Chapter Title
Tables
Table 5.1:__ Noise
Standards for Daytime Construction Activities
Table 5.2:__ Relevant
Road Traffic Noise Standards for Planning Purposes
Table 5.3:__ Area
Sensitivity Rating
Table 5.4:__ Acceptable
Noise Level for Fixed Noise Source
Table 5.5:__ Noise
Criteria for Fixed Plant Noise
Table 5.6:__ Representative
Noise Sensitive Receivers
Table 5.7: __ Projected Background Traffic Flows at
Concerned Road Links (2015) - Maximum_
Table 5.8:__ Projected
Traffic Flows at Concerned Road Links (Year 2015) – Minimum
Table 5.9:__ Unmitigated
Construction Airborne Noise Impact
Table 5.10:_ Road
Traffic Noise in Year 2032
Table 5.11:_ Maximum
Allowable SWLs of Fixed Noise Sources
Table 5.12:_ Correction
Factor for Maximum Allowable SWL of the Open Air Entertainment Activities
Table 5.13:_ Quiet
PME Recommended for Adoption during Construction Phase
Table 5.14:_ Noise
Mitigation Measures for Certain PME during Construction Phase
Table 5.15:_ Mitigated
Construction Airborne Noise Impact
Figures
Figure 5.1 Locations
of Representative Noise Sensitive Receivers
Figure 5.2 Photos
of Representative Receivers
Figure 5.3 Locations
of Background Noise Measurement
Figure 5.4 Location
of Open Air Entertainment Noise Assessment
Figure 5.5 Locations
of Proposed Fixed Plant Noise Sources
Figure 5.5a Locations
of Proposed Fixed Plant Noise Sources (Sections)
Figure 5.6 Schematic
Configuration of Movable Noise Barriers
Appendices
Appendix 5.1 Measured Background Noise Levels
Appendix 5.2 Road Traffic Network
Appendix 5.3 Traffic Flow in Year 2032
Appendix 5.4 Unmitigated Construction Plant Inventory
and Noise Impact
Appendix 5.5 Unmitigated Road Traffic Noise Impact
Appendix 5.6 Fixed Plant Noise Impact Assessments
Appendix 5.7 Mitigated Construction Plant Inventory
and Noise Impact
Control over the generation of construction noise in Hong Kong is governed by the Noise Control Ordinance (NCO) and the Environmental Impact Assessment Ordinance (EIAO) and their subsidiary requirements. Various Technical Memoranda (TMs) have been issued under the NCO and the EIAO to stipulate control approaches and criteria. These TMs prescribe the maximum permitted noise levels for the use of Powered Mechanical Equipment (PME) and certain construction activities and processes, according to the type of equipment or activity, the perceived noise climate of the area, and the working hours of equipment operation and usage. The TMs applicable to the control of noise form construction activities of proposed construction works are:
· TM on Environmental Impact Assessment Process (EIAO-TM)
· TM on Noise from Construction Work other than Percussive Piling (GW-TM)
· TM on Noise from Construction Work in Designated Areas (DA-TM)
Table 5.1: Noise Standards for Daytime Construction Activities
Noise Sensitive Use |
0700 to 1900 hours on any day not being a Sunday or
general holiday, Leq (30 min),
dB(A) |
All domestic premises including temporary housing accommodation |
75 |
Hotels and hostel |
|
Educational institutions including kindergarten, nurseries and all others where unaided voice communications is required |
70 65 during examination |
Source: EIAO-TM, Annex 5, Table 1B – Noise Standards for Daytime Construction Activities
Note: The above noise standards apply to uses,
which rely on opened windows for ventilation
The above standards shall be viewed as the maximum
permissible noise levels assessed at 1 m from the external facade
The above standards shall be met as far as possible. All practicable mitigation
measures shall be exhausted and the residual impacts are minimised
Road
Traffic Noise
Table 5.2: Relevant Road Traffic Noise Standards for Planning Purposes
Uses |
Road Traffic Noise Peak Hour Traffic L10 (1hour), dB(A) |
All domestic premises including temporary housing accommodation |
70 |
Educational institutions including kindergartens, nurseries and all others where unaided voice communication is required |
65 |
Notes: (i) The above
standards apply to uses which rely on opened windows for ventilation
(ii) The above standards should be viewed as the maximum permissible noise
levels assessed at 1m from the external facade
Table 5.3: Area Sensitivity Rating
Type of Area Containing NSR |
Degree to which NSR is affected by IF |
||
Not Affected |
Indirectly Affected |
Directly Affected |
|
(i) Rural area, including country parks or village type developments |
A |
B |
B |
(ii) Low density residential area consisting of low-rise or isolated high-rise developments |
A |
B |
C |
(iii) Urban area |
B |
C |
C |
(iv) Area other than those above |
B |
B |
C |
Table 5.4: Acceptable Noise Level for Fixed Noise Source
|
Area Sensitivity Rating (ASR) |
||
Time Period |
A |
B |
C |
Day
(0700 to 1900 hours) |
60 |
65 |
70 |
Evening
(1900 to 2300 hours) |
|||
Night
(2300 to 0700 hours) |
50 |
55 |
60 |
Table 5.5: Noise Criteria for Fixed Plant Noise
NSR ID. |
Time Period |
ASR* |
ANL-5, dB(A) |
Background Noise Level, dB(A)# |
Fixed Plant Noise Criteria |
|
VSA |
Daytime (0700 to 1900) |
C |
65 |
55 |
55 |
|
HKJCC |
Daytime (0700 to 1900) |
B |
60 |
53 |
53 |
|
|
Evening Time (1900 – 2300) |
60 |
50 |
50 |
||
Notes: (*) NSR “VSA” is within 100m of a zone designated as “Industrial” and NSR “HKJCC” is between 100 m and 250 m from “Industrial” zone.
(#) Background noise measurement results are shown in Appendix 5.1.
Potential noise impact from open air entertainment activity is considered as fixed noise in this EIA report. Therefore, the noise standard for fixed noise sources as stipulated in Annex 5 of the EIAO-TM and described above will be adopted in assessing open air entertainment activity noise as well.
Description of the Environment
Identification of Noise Sensitive Receivers
Table 5.6: Representative Noise Sensitive Receivers
No. |
NSR ID |
Description |
Use* |
Existing or
Planned# |
No. of Storeys^ |
1st Assessment Level (mPD) |
ASR |
Noise Impact Assessment |
|||
Constr-uction |
Road Traffic |
Fixed Plant |
Open Air Entertai-nment |
||||||||
1 |
VSA |
Victoria Shanghai Academy |
E |
E |
7 |
10.5 |
C |
√ |
√ |
√ |
√ |
2 |
HKJCC |
Hong Kong Juvenile Care Centre |
E |
E |
4 |
72.5 |
B |
√ |
√ |
√ |
√ |
3 |
BC |
Broadview Court |
R |
E |
38 |
28.8 |
B |
|
√ |
|
|
4 |
SWC |
South Wave Court |
R |
E |
34 |
30.3 |
B |
|
√ |
|
|
5 |
WCH1 |
Planned Development on Wong Chuk
Hang Station Depot (Tower 1) |
R |
P |
28 |
16.3 |
C |
|
√ |
|
|
6 |
WCH2 |
Planned Development on Wong Chuk
Hang Station Depot |
R |
P |
29 |
16.7 |
C |
|
√ |
|
|
7 |
WCH3 |
Planned Development on Wong Chuk
Hang Station Depot (Tower 9) |
R |
P |
35 |
17.9 |
C |
|
√ |
|
|
8 |
GG |
Grandview Garden |
R |
E |
25 |
36.7 |
C |
|
√ |
|
|
Note: *
Use: E = Educational, R = Residential
# Existing/planned: E = Existing, P = Planned
^ Sensitive use only
Background Noise Condition
The contribution to the existing heavily trafficked Wong Chuk Hang Road, Nam Long Shan Road, Shum Wan Road, Heung Yip Road and Police School Road is expected to be limited. According to the 2012 Annual Traffic Census, the annual average daily traffic of Wong Chuk Hang Road and Nam Long Shan Road are 66,800 veh/day and 2,360 veh/day respectively.
The projected maximum traffic flows in 2015
of the concerned major road links within the assessment area and their
corresponding capacities are shown in Table 5.7. The
estimated minimum overall traffic flows with construction traffic along the
concerned road links are shown in Table 5.8.
Table 5.7: Projected Background Traffic Flows at Concerned Road Links (2015) - Maximum
Concerned Roads Links |
Traffic flow (veh/hr) - Year 2015 |
|||
Without Project(1) |
With Project(2) |
Difference |
Capacity(3) |
|
Maximum
(4) |
|
|
|
|
A.
Wong Chuk Hang Road |
4,795 |
4,810 |
+15 |
5,550 |
B.
Nam Long Shan Road |
1,415 |
1,285 |
-130 |
2,400 |
C.
Shum Wan Road |
1,045 |
1,025 |
-20 |
1,600 |
D.
Heung Yip Road |
1,640 |
1,515 |
-125 |
3,400 |
E.
Police School Road |
1,105 |
980 |
-125 |
1,600 |
(1) Assume second entrance is still in operation without the construction of the Project
(2) Assume second entrance is closed while with the construction vehicles access to the Project
(3) Capacity used in the EIA traffic forecast
(4) Traffic flow during the project construction hours.
Table 5.8: Projected Traffic Flows at Concerned Road
Links (Year 2015) – Minimum
Concerned Roads Links |
Traffic flow (veh/hr) - Year 2015 |
|||
Without Project(1) |
With Project(2) |
Difference |
Capacity(3) |
|
Minimum
(4) |
|
|
|
|
A. Wong Chuk
Hang Road |
4,485 |
4,500 |
+15 |
5,550 |
B. Nam Long Shan Road |
875 |
755 |
-120 |
2,400 |
C. Shum Wan Road |
940 |
710 |
-230 |
1,600 |
D. Heung Yip Road |
1,325 |
1,205 |
-120 |
3,400 |
E. Police School Road |
685 |
565 |
-120 |
1,600 |
(1) Assume second entrance is still in operation without the construction of the Project
(2) Assume second entrance is closed while with the construction vehicles access to the Project
(3) Capacity used in the EIA traffic forecast
(4) Traffic flow during the project construction hours.
It is noted that the estimated flow of “Maximum Hour with Construction Traffic” and “Minimum Hour with Construction Traffic” scenario for the concerned road links (except Wong Chuk Hang Road) are below “Maximum Hour without Construction Traffic” and “Minimum Hour without Construction Traffic”. All concerned road links are estimated to be operating within their capacity during the construction phase.
During the construction phase, the current second entrance gate to the Ocean Park along Shum Wan Road is assumed to be closed and the associated traffic from tourist coaches is diverted. The construction vehicles are assumed to use Shum Wan Road, however, the volume of construction vehicles is less than the coach volume and therefore a decrease in traffic along Nam Long Shan Road, Shum Wan Road, Heung Yip Road and Police School Road is expected.
For Wong Chuk Hang Road, estimated traffic flow of Maximum Hour and Minimum Hour with construction traffic is 15 veh/hr higher than that of without construction traffic, i.e., about 0.3% increased only. Minor increase to Wong Chuk Hang Road due to construction traffic and the associated coach diversion is expected. The trucks movement would be within acceptable speed limit. Therefore, potential noise impact from the movements of construction trucks would unlikely be significant.
The Project does not comprise of a designated venue for open air entertainment. However, open air entertainment activities are expected to occur at various locations within the Project at different times of the day. Noise impact from these open air shows is expected due to the use of sound amplification systems for voice and potentially instrumental music. In addition, temporary open air shows and indoor attractions at the Summit of the existing Ocean Park during special event would likely to generate noise impacts.
§ Scenario without the Project at the design year;
§ Unmitigated scenario at assessment year;
§ Mitigated scenario at assessment year; and
§ Prevailing scenario for indirect technical remedies eligibility assessment, if applicable.
Open
Air Entertainment Noise
The open air shows during operation phase are expected to be held at various locations at non-designated time periods. Majority of the open area accessible by visitors may hold such open air shows at various times, with the aim to spread guests across the Ocean Park. As such, as a conservative approach, area which shows may potentially be held that is closest to the nearest NSR has been set as assessment point. This assessment point would represent the worst case scenario where nearby NSRs are expected to be the most affected should shows are held at this location, given the close proximity, when compared to other open areas. The chosen assessment point is shown in Figure 5.4.
The maximum allowable SWLs at the chosen assessment point have been determined for future detailed operation planning. The SWLs were determined by adopting standard acoustics principles, equivalent to those used in fixed plant noise assessment, as discussed above.
Where NSR has no direct line of sight to the assessment point as it is blocked by buildings or natural terrains, a 10 dB(A) attenuation would be applied. If exceedance to the noise criteria is found, the SWL of the source would be gradually lowered until the corrected SPL at all NSRs complies with the relevant criteria.
Fixed plants are expected to operate throughout the entire opening hours, where open air entertainment activities will be occurring irregularly. Therefore, impact from both fixed noise sources at the same time is anticipated. As such, cumulative assessment of fixed plant noise and open air entertainment has been assessed. The maximum allowable SWLs have been determined under the cumulative scenario as a conservative approach. Potential noise impact from temporary open air shows and indoor attractions at the Summit of the existing Ocean Park during special event, as shown in Figure 5.5, have also been included in the cumulative assessment.
Table 5.9: Unmitigated Construction Airborne Noise Impact
NSR ID |
Use |
Predicted Noise Level, dB(A) |
Noise Criteria, dB(A) |
Exceedance of Noise Criteria |
Exceedance of Noise Criteria during Examination Period |
Mitigation Measure required? |
VSA |
Educational |
59-67 |
70 or 65 during examination |
No |
Yes |
During Examination Only |
HKJCC |
Educational |
59-68 |
70 or 65 during examination |
No |
Yes |
During Examination Only |
Note: Bold figures denote exceedance in relevant noise criteria.
Table 5.10: Road Traffic Noise in Year 2032
NSR ID |
Noise Criteria |
Without Project |
With Project |
Difference |
||
Predicted Noise Level L10(1hr) dB(A) |
Exceedance of Noise Criteria? |
Predicted Noise Level L10(1hr) dB(A) |
Exceedance of Noise Criteria? |
|||
VSA |
65 |
76-79 |
Yes |
76-80 |
Yes |
0.1 |
HKJCC |
65 |
70 |
No |
70 |
No |
0.0-0.1 |
BC |
70 |
68-73 |
Yes |
68-73 |
Yes |
0.0-0.1 |
SWC |
70 |
72-76 |
Yes |
72-77 |
Yes |
0.0-0.1 |
WCH1 |
70 |
51-75 |
Yes |
51-75 |
Yes |
0.0-0.1 |
WCH2 |
70 |
50-71 |
Yes |
50-71 |
Yes |
0.0-0.2 |
WCH3 |
70 |
51-74 |
Yes |
52-74 |
Yes |
0.1-0.2 |
GG |
70 |
71-79 |
Yes |
71-79 |
Yes |
0.0 |
Source: Bold figures denote exceedance of relevant noise criteria.
Table 5.11: Maximum Allowable SWLs of Fixed Noise Sources
|
Source ID |
Noise Source Description |
Maximum Allowable SWL, dB(A)* at both day and evening time |
|
|
|
|
Fixed Plant |
|||
|
N1 |
Pool Filtration
Plant Room |
82 |
|
N2 |
Pool Filtration
Plant Room |
82 |
|
N3 |
Pool Filtration
Plant Room |
82 |
|
N4 |
Pump Room |
82 |
|
N5 |
Plumbing Service
Plant Room |
82 |
|
N6 |
Pool Filtration
Plant Room |
82 |
|
N7 |
Pool Filtration
Plant Room |
83 |
|
N8 |
Pool Filtration
Plant Room |
83 |
|
N9 |
Pool Filtration
Plant Room |
83 |
|
N10 |
Boiler Plant |
83 |
|
N11 |
Boiler Plant |
83 |
|
N12 |
Chiller Plant |
83 |
|
N13 |
Calorifier Room |
83 |
|
N14 |
Water Meter Room |
83 |
|
N15 |
Water Meter Room |
83 |
|
N16 |
Shower Room |
82 |
|
N17 |
Shower Room |
82 |
|
N18 |
Shower Room |
82 |
|
N19 |
Shower Room |
82 |
|
N20 |
Shower Room |
82 |
|
N21 |
Kitchen |
83 |
|
N22 |
Air Handling Unit /
Fan |
83 |
|
N23 |
Air Handling Unit /
Fan |
83 |
|
N24 |
Washroom |
83 |
|
N25 |
Kitchen |
83 |
|
N26 |
Fan Room |
83 |
|
N27 |
Kitchen |
83 |
|
N28 |
Transfer Room |
83 |
|
N29 |
Generator Room |
83 |
|
N30 |
Washroom |
83 |
|
N31 |
Food and Beverage |
83 |
|
N32 |
Air Ventilation |
83 |
|
N33 |
Air Ventilation |
83 |
|
N34 |
Air Ventilation |
83 |
|
N35 |
Air Ventilation |
83 |
|
N36 |
Air Ventilation |
83 |
|
N37 |
Air Ventilation |
83 |
|
N38 |
Air Ventilation |
83 |
|
N39 |
Air Ventilation |
83 |
|
N40 |
Shower Room |
82 |
|
N41 |
Transformer Room |
82 |
|
N42 |
Transformer Room |
82 |
|
N43 |
Transformer Room |
82 |
|
N44 |
Transformer Room |
82 |
|
N45 |
Transformer Room |
82 |
|
N46 |
Transformer Room |
82 |
|
N47 |
Transformer Room |
82 |
|
N48 |
Transformer Room |
82 |
|
N49 |
Shower Room |
82 |
|
N50 |
Air Ventilation |
82 |
|
N51 |
Air Ventilation |
82 |
|
N52 |
Washroom |
83 |
|
N53 |
Washroom |
82 |
|
N54 |
Cooling Tower |
82 |
|
N55 |
Cooling Tower |
82 |
|
N56 |
Cooling Tower |
82 |
|
N57 |
Cooling Tower |
82 |
|
N58 |
Cooling Tower |
82 |
|
N59 |
Cooling Tower |
82 |
|
N60 |
Cooling Tower |
82 |
|
N61 |
Cooling Tower |
82 |
|
N62 |
Cooling Tower |
83 |
|
N63 |
Cooling Tower |
83 |
|
N64 |
Cooling Tower |
83 |
|
N65 |
Cooling Tower |
83 |
|
N66 |
Air Handling Unit |
82 |
|
N67 |
Kitchen |
82 |
|
N68 |
Kitchen |
82 |
|
N69 |
Washroom |
82 |
|
N70 |
Washroom |
82 |
|
N71 |
Pool Filtration
Plant Room |
82 |
|
N72 |
Pool Filtration
Plant Room |
82 |
|
N73 |
Pool Filtration
Plant Room |
82 |
|
N74 |
Pool Filtration
Plant Room |
82 |
|
N75 |
Shower Room |
82 |
|
N76 |
Shower Room |
82 |
|
N77 |
Air Ventilation |
82 |
|
N78 |
Air Ventilation |
82 |
|
N79 |
Air Ventilation |
82 |
|
N80 |
Air Ventilation |
82 |
|
N81 |
Air Ventilation |
82 |
|
N82 |
Mechanical,
electrical, plumbing |
82 |
|
N83 |
Mechanical,
electrical, plumbing |
82 |
|
N84 |
Air Ventilation |
82 |
|
N85 |
Air Ventilation |
82 |
|
N86 |
Air Ventilation |
82 |
|
N87 |
Air Ventilation |
82 |
|
N88 |
Air Ventilation |
82 |
|
N89 |
Air Ventilation |
82 |
|
N90 |
Air Ventilation |
82 |
|
N91 |
Air Ventilation |
82 |
|
N92 |
Air Ventilation |
82 |
|
N93 |
Air Ventilation |
82 |
|
N94 |
Air Ventilation |
82 |
|
N95 |
Air Ventilation |
82 |
|
N96 |
Air Ventilation |
82 |
|
N97 |
Air Ventilation |
82 |
|
P1 |
PA system |
94 |
|
P2 |
PA system |
94 |
|
P3 |
PA system |
94 |
|
P4 |
PA system |
94 |
|
P5 |
PA system |
94 |
|
P6 |
PA system |
94 |
|
P7 |
PA system |
94 |
|
P8 |
PA system |
94 |
|
P9 |
PA system |
94 |
|
P10 |
PA system |
94 |
|
P11 |
PA system |
94 |
|
P12 |
PA system |
94 |
|
P13 |
PA system |
94 |
|
P14 |
PA system |
94 |
|
P15 |
PA system |
94 |
Open Air Entertainment Activity |
102 |
Note: * Maximum allowable SWL of each source.
The
proposed maximum allowable SWL for open air entertainment activity is only at
the selected assessment point, but not at all open show areas. As mentioned in
above sections, open air entertainment activities may occur at various
locations, subject to detailed planning of future operation style. Should the
NSRs are affected by more than one opening air entertainment activity location,
the maximum permissible SWL at each location shall be applied a correction
factor to account for the cumulative effect. The values of the correction
factor related to the number of locations are shown in Table 5.12 below.
Table 5.12: Correction Factor for Maximum Allowable SWL of the Open Air Entertainment Activities
Number of Open Air Entertainment Locations |
Correction to Maximum Allowable SWL, dB(A) |
1 |
0 |
2 |
-3 |
3 |
-5 |
4 |
-6 |
5 |
-7 |
6 |
-8 |
7 |
-8 |
8 |
-9 |
9 |
-10 |
10 |
-10 |
§ Good site practice to limit noise emissions at source;
§ Selection of quiet plant;
§ Use of movable noise barrier;
§ only well-maintained plant to be operated on-site and plant should be serviced regularly during the construction works;
§ machines and plant that may be in intermittent use to be shut down between work periods or should be throttled down to a minimum;
§ plant known to emit noise strongly in one direction, should, where possible, be orientated to direct noise away from the NSRs;
§ mobile plant should be sited as far away from NSRs as possible; and
§ material stockpiles and other structures to be effectively utilised, where practicable, to screen noise from on-site construction activities.
Table 5.13: Quiet PME Recommended for Adoption during Construction Phase
PME |
Power rating / size, weight |
Reference |
SWL, dB(A) |
Excavator, wheeled / tracked |
70lW |
EPD-01217 |
100 |
Table 5.14: Noise Mitigation Measures for Certain PME during Construction Phase
PME |
Mitigation Measure Proposed |
Noise Reduction, dB(A) |
Concrete lorry mixer |
Movable Barrier |
5 |
Breaker, hand-held, mass >= 20kg and <= 35kg |
Movable Barrier |
5 |
Crane, mobile / barge mounted (diesel) |
Movable Barrier |
5 |
Concrete pump, stationary/lorry mounted |
Movable Barrier |
10 |
Poker, vibratory, hand-held |
Movable Barrier |
10 |
Saw, circular, wood |
Movable Barrier |
10 |
Table 5.15: Mitigated Construction Airborne Noise Impact
NSR ID |
Use |
Predicted Noise Level, dB()A |
Noise Criteria, dB(A) |
Exceedance of Noise Criteria |
Residual Impact |
VSA |
Educational |
59-65 |
70 or 65 during examination |
No |
No |
HKJCC |
Educational |
59-65 |
70 or 65 during examination |
No |
No |
As mentioned in Section 5.6, the increased traffic flow under the operation of the Project is expected to cause less than 1 dB(A) increase in road traffic noise level. Therefore, no adverse road traffic noise impact is anticipated and no mitigation measure is required.
§ choose quiet plant such as those which have been effectively silenced;
§ include noise levels specification when ordering new plant (including chiller and E&M equipment);
§ locate fixed plant / louvre away from any NSRs as far as practicable;
§ locate fixed plant in walled plant rooms or in specially designed enclosures;
§ locate noisy machine in a basement or a completely separate building;
§ install direct noise mitigation measures including silencers, acoustic louvres and acoustic enclosure where necessary; and
§ develop and implement a regularly scheduled plant
maintenance programme so that equipment is properly operated and serviced in
order to maintain a controlled level of noise.
Open
Air Entertainment Noise
With the adoption of the proposed maximum allowable SWLs in Table 5.11 and Table 5.12, all representative NSRs is expected to comply with the relevant noise criteria for the daytime and evening periods. No adverse open air entertainment noise impact is anticipated. However, the following measures should be considered as far as practicable during stage:
§ use small clusters of small power loudspeakers rather than a few large power loudspeakers; and
§ loudspeakers should be pointed away from nearby NSRs.