and Chinese names of
surveyed tree recorded
§
Height full height measured from ground level
to top branch in meters
§
Crown spread diameter of tree canopy in meters
§
Trunk diameter diameter of main trunk measured
at a height of 1300mm above ground level
§
Tree form estimated according to canopy,
branch and trunk. This will be rated as
good, fair or poor.
§
Amenity value estimated according to species,
age, size health condition and tree form.
This will be rated as high, medium or low.
§
Health condition estimated according to
foliage, exposed roots, branches and trunk.
This will be rated as good, fair or poor.
§
Survival rate after transplanting Estimated
according to condition of tree, size, maturity, species, access and
location. This will be rated as high,
medium or low.
§
Special features supplementary special site
features identified on site, as well as tree defects, physical characteristics
and ground conditions area recorded.
Visual Impact Assessment
First, visual
assessment is conducted by identifying key VSRs. Second, assessment of the severity of impact
in terms of nature, distance and the number and type of sensitive receivers is
conducted. Third, the visual
compatibility or impact magnitude of this Project and its associated works with
the existing and planned users and possible interference with key views is
analyzed. Each of the VSRs is given an
identity number and used in all relevant tables and figures. The difference between mitigated and
unmitigated conditions is properly highlighted to demonstrate the effectiveness
of proposed recommended mitigation measures.
Type of visual sensitive receivers
Type of visual
sensitive receivers is classified according to the activities, the number,
availability of alternative views, duration and frequency of the view and the
degree of visibility from a sensitive receivers point of view. In general, the type of receivers can be
separated into five categories:
§
Residents These VSRs can view the impact from
their homes. They are considered to be
highly sensitive as their visual perception has a substantial effect on their
quality of life and home environment.
§
Workers These VSRs can view the impact from
their workplace or school. They are
considered to be moderately sensitive as the visual perception is less
important and has a lesser effect on their quality of life. The degree of impact is dependant on the type
of workplace, i.e. industrial, retail or commercial.
§
Outdoor leisure activity participants These
VSRs can view the impact whilst taking part in an outdoor leisure activity. The
degree of sensitivity is denoted by the type and duration of the leisure
activity.
§
Travellers These VSRs can view the impact
whilst travelling to another location.
The degree of sensitivity is dependant on the duration and speed of
their travel.
§
Community These VSRs can view the impact
whilst in a community building. The
degree of sensitivity is dependant on the type of activities and services that
takes place.
Sensitivity of Visual Sensitive Receivers
To analyze
sensitivity of VSRs, a number of factors needs to be evaluated. These factors include:
§
Value and quality of existing views;
§
Availability and amenity of alternative views;
§
Type of VSRs
§
Number of VSRs;
§
Duration and frequency of view; and
§
Degree of visibility.
The above factors
are considered and analyzed before the sensitivity of each of the VSRs is
classified into the following three categories:
High: The
VSRs are highly sensitive to any changes in their visual experience.
Medium: The
VSRs are moderately sensitive to any changes in their visual experience.
Low: The VSRs are slightly sensitive
to any changes in their viewing experience.
Magnitude of change
Magnitude of change
for VSRs is evaluated by a number of different factors such as:
§
Duration of impact, i.e. whether the impact is
temporary or permanent
§
The number of sensitive receivers
§
Reversibility of the impact
§
Scale and distance of the impact from the viewer
§
Degree of visibility of the impact
§
Compatibility of the project with the
surrounding landscape
The above factors
are carefully analyzed and classified in the following categories:
Large: The VSRs will suffer a major
change in their visual experience.
Intermediate: The VSRs will suffer a moderate change in
their visual experience.
Small: The VSRs will suffer a slight
change in their visual experience.
Negligible: The VSRs will suffer no discernible
change in their visual experience.
The visual impact
assessment is conducted individually for the construction phase and operation
phase due to the disparate visual experience from different potential sources
of visual impact from this Project and its associated works.
Evaluation of the
sensitivity and magnitude of VSRs is conducted in a logical, reasonable and
consistent manner for both construction and operation phases. Each of the VSRs is given a degree of visual
impact significance depending on the severity of sensitivity and
magnitude. The rationale for
categorising the degree of visual impact significance into four thresholds is
illustrated in Table 12.1.
Mitigation Measures
After identifying LRs,
LCAs and VSRs that require mitigation measures to reduce the degree of impact,
possible mitigation measures that can be implemented for this Project and its
associated works will be reviewed and evaluated. Identification of potential mitigation measures
may include:
§
Alternative design or revisions to basic
engineering or architecture design to prevent or minimise adverse impacts
§
Remedial measures during and after construction
phase
§
Compensatory measures for unavoidable adverse
impacts and attempt to generate beneficial long term impacts
Recommended
mitigation measures are evaluated for comparison before adopting as mitigation
or compensatory measures. This is
conducted through evaluating possible mitigation measures by the degree of
residual impact assessment to illustrate mitigation effectiveness.
Residual Impact Assessment
Residual impacts
are evaluated by the sensitivity and magnitude of change for both landscape and
visual impact assessment after the implementation of proposed mitigation
measures. In accordance to Annex 10 of
EIAO-TM, overall assessment of residual landscape and visual impacts for this
Project is placed into one of the following five thresholds.
§
Beneficial
The Project complements the landscape and visual character of its setting and
follows the relevant planning objectives. It will improve overall landscape or
visual quality.
§
Acceptable
There are no significant effects on landscape or visual effects caused by
this Project.
§
Acceptable
with mitigation measures There will be some adverse effects that may be
eliminated, reduced, or offset by specific mitigation measures.
§
Unacceptable
The adverse effects are considered to be excessive with implemented mitigation
measures.
§
Undetermined
Significant adverse effects are likely but the extent of which they occur or
may be mitigated cannot be determined from this study. Further detailed study
may be required.
A review of the
existing and planned development for the proposed works and for the
surroundings has been undertaken. It
aims in identifying issues with neighbouring planned land uses, identifying
potential resources and sensitive receivers and ensuring a high compatibility
between the Project and the surroundings.
The assessment
covers areas shown on the Outline Zoning Plan (OZP) number S/H15/28 Aberdeen
and Ap Lei Chau. Zoning in this OZP is
overlaid onto the Landscape Impact Assessment Area and illustrated in Figure 12.3. A review on this OZP reveals that the entire
Project Area is within the land use type Other Specified Uses OU for Ocean
Park only. The planning intention of
this zone is primarily for comprehensively planned low-density and generally
low- to medium-rise marine-themed park development in Hong Kong with related
retail, dining and entertainment facilities serving visitors as well as the
general public. There is a height
restrictions for buildings in this zone which states that No new development,
or addition, alteration and / or modification to or redevelopment of an
existing building shall result in a total development and / or redevelopment in
excess of the maximum building height in terms of number of storey(s) as
stipulated on the Plan, or the height of the existing building, whichever is
the greater.
Since all the
proposed works of the Project are low- to medium-rise development of
marine-themed retail, dining and entertainment facilities within Ocean Park,
the Project is in line with the planning intention of this OU zone. No re-zoning under Section 12A of the Town
Planning Ordinance will be required for the implementation of the Project. However, should the building height
restriction of this OU zone be violated by the proposed redevelopment,
planning application under Section 16 of the Town Planning Ordinance will be
required. Table
12.2 summarises the findings of the planning and development
control review on areas within the Landscape Impact Assessment Area.
Table 12.2: Review
of Existing Planning and Development Control Framework
Land Use
Zonings
|
Landscape
Planning, Design and Conservation Intention of Zoning
|
Potential
Impacts
|
Mitigation
Measures and Future Outlook of the Area with the Proposed Works
|
Outline
Zoning Plan number S/H15/28 Aberdeen and Ap Lei Chau (Figure 12.3)
|
1.
Other Specified
Uses OU for Ocean Park only
|
This
zone encompasses the Ocean Park. Part
of this zone is within the Project Area, which has been operated as Middle
Kingdom, Aviary, Flamingo Pond, and Bird Paradise till January 2011.
This
zone is intended primarily for comprehensively planed low-density and
generally low- to medium-rise marine-themed park development in Hong Kong
with related retail, dining and entertainment facilities serving visitors as
well as the general public.
|
Part of this zone, which includes the Middle
Kingdom, Aviary, Flamingo Pond, and Bird Paradise, and part of the shrubland
in the periphery, is proposed to be redeveloped into a Water Park. The Water Park will comprise (i) an indoor
zone with a wave pool; lazy river, play structure, water
slides, surf-rider, various pools, F&B facilities, E&M utilities,
back of house and car-parking; (ii) an outdoor zone with a wave pool, lazy
river, water slides, ride platforms, various pools, sea turtle exhibit and
some small-scale F&B facilities; (iii) a general approach area with coach
and taxi drop-off point and EVA; and (iv) sewerage facilities including
sewage sump pit and twin above-ground rising mains of 150mm diameter
each. Rezoning under Section 12A of
the Town Planning Ordinance is not required for the implementation of this
Project. However, planning application
under Section 16 of the Town Planning Ordinance will be required if building
height restriction is violated.
|
The future overall outlook of this zone in operation
stage is expected to be similar with the existing conditions, with vegetated
slopes surrounding man-made structures.
However, the Project will have an outlook which is less natural
compared to the existing facilities such as the Aviary, Flamingo Pond and
Bird Paradise. Proposed mitigations
measures are listed in Table 12.13, and Table 12.14.
|
2.
Coastal
Protection Area CPA
|
This
zone encompasses the natural coastal areas at Sham Shui Kok.
This
zone is intended to conserve, protect and retain the natural coastlines and
the sensitive coastal natural environment, including attractive geological
features, physical landform or area of high landscape, scenic or ecological
value, with a minimum of built development.
It may also cover areas which serve as natural protection areas
sheltering nearby developments against the effects of coastal erosion.
|
This zone is outside the Project Area. No impact to this zone due to this Project
is anticipated.
|
This zone is outside the Project Area. The
proposed works of this Project will not affect the future outlook of this
zone. No mitigation measure is
proposed.
|
3.
Green
Belt GB
|
This zone encompasses Nam Long Shan (Brick Hill) and
an adjacent vegetated slope between Shum Wan Road and Nam Long Shan Road
north of Ocean Park.
This zone is intended primarily for defining the
limits of urban and sub-urban development areas by natural features, to
protect the natural landscape and environment, as well as to provide a
countryside recreational outlet for the local population and visitors. There is a general presumption against
development within this zone.
|
This zone is outside the Project Area. No impact to this zone due to this Project
is anticipated.
|
This zone is outside the Project Area. The
proposed works of this Project will not affect the future outlook of this
zone. No mitigation measure is
proposed.
|
4.
Government,
Institution or Community G/IC
|
This zone encompasses the areas occupied by Po
Chong Wan Temporary Industrial Area, Victoria Shanghai Academy, Canadian
International School and Hong Kong Juvenile Care Centre.
This zone is intended primarily for the provision
of Government, institution or community facilities to serve the needs of
local residents and/or a wider district, region or the territory. It is also intended to provide land for
uses directly related to or in support of the work of the Government,
organisations providing social services to meet community needs, and other
institutional establishments.
|
This zone is outside the Project Area. No impact to this zone due to this Project
is anticipated.
|
This zone is outside the Project Area. The
proposed works of this Project will not affect the future outlook of this
zone. No mitigation measure is
proposed.
|
5.
Industrial
I
|
This zone encompasses the areas occupied by
shipyards and Hospital Authority Shum Wan Laundry.
This zone is intended primarily for general
industrial uses to ensure an adequate supply of industrial floor space to
meet demand from production-oriented industries. Information technology and
telecommunications industries and office related to industrial use are also
always permitted in this zone.
|
This zone is outside the Project Area. No impact to this zone due to this Project
is anticipated.
|
This zone is outside the Project Area. The
proposed works of this Project will not affect the future outlook of this
zone. No mitigation measure is proposed.
|
Findings on Existing Trees
A survey of
existing trees covering areas within the Project boundary was conducted between
April and November 2013. A total of
3,167 nos. of trees are identified within and in close proximity to the survey
area. The average size of the trees
surveyed is around 6.6m in height, 4.2m wide crown spread and with average
trunk diameter of approximately 0.18m.
There were a total
of 102 tree species surveyed inside the survey area. The general conditions of the trees were
found to be fair to poor. The dominant
tree species are Pinus massoniana and
Acacia confusa, which were widespread
throughout. Polyspora axillaris, Leucaena leucocephala, Schefflera
heptaphylla, Macaranga tanarius var.
tomentosa, Sterculia lanceolata and dead trees are also quite common as well.
No registered Old
and Valuable Tree (OVT) or potentially registrable OVT was found in the tree
survey.
Table 12.3 summarises the quantity of all tree species identified in
the tree survey, in descending order of abundance. Tree assessment schedule and tree survey plan
are appended in Appendix
12.1.
Table 12.3: Summary of Tree Survey Findings
Botanical Name
|
Chinese Name
|
Qty
|
Pinus massoniana
|
馬尾松
|
571
|
Acacia confusa
|
台灣相思
|
549
|
Polyspora axillaris
|
大頭茶
|
258
|
Leucaena leucocephala
|
銀合歡
|
200
|
Schefflera heptaphylla
|
鵝掌柴
|
163
|
Sterculia lanceolata
|
假蘋婆
|
159
|
Dead tree
|
枯樹
|
110
|
Macaranga tanarius var. tomentosa
|
血桐
|
100
|
Livistona chinensis
|
蒲葵
|
55
|
Cratoxylum cochinchinense
|
黃牛木
|
53
|
Celtis sinensis
|
朴樹
|
51
|
Casuarina equisetifolia
|
木麻黃
|
46
|
Caryota mitis
|
短穗魚尾葵
|
42
|
Pinus elliottii
|
濕地松
|
42
|
Mallotus paniculatus
|
白楸
|
41
|
Schima superba
|
木荷
|
41
|
Ficus microcarpa
|
細葉榕
|
35
|
Aporusa dioica
|
銀柴
|
34
|
Araucaria heterophylla
|
異葉南洋杉
|
34
|
Delonix regia
|
鳳凰木
|
33
|
Dimocarpus longan
|
龍眼
|
32
|
Rhus succedanea
|
木蠟樹
|
32
|
Syzygium jambos
|
蒲桃
|
28
|
Microcos nervosa
|
破布葉
|
27
|
Tetradium glabrifolium
|
楝葉吳茱萸
|
26
|
Itea chinensis
|
老鼠刺
|
20
|
Ravenala madagascariensis
|
旅人蕉
|
18
|
Choerospondias axillaris
|
南酸棗
|
17
|
Ficus hispida
|
對葉榕
|
16
|
Roystonea regia
|
王棕
|
16
|
Acronychia pedunculata
|
山油柑
|
15
|
Distylium racemosum
|
蚊母樹
|
14
|
Ficus subpisocarpa
|
筆管榕
|
14
|
Archontophoenix alexandrae
|
假檳榔
|
12
|
Ficus benjamina
|
垂葉榕
|
12
|
Archidendron lucidum
|
亮葉猴耳環
|
11
|
Bridelia tomentosa
|
土蜜樹
|
11
|
Lithocarpus glaber
|
柯
|
11
|
Grevillea robusta
|
銀樺
|
10
|
Bauhinia purpurea
|
紅花羊蹄甲
|
9
|
Carallia brachiata
|
竹節樹
|
9
|
Ficus variegata
|
青果榕
|
9
|
Ficus virens
|
黃葛樹
|
9
|
Garcinia subelliptica
|
菲島福木
|
9
|
Spathodea campanulata
|
火焰樹
|
9
|
Juniperus chinensis 'Kaizuca'
|
龍柏
|
8
|
Vernicia montana
|
木油樹
|
8
|
Cinnamomum camphora
|
樟樹
|
7
|
Pongamia pinnata
|
水黃皮
|
7
|
Antirhea chinensis
|
毛茶
|
6
|
Vitex quinata
|
山牡荊
|
6
|
Cocos nucifera
|
椰子
|
5
|
Garcinia oblongifolia
|
嶺南山竹子
|
5
|
Strychnos angustiflora
|
牛眼馬錢
|
5
|
Chrysalidocarpus lutescens
|
散尾葵
|
4
|
Cyclobalanopsis myrsinifolia
|
小葉青岡
|
4
|
Hyophorbe lagenicaulis
|
酒瓶椰子
|
4
|
Litsea glutinosa
|
潺槁樹
|
4
|
Plumeria rubra
|
雞蛋花
|
4
|
Podocarpus macrophyllus
|
羅漢松
|
4
|
Reevesia thyrsoidea
|
梭羅樹
|
4
|
Styrax suberifolius
|
栓皮安息香
|
4
|
Washingtonia robusta
|
華盛頓葵
|
4
|
Lagerstroemia speciosa
|
大花紫薇
|
3
|
Machilus velutina
|
絨毛潤楠
|
3
|
Melia azedarach
|
楝
|
3
|
Pandanus utilis
|
馬達加斯加露兜
|
3
|
Schefflera actinophylla
|
傘樹
|
3
|
Alangium chinense
|
八角楓
|
2
|
Albizia lebbeck
|
大葉合歡
|
2
|
Aquilaria sinensis
|
土沉香
|
2
|
Bombax ceiba
|
木棉
|
2
|
Celtis timorensis
|
假玉桂
|
2
|
Clausena lansium
|
黃皮
|
2
|
Juniperus chinensis
|
圓柏
|
2
|
Ligustrum lucidum
|
女貞
|
2
|
Neodypsis decaryi
|
三角椰子
|
2
|
Rhaphiolepis indica
|
石斑木
|
2
|
Trema tomentosa
|
山黃麻
|
2
|
Aleurites moluccana
|
石栗
|
1
|
Artocarpus hypargyreus
|
白桂木
|
1
|
Bauhinia variegata
|
宮粉羊蹄甲
|
1
|
Bougainvillea spectabilis
|
簕杜鵑
|
1
|
Celtis biondii
|
紫彈朴
|
1
|
Cinnamomum burmannii
|
陰香
|
1
|
Citrus maxima
|
柚
|
1
|
Diospyros morrisiana
|
羅浮柿
|
1
|
Dracaena concinna
|
紅邊龍血樹
|
1
|
Dracaena marginata
|
紅邊鐵樹
|
1
|
Duranta erecta
|
假連翹
|
1
|
Eurya nitida
|
細齒葉柃
|
1
|
Fraxinus insularis
|
苦櫪木
|
1
|
Ilex pubescens
|
毛冬青
|
1
|
Jatropha pandurifolia
|
琴葉珊瑚
|
1
|
Machilus chekiangensis
|
浙江潤楠
|
1
|
Malus sp.
|
薔薇科萍果屬
|
1
|
Michelia x alba
|
白蘭
|
1
|
Pandanus tectorius
|
露兜樹
|
1
|
Pyrus sp.
|
薔薇科梨屬
|
1
|
Rhus chinensis
|
鹽膚木
|
1
|
Sapium discolor
|
山烏桕
|
1
|
Scolopia saeva
|
廣東刺柊
|
1
|
Sinosideroxylon wightianum
|
革葉鐵欖
|
1
|
|
Total:
|
3,167
|
Recommended Treatment of Existing Trees
Among the 3,167
nos. of trees identified in the tree survey, 1,418 of them are not in direct
conflict with the proposed works and can be retained and preserved on site. For
the remaining 1,749 trees, 70 of them are dead trees which are proposed to be
removed; 1 of them is proposed to be retained on site with pruning due to
conflict of part of the tree with the proposed works; 65 of them are proposed
to be transplanted. The remaining 1,613 trees are not suitable to be
transplanted and therefore proposed to be felled for the implementation of the
proposed works.
Compensatory Tree Planting Proposal
Among the 1,613 trees to be felled, 84 of them are
Leucaena leucocephala, which is a
self-seeded invasive undesirable species preventing the natural succession of
native vegetation. Owing to the invasive nature, the loss of Leucaena leucocephala will only be
compensated in term of number but not in DBH. Compensatory tree planting
proposal is therefore required for the compensation of the 1,613 nos. of felled
trees and the aggregated DBH of 290.02m.
The large number and DBH of the affected trees are
due to the significant density of the existing trees. A high percentage of
these affected trees were originally planted as whip trees with small spacing
in support of Ocean Parks earlier use of the site for tourist attractions.
They were planted some time ago and have since developed into trees of large
DBH. Therefore, trees affected by this Project are large in number and
aggregated DBH despite the small vegetated area being affected. To allow
sufficient space for future healthy growth and establishment of the
compensatory trees, a minimum of approximately 4m spacing between proposed
compensatory heavy standard trees will be provided. However, such provision of
suitable spacing limits the number of on-site tree compensation.
Provision of on-site tree compensation is
constrained by a few factors, such as the limited available space within the
Project boundary. A significant proportion of the compensatory tree planting
for this Project is required to be whip tree planting as the existing natural
terrain is very steep, and re-formed / stabilised slopes can only be planted
with whip trees. On-site compensatory tree planting is also restricted on the
ground level along the coastal area due to insufficient soil depth because of
high basement level.
The density of the existing tree planting in areas
unaffected by the Project and adjoining the site is already high. Therefore,
there are very limited opportunities for additional tree planting. Most of these
areas are on steep slopes and not suitable for tree planting, but whip tree
planting may be feasible. However, many of these areas, both within and
adjoining the Project boundary, are already earmarked for compensatory tree
planting for the Repositioning project.
Despite the site constraint, on-site compensatory
tree planting will be provided as far as practicable to compensate for the
proposed felling of 1,613 nos. of existing trees with aggregated DBH of 290.02m
for this Project. The maximised on-site tree compensation will consist of
approximately 608 nos. of heavy standard trees and approximately 18,202 nos. of
whip trees. The numbers and locations of compensatory trees would be determined
and agreed with relevant authorities in the tree removal application process
under LAO PN No. 7/2007 - Tree Preservation and Tree Removal Application for
Building Development in Private Projects.
Part of the compensatory tree planting area for
the Repositioning project of Ocean Park is within the Project boundary of this
Project and will be affected. Therefore,
among the proposed compensatory trees, 227 nos. of heavy standard trees and 109
nos. of whip trees are considered compensatory planting for the Repositioning
project. The remaining 381 nos. of heavy standard trees and 18,093 nos. of whip
trees are considered compensatory planting for the loss of 1,613 nos. of trees
due to this Project.
This results in a compensation ratio of 1:11.45 in
terms of tree number. Since a significant number of proposed compensatory trees
are whip trees, an alternative view on the level of compensatory planting
provision could consider 10 whip trees at 0.01m DBH being equivalent to one
heavy standard tree at 0.1m DBH in terms of number. This would mean that the
total number of 18,093 whip trees could be considered to be equivalent to 1,809
heavy standard trees in terms of number. This calculation method results in a
compensation ratio of 1:1.36 in terms of tree number. In terms of girth size,
the aggregated DBH of proposed compensatory trees for this Project is 219.03m
(38.1m+180.93m), which results in a compensation ratio of 1:0.76 in DBH.
Other than on-site tree compensation, off-site
compensation will be further explored as far as practicable within the lot
boundary of Ocean Park, such as at the area currently occupied by the project
site office. Approximately 1,700 m2
could be vacated at the existing project site office at Nam Long Shan Road
which has a potential of accommodating approximately 120 nos. of heavy standard
trees. With the addition of 120 nos. of heavy standard trees, the compensation
ratio will increase from 1:1.36 to 1:1.43 in terms of number, and from 1:0.76
to 1:0.80 in terms of DBH.
Notwithstanding the
above, OPC will further explore suitable locations for off-site compensation
outside Ocean Park as far as practicable. The availability of off-site
locations for tree compensation is subject to further investigation and
agreement with relevant authorities.
12.7
Baseline Study
Aerial photograph showing the extent of the Project Area
and the Landscape Impact Assessment Area is presented in Figure 12.4.
LR1.1 Tall shrubland
This LR is approximately 7.42ha in size. It is mainly
located along the west-facing down slope of Nam Long Shan east of the Project
area. This LR is co-dominated by shrubs
and trees. Dominant species include Acronychia pedunculata, Alangium chinense, Aporusa dioica, Breynia
fruticosa, Bridelia tomentosa, Celtis sinensis, Cratoxylum cochinchinense, Dalbergia
hancei, Diospyros vaccinioides, Ilex asprella, Litsea glutinosa, Litsea
rotundifolia, Macaranga tanarius,
Mallotus paniculatus, Melastoma sanguineum, Microcos nervosa, Polyspora axillaris, Rhaphiolepis
indica, Rhodomyrtus tomentosa, Rhus hypoleuca, Rhus succedanea, Sageretia
thea, Schima superb, Sinosideroxylon wightianum and Sterculia lanceolata. There are
approximately 1,000 trees in this LR with heights mainly range from 3m to
5m. This type of landscape resource is
common in this area. The amenity value
of this LR is medium. Since this LR is
natural and semi-mature, sensitivity is considered medium.
LR1.2
Shrubland
This LR is approximately 43.72ha in size. It is located on the upper slopes of Brick
Hill and the coastal hill slopes east and south of Ocean Park. This LR is dominated by shrubs and herbaceous
plants, with Polyspora axillaris
being the dominant species. Other common
species include Acronychia pedunculata,
Aporusa dioica, Baeckea frutescens, Breynia fruticosa, Cratoxylum cochinchinense,
Cyclobalanopsis myrsinifolia, Dalbergia hancei, Diospyros vaccinioides, Ilex
asprella, Litsea rotundifolia, Mallotus paniculatus, Melastoma sanguineum,
Melodinus suaveolens, Phyllanthus cochinchinensis, Polyspora axillaris,
Rhaphiolepis indica, Rhodomyrtus tomentosa, Rhus hypoleuca, Rhus succedanea,
Sageretia thea, Schima superb, Sinosideroxylon wightianum, Strophanthus
divaricatus, and Strychnos
angustiflora. Heights of vegetation predominantly range from 1m to 2m. There are approximately 900 trees in this LR.
This type of landscape resource is common in this area. The amenity value of this LR is medium. Since this LR is natural and semi-mature,
sensitivity is considered medium.
LR1.3
Hillside grassland
This LR is approximately 0.89ha in size. It is artificially established and maintained
on the eastern hillside. This LR is
dominated by the grass species Paspalum
notatum which is widely used for hydroseeding. Other floral species include Melastoma malabathricum, Melastoma sanguineum, Rhodomyrtus tomentosa and Polyspora axillaris. This
type of landscape resource is common in this area. The amenity value of this LR is low. Since this LR is young, artificially
maintained and easily replaceable, sensitivity is considered low.
LR1.4 Woodland
This LR is approximately 8.78ha in size. It is mainly
located along the down slope of Nam Long Shan north and northwest of the
Project area. This LR is dominated by
young trees. Dominant species include Acronychia pedunculata,
Alangium chinense, Aporusa dioica, Bridelia tomentosa, Celtis sinensis,
Cratoxylum cochinchinense, Mallotus paniculatus, Pinus massoniana, Polyspora
axillaris, Psychotria asiatica, Rhus hypoleuca, Rhus succedanea, Schima superb and Sterculia
lanceolata. There are approximately 5,500 trees in this LR with heights mainly
range from 6m to 10m. This type of
landscape resource is common in Hong Kong.
The amenity value of this LR is high.
Since this LR is natural and dominated by young trees, sensitivity is
considered high.
LR2.1
Planting on modified slopes
This LR is approximately 6.56ha in size. It is predominately located on slopes around
Flamingo Pond and Bird Paradise. It is
dominated by exotic tree plantation with Acacia
auriculiformis, Acacia confusa, Casuarina equisetifolia and Eucalyptus citriodora. The weedy tree species Leucaena leucocephala is also very common in this LR. There are approximately 3,700 trees in this
LR with heights mainly range from 10m to 16m.
This type of resource is very common in this area. The amenity value for this LR is medium. Although this LR is artificial, it is
semi-mature with high vegetation coverage.
Sensitivity is therefore considered medium.
LR2.2
Roadside planting
This LR is approximately 0.24ha in size. It includes young to semi-mature trees and
amenity shrub planting along Shum Wan Road.
Dominant tree species include Archontophoenix
alexandrae, Ficus microcarpa and Cinnamomum camphora and dominant shrubs
include Ficus microcarpa Golden
Leaves. There are approximately 100
trees with heights range from 9m to 12m in this LR. This type of landscape is very common in the
area. The amenity value of this resource
is medium. Although this LR is
artificial, trees in this LR are semi-mature and properly maintained. Sensitivity is therefore considered medium.
LR2.3
Amenity planting
This LR is approximately 3.44ha in size. It includes the amenity tree and shrub
planting inside Ocean Park. Dominant
species include Acacia confusa, Alternanthera philoxeroides, Cyperus involucratus, Hibiscus rosa-sinensis, Ixora chinensis, Livistona chinensis, Macaranga
tanarius, Philodendron selloum, Phyllanthus myrtifolius and Wedelia trilobata. There are approximately 2,100 trees in this
LR with heights range from 5m to 18m. This
type of landscape is common in this area.
Although the amenity value of this LR is high with well-maintained
landscape planting, it is easily replaceable.
Sensitivity is therefore considered medium.
LR3.1
Floral species of conservation interest
There are a total of 17 floral species of conservation
interest within the Landscape Impact Assessment Area, namely Ania hongkongensis, Aristolochia thwaitesii, Artocarpus
hypargyreus, Arundina graminifolia,
Brainea insignis, Cymbidium ensifolium, Eulophia graminea, Geodorum densiflorum, Goodyera
viridiflora, Habenaria dentate, Habenaria linguella, Ixonanthes reticulate, Lilium brownie, Peristylus calcaratus, Platycodon
grandiflorus, Spathoglottis pubescens
and Spiranthes hongkongensis. These floral species are all found in natural
habitats and the majority of them are locally uncommon or rare. Many of these floral species of conservation
interest have visually attractive flowers.
The amenity value of this resource is high. Due to its rarity, its sensitivity is
considered high.
LR4.1
Coastal open water
This LR is approximately 43.30ha in size. It includes the open waters in Aberdeen South
Typhoon Shelter and Aberdeen Channel.
The water quality of this resource is high with clean and clear seawater
with little floating refuse. This type
of landscape is common in the area. The
amenity value of this resource is high.
Due to its susceptibility to potential impacts from deteriorated water
quality, sensitivity of this LR is considered high.
LR4.2
Pond
This LR is approximately 0.25ha in size. It includes two disused man-made ponds with
well-defined artificial banks, which were previously used as Flamingo Pond
and Bird Paradise Pond, and a pond in the Japanese-style garden Garden of
Joy within Ocean Park. Water is
observed flowing from streams into the Flamingo Pond and Bird
Paradise. The water quality of these
two ponds is moderate with water visibly turbid. Fish is observed in these two ponds. For the pond in Garden of Joy, water
quality is good with visible clear water.
Overall, this type of landscape is uncommon in the local context but
common in the regional context. The
amenity value of this resource is medium.
Sensitivity is considered medium.
LR4.3
Stream
This LR is approximately 0.16ha in size. It includes two rocky streams within the
Project area, one flowing from the east, another from the north on the hill
slope of Brick Hill. The eastern one was
observed to be of flowing water throughout the wet and dry seasons and is the
main water source feeding the ponds inside the Ocean Park. The northern stream is seasonal. Both streams are partially modified as pipe
culvert or box culvert with a length of approximately 250m remaining
natural. Water quality in these two
streams is good and visibly clear. Small
sections of modified streams are also found north of the Project area beside
Shum Wan Road. This type of landscape is
common in the area. The amenity value of
this resource is medium. Since the
streams have limited water flow, sensitivity is considered medium.
LR5.1
Natural coastline
This LR is approximately 1.3km in length. It is located along the eastern side of
Aberdeen Channel, extending from the south of the bay of TSW along Sham Shui
Kok to the western side of Deep Water Bay at the Headland Area. This exposed shore comprises bedrock and
large boulders. This type of landscape
is common in the area. The amenity value
of this resource is medium. Although
locally common, this LR is natural and not readily replaceable. The sensitivity is therefore considered high.
Landscape Character Areas
Five LCAs have been identified within the Landscape Impact
Assessment Area. LCAs are mapped and
illustrated on Figure 12.7. Photographs of LCAs are shown in Figure 12.8.
LCA1
Theme park
This LCA is approximately 51.42ha in size. It comprises Ocean Park which includes a
variety of recreational features, such as rides, buildings and structures in
different shapes, colours, styles and scales.
Well-maintained amenity tree and shrub planting is also common in this
LCA. These features in this LCA form a
distinct, complex landscape character which is colourful and
heterogeneous. This type of landscape
character is uncommon in the local context but common in the regional
context. The amenity value is considered
high. Since this LCA is mostly
artificial and easily replaceable, even though its amenity value is high,
sensitivity is considered medium.
LCA2
Natural hillside
This LCA is approximately 37.51ha in size. It is located north and east of the Project
area, mainly on hill slopes of Brick Hill.
This LCA consists of hillsides, knolls, streams, ridges and spurs. It is dominated by shrubby type of vegetation
with occasional rock outcrops. Man-made
features such as footpaths, roads, retaining walls and modified slopes are also
present. As this LCA is dominated by
natural vegetation and natural coastline, the amenity value is high. Its sensitivity is also considered high since the natural landscape can hardly be
replaced once disturbed.
LCA3
Open water
This LCA is approximately 42.47ha in size. It includes part of the Aberdeen
Channel. This LCA is open sea partially
enclosed by landmasses on the west and east side. Ferry traffic and recreational waterborne
activities are present in low frequencies.
As this LCA is dominated by natural open sea with infrequent human
activities, the amenity value is high.
Sensitivity is also considered high due to its susceptibility to potential impacts from deteriorated water
quality.
LCA4
Typhoon shelter
This LCA is approximately 12.67ha in size. It is bordered by urban coastline on the
north side and surrounded by stone armoured breakwaters on the south side. Vessels in this typhoon shelter include
freighters, fishing boats, pleasure crafts and sampans. Other features such as jetties, pontoons and
navigational features are also found in this LCA. Though the landscape is dominated by open
water, human activities are intensive with vessels forming a substantial part
of the landscape. Amenity value of this
LCA is medium. Sensitivity is also
considered medium due to frequent
human activities within this LCA.
LCA5
Urban non-residential development
This LCA is approximately 7.57ha in size. It is dominated by low-rise non-residential
development such as Po Chong Wan Industrial Area, shipyards, Shum Wan Laundry,
Victoria Shanghai Academy and Hong Kong Juvenile Care Centre. Amenity and roadside planting are scattered
in this LCA. As this LCA is largely
developed with few landscape features, the amenity value is low. Sensitivity is also considered low.
Table 12.4 and Table 12.5 summarise the sensitivity of all LRs and LCAs.
Table 12.4: Sensitivity
of Landscape Resources
ID No.
|
Name
|
Quality
of existing landscape (Low / Medium / High)
|
Importance
/ Rarity of landscape elements (Low / Medium / High)
|
Ability
to accommodate change (Low / Medium / High)
|
Maturity
of Landscape (Young / Semi-mature / Mature)
|
Significance
of change in local context (Low / Medium / High)
|
Significance
of change in regional context (Low / Medium / High)
|
Sensitivity
(Low / Medium / High)
|
LR1.1
|
Tall shrubland
|
Medium
|
Low
|
Medium
|
Semi-mature
|
Medium
|
Low
|
Medium
|
LR1.2
|
Shrubland
|
Medium
|
Low
|
Medium
|
Semi-mature
|
Medium
|
Low
|
Medium
|
LR1.3
|
Hillside
grassland
|
Low
|
Low
|
High
|
young
|
Low
|
Low
|
Low
|
LR1.4
|
Woodland
|
Medium
|
Low
|
Low
|
Semi-mature
|
High
|
Medium
|
High
|
LR2.1
|
Planting on modified slopes
|
Medium
|
Low
|
Medium
|
Semi-mature
|
Medium
|
Low
|
Medium
|
LR2.2
|
Roadside planting
|
Medium
|
Low
|
Medium
|
Semi-mature
|
Medium
|
Low
|
Medium
|
LR2.3
|
Amenity planting
|
High
|
Low
|
High
|
Semi-mature
|
Medium
|
Low
|
Medium
|
LR3.1
|
Floral species of conservation
interest
|
High
|
High
|
Low
|
Mature
|
Medium
|
High
|
High
|
LR4.1
|
Coastal open water
|
High
|
Low
|
Low
|
Mature
|
High
|
Medium
|
High
|
LR4.2
|
Pond
|
Medium
|
Medium
|
Low
|
Semi-mature
|
Medium
|
Low
|
Medium
|
LR4.3
|
Stream
|
Medium
|
Low
|
Medium
|
Semi-mature
|
Medium
|
Low
|
Medium
|
LR5.1
|
Natural coastline
|
Medium
|
Low
|
Low
|
Mature
|
High
|
Medium
|
High
|
Table 12.5: Sensitivity of Landscape Character Areas
ID No.
|
Name
|
Quality of existing landscape (Low / Medium /
High)
|
Importance / Rarity of landscape elements (Low /
Medium / High)
|
Ability to accommodate change (Low / Medium /
High)
|
Maturity of Landscape (Young / Semi-mature /
Mature)
|
Significance of change in local context (Low /
Medium / High)
|
Significance of change in regional context (Low
/ Medium / High)
|
Sensitivity (Low / Medium / High)
|
LCA1
|
Theme park
|
High
|
High
|
High
|
Semi-mature
|
Medium
|
Low
|
Medium
|
LCA2
|
Natural hillside
|
High
|
Low
|
Low
|
Semi-mature
|
High
|
Medium
|
High
|
LCA3
|
Open water
|
High
|
Low
|
Low
|
Mature
|
High
|
Medium
|
High
|
LCA4
|
Typhoon shelter
|
Medium
|
Medium
|
Medium
|
Semi-mature
|
Medium
|
Low
|
Medium
|
LCA5
|
Urban non-residential
development
|
Low
|
Low
|
High
|
Semi-mature
|
Low
|
Low
|
Low
|
Visual Envelope and Zone of
Visual Influence
The visual envelope (VE) for the Project area is largely defined
by natural topography on the north, east and south sides. To the west side of the Project area, the VE
is mostly confined by hills of Yuk Kwai Shan and Ap Lei Pai. Within this VE, the extent of existing views
is determined by factors such as the presence of intervening visual obstacles,
such as buildings and roadside trees.
The VE is mapped on Figure 12.2.
Visual Sensitive Receivers
Fourteen VSRs have been identified within the VE. These VSRs are mapped and illustrated in Figure 12.2. Photographs
showing the existing views of the Project area from the VSRs are shown in Figure 12.9a to Figure 12.9b.
VSR1.1
Residents at Larvotto
There are 9 residential building blocks ranging from 25 to
29 floors in Larvotto on the west side of Ap Lei Chau Praya Road. Block 1 has the most direct and unobstructed
view of the Project area. The shortest
viewing distance is approximately 700m.
The existing view as shown in Figure 12.9a was taking from
the Sky Garden on the 19th floor of Block 1, Larvotto, which could
represent the clearest view of the Project area among all residents
in this VSR. Since the sensitive
receivers are residents and the existing view of the Project area is unobstructed, the sensitivity of this VSR is therefore considered high.
VSR1.2
Residents at Lei Tung Estate
In Lei Tung Estate, the views of the Project area from most residents are substantially blocked by buildings (e.g. those
of Larvotto) or natural topography (e.g. Yuk Kwai Shan). The relatively unobstructed views are visible
from Tung Yat House with a viewing distance of approximately 1,000m and
substantial blockage by Block 1, Larvotto, as shown in Figure 12.9a. With the long viewing distance and the
substantial blockage of view, the sensitivity of this VSR is considered low even though the sensitive receivers are
residents.
VSR2.1
Workers at Ocean Park
This VSR includes all the working staff, both indoor and
outdoor workers, of the Ocean Park. In
most parts of the Ocean Park, the view of the Project area is substantially blocked by existing vegetation. The clearest view of the Project area is observable from near the Mine Train with a viewing distance of
approximately 50m, which is a shared view with VSR2.2 and shown in Figure 12.9a. In places where access by park visitors is
restricted, the Project area is visible from
the Staff Canteen with a viewing distance of approximately 100m as shown in Figure 12.9a. Such view is not visible when sitting down
but only observable when standing next to the windows. As the sensitive receivers are workers, the
visual perception is not very important and does not have a significant effect
on their quality of life. Also, they
will overlook the site from a significant height (>50m) and not from the same
level. The sensitivity of this VSR is
therefore considered low.
VSR2.2
Staff and temporary residents at the planned Spa Hotel
The planned location of the Spa Hotel is at the location of
the existing Mine Train. Information
such as the layout and height of this planned hotel is yet not available. The existing view as shown in Figure 12.9a was taken from the
footpath beside the Mine Train to represent the view from the location of the
planned Spa Hotel at a height of approximately 80m with a horizontal viewing
distance of approximately 10m. The
existing view of the Project area is partially
obstructed by vegetation on the slope beside the footpath. As the sensitive receivers are workers and
temporary residents, the visual perception is not very important and does not
have a significant effect on their quality of life. Also, they will overlook the site from a
significant height (>50m) and not from the same level. The sensitivity of this VSR is therefore
considered low.
VSR2.3
Staff and temporary residents at the planned Fisherman's Wharf Hotel
The planned location of the Fishermans Wharf Hotel is next
to the TSW entrance of the Ocean Park.
Information such as the layout and height of this planned hotel is yet
not available. The existing view as
shown in Figure 12.9a was taken from the footpath beside the planned
Fishermans Wharf Hotel to represent the view from the planned Fishermans
Wharf Hotel at ground level from within the Project area. The existing view of the
Project area is partially obstructed by roadside trees. However, the visual obstruction by roadside
trees will be less substantial when viewing from a significant height at the
same location. As the sensitive
receivers are workers and temporary residents, the visual perception is not
very important and does not have a significant effect on their quality of
life. The sensitivity of this VSR is
therefore considered low.
VSR2.4
Workers at shipyards along the east coast of Yuk Kwai Shan
This VSR is located along the coastline between Yuk Kwai
Shan and Aberdeen South Typhoon Shelter.
Views of the Project area from this VSR are
often obstructed by the breakwaters and the vessels within the typhoon shelter,
with a viewing distance of approximately 700m as shown in Figure 12.9a. As the sensitive receivers are workers, the
visual perception is not very important and does not have a significant effect
on their quality of life. Also, the
views of the Project area are often
obstructed. The sensitivity of this VSR
is therefore considered low.
VSR3.1
Recreational users in Ocean Park
This VSR includes all the recreational users of the Ocean
Park. In most parts of the Ocean Park,
the view of the Project area is substantially
blocked by existing vegetation. Similar
to VSR2.2, a clear view of the Project area is observable from
near the Mine Train with a viewing distance of approximately 50m as shown in Figure 12.9a. Also, at the Ocean Park Tower, a clear
unobstructed view of the Project area is also visible
with a viewing distance of approximately 200m as shown in Figure 12.9a. As the sensitive receivers are
recreationists, the visual perception is not very important and does not have a
significant effect on their quality of life.
Also, they will overlook the site from a significant height (>50m)
and not from the same level. The
sensitivity of this VSR is therefore considered low.
VSR3.2
Hikers on Yuk Kwai Shan
This VSR includes hikers on the footpaths of Yuk Kwai
Shan. At most locations along the
footpath, the natural hillside dominates the foreground view with the Project area visible in the background. The
most unobstructed views of the Project area are available from
the hill top with a viewing distance of approximately 1,000m as shown in Figure 12.9a. As the sensitive receivers are outdoor
leisure activity participants, the quality of views are important for their
enjoyment. However, given the long
viewing distance and the transient nature of the views along the hiking trail,
the sensitivity of this VSR is considered medium. In night-time,
hiking activities are not expected on this hiking trail because this trail is
steep, not properly paved and not equipped with any lighting. The sensitivity is therefore considered low for night-time.
VSR3.3
Hikers on the beach between Yuk Kwai Shan and Ap Lei Pai
The VSR is located between Yuk Kwai Shan and Ap Lei
Pai. It includes not only the hikers
going from Yuk Kwai Shan to Ap Lei Pai but also recreationists fishing on the
rocky shore. To the east, the Project area is clearly visible with no obstruction as shown in Figure 12.9a. The viewing distance is approximately
800m. Views of open waters are also
available to the west. As the sensitive
receivers are outdoor leisure activity participants, the quality of views are
important for their enjoyment. However,
given the long viewing distance, the short duration of views and the
availability of similar alternative views, the sensitivity of this VSR is
considered medium. In night-time, hiking activities are not expected
on this hiking trail because this trail is steep, not properly paved and not
equipped with any lighting. The
sensitivity is therefore considered low for night-time.
VSR3.4
Hikers on Ap Lei Pai
This VSR includes hikers on the footpaths of Ap Lei
Pai. At most locations along the
footpath, the natural hillside dominates the foreground view with the Project area visible in the background. The
most unobstructed views of the Project area are available from
the hill top with a viewing distance of approximately 700m as shown in Figure 12.9b. As the sensitive receivers are outdoor
leisure activity participants, the quality of views are important for their
enjoyment. However, given the long
viewing distance and the transient nature of the views along the hiking trail,
the sensitivity of this VSR is considered medium. In night-time,
hiking activities are not expected on this hiking trail because this trail is
steep, not properly paved and not equipped with any lighting. The sensitivity is therefore considered low for night-time.
VSR3.5
Hikers on Brick Hill
This VSR includes hikers on the footpaths of Brick
Hill. At most locations along the
footpaths, the Project area is visually
blocked by the natural hill slopes and vegetation. The most unobstructed views of the Project area are available along the footpath from Nam Long Shan Road Rest Garden
to the hill top of Nam Long Shan with a viewing distance of approximately 100m
to 700m as shown in Figure 12.9b. As the
sensitive receivers are outdoor leisure activity participants, the quality of
views are important for their enjoyment.
However, given the short duration of the views along the hiking trail,
the sensitivity of this VSR is considered low.
VSR4.1
Travellers along Shum Wan Road
The VSR includes all the travellers, including drivers,
passengers and pedestrians along Shum Wan Road, part of which is within the
Project area. The existing view
as shown in Figure 12.9b was taken from approximately 130m from the
Project area where visual obstruction by roadside trees is
minimal. Part of Shum Wan Road is within
the Project area. The shortest
viewing distance is approximately 120m.
As the sensitive receivers are travellers and the views are partially
blocked in most parts along Shum Wan Road, the sensitivity of this VSR is
considered low.
VSR4.2
Travellers along Ap Lei Chau Praya Road
This VSR includes motorists, passengers and pedestrians
along Ap Lei Chau Praya Road. Since the
east side of Ap Lei Chau Praya Road is dominated by building structures of
shipyards, the Project area is barely visible by travellers along Ap Lei Chau
Praya Road except at the end of the road near the roundabout, where the views
of the Project area is sometimes partially obstructed by vessels in the typhoon
shelter as shown in Figure 12.9b. The
viewing distance of the Project area from this roundabout is approximately
700m. As the sensitive receivers are
travellers and the views are substantially blocked in most parts along Ap Lei
Chau Praya Road, the sensitivity of this VSR is considered low.
VSR4.3
Boat users in Aberdeen Channel
This VSR includes sensitive receivers on boats in the
Aberdeen Channel. Views of the Project
area from this VSR are unobstructed with a shortest viewing distance of
approximately 200m. The existing view as
shown in Figure 12.9b was taken from the end of the southern breakwater
of Aberdeen South Typhoon Shelter to represent the views of the boat
users. Although the Project area is
clearly observable with no obstruction, since the sensitive receivers are
travellers and the views are transient in nature, the sensitivity of this VSR
is considered low.
Table 12.6 summarises the description and sensitivity of selected
VSRs to accommodate changes.
Table 12.6: Sensitivity
of Visual Sensitive Receivers
ID No.
|
VSR Name
|
Type of Receivers (Residents / Students /
Workers / Recreationists / Travellers)
|
Population of Receivers (Small / Medium / Large)
|
Amenity Value of Existing View (Low / Moderate /
High)
|
Availability of Alternative View (Yes / No)
|
Amenity of Alternative View (Low / Moderate /
High)
|
Duration of view (Short / Medium / Long)
|
Frequency of view (Low / Medium / High)
|
Degree of visibility (Low / Medium / High)
|
Sensitivity (Low / Medium / High)
|
VSR1.1
|
Residents at Larvotto
|
Residents
|
Large
|
High
|
Yes
|
Medium
|
Long
|
High
|
High
|
High (daytime and night-time)
|
VSR1.2
|
Residents at Lei Tung Estate
|
Residents
|
Large
|
Medium
|
Yes
|
Medium
|
Long
|
High
|
Low
|
Low (daytime and night-time)
|
VSR2.1
|
Workers at Ocean Park
|
Workers
|
Medium
|
Medium
|
Yes
|
Medium
|
Long
|
Low
|
Low
|
Low (daytime and night-time)
|
VSR2.2
|
Staff and temporary residents
at the planned Spa Hotel
|
Workers and
temporary residents
|
Large
|
Medium
|
Yes
|
Medium
|
Long
|
Medium
|
Medium
|
Low (daytime and night-time)
|
VSR2.3
|
Staff and temporary residents
at the planned Fisherman's Wharf Hotel
|
Workers and temporary residents
|
Large
|
Medium
|
Yes
|
Medium
|
Long
|
Medium
|
High
|
Low (daytime and night-time)
|
VSR2.4
|
Workers at shipyards along the
east coast of Yuk Kwai Shan
|
Workers
|
Small
|
Medium
|
Yes
|
Low
|
Medium
|
Low
|
Medium
|
Low (daytime and night-time)
|
VSR3.1
|
Recreational users in Ocean
Park
|
Outdoor leisure
activity participants
|
Large
|
Medium
|
Yes
|
Medium
|
Short
|
Medium
|
Low
|
Low (daytime and night-time)
|
VSR3.2
|
Hikers on Yuk Kwai Shan
|
Outdoor leisure activity
participants
|
Small
|
High
|
Yes
|
High
|
Medium
|
High
|
High
|
Medium in daytime;
low in night-time
|
VSR3.3
|
Hikers on the beach between Yuk
Kwai Shan and Ap Lei Pai
|
Outdoor leisure activity
participants
|
Small
|
High
|
Yes
|
High
|
Medium
|
High
|
High
|
Medium in daytime;
low in night-time
|
VSR3.4
|
Hikers on Ap Lei Pai
|
Outdoor leisure activity participants
|
Small
|
High
|
Yes
|
High
|
Medium
|
High
|
High
|
Medium in daytime;
low in night-time
|
VSR3.5
|
Hikers on Brick Hill
|
Outdoor leisure activity
participants
|
Small
|
High
|
Yes
|
High
|
Short
|
Medium
|
Medium
|
Low (daytime and night-time)
|
VSR4.1
|
Travellers along Shum Wan Road
|
Travellers
|
Large
|
Medium
|
Yes
|
Medium
|
Short
|
Low
|
Medium
|
Low (daytime and night-time)
|
VSR4.2
|
Travellers along Ap Lei Chau
Praya Road
|
Travellers
|
Medium
|
Low
|
Yes
|
Medium
|
Short
|
Low
|
Low
|
Low (daytime and night-time)
|
VSR4.3
|
Boat users in Aberdeen Channel
|
Travellers
|
Small
|
Medium
|
Yes
|
High
|
Short
|
Low
|
High
|
Low (daytime and night-time)
|
Vantage Points
Photographs were taken from 7 selected vantage points to
show the representative visual context of VSRs.
These photographs are illustrated in Figures 12.12a to 12.12j.
Vantage
Point A from the hill top of Yuk Kwai Shan
This vantage point is selected to show the view of the
Project area from the hill tops visible by hikers. It represents the potentially most affected
view by VSR3.2 Hikers on Yuk Kwai Shan and VSR3.5 Hikers on Brick
Hill. The view is characterised by an
unobstructed view overseeing the Project area from a height of approximately
180m with a viewing distance of approximately 1,000m.
Vantage
Point B the beach between Yuk Kwai Shan and Ap Lei Pai
This vantage point is selected to show the direct view of
the Project area from sea level from the west.
It represents the most unobstructed view from the eastern shoreline of
Yuk Kwai Shan and Ap Lei Pai, which includes the potentially most affected view
of VSR3.3 Hikers on the beach between Yuk Kwai Shan and Ap Lei Pai. The viewing distance is approximately 800m.
Vantage
Point C from the hill top of Ap Lei Pai
This vantage point, which is taken from the hill top of Ap
Lei Pai, shows the view of the Project area from the most direct angle where
the entire Project area, rather than only part of the Project area, is directly
visible, with no obstruction and a viewing distance of approximately 700m. It represents the potentially most affected
view of VSR3.4 Hikers on Ap Lei Pai.
Vantage
Point D from the end of the southern breakwaters in Aberdeen South Typhoon
Shelter
This vantage point is selected to represent the views of
VSR4.3 Boat users in Aberdeen Channel with a viewing distance of
approximately 200m from the west. The
view of this vantage point is similar to that of vantage point B from a similar
direction toward the Project area, but with a shorter viewing distance which
better represent the views of boat users.
This vantage point could also represent the potentially most affected
view of VSR 2.4 Workers at shipyards along the east coast of Yuk Kwai Shan
and VSR4.2 Travellers along Ap Lei Chau Praya Road due to a similar direction
from the Project area and at similar levels.
Vantage
Point E from the Sky Garden on 19/F, Block 1, Larvotto
This vantage point is taken from the Sky Garden on the 19th
floor of Block 1, Larvotto. It shows the
potentially most affected view of VSR1.1 Residents at Larvotto, which is an
unobstructed view of the Project area from approximately 700m with an elevation
of approximately 90m. The potentially
most affected views from VSR1.2 Residents at Lei Tung Estate are similar to
that of this vantage point, but with longer viewing distance and substantial
visual obstruction by the residential buildings of Larvotto.
Vantage
Point F from the planned Fishermans Wharf Hotel
This vantage point is taken from the proposed location of
the planned Fishermans Wharf Hotel just outside the TSW entrance of the Ocean
Park beside Shum Wan Road. It shows the
existing view of the planned VSR2.3 Staff and temporary residents at the
planned Fisherman's Wharf Hotel from within the Project area. It also represents the close-up view of
VSR4.1 Travellers along Shum Wan Road.
Vantage
Point G from the planned Spa Hotel
This vantage point is selected to show the view of the
Project area from the planned VSR2.2 Staff and temporary residents at the
planned Spa Hotel. Since the Mine Train
is situated at the proposed location of the planned Spa Hotel, this vantage
point is taken from the footpath adjacent to the Mine Train to show an elevated
view from a height of approximately 80m from the ground level of the planned
Spa Hotel. This vantage point is also a
representative view of VSR2.1 Workers at Ocean Park and VSR3.1 Recreational
users in Ocean Park.
Sources of Potential Impacts
During the construction phase, sources of potential
landscape and visual impacts would arise from the following:
§ Site
clearance for the proposed structures, particularly at the existing woodland
and tall shrubland area.
During the operation phase, sources of potential landscape
and visual impacts would arise from the following:
§ Operation
of the Indoor Zone of the Water Park (with a wave pool, lazy river, play
structure, water slides, surf-rider, various pools, F&B facilities, E&M
utilities, back of house and car-parking;
§ Operation
of the Outdoor Zone of the Water Park (with a wave pool, lazy river, water
slides, ride platforms, various pools, sea turtle exhibit and some
small-scale F&B facilities; and
§ Operation
of the General Approach Area with coach and taxi drop-off point and EVA.
Magnitude
of Change for Landscape Resources
LR1.1 Tall shrubland
Approximately 0.11ha out of
7.42ha in this LR will be cleared for the proposed works of the Project. Approximately 1 Leucaena leucocephala and approximately 21 other trees (with
aggregated DBH of approximately 3.49m) out of 1,000 trees will need to be
removed. The magnitude of change for
this LR is expected to be adversely small.
LR1.2 Shrubland
Approximately 0.17ha out of
43.72ha in this LR will be cleared for the proposed works of the Project. Approximately 6 trees (with aggregated DBH of
approximately 0.75m) out of 900 trees will need to be removed. The magnitude of change for this LR is
expected to be adversely small.
LR1.3 Hillside grassland
This LR is located entirely
outside the Project area. Therefore, this LR is expected to have a negligible magnitude of change.
LR1.4 Woodland
Approximately 1.53ha out of
8.78ha in this LR will be cleared for the proposed works of the Project. Approximately 8 Leucaena leucocephala and 439 other trees (with aggregated DBH of
approximately 79.23m) out of 5,500 trees will need to be removed. The magnitude of change for this LR is
expected to be adversely large.
LR2.1 Planting on modified slopes
Approximately 0.28ha out of
6.56ha in this LR will be cleared for the proposed works of the Project. Approximately 158 trees (with aggregated DBH
of approximately 31.56m) out of 3,700 trees will need to be removed. The magnitude of change for this LR is
expected to be adversely intermediate.
LR2.2 Roadside planting
Approximately 0.09ha out of
0.24ha in this LR will be cleared for the proposed works of the Project. Approximately 43 trees (with aggregated DBH
of approximately 7.57m) out of 100 trees will need to be removed. The magnitude of change of this LR is
expected to be adversely large.
LR2.3 Amenity planting
Approximately 1.74ha out of
3.44ha in this LR will be cleared for the proposed works of the Project. Approximately 37 Leucaena leucocephala and 699 other trees (with aggregated DBH of
approximately 146.13m) out of 2,100 trees will need to be removed. The magnitude of change for this LR is
expected to be adversely large.
LR3.1 Floral species of conservation interest
Out of the 17 identified floral
species of conservation interest, only one of them, which is Platycodon grandiflorus, is found within the Project area. The Platycodon
grandiflorus is located at the southern end on the hillside of the Project area, which will not be directly affected by the construction activities. Hence, this LR is expected to have a negligible magnitude of change.
LR4.1 Coastal open water
This LR is located entirely
outside the Project area. Also, the Project does not involve any
reclamation, dredging or any seawall construction. Therefore, this LR is expected to have a negligible magnitude of change.
LR4.2 Pond
The Flamingo Pond and Bird
Paradise Pond within the Project area, covering
approximately 0.24ha out of 0.25ha in this LR, will be removed for the
commencement of this Project. The pond
in the Garden of Joy which is approximately 0.01ha outside the Project area will be unaffected by the proposed works of this Project. The magnitude of change for this LR is
expected to be adversely large.
LR4.3 Stream
The natural sections of
approximately 75m in length (out of 250m) of one of the two streams within the
Project area will be intercepted by the proposed structures and diverted to
drainage channels. Approximately 28m of
existing box culvert of the other stream will be demolished with flow diverted
to drainage pipe. Other parts of these
two streams and the streams outside the Project area will not be
affected. The magnitude of change for
this LR is expected to be adversely large.
LR5.1 Natural coastline
This LR is located entirely
outside the Project area. Also, the Project does not involve any
reclamation, dredging or any seawall construction. Therefore, this LR is expected to have a negligible magnitude of change.
Magnitude
of Change for Landscape Character Areas
LCA1 Theme park
Approximately 6.55ha out of
51.42ha in this LCA will be cleared for the proposed works of the Project. Approximately 84 Leucaena leucocephala and 1,529 other trees (with aggregated DBH of
approximately 290.02m) out of 6,000 trees will need to be removed. The magnitude of change for this LCA is
expected to be adversely large.
LCA2 Natural hillside
This LCA is located entirely
outside the Project area. Therefore, this LCA is expected to have a negligible magnitude of change.
LCA3 Open water
This LCA is located entirely
outside the Project area. Also, the Project does not involve any
reclamation, dredging or any seawall construction. Therefore, this LCA is expected to have a negligible magnitude of change.
LCA4 Typhoon shelter
This LCA is located entirely
outside the Project area. Also, the Project does not involve any
reclamation, dredging or any seawall construction. Therefore, this LCA is expected to have a negligible magnitude of change.
LCA5 Urban non-residential development
This LCA is located entirely
outside the Project area. Therefore, this LCA is expected to have a negligible magnitude of change.
Table 12.7 and Table 12.8
summarise the magnitude of change for all LRs and LCAs respectively. The magnitude of change for all LRs and LCAs
is expected to be the same for construction and operation phases.
Table 12.7: Magnitude of Change of Landscape Resources
ID No.
|
Name
|
Scale of Works (Negligible / Small / Medium /
Large)
|
Reversibility (Reversible / Irreversible)
|
Compatibility with surrounding landscape (Low /
Medium / High)
|
Duration of impacts (Short / Medium / Long)
|
Magnitude of Change (Negligible / Small / Intermediate / Large)
|
LR1.1
|
Tall Shrubland
|
Small
|
Irreversible
|
Medium
|
Long
|
Adversely small
|
LR1.2
|
Shrubland
|
Small
|
Irreversible
|
Medium
|
Long
|
Adversely small
|
LR1.3
|
Hillside
grassland
|
Negligible
|
N.A.
|
N.A.
|
N.A.
|
Negligible
|
LR1.4
|
Woodland
|
Medium
|
Irreversible
|
Low
|
Long
|
Adversely large
|
LR2.1
|
Planting on modified slopes
|
Medium
|
Irreversible
|
Medium
|
Long
|
Adversely intermediate
|
LR2.2
|
Roadside planting
|
Large
|
Irreversible
|
Medium
|
Long
|
Adversely large
|
LR2.3
|
Amenity planting
|
Large
|
Irreversible
|
Medium
|
Long
|
Adversely large
|
LR3.1
|
Floral species of conservation
interest
|
Negligible
|
N.A.
|
N.A.
|
N.A.
|
Negligible
|
LR4.1
|
Coastal open water
|
Negligible
|
N.A.
|
N.A.
|
N.A.
|
Negligible
|
LR4.2
|
Pond
|
Large
|
Irreversible
|
Low
|
Long
|
Adversely large
|
LR4.3
|
Stream
|
Large
|
Irreversible
|
Low
|
Long
|
Adversely large
|
LR5.1
|
Natural coastline
|
Negligible
|
N.A.
|
N.A.
|
N.A.
|
Negligible
|
Table 12.8: Magnitude of Change of Landscape Character
Areas
ID No.
|
Name
|
Scale of Works (Negligible / Small / Medium /
Large)
|
Reversibility (Reversible / Irreversible)
|
Compatibility with surrounding landscape (Low /
Medium / High)
|
Duration of impacts (Short / Medium / Long)
|
Magnitude of Change (Negligible / Small / Intermediate / Large)
|
LCA1
|
Theme park
|
Large
|
Irreversible
|
Medium
|
Long
|
Adversely large
|
LCA2
|
Natural hillside
|
Negligible
|
N.A.
|
N.A.
|
N.A.
|
Negligible
|
LCA3
|
Open water
|
Negligible
|
N.A.
|
N.A.
|
N.A.
|
Negligible
|
LCA4
|
Typhoon shelter
|
Negligible
|
N.A.
|
N.A.
|
N.A.
|
Negligible
|
LCA5
|
Urban non-residential
development
|
Negligible
|
N.A.
|
N.A.
|
N.A.
|
Negligible
|
Magnitude
of Change for Visual Sensitive Receivers during Construction
VSR1.1
Residents at Larvotto
The existing unobstructed view of the Project area, which
is largely dominated by dense vegetation, will change to a construction site
which is clearly visible in daytime by residents in Block 1, Larvotto. In night-time, the lighting from the Project
area will also be visible by this VSR.
However, since night-time construction activities are not expected, only
minimal lighting, which is similar to the existing lighting in the Project
area, is expected to be provided. The
magnitude of change is considered adversely small for daytime and night-time during the construction
phase.
VSR1.2
Residents at Lei Tung Estate
Since the existing view of this VSR is dominated by the
residential buildings of Larvotto, and the view of the Project area is barely
visible, the magnitude of change, both in the daytime and night-time, are
considered negligible during the
construction phase.
VSR2.1
Workers at Ocean Park
At locations where the Project area is visible within Ocean
Park, the existing view, which is largely dominated by dense vegetation, will
be replaced by the view of a construction site.
However, since the vegetation within the park often partially screens
the view of the Project area, the magnitude of change is considered adversely small during the
construction phase for both daytime and night-time.
VSR2.2
Staff and temporary residents at the planned Spa Hotel
Since the planned Spa Hotel is at a preliminary planning
stage, no construction programme is currently available. Construction of this hotel is not anticipated
to complete before completion of this Project.
This VSR will not be present during construction of this Project. Magnitude of change is therefore not
applicable to this VSR during construction phase.
VSR2.3
Staff and temporary residents at the planned Fisherman's Wharf Hotel
Since the planned Fishermans Wharf Hotel is at a
preliminary planning stage, no construction programme is currently
available. Construction of this hotel is
not anticipated to complete before completion of this Project. This VSR will not be present during
construction of this Project. Magnitude
of change is therefore not applicable to this VSR during the construction
phase.
VSR2.4
Workers at shipyards along the east coast of Yuk Kwai Shan
The existing view of the Project area, which is largely
dominated by dense vegetation but often partially obstructed by vessels in
Aberdeen South Typhoon Shelter, will change to a construction site which is
visible in daytime. In night-time, the
lighting from the Project area will also be partially visible by this VSR. However, since night-time construction
activities are not expected, only minimal lighting, which is similar to the
existing lighting in the Project area, is expected to be provided. Also, the lighting from vessels will be more
prominent than that from the Project area.
The magnitude of change is considered adversely small during the construction phase for both daytime and
night-time.
VSR3.1
Recreational users in Ocean Park
At locations where the Project area is visible within Ocean
Park, the existing view, which is largely dominated by dense vegetation, will
be replaced by the view of a construction site.
However, since the vegetation within the park often partially screens
the view of the Project area, the magnitude of change is considered adversely small during the
construction phase for both daytime and night-time.
VSR3.2
Hikers on Yuk Kwai Shan
The existing unobstructed view of the Project area, which
is largely dominated by dense vegetation, will change to a construction site
which is clearly visible in daytime. In
night-time, hiking activities are not expected on this hiking trail because
this trail is steep, not properly paved and not equipped with any
lighting. The magnitude of change is
therefore considered adversely
small
for daytime and night-time during construction.
VSR3.3
Hikers on the beach between Yuk Kwai Shan and Ap Lei Pai
The existing unobstructed view of the Project area, which
is largely dominated by dense vegetation, will change to a construction site
which is clearly visible in daytime. In
night-time, hiking activities are not expected on this hiking trail because
this trail is steep, not properly paved and not equipped with any
lighting. The magnitude of change is
therefore considered adversely
small
for daytime and night-time during construction.
VSR3.4
Hikers on Ap Lei Pai
The existing unobstructed view of the Project area, which
is largely dominated by dense vegetation, will change to a construction site
which is clearly visible in daytime. In
night-time, hiking activities are not expected on this hiking trail because
this trail is steep, not properly paved and not equipped with any lighting. The magnitude of change is therefore
considered adversely
small
for daytime and night-time during construction.
VSR3.5
Hikers on Brick Hill
The existing partially obstructed view of the Project area,
which is largely dominated by dense vegetation, will change to a construction
site which is clearly visible in daytime.
In night-time, hiking activities are not expected in most parts of the
hiking trails, but night-time visitors to the Nam Long Shan Road Rest Garden,
particularly in special occasions, such as the Mid-autumn Festival, is
expected. However, the overall number of
night-time visitors is expected to be low.
The magnitude of change is therefore considered adversely small for both daytime
and night-time during construction.
VSR4.1
Travellers along Shum Wan Road
The existing partially obstructed view of the Project area,
which is largely dominated by dense vegetation, will change to a construction
site which is clearly visible in daytime.
In night-time, the lighting from the Project area will also be visible
by this VSR. However, since night-time
construction activities are not expected, only minimal lighting, which is
similar to the existing lighting in the Project area, is expected to be
provided. The magnitude of change is
considered adversely
small
during the construction phase for both daytime and night-time.
VSR4.2
Travellers along Ap Lei Chau Praya Road
The existing view of the Project area, which is largely
dominated by dense vegetation, will change to a construction site which is
visible in daytime, but only near the end of Ap Lei Chau Praya Road near the
roundabout. In night-time, the lighting
from the Project area will also be partially visible by this VSR at the same
location. However, since night-time construction
activities are not expected, only minimal lighting, which is similar to the
existing lighting in the Project area, is expected to be provided. Also, the lighting from vessels will be more
prominent than that from the Project area.
The magnitude of change is considered adversely small during the construction phase for both daytime and
night-time.
VSR4.3
Boat users in Aberdeen Channel
Without mitigation, the existing unobstructed view of the
Project area, which is largely dominated by dense vegetation, will change to a
construction site which is clearly visible in daytime. In night-time, the lighting from the Project
area will also be visible by this VSR.
However, since night-time construction activities are not expected, only
minimal lighting, which is similar to the existing lighting in the Project
area, is expected to be provided. The
potential visual impact is considered slight adverse during the construction phase for both daytime and
night-time.
Magnitude
of Change for Visual Sensitive Receivers during Operation
VSR1.1
Residents at Larvotto
The existing unobstructed view of the Project area, which
is largely dominated by dense vegetation, will be replaced by the view of the
Water Park dominated by hard structures such as pools as shown in Figure
12.12e. In night-time, the lighting
from the Project will also be visible by this VSR. However, the overall lighting of the Water
Park is expected to be similar to the existing lighting in the Project area as
shown in Figure 12.12f. The
magnitude of change is considered adversely small for daytime and night-time during the operation
phase.
VSR1.2
Residents at Lei Tung Estate
Since the existing view of this VSR is dominated by the
residential buildings of Larvotto, and the view of the Project area is barely
visible. The magnitude of change, both
in the daytime and night-time, are considered negligible during the operation phase even without mitigation.
VSR2.1
Workers at Ocean Park
At locations where the Project area is visible within Ocean
Park, the existing view, which is largely dominated by dense vegetation, will
be replaced by the view of the predominant hard structures of the Water
Park. However, since the vegetation
within Ocean Park often partially screens the view of the Project area, the
magnitude of change is considered adversely small during the operation phase for both daytime and
night-time.
VSR2.2
Staff and temporary residents at the planned Spa Hotel
Since the planned Spa Hotel is at a preliminary planning
stage, no construction programme is currently available. Construction of this hotel is not anticipated
to complete before completion of this Project.
This VSR will not be present by Day 1 of operation. Magnitude of change is therefore considered
not applicable to this VSR by Day 1 of operation. However, by Year 10 of operation, it is
assumed that the Spa Hotel will have been in operation. The existing view of the Project area, which
is dominated by dense vegetation but partially blocked by existing vegetation,
will be replaced by the view of the predominant hard structures of the Water
Park as shown in Figure 12.12i and Figure 12.12j. The magnitude of change is considered adversely small by Year 10 of
operation for both daytime and night-time.
VSR2.3
Staff and temporary residents at the planned Fisherman's Wharf Hotel
Since the planned Fishermans Wharf Hotel is at a
preliminary planning stage, no construction programme is currently available. Construction of this hotel is not anticipated
to complete before completion of this Project.
This VSR will not be present by Day 1 of operation. Magnitude of change is therefore considered
not applicable to this VSR by Day 1 of operation. However, by Year 10 of operation, it is
assumed that the Fishermans Wharf Hotel will have been in operation. The existing view of the Project area, which
is dominated by dense vegetation but partially screened by roadside trees, will
be replaced by the view of the predominant hard structures of the Water Park as
shown in Figure 12.12g and Figure 12.12h. The magnitude of change is considered adversely small by Year 10 of
operation for both daytime and night-time.
VSR2.4
Workers at shipyards along the east coast of Yuk Kwai Shan
The existing view of the Project area, which is largely
dominated by dense vegetation but often partially obstructed by vessels in
Aberdeen South Typhoon Shelter, will change to the predominate hard structures
of the Water Park which is visible in daytime.
In night-time, the lighting from the Water Park will also be partially
visible by this VSR. However, the
lighting from vessels will be more prominent than that from the Water
Park. The magnitude of change is
considered adversely
small
during the operation phase for both daytime and night-time.
VSR3.1
Recreational users in Ocean Park
At locations where the Project area is visible within Ocean
Park, the existing view, which is largely dominated by dense vegetation, will
be replaced by the view of the predominant hard structures of the Water
Park. However, since the vegetation
within Ocean Park often partially screens the view of the Project area, the
magnitude of change is considered adversely small during the operation phase for both daytime and
night-time.
VSR3.2
Hikers on Yuk Kwai Shan
The existing unobstructed view of the Project area, which
is largely dominated by dense vegetation, will change to the predominant hard
structures of the Water Park which is clearly visible in daytime as shown in Figure
12.12a. In night-time, hiking
activities are not expected on this hiking trail because this trail is steep,
not properly paved and not equipped with any lighting. The magnitude of change is therefore
considered adversely
small
for daytime and night-time during operation.
VSR3.3
Hikers on the beach between Yuk Kwai Shan and Ap Lei Pai
The existing unobstructed view of the Project area, which
is largely dominated by dense vegetation, will change to the predominant hard
structures of the Water Park which is clearly visible in daytime as shown in Figure
12.12b. In night-time, hiking
activities are not expected on this hiking trail because this trail is steep,
not properly paved and not equipped with any lighting. The magnitude of change is therefore
considered adversely
small
for daytime and night-time during operation.
VSR3.4
Hikers on Ap Lei Pai
The existing unobstructed view of the Project area, which
is largely dominated by dense vegetation, will change to the predominant hard
structures of the Water Park which is clearly visible in daytime as shown in Figure
12.12c. In night-time, hiking
activities are not expected on this hiking trail because this trail is steep,
not properly paved and not equipped with any lighting. The magnitude of change is therefore
considered adversely
small
for daytime and night-time during operation.
VSR3.5
Hikers on Brick Hill
The existing partially obstructed view of the Project area,
which is largely dominated by dense vegetation, will change to the predominant
hard structures of the Water Park which is clearly visible in daytime. In night-time, hiking activities are not
expected in most parts of the hiking trails, but night-time visitors to the Nam
Long Shan Road Rest Garden, particularly in special occasions, such as the
Mid-autumn Festival, is expected.
However, the overall number of night-time visitors is expected to be
low. Also, the overall lighting of the
Water Park is expected to be similar to the existing lighting in the Project
area. The magnitude of change is
therefore considered adversely
small
for daytime and night-time during operation.
VSR4.1
Travellers along Shum Wan Road
The existing partially obstructed view of the Project area,
which is largely dominated by dense vegetation, will change to the predominant
hard structures of the Water Park which is clearly visible in daytime. In night-time, the lighting from the Water
Park will also be visible by this VSR.
However, the overall lighting of the Water Park is expected to be
similar to the existing lighting in the Project area. The magnitude of change is considered adversely small during the
operation phase for both daytime and night-time.
VSR4.2
Travellers along Ap Lei Chau Praya Road
The existing view of the Project area, which is largely
dominated by dense vegetation, will change to the predominant hard structures
of the Water Park which is visible in daytime, but only near the end of Ap Lei
Chau Praya Road near the roundabout. In
night-time, the lighting from the Water Park will also be partially visible by
this VSR at the same location. However,
the overall lighting of the Water Park is expected to be similar to the
existing lighting in the Project area.
Also, the lighting from vessels will be more prominent than that from
the Project area. The magnitude of
change is considered adversely
small
during the operation phase for both daytime and night-time.
VSR4.3
Boat users in Aberdeen Channel
The existing unobstructed view of the Project area, which
is largely dominated by dense vegetation, will change to the predominant hard
structures of the Water Park which is clearly visible in daytime as shown in Figure
12.12d. In night-time, the lighting
from the Water Park will also be visible by this VSR. However, the overall lighting of the Water
Park is expected to be similar to the existing lighting in the Project
area. The magnitude of change is
considered adversely
small
during the operation phase for both daytime and night-time.
Table 12.9 summarises the
magnitude of change for all VSRs.
Table 12.9: Magnitude of Change for Visual Sensitive Receivers
ID No.
|
VSR Name
|
Scale of Works (Small / Medium / Large)
|
Reversibility (Reversible / Irreversible)
|
Blockage (None / Partial / Substantial)
|
Minimum Viewing Distance (m)
|
Compatibility with surrounding landscape (Low /
Medium / High)
|
Duration of impacts (Construction) (Short /
Medium / Long)
|
Duration of impacts (Operation) (Short / Medium
/ Long)
|
Magnitude of Change (Construction)
(Negligible / Small / Intermediate / Large)
|
Magnitude of Change (Operation) (Negligible /
Small / Intermediate / Large)
|
VSR1.1
|
Residents at Larvotto
|
Small
|
Irreversible
|
Partial for most receivers; none for ~5% of receivers
|
700
|
High
|
Short
|
Long
|
Adversely small
|
Adversely small
|
VSR1.2
|
Residents at Lei Tung Estate
|
Small
|
Irreversible
|
Substantial
|
1,000
|
High
|
Short
|
Long
|
Negligible
|
Negligible
|
VSR2.1
|
Workers at Ocean Park
|
Medium
|
Irreversible
|
Partial
|
0
|
High
|
Short
|
Medium
|
Adversely small
|
Adversely small
|
VSR2.2
|
Staff and temporary residents
at Spa Hotel
|
Medium
|
Irreversible
|
Partial
|
10
|
High
|
Short
|
Medium
|
N/A
|
N/A for Day 1;
adversely small for Year 10
|
VSR2.3
|
Staff and temporary residents
at Fisherman's Wharf Hotel
|
Medium
|
Irreversible
|
Partial
|
10
|
High
|
Short
|
Medium
|
N/A
|
N/A for Day 1;
adversely small for Year 10
|
VSR2.4
|
Workers at shipyards along the
east coast of Yuk Kwai Shan
|
Small
|
Irreversible
|
Partial
|
500
|
High
|
Short
|
Medium
|
Adversely small
|
Adversely small
|
VSR3.1
|
Recreational users in Ocean
Park
|
Medium
|
Irreversible
|
Partial
|
0
|
High
|
Short
|
Short
|
Adversely small
|
Adversely small
|
VSR3.2
|
Hikers on Yuk Kwai Shan
|
Small
|
Irreversible
|
None
|
800
|
High
|
Short
|
Short
|
Adversely small
|
Adversely small
|
VSR3.3
|
Hikers on the beach between Yuk
Kwai Shan and Ap Lei Pai
|
Small
|
Irreversible
|
None
|
800
|
High
|
Short
|
Short
|
Adversely small
|
Adversely small
|
VSR3.4
|
Hikers on Ap Lei Pai
|
Small
|
Irreversible
|
None
|
700
|
High
|
Short
|
Short
|
Adversely small
|
Adversely small
|
VSR3.5
|
Hikers on Brick Hill
|
Small
|
Irreversible
|
Partial
|
100
|
High
|
Short
|
Short
|
Adversely small
|
Adversely small
|
VSR4.1
|
Travellers along Shum Wan Road
|
Medium
|
Irreversible
|
Partial
|
0
|
High
|
Short
|
Short
|
Adversely
small
|
Adversely small
|
VSR4.2
|
Travellers along Ap Lei Chau
Praya Road
|
Small
|
Irreversible
|
Substantial
|
700
|
High
|
Short
|
Short
|
Adversely small
|
Adversely small
|
VSR4.3
|
Boat users in Aberdeen Channel
|
Medium
|
Irreversible
|
None
|
200
|
High
|
Short
|
Short
|
Adversely small
|
Adversely small
|
12.9
Potential
Impact without Mitigation
Potential
Landscape Impacts without Mitigation
The potential
landscape impacts without mitigation measures for individual LRs and LCAs are
derived from the sensitivities and magnitude of changes in accordance with Table 12.1 and
summarised in Table
12.10 and Table 12.11 respectively. The potential
impacts are expected to be the same for construction and operation phases.
Table 12.10: Potential Landscape Impacts on Landscape
Resources Without Mitigation Measures
ID No.
|
Name
|
Sensitivity
(Low / Medium / High)
|
Magnitude
of Change (Negligible / Small / Intermediate / Large)
|
Significant
Threshold (Unmitigated) (Insubstantial / Slight / Moderate / Significant)
|
LR1.1
|
Tall
Shrubland
|
Medium
|
Adversely small
|
Slight adverse
|
LR1.2
|
Shrubland
|
Medium
|
Adversely
small
|
Slight
adverse
|
LR1.3
|
Hillside grassland
|
Low
|
Negligible
|
Insubstantial
|
LR1.4
|
Woodland
|
High
|
Adversely
large
|
Significant
adverse
|
LR2.1
|
Planting on modified slopes
|
Medium
|
Adversely
intermediate
|
Moderate
adverse
|
LR2.2
|
Roadside planting
|
Medium
|
Adversely
large
|
Significant
adverse
|
LR2.3
|
Amenity planting
|
Medium
|
Adversely
large
|
Significant
adverse
|
LR3.1
|
Floral species of conservation
interest
|
High
|
Negligible
|
Insubstantial
|
LR4.1
|
Coastal
open water
|
High
|
Negligible
|
Insubstantial
|
LR4.2
|
Pond
|
Medium
|
Adversely
large
|
Significant
adverse
|
LR4.3
|
Stream
|
Medium
|
Adversely
large
|
Significant
adverse
|
LR5.1
|
Natural coastline
|
High
|
Negligible
|
Insubstantial
|
Table 12.11: Potential Landscape Impacts on Landscape
Character Areas Without Mitigation Measures
ID No.
|
Name
|
Sensitivity
(Low / Medium / High)
|
Magnitude
of Change (Negligible / Small / Intermediate / Large)
|
Significant
Threshold (Unmitigated) (Insubstantial / Slight / Moderate / Significant)
|
LCA1
|
Theme
park
|
Medium
|
Adversely large
|
Moderate adverse
|
LCA2
|
Natural hillside
|
High
|
Negligible
|
Insubstantial
|
LCA3
|
Open water
|
High
|
Negligible
|
Insubstantial
|
LCA4
|
Typhoon shelter
|
Medium
|
Negligible
|
Insubstantial
|
LCA5
|
Urban non-residential
development
|
Low
|
Negligible
|
Insubstantial
|
Potential Visual Impacts without Mitigation
The potential
landscape impacts without mitigation measures for individual VSRs are derived from
the sensitivities and magnitude of changes in accordance with Table 12.1 and
summarised in Table
12.12.
Table 12.12: Potential Landscape Impacts on Visual Sensitive
Receivers Without Mitigation Measures
ID No.
|
Name
|
Sensitivity
(Low / Medium / High)
|
Magnitude of
Change (Negligible / Small / Intermediate / Large)
|
Significant Threshold
(Unmitigated) (Insubstantial / Slight / Moderate / Significant)
|
Construction
|
Operation
|
Construction
|
Operation
|
VSR1.1
|
Residents
at Larvotto
|
High (daytime and
night-time)
|
Adversely small
|
Adversely small
|
Moderate adverse (daytime
and night-time)
|
Moderate adverse
(daytime and night-time)
|
VSR1.2
|
Residents at Lei Tung Estate
|
Low (daytime and
night-time)
|
Negligible
|
Negligible
|
Insubstantial
(daytime and night-time)
|
Insubstantial
(daytime and night-time)
|
VSR2.1
|
Workers
at Ocean Park
|
Low (daytime and
night-time)
|
Adversely small
|
Adversely small
|
Slight
adverse (daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
VSR2.2
|
Staff and temporary residents
at Spa Hotel
|
Low (daytime and night-time)
|
Negligible
|
Adversely small
|
N/A
|
N/A
for Day 1; slight adverse (daytime and night-time) for Year 10
|
VSR2.3
|
Staff
and temporary residents at Fishermans Wharf Hotel
|
Low (daytime and
night-time)
|
Negligible
|
Adversely small
|
N/A
|
N/A
for Day 1; slight adverse (daytime and night-time) for Year 10
|
VSR2.4
|
Works
at shipyards along the east coast of Yuk Kwai Shan
|
Low (daytime and
night-time)
|
Adversely small
|
Adversely small
|
Slight
adverse (daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
VSR3.1
|
Recreational users in Ocean
Park
|
Low (daytime and
night-time)
|
Adversely small
|
Adversely small
|
Slight
adverse (daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
VSR3.2
|
Hikers
on Yuk Kwai Shan
|
Medium in daytime;
low in night-time
|
Adversely small
|
Adversely small
|
Slight
adverse (daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
VSR3.3
|
Hikers
on the beach between Yuk Kwai Shan and Ap Lei Pai
|
Medium in daytime;
low in night-time
|
Adversely small
|
Adversely small
|
Slight
adverse (daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
VSR3.4
|
Hikers
on Ap Lei Pai
|
Medium in daytime;
low in night-time
|
Adversely small
|
Adversely small
|
Slight
adverse (daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
VSR3.5
|
Hikers
on Brick Hill
|
Low (daytime and
night-time)
|
Adversely small
|
Adversely small
|
Slight
adverse (daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
VSR4.1
|
Travellers along Shum Wan Road
|
Low (daytime and
night-time)
|
Adversely
small
|
Adversely small
|
Slight
adverse (daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
VSR4.2
|
Travellers along Ap Lei Chau
Praya Road
|
Low (daytime and
night-time)
|
Adversely small
|
Adversely small
|
Slight
adverse (daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
VSR4.3
|
Boat users in Aberdeen Channel
|
Low (daytime and night-time)
|
Adversely
small
|
Adversely small
|
Slight
adverse (daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
Mitigation measures for
potential landscape and visual impacts have been carefully considered to
achieve the following:
§ Avoid
impacts on important landscape resources and visual sensitive receivers;
§ Lessen
unavoidable impacts by location, design and reducing the extent of works; and
§ Enhancement
of existing landscape resources and visual quality.
Recommended mitigation measures
for construction and operation phase impacts are summarised in Table 12.13 and Table 12.14 respectively. The construction phase mitigation measures
listed below shall be adopted from the commencement of construction and
throughout the entire construction period.
The operation phase mitigation measures shall be adopted during detailed
design and built as part of the construction works so that they shall be in
place at the Day 1 of operation phase.
Table
12.13: Recommended Construction Phase Mitigation
Measures
Mitigation Code
|
Responsible Agent for Mitigation Implementation
|
Mitigation
Measure
|
Target LR(s),
LCA(s) and / or VSR(s)
|
CP01
|
OPC via Contractor
|
Minimisation of Construction Period
The construction programme should be carefully designed to minimise the
length of the construction period.
|
VSR1.1; VSR2.1;
VSR2.4; VSR3.1; VSR3.2; VSR3.3; VSR3.4; VSR3.5; VSR4.1; VSR4.2; VSR4.3
|
CP02
|
OPC via Contractor
|
Minimisation of Works Areas
The footprint of the proposed hard structures as well as the extent of
temporary works areas should be minimised as far as practicable.
|
VSR1.1; VSR2.1;
VSR2.4; VSR3.1; VSR3.2; VSR3.3; VSR3.4; VSR3.5; VSR4.1; VSR4.2; VSR4.3
|
CP03
|
OPC via Contractor
|
Construction Site Controls
Construction site controls should be enforced, where possible, to ensure that
the landscape and visual impacts arising from the construction phase
activities, such as the storage of materials, the location and appearance of
site accommodation, etc. are minimised.
|
VSR1.1; VSR2.1;
VSR2.4; VSR3.1; VSR3.2; VSR3.3; VSR3.4; VSR3.5; VSR4.1; VSR4.2; VSR4.3
|
CP04
|
OPC via Contractor
|
Preservation of Existing Vegetation
The development proposal should avoid disturbance to existing vegetation as
far as practicable. A formal tree
removal application should be submitted for approval by relevant authorities
in accordance with LAO PN No. 07/2007 Tree Preservation and Tree Removal
Application for Building Development in Private Projects during the detailed
design phase of the Project. Where possible, all trees which are not in
direct conflict with the development proposals should be retained in situ.
|
LR1.1; LR1.2;
LR1.4; LR2.1; LR2.2; LR2.3; LCA1; VSR1.1; VSR2.1; VSR2.4; VSR3.1; VSR3.2;
VSR3.3; VSR3.4; VSR3.5; VSR4.1; VSR4.2; VSR4.3
|
CP05
|
OPC via Contractor
|
Transplantation of Existing Trees
Trees which are in direct
conflict with the development proposals and suitable for transplantation
should be transplanted as far as practicable.
A tree transplantation proposal should be submitted together with the
tree removal application. Trees
proposed to be transplanted should preferably be transplanted from their
original locations directly to their final recipient locations in one go. If this is infeasible, the trees should be
held in a temporary tree nursery, preferably within the Project area, where
the trees will be properly maintained.
|
LR2.1; LR2.2;
LR2.3; LCA1; VSR1.1; VSR2.1; VSR2.4; VSR3.1; VSR3.2; VSR3.3; VSR3.4; VSR3.5;
VSR4.1; VSR4.2; VSR4.3
|
CP06
|
OPC via Contractor
|
No Intrusion Zones Where
practicable, no intrusion zones should be designated within the Project
area for protection of existing vegetation.
Durable boundary fences should be erected to clearly demarcate these
no intrusion zones. No construction
activities, storage of materials and vehicular access will be allowed within
the no intrusion zones to prevent potential damage to canopies and root
zones of vegetation.
|
LR1.1; LR1.2;
LR1.4; LR2.1; LR2.2; LR2.3; LCA1
|
CP07
|
OPC via Contractor
|
Temporary Tree Nurseries
Temporary tree nurseries may be set up within the Project area at an early
stage to allow small trees to grow during the construction period. By the time these trees are needed for
landscape planting at the end of the construction phase, they will have grown
larger, require minimal pruning and suffer much less damage during
transplanting, as the moving distance from an on-site rather than off-site
nursery will be much smaller. The
temporary tree nurseries can also temporarily hold the existing trees to be
transplanted if direct transplantation from their original locations to the
final recipient location is impracticable.
The locations of the temporary tree nurseries should be carefully
selected so that the trees can also act as screen planting to block the views
of the Project area from the VSRs during the construction phase, if
practicable.
|
LR2.3; LCA1;
VSR1.1; VSR2.1; VSR2.4; VSR3.1; VSR3.2; VSR3.3; VSR3.4; VSR3.5; VSR4.1;
VSR4.2; VSR4.3
|
CP08
|
OPC via Contractor
|
Advance Planting
Advance planting should be undertaken at the earliest possible stage of the
construction phase of the project.
Plant species, preferably native ones, should be carefully selected to
blend in with the existing preserved vegetation. Landscape planting in movable planters
should also be considered as a temporary greening measure for the Project
area.
|
LR1.1; LR1.2;
LR1.4; LR2.1; LR2.2; LR2.3; LCA1; VSR1.1; VSR2.1; VSR2.4; VSR3.1; VSR3.2;
VSR3.3; VSR3.4; VSR3.5; VSR4.1; VSR4.2; VSR4.3
|
CP09
|
OPC via Contractor
|
Construction Site Hoardings
Two types of hoardings should be considered. One is used for areas in close contact with
visitors and for areas where visual intrusion is a key concern. It should be graphical and thematic, and visually
impermeable to block the views of construction activities from the
VSRs. The other is used for areas to
be viewed at a distance. It should be subtle and camouflaged so that it
blends in with the surrounding landscape.
|
VSR1.1; VSR2.1;
VSR2.4; VSR3.1; VSR3.2; VSR3.3; VSR3.4; VSR3.5; VSR4.1; VSR4.2; VSR4.3
|
CP10
|
OPC via Contractor
|
Dust and Erosion Control for Exposed Soil
Exposed soil shall be covered or camouflaged and watered frequently. Areas that are expected to be left with
bare soil for a long period of time should be hydroseeded and / or covered
with suitable protective fabrics.
|
LR1.1; LR1.2;
LR1.4; LR2.1; LR2.2; LR2.3; LCA1; VSR1.1; VSR2.1; VSR2.4; VSR3.1; VSR3.2;
VSR3.3; VSR3.4; VSR3.5; VSR4.1; VSR4.2; VSR4.3
|
CP11
|
OPC via Contractor
|
Appearance of Construction Plant / Machinery
To minimise the visual intrusion of construction activities to visitors and
other VSRs, a suitable colour scheme of construction machines and plants
should be adopted where possible.
|
VSR1.1; VSR2.1;
VSR2.4; VSR3.1; VSR3.2; VSR3.3; VSR3.4; VSR3.5; VSR4.1; VSR4.2; VSR4.3
|
CP12
|
OPC via Contractor
|
Construction Lighting Control -
All security floodlights for construction sites should be equipped with
adjustable shield, frosted diffusers and reflective covers, and be carefully
controlled to minimise light pollution and night-time glare to the VSRs.
|
VSR1.1; VSR2.1;
VSR2.4; VSR3.1; VSR3.2; VSR3.3; VSR3.4; VSR3.5; VSR4.1; VSR4.2; VSR4.3
|
CP13
|
OPC via Contractor
|
Appearance of Construction Workers
To protect Ocean Parks image, construction workers should be required to
enter the park areas with their helmets and safety vests properly stored or
carried in non-transparent bags. They
should also dress properly and cleanly.
|
VSR2.1; VSR3.1
|
Table
12.14: Recommended Operation Phase Mitigation Measures
Mitigation Code
|
Responsible Agent for Mitigation
Implementation
|
Mitigation Measure
|
Target LR(s), LCA(s) and / or VSR(s)
|
OP01
|
OPC via Contractor
|
Sensitive
Design and Disposition All proposed hard structures should be sensitively
designed in a manner that responds to the existing and planned landscape
context, and minimises potential adverse landscape and visual impacts. The structural design should seek to reduce
the apparent visual mass through the use of natural materials such as wooden
frame and semi-transparent panels.
Subdued tones should be considered for the colour palette with
non-reflective finishes to reduce glare effect. Site specific measures, such as the
disposition of the key structures closer to the northern slopes, the design of building
forms as extension along the existing slope topography, the use of concave
roof form and the location of ride platforms on or near the slopes to
minimise structural support, should also be considered for better integration
with the surroundings and minimisation of potential visual impacts.
|
VSR1.1; VSR2.1; VSR2.2; VSR2.3; VSR2.4;
VSR3.1; VSR3.2; VSR3.3; VSR3.4; VSR3.5; VSR4.1; VSR4.2; VSR4.3
|
OP02
|
OPC via Contractor
|
Compensatory
Tree Planting
Existing trees to be felled should be compensated as far as
practicable. Native species should be
proposed as far as practicable to re-create a native landscape, restore the
ecological habitats and blend in with the existing native vegetation. A compensatory tree planting proposal
should be submitted together with the tree removal application for approval
by relevant authorities in accordance with LAO Practice Note No. 7/2007. It
is recommended that approximately 608 heavy standard trees and approximately
18,202 whip trees could be planted on-site. The availability of off-site
compensatory tree planting area is still subject to further investigation and
agreement with relevant authorities.
|
LR1.1; LR1.2; LR1.4; LR2.1; LR2.2; LR2.3;
LCA1; VSR1.1; VSR2.1; VSR2.2; VSR2.3; VSR2.4; VSR3.1; VSR3.2; VSR3.3; VSR3.4;
VSR3.5; VSR4.1; VSR4.2; VSR4.3
|
OP03
|
OPC via Contractor
|
Enhancement
Planting Other than compensatory tree
planting, additional trees, shrubs, groundcovers and lawn should also be
considered to maximise greening within the redevelopment area.
|
LR1.1; LR1.2; LR1.4; LR2.1; LR2.2; LR2.3; LCA1;
VSR1.1; VSR2.1; VSR2.2; VSR2.3; VSR2.4; VSR3.1; VSR3.2; VSR3.3; VSR3.4;
VSR3.5; VSR4.1; VSR4.2; VSR4.3
|
OP04
|
OPC via Contractor
|
Green
Roofs and Vertical Greening Green Roofs and Vertical Greening should
be provided where feasible and appropriate to screen and soften the hard
edges of building structures.
|
LR2.3; LCA1; VSR1.1; VSR2.1; VSR2.2;
VSR2.3; VSR2.4; VSR3.1; VSR3.2; VSR3.3; VSR3.4; VSR3.5; VSR4.1; VSR4.2;
VSR4.3
|
OP05
|
OPC via Contractor
|
Reprovision
of Flamingo Pond
A pond is recommended to replace the demolished Flamingo Pond as
compensation for the loss of semi-natural ponds, where wildlife, such as
birds, can utilise.
|
LR4.2; LCA1
|
OP06
|
OPC via Contractor
|
Responsive
Lighting Design
Overall lighting design would carefully consider a reasonable level of
functional and thematic lighting with due consideration of possible light
pollution and night-time glare to the surroundings. Consideration shall be made by the lighting
designers to the following measures:
-
Lighting
shall be designed with due consideration of mounting height and direction of
light fixtures so as not to point directly towards any sensitive receiver.
-
Lighting
shall be arranged with due consideration of reflectance so as to avoid glare
effect.
-
Lighting
shall be regularly monitored during operation.
-
Lights
located adjacent or in proximity to neighbours shall be carefully designed to
prevent possible light intrusion.
-
Lighting
operation schedule shall specify only lights necessary for security to be
left on after business hours.
-
Paving
materials should be selected as necessary to reduce potential glare from
surface reflectance.
-
Particular
attention should be paid to the use of lighting having a high intensity or
harsher tone (e.g. metal halide lamps).
-
Lights
shall generally be models having precise cut-off range (such as full cut-off
optics where available and practicable) and if necessary be fitted with
adjustable anti-glare shields.
|
VSR1.1; VSR2.1; VSR2.2; VSR2.3; VSR2.4; VSR3.1;
VSR3.2; VSR3.3; VSR3.4; VSR3.5; VSR4.1; VSR4.2; VSR4.3
|
OP07
|
OPC via Contractor
|
Woodland
Compensation
1.53ha of affected woodland is recommended to be reinstated / compensated by 1.62ha
of whip tree planting adjacent to the existing unaffected woodland and tall
shrubland. Native species should be
proposed as far as practicable to re-create a native landscape, restore the
ecological habitats and blend in with the existing native vegetation. This is
also an ecological mitigation measure as discussed in detail in Section 10.7.3.
|
LR1.4; LCA1; VSR1.1; VSR2.1; VSR2.2;
VSR2.3; VSR2.4; VSR3.1; VSR3.2; VSR3.3; VSR3.4; VSR3.5; VSR4.1; VSR4.2;
VSR4.3
|
Photomontages
Series of computer generated
images or photomontages have been prepared to illustrate the proposed works and
recommended mitigation measures. The locations of the vantage points A to G
used for these images have been identified on Figure 12.2.
The photomontages are presented
in Figures 12.12a to 12.12j. The photomontages show the
existing conditions, after the completion of the construction phase when the primary
mitigation measures have been implemented, Day 1 and Year 10 of the operation
phase with the implementation of the secondary mitigation measures. Year 10 of the operation phase is designed to
demonstrate predicted residual impacts, which would exist in the design year
during the operation phase, 10 years after the completion of the construction
phase.
Potential
Landscape Impacts with Mitigation during Construction
LR1.1 Tall shrubland
By preserving existing
vegetation (CP04), setting up no intrusion zone to protect existing vegetation
(CP06), advance planting (CP08) and implementing erosion control measures (such
as hydroseeding) on exposed slopes (CP10), unnecessary disturbance to this LR
will be minimised. However, site
clearance and tree removal are unavoidable and the impact cannot be fully
offset by the proposed mitigation measures.
This LR is still expected to receive a slight adverse landscape impact during construction phase.
LR1.2 Shrubland
By preserving existing
vegetation (CP04), setting up no intrusion zone to protect existing vegetation
(CP06), advance planting (CP08) and implementing erosion control measures (such
as hydroseeding) on exposed slopes (CP10), unnecessary disturbance to this LR
will be minimised. However, site clearance
and tree removal are unavoidable and the impact cannot be fully offset by the
proposed mitigation measures. This LR is
still expected to receive a slight adverse landscape impact
during construction phase.
LR1.3 Hillside grassland
This LR is located entirely
outside the Project area. No direct
landscape impact is expected. No
construction mitigation measure is proposed for this LR. It is expected to receive an insubstantial landscape impact during construction phase.
LR1.4 Woodland
By preserving existing vegetation (CP04), setting up no
intrusion zone to protect existing vegetation (CP06), advance planting (CP08)
and implementing erosion control measures (such as hydroseeding) on exposed
slopes (CP10), unnecessary disturbance to this LR will be minimised. However, site clearance and tree removal are
unavoidable and the impact cannot be fully offset by the proposed mitigation
measures. This LR is still expected to receive
a moderate adverse landscape impact during
construction phase.
LR2.1 Planting on modified slopes
By preservation of existing
vegetation (CP04), transplanting affected trees (CP05), setting up no intrusion
zone to protect existing vegetation (CP06), advance planting (CP08) and
implementing erosion control measures (such as hydroseeding) on exposed slopes
(CP10), unnecessary disturbance to this LR will be minimised. However, site clearance and tree removal are
unavoidable and the impact cannot be fully offset by the proposed mitigation
measures. This LR is still expected to
receive a moderate adverse landscape impact during
construction phase.
LR2.2 Roadside planting
By preservation of existing
vegetation (CP04), transplanting affected trees (CP05), setting up no intrusion
zone to protect existing vegetation (CP06), advance planting (CP08) and
implementing erosion control measures (such as hydroseeding) on exposed soil
(CP10), unnecessary disturbance to this LR will be minimised. However, site clearance and tree removal are
unavoidable and the impact cannot be fully offset by the proposed mitigation
measures. This LR is still expected to
receive a significant adverse landscape impact during
construction phase.
LR2.3 Amenity planting
By preservation of existing vegetation
(CP04), transplanting affected trees (CP05), setting up no intrusion zone to
protect existing vegetation (CP06), setting up temporary tree nursery (CP07),
advance planting (CP08) and implementing erosion control measures (such as
hydroseeding) on exposed soil (CP10), unnecessary disturbance to this LR will
be minimised. However, site clearance
and tree removal are unavoidable and the impact cannot be fully offset by the
proposed mitigation measures. This LR is
still expected to receive a moderate adverse landscape impact
during construction phase.
LR3.1 Floral species of conservation interest
Out of the 17 identified floral
species of conservation interest, only one of them, which is Platycodon grandiflorus, is found within the Project area. The Platycodon
grandiflorus is located at the southern end on the hillside of the Project
area, which will not be affected by the construction activities. No direct landscape impact is expected. Hence, no mitigation measure is proposed for
this LR, which is expected to receive an insubstantial landscape impact during construction phase.
LR4.1 Coastal open water
This LR is located entirely
outside the Project area. Also, the
Project does not involve any reclamation, dredging or any seawall construction. No direct landscape impact is expected. Therefore, no construction mitigation is
proposed for this LR. This LR is
expected to receive an insubstantial landscape impact
during construction phase.
LR4.2 Pond
The Flamingo Pond and Bird
Paradise Pond will be demolished for the implementation of the proposed
construction works. No mitigation
measure is considered practicable to mitigate the temporary loss of these
ponds. This LR is expected to receive a significant
adverse landscape impact during construction phase.
LR4.3 Stream
No specific mitigation measure
is considered practicable to directly mitigate the temporary loss of the
natural stream section of 75m in length.
This LR is expected to receive a significant adverse landscape impact during construction phase.
LR5.1 Natural coastline
This LR is located entirely
outside the Project area. Also, the
Project does not involve any reclamation, dredging or any seawall
construction. No direct landscape impact
is expected. Therefore, no construction
mitigation is proposed for this LR. This
LR is expected to receive an insubstantial landscape impact
during construction phase.
LCA1 Theme park
By preservation of existing
vegetation (CP04), transplanting affected trees (CP05), setting up no intrusion
zone to protect existing vegetation (CP06), setting up temporary tree nursery
(CP07), advance planting (CP08) and implementing erosion control measures (such
as hydroseeding) on exposed slopes (CP10), unnecessary disturbance to this LCA
will be minimised. However, site
clearance and tree removal are unavoidable and the impact cannot be fully
offset by the proposed mitigation measures.
Given the scale of the Project, this LCA is still expected to receive a moderate
adverse landscape impact during construction phase.
LCA2 Natural hillside
This LCA is located entirely
outside the Project area. No direct
landscape impact is expected. Therefore,
no construction mitigation is proposed for this LCA. This LCA is expected to receive an insubstantial landscape impact during construction phase.
LCA3 Open water
This LCA is located entirely
outside the Project area. Also, the
Project does not involve any reclamation, dredging or any seawall
construction. No direct landscape impact
is expected. Therefore, no construction
mitigation is proposed for this LCA.
This LCA is expected to receive an insubstantial landscape impact during construction phase.
LCA4 Typhoon shelter
This LCA is located entirely
outside the Project area. Also, the
Project does not involve any reclamation, dredging or any seawall
construction. No direct landscape impact
is expected. Therefore, no construction
mitigation is proposed for this LCA.
This LCA is expected to receive an insubstantial landscape impact during construction phase.
LCA5 Urban non-residential development
This LCA is located entirely
outside the Project area. No direct
landscape impact is expected. Therefore,
no construction mitigation is proposed for this LCA. This LCA is expected to receive an insubstantial landscape impact during construction phase.
Potential
Landscape Impacts with Mitigation during Operation
LR1.1 Tall shrubland
By compensatory tree planting
(OP02) and enhancement planting (OP03), the affected landscape will be
partially restored by planting approximately 1,796 whip trees. The tree
compensation ratio will be approximately 1:5.14 in terms of DBH. Although the aggregated DBH of the
compensatory planting is approximately 5 times the aggregated DBH of trees
lost, in Day 1 of operation, the planting in reinstated areas will be young
compared to the removed tall shrubland.
The landscape impact is still expected to be slight
adverse. However, in
Year 10 of operation, when the replacement planting matures and fully blends in
with the existing tall shrubland, the landscape impact is expected to be insubstantial.
LR1.2 Shrubland
By compensatory tree planting
(OP02) and enhancement planting (OP03), the affected landscape will be
partially restored by planting approximately 4 heavy standard tree and approximately 1,208
whip trees. The tree compensation ratio will be approximately 1:16.62 in terms
of DBH. Although the aggregated DBH of
the compensatory planting is more than 16 times the aggregated DBH of trees
lost, in Day 1 of operation, the planting in reinstated areas will be young
compared to the removed shrubland. The
landscape impact is still expected to be slight adverse. However, in Year 10 of
operation, when the replacement planting matures and fully blends in with the
existing shrubland, the landscape impact is expected to be insubstantial.
LR1.3 Hillside grassland
This LR is located entirely
outside the Project area. No direct
landscape impact is expected. No
operation mitigation measure is proposed for this LR. It is expected to receive an insubstantial
landscape impact during operation phase (Day 1 and Year
10).
LR1.4 Woodland
By compensatory tree planting
(OP02), enhancement planting (OP03) and woodland compensation (OP07), the
affected landscape will be partially restored by planting approximately 13
heavy standard trees and approximately 8,930 whip trees. The tree compensation
ratio will be approximately 1:1.14 in terms of DBH. Although the aggregated DBH of the
compensatory planting is more than the aggregated DBH of trees lost, in Day 1
of operation, the planting in reinstated areas and the woodland compensation
area will be young compared to the trees removed in the woodland. The landscape impact is still expected to be moderate
adverse. However, in
Year 10 of operation, when the replacement planting matures and starting to
blend in with the existing woodland, the landscape impact is expected to be slight
adverse.
LR2.1 Planting on modified slopes
By compensatory tree planting
(OP02) and enhancement planting (OP03), the affected landscape will be
partially restored by planting approximately 74 heavy standard trees and
approximately 584 whip trees. The tree compensation ratio will be approximately
1:0.42 in terms of DBH. In Day 1 of
operation, the planting in reinstated areas will be young compared to the
removed trees on modified slopes. The
landscape impact is still expected to be moderate adverse. However, in Year 10 of
operation, when the replacement planting matures, the landscape impact is
expected to be slight adverse.
LR2.2 Roadside planting
By compensatory tree planting
(OP02) and enhancement planting (OP03), the affected landscape will be
partially restored by planting approximately 10 heavy standard trees. The tree
compensation ratio will be approximately 1:0.13 in terms of DBH. In Day 1 of operation, the planting in
reinstated areas will be young compared to the removed roadside planting. The landscape impact is still expected to be moderate
adverse. However, in
Year 10 of operation, when the replacement planting matures, the landscape
impact is expected to be slight adverse.
LR2.3 Amenity planting
By compensatory tree planting
(OP02), enhancement planting (OP03) and green roof and vertical greening
(OP04), the affected landscape will be partially restored by planting
approximately 87 heavy standard trees and approximately 5,983 whip trees. The
tree compensation ratio will be approximately 1:0.47 in terms of DBH. In Day 1 of operation, the planting in reinstated
areas will be young compared to the removed amenity planting. The landscape impact is still expected to be moderate
adverse. However, in
Year 10 of operation, when the replacement planting matures, the landscape
impact is expected to be slight adverse.
LR3.1 Floral species of conservation interest
All the identified floral
species of conservation interest will not be affected by the construction
activities. No direct landscape impact
is expected. Hence, no mitigation measure
is proposed for this LR, which is expected to receive an insubstantial landscape impact during operation phase (Day 1 and Year 10).
LR4.1 Coastal open water
This LR is located entirely
outside the Project area. No direct
landscape impact is expected. Therefore,
no operation mitigation measure is proposed for this LR. This LR is expected to receive an insubstantial landscape impact during operation phase (Day 1 and Year 10).
LR4.2 Pond
The two removed semi-natural
ponds Flamingo Pond and Bird Paradise Pond will be replaced by artificial
indoor and outdoor pools of the Project.
A new Flamingo Pond will be reprovided (OP05) in the existing
developed area. This LR is expected to
receive a slight adverse landscape impact during
operation phase (Day1 and Year 10).
LR4.3 Stream
No specific mitigation measure
is proposed to directly compensate for the loss of the natural stream section
of 75m in length. However, some parts of
the diverted drainage channel are adjacent to the compensatory planting
areas. Also, the preserved existing
natural stream sections are partly within the woodland compensation areas. The compensatory planting will therefore
enhance the overall landscape quality of the diverted drainage channels and the
natural stream sections. This LR is therefore
expected to receive a moderate adverse landscape impact
during operation phase (Day 1 and Year 10).
LR5.1 Natural coastline
This LR is located entirely
outside the Project area. No direct
landscape impact is expected. Therefore,
no operation mitigation measure is proposed for this LR. This LR is expected to receive an insubstantial
landscape impact during operation phase (Day 1 and Year
10).
LCA1 Theme park
By compensatory tree planting
(OP02), enhancement planting (OP03), green roof and vertical greening (OP04),
reprovision of Flamingo Pond (OP05) and woodland compensation (OP07), the affected
landscape will be largely restored.
Planting of approximately 608 heavy standard trees and approximately
18,202 whip trees will be provided. Upon
completion of the Project, the original landscape, which is predominantly
covered with vegetation, will be replaced with hard structures of the Project
with landscape planting, green roofs and vertical greening. Although the coverage of hard structures will
increase, the overall landscape character as a theme park will remain
unchanged. The landscape impact is
therefore expected to be slight adverse in Day 1 of
operation. In Year 10 of operation, the
hard structures will still be prominent in the Project area, but the planting
will blend in with the surrounding environment.
The landscape impact will be insubstantial in Year 10 of operation.
LCA2 Natural hillside
This LCA is located entirely
outside the Project area. No direct
landscape impact is expected. Therefore,
no operation mitigation measure is proposed for this LCA. This LCA is expected to receive an insubstantial landscape impact during operation phase (Day 1 and Year 10).
LCA3 Open water
This LCA is located entirely
outside the Project area. No direct
landscape impact is expected. Therefore,
no operation mitigation measure is proposed for this LCA. This LCA is expected to receive an insubstantial landscape impact during operation phase (Day 1 and Year 10).
LCA4 Typhoon shelter
This LCA is located entirely
outside the Project area. No direct
landscape impact is expected. Therefore,
no operation mitigation measure is proposed for this LCA. This LCA is expected to receive an insubstantial landscape impact during operation phase (Day 1 and Year 10).
LCA5 Urban non-residential development
This LCA is located entirely
outside the Project area. No direct
landscape impact is expected. Therefore,
no operation mitigation measure is proposed for this LCA. This LCA is expected to receive an insubstantial landscape impact during operation phase (Day 1 and Year 10).
Table 12.15 and Table 12.16 summarise the results of the landscape impact assessment for LRs and
LCAs respectively, which are also illustrated in Figure 12.10. Figure 12.13 shows a preliminary schematic landscape plan which also illustrates
the proposed landscape mitigation measures.
Table
12.15: Impact
Assessment for Landscape Resources
ID No.
|
LR Name
|
Significance Threshold (Unmitigated)
(Insubstantial / Slight / Moderate / Significant)
|
Proposed Mitigation Measures
|
Significance Threshold (Mitigated)
(Insubstantial / Slight / Moderate / Significant)
|
Construction
|
Operation
|
Construction
|
Operation (Day 1)
|
Operation (Year 10)
|
LR1.1
|
Tall shrubland
|
Slight
adverse
|
Slight adverse
|
CP04; CP06; CP08;
CP10; OP02; OP03
|
Slight
adverse
|
Slight
adverse
|
Insubstantial
|
LR1.2
|
Shrubland
|
Slight
adverse
|
Slight adverse
|
CP04; CP06; CP08;
CP10; OP02; OP03
|
Slight
adverse
|
Slight
adverse
|
Insubstantial
|
LR1.3
|
Hillside grassland
|
Insubstantial
|
Insubstantial
|
-
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
LR1.4
|
Woodland
|
Significant
adverse
|
Significant adverse
|
CP04; CP06; CP08;
CP10; OP02; OP03; OP07
|
Moderate
adverse
|
Moderate
adverse
|
Slight adverse
|
LR2.1
|
Planting on
modified slopes
|
Moderate
adverse
|
Moderate adverse
|
CP04; CP05; CP06;
CP08; CP10; OP02; OP03
|
Moderate
adverse
|
Moderate
adverse
|
Slight adverse
|
LR2.2
|
Roadside planting
|
Significant
adverse
|
Significant adverse
|
CP04; CP05; CP06;
CP08; CP10; OP02; OP03
|
Significant
adverse
|
Moderate
adverse
|
Slight adverse
|
LR2.3
|
Amenity planting
|
Significant
adverse
|
Significant adverse
|
CP04; CP05; CP06;
CP07; CP08; CP10; OP02; OP03; OP04
|
Moderate
adverse
|
Moderate adverse
|
Slight adverse
|
LR3.1
|
Floral species of
conservation interest
|
Insubstantial
|
Insubstantial
|
-
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
LR4.1
|
Coastal open water
|
Insubstantial
|
Insubstantial
|
-
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
LR4.2
|
Pond
|
Significant adverse
|
Significant adverse
|
OP05
|
Significant adverse
|
Slight
adverse
|
Slight
adverse
|
LR4.3
|
Stream
|
Significant
adverse
|
Significant adverse
|
-
|
Significant
adverse
|
Moderate adverse
|
Moderate
adverse
|
LR5.1
|
Natural coastline
|
Insubstantial
|
Insubstantial
|
-
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
Table 12.16: Impact Assessment for Landscape Character Areas
ID No.
|
LR Name
|
Significance Threshold (Unmitigated)
(Insubstantial / Slight / Moderate / Significant)
|
Proposed Mitigation Measures
|
Significance Threshold (Mitigated) (Insubstantial
/ Slight / Moderate / Significant)
|
Construction
|
Operation
|
Construction
|
Operation (Day 1)
|
Operation (Year 10)
|
LCA1
|
Theme park
|
Moderate adverse
|
Moderate adverse
|
CP04; CP05; CP06; CP07;
CP08; CP10; OP02; OP03; OP04; OP05; OP07
|
Moderate adverse
|
Slight adverse
|
Insubstantial
|
LCA2
|
Natural hillside
|
Insubstantial
|
Insubstantial
|
-
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
LCA3
|
Open water
|
Insubstantial
|
Insubstantial
|
-
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
LCA4
|
Typhoon shelter
|
Insubstantial
|
Insubstantial
|
-
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
LCA5
|
Urban
non-residential development
|
Insubstantial
|
Insubstantial
|
-
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
Potential
Visual Impacts with Mitigation during Construction
VSR1.1
Residents at Larvotto
With mitigation, the existing unobstructed view of the
Project area, which is largely dominated by dense vegetation, will
change to a construction site which is still large visible in daytime by
residents in Block 1, Larvotto, even with screen hoardings and temporary
landscape planting. In night-time, the
lighting from the Project area will also be
visible by this VSR. However, since
night-time construction activities are not expected, only minimal lighting,
which is similar to the existing lighting in the Project area, is expected to be provided.
The potential visual impact is considered moderate adverse for daytime and slight adverse for night-time during the construction phase.
VSR1.2
Residents at Lei Tung Estate
Since the existing view of this VSR is dominated by the
residential buildings of Larvotto, and the view of the Project area is barely visible, the potential visual impacts, both in the daytime
and night-time, are considered insubstantial during the construction phase.
VSR2.1
Workers at Ocean Park
With mitigation, at locations where the Project area is visible within Ocean Park, the existing view, which is largely
dominated by dense vegetation, will be replaced by the view of a construction
site with screen hoardings and temporary landscape planting. However, since the vegetation within the park
often partially screens the view of the Project area, the potential
visual impact on this VSR is considered slight adverse during the construction phase for both daytime and
night-time.
VSR2.2
Staff and temporary residents at the planned Spa Hotel
Since construction of this hotel is not anticipated to
complete before completion of this Project, this VSR will not be present during
construction phase. Potential visual
impact to this VSR is therefore not applicable during the construction phase.
VSR2.3
Staff and temporary residents at the planned Fisherman's Wharf Hotel
Since construction of this hotel is not anticipated to
complete before completion of this Project, this VSR will not be present during
construction phase. Potential visual
impact to this VSR is therefore not applicable during the construction phase.
VSR2.4
Workers at shipyards along the east coast of Yuk Kwai Shan
With mitigation, the existing view of the Project area, which is largely dominated by dense vegetation but often partially
obstructed by vessels in Aberdeen South Typhoon Shelter, will change to a
construction site which is visible in daytime but partially screened by screen
hoardings and temporary landscape planting.
In night-time, the lighting from the Project area will also be partially visible by this VSR. However, since night-time construction
activities are not expected, only minimal lighting, which is similar to the
existing lighting in the Project area, is expected to be
provided. Also, the lighting from
vessels will be more prominent than that from the Project area. The potential visual impact is
considered slight adverse during the
construction phase for both daytime and night-time.
VSR3.1
Recreational users in Ocean Park
With mitigation, at locations where the Project area is visible within Ocean Park, the existing view, which is largely
dominated by dense vegetation, will be replaced by the view of a construction
site with screen hoardings and temporary landscape planting. However, since the vegetation within the park
often partially screens the view of the Project area, the potential
visual impact on this VSR is considered slight adverse during the construction phase for both daytime and
night-time.
VSR3.2
Hikers on Yuk Kwai Shan
With mitigation, the existing unobstructed view of the
Project area, which is largely dominated by dense vegetation, will
change to a construction site which is still largely visible even with screen
hoardings and temporary landscape planting in daytime. In night-time, hiking activities are not
expected on this hiking trail because this trail is steep, not properly paved
and not equipped with any lighting. The
potential visual impact is therefore considered slight adverse for daytime and insubstantial for night-time during construction.
VSR3.3
Hikers on the beach between Yuk Kwai Shan and Ap Lei Pai
With mitigation, the existing unobstructed view of the
Project area, which is largely dominated by dense vegetation, will
change to a construction site which is partially visible even with screen
hoardings and temporary landscape planting in daytime. In night-time, hiking activities are not
expected on this hiking trail because this trail is steep, not properly paved
and not equipped with any lighting. The
potential visual impact is therefore considered slight adverse for daytime and insubstantial for night-time during construction.
VSR3.4
Hikers on Ap Lei Pai
With mitigation, the existing unobstructed view of the
Project area, which is largely dominated by dense vegetation, will change
to a construction site which is still largely visible even with screen
hoardings and temporary landscape planting in daytime. In night-time, hiking activities are not
expected on this hiking trail because this trail is steep, not properly paved
and not equipped with any lighting. The
potential visual impact is therefore considered slight adverse for daytime and insubstantial for night-time during construction.
VSR3.5
Hikers on Brick Hill
With mitigation, the existing partially obstructed view of
the Project area, which is largely dominated by dense vegetation, will
change to a construction site which is still largely visible even with screen
hoardings and temporary landscape planting in daytime. In night-time, hiking activities are not
expected in most parts of the hiking trails, but night-time visitors to the Nam
Long Shan Road Rest Garden, particularly in special occasions, such as the
Mid-autumn Festival, is expected.
However, the overall number of night-time visitors is expected to be
low. The potential visual impact is
therefore considered slight
adverse
for daytime and insubstantial for night-time
during construction.
VSR4.1
Travellers along Shum Wan Road
With mitigation, the existing partially obstructed view of
the Project area, which is largely dominated by dense vegetation, will
change to a construction site which is partially visible with screen hoardings
and temporary landscape planting in daytime.
In night-time, the lighting from the Project area will also be partially visible by this VSR. However, since night-time construction
activities are not expected, only minimal lighting, which is similar to the
existing lighting in the Project area, is expected to be
provided. The potential visual impact is
considered slight adverse during the
construction phase for both daytime and night-time.
VSR4.2
Travellers along Ap Lei Chau Praya Road
With mitigation, the existing view of the Project area, which is largely dominated by dense vegetation, will change to a
construction site which is partially visible with screen hoardings and
temporary landscape planting in daytime, but only near the end of Ap Lei Chau
Praya Road near the roundabout. In
night-time, the lighting from the Project area will also be
partially visible by this VSR at the same location. However, since night-time construction
activities are not expected, only minimal lighting, which is similar to the
existing lighting in the Project area, is expected to be
provided. Also, the lighting from
vessels will be more prominent than that from the Project area. The potential visual impact is
considered slight adverse for daytime and insubstantial for night-time
during the construction phase.
VSR4.3
Boat users in Aberdeen Channel
With mitigation, the existing unobstructed view of the
Project area, which is largely dominated by dense vegetation, will
change to a construction site which is partially visible with screen hoardings
and temporary landscape planting in daytime.
In night-time, the lighting from the Project area will also be partially visible by this VSR. However, since night-time construction
activities are not expected, only minimal lighting, which is similar to the
existing lighting in the Project area, is expected to be
provided. The potential visual impact is
considered slight adverse during the
construction phase for both daytime and night-time.
Potential
Visual Impacts with Mitigation during Operation
VSR1.1
Residents at Larvotto
With mitigation, the existing unobstructed view of the
Project area, which is largely dominated by dense vegetation, will be
replaced by the view of the Water Park dominated by hard structures such as
pools with landscape planting, green roofs and vertical greening, which are
still young in Day 1 as shown in Figure 12.12e. In night-time, the lighting from the Water
Park will be visible by this VSR as shown in Figure 12.12f. However, the overall lighting of the Water
Park is expected to be similar to the existing lighting in the Project area. In Day 1 of operation, the
potential visual impact is considered moderate adverse for daytime and slight adverse for night-time. In Year 10 of operation, the planting
within the Water Park will be mature and have a better screening effect on the
hard structures in daytime and lighting in night-time. The potential visual impact will be lessened
to slight adverse for daytime and insubstantial in night-time 10
years after completion of the Project.
VSR1.2
Residents at Lei Tung Estate
Since the existing view of this VSR is dominated by the
residential buildings of Larvotto, and the view of the Project area is barely visible, the potential visual impacts, both in the daytime
and night-time, are considered insubstantial during the operation phase (Day 1 and Year 10).
VSR2.1
Workers at Ocean Park
With mitigation, at locations where the Project area is visible within Ocean Park, the existing view, which is largely
dominated by dense vegetation, will be replaced by the view of the predominant
hard structures of the Water Park with pre-mature landscape planting, green
roofs and vertical greening in Day 1 of operation. The potential visual impact on this VSR is
considered slight adverse in Day 1 of
operation for both daytime and night-time.
As the landscape planting in the Water Park matures in Year 10 of
operation, thereby better screen off the hard structures in the daytime and
shield the lighting in night-time, the potential visual impact is expected to
be slight adverse for daytime and insubstantial in night-time in
Year 10 of operation.
VSR2.2
Staff and temporary residents at the planned Spa Hotel
Since construction of this hotel is not anticipated to
complete before completion of this Project, this VSR will not be present by Day
1 of operation. Potential visual impact
to this VSR is therefore not applicable by Day 1 of operation. However, by Year 10 of operation, with
mitigation, the existing view of the Project area, which is
dominated by dense vegetation but partially blocked by existing vegetation,
will be replaced by the view of the predominant hard structures of the Water
Park with landscape planting, green roofs and vertical greening, which can
screen the hard structures in the daytime and shield the lighting in
night-time, as shown in Figure 12.12i and Figure 12.12j. The potential
visual impact on this VSR is considered slight adverse for daytime and insubstantial in night-time in Year 10 of operation.
VSR2.3
Staff and temporary residents at the planned Fisherman's Wharf Hotel
Since construction of this hotel is not anticipated to
complete before completion of this Project, this VSR will not be present by Day
1 of operation. Potential visual impact
to this VSR is therefore not applicable by Day 1 of operation. However, by Year 10 of operation, with
mitigation, the existing view of the Project area, which is
dominated by dense vegetation but partially screened by roadside trees, will be
replaced by the view of the predominant hard structures of the Water Park with
roadside planting, landscape planting, green roofs and vertical greening, which
can screen the hard structures in the daytime and shield the lighting in night-time,
as shown in Figure 12.12g and Figure 12.12h. However, hard structures will still be
partially visible due to the short viewing distance. The potential visual
impact on this VSR is considered slight adverse for both daytime and night-time in Year 10 of operation.
VSR2.4
Workers at shipyards along the east coast of Yuk Kwai Shan
With mitigation, the existing view of the Project area, which is largely dominated by dense vegetation but often partially
obstructed by vessels in Aberdeen South Typhoon Shelter, will change to the
predominate hard structures of the Water Park with pre-mature landscape
planting, green roofs and vertical greening in Day 1 of operation. In night-time, the lighting from the Water
Park will also be partially visible by this VSR. However, the lighting from vessels will be
more prominent than that from the Water Park.
The potential visual impact is considered slight adverse for daytime and insubstantial in night-time in Day 1 of operation phase. In Year 10 of operation when the planting in
the Water Park matures and better screens the hard structures, the potential
visual impact as expected to be insubstantial for both daytime and night-time.
VSR3.1
Recreational users in Ocean Park
With mitigation, at locations where the Project area is visible within Ocean Park, the existing view, which is largely
dominated by dense vegetation, will be replaced by the view of the predominant
hard structures of the Water Park with pre-mature landscape planting, green
roofs and vertical greening in Day 1 of operation. The potential visual impact on this VSR is
considered slight adverse in Day 1 of
operation for both daytime and night-time.
As the landscape planting in the Water Park matures in Year 10 of
operation, thereby better screen off the hard structures in the daytime and
shield the lighting in night-time, the potential visual impact is expected to
be slight adverse for daytime and insubstantial in night-time.
VSR3.2
Hikers on Yuk Kwai Shan
With mitigation, the existing unobstructed view of the
Project area, which is largely dominated by dense vegetation, will
change to the predominant hard structures of the Water Park with pre-mature
landscape planting, green roofs and vertical greening in Day 1 of operation as
shown in Figure 12.12a. The
potential visual impact is considered slight adverse in daytime in Day 1 of operation. The potential visual impact will remain slight adverse in Year 10 of
operation because the hard structures of the Water Park will still be partially
visible even when the planting in the Water Park matures. In night-time, hiking activities are not
expected on this hiking trail because this trail is steep, not properly paved
and not equipped with any lighting. The
potential visual impact is therefore considered insubstantial for night-time during operation (Day 1 and Year 10).
VSR3.3
Hikers on the beach between Yuk Kwai Shan and Ap Lei Pai
With mitigation, the existing unobstructed view of the
Project area, which is largely dominated by dense vegetation, will
change to the predominant hard structures of the Water Park with pre-mature
landscape planting, green roofs and vertical greening in Day 1 of operation as
shown in Figure 12.2b. The
potential visual impact is considered slight adverse in daytime in Day 1 of operation. The potential visual impact will remain slight adverse in Year 10 of
operation because the hard structures of the Water Park will still be partially
visible even when the planting in the Water Park matures. In night-time, hiking activities are not
expected on this hiking trail because this trail is steep, not properly paved
and not equipped with any lighting. The
potential visual impact is therefore considered insubstantial for night-time during operation (Day 1 and Year 10).
VSR3.4
Hikers on Ap Lei Pai
With mitigation, the existing unobstructed view of the
Project area, which is largely dominated by dense vegetation, will
change to the predominant hard structures of the Water Park with pre-mature
landscape planting, green roofs and vertical greening in Day 1 of operation as
shown in Figure 12.12c. The
potential visual impact is considered slight adverse in daytime in Day 1 of operation. The potential visual impact will remain slight adverse in Year 10 of
operation because the hard structures of the Water Park will still be partially
visible even when the planting in the Water Park matures. In night-time, hiking activities are not
expected on this hiking trail because this trail is steep, not properly paved
and not equipped with any lighting. The
potential visual impact is therefore considered insubstantial for night-time during operation (Day 1 and Year 10).
VSR3.5
Hikers on Brick Hill
With mitigation, the existing partially obstructed view of
the Project area, which is largely dominated by dense vegetation, will
change to the predominant hard structures of the Water Park with pre-mature
landscape planting, green roofs and vertical greening in Day 1 of
operation. The potential visual impact
is considered slight
adverse
in daytime in Day 1 of operation. The
potential visual impact will remain slight adverse in Year 10 of operation because the hard structures of the
Water Park will still be partially visible even when the planting in the Water
Park matures. In night-time, hiking
activities are not expected in most parts of the hiking trails, but night-time
visitors to the Nam Long Shan Road Rest Garden, particularly in special
occasions, such as the Mid-autumn Festival, is expected. However, the overall number of night-time
visitors is expected to be low. The potential
visual impact is therefore considered insubstantial for night-time during operation (Day 1 and Year 10).
VSR4.1
Travellers along Shum Wan Road
With mitigation, the existing partially obstructed view of
the Project area, which is largely dominated by dense vegetation, will
change to the predominant hard structures of the Water Park with pre-mature
landscape planting, green roofs and vertical greening in daytime Day 1 of
operation. In night-time, the lighting
from the Water Park will also be visible by this VSR. However, the overall lighting of the Water
Park is expected to be similar to the existing lighting in the Project
area. The potential visual impact is
considered slight adverse in Day 1 of
operation for both daytime and night-time.
In Year 10 of operation, when planting within the Water Park becomes
mature, hard structures and lighting will be further screened by
vegetation. However, given the
potentially short viewing distance, the potential visual impact will remain slight adverse in Year 10 of
operation for both daytime and night-time.
VSR4.2
Travellers along Ap Lei Chau Praya Road
With mitigation, the existing view of the Project area,
which is largely dominated by dense vegetation, will change to the predominant
hard structures of the Water Park with pre-mature landscape planting, green
roofs and vertical greening in Day 1 of operation. This view is visible only at the end of Ap
Lei Chau Praya Road near the roundabout.
In night-time, the lighting from the Water Park will also be partially
visible by this VSR at the same location.
However, the overall lighting of the Water Park is expected to be
similar to the existing lighting in the Project area. Also, the lighting from vessels will be more
prominent than that from the Project area.
The potential visual impact is considered slight adverse for daytime and insubstantial for night-time in Day 1 of operation. As the landscape planting with the Water Park
matures and further screens the hard structures, the potential visual impact
will become insubstantial for both daytime
and night-time 10 years after completion of the Project.
VSR4.3
Boat users in Aberdeen Channel
With mitigation, the existing unobstructed view of the
Project area, which is largely dominated by dense vegetation, will change to
the predominant hard structures of the Water Park with pre-mature landscape
planting, green roofs and vertical greening in Day 1 of operation as shown in Figure
12.12d. In night-time, the lighting
from the Water Park will also be visible by this VSR. However, the overall lighting of the Water
Park is expected to be similar to the existing lighting in the Project
area. The potential visual impact is
considered slight adverse in Day 1 of
operation for both daytime and night-time.
In Year 10 of operation, the mature planting will better screen off the
hard structures, which will still be partially visible by this VSR. Given the potentially short viewing distance,
the potential visual impact is expected to remain slight adverse 10 years after
completion of the Project for both daytime and night-time.
Table 12.17 summarises the results of the visual impact assessment, which are also
illustrated in Figure 12.11.
Table 12.17: Visual Impact Assessment
ID No.
|
VSR Name
|
Significance Threshold (Unmitigated)
(Insubstantial / Slight / Moderate / Significant)
|
Proposed Mitigation Measures
|
Significance Threshold (Mitigated) (Insubstantial
/ Slight / Moderate / Significant)
|
Construction
|
Operation
|
Construction
|
Operation (Day 1)
|
Operation (Year 10)
|
VSR1.1
|
Residents at
Larvotto
|
Moderate adverse
(daytime and night-time)
|
Moderate
adverse (daytime and night-time)
|
CP01; CP02; CP03; CP04; CP05; CP07; CP08; CP09; CP10; CP11; CP12;
OP01; OP02; OP03; OP04; OP06; OP07
|
Moderate adverse in
daytime;
slight adverse in night-time
|
Moderate adverse in
daytime;
slight adverse in night-time
|
Slight adverse in
daytime;
insubstantial in night-time
|
VSR1.2
|
Residents at Lei
Tung Estate
|
Insubstantial
(daytime and night-time)
|
Insubstantial
(daytime and night-time)
|
-
|
Insubstantial (daytime and night-time)
|
Insubstantial (daytime and night-time)
|
Insubstantial (daytime and night-time)
|
VSR2.1
|
Workers at Ocean
Park
|
Slight
adverse (daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
CP01; CP02; CP03; CP04; CP05; CP07; CP08; CP09; CP10; CP11; CP12;
CP13; OP01; OP02; OP03; OP04; OP06; OP07
|
Slight adverse (daytime and night-time)
|
Slight adverse (daytime and night-time)
|
Slight adverse in
daytime;
insubstantial in night-time
|
VSR2.2
|
Staff and temporary
residents at the planned Spa Hotel
|
N/A
|
N/A for Day 1;
slight adverse (daytime and night-time) for Year 10
|
OP01; OP02; OP03; OP04; OP06; OP07
|
N/A
|
N/A
|
Slight adverse in
daytime;
insubstantial in night-time
|
VSR2.3
|
Staff and temporary
residents at the planned Fisherman's Wharf Hotel
|
N/A
|
N/A for Day 1;
slight adverse (daytime and night-time) for Year 10
|
OP01; OP02; OP03; OP04; OP06; OP07
|
N/A
|
N/A
|
Slight adverse (daytime and night-time)
|
VSR2.4
|
Workers at
shipyards along the east coast of Yuk Kwai Shan
|
Slight
adverse (daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
CP01; CP02; CP03; CP04; CP05; CP07; CP08; CP09; CP10; CP11; CP12;
OP01; OP02; OP03; OP04; OP06; OP07
|
Slight adverse (daytime and night-time)
|
Slight adverse in
daytime;
insubstantial in night-time
|
Insubstantial (daytime and night-time)
|
VSR3.1
|
Recreational users
in Ocean Park
|
Slight
adverse (daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
CP01; CP02; CP03; CP04; CP05; CP07; CP08; CP09; CP10; CP11; CP12;
CP13; OP01; OP02; OP03; OP04; OP06; OP07
|
Slight adverse (daytime and night-time)
|
Slight adverse (daytime and night-time)
|
Slight adverse in
daytime;
insubstantial in night-time
|
VSR3.2
|
Hikers on Yuk Kwai
Shan
|
Slight adverse
(daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
CP01; CP02; CP03; CP04; CP05; CP07; CP08; CP09; CP10; CP11; CP12;
OP01; OP02; OP03; OP04; OP06; OP07
|
Slight adverse in
daytime;
insubstantial in night-time
|
Slight adverse in
daytime;
insubstantial in night-time
|
Slight adverse in
daytime;
insubstantial in night-time
|
VSR3.3
|
Hikers on the beach
between Yuk Kwai Shan and Ap Lei Pai
|
Slight adverse
(daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
CP01; CP02; CP03; CP04; CP05; CP07; CP08; CP09; CP10; CP11; CP12;
OP01; OP02; OP03; OP04; OP06; OP07
|
Slight adverse in
daytime;
insubstantial in night-time
|
Slight adverse in
daytime;
insubstantial in night-time
|
Slight adverse in
daytime;
insubstantial in night-time
|
VSR3.4
|
Hikers on Ap Lei
Pai
|
Slight adverse
(daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
CP01; CP02; CP03; CP04; CP05; CP07; CP08; CP09; CP10; CP11; CP12;
OP01; OP02; OP03; OP04; OP06; OP07
|
Slight adverse in
daytime;
insubstantial in night-time
|
Slight adverse in
daytime;
insubstantial in night-time
|
Slight adverse in
daytime;
insubstantial in night-time
|
VSR3.5
|
Hikers on Brick Hill
|
Slight adverse
(daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
CP01; CP02; CP03; CP04; CP05; CP07; CP08; CP09; CP10; CP11; CP12;
OP01; OP02; OP03; OP04; OP06; OP07
|
Slight adverse in
daytime;
insubstantial in night-time
|
Slight adverse in
daytime;
insubstantial in night-time
|
Slight adverse in
daytime;
insubstantial in night-time
|
VSR4.1
|
Travellers along Shum Wan Road
|
Slight
adverse (daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
CP01; CP02; CP03; CP04; CP05; CP07; CP08; CP09; CP10; CP11; CP12;
OP01; OP02; OP03; OP04; OP06; OP07
|
Slight adverse (daytime and night-time)
|
Slight adverse (daytime and night-time)
|
Slight adverse (daytime and night-time)
|
VSR4.2
|
Travellers along Ap Lei Chau
Praya Road
|
Slight
adverse (daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
CP01; CP02; CP03; CP04; CP05; CP07; CP08; CP09; CP10; CP11; CP12;
OP01; OP02; OP03; OP04; OP06; OP07
|
Slight adverse in
daytime;
insubstantial in night-time
|
Slight adverse in
daytime;
insubstantial in
night-time
|
Insubstantial (daytime and night-time)
|
VSR4.3
|
Boat users in Aberdeen Channel
|
Slight
adverse (daytime and night-time)
|
Slight
adverse (daytime and night-time)
|
CP01; CP02; CP03; CP04; CP05; CP07; CP08; CP09; CP10; CP11; CP12;
OP01; OP02; OP03; OP04; OP06; OP07
|
Slight adverse (daytime and night-time)
|
Slight adverse (daytime and night-time)
|
Slight adverse (daytime and night-time)
|
No interfacing or concurrent
project has been identified as stated in Section 2.12. No cumulative landscape and
visual impact is therefore anticipated.
12.13 Summary
Review
of Planning and Development Control Framework
The entire Project area is
within the land use type Other Specified Uses OU for Ocean Park
only. The planning intention of this
zone is primarily for comprehensively planed low-density and generally low- to
medium-rise marine-themed park development in Hong Kong with related retail,
dining and entertainment facilities serving visitors as well as the general
public. Height restrictions apply to
buildings in this zone. The Project is
in line with the planning intention of this OU zone. No re-zoning under Section 12A of the Town
Planning Ordinance will be required for the implementation of the Project. However, should the building height
restrictions of this OU zone be violated by the proposed redevelopment,
planning application under Section 16 of the Town Planning Ordinance will be
required.
Summary
of Potential Impact on Existing Trees
To facilitate implementation of
the Project, 70 dead trees are proposed to be removed, 1 tree is recommended to
be retained on site with pruning, 65 trees are proposed to be transplanted, and
1,613 trees (including 84 Leucaena
leucocephala) are proposed to be felled.
Compensatory tree planting will be provided as far as practicable to
compensate for the loss of existing trees due to this Project. Recommended on-site compensatory tree planting
includes approximately 608 heavy standard trees (with DBH 0.1m) and approximately
18,202 whip trees (with DBH 0.01m).
Off-site compensation will be further explored as far as practicable
within the lot boundary of Ocean Park, such as the area currently occupied by
project site office which has a potential of accommodating approximately 120
nos. of heavy standard trees. The
availability of off-site compensatory tree planting area is still subject to
further investigation and agreement with relevant authorities.
Summary
of Sources of Potential Landscape and Visual Impacts
During the construction phase, sources of potential
landscape and visual impacts would arise from the following:
§ Site
clearance for the proposed structures, particularly at the existing woodland
and tall shrubland area.
During the operation phase, sources of potential landscape
and visual impacts would arise from the following:
§ Operation
of the Indoor Zone of the Water Park (with a wave pool, lazy river, play
structure, water slides, surf-rider, various pools, F&B facilities, E&M
utilities, back of house and car-parking;
§ Operation
of the Outdoor Zone of the Water Park (with a wave pool, lazy river, water
slides, ride platforms, various pools, sea turtle exhibit and some
small-scale F&B facilities; and
§ Operation
of the General Approach Area with coach and taxi drop-off point and EVA.
Summary
of Recommended Landscape and Visual Mitigation Measures
Proposed construction phase
mitigation measures comprise the following (described in detail in Table 12.13):
CP01 Minimisation of
Construction Period;
CP02 Minimisation of Works
Areas;
CP03 Construction Site
Controls;
CP04 Preservation of
Existing Vegetation;
CP05 Transplantation of
Existing Trees;
CP06 No Intrusion Zones;
CP07 Temporary Tree
Nurseries;
CP08 Advance Planting;
CP09 Construction Site
Hoardings;
CP10 Dust and Erosion
Control for Exposed Soil;
CP11 Appearance of
Construction Plant / Machinery;
CP12 Construction Lighting
Control; and
CP13 Appearance of
Construction Workers.
Proposed operation phase
mitigation measures comprise the following (described in detail in Table 12.14):
OP01 Sensitive Design and
Disposition;
OP02 Compensatory Tree
Planting;
OP03 Enhancement Planting;
OP04 Green Roofs and
Vertical Greening;
OP05 Reprovision of
Flamingo Pond;
OP06 Responsive Lighting
Design; and
OP07 Woodland
Compensation.
Summary
of Predicted Landscape and Visual Impacts
Construction Phase
The following LRs are expected
to receive a significant adverse residual impact during
construction.
LR2.2 Roadside
planting;
LR4.2 Pond; and
LR4.3 Stream.
The following LRs, LCA and VSR
are expected to receive a moderate adverse residual impact during
construction.
LR1.4 Woodland;
LR2.1 Plantation
on modified slopes;
LR2.3 Amenity
planting;
LCA1 Theme park; and
VSR1.1 Residents at
Larvotto (daytime).
The following LRs and VSRs are
expected to receive a slight adverse residual impact during
construction.
LR1.1 Tall shrubland;
LR1.2 Shrubland;
VSR1.1 Residents at
Larvotto (night-time);
VSR2.1 Workers at
Ocean Park (daytime and night-time);
VSR2.4 Workers at
shipyards along the east coast of Yuk Kwai Shan (daytime and night-time);
VSR3.1 Recreational
users in Ocean Park (daytime and night-time);
VSR3.2 Hikers on Yuk
Kwai Shan (daytime);
VSR3.3 Hikers on the
beach between Yuk Kwai Shan and Ap Lei Pai (daytime);
VSR3.4 Hikers on Ap
Lei Pai (daytime);
VSR3.5 Hikers on
Brick Hill (daytime);
VSR4.1 Travellers
along Shum Wan Road (daytime and night-time);
VSR4.2 Travellers
along Ap Lei Chau Praya Road (daytime); and
VSR4.3 Boat users in
Aberdeen Channel (daytime and night-time).
Potential impact is
not applicable to the following VSRs during construction.
VSR2.2 Staff and
temporary residents at the planned Spa Hotel; and
VSR2.3 Staff and
temporary residents at the planned Fishermans Wharf Hotel.
All other LRs, LCAs and VSRs are
expected to experience insubstantial residual impact during
construction.
Day 1 of Operation Phase
The following LRs and VSR are
expected to receive a moderate adverse residual impact in Day
1 of operation.
LR1.4 Woodland;
LR2.1 Planting on
modified slopes;
LR2.2 Roadside
planting;
LR2.3 Amenity
planting;
LR4.3 Stream; and
VSR1.1 Residents at
Larvotto (daytime).
The following LRs, LCA and VSRs
are expected to receive a slight adverse residual impact in Day
1 of operation.
LR1.1 Tall shrubland;
LR1.2 Shrubland;
LR4.2 Pond;
LCA1 Theme park;
VSR1.1 Residents at
Larvotto (night-time);
VSR2.1 Workers at
Ocean Park (daytime and night-time);
VSR2.4 Workers at
shipyards along the east coast of Yuk Kwai Shan (daytime);
VSR3.1 Recreational
users in Ocean Park (daytime and night-time);
VSR3.2 Hikers on Yuk
Kwai Shan (daytime);
VSR3.3 Hikers on the
beach between Yuk Kwai Shan and Ap Lei Pai (daytime);
VSR3.4 Hikers on Ap
Lei Pai (daytime);
VSR3.5 Hikers on
Brick Hill (daytime);
VSR4.1 Travellers
along Shum Wan Road (daytime and night-time);
VSR4.2 Travellers along
Ap Lei Chau Praya Road (daytime); and
VSR4.3 Boat users in
Aberdeen Channel (daytime and night-time).
Potential impact is not applicable to the following VSRs in
Day 1 of operation.
VSR2.2 Staff and temporary residents at the planned Spa
Hotel; and
VSR2.3 Staff and temporary
residents at the planned Fishermans Wharf Hotel.
All other LRs, LCAs and VSRs are
expected to experience insubstantial residual impact in Day
1 of operation.
Year 10 of Operation Phase
The following LR is expected to
receive a moderate adverse residual impact in Year 10 of
operation.
LR4.3 Stream.
The following LRs and VSRs are
expected to receive a slight adverse residual impact in
Year 10 of operation.
LR1.4 Woodland;
LR2.1 Planting on
modified slopes;
LR2.2 Roadside
planting;
LR2.3 Amenity
planting;
LR4.2 Pond;
VSR1.1 Residents in
Larvotto (daytime);
VSR2.1 Workers at
Ocean Park (daytime);
VSR2.2 Staff and
temporary residents at the planned Spa Hotel (daytime);
VSR2.3 Staff and
temporary residents at the planned Fishermans Wharf Hotel (daytime and
night-time);
VSR3.1 Recreational
users in Ocean Park (daytime);
VSR3.2 Hikers on Yuk
Kwai Shan (daytime);
VSR3.3 Hikers on the
beach between Yuk Kwai Shan and Ap Lei Pai (daytime);
VSR3.4 Hikers on Ap
Lei Pai (daytime);
VSR3.5 Hikers on
Brick Hill (daytime);
VSR4.1 Travellers
along Shum Wan Road (daytime and night-time); and
VSR4.3 Boat users in
Aberdeen Channel (daytime and night-time).
All other LRs, LCAs and VSRs are
expected to experience insubstantial residual impact in
Year 10 of operation.
Landscape
Impact
With the implementation of
proposed mitigation measures, the anticipated landscape impacts are generally
moderate adverse to insubstantial during the construction phase due to site
clearance and removal of existing vegetation.
Upon completion of the Project, compensatory planting, enhancement
planting, green roofs and vertical greening will be provided to compensate for
the loss of vegetation during construction.
A new Flamingo Pond will also be constructed to replace the removed
semi-natural ponds. However, the loss of
some of the landscape resources will not be fully compensated. The residual landscape impact in operation
phase is therefore generally insubstantial with slight adverse impacts expected
for some landscape resources.
Visual
Impact
With the implementation of
proposed mitigation measures, the anticipated visual impacts are generally
slight adverse to insubstantial for daytime and largely insubstantial for night-time
during the construction phase due to unobstructed or partially obstructed views
of construction activities and screen hoarding.
Upon completion of the Project, planting within the proposed Project can
act as visual screen to visual sensitive receivers. The residual visual impact in operation phase
is generally slight adverse to insubstantial in daytime and largely
insubstantial in night-time with slight adverse impacts expected on some VSRs.
Overall
Acceptability
Overall, in terms of Annex 10,
Clause 1.1 (c) of the EIAO TM, it is concluded that the landscape and visual
impacts are acceptable with mitigation measures.