TABLE OF CONTENTS
Page
15 Conclusions. 15-2
15.1 Impact Summary. 15-2
15.2 Benefits of the Project 15-2
15.3 Air Quality Impact 15-3
15.4 Noise Impact 15-3
15.5 Water Quality Impact 15-4
15.6 Land Contamination. 15-6
15.7 Hazard to Life. 15-6
15.8 Ecological Impact 15-7
15.9 Fisheries Impact 15-8
15.10 Landscape and Visual Impact 15-9
15.11 Cultural Heritage Impact 15-10
15.12 Waste Management Implications. 15-10
15.13 Health Impact 15-10
15.14 Environmental Outcomes. 15-11
15.15 Overall Conclusion. 15-17
LIST OF TABLES
Table 15.1 Summary of Key Environmental Outcomes / Benefits. 15-11
15.1.1.1
The Project covers the
following DP elements of Schedule 2 under the EIAO (Cap.499):
¡P
DP1 ¡V
|
Sewage treatment
works with an installed capacity of more than 15,000 m3 per day
under Item F.1 in Schedule 2 Part I;
|
¡P
DP2 ¡V
|
Sewage
treatment works under Item F.2 in Schedule 2 Part I---
¡± With an installed capacity
of more than 5,000 m3 per day; and
¡± A boundary of which is less
than 200m from the nearest boundary of an existing or planned residential
area, educational institution and health care institution.
|
¡P
DP3 ¡V
|
An activity for the
reuse of treated sewage effluent from a treatment plant under Item F.4 in
Schedule 2 Part I;
|
¡P
DP4 ¡V
|
Underground rock
caverns under Item Q.2 in Schedule 2 Part I;
|
¡P
DP5 ¡V
|
An
explosives depot in a stand‑alone, purpose built building under Item K.10 in
Schedule 2 Part I; and
|
¡P
DP6 ¡V
|
Decommissioning
of an explosives depot under Item 11 in Schedule 2 Part II.
|
15.1.1.2
This EIA report has provided an
assessment of the potential environmental impacts associated with the
construction and operation of the Project based on the preliminary engineering
design information available. The
assessment has been conducted, in accordance with the Study Brief No. ESB-273/2014 under the EIAO for the Project,
covering the following environmental issues.
¡P
Air Quality Impact
¡P
Noise Impact
¡P
Water Quality Impact
¡P
Land Contamination
¡P
Hazard to Life
¡P
Ecological Impact
¡P
Fisheries Impact
¡P
Landscape and Visual Impact
¡P
Cultural Heritage Impact
¡P
Waste Management Implications
¡P
Health Impact
15.1.1.3
The findings of this EIA Study
have determined the likely nature and extent of environmental impacts predicted
to arise from the construction and operation of the Project. During the EIA process, specific environmental
control and mitigation measures have been identified and incorporated into the
planning and design of the Project in order to achieve compliance with
environmental legislation and standards during both the construction and
operation phases. An EM&A
programme has also been developed.
The Implementation Schedules listing the recommended mitigation measures
are presented in the Section
16. A summary of the
environmental impacts are presented in the sections below.
15.2.1.1
Upon relocation of the STSTW to
caverns, 28 ha of land in Sha Tin with sea frontage can be released for
re-development to meet the needs of the society.
15.2.1.2
The living environment of the
surrounding area would be improved. The common potential impacts of a sewage
treatment works, particularly odour and visual impacts, can be very effectively
controlled and minimised. Odour
management of the STSTW would be greatly enhanced since the caverns would serve
as very effective natural barriers.
15.2.1.3
Advanced technologies can be
adopted for the new sewage treatment facilities to enhance operation process
performance, resilience and reliability, as well as operation efficiency.
15.2.1.4
Subject to subsequent planning,
the released STSTW site will provide opportunities for developing a green and
vibrant waterfront living environment with ample open space, a continuous
promenade and recreational facilities such as amenity areas, cycle tracks and
other leisure purposes could be created.
15.2.1.5
The development opportunities
of the surrounding area adjacent to the existing STSTW site would be enhanced
after completion of the Project and the accessibility of the area would be
improved by improving transport infrastructure at the area.
15.2.1.6
The project location is rich in
granite. Excavation of caverns will
produce a large amount of hard granitic rocks, which are valuable natural
resources for construction use.
Rocks produced under this Project would become a local source to support
the construction industry.
15.3.1.1
The assessment shows that the
potential construction dust impacts from the construction works of the Project
would mainly be related to construction dust from excavation, materials
handling, spoil removal and wind erosion.
With the implementation of mitigation measures specified in the Air
Pollution Control (Construction Dust) Regulation together with the recommended
dust suppression measures including watering 8 times a day on active works
areas, exposed areas and unpaved haul roads, and dust collector with 99% removal efficiency
for rock crusher, good site practices, the predicted
dust impact at ASRs would comply with the hourly, daily and annual particulate
criteria stipulated in the AQOs and EIAO-TM. An EM&A programme during
construction phase is recommended to ensure that the mitigation measures are to
be properly implemented.
15.3.1.2
Potential operational air
quality impacts would come from odour emission from the ventilation shaft of
CSTW after the deodourisation treatment at design odour removal efficiency of
80 ¡V 97%. The odour impact
assessment results show that the predicted odour concentration at all ASRs
located in the vicinity of CSTW would comply with the odour criterion (5 odour units based on an
averaging time of 5 seconds) stipulated in the
EIAO-TM. No further mitigation
measures are required. A
commissioning test on deodorisers is however recommended to ensure the
effectiveness of the deodorisation treatment implemented in the Project.
Construction Phase
15.4.1.1
This assessment has presented construction
noise impacts of the Project during construction of relocated STSTW including water reclamation facilities, decommissioning and demolition of the existing STSTW and the temporary explosives magazine.
The predicted maximum unmitigated noise levels at representative NSRs
would range from 70 to 89 dB(A).
With the adoption of quiet PME, use of movable noise barrier/acoustic
mat, and limitation of the number of on-time operating PMEs within 120m of the Neighbourhood
Advice-Action Council Harmony Manor during construction of access road, the
noise levels due to the Project itself at all representative residential NSRs
would comply with the EIAO-TM criterion of 75 dB(A). All representative educational NSRs
would also comply with the noise criteria except that occasional exceedances of
noise criterion during examination period are predicted at educational
NSR NR-C07 due to construction activities at the main
portal and at Area 73. As this NSR is located in close vicinity
of these work areas, all practical mitigation measures have been
exhausted. As the affected period
would be limited to examination periods and the affected educational NSR has
been noise insulated with air conditioners, it is considered that the residual
noise impact is in short term period and would be minimised by keeping the
windows closed during the affected examination periods. Notwithstanding this, it is recommended that particularly noisy construction activities should
be scheduled to avoid examination periods of this NSR as far as
practicable. The Contractor should
liaise with the school representative(s) to obtain the examination schedule so
as to avoid noisy construction activities during school examination period.
During the actual construction period, as much as
practically possible should be done to reduce the construction noise, and
on-going liaison with all concerned parties and site monitoring should also be
conducted during the course of the construction period. A construction noise EM&A programme
is recommended to check the compliance of the noise criteria during normal
daytime working hours.
15.4.1.2
Ground-borne construction noise
impacts pertinent to the use of hydraulic breaker, hand-held breaker, drill rig
and TBM would comply with criteria of EIAO-TM. No adverse ground-borne construction
noise impacts is predicted and therefore no noise mitigation measure and
noise monitoring are proposed.
15.4.1.3
For the temporary modification works at the
merging point of Ma On Shan Road and temporary access haul road, the provision
of 220m length of noise barrier of a height at 10mPD on the temporary access haul road to replace the existing 150m length of noise barrier at
9.2mPD to 10mPD height on Ma On Sha Road would pose negligible difference in
the overall traffic noise level at the sensitive facades in the vicinity. Once the construction work is completed,
the noise barrier on the concerned road section of Ma On Shan Road would be
re-installed according to the existing configuration.
Operational Phase
15.4.1.4
The noise impact associated
with the operation of the Project has been assessed. The predicted fixed plant noise levels
at the representative NSRs would comply with the criteria based on the plant
design information provided by the Engineer at the time of the assessment. If there is any change in engineering
design information during detailed design stage or fitting-out stage, the fixed
source noise design should be reviewed by the Engineer/Contractor to ensure
that both the NCO and EIAO-TM criteria at the NSRs can be met in the
future. Prior to the operational
phase of the Project, a commissioning test for the ventilation buildings, the
ventilation shaft, ventilation fan
for chiller plant room and cooling tower at the administration building would
be conducted to ensure compliance with the relevant allowable maximum sound
power levels.
15.5
Water
Quality Impact
Construction Phase
Land-based
Construction
15.5.1.1
Minor water quality impact would be associated
with land-based construction. Impacts may result from the surface runoff,
accidental spillage, sewage from on-site construction workers and groundwater
infiltration. Impacts could be
controlled to comply with the WPCO standards by implementing the recommended
mitigation measures.
Tolo Harbour Effluent Export Scheme (THEES) Connection Works
15.5.1.2
Both the TPSTW and existing
STSTW are secondary treatment plants with disinfection process. Under normal
operation of the THEES, the TPEPS would pump the secondarily treated and
disinfected effluent of TPSTW via a rising main and a submarine pipeline to the
STEPS. The STEPS would receive the secondarily treated and disinfected effluent
from both TPSTW and STSTW for combined discharge to the KTN in the Victoria
Harbour WCZ via the THEES effluent tunnel.
15.5.1.3
In order to maintain the
current arrangement in discharging effluent to KTN through THEES tunnel, the
provision of a dry construction zone within the THEES tunnel to allow
connection from the CSTW would be essential for the Project. During the
connection works, the THEES tunnel needs to be temporarily suspended from its
normal operation with effluent bypass into the Tolo Harbour.
15.5.1.4
Under the existing practice,
regular inspection and repair of the THEES would be carried out when necessary
to maintain proper functioning and integrity of the THEES. During each THEES
maintenance event, secondarily treated and disinfected effluent from TPSTW and
STSTW would be temporarily discharged to the Tolo Harbour to provide a dry zone
within the THEES tunnel for a maximum duration of 4 weeks. To minimize water
quality impact to Tolo Harbour, the necessary THEES connection works required
for this Project will be split into a number of steps for sequential and
synchronized implementation with THEES maintenance, thereby avoiding the need
for additional temporary suspension of the THEES. Each suspension will not be
longer than 4 weeks and will be outside the algae blooming season (January to
May), and the frequency will be no more than once per year during the
construction phase of the Project.
Therefore, no additional water quality effect on the Tolo Harbour waters
would result from the proposed THEES connection works. No cumulative or residual impact would
be expected during the construction phase of the Project with the recommended
mitigation measures properly implemented.
Operational Phase
15.5.1.5
The CSTW effluent together with
the TPSTW effluent will be discharged to the Victoria Harbour via the THEES
during normal operation. Compared with the existing STSTW, the CSTW has the same
design flow capacity (340,000m3 ADWF) per day) and effluent
standard. Hence, this Project will
not induce any change to the flow and loading of THEES effluent to the Victoria
Harbour.
15.5.1.6
Maintenance of the THEES tunnel
is required to ensure proper functioning and integrity of the tunnel. During
the inspection or maintenance of the THEES tunnel, temporary suspension of the
normal THEES operation with effluent bypass into the Tolo Harbour is
unavoidable in order to provide a safe and dry zone within the THEES tunnel. It
should be noted that such temporary effluent bypass during THEES maintenance is
part and parcel of the existing THEES regardless of whether the Project is
implemented or not.
15.5.1.7
Mathematical modelling was
undertaken under this EIA to study the water quality impact arising from a
4-week THEES maintenance discharge.
The model results indicated that even for such a discharge in the algae
blooming season (January to May) under the ultimate development scenario, the
increase in pollution level in Tolo Harbour would still be transient and
reversible.
15.5.1.8
With the design capacity,
effluent standards and effluent discharge points being the same as those of the
existing STSTW, this Project will not change the flow, load and discharge point
of the THEES effluent to Victoria Harbour and Tolo Harbour.
15.5.1.9
In order to further minimize
water quality impact, it is recommended under this Project to schedule the
THEES maintenance outside the algae blooming season (January to May). Water quality modelling indicates that
the pollution elevation in Tolo Harbour and the associated recovery period
would be significantly reduced and alleviated as compared to the case of inside
the algae blooming season (January to May). An event and action plan and a
water quality monitoring programme (presented in the standalone EM&A
Manual) is proposed for the THEES maintenance events during both construction
and operational phases to minimize water quality impacts.
15.5.1.10 Emergency discharges from the Project would possibly be the consequence
of pump failure, interruption of the electrical power supply or failure of
treatment units. Mitigation measures, including dual power supply or ring main
supply from electric company, standby pumps, treatment units and equipment,
would be provided to avoid the occurrence of any emergency discharge. A contingency plan has also been
formulated to minimize the impact of emergency discharges and facilitate
subsequent management of the situation emergency. An event and action plan and a water
quality monitoring programme (presented in the standalone EM&A Manual) is
proposed for the emergency discharge events during operational phase to
minimize water quality impacts. No
cumulative or residual impact would be expected during the operational phase of
the Project with the recommended mitigation measures properly implemented.
15.6
Land
Contamination
15.6.1.1
Site appraisal was carried out
in the period from November 2014 to March 2015 with site walkovers conducted in
November 2014 and January / July / November 2015. Based on the site appraisal, within the
Project boundary, the existing STSTW and the temporary works area on Area 73,
currently part of a VDC, are considered to be areas with potential land
contamination concerns.
15.6.1.2
A sampling and testing
programme, targeting the existing STSTW and the temporary works area on Area
73, has been proposed. Since the
sites will continue to be in use until the full commissioning of the relocated
STSTW, the proposed SI works and any necessary remediation action are
recommended to be carried out after decommissioning of the existing STSTW and
when the temporary works area on Area 73 is vacated, but prior to
re-development.
15.6.1.3
In addition, two sites (the
David Camp and proposed A Kung Kok Shan Road surface magazine site) within the
Project boundary are inaccessible or yet to be constructed. Further site
walkover is recommended within the sites when access to the camp site is
available and before the decommissioning of the surface magazine site to
confirm the presence of any land contamination. If land contamination were
presence, detailed land contamination assessment and remediation would be
required prior to the re-development.
15.6.1.4
Further site walkover,
assessment and remediation (if necessary), including the submission of
Supplementary CAP(s), CAR(s)/RAP(s) and RR(s) would follow EPD¡¦s prevailing
guidelines and recommendation in the EIA Study.
15.6.1.5
With the implementation of
further site walkover, land contamination assessment and, if required,
remediation works for the Project Site, any soil/groundwater contamination
would be identified and properly treated prior to re-development. Land contamination impacts are therefore
considered surmountable to future occupants.
Storage, Transport and Use of Explosives
15.7.1.1
A QRA has been carried out to
assess the hazard to life issues arising from the storage, transport and use of
explosives during the construction of the Project.
15.7.1.2
The criterion of Annex 4 of the
EIAO-TM for Individual Risk would meet with regards to the hazard to life posed
by storage, transport and use of explosives. The assessment results show that the
societal risk for the storage and use of explosives lies within the acceptable
region, and the transport of explosives lies within the lower ALARP region when
compared to the criteria stipulated in the EIAO-TM. A detailed ALARP assessment has
been undertaken considering a range of mitigation measures and the results show
compliance with the ALARP principles provided that the recommendations in Section 7.14 are
followed.
HP Underground Town Gas Transmission Pipelines
15.7.1.3
The transport route of
explosives is close to an HP underground town gas transmission pipelines. A QRA
has therefore been conducted to assess the increased societal risk arising from
the incremental population during both construction and operational phases of
the Project.
15.7.1.4
The criterion of Annex 4 of the
EIAO-TM for Individual Risk would meet with regards to the hazards to life
posed by the HP underground town gas transmission pipelines during both
construction stage and operational stage.
The assessment results show that the societal risk lies within the lower
ALARP region of the HKRG. However,
with the comparison of the ¡¥without Project¡¦ scenarios, it is found that the
ALARP is due to the background population instead of the population induced by
the Project.
15.8.1.1
Ecological impact assessment
for the relocation of STSTW has been conducted following the guidelines of the
EIAO-TM Annex 8 and Annex 16.
15.8.1.2
Terrestrial habitats identified
within the assessment area include woodland, fung shui wood, plantation,
shrubland, cultivated land, developed area, and stream. Marine habitats within the assessment area
include subtidal hard substrata, soft bottom habitats, and intertidal
habitats. The ecological values of
the identified habitats are rated between low and moderate to high. No sites of conservation importance will
be directly affected.
15.8.1.3
Direct impacts arising from the
proposed land-based works include permanent loss and temporary loss of some
woodland, plantation, and shrubland, as well as minor habitat fragmentation of
woodland and plantation in Nui Po Shan.
Given the relatively low to moderate ecological values of the habitats
and the small area affected, impacts are anticipated to be generally minor in
nature. The permanent loss of
woodland (0.65 ha) will be mitigated by compensatory planting (approximately
0.92 ha) of native species, while all temporarily affected works area will be
reinstated. A Woodland Compensation
Plan should be prepared to form the basis (e.g. implementation details,
management requirement, and monitoring requirements) and submitted for approval
from EPD at least three months before commencement of compensatory woodland
planting. All temporarily affected
works area will be reinstated.
Avoidance measures would be implemented to preserve a natural stream in
vicinity of the proposed access road on Nui Po Shan (e.g. provision of an
elevated section at the stream crossing).
15.8.1.4
Some plant species of
conservation importance were recorded within the Project boundary. To minimise the loss, a Detailed
Vegetation Survey should be conducted prior to the commencement of construction
works to identify potentially affected plant species. All identified species would be labelled
and fenced off on site for better preservation, or in case of unavoidable loss,
for transplantation according to the Protection and Transplantation Proposal.
15.8.1.5
Construction site runoff and
other disturbance impacts resulting from the proposed aboveground works may
potentially result in indirect impact on the streams, wildlife, and some fauna
species of conservation importance (amphibian Lesser Spiny Frog and freshwater
crab Cryptopotamon anacoluthon) recorded at stream S2 at Nui Po Shan. Standard mitigation measures such as
good site practice, control of glare / lighting, minimisation of groundwater
infiltration, and water quality impact control measures are proposed.
15.8.1.6
There would be no disturbance
to marine or riverbed sediments under the Project and hence loss of marine
habitat is avoided. According to
the water quality impact assessment, no unacceptable ecological impact is
anticipated on marine ecological resources. Nevertheless, an event and action plan
and a water quality monitoring programme should be implemented during
construction and operation phases to verify whether or not impact predictions
are representative, and to ensure that it would not result in unacceptable
impacts. During operation phase,
monitoring of the treated effluent quality from the CSTW should be carried out
to ensure that the effluent quality would comply with the design standards.
15.8.1.7
Excavation in rock would have relatively minor potential impacts on
groundwater as compared to excavation in soft ground. The rock itself is a natural barrier
with very low permeability which can prevent potential groundwater drawdown in
any soil and aquifer layers above the rock stratum. Thus it would not adversely affect the
groundwater level within the soil layer as well as the water level of the
adjacent streams. Since the
majority of the CSTW is situated in very competent rock stratum in Nui Po Shan,
the impact on groundwater would be minor.
Nonetheless, precautionary measures would be taken in cavern design and
construction to minimize the potential impacts from the change in groundwater
level. Preventive measures such as
pre-grouting and post-grouting, which have been successfully applied in other tunnel
projects in Hong Kong, would be conducted to minimize any impact from the
cavern construction activities to the adjacent groundwater table. Surface water level or groundwater level
near the caverns will be closely monitored during the construction stage to
ensure that the surrounding groundwater level will not be adversely affected
due to the cavern construction activities and presence of the caverns. Post-construction monitoring of
groundwater for 1 year will also be carried out after completion of excavation
works.
15.8.1.8
With proper implementation of mitigation measures, no adverse residual
ecological impacts are expected from the Project. The implementation of mitigation measures would be subject
to regular audit as part of the EM&A programme.
15.9
Fisheries
Impact
15.9.1.1
A study based
on existing information on commercial fisheries resources and fishing
operations within the waters of the assessment area has been undertaken,
following the criteria and guidelines for evaluating and assessing fisheries
impact as stated in Annexes 9 and 17 of the EIAO-TM. Sites of
fisheries importance have been identified, where present.
15.9.1.2
No important spawning or
nursery grounds were identified in the immediate vicinity of the existing
STSTW, while the nearest important nursery area for commercial fisheries
resources is located in Three Fathoms Cove in Tolo Channel (approximately 6.5
km from the existing STSTW). The
nearest FCZs (Yim Tin Tsai FCZ and Yim Tin Tsai (East) FCZ) are located approximately
4.5 km away from the existing STSTW. The importance of capture
fisheries resources in the vicinity of the existing STSTW was identified
as low in terms of both production weight
and value. Fish fry production was low in the immediate
vicinity of the existing STSTW in Tolo Harbour.
15.9.1.3
The Project will only involve
land-based construction works.
There will be no disturbance to marine or riverbed sediments. Under the Project design, any Project
effluent bypass to the Tolo Harbour will be discharged separately through the
existing emergency outfalls of the TPSTW and
STSTW. Construction of connection
pipes to existing emergency outfall of STSTW was proposed to be by trenchless
method underneath Shing Mun River.
This construction method would not cause disturbance to the marine
sediment and hence no impact to or loss of fishing
ground is anticipated.
15.9.1.4
During the construction phase,
THEES connection works required for this Project will be arranged to be
synchronized within the THEES maintenance.
Such that no additional water quality impact, and hence, fisheries
impact from changes of water quality will be induced by the proposed THEES
connection works.
15.9.1.5
Despite not being specifically
induced by this Project, the scenario of THEES maintenance or bypass under
extreme emergency situations during the operation phase of the Project have
been considered. Indirect fisheries
impacts due to deterioration of water quality are expected during these
abnormal operation periods. Changes
in water quality (e.g. SS, DO, TIN, chlorophyll-a) at Yim Tin Tsai FCZ,
Yim Tin Tsai (East) FCZ, potential subzone of Yim Tin Tsai FCZ, Yung Shue Au
FCZ, Lo Fu Wat FCZ and the nursery area for commercial fisheries resources at
Three Fathoms Cove are expected during these scenarios. However, no significant changes in water
quality parameters are predicted as the pollution elevation associated with the
discharge would be reversible and hence no unacceptable water quality impacts
are expected. With the
implementation of mitigation measures for water quality, no unacceptable fisheries
impacts are expected.
15.10
Landscape
and Visual Impact
15.10.1.1 The Project will inevitably result in some landscape and visual
impacts during construction and operation phases. These impacts have been minimised
through careful consideration of alternatives, minimisation of works areas, and
incorporation of aesthetic external designs and landscape treatments of
proposed aboveground structures.
15.10.1.2 The Project is generally located within GB Zones of the Approved Sha
Tin OZP No. S/ST/32 (11.12.2015) and, for a small part, on the Approved Ma On
Shan OZP No. S/MOS/22 (15.1.2016).
It is recommended that both the Sha Tin OZP and Ma On Shan OZP shall be
amended to incorporate the latest changes arising from the Project. The demolition of decommissioning of
existing STSTW is located within the OU under the Approved Sha Tin OZP No.
S/ST/32 (11.12.2015). Since the
future developments at the site of the existing STSTW after its decommissioning
are under a separate project, any recommendation to the change in OZP shall be
made later.
15.10.1.3 Based on a broad brush estimate, approximately 828 existing trees in
the Amenity Planting Area in the Existing STSTW (LR-01), Roadside Planting
Areas along Ma On Shan Road (LR-07) and Woodland on Slopes of Nui Po Shan
(LR-08) will be affected by the proposed works. The affected trees shall be considered
for transplanting in accordance with DEVB TCW No. 7/2015 - Tree Preservation
and the latest Guidelines on Tree Preservation during Development issued by
DEVB. Many of the affected trees
are of semi-mature to mature size.
None of these are Registered Old and Valuable Trees. Under the proposed scheme for the
Project, opportunities for tree compensation within the Project boundary has
been fully explored and incorporated in the proposed mitigation measures as
much as practicable. Approximately
330 nos. of heavy standard trees and 10,000 nos. of tree whips can be
compensated for the loss of existing trees due to the Project. Tree Preservation and Removal Proposals
including compensation planting scheme shall be submitted in accordance with
DEVB TCW No. 7/2015 - Tree Preservation.
15.10.2.1 With the implementation of proposed mitigation measures it is
predicted that there would be substantial to slight residual impact on existing
landscape resources (LR-01, LR-07 and LR-08) during construction, and moderate
to insubstantial impact on day 1 of operation. The residual impact on these landscape
resources would be further reduced to slight to insubstantial when the proposed
compensatory planting, buffer planting and woodland mix planting become mature
in year 10 of operation.
15.10.2.2 It is predicted that there would be substantial to slight residual
impact on landscape character areas (LCA-01, LCA-04, LCA-05 and LCA-07) during
construction and moderate to insubstantial impact on day 1 of operation. The residual impact on these landscape
character areas would be further reduced to slight to insubstantial when the
proposed compensatory planting, buffer planting and woodland mix planting
become mature in year 10 of operation.
15.10.2.3 Regarding visual impact, it is predicted that there would be
moderate residual impact on residential VSRs in Chevalier Garden (R-01) Kam Tai
Court (R-12). The residual impact
on these VSRs would remain moderate on day 1 of operation and would be reduced
to slight when the proposed tree planting becomes mature in year 10 of
operation. There would be slight to
insubstantial residual impact on other VSRs within the visual envelope during
the construction and operation of the Project.
15.10.2.4 As a whole, the residual landscape and visual impacts of the
proposed Project is considered acceptable with the proposed mitigation measures
implemented during construction and operation phases.
15.11
Cultural
Heritage Impact
15.11.1.1 The CHIA has assessed current condition and potential impact on
cultural heritage resources within the study area. As no terrestrial and marine
archaeological potential is identified, it is considered that there is no
impact on archaeology and mitigation measures are not required.
15.11.1.2 Two
built heritage resources in Tai Shui Hang (both are Grade 3 historic buildings)
as well as the Pak Kong-Mui Tsz Lam Trackway (Site of Archaeological Interest)
are identified outside the 50m study area from the site boundary of the
Project. Thus, no potential direct
or indirect impact to these cultural heritage resources is anticipated, and
therefore no mitigation measures are required.
15.12.1.1 Different types of waste generated from the Project during the
construction phase are likely to include C&D materials from demolition,
excavation and site formation works, general refuse from workforce, and
chemical waste from the maintenance of construction vehicles and equipment. During the operation phase, the major
types of waste would be grit and screenings, and sewage sludge.
15.12.1.2 Approximately 6,000,000m3 of inert materials and 124,000
m3 of non-inert materials would be generated during the construction
phase of the Project. About
3,740,000 m3 of total excavated materials is rock generated from the
caverns excavations. An estimated
volume of 595,000 m3 is soft materials while 1,669,000 m3
would be AHM. Soft inert C&D
materials from the above construction works will be sorted and reused as
filling material as much as possible.
The surplus will be transported and disposed at Tuen Mun Area 38 Fill
Bank. Hard inert C&D material includes Grade III granitic rock and Grade I
& II granitic rock. The Grade
III granitic rock and AHM will be re-used as much as possible and the surplus
will be transported to Tuen Mun Area 38 Fill Bank for reuse by other
projects. The Grade I & II rock
will be transported to Lam Tei Quarry for recycling as useful aggregates. Non-inert waste will be recycled as far
as possible before disposed to landfill.
Opportunities in minimisation of generation and maximisation of reuse
would be continually investigated during the detailed design and construction
phases. With the implementation of
the recommended good site practices and mitigation measures for the handling,
transportation and disposal of the identified waste arising, adverse
environmental impacts is not anticipated.
15.12.1.3 The waste management assessment has recommended good waste
management practices to ensure that adverse environmental impacts are
prevented. The assessment
concluded that no unacceptable environmental impacts would result from the
storage, handling, collection, transport and disposal of wastes arising from
the construction and operation of the Project.
15.13.1.1 The risk arising from exposure to TAPs associated with the emissions
of the relocated STSTW is evaluated. The non-carcinogenic and carcinogenic
health impact of the TAPs imposed to the impacted HRs were assessed and
compared with international guideline levels. The assessment findings revealed
that the levels of TAPs at HRs would be extremely small when compared to the
derived reference levels. The highest incremental cancer risk arising from the
operation of CSTW is predicted to be 7.1E-08 which is far below the guidance
level of 1E-06 adopted by USEPA and it is considered that the Project would not
present an unacceptable risk and no further analysis is necessary. For the
criteria air pollutants, while it is not possible to rule out the additional
potential health effects from the operation of CSTW with complete certainty,
the impact on health from extremely small additional air pollutants is likely
to be very small and unlikely to be quantifiable.
15.13.1.2 A minor portion of treated effluent would be reused but would be
limited to non-potable uses inside the plant and therefore the general public
is not expected to be exposed to the treated effluent. Thus, there is no health
risk to the general public caused from the reuse of treated effluent.
15.14
Environmental
Outcomes
15.14.1.1 The EIA Study for the STSTW to Caverns has predicted that the
Project, with the implementation of the proposed environmental control and
mitigation measures, the environmentally sensitive receivers within the Study
Area would be protected from adverse environmental impacts arising from the
proposed Project. Table 15.1 summarises
the environmental outcomes/benefits that have accrued from the environmental
considerations and analysis during the EIA process and the implementation of
environmental control measures of the Project.
Table 15.1 Summary
of Key Environmental Outcomes / Benefits
Area/Issue
|
Environmental
Outcomes / Benefits and Mitigation Measures
|
Environmental Benefits of the Project
|
¡P
Release of 28ha of
land in Sha Tin with sea frontage for a re- development to meet the needs of
the society.
¡P
Subject to
subsequent planning, the released STSTW site will provide opportunities for
developing a green and vibrant waterfront living environment
¡P
The living environment of the surrounding area
would be improved upon relocation of the existing STSTW to caverns. The common potential impacts of a
sewage treatment works, i.e. odour and visual impacts, can be very
effectively controlled and minimised.
¡P
Advanced technologies can be adopted for the new
sewage treatment facilities to enhance operation process performance,
resilience and reliability, as well as operation efficiency
¡P
The development opportunities of the surrounding
area adjacent to the existing STSTW site would be enhanced after completion
¡P
Produce large amount of hard granitic rocks to
support the construction industry as a local source.
|
Environmentally
Friendly Design Considered and key environmental problems avoided and any
compensation area
|
¡P
The
layout of sewage and sludge treatment units are optimised to have the best
hydraulic performance with minimum construction and demolition materials,
footprint and energy requirements, as well as to facilitate plant operation
and maintenance.
¡P
Impacts to ecological
sensitive areas have been minimised through putting the sewage treatment
system into caverns as much as possible.
¡P
Engineering design for fixed
plant complies with day-time, evening time and night time noise criteria.
¡P
The adoption of new carven
sewage treatment system will reduce the public nuisance from odorous gas.
¡P
Adoption of aesthetically
pleasing and green design of aboveground structures to blend into the
adjacent landscape and visual context.
|
Population and
Environmentally Sensitive Areas Protected
|
With the adoption of environmentally friendly
design mentioned above, major environmentally sensitive receivers would be
protected.
|
Air Quality Impact
|
Environmental benefits of
environmental protection measures recommended:
Construction
Watering
8 times a day on active works areas, exposed areas and unpaved haul roads to reduce dust emission by 87.5% and dust
collector with 99% removal efficiency for rock crusher.
Dust suppression measures
stipulated in the Air Pollution Control (Construction Dust) Regulation.
Operation
Relocate the
STSTW into caverns will allow effective control of odour arising from the
sewage treatment process and will significantly reduce the potential odour
impacts. The exhausted odorous air will be conveyed to four deodourisers
(with 80 ¡V 97% odour removal efficiency) for treatment before discharge to
the environment. Predicted odour concentrations at the ASRs are well below
the criteria.
Compensation areas included:
N/A
Population and
environmentally sensitive receivers protected:
Existing
ASRs
within 500m
of the project boundary, including residential premises, schools, hospital
and institutional uses.
|
Noise Impact
|
Environmental benefits of
environmental protection measures recommended:
Construction
Residential NSRs and educational NSRs are
protected with implementation of quiet PME, movable barriers and acoustic
mats, and limitation of
on-time operating PMEs as well as good site practices during
construction of relocated STSTW and demolition of existing STSTW and
temporary explosives magazine, except occasional exceedance of noise
criterion for examination period by 1 dB(A) at S.K.H. Ma On Shan Holy Spirit
Primary School during examination period.
For the temporary modification
works at the merging point of Ma On Shan Road and temporary access haul road,
the provision of 220m length of noise barrier of a height at 10mPD on the
temporary access haul road to replace the existing 150m length of noise
barrier at 9.2mPD to 10mPD height on Ma On Sha Road would pose negligible
difference in the overall traffic noise level at the sensitive facades in the
vicinity. Once the construction
work is completed, the noise barrier on the concerned road section of Ma On
Shan Road would be re-installed according to the existing configuration.
Operation
The
fixed plant noise impact from operation of ventilation shaft, cooling tower and ventilation fan for chiller
plant room at administration building, and
ventilation buildings at main portal and secondary portal of the CSTW has been
assessed. The predicted fixed
plant noise levels at the representative NSRs would comply with the noise
criteria based on the noise emission inventory provided by the Engineer.
Compensation areas included:
N/A
Population and
environmentally sensitive receivers protected:
Existing and planned NSRs within 300m of the project boundary,
including residential premises, schools and institutional uses.
|
Water quality
|
Environmental benefits of
environmental protection measures recommended:
Construction Phase
The key issue from
the land-based construction activities would be the potential for surface
runoff, accidental spillage, sewage from on-site construction workers and
groundwater infiltration. Impacts can be controlled to comply with statutory
standards by implementing mitigation measures such as on-site drainage and
sediment traps to control run-off.
During the
connection works of the relocated STSTW to the existing THEES tunnel, the
THEES tunnel needs to be temporarily suspended from its normal operation with
treated effluent bypass into the Tolo Harbour to provide a dry construction
zone. To minimise water quality
impact to Tolo Harbour, the necessary THEES connection works required for
this Project will be split into a number of steps for sequential and
synchronized implementation with THEES maintenance. Each suspension will not
be longer than 4 weeks and will be outside the algae blooming season (January
to May), and the frequency will be no more than once per year. No cumulative or residual impact would
be expected.
Operation
Phase
The main operational
impact from the Project would come from the emergency discharge from the CSTW
in case of complete failure of plant or power supply. Mitigation measures, including dual
power supply or ring power main supply, standby pumps, treatment units and
equipment, would be provided to avoid the occurrence of any emergency
discharge. A contingency plan has
also been formulated to minimise the impact of emergency discharges and
facilitate subsequent management of the situation.
Compensation areas included:
N/A
Population and
environmentally sensitive receivers protected:
Water
sensitive receivers in Victoria Harbour and Tolo Harbour
|
Land Contamination
|
Environmental benefits of
environmental protection measures recommended:
Further site walkover, land contamination
assessment and, if required, remediation works would be carried out prior to
the re-development for the existing STSTW site and part of VDC within the
Project boundary. Land contamination impacts are considered surmountable to
future occupants if the recommended actions were followed and contaminated soil and groundwater (if any)
were properly treated using appropriate remediation methods and according to
EPD¡¦s approved RAP.
Compensation areas included:
N/A
Population and
environmentally sensitive receivers protected:
Future occupants
within the concerned sites.
|
Hazard to life
|
Environmental benefits of
environmental protection measures recommended:
With the implementation of the proposed
mitigation measures as proposed, no insurmountable environmental impact would
be expected during construction phase.
Compensation areas included:
N/A
Population and
environmentally sensitive receivers protected:
Existing and planned sensitive receivers in the
vicinity of the Project sites, the temporary magazine and the transport route
of explosives.
|
Ecology
|
Environmental benefits of
environmental protection measures recommended:
The current proposed locations of both main
portal and secondary portal areas are situated adjacent to woodland habitats,
while the proposed alignment of the access road runs along woodland,
plantation and shrubland habitats.
The layout of the portal areas and the access road alignment have been
designed to minimise encroachment into adjacent woodland habitats, avoid
potential extensive excavation works of hilly terrain, and minimising the
slope cutting and vegetation removal potentially needed.
Construction of the connection pipes to emergency
outfall by trenchless method underneath Shing Mun River was proposed. With the adoption of trenchless
method, no permanent / temporary loss of marine habitat is anticipated.
Compensation areas included:
In view of the inevitable permanent loss of
woodland habitat, mitigation measure by compensatory planting (approximately
0.92 ha) of native species would be provided at the main and secondary portal
areas, and along the access road.
Population and
environmentally sensitive receivers protected:
Direct loss of
woodland, plantation and shrubland habitats have been minimised with the
layout design. Loss of marine
habitat has been avoided as trenchless method would be adopted.
|
Fisheries impact
|
Environmental benefits of
environmental protection measures recommended:
Under the Project
design, any Project effluent bypass to the Tolo Harbour will be discharged
through the existing emergency submarine outfall of the STSTW, which is
located in Sha Tin Hoi. Construction of connecting pipes between the
relocated STSTW and the existing outfall by trenchless method across Shing
Mun River was proposed. No
loss of fishing ground is anticipated.
Compensation areas included:
N/A
Population and
environmentally sensitive receivers protected:
Loss
of fishing ground has been avoided as trenchless method would be
adopted.
|
Landscape and visual
|
Environmental benefits of
environmental protection measures recommended:
Implementation of the proposed mitigation
measures would minimise and reduce the potential adverse landscape and visual
impacts during the construction and operation phase of the Project to an
acceptable level.
Compensation areas included:
Based on a broad brush estimate, approximately
828 existing trees will be removed.
The affected trees shall be considered for transplanting in accordance
with DEVB TCW No. 7/2015 - Tree Preservation and the latest Guidelines on
Tree Preservation during Development issued by DEVB. Under the proposed scheme for the
Project, opportunities for tree compensation within the Project boundary has
been fully explored and incorporated in the proposed mitigation measures as
much as practicable. Tree
Preservation and Removal Proposals including compensation planting scheme
shall be submitted in accordance with DEVB TCW No. 7/2015 - Tree
Preservation.
Population and
environmentally sensitive receivers protected:
With the implementation of proposed mitigation
measures, the landscape resources, character areas and visually sensitive
receivers identified within the assessment boundary will be protected.
|
Cultural Heritage
|
Environmental benefits of
environmental protection measures recommended:
No
potential direct or indirect impact
to cultural heritage resources is anticipated, and therefore no mitigation
measures are required.
Compensation areas included:
N/A
Population and
environmentally sensitive receivers protected:
Cheung
Village House, No. 6 and Nos. 16-18 Tai Shui Hang; Pak Kong-Mui Tsz Lam
Trackway
|
Waste Management Implication
|
Environmental benefits of
environmental protection measures recommended:
Implementation of the proposed waste control and
mitigation measures would avoid the potential water quality, dust, odour, and
noise impacts associated with handling, transportation and disposal of the
identified wastes arising from the construction phase of the Project.
It is estimated that approximately 6,000,000 m3
of inert C&D materials would be generated from the Project, which
are proposed to be transported to Tuen Mun Area 38 Fill Bank for reuse by
other projects. About 124,000 m3 of non-inert C&D materials
would be generated and recycled or disposed of at landfill.
With the implementation of the recommended
mitigation measures, no adverse environment impacts would be expected.
Compensation areas included:
N/A
Population and
environmentally sensitive receivers protected:
Water quality, air, and noise sensitive receivers
in the vicinities of Project sites, the waste transportation routes and the
waste disposal site(s).
|
Health Impact
|
Environmental benefits of
environmental protection measures recommended:
The
non-carcinogenic and carcinogenic health impact of the TAPs imposed to the
human receptors would be negligibly small when compared to the international
guideline levels.
The
treated effluent from the Project would be limited to non-potable use inside
the plant for polymer preparation. No direct human contact is involved and
the health impact to humans is not expected.
Compensation areas included:
N/A.
Population and environmentally
sensitive receivers protected:
Existing
ASRs
within 500m
of the project boundary, including residential premises, schools, hospital
and institutional uses.
|
15.15
Overall
Conclusion
15.15.1.1 The findings of this EIA
have provided information on the nature and extent of environmental impacts
arising from the construction and operation of the Project. The EIA has, where appropriate,
identified mitigation measures to ensure compliance with environmental
legislation and standards.
15.15.1.2 Overall, the EIA Report has
predicted that the Project would be environmentally acceptable with the
implementation of the proposed mitigation measures for construction and
operation phases. An EM&A
programme has been recommended to ensure the effectiveness of recommended
mitigation measures.
<End of Section 15>