Content |
Chapter Title
Figures
Figure
4.1:__ Typical
sloping seawall section_ 4-5 |
Drawings
Drawing No. MCL/P132/EIA/4-001 Key Project Components – Land Formation
Drawing No. MCL/P132/EIA/4-002 Key Project Components – Airfield Facilities
Drawing No. MCL/P132/EIA/4-003 Key Project Components – Passenger Facilities
Drawing No. MCL/P132/EIA/4-004 Key Project Components – Road Network and Key Infrastructure
Drawing No. MCL/P132/EIA/4-005 Terminal 2 Road Network
Drawing No. MCL/P132/EIA/4-006 South Cargo Road Improvement Works
Drawing No. MCL/P132/EIA/4-007 Extension of South Perimeter Road
Drawing No. MCL/P132/EIA/4-008 Proposed Temporary Works Areas for Land Formation Activities
Drawing No. MCL/P132/EIA/4-009 Location of Concurrent Projects for Cumulative Impact Assessment
Appendices
Appendix 4.1 Summary
of Airport Master Layout Plan
Appendix 4.2 Tentative
Construction Programme
¡ Land formation of not more than 650 ha to the
north of the existing airport island with partial construction over the
contaminated mud pits (CMP). The area of land formation is defined to be the
area at and above the high water mark of +2.3 mPD; and
¡ Modification and integration of the existing
seawall at the northern, western and eastern sides of the existing North Runway
into the new land formation and construction of new seawall around the land
formation.
¡ Construction of a third runway, related taxiway
systems, associated airfield infrastructure, aircraft navigational aids,
approach lighting systems and new Hong Kong International Airport Approach Area
(HKIAAA) beacons;
¡ Construction of the third runway passenger
concourse aprons;
¡ Temporary closure and modification of the
existing North Runway
along with related taxiway systems; and
¡ Expansion of the freighter aprons in the existing Midfield area between the existing north and south runways.
¡ Construction of the third runway passenger
concourse (TRC) and passenger fixed link bridges;
¡ Expansion of the existing passenger T2;
¡ Extension of the Automated
People Mover
(APM) and associated depot and maintenance / stabling areas; and
¡ Expansion of the Baggage
Handling System
(BHS) and associated baggage halls and early bag store.
¡ Expansion of the landside and airside road network in the passenger, cargo and maintenance areas and landside transportation facilities, including new car parks;
¡ Construction of new airside road access, including the construction of new airside road tunnels and ramps, to connect the new third runway facilities with the existing airport;
¡ Modification of existing and construction of
new land-based infrastructure including the seawater cooling and flushing
system, stormwater drainage system, greywater system, sewerage network and
potable water supply, Towngas supply, 132 kV / 11 kV and other power supply
networks, communication networks; and
¡ Modifications and re-provisions to existing
marine facilities including the underwater aviation fuel pipelines between HKIA
and the off-airport fuel receiving facilities at Sha Chau, the associated
underwater 11 kV cable and pilot cable and sea rescue boat points.
Table 4.1: Preferred Ground Improvement Methods to be Adopted at Various
Locations Within / Outside
CMP Area
Location |
Preferred Ground Improvement Method |
|
|
Within CMP area |
Outside CMP area |
Runway |
DCM |
Stone Columns / Sand Compaction Piles / Vertical Sand Drains / DCM |
Seawall |
DCM |
Steel Cells / Stone Columns / Sand Compaction Piles / Vertical Sand Drains / DCM |
General land formation area |
DCM |
Prefabricated Vertical Drains (PVD) / Sand Compaction Piles / Stone Columns / Vertical Sand Drains / DCM |
Table 4.2: General Arrangement
of the Various
Ground Improvement Methods
Ground Improvement Method |
General Arrangement |
Deep Cement Mixing (DCM) |
Under seawalls – DCM will be arranged in panels and extending inward from below the seawall. The panels comprise continuous DCM clusters, each composed of mutually overlapping columns, and will penetrate into firm stiff alluvial material that comprises of firm clay underlying the soft marine sediments. General land formation area / under runway – DCM will comprise individual clusters, with each cluster typically comprising mutually overlapping columns. |
Prefabricated Vertical Drains (PVD) |
General land formation area – PVD are proposed to be installed through the full thickness of the soft silt and clay underlying the seabed, with a surcharge preloading applied to the area to accelerate consolidation. |
Sand Compaction Piles |
Where sand compaction piles are adopted instead of stone columns (for either seawall, runway areas or general land formation areas), these will be arranged in a triangular grid pattern. |
Steel Cells |
Seawalls – The steel cells will form part of the seawall structure and will be installed to above sea level. Each cell will be constructed as a single unit and delivered to site using semi-submersible barges and custom-built installation barges which can install the cells without infringement of the airport height restriction, to facilitate the commencement of filling within a practical time frame. |
Stone Columns |
Under seawalls – Stone columns will be placed in a triangular pattern and will be toed-in to the top of firm to stiff alluvial material underlying the soft marine sediment. In conjunction with steel cells, stone columns will be placed to seaward and on the land formation side of the steel cells to support the revetment structure and the land formation fill respectively. Under runway – The arrangement of stone columns is similar to the proposed ground improvement under seawalls. Sand compaction piles may also be adopted as an alternative. |
Vertical Sand Drains |
Vertical sand drains may be adopted in the transition areas between the various other ground improvement methods. The sand drains will be arranged in a triangular grid. |
Ground
Improvement |
Table 4.3: Summary of Construction and Runway Operational Configuration Phasing
Phase |
Description |
Runway Operational Configuration |
Timeframe |
Advanced Works |
Diversion of the submarine pipeline and power cable |
|
2015 to 2016 |
Phase 1 |
Land formation works will commence before subsequent construction of third runway, new taxiways and the new TRC. Expansion of T2 will also be commenced. The existing two-runway system remains operational throughout construction phase. |
2016 to 2021 |
|
Phase 2 |
Upon completion of the third runway and associated taxiways, the existing North Runway will be closed for modification works, while construction activities for the TRC and aprons, vehicle tunnels and reconfiguration of T2 are ongoing. During this interim period, the existing South Runway and the new third runway will be operational. |
|
2021 to 2023 |
Phase 3 |
Upon completion of all essential infrastructure and facilities including part of the TRC and aprons and expanded T2, the airport will operate under the 3RS. Construction of the remaining facilities will continue until completion. |
|
2023 and after |
1. Land formation from seabed to above water level:
a. Place sand blanket on the seabed
b. Conduct ground improvement works
c. Complete a minimum of 200 m leading seawall up to and above seawater level
d. Deposit marine fill
2. Land formation above water level:
a. Place the fill materials up to an intermediate level and apply compaction to the fill, and repeat up to formation level
b. Place additional fill on top to act as surcharge to the level as required
c. Hold the surcharge for a period of time and subsequently remove to the formation level
1. Install all underground utilities including stormwater box culvert and associated drainage system, seawater and potable water pipes, cable and communication ductworks
2. Excavate and prepare the compacted subgrade. Place and compact the crushed aggregate based and sub-base course in layers
3. Install airfield ground lights (AGL) ductwork and light cans
4. Construction of airside perimeter roads, security fencing and gate houses
5. Install approach light / HKIAAA beacons structures and systems
6. Place the asphalt base course, wearing course for runway and associated taxiway system
7. Install the AGL and airfield line marking
8. Testing and commissioning and follow with flight check.
1.
Site
formation works i.e. site grading, installing cofferdam / well points for water
cutoff and general excavation will be firstly carried out for the construction of
infrastructures and superstructures;
2.
Install
piles for TRC and other structures i.e. fixed linked bridge. After piles
installation, construction of APM stations under eastern and western TRC will
then be commenced. A combination of in-situ column-beam structural frame
and precast concrete T-beams and slabs will be adopted for the construction of
TRC superstructure. Steel roof truss with prefabricated roof panel and
façade will then be erected and fixed after the completion of concrete
structures;
3.
Piles
for APM tunnels and BHS tunnels (if any) will also be installed
concurrently. After the completion of piles installation, blinding and
waterproofing membrane will be laid and construction of APM & BHS tunnel
box structures will be commenced section by section. Completed tunnel box
section will then be wrapped by waterproofing membrane and backfilling
work will be carried out to final site formation level;
4.
Install underground utility and infrastructure including drainage, sewerage, fuel hydrant system etc. at
airfield;
5.
Place
the asphalt base course, wearing course and pavement quality concrete as paving
for stands and taxiways;
6.
Construct
airside, landside road connections, security fencing and
associated gate houses;
7.
Install
services, fit-outs and systems for the TRC, APM and BHS tunnels and other buildings;
8.
Carry out testing and commissioning; and
9.
Landscaping.
1.
The advance works comprise car
park reprovision and temporary road diversion followed by diversion of
utilities outside the existing T2 to free up underground spaces for the
construction of T2 expansion.
2.
The piling and substructure
works for the T2 expansion will then commence.
Facilities to be located within the southern and eastern part of the T2
expansion such as the underground AIS, BHS basement and annex buildings will
also be constructed first.
3.
The existing T2 will be fully
shut down for the demolition of the part of the existing T2 structures that will not be retained
and implementation of the subsequent extensive
building modification and expansion works. While the existing foundation will be retained
and reused, additional pile foundation will be constructed within the existing
T2 footprint after completion of demolition works. Basement
walls will be formed using diaphragm walls and bored cast foundation piles. A
combination of in-situ concrete construction and construction from using
precast concrete beams and slabs will be adopted for the main levels, while the
roof will be constructed by erection of trusses followed by prefabrication of
roof panels using pre-assembled jigs.
4.
Construction of the APM depot,
APM tunnel, BHS tunnel, landside utilities, elevated road and at-grade road
network will also be carried out concurrently to enable timely completion of
the T2 expansion works.
1. Earthworks, excavation or embankment works;
2. Compaction of the road sub-grade;
3. Utilities / pipeline ducting and protection works will be installed after earthworks are completed. Road sub-base, road kerbs, road base, wearing course;
4. Footpath, highway finishes, street furniture, lighting etc..
¡ Land formation activities for a new landform of
up to 650 ha which will
be less than 100 m from the nearest seawater intake (Items C.1 and C.2, Part I,
Schedule 2).
¡ Provision of new facilities including airport-related facilities (Item
B.1, Part I, Schedule 2).
¡ Provision of the reuse of treated sewage
effluent (Item F.4, Part I, Schedule 2).
¡ Provision of rail-based facilities including an
underground tunnel for the APM, associated stations and a depot (Items A.2, A.4, and A.7, Part I,
Schedule 2).
¡ Provision of new roads, including roads
designed as primary
distributor roads (the T2 road network), comprising viaducts, and road tunnels
(Items A.1, A.7 and A.8, Part I, Schedule 2).
¡ Construction activities associated with the submarine aviation fuel
pipelines (including SI boreholes) that are located within the Sha Chau and
Lung Kwu Chau Marine Park, and temporary power supply for the submarine 11 kV
cable located within the Lung Kwu Chau, Tree Island and Sha Chau Site of
Special Scientific Interest, (Items H.2 and Q.1, Part I,
Schedule 2).
¡ Provision of temporary
construction-related facilities including two on-site concrete batching plants
and on-site storage of sand (Items K.5 and K.11, Part I, Schedule 2).
Table 4.4: Summary
of Components from Concurrent Projects Adopted
for Cumulative Impact Assessment
Concurrent Project* |
Cumulative Impacts Considered |
Information Sources |
||||||||
|
Air Quality |
Noise |
Water Quality |
Sewage |
Ecology |
Fisheries |
Landscape & Visual |
|||
Black Point Gas Supply |
Insufficient information available - not assessed for cumulative impacts |
|
||||||||
Container Terminal 10 Development at Southwest Tsing Yi |
N/A – outside assessment area |
N/A – outside assessment area |
Construction
Phase No information available Operation Phase Reclamation boundary and stormwater discharge incorporated |
N/A – outside assessment area |
Inferred from water quality impact assessment |
Inferred from water quality impact assessment |
N/A – outside assessment area |
Communication with project proponent in August 2013 |
||
Cycle Track between Tsuen Wan and Tuen Mun |
Insufficient information available - not assessed for cumulative impacts |
|
||||||||
Development of the Integrated Waste Management Facilities Phase 1 |
Construction Phase N/A – outside assessment area Operation Phase Emissions incorporated into PATH model |
N/A – outside assessment area |
Construction
Phase N/A – no marine works associated with the Tsang Tsui site, while the Shek Kwu Chau site is outside assessment area Operation Phase Reclamation boundary and stormwater discharge incorporated |
N/A – outside assessment area |
N/A – outside assessment area |
N/A – outside assessment area |
N/A – outside assessment area |
Approved EIA report (EIA-201/2011) |
||
Effluent Polishing Scheme at Yuen Long Sewage Treatment Works |
N/A – outside assessment area |
N/A – outside assessment area |
Construction
Phase No information available Operation Phase Discharges incorporated |
N/A – outside assessment area |
N/A – outside assessment area |
N/A – outside assessment area |
N/A – outside assessment area |
Communication with project proponent in August 2013 |
||
Enhancing Land Supply Strategy Study: Reclamation outside Victoria Harbour and Rock Cavern Development |
Insufficient information available - not assessed for cumulative impacts |
|
||||||||
Harbour Area Treatment Scheme - Stage 2A |
N/A – outside assessment area |
N/A – outside assessment area |
Construction
Phase N/A – no concurrent construction anticipated Operation Phase Discharges
incorporated |
N/A – outside assessment area |
Inferred from water quality impact assessment |
Inferred from water quality impact assessment |
N/A – outside assessment area |
Approved EIA report (EIA-148/2008) |
||
Hong Kong – Zhuhai – Macao Bridge: Hong Kong Boundary Crossing Facilities |
Construction
Phase Dust emissions incorporated Operation Phase Induced traffic incorporated |
Construction
Phase Construction noise sources incorporated Operation Phase Induced traffic incorporated |
Construction
Phase Reclamation boundary and sediment loss incorporated Operation Phase Reclamation boundary and intake / discharges incorporated |
N/A – no sewage loading from HKBCF (on-site treatment plant) |
Construction
Phase Inferred from water quality impact assessment Operation Phase Habitat / resource loss incorporated; Indirect disturbances (i.e. noise and air pollutant from the increase in road traffic) incorporated |
Construction
Phase Inferred from water quality impact assessment Operation Phase Habitat / resource loss incorporated |
Incorporated as part of the planned baseline |
Approved EIA report (EIA-173/2009) Communication with project proponent in August 2013 |
||
Hong Kong – Zhuhai – Macao Bridge: Hong Kong Link Road |
Construction
Phase Dust emissions incorporated Operation Phase Induced traffic incorporated |
Construction
Phase Construction noise sources incorporated Operation Phase Induced traffic incorporated |
Construction
Phase Reclamation boundary and sediment loss incorporated Operation Phase Reclamation boundary incorporated |
N/A – no sewage loading from the link road |
Construction
Phase Inferred from water quality impact assessment; Fragmentation in terrestrial habitat incorporated Operation Phase Habitat / resource loss incorporated; Indirect disturbances (i.e. noise and air pollutant from the increase in road traffic) and Fragmentation in terrestrial habitat incorporated |
Construction
Phase Inferred from water quality impact assessment Operation Phase Habitat / resource loss incorporated |
Incorporated as part of the planned baseline |
Approved EIA report (EIA-172/2009) Communication with project proponent in August 2013 |
||
Hong Kong - Zhuhai - Macao Bridge: Outside HKSAR |
N/A – outside assessment area |
N/A – outside assessment area |
Construction
Phase N/A – no concurrent construction anticipated Operation Phase Reclamation boundary incorporated |
N/A – outside assessment area |
N/A – outside assessment area |
N/A – outside assessment area |
N/A – outside assessment area |
Project website |
||
Lantau Logistics Park |
Construction
Phase N/A – outside assessment area Operation Phase Induced traffic incorporated |
N/A – outside assessment area |
Construction
Phase Reclamation boundary and sediment loss incorporated Operation Phase Reclamation boundary and intake / discharges incorporated |
Construction
Phase Cumulative impacts not applicable Operation Phase Induced sewage loading incorporated |
Construction
Phase Inferred from water quality impact assessment Operation Phase Habitat / resource loss incorporated (marine ecology only - outside terrestrial ecological assessment area) |
Construction
Phase Inferred from water quality impact assessment Operation Phase Habitat / resource loss incorporated |
Visual impacts incorporated |
Communication with project proponent in September 2013 |
||
Leisure and Entertainment Node at Sunny Bay |
Construction
Phase N/A – outside assessment area Operation Phase Induced traffic incorporated |
N/A – outside assessment area |
Construction
Phase No information available Operation Phase Reclamation boundary and stormwater discharge incorporated |
No information available |
Construction
Phase No information available Operation Phase Habitat / resource loss incorporated (marine ecology only - outside terrestrial ecological assessment area) |
Construction
Phase No information available Operation Phase Habitat / resource loss incorporated |
Visual impacts incorporated |
Communication with Planning Department in August 2013 |
||
New Contaminated Mud Marine Disposal Facility at HKIA East / East Sha Chau Area |
N/A – not associated with air quality impacts |
N/A – outside assessment area |
Construction
Phase Bathymetry and sediment loss incorporated Operation Phase Bathymetry incorporated |
N/A – not associated with sewage loading |
Construction
Phase Inferred from water quality impact assessment (marine ecology only) Operation Phase Habitat / resource loss incorporated (marine ecology only) |
Construction
Phase Inferred from water quality impact assessment Operation Phase Habitat / resource loss incorporated |
Landscape and visual impacts incorporated |
Approved EIA report (EIA-106/2005) Communication with project proponent in October 2013 |
||
Organic Waste Treatment Facilities, Phase I |
Construction
Phase N/A – outside assessment area Operation Phase Emissions incorporated into PATH model |
N/A – outside assessment area |
Construction
Phase N/A – no marine works Operation Phase N/A – no marine discharges |
Construction
Phase Cumulative impacts not applicable Operation Phase N/A – on-site treatment plant |
N/A – outside terrestrial ecology assessment area and not associated with impacts to marine ecology |
N/A – not associated with impacts to fisheries |
N/A – outside assessment area |
Approved EIA report (EIA-176/2009) Communication with project proponent in August 2013 |
||
Outlying Islands Sewerage Stage 2 - upgrading of Cheung Chau and Tai O sewage collection, Treatment and Disposal Facilities (Upgrading of Tai O Sewage Collection, Treatment and Disposal Facilities) |
N/A – outside assessment area |
N/A – outside assessment area |
Construction
Phase Reclamation boundary and sediment loss incorporated Operation Phase Reclamation boundary and discharges incorporated |
N/A – outside assessment area |
Construction
Phase Inferred from water quality impact assessment Operation Phase No information available |
Construction
Phase Inferred from water quality impact assessment Operation Phase No information available |
N/A – outside assessment area |
Communication with project proponent in August 2013 |
||
Planned developments on the existing airport island, including the Midfield development, the North Commercial District (NCD), the Intermodal Transfer Terminus (ITT) and other airport facilities related works |
Construction
Phase Dust emissions incorporated Operation Phase Induced traffic incorporated |
Construction
Phase Construction noise sources incorporated Operation Phase Induced traffic incorporated |
Construction
Phase N/A – no marine works Operation Phase Discharges incorporated |
Construction
Phase Cumulative impacts not applicable Operation Phase Sewage loading incorporated |
Construction
Phase Impacts incorporated (terrestrial ecology only) Operation Phase Habitat / resource loss incorporated (terrestrial ecology only) |
N/A – not associated with impacts to fisheries |
Landscape and visual impacts incorporated |
Communication with project proponent in September 2013 |
||
Planning and Engineering Study for Tuen Mun Areas 40 and 46 and the Adjoining Areas |
Insufficient information available - not assessed for cumulative impacts |
|
||||||||
Potential Sites for Columbarium Developments – Group B – Feasibility Study |
Construction
Phase N/A – No information available Operation Phase N/A – No
information available |
Construction
Phase N/A – No information available Operation Phase N/A – No
information available |
Construction
Phase N/A – no marine works Operation Phase N/A – no marine
discharges |
No information
available |
No information
available |
N/A – not associated with impacts to fisheries |
Visual impacts incorporated |
Communication with works agent in January 2014 |
||
Proposed Residential Development at Tung Chung (Area 54) |
Construction
Phase N/A – No information available Operation Phase Induced traffic incorporated |
Construction
Phase N/A – No information available Operation Phase Induced traffic incorporated |
Construction
Phase N/A – no marine works Operation Phase Induced discharges
incorporated |
Construction
Phase Cumulative impacts not applicable Operation Phase Induced sewage loading incorporated |
Construction
Phase Impacts incorporated (terrestrial ecology only) Operation Phase Habitat / resource
loss incorporated (terrestrial ecology only) |
N/A – not
associated with impacts to fisheries |
Visual impacts incorporated |
Communication with project proponent in October 2013 |
||
Proposed Submarine Pipelines System from Tuen Mun to Tung Chung and Associated Offtake and Pigging Station at Chek Lap Kok |
Insufficient information available - not assessed for cumulative impacts |
|
||||||||
Providing Sufficient Water Depth at Kwai Tsing Container Basin and its Approach Channel |
N/A – outside assessment area |
N/A – outside assessment area |
Construction
Phase Bathymetry and sediment loss incorporated Operation Phase Bathymetry incorporated |
N/A – outside assessment area |
Construction
Phase Inferred from water quality impact assessment (marine ecology only) Operation Phase N/A – not associated with marine or terrestrial ecological impact |
Construction
Phase Inferred from water quality impact assessment Operation Phase N/A – not associated with fisheries impact |
N/A – outside assessment area |
Approved EIA report (EIA-183/2010) Communication with project consultant in August 2013 |
||
Public Housing Development at Tung Chung West (Area 39) |
Construction
Phase N/A – outside assessment area Operation Phase Induced traffic incorporated |
N/A – outside assessment area |
Construction
Phase N/A – no marine works Operation Phase Induced discharges
incorporated |
Construction
Phase Cumulative impacts not applicable Operation Phase Induced sewage loading incorporated |
Construction
Phase Impacts incorporated (terrestrial ecology only) Operation Phase Habitat / resource
loss incorporated (terrestrial ecology only) |
N/A – not
associated with impacts to fisheries |
Visual impacts incorporated |
Communication with project proponent in October 2013 |
||
Sludge Treatment Facilities |
Construction
Phase N/A – outside assessment area Operation Phase Emissions incorporated into PATH model |
N/A – outside assessment area |
Construction
Phase N/A – no programme overlap Operation Phase Intake / discharges incorporated |
N/A – outside assessment area |
Construction
Phase N/A – no concurrent construction anticipated Operation Phase Inferred from water quality impact assessment (marine ecology only) |
Construction
Phase N/A – no concurrent construction anticipated Operation Phase Inferred from water quality impact assessment |
N/A – outside assessment area |
Approved EIA report (EIA-155/2008) Communication with project consultant in February 2013 |
||
Tonggu Channel |
N/A – outside
assessment area |
N/A – outside assessment area |
Construction
Phase Sediment loss incorporated Operation Phase N/A – maintenance
dredging schedule not available |
N/A – outside assessment area |
Construction
Phase Inferred from water quality impact assessment (marine ecology only) Operation Phase N/A – not
associated with marine ecological or terrestrial impact |
Construction
Phase Inferred from water quality impact assessment Operation Phase N/A – not
associated with fisheries impact |
N/A – outside assessment area |
Various published information |
||
Tuen Mun –
Chek Lap Kok Link |
Construction
Phase N/A – outside assessment area Operation Phase Induced traffic incorporated |
N/A – outside assessment area |
Construction
Phase N/A – no concurrent marine construction activities anticipated Operation Phase Reclamation boundary and stormwater discharge incorporated |
N/A – not associated with sewage loading |
Habitat / resource loss incorporated; Indirect disturbances (i.e. noise and air pollutant from the increase in road traffic) and fragmentation in terrestrial habitat incorporated |
Construction
Phase N/A – no concurrent marine construction anticipated Operation Phase Habitat / resource loss incorporated |
Southern Connection - Incorporated as part of baseline Northern Connection – visual impacts incorporated |
Approved EIA report (EIA-174/2009) Communication with project proponent in August 2013 |
||
Tung Chung New Town Extension |
Construction
Phase N/A – Insufficient information available Operation Phase Induced traffic incorporated |
Construction
Phase N/A – Insufficient information available Operation Phase Induced traffic incorporated |
Construction
Phase Not incorporated – outside the worst case assessment years of the project Operation Phase Reclamation boundary and intake / discharges incorporated |
Construction
Phase Cumulative impacts not applicable Operation Phase Sewage loading incorporated |
Construction
Phase N/A – Insufficient information available Operation Phase Habitat / resource loss incorporated |
Construction
Phase N/A – Insufficient information available Operation Phase Habitat / resource loss incorporated |
Landscape and visual impacts incorporated |
Communication with project proponent in September 2013 |
||
West New Territories (WENT) Landfill Extensions |
Construction
Phase N/A – outside assessment area Operation Phase Emissions incorporated into PATH model |
N/A – outside assessment area |
Construction
Phase N/A – no marine works Operation Phase Discharges incorporated |
N/A – outside assessment area |
N/A – outside terrestrial ecology assessment area and not associated with impacts to marine ecology |
N/A – not associated with impacts to fisheries |
N/A – outside assessment area |
Approved EIA report (EIA-171/2009) Communication with project proponent in January 2013 |
||
*Concurrent Projects refer to
those projects that are planned / committed or are currently under
construction. Projects that are already in operation phase (existing) form part
of the existing baseline and are not defined as concurrent projects for the
purpose of this summary. Existing projects will nevertheless form part of
individual environmental assessments, where applicable, and will be detailed in
the relevant technical sections of this EIA report.
PATH = Pollutants in the
Atmosphere and their Transport over Hong Kong model
Note:
Other environmental aspects
including Hazard to Human Life, Waste Management, Land Contamination and
Cultural Heritage are independent of concurrent projects,
hence no cumulative impact assessment is required. For Health Impact (due to
pollutant emissions), this is an outcome of the operation phase air quality
impact assessment, hence cumulative health impacts are referred from the
concurrent projects considered in the operation phase air quality impact
assessment.