Expansion of Hong Kong |
|
|
June 2014 |
|
|
|
Content |
Content |
Content
Chapter Title
Charts
Chart 1-1:___ Project
Organisation Chart Chart 5-1:___ Flow
Chart for DCM Monitoring |
Drawings
MCL/P132/EMA/1-001 Key Project Components –
Land Formation
MCL/P132/EMA/1-002 Key
Project Components – Airfield Facilities
MCL/P132/EMA/1-003 Key
Project Components – Passenger Facilities
MCL/P132/EMA/1-004 Key
Project Components – Road Network and Key Infrastructure
MCL/P132/EMA/2-001 Air
Quality Monitoring Stations (Construction)
MCL/P132/EMA/4-001 Proposed Locations of
Construction Noise Monitoring Stations
MCL/P132/EMA/5-001 Water Quality Monitoring
Stations for Submarine 11 kV Cable Diversion Works
MCL/P132/EMA/5-002 Water Quality Monitoring
Stations for Land Formation Works
MCL/P132/EMA/5-003 Indicative Locations for DCM
Monitoring Stations
MCL/P132/EMA/10-001 Pre-Construction Phase
Coral Dive Survey Locations
MCL/P132/EMA/10-003 Land Based Dolphin
Monitoring in Baseline and Construction Phase
MCL/P132/EMA/12-001.1 Landscape and Visual Mitigation
Arrangement Plan – Chek Lap Kok
MCL/P132/EMA/12-001.2 Landscape and Visual
Mitigation Arrangement Blow Up Plan – Chek Lap Kok
MCL/P132/EMA/12-001.3 Landscape and Visual
Mitigation Arrangement Blow Up Plan – Chek Lap Kok
MCL/P132/EMA/12-001.4 Landscape and Visual
Mitigation Arrangement Blow Up Plan – Chek Lap Kok
MCL/P132/EMA/12-001.5 Landscape and Visual
Mitigation Arrangement Blow Up Plan – Chek Lap Kok
MCL/P132/EMA/12.001.6 Landscape and
Visual Mitigation Arrangement Plan – Sha
Chau
MCL/P132/EMA/14-001 Flow Chart of Complaint
Investigation Procedures
Appendices
Appendix A Tentative
Construction Programme
Appendix B Sample
Environmental Monitoring Data Recording Sheets
Appendix C Implementation
Schedule for Environmental Mitigation Measures
Appendix D Configuration
of Silt Curtains
Appendix E Sample
Template for Interim Notifications
¡ Land formation of not more than 650 ha to the north of the existing airport island with partial construction over the contaminated mud pits (CMP). The area of land formation is defined to be the area at and above the high water mark of +2.3 mPD; and
¡ Modification and integration of the existing seawall at the northern, western and eastern sides of the existing North Runway into the new land formation and re-provisioning of new seawall around the land formation.
¡ Construction of a third runway, related taxiway systems, associated airfield infrastructure, aircraft navigational aids, approach lighting systems and new Hong Kong International Airport Approach Area (HKIAAA) beacons;
¡ Construction of the third runway passenger concourse aprons;
¡ Temporary closure and modification of the existing North Runway along with related taxiway systems; and
¡ Expansion of the freighter aprons in the existing Midfield area between the existing North and South runways.
¡ Construction of the third runway passenger concourse (TRC) and passenger fixed link bridges;
¡ Expansion of the existing passenger Terminal 2 (T2);
¡ Extension of the automated people mover (APM) and associated depot and maintenance / stabling areas; and
¡ Expansion of the baggage handling system (BHS) and associated baggage halls and early bag store.
¡ Expansion of the landside and airside road network in the passenger, cargo and maintenance areas and landside transportation facilities, including new car parks;
¡ Construction of new airside road access, including the construction of new airside road tunnels and ramps, to connect the new third runway facilities with the existing airport;
¡ Modification to existing and construction of new land based infrastructure including the seawater cooling and flushing system, stormwater drainage system, greywater system, sewerage network and potable water supply, Towngas supply, 132 kV / 11 kV and other power supply networks; communication networks; and
¡ Modifications and re-provisions to existing marine facilities including the underwater aviation fuel pipelines between HKIA and the off-airport fuel receiving facilities at Sha Chau, the associated underwater 11 kV cable and pilot cable and sea rescue boat points.
|
|
¡ To monitor the Contractor’s compliance with Contract Specifications, including the effective implementation and operation of the environmental mitigation measures;
¡ To employ an Independent Environmental Checker (IEC) to audit the results of the EM&A works carried out by the Environmental Team (ET);
¡ To monitor Contractors’ compliance with the requirements in the Environmental Permit (EP) and EM&A Manual;
¡ To facilitate ET’s implementation of the EM&A programme;
¡ Participate in joint site inspection by the ET and IEC;
¡ To oversee the implementation of the agreed Event and Action Plan in the event of any exceedance; and
¡ To adhere to the procedures for carrying out complaint investigation.
¡ To comply with the relevant contract conditions and specifications on environmental protection;
¡ To facilitate ET’s monitoring and site inspection activities;
¡ To participate in the site inspections undertake by the ET and IEC, and undertake any corrective actions;
¡ To provide information / advice to the ET regarding works programme and activities which may contribute to the generation of adverse environmental impacts;
¡ To submit proposals on mitigation measures in case of exceedance of action and limit levels in accordance with the Event and Action Plans;
¡ To implement measures to reduce impact where action and limit levels are exceeded; and
¡ To adhere to the procedures for carrying out complaint investigation.
¡ To monitor and audit various environmental parameters as required in this EM&A Manual;
¡ To analyse the environmental monitoring and audit data, review the success of EM&A programme and the adequacy of mitigation measures implemented, confirm the validity of the EIA predictions and identify any adverse environmental impacts arising;
¡ To monitor compliance with conditions in the EP, environmental protection, pollution prevention and control regulations and contract specifications;
¡ To audit environmental conditions on site;
¡ To report on the environmental monitoring and audit results to EPD, the AAHK / PM, the IEC and Contractor(s) or their delegated representatives;
¡ To recommend suitable mitigation measures to the Contractor(s) in the case of exceedance of action and limit levels in accordance with the Event and Action Plans;
¡ To liaise with the IEC on all environmental performance matters, and ensure timely submission of all relevant EM&A pro forma for IEC’s approval;
¡ To provide advice to the Contractor(s) on environmental improvement, awareness and enhancement matters, etc. on site;
¡ To adhere to the procedures for carrying out complaint investigation;
¡ To prepare reports on the environmental monitoring data and the site environmental conditions;
¡ To submit the EM&A report to Environmental Protection Department (EPD) timely;
¡ To review proposals of mitigation measures from the Contractor(s) in case of exceedance of action and limit levels, in accordance with the Event and Action Plan;
¡ To carry out site inspection to investigate and audit the Contractor’s site practice, equipment and work methodologies with respect to pollution control and mitigation measures; and
¡ On an as-need basis, to review Contractor’s works methodology paper from environmental perspective.
¡ To provide proactive advice to the AAHK / PM on EM&A matters related to the project;
¡ To review and verify the monitoring data and all submissions in connection with the EP and EM&A Manual submitted by the ET;
¡ To arrange and conduct regular, at least monthly site inspections of the works during the construction phase, and to carry out ad hoc inspections if significant environmental problems are identified;
¡ To check compliance with the agreed Event and Action Plan in the event of any exceedance;
¡ To check compliance with the procedures for carrying out complaint investigation;
¡ To check the effectiveness of corrective measures;
¡ To feedback audit results to the ET by signing off relevant EM&A pro forma;
¡ To check that mitigation measures are effectively implemented;
¡ To report the works conducted, and the findings, recommendations and improvements of the site inspections, after reviewing ET’s and Contractor’s works, to the AAHK / PM on a monthly basis;
¡ To verify the investigation result of the environmental complaint cases and the effectiveness of corrective measures;
¡ To verify EM&A report that has been certified by ET leader; and
¡ To audit EIA recommendations and requirements against the status of implementation of environmental mitigation measures on site.
¡ To identify the extent of dust impact during construction phase on sensitive receivers;
¡ To audit the compliance of the Contractor with regard to dust control, contract conditions and the relevant dust impact criteria;
¡ To determine the effectiveness of mitigation measures to control fugitive dust emission from activities during the construction phase;
¡ To recommend further mitigation measures if found to be necessary; and
¡ To comply with action and limit levels for air quality as defined in this Manual.
¡ The wind sensors shall be installed on masts at an elevated level 10 m above ground so that they are clear of obstructions or turbulence caused by the buildings;
¡ The wind data shall be captured by a data logger. The data recorded in the data logger shall be downloaded periodically for analysis at least once a month;
¡ The wind data monitoring equipment shall be re-calibrated at least once every six months; and
¡ Wind direction shall be divided into 16 sectors of 22.5 degrees each.
Table 2‑1: Construction Air Quality Monitoring Stations
ID |
ID Adopted in EIA |
Description |
Monitoring
Parameters |
AR1 |
TC-13 |
Seaview Crescent Block 1 |
1-hour TSP |
AR2 |
ST-1 |
Village house at Tin Sum |
1-hour TSP |
¡ At the site boundary or such locations close to the major dust emission source;
¡ Close to the sensitive receptors; and
¡ Take into account the prevailing meteorological conditions.
¡ A horizontal platform with appropriate support to secure the samplers against gusty wind shall be provided;
¡ No two samplers shall be placed less than 2 m apart;
¡ The distance between the sampler and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the sampler;
¡ A minimum of 2 m of separation from walls, parapets and penthouses is required for rooftop samplers;
¡ A minimum of 2 m separation from any supporting structure, measured horizontally is required;
¡ No furnace or incinerator flue is nearby;
¡ Airflow around the sampler is unrestricted;
¡ The sampler is more than 20 m from the dripline;
¡ Any wire fence and gate, to protect the sampler, shall not cause any obstruction during monitoring;
¡ Permission must be obtained to set up the samplers and to obtain access to the monitoring stations; and
¡ A secured supply of electricity is needed to operate the samplers.
Table 2‑2: Typical Action and Limit Levels for Air Quality
Parameters |
Action Level |
Limit Level |
1-hour TSP Level in µg/m3 |
For baseline level
≤ 384 µg/m3, Action level = (130% of baseline level + Limit
level)/2 For baseline level
˃ 384 µg/m3, Action level = Limit level |
500 |
Table 2‑3: Typical Event and Action Plan for Air Quality
|
Action |
|||
Event |
ET |
IEC |
AAHK / PM |
Contractor |
Action Level |
|
|
|
|
1. Exceedance for one sample |
1. Identify source,
investigate the causes of exceedance and propose remedial measures; 2. Inform IEC and
AAHK / PM; 3. Repeat
measurement to confirm finding; 4. Increase
monitoring frequency to daily. |
1. Check
monitoring data submitted by ET; 2. Check Contractor’s
working method. |
1. Notify
Contractor. |
1. Rectify any
unacceptable practice; 2. Amend working
methods if appropriate. |
2. Exceedance for two or more consecutive samples |
1. Identify
source; 2. Inform IEC and
AAHK / PM; 3. Advise the AAHK
/ PM on the effectiveness of the proposed remedial measures; 4. Increase
monitoring frequency to daily; 5. Discuss with
IEC and Contractor on remedial actions required 6. If exceedance
continues, arrange meeting with IEC and AAHK / PM 7. If exceedance
stops, cease additional monitoring. |
1. Check
monitoring data submitted by ET; 2. Check
Contractor’s working method 3. Discuss with ET
and Contractor on possible remedial measures; 4. Advise AAHK /
PM on the effectiveness of the proposed remedial measures; 5. Supervisor
implementation of remedial measures. |
1. Confirm receipt
of notification of failure in writing; 2. Notify
Contractor; 3. Ensure remedial
measures properly implemented. |
1. Submit
proposals for remedial actions to IEC within three working days of
notification; 2. Implement the
agreed proposals; 3. Amend proposal
if appropriate. |
Limit Level |
|
|
|
|
1. Exceedance for one sample |
1. Identify the
source, investigate the causes of exceedance and propose remedial measures; 2. Inform AAHK /
PM and Contractor. If the exceedance is valid, inform EPD; 3. Repeat
measurement to confirm finding; 4. Increase
monitoring frequency to daily; 5. Assess
effectiveness of Contractor’s remedial actions and keep IEC, EPD and AAHK /
PM informed of the results. |
1. Check
monitoring data submitted by ET; 2. Check
Contractor’s working method; 3. Discuss with ET
and Contractor on possible remedial measures; 4. Advise AAHK /
PM on the effectiveness of the proposed remedial measures; 5. Monitor the implementation
of remedial measures. |
1. Confirm receipt
of notification of failure in writing; 2. Notify
Contractor; 3. Ensure remedial
measures properly implemented. |
1. Take immediate
action to avoid further exceedance; 2. Submit
proposals for remedial actions to IEC within three working days of
notification; 3. Implement the
agreed proposals; 4. Amend proposal
if appropriate. |
2. Exceedance for two or more consecutive sample |
1. Notify IEC,
AAHK / PM, Contractor and EPD; 2. Identify
source; 3. Repeat
measurement to confirm finding; 4. Increase
monitoring frequency to daily; 5. Carry out
analysis of Contractor’s working procedures to determine possible mitigation
to be implemented; 6. Arrange meeting
with IEC and AAHK / PM to discuss the remedial actions to be taken; 7. Assess
effectiveness of Contractor’s remedial actions and keep IEC, EPD and AAHK /
PM informed of the results; 8. If exceedance
stops, cease additional monitoring. |
1. Check
monitoring data submitted by ET; 2. Check
Contractor’s working method; 3. Discuss amongst
AAHK / PM, ET, and Contractor on the potential remedial actions; 4. Review
Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise AAHK / PM accordingly; 5. Monitor the
implementation of remedial measures. |
1. Confirm receipt
of notification of failure in writing; 2. Notify
Contractor; 3. In consultation
with the IEC, agree with the Contractor on the remedial measures to be
implemented; 4. Ensure remedial
measures properly implemented; 5. If exceedance
continues, consider what portion of the work is responsible and instruct the
Contractor to stop that portion of work until the exceedance is abated. |
1. Take immediate
action to avoid further exceedance; 2. Submit
proposals for remedial actions to IEC within three working days of
notification; 3. Implement the
agreed proposals; 4. Resubmit
proposals if problem still not under control; 5. Stop the
relevant portion of works as determined by AAHK / PM until the exceedance is
abated. |
¡ Provide data and information for verifying predictions on the effectiveness of measures to mitigate aircraft noise impact of the Project;
¡ Formulate audit requirements, including any necessary compliance and post-project audit program, in order to review the monitoring data and identify any remedial works, as necessary, required to address unacceptable or unanticipated aircraft noise impacts; and
¡ Provide tools, procedures and supplementary information, including noise descriptor and flight tracks, which are useful and relevant for communicating the aircraft noise of the Project to the general public.
¡ An exercise by AAHK to verify predictions on the effectiveness of measures to mitigate aircraft noise impact and the preparation of a Prediction Verification Report;
¡ Review Report, prepared on an annual basis by AAHK, for detailing the compliance with noise abatement procedures and unanticipated events, as well as any further necessary investigation and/or remedial action(s);
¡ Noise Contour Report, prepared in at least every five years by AAHK, to compare actual airport operation to forecast airport operation with respect to aircraft noise, taking into account data collected on actual aircraft operational levels, fleet mix, runway and flight track utilizations; and produce an updated noise contour using the most currently available and internationally accepted noise modelling methodology
Table 4‑1: Construction Noise Monitoring Stations
ID |
ID
adopted in EIA |
Description |
NM1 |
TC-1 |
Seaview Crescent
Block 1 |
NM2 |
TC-5 |
Tung Chung West
Development (Monitoring to start
after occupation of development in 2023/24, subject to the construction programme of the
Project) |
NM3 |
TC-30 |
Ho Yu College |
NM4 |
TC-37 |
Ching Chung Hau Po
Won Primary School |
NM5 |
TS-1 |
House, Tin Sum |
NM6 |
SLW-1 |
House No. 1, Sha Lo
Wan |
¡ Monitoring at sensitive receivers close to the major site activities which are likely to have noise impacts;
¡ Monitoring at the noise sensitive receivers as defined in the Technical Memorandum; and
¡ Assurance of minimal disturbance to the occupants during monitoring.
¡ One set of measurements between 0700-1900 hours on normal weekdays;
Table 4‑2: Typical Action and Limit Levels for Construction Noise
Time Period |
Action |
Limit |
0700-1900 hours on normal weekdays |
When one valid
documented complaint is received. |
75* dB(A) |
Note: * reduce to 70 dB(A) for schools and 65 dB(A) during school examination periods.
Table 4‑3: Event and Action Plan for Construction Noise
|
Action |
|||
Event |
ET |
IEC |
AAHK /
PM |
Contractor |
Action Level |
1. Notify AAHK /
PM, IEC and Contractor; 2. Carry out
investigation; 3. Report the
results of investigation to the IEC, AAHK / PM and Contractor; 4. Discuss with
the IEC and Contractor on remedial measures required; 5. Increase
monitoring frequency to check mitigation effectiveness. |
1. Review the
investigation results submitted by the ET; 2. Review the
proposed remedial measures by the Contractor and advise the AAHK / PM
accordingly; 3. Advise AAHK /
PM on the effectiveness of the proposed remedial measures. |
1. Confirm receipt
of notification of failure in writing; 2. Notify
Contractor; 3. In
consolidation with the IEC, agree with the Contractor on the remedial
measures to be implemented; 4. Supervise the
implementation of remedial measures. |
1. Submit noise
mitigation proposals to IEC and AAHK / PM; 2. Implement noise
mitigation proposals. |
Limit Level |
1. Inform IEC,
AAHK / PM and Contractor; 2. Repeat
measurements to confirm findings; 3. Inform EPD
after confirming the validity of exceedance; 4. Increase
monitoring frequency; 5. Identify source
and investigate the cause of exceedance; 6. Carry out
analysis of Contractor’s working procedures; 7. Discus with the
IEC, Contractor and AAHK / PM on remedial measures required; 8. Assess
effectiveness of Contractor’s remedial actions and keep IEC, EPD and AAHK /
PM informed of the results; 9. If exceedance
stops, cease additional monitoring. |
1. Discuss amongst
AAHK / PM, ET and Contractor on the potential remedial actions; 2. Review
contractor’s remedial actions whenever necessary to assure their effectiveness
and advise AAHK / PM accordingly. |
1. Confirm receipt
of notification of failure in writing; 2. Notify
Contractor; 3. In
consolidation with the IEC, agree with the Contractor on the remedial
measures to be implemented; 4. Supervise the
implementation of remedial measures; 5. If exceedance
continues, consider stopping the Contractor to continue working on that
portion of work which causes the exceedance until the exceedance is abated. |
1. Take immediate
action to avoid further exceedance; 2. Submit proposals
for remedial actions to IEC and AAHK / PM within three working days of
notification; 3. Implement the
agreed proposals; 4. Submit further
proposal if problem still not under control; 5. Stop the
relevant portion of works as instructed by AAHK / PM until the exceedance is
abated. |
Dissolved Oxygen and Temperature Measuring Equipment
¡ A dissolved oxygen level in the range of 0-20 mg/L and 0-200 % saturation; and
¡ A temperature of 0-45 degree Celsius with a capability of measuring to ±0.1 degree Celsius
pH Measuring Equipment
Turbidity Measurement Instrument
Salinity
Alkalinity
Nutrient, Heavy Metals and Suspended Solids (SS)
Water Depth Detector
Positioning Device
Calibration of In-situ Instruments
Table 5‑1: Laboratory analysis for SS, alkalinity, nutrient and heavy metals
Parameters |
Instrumentation |
Analytical
Method |
Reporting
Limit |
Suspended Solid (SS) |
Analytical
Balance |
APHA
2540D |
2 mg/L |
Nutrient |
|
|
|
Ammonia as N |
FIA |
APHA
4500 |
0.01
mg/L |
Unionised ammonia (NH3)* |
By
calculation |
By
calculation |
By
calculation |
Nitrite as N |
FIA |
APHA
4500 |
0.01
mg/L |
Nitrate as N |
FIA |
APHA
4500 |
0.01
mg/L |
TKN as N |
Titration |
APHA
4500 |
0.1
mg/L |
Total Phosphorus |
Colorimetric |
APHA
4500 |
0.01
mg/L |
Reactive Phosphorus |
FIA |
APHA
4500 |
0.01
mg/L |
Heavy
Metals |
|
|
|
Cadmium (Cd) |
ICP-MS |
USEPA
6020A |
0.1
µg/L |
Chromium (Cr) |
ICP-MS |
USEPA
6020A |
0.2
µg/L |
Copper (Cu) |
ICP-MS |
USEPA
6020A |
0.2
µg/L |
Nickel (Ni) |
ICP-MS |
USEPA
6020A |
0.2
µg/L |
Lead (Pb) |
ICP-MS |
USEPA
6020A |
0.2
µg/L |
Zinc (Zn) |
ICP-MS |
USEPA
6020A |
1 µg/L |
Arsenic (As) |
ICP-MS |
USEPA
6020A |
1 µg/L |
Silver (Ag) |
ICP-MS |
USEPA
6020A |
0.1
µg/L |
Mercury (Hg) |
ICP-MS |
APHA
7470A |
0.05
µg/L |
*Note: Calculation based on the
laboratory result of ammonia nitrogen (NH4-N) and in-situ measured
pH, salinity and temperature.
Table 5‑2: Water Quality Monitoring Stations (construction and post construction phases)
Monitoring Stations |
|
Coordinates |
|
|
|
Description |
Easting |
Northing |
Parameters |
Construction Activities Monitored |
|
C1 |
Control |
804247 |
815620 |
DO, pH, Temperature, Salinity, Turbidity,
SS |
From commencement of advance marine works
(submarine 11 kV cable diversion) until completion of all marine filling works
for land formation |
C2 |
Control |
806945 |
825682 |
||
C3 |
Control |
817803 |
822109 |
From commencement of land formation until
completion of all marine filling works |
|
IM1 |
Impact |
806458 |
818351 |
From commencement of land formation until
completion of all marine filling works |
|
IM2 |
Impact |
806193 |
818852 |
From commencement of land formation until
completion of nearest 1 km of seawall |
|
IM3 |
Impact |
806019 |
819411 |
||
IM4 |
Impact |
805039 |
819570 |
||
IM5 |
Impact |
804924 |
820564 |
||
IM6 |
Impact |
805828 |
821060 |
||
IM7 |
Impact |
806835 |
821349 |
From commencement of land formation until
completion of all marine filling works |
|
IM8 |
Impact |
807838 |
821695 |
From commencement of land formation until
completion of nearest 1 km of seawall |
|
IM9* |
Impact |
808811 |
822094 |
DO, pH, Temperature, Salinity, Turbidity,
SS, Alkalinity *Heavy metals and nutrient |
From commencement of land formation until completion
of nearest 1 km of seawall |
IM10* |
Impact |
809838 |
822240 |
From commencement of land formation until
completion of all marine filling works |
|
IM11* |
Impact |
810545 |
821501 |
||
IM12* |
Impact |
811519 |
821162 |
From commencement of land formation until
completion of nearest 1 km of seawall |
|
IM13 |
Impact (for submarine 11 kV cable
diversion) |
Mobile station (500 m envelope of water
jetting works) |
DO, pH, Temperature, Salinity, Turbidity,
SS |
From commencement until completion of water
jetting works |
|
IM14 |
Impact (for submarine 11 kV cable
diversion) |
Mobile station (500 m envelope of field
joint excavation works) |
From commencement until completion of field
joint excavation works |
||
SR1 |
Future Hong Kong-Zhuhai-Macao Bridge Hong
Kong Boundary Crossing Facilities (HKBCF) Seawater Intake for cooling |
812745 |
820085 |
DO, pH, Temperature, Salinity, Turbidity,
SS |
From commencement of advance marine works
(submarine 11 kV cable diversion) until completion of all marine filling
works for land formation |
SR2 |
Planned marine park / hard corals at The
Brothers / Tai Mo To |
814166 |
821463 |
||
SR3 |
Sha Chau and Lung Kwu Chau Marine Park / fishing
and spawning grounds in North Lantau |
807571 |
822147 |
||
SR4 |
Sha Lo Wan |
807798 |
816802 |
||
SR5 |
San Tau Beach SSSI |
810728 |
816230 |
||
SR6 |
Tai Ho Bay, Near Tai Ho Stream SSSI |
814663 |
817899 |
||
SR7 |
Ma Wan Fish Culture Zone (FCZ) |
823742 |
823636 |
||
SR8 |
Seawater Intake for cooling at Hong Kong
International Airport (East) |
811593 |
820417 |
¡ Impact (IM)
stations should be within the 500 m envelope of construction works;
¡ Sensitive
receivers (SR) stations should be at close proximity to key sensitive
receivers; and
¡ Control
stations (C), as far as practicable, should be at representative locations of
the water body being monitored while undisturbed by the project.
For
a combined DCM works area with longest diameter length smaller or equal to 200
m:
i. Two monitoring stations upstream of DCM works area;
ii. Three monitoring stations downstream and at 150 m envelope of DCM works area;
iii. Three monitoring stations downstream and at 250 m envelope of DCM works area;
iv. Monitoring stations should be at least 50 m apart;
v. Downstream monitoring stations should be perpendicular to the tidal direction.
For a combined DCM works area with longest diameter length larger than 200 m:
i. Two monitoring stations upstream of DCM works area;
ii. Five monitoring stations downstream and at 150 m envelope of DCM works area;
iii. Five monitoring stations downstream and at 250 m envelope of DCM works area;
iv. Downstream monitoring stations should be perpendicular to the tidal direction.
1 As defined by the United States Army Corporation of Engineers (USACE) classification system for silt curtains.
Chart 5-1: Flow
Chart for DCM Monitoring
|
Table 5‑3: Action and Limit Levels for Water Quality
Parameters |
Action
Level |
Limit
Level |
DO in mg/L (Surface, Middle & Bottom) |
Surface
and Middle 5
percentile of baseline data for surface and middle layer |
Surface
and Middle 5 mg/L
or 1 percentile of baseline data for surface and middle layer for Fish
Culture Zone (SR7) 4 mg/L
or 1 percentile of baseline data for surface and middle layer for other
stations |
Bottom 5
percentile of baseline data for bottom layer |
Bottom 2 mg/L
or 1 percentile of baseline data for surface and middle layer |
|
Temperature in oC (for intensive DCM monitoring only) |
1.8oC
above the temperature recorded at representative control stations at the same
tide of the same day |
2oC
above the temperature recorded at representative control stations at the same
tide of the same day |
SS in mg/L |
95 percentile
of baseline data or 120% of upstream control station at the same tide of the
same day, whichever is higher |
99
percentile of baseline data or 130% of upstream control station at the same
tide of the same day, whichever is higher |
Turbidity in NTU |
||
Alkalinity in ppm |
||
Nutrient |
||
Ammonia (NH3) |
||
Unionised ammonia (NH3) (with 0.021 mg/L as the upper limit) |
||
Nitrite (NO2) |
||
Nitrate (NO3) |
||
TKN |
||
Total Phosphorus |
||
Reactive Phosphorus |
||
Heavy
Metals |
|
|
Cadmium (Cd) |
0.2 µg/L |
|
Chromium (Cr) |
15 µg/L |
|
Copper (Cu) |
3.1 µg/L |
|
Nickel (Ni) |
8.2 µg/L |
|
Lead (Pb) |
7.2 µg/L |
|
Zinc (Zn) |
10 µg/L |
|
Arsenic (As) |
25 µg/L |
|
Silver (Ag) |
1.9 µg/L |
|
Mercury (Hg) |
0.05 µg/L |
Notes:
1. For DO measurement, non-compliance occurs when monitoring result is lower than the limits.
2. For parameters other than DO, non-compliance of water quality results when monitoring results is higher than the limits.
3. Depth-averaged results are used unless specified otherwise.
4. All the figures given in the table are used for reference only and the EPD may amend the figures whenever necessary.
5. For all mobile impact stations, the baseline data will be represented by the nearest stationary monitoring station.
Table 5‑4: Event and Action Plan for Water Quality
|
Action |
|||
Event |
ET |
IEC |
AAHK /
PM |
Contractor |
Action level being exceeded by one sampling
day |
1.
Repeat in-situ measurement to confirm findings; 2.
Identify reasons for non-compliance and sources of impact; 3.
Inform IEC and Contractor; 4.
Check monitoring data, all plant, equipment and Contractor’s working methods; 5.
Discuss mitigation measures with IEC and Contractor; 6.
Repeat measurement on next day of exceedance. |
1.
Discuss with ET and Contractor on the mitigation measures; 2.
Review proposals on mitigation measures submitted by Contractor and advise
AAHK / PM accordingly; 3.
Assess the effectiveness of the implemented mitigation measures. |
1.
Discuss with IEC on the proposed mitigation measures; 2. Make
agreement on the mitigation measures to be implemented; 3.
Assess the effectiveness of the implemented mitigation measures. |
1.
Inform AAHK / PM and confirm notification of the non-compliance in writing; 2.
Rectify unacceptable practice; 3.
Check all plant and equipment; 4.
Consider changes of working methods; 5. Discuss
with ET and IEC and propose mitigation measures. |
Action Level being exceeded by more than
two consecutive sampling days |
1.
Repeat in-situ measurement to confirm findings; 2.
Identify reasons for non-compliance and sources of impact; 3. Inform
IEC and Contractor; 4.
Check monitoring data, all plant, equipment and Contractor’s working methods; 5.
Discuss mitigation measures with IEC and Contractor; 6.
Ensure mitigation measures are implemented; 7.
Prepare to increase the monitoring frequency to daily; 8.
Repeat measurement on next day of exceedance. |
1.
Discuss with ET and Contractor on the mitigation measures; 2.
Review proposals on mitigation measures submitted by Contractor and advise
AAHK / PM accordingly; 3. Assess
the effectiveness of the implemented mitigation measures. |
1.
Discuss with IEC on the proposed mitigation measures; 2. Make
agreement on the mitigation measures to be implemented; 3.
Assess the effectiveness of the implemented mitigation measures. |
1.
Inform AAHK / PM and confirm notification of the non-compliance in writing; 2.
Rectify unacceptable practice; 3.
Check all plant and equipment; 4.
Consider changes of working methods; 5.
Discuss with ET and IEC and propose mitigation measures to IEC and AAHK / PM
within 3 working days; 6.
Implement the agreed mitigation measures. |
Limit Level being exceeded by one sampling
day |
1.
Repeat in-situ measurement to confirm findings; 2.
Identify reasons for non-compliance and sources of impact; 3. Inform
IEC, Contractor and EPD; 4.
Check monitoring data, all plant, equipment and Contractor’s working methods; 5.
Discuss mitigation measures with IEC, AAHK / PM and Contractor; 6.
Ensure mitigation measures are implemented; 7.
Increase the monitoring frequency to daily until no exceedance of limit
level. |
1.
Discuss with ET and Contractor on the mitigation measures; 2.
Review proposals on mitigation measures submitted by Contractor and advise
AAHK / PM accordingly; 3.
Assess the effectiveness of the implemented mitigation measures. |
1.
Discuss with IEC, ET and Contractor on the proposed mitigation measures; 2.
Request Contractor to critically review the working methods; 3. Make
agreement on the mitigation measures to be implemented; 4.
Assess the effectiveness of the implemented mitigation measures. |
1.
Inform AAHK / PM and confirm notification of the non-compliance in writing; 2.
Rectify unacceptable practice; 3.
Check all plant and equipment; 4.
Consider changes of working methods; 5.
Discuss with ET, IEC and AAHK / PM and propose mitigation measures to IEC and
AAHK / PM within three working days; 6.
Implement the agreed mitigation measures. |
Limit Level being exceeded by more than one
consecutive sampling days |
1. Repeat
in-situ measurement to confirm findings; 2.
Identify reasons for non-compliance and sources of impact; 3.
Inform IEC, Contractor and EPD; 4.
Check monitoring data, al plant, equipment and Contractor’s working methods; 5.
Discuss mitigation measures with IEC, AAHK / PM and Contractor; 6.
Ensure mitigation measures are implemented; 7.
Increase the monitoring frequency to daily until no exceedance of limit level
for two consecutive days. |
1.
Discuss with ET and Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by Contractor and advise AAHK / PM
accordingly; 3.
Assess the effectiveness of the implemented mitigation measures. |
1.
Discuss with IEC, ET and Contractor on the proposed mitigation measures; 2.
Request contractor to critically review the working methods; 3. Make
agreement on the mitigation measures to be implemented; 4.
Assess the effectiveness of the implemented mitigation measures; 5. Consider
and instruct, if necessary, the Contractor to slow down or to stop all or
part of the construction activities until no exceedance of limit level. |
1.
Inform AAHK / PM and confirm notification of the non-compliance in writing; 2.
Rectify unacceptable practice; 3.
Check all plant and equipment; 4.
Consider changes of working methods; 5.
Discuss with ET, IEC and AAHK / PM and propose mitigation measures to IEC and
AAHK / PM within three working days; 6.
Implement the agreed mitigation measures; 7. As directed
by AAHK / PM, to slow down or to stop all or part of the construction
activities. |
Table 5‑5: Event and Action Plan for DCM Process
|
Action |
|||
Event |
ET |
IEC |
AAHK / PM |
Contractor |
Action
level being exceeded by one sampling day |
1. Repeat in-situ measurement to confirm
findings; 2. identify reasons for non-compliance and
sources of impact; 3. Inform IEC and Contractor; 4. Check monitoring data, all plant,
equipment and Contractor’s working methods; 5. Discuss mitigation measures with IEC and
Contractor; 6. During intensive DCM monitoring,
increase monitoring frequency in accordance with Chart 5-1. During regular DCM monitoring, repeat
measurement on next day of exceedance. |
1. Discuss with ET and Contractor on the
mitigation measures; 2. Review proposals on mitigation measures
submitted by Contractor and advise AAHK / PM accordingly; 3. Assess the effectiveness of the
implemented mitigation measures. |
1. Discuss with IEC on the proposed
mitigation measures; 2. Make agreement on the mitigation
measures to be implemented; 3. Assess the effectiveness of the
implemented mitigation measures. |
1. Inform AAHK / PM and confirm
notification of the non-compliance in writing; 2. Rectify unacceptable practice; 3. Check all plant and equipment; 4. Consider changes of working methods; 5. Discuss with ET and IEC and propose
mitigation measures. |
Action
Level being exceeded by more than two consecutive sampling days |
1. Repeat in-situ measurement to confirm
findings; 2. Identify reasons for non-compliance and
sources of impact; 3. Inform IEC and Contractor; 4. Check monitoring data, all plant,
equipment and Contractor’s working methods; 5. Discuss mitigation measures with IEC and
Contractor; 6. Ensure mitigation measures are
implemented; 7. During intensive DCM monitoring,
increase monitoring frequency in accordance with Chart 5-1. During regular DCM monitoring, repeat
measurement on next day of exceedance and prepare to increase the monitoring
frequency to daily. |
1. Discuss with ET and Contractor on the
mitigation measures; 2. Review proposals on mitigation measures
submitted by Contractor and advise AAHK / PM accordingly; 3. Assess the effectiveness of the
implemented mitigation measures. |
1. Discuss with IEC on the proposed
mitigation measures; 2. Make agreement on the mitigation
measures to be implemented; 3. Assess the effectiveness of the
implemented mitigation measures. |
1. Inform AAHK / PM and confirm
notification of the non-compliance in writing; 2. Rectify unacceptable practice; 3. Check all plant and equipment; 4. Consider changes of working methods; 5. Discuss with ET and IEC and propose
mitigation measures to IEC and AAHK / PM within 3 working days; 6. Implement the agreed mitigation
measures. 7. As directed by AAHK / PM, to slow down
all or part of the construction activities. |
Limit Level
being exceeded by one sampling day |
1. Repeat in-situ measurement to confirm
findings; 2. Identify reasons for non-compliance and
sources of impact; 3. Inform IEC, Contractor and EPD; 4. Check monitoring data, all plant,
equipment and Contractor’s working methods; 5. Discuss mitigation measures with IEC,
AAHK / PM and Contractor; 6. Ensure mitigation measures are
implemented; 7. During intensive DCM monitoring,
increase monitoring frequency in accordance with Chart 5-1. During regular DCM monitoring, increase
the monitoring frequency to daily until no exceedance of limit level |
1. Discuss with ET and Contractor on the
mitigation measures; 2. Review proposals on mitigation measures
submitted by Contractor and advise AAHK / PM accordingly; 3. Assess the effectiveness of the
implemented mitigation measures. |
1. Discuss with IEC, ET and Contractor on
the proposed mitigation measures; 2. Request Contractor to critically review
the working methods; 3. Make agreement on the mitigation
measures to be implemented; 4. Assess the effectiveness of the
implemented mitigation measures. |
1. Inform AAHK / PM and confirm
notification of the non-compliance in writing; 2. Rectify unacceptable practice; 3. Check all plant and equipment; 4. Consider changes of working methods; 5. Discuss with ET, IEC and AAHK / PM and
propose mitigation measures to IEC and AAHK / PM within three working days; 6. Implement the agreed mitigation
measures. |
Limit
Level being exceeded by more than one consecutive sampling days |
1. Repeat in-situ measurement to confirm
findings; 2. Identify reasons for non-compliance and
sources of impact; 3. Inform IEC, Contractor and EPD; 4. Check monitoring data, al plant,
equipment and Contractor’s working methods; 5. Discuss mitigation measures with IEC, AAHK
/ PM and Contractor; 6. Ensure mitigation measures are
implemented; 7. During intensive DCM monitoring,
increase monitoring frequency in accordance with Chart 5-1. During regular DCM monitoring,
re-initiate the intensive DCM monitoring in accordance with
Chart 5-1. |
1. Discuss with ET and Contractor on the
mitigation measures; 2. Review proposals on mitigation measures
submitted by Contractor and advise AAHK / PM accordingly; 3. Assess the effectiveness of the
implemented mitigation measures. |
1. Discuss with IEC, ET and Contractor on
the proposed mitigation measures; 2. Request contractor to critically review
the working methods; 3. Make agreement on the mitigation
measures to be implemented; 4. Assess the effectiveness of the
implemented mitigation measures; 5. Consider and instruct, if necessary, the
Contractor to slow down or to stop all or part of the construction activities
until no exceedance of limit level. |
1. Inform AAHK / PM and confirm
notification of the non-compliance in writing; 2. Rectify unacceptable practice; 3. Check all plant and equipment; 4. Consider changes of working methods; 5. Discuss with ET, IEC and AAHK / PM and
propose mitigation measures to IEC and AAHK / PM within three working days; 6. Implement the agreed mitigation
measures; 7. As directed by AAHK / PM, to stop all or
part of the construction activities. |
Table 5-6: Treated Effluent Quality Criteria for Greywater Treatment Facility
Parameters |
Criteria Level |
SS |
≤ 5 mg/L |
BOD5 |
≤ 10 mg/L |
COD |
≤ 50 mg/L |
Oil and
Grease |
≤ 10 mg/L |
Surfactants
(total) |
≤ 5 mg/L |
E. coli |
< 1 count / 100ml |
pH |
6.0 – 9.0 |
Turbidity |
< 2 NTU |
Faecal
Coliforms |
Non detectable / 100ml |
Table 7‑1: Summary of Waste Arising during Construction Phase
Waste Type |
Key
Sources of Waste Generation |
Timing
of Waste Generation |
Estimated
Total Quantity of Waste Generation |
Waste Reuse
or Disposal |
Handling
Methods |
Inert C&D Material |
Excavation for APM
& BHS tunnels, new APM depot and airside tunnels; piling works for
TRC & other buildings; superstructure construction works; surplus
surcharge material; modification of existing northern seawall; excavation and
demolition as well as superstructure construction works for T2 expansion;
excavation for improvement of road networks; and HDD for
diversion of existing submarine pipelines |
Q3 of
2015 to Q4 of 2022 |
9,543,500 m3 (in-situ volume) |
About 3,639,230 m3
of the inert C&D materials generated would be reused on-site as fill
materials for the proposed land formation works. The remaining 5,904,270 m3 would
be delivered off-site to any identified projects that need fill materials
and/or to the government’s PFRF for beneficial use by other projects in Hong
Kong. |
Segregation
of inert C&D material to avoid
contamination from other waste arising Stockpile areas
should be covered and applied with regular water spraying |
Non-inert C&D Material |
Site clearance of
the golf course area; demolition works for T2 expansion;
and superstructure construction works for various buildings
/ facilities |
Q4 of
2016 to Q4 of 2021 |
96,200 m3 (in-situ volume) |
The non-inert
C&D material will be disposal of at landfills after on-site sorting and segregation of
recyclable materials |
Separation of
non- inert C&D materials from
inert C&D materials Stored in
compatible containers in designated area on-site |
Excavated Marine Sediments |
Excavation at the
cable field joint area |
2015/16 |
About 10,200 m3 (in-situ volume) |
Type 1 open sea
disposal for Category L sediment or Type 1 open sea disposal at dedicated
sites for Category Mp sediment, according to PNAP ADV-21 (subject
to endorsement by MFC of CEDD and EPD
as well as obtaining dumping permit from EPD under DASO) |
Stockpile with
tarpaulin covers with earth bunds and sand bags barriers, if applicable. |
|
Piling works of
the TRC, APM & BHS tunnels, airside tunnels and other facilities on the
proposed land formation area |
Q1 of 2017 to Q3
of 2022 |
About
705,350 m3 (in-situ volume) |
Treatment by
cement mixing and stabilisation and on-site reuse of treated sediments as
backfilling materials, although the treatment level / details and the reuse
mode are under further development. |
|
|
Piling works of
marine sections of the approach lights for the third runway |
2018 to
2019 (subject to detailed design) |
Western approach
lights: about 530 m3 of marine sediments (in-situ volume) Eastern
approach lights: about 1,060 m3 of DCM-treated sediment (in-situ
volume) |
Treatment by cement
mixing and stabilisation and on-site reuse of treated sediments as
backfilling materials, although the treatment level / details and the reuse
mode are under further development. |
|
|
Piling works of
new HKIAAA beacons |
2018 to
2019 (subject to detailed design) |
About 220 m3 (in-situ volume) |
Treatment by
cement mixing and stabilisation and on-site reuse of treated sediments as
backfilling materials, although the treatment level / details and the reuse
mode are under further development. |
|
|
Basement works of
T2 expansion |
Q4 of
2016 to Q1 of 2019 |
About
50,730 m3 (in-situ volume) |
Treatment by
cement mixing and stabilisation and on-site reuse of treated sediments as backfilling
materials, although the treatment level / details and the reuse mode are
under further development. |
|
|
Excavation works
of APM depot |
Q1 of
2018 to Q3 of 2020 |
About
9,770 m3 (in-situ volume) |
Treatment by cement
mixing and stabilisation and on-site reuse of treated sediments as
backfilling materials, although the treatment level / details and the reuse
mode are under further development. |
|
Chemical Waste |
Used cleansing
fluids, solvents, lubricating oil, waste fuel, etc., from
maintenance and servicing of construction plant and equipment |
2015 to
Early 2023 |
Anticipated as
small quantity To be quantified
in the site Waste Management Plan to be prepared by the Contractor |
Disposal of at the
Chemical Waste Treatment Centre or other licensed recycling facilities
|
Stored in
compatible containers in designated area on-site |
General Refuse & Floating Refuse |
Food scraps, waste
paper, empty containers, etc. generated from the construction workforce |
2015 to
Early 2023 |
General refuse: maximum
daily arising of up to 9,100 kg |
Encourage
segregation of recyclable materials (e.g., paper, tin-cans, etc.) for
collection by outside recyclers Collection
of non-recyclable refuse by a reputable collector for disposal at designated
landfill sites. |
Provide on-site
collection points together with recycling bins |
|
Floating refuse
trapped or accumulated in the newly constructed seawall |
2015 to
Early 2023 |
Floating refuse: roughly 65 m3/year
to be collected from the newly constructed seawall |
Collection by a reputable
waste collector for disposal at designated landfill sites |
Provide on-site
collection points |
Avoidance
Timing of Construction Works
Minimisation
Preservation
of Nesting Vegetation
Coral
Dive Survey at Directly Affected Site and Potential Recipient Site(s)
¡ Temperature, time and date;
¡ Location (GPS);
¡ Depth range;
¡ Visibility;
¡ Substratum type (i.e. hard substratum seabed, intertidal rocky area); and
¡ Other invertebrates present.
Rapid
Ecological Assessment Survey
¡ Tier I assessed the relative coverage of major benthic groups and substrata.
¡ Tier II provided an inventory of sedentary/ sessile benthic taxa, which will be ranked in terms of their abundance at the survey site.
1)
Baseline Monitoring – 6 months of baseline surveys will be
undertaken before the commencement of construction works at a frequency of two
full surveys per month. The commencement date of baseline survey shall
be agreed between the ET / IEC / AAHK / PM to ensure timely submission of the
baseline monitoring report to EPD and relevant authorities. The purpose of the baseline monitoring is to
establish pre-construction conditions prior to the commencement of the works
and to demonstrate the suitability of the proposed monitoring methods.
2)
Construction Phase Monitoring – This will be conducted for the duration of
the marine construction works for the third runway project at a
frequency of two full surveys per month with a review on the frequency after
the first year.
The purpose of the construction phase monitoring is to evaluate conditions
during construction and provide data for the preparation of Marine Park
establishment and management plan.
3)
Post Construction Phase Monitoring – This will be conducted upon the completion of
marine construction works for 12 months at a frequency of two full surveys per
month. The purpose of the post construction phase monitoring is to evaluate
conditions after completion of all marine works and collect data for the review
of recovery of the marine environment.
4)
Operation Phase Monitoring - This will be conducted for a period of at
least 12 months after the implementation of proposed Marine Park at a
frequency of two full surveys per month. The main purpose of the mitigation effectiveness monitoring is to
detect any rebound in use of areas north and east of HKIA during the
implementation of proposed Marine Park as mitigation for habitat loss for the
airport expansion, and to evaluate the overall, long-terms impacts of the
project on CWDs.
Table 10.3: Land-based Survey Station Details
Station |
Location |
Geographical Coordinates |
Station Height (m) |
Approx. Tracking Distance (km) |
D |
SHA CHAU |
22° 20’ 43.5” N 113° 53’ 24.66” E |
45.66 |
3 |
Theodolite
Tracking Data Analysis
§ Acoustic
decoupling of construction equipment;
§ Construction
vessel speed limits, predefined vessel routing and skipper training. A “Regular Marine Travel Routes Plan” will be prepared
and submitted to the relevant Authority for approval within 2 months of the
commencement of construction to define the routings for construction vessels
within Hong Kong waters;
§ Dolphin
exclusion zones (DEZ) during ground improvement works (e.g. DCM), water jetting
works for submarine cables diversion, open trench dredging at the field joint
locations and seawall construction and also during bored piling work but as a
precautionary measure only. A DEZ for
night time works would be developed and specified before construction for
evaluation by the Authorities;
§ Chemical/
oil spill response plan; and
§ SkyPier
high speed ferries’ speed and routing restrictions.
¡ Audit of acoustic decoupling for land formation works and the vessel restrictions requirements, as specified by the specifications prepared prior to commencement of marine construction works;
¡ Implementation and audit of the dolphin exclusion zone during marine works in accordance with the specification prepared prior to commencement of marine construction works;
¡ Audit the spill response plan during marine works in accordance with the specification prepared prior to commencement of marine construction works;
¡ Audit the “Regular Marine Travel Routes Plan” and the construction vessel adherence to this specification; and
¡ Audit of the SkyPier high speed ferries’ speed and routing restrictions in accordance with the specification prepared prior to commencement of marine construction works.
¡ Audit the pre-construction coral dive survey is also proposed at the artificial seawall at northern and northeastern airport island, and the daylighting locations at Sha Chau to check the status of Balanophyllia sp. and other coral species and review the feasibility of translocation. A pre-construction coral dive survey plan and report will be prepared for agreement with the Authority (See Section 10.2.2);
¡ Audit the baseline, construction and post-construction phase dolphin monitoring, which may be revised or updated prior to commencement of marine construction works (see Section 10.2.4);
¡ Audit the actual numbers of HSFs operating from SkyPier after the HZMB and HKBCF commence operations by review of information obtained from the SkyPier operators;
¡ Audit the cumulative assessment construction phase dolphin monitoring in accordance with the specification prepared prior to commencement of marine construction works (see Section 10.2.6).
¡ Compensation of a Marine Park of size around 2,400 ha to connect between the existing Sha Chau and Lung Kwu Chau Marine Park and planned marine park at The Brothers for the loss of marine habitats in northern Lantau waters;
¡ Chemical/ Oil spill response plan; and
¡ SkyPier high speed ferries’ speed and routing restrictions.
¡ Audit the spill response plan once every 6 months for a period of one year; and
¡ Audit of the SkyPier high speed ferries’ speed and routing restrictions in accordance with the specification prepared once every 3 months for a period of one year.
¡ The construction area and contractor’s temporary works areas shall be minimised to avoid impacts on adjacent landscape (CM1);
¡ Reduction of construction period to practical minimum (CM2);
¡ Phasing of the construction stage to reduce visual impacts during the construction phase (CM3);
¡ Construction traffic (land and sea) including construction plants, construction vessels and barges shall be kept to a practical minimum (CM4);
¡ Erection of decorative mesh screens or construction hoardings around works areas in visually unobtrusive colours (CM5);
¡ Avoidance of excessive height and bulk of site buildings and structures (CM6);
¡ Control of night-time lighting by hooding all lights and through minimisation of night working periods (CM7);
¡ All existing trees shall be carefully protected during construction. Detailed Tree Protection Specification shall be provided in the Contract Specification. Under this specification, the Contractor shall be required to submit, for approval, a detailed working method statement for the protection of trees prior to undertaking any works adjacent to all retained trees, including trees in contractor’s works areas (CM8);
¡ Trees unavoidably affected by the works shall be transplanted where practical. A detailed Tree Transplanting Specification shall be provided in the Contract Specification, if applicable. Sufficient time for necessary tree root and crown preparation periods shall be allowed in the project programme (CM9); and
¡ Land formation works shall be followed with advanced hydroseeding around taxiways and runways as soon as practical (CM10).
¡ Sensitive landscape design of reclamation edge by incorporating different angles of gradient and the use of a range of armour rock sizes placed randomly in a riprap approach for an irregular appearance. Planting of native coastal plants shall be incorporated (OM1);
¡ All above ground structures, including, Vent Shafts, Emergency and Firemen’s’ Accesses etc. shall be, either fully integrated with the planned buildings, or sensitively designed in a manner that responds to the existing and planned urban context, and minimises potential adverse landscape and visual impacts (OM2);
¡ Sensitive design of buildings and structures in terms of scale, height and bulk (visual weight) (OM3);
¡ Use appropriate building materials and colours in built structures to create cohesive visual mass (OM4);
¡ Lighting units to be directional and minimise unnecessary light spill and glare (OM5);
¡ Greening measures, including vertical greening, green roofs, road verge planting and peripheral screen planting shall be implemented (OM6);
¡ Compensatory Tree Planting for all felled trees shall be provided to the satisfaction of relevant Government departments. Required numbers and locations of compensatory trees shall be determined and agreed separately with Government during the Tree Felling Application process under the relevant technical circulars (OM7);
¡ Streetscape (e.g. paving, signage, street furniture, lighting etc.) shall be sensitively designed in a manner that responds to the existing and planned urban context, and minimises potential adverse landscape and visual impacts (OM8);
¡ All streetscape areas and hard and soft landscape areas disturbed during construction shall be reinstated to equal or better quality (due to implementation of screen planting, road verge planting etc.), to the satisfaction of the relevant Government departments (OM9);
¡ Aesthetic improvement planting of viaduct structure through greening of structure to mitigate visual impact of viaduct form (OM10); and
¡ Sensitive design of footbridges, noise barriers and enclosures with greening (screen planting / climbers / planters) and chromatic measures (OM11).
¡ The extent of the agreed works areas shall be regularly checked during the construction phase. Any trespass by the contractor outside the limit of works, including and damage to existing trees and woodland all noted and remedial action determined;
¡ The progress of the engineering works all be regularly reviewed on site to identify the earliest practical opportunities for the landscape works to be undertaken;
¡ All existing trees and vegetation within the study area which are not directly affected by the works shall be retained and protected;
¡ The methods of protecting existing vegetation proposed by the contractors shall be acceptable and enforced;
¡ All landscaping works shall be carried out in accordance with the specifications;
¡ The planting of trees and shrubs shall be carried out properly and within the right season as far as practical;
¡ The species and mix of the new trees and shrubs to be planted shall suitable; and
¡ The newly planted trees and grasses areas shall be maintained throughout the establishment period, particularly in respect of the following:
-
Regular watering, weeding and fertilising of
all trees and shrub planting and areas of grass reinstatement;
-
Regular grass cutting for reinstated areas;
-
Firming up of trees after periods of strong
winds;
-
Regular checks for eradication of pests,
fungal infection, etc.;
-
Pruning of dead or broken branches; and
-
Prompt replacement of dead plants and
regressing of failed areas of grass.
Table 12‑1: Monitoring Programme for Landscape and Visual
Stage |
Monitoring Task |
Monitoring Report |
Form of Approval |
Frequency |
Detailed
Design |
Checking of design works against the
recommendations of the landscape and visual impact assessments within the EIA
shall be undertaken during detailed design and tender stage, to ensure that
they fulfil the intention of the mitigation measures. Any changes to the
design, including design changes on site shall also be checked. |
Report by AAHK / PM confirming that the
design conforms to requirements of EP. |
Approved by Client |
At the end of the Detailed Design Phase |
Construction |
Checking of the contractor’s operations
during the construction period. |
Report on Contractor's compliance, by ET |
Counter signature of report by IEC |
Weekly |
Establishment
Works |
Checking of the planting works during the twelve-month
Establishment Period after completion of the construction works. |
Report on Contractor's compliance, by ET |
Counter signature of report by IEC |
Every two months |
Long
Term Management (10 year) |
Monitoring of the long-term management of the
planting works in the period up to 10 years after completion of the
construction works. |
Report on Compliance by ET or Maintenance Agency as
appropriate |
Counter signature of report by Management
Agency |
Annually |
Table 12‑2: Preliminary Funding, Implementation, Management and Maintenance Proposal
Landscape and Visual Mitigation Measure ID No. |
Funding Agency |
Implementation Agency |
Management Agency |
Maintenance Agency |
Construction Phase |
||||
CM1
– CM10 |
AAHK |
Contractor |
- |
- |
Operation Phase |
||||
OM1,
OM5, OM8, OM10, OM11 |
AAHK |
Design Engineer |
AAHK |
AAHK |
OM2
– OM4 |
AAHK |
Design Engineer |
Building Operator |
Building Operator |
OM6,
OM7, OM9 |
AAHK |
Contractor |
AAHK |
AAHK |
Table 12‑3: Event and Action Plan for Landscape and Visual
Event Action Level |
Action |
|||
ET |
IEC |
AAHK / PM |
CONTRACTOR |
|
Design Check |
Check final design conforms to the
requirements of EP and prepare report. |
Check report. Recommend remedial design if necessary. |
Undertake remedial if design necessary. |
|
Non-conformity on one occasion |
Identify source. Inform IEC and AAHK / PM. Discuss remedial actions with IEC, AAHK /
PM and Contractor. Monitor remedial actions until
rectification has been completed. |
Check report. Check Contractor’s working method. Discuss with ET and Contractor on possible
remedial measures. Advise AAHK / PM on effectiveness of
proposed remedial measures. Check implementation of remedial measures. |
Notify Contractor. Ensure remedial measures are properly
implemented. |
Amend working methods to prevent recurrence
of non-conformity. Rectify damage and undertake additional
action necessary. |
Repeated Non-conformity |
Identify source. Inform IEC and AAHK / PM. Increase monitoring frequency. Discuss remedial actions with IEC, AAHK /
PM and Contractor. Monitor remedial actions until
rectification has been completed. If non-conformity stops, cease additional
monitoring. |
Check monitoring report. Check Contractor’s working method. Discuss with ET and Contractor on possible
remedial measures. Advise AAHK / PM on effectiveness of
proposed remedial measures. Supervise implementation of remedial
measures. |
Notify Contractor. Ensure remedial measures area properly
implemented. |
Amend working methods to prevent recurrence
of non-conformity. Rectify damage and undertake additional
action necessary. |
¡ The EIA and EM&A recommendations on environmental protection and pollution control mitigation measures;
¡ The Environmental Permit conditions;
¡ On-going results of the EM&A programme;
¡ Works progress and programme;
¡ Individual works methodology proposals (which should include proposal on associated pollution control measures);
¡ Contract specifications on environmental protection;
¡ Relevant environmental protection and pollution control laws; and
¡ Previous site inspection results undertaken by the ET and others.
¡ The Contractor to log complaint and date of receipt onto the complaint database and inform AAHK / PM, ET and IEC immediately;
¡ The Contractor to investigate the complaint to determine its validity, and assess whether the source of the problem is due to construction works of the Project with the support of additional monitoring frequency, stations and parameters, if necessary;
¡ The Contractor to identify mitigation measures in consultation with IEC, ET and AAHK / PM if a complaint is valid and due to the construction works of the Project;
¡ The Contractor to implement the remedial measures as required by the AAHK / PM and to agree with the ET and IEC any additional monitoring frequency, stations and parameters, where necessary, for checking the effectiveness of the mitigation measures;
¡ AAHK / PM, ET and IEC to review the effectiveness of the Contractor’s remedial measures and the updated situation;
¡ The ET to undertake additional monitoring and audit to verify the situation if necessary, and oversee that circumstances leading to the complaint do not recur;
¡ If the complaint is referred by the EPD, the Contractor is to prepare interim report on the status of the complaint investigation and follow-up actions stipulated above, including the details of the remedial measures and additional monitoring identified or already taken, for submission to EPD within the time frame assigned by the EPD; and
¡ The ET to record the details of the complaint, results of the investigation, subsequent actions taken to address the complaint and updated situation including the effectiveness of the remedial measures, supported by regular and additional monitoring results in the monthly EM&A reports.
i. Up to half a page of executive summary
ii. Brief project background information
iii. Drawings showing locations of the baseline monitoring stations
iv. An updated construction programme with milestones of environmental protection / mitigation activities annotated
v. Monitoring results (in both hard and diskette copies) together with the following information:
¡ Monitoring methodology
¡ Name of laboratory and types of equipment used and calibration details
¡ Parameters monitored
¡ Monitoring locations (and depth, where relevant)
¡ Monitoring date, time, frequency and duration
¡ Quality assurance (QA) / quality control (QC) results and detection limits
vi. Details of influencing factors, including:
¡ Major activities, if any, being carried out on the site during the period / monitoring
¡ Weather conditions during the period / monitoring
¡ Other factors which might affect results
vii. Determination of the action and limit Levels for each monitoring parameter and statistical analysis of the baseline data, the analysis should conclude if there is any significant difference between control and impact stations for the parameters monitored
viii. Revisions for inclusion in the EM&A Manual
ix. Comments and conclusions
i. Executive summary (one to two pages):
¡ Breaches of action and limit levels
¡ Complaint log
¡ Notifications of any summons and status of prosecutions
¡ Changes made that affect the EM&A
¡ Future key issues
ii. Basic project information:
¡ Project organisation including key personnel contact names and telephone numbers
¡ Scope of works of the project
¡ Construction programme
¡ Works undertaken during the month with illustrations (such as location of works etc.)
¡ Drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations(with coordinates of the monitoring locations).
iii. A brief summary of EM&A requirements including:
¡ All monitoring parameters
¡ Environmental quality performance limits (action and limit levels)
¡ Event-Action Plans
¡ Environmental mitigation measures, as recommended in the project EIA study final report
¡ Environmental requirements in contract documents
iv. Environmental status
¡ Advice on status of compliance with environmental permit including the status of submissions under the environmental permit
v. Implementation status
¡ Implementation status of environmental protection and pollution control / mitigation measures, as recommended in the EIA Report
vi. Monitoring results (in both hard and diskette copies) together with the following information:
¡ Monitoring methodology
¡ Name of laboratory and types of equipment used and calibration details
¡ Parameters monitored
¡ Monitoring locations
¡ Monitoring date, time frequency, and duration
¡ Weather conditions during the period / monitoring
¡ Graphical plots of the monitored parameters in the month annotated against
¡ The major activities being carried out on site during the period
¡ Weather conditions that may affect the monitoring results
¡ Any other factors which might affect the monitoring results
¡ QA / QC results and detection limits
vii. Analysis of monitoring results, non-compliance, complaints, and notifications of summons and status of prosecutions:
¡ Analysis and interpretation of monitoring results in the month
¡ Any non-compliance (exceedances) of the environmental quality performance limits (action and limit levels)
¡ Changes made that affect the EM&A during the month
¡ Complaints received (written or verbal) for each media, including locations and nature of complaints, investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary
¡ Notification of summons and status of prosecutions for breaches of current environmental protection / pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary
¡ Reasons for and the implications of non-compliance, complaints, summons and prosecutions including review of pollution sources and working procedures
¡ Actions taken in the event of non-compliance and deficiency, and follow-up actions related to earlier non-compliance
viii. Others
¡ An account of the future key issues as reviewed from the works programme and work method statements
¡ Comment on the solid and liquid waste management status during the month including waste generation and disposal records
¡ Outstanding issues and deficiencies
¡ Comments on effectiveness of the environmental management systems, practices, procedures and mitigation measures, recommendations (for example, any improvement in the EM&A programme) and conclusions
ix. Appendix
¡ Monitoring schedule for the present and next reporting period
¡ Cumulative statistics on complaints, notifications of summons and successful prosecutions
¡ Outstanding issues and deficiencies
i. Executive summary (one to two pages):
¡ Breaches of action and limit levels
¡ Complaint log
¡ Notifications of any summons and status of prosecutions
¡ Changes made that affect the EM&A
¡ Future key issues
ii. Environmental status:
¡ Advice on status of compliance with environmental permit including the status of submissions under the environmental permit
iii. Implementation status:
¡ Implementation status of environmental protection and pollution control / mitigation measures, as recommended in the EIA Report
iv. Monitoring results (in both hard and diskette copies) together with the following information:
¡ Monitoring methodology
¡ Name of laboratory and types of equipment used and calibration details
¡ Parameters monitored
¡ Monitoring locations
¡ Monitoring date, time frequency, and duration
¡ Weather conditions during the period / monitoring
¡ Graphical plots of the monitored parameters in the month annotated against:
- The major activities being carried out on site during the period
- Weather conditions that may affect the monitoring results
- Any other factors which might affect the monitoring results
- QA / QC results and detection limits
v. Analysis of monitoring results, non-compliance, complaints, and notifications of summons and status of prosecutions:
¡ Analysis and interpretation of monitoring results in the month
¡ Any non-compliance (exceedances) of the environmental quality performance limits (action and limit levels)
¡ Changes made that affect the EM&A during the month
¡ Complaints received (written or verbal) for each media, including locations and nature of complaints, investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary
¡ Notification of summons and status of prosecutions for breaches of current environmental protection / pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary
¡ Reasons for and the implications of non-compliance, complaints, summons and prosecutions including review of pollution sources and working procedures
¡ Actions taken in the event of non-compliance and deficiency, and follow-up actions related to earlier non-compliance
vi. Others
¡ An account of the future key issues as reviewed from the works programme and work method statements
¡ Comment on the solid and liquid waste management status during the month including waste generation and disposal records
¡ Outstanding issues and deficiencies
¡ Comments on effectiveness of the environmental management systems, practices, procedures and mitigation measures, recommendations (for example, any improvement in the EM&A programme) and conclusions
vii. Appendix
¡ Monitoring schedule for the present and next reporting period
¡ Cumulative statistics on complaints, notifications of summons and successful prosecutions
¡ Outstanding issues and deficiencies
i. Up to half a page executive summary
ii. Basic project information including a synopsis of the project organization and programme, and a synopsis of works undertaken during the quarter
iii. A brief summary of EM&A requirements including:
¡ Monitoring parameters
¡ Environmental quality performance limits (Action and Limit levels)
¡ Environmental mitigation measures, as recommended in the project EIA Final Report
iv. Drawings showing the project area, environmental sensitive receivers and the locations of the monitoring and control stations
v. Implementation status of environmental protection and pollution control / mitigation measures, as recommended in the EIA Report
vi. Graphical plots of the monitored parameters over the past four months (the last month of the previous quarter and the present quarter) for representative monitoring stations annotated against:
¡ The major activities being carried out on site during the period
¡ Weather conditions during the period
¡ Any other factors which might affect the monitoring results
vii. Advice on the solid and liquid waste management during the quarter including waste generation and disposal records
viii. A summary of non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels)
ix. A brief review of the reasons for and the implications of any non-compliance, including a review of pollution sources and working procedures
x. A summary description of actions taken in the event of non-compliance and any follow-up procedures related to any earlier non-compliance
xi. A summary of all complaints received (written or verbal) for each media, liaison and consultation undertaken, actions and follow-up procedures taken
xii. Comments on the effectiveness and efficiency of the mitigation measures; recommendations on any improvements in the EM&A programme and conclusions for the quarter
xiii. Proponents’ contacts and any hotline telephone number for the public to make enquiries.
i. One to two pages of executive summary
ii. Basic project information including a synopsis of the project organization and programme, and a synopsis of works undertaken during the past 12 months
iii. A brief summary of EM&A requirements including:
¡ Monitoring parameters
¡ Environmental quality performance limits (Action and Limit levels)
¡ Environmental mitigation measures, as recommended in the project EIA Final Report
iv. Drawings showing the project area, environmental sensitive receivers and the locations of the monitoring and control stations
v. Implementation status of environmental protection and pollution control / mitigation measures, as recommended in the EIA Report
vi. Graphical plots of the monitored parameters over the past 12 months for representative monitoring stations annotated against:
¡ The major activities being carried out on site during the period
¡ Weather conditions during the period
¡ Any other factors which might affect the monitoring results
vii. Advice on the solid and liquid waste management during the past 12 months including waste generation and disposal records
viii. A summary of non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels)
ix. A brief review of the reasons for and the implications of any non-compliance, including a review of pollution sources and working procedures
x. A summary description of actions taken in the event of non-compliance and any follow-up procedures related to any earlier non-compliance
xi. A summary of all complaints received (written or verbal) for each media, liaison and consultation undertaken, actions and follow-up procedures taken
xii. Comments on the effectiveness and efficiency of the mitigation measures; recommendations on any improvements in the EM&A programme and conclusions for the quarter
xiii. Proponents’ contacts and any hotline telephone number for the public to make enquiries.
i. An executive summary
ii. Basic project information including a synopsis of the project organization and programme, contacts of key management, and a synopsis of work undertaken during the entire construction period
iii. A brief summary of EM&A requirements including:
¡ Monitoring parameters
¡ Environmental quality performance limits (action and limit levels)
¡ Environmental mitigation measures, as recommended in the project EIA study final report
iv. Drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations
v. Advice on the implementation status of environmental and pollution control / mitigation measures, as recommended in the project EIA study final report, summarised in the updated implementation status pro forma
vi. Graphical plots of the monitoring parameters over the construction period for representative monitoring stations, including the post-project monitoring annotated against:
¡ The major activities being carried out on site during the period
¡ Weather conditions during the period
¡ Any other factors which might affect the monitoring results
¡ The baseline condition
vii. Compare the EM&A data with the EIA predictions
viii. Effectiveness of the solid and liquid waste management
ix. A summary of non-compliance (exceedances) of the environmental quality performance limits (action and limit levels)
x. A brief account of the reasons the non-compliance including a review of pollution sources and working procedures
xi. A summary of the actions taken against the non-compliance
xii. A summary of all complaints received (written or verbal) for each media, liaison and consultation undertaken, actions and follow-up procedures taken
xiii. A review of the monitoring methodology adopted and with the benefit of hindsight, comment on its effectiveness (including cost effectiveness)
xiv. A summary of notifications of summons and successful prosecutions for breaches of the current environmental protection / pollution control legislations, locations and nature of the breaches, investigation, follow-up actions taken and results
xv. A review of the practicality and effectiveness of the EM&A programme (e.g. effectiveness and efficiency of the mitigation measures), and recommendation on any improvement in the EM&A programme
xvi. A conclusion to state the return of ambient and / or the predicted scenario as per EIA findings