Page
16 Implementation
Schedule of Recommended Mitigation Measures
16.1 Implementation
Schedule of Recommended Mitigation Measures
Table 16.1 Implementation
Schedule of Recommended Mitigation Measures
EIA Ref. |
EM&A Log Ref. |
Environmental
Protection Measures |
Location
/ Duration of Measures / Timing of Completion of Measures |
Implementation
Agent |
Implementation Stage [1] |
Relevant Legislation & Guidelines |
||||
Des |
C |
O |
Dec |
|||||||
|
Air
Quality Impact |
|||||||||
|
Construction Phase |
|||||||||
Table 3.5 |
2.4.1 |
The rock crushing
plant is configured as an enclosed system. Dust collector with dust removal
efficiency of 99% will be provided at
the exhaust of the rock crusher during rock crushing. Watering will be provided
to maintain material in wet condition. Vehicles would be
required to pass through the wheel washing facilities provided at site exit. |
Rock Crushing Plant / Construction Phase |
Contractor |
¡Ô |
¡Ô |
|
¡Ô |
Air Pollution Control Ordinance (APCO) |
|
3.8.1 |
2.4.1 |
Watering eight
times a day on active works areas, exposed areas and unpaved haul roads to reduce dust emission
by 87.5%. |
All active works areas, exposed areas and unpaved haul roads |
Contractor |
|
¡Ô |
|
¡Ô |
APCO |
|
3.8.1 |
2.4.1 |
Dust suppression measures
stipulated in the Air Pollution Control (Construction Dust) Regulation and
good site practices: ¡P
Use of regular
watering to reduce dust emissions from exposed site surfaces and unpaved
roads, particularly during dry weather. ¡P
Use of frequent
watering for particularly dusty construction areas and areas close to ASRs. ¡P
Side enclosure
and covering of any aggregate or dusty material storage piles to reduce
emissions. Where this is not
practicable owing to frequent usage, watering shall be applied to aggregate
fines. ¡P
Open stockpiles
shall be avoided or covered.
Where possible, prevent placing dusty material storage piles near
ASRs. ¡P
Tarpaulin
covering of all dusty vehicle loads transported to, from and between site
locations. ¡P
Establishment and
use of vehicle wheel and body washing facilities at the exit points of the
site. ¡P
Provision of
wind shield and dust extraction units or similar dust mitigation measures at
the loading area of barging point, and use of water sprinklers at the loading
area where dust generation is likely during the loading process of loose
material, particularly in dry seasons/ periods. ¡P
Provision of not
less than 2.4m high hoarding from ground level along site boundary where
adjoins a road, streets or other accessible to the public except for a site
entrance or exit. ¡P
Imposition of
speed controls for vehicles on site haul roads. ¡P
Where possible,
routing of vehicles and positioning of construction plant should be at the
maximum possible distance from ASRs. ¡P
Every stock of
more than 20 bags of cement or dry PFA should be covered entirely by
impervious sheeting or placed in an area sheltered on the top and the 3
sides. ¡P
Instigation of
an environmental monitoring and auditing program to monitor the construction
process in order to enforce controls and modify method of work if dusty
conditions arise. |
Construction Sites |
Contractor |
|
¡Ô |
|
¡Ô |
APCO and Air Pollution Control (Construction Dust) Regulation |
|
|
Operation Phase |
|||||||||
3.5.2 |
- |
Sludge tanks with
totally enclosed design proven by DSD should be deployed for transporting
sludge. With thorough
cleaning practice and regular condition test of the sludge tanks, odour
emission and leachate leakage during storage and transportation are not
anticipated. |
Cavern Sewage Treatment Works (CSTW) / Operation Phase |
Project Proponent / Operator |
¡Ô |
|
¡Ô |
|
- |
|
3.6.2, 3.7.2 |
2.4.2 |
All treatment
units with potential odour emission will be covered and the exhausted air will
be conveyed to the deodouriser (with 80 ¡V 97% odour removal efficiency) for
treatment before discharge to the environment. |
CSTW
/ Operation Phase |
Design team / Project Proponent / Operator |
¡Ô |
|
¡Ô |
|
- |
|
3.7.2 |
2.4.2 |
The following appropriate
odour control measures would be implemented. (i) Adopting the advantage of caverns as natural barriers
for odour control; (ii) Covering up of odour sources; (iii) Preventing odour leakage through the access tunnels
by applying negative pressure inside caverns; (iv) Installing deodourizing units to clean up the
collected foul air; (v) Discharging exhausted air at height to further
enhance the dilution effect; and (vi) Enhancing the odour management of the sludge
transportation. |
CSTW
/ Operation Phase |
Design team / Project Proponent / Operator |
¡Ô |
|
¡Ô |
|
- |
|
3.10.2 |
2.3.1 |
Odour monitoring
at the inlet and outlet of the deodourizing units is proposed to be conducted
for first three years of the operation of CSTW, quarterly in the first year, and
once every 6 months in the second and third years if monitoring results
remain below the limit levels. |
CSTW
/ Operation Phase |
Project Proponent / Operator |
¡Ô |
|
¡Ô |
|
- |
|
3.10.2 |
2.3.2 |
An Odour
Complaint Registration System is also proposed in the EM&A programme to
check whether the deodorizing units can fulfill the recommended odour removal
performance. |
CSTW
/ Operation Phase |
Operator |
|
|
¡Ô |
|
- |
|
3.10.2 |
- |
Any unexpected leakage from tanks could be observed
with monitoring equipment. Monitoring equipment would be installed in the
CSTW to monitor the concentration of H2S, CO and CO2 and
methane. Investigation and repair works would be carried out immediately if
abrupt increase of these concentrations are reported. Emergency Plan would be
established for these upset conditions. |
CSTW
/ Operation Phase |
Project Proponent / Operator |
¡Ô |
|
¡Ô |
|
- |
|
|
Noise
Impact |
|||||||||
|
Construction Phase |
|||||||||
4.5.1.6 |
- |
Re-provision of 220m length noise
barrier with 10mPD on temporary access haul road to replace the existing 150m
length noise barrier with 9.2mPD to 10mPD on Ma On Sha Road. The location of the relocated noise barrier is shown in Figure No. 60334056/EIA/4.02 and Appendix 4.07. Once
the construction work for the CSTW is completed, the temporary access roads
would be demolished and the relevant section of Ma On Shan Road and
associated noise barrier would be recovered as before. |
Proposed temporary access / Construction Phase |
Contractor |
|
¡Ô |
|
|
Technical Memorandum on Environmental Impact Assessment Process
(EIAO-TM), Noise Control Ordinance (NCO) |
|
4.8.1 |
3.8.1 |
The use of quiet
plant associated with the construction works is prescribed in British Standard
¡§Code of practice for noise and vibration control on construction and open
sites, BS5228¡¨ which contains the SWLs for specific quiet PME. |
All Construction Work Sites |
Contractor |
|
¡Ô |
|
¡Ô |
EIAO-TM, NCO |
|
4.8.1 |
3.8.1 |
To alleviate the construction
noise impact on the affected NSRs, movable noise barrier for Air Compressor,
Bar Bender and Cutter, Breaker, Chisel, Saw, Compactor, Mixers, Pump, Crane,
Desander, Drilling Rig, Dump Truck, Excavator, Generator, Grab, Lorry, Paver,
Poker and Roller are
proposed. |
All Construction Work Sites |
Contractor |
|
¡Ô |
|
¡Ô |
EIAO-TM, NCO |
|
4.8.1 |
3.8.1 |
Provision of
noise barrier/acoustic mats for Drilling Jumbo so as to have screening
effecting with 10 dB(A) noise attenuation |
Drilling Jumbo operate outside the portal and within 20m inside the
portal |
Contractor |
|
¡Ô |
|
|
EIAO-TM, NCO |
|
4.8.1 |
3.8.1 |
To further alleviate the
construction noise impact on the Neighbourhood Advice-Action Council Harmony
Manor, it is proposed to limit the number of on-time operating PMEs within
120m of this NSR during construction of access road. |
Construction Site for access road for
magazine at A Kung Kok Road |
Contractor |
|
¡Ô |
|
¡Ô |
EIAO-TM, NCO |
|
4.9.1 |
3.8.1 |
In addition to the
above-mentioned mitigation measures, good site practices listed below shall
be adopted by all the contractors to further ameliorate the noise
impacts. ¡P
Only
well-maintained plant should be operated on-site and plant should be serviced
regularly during the construction program. ¡P
Silencers or
mufflers on construction equipment should be utilised and should be properly
maintained during the construction program. ¡P
Mobile plant, if
any, should be sited as far away from NSRs as possible. ¡P
Machines and
plant (such as trucks) that may be in intermittent use should be shut down
between works periods or should be throttled down to a minimum. ¡P
Plant known to
emit noise strongly in one direction should, wherever possible, be orientated
so that the noise is directed away from the nearby NSRs. ¡P
Material
stockpiles and other structures should be effectively utilised, wherever
practicable, in screening noise from on-site construction activities. |
All Construction Work Sites |
Contractor |
|
¡Ô |
|
¡Ô |
EIAO-TM, NCO |
|
|
Operation Phase |
|||||||||
4.7.4 |
3.8.2 |
The maximum
allowable sound power levels for the ventilation shaft, ventilation buildings at main portal and emergency
portal,
ventilation fan for chiller plant room and cooling tower at the
administration building as presented in Table 4.16 of the EIA
Report should be achieved such that the
nearest affected NSRs can be in compliance with the noise criteria |
Ventilation
Shaft,
Administration Building and Ventilation Buildings/
Operation Phase |
Project
Proponent |
¡Ô |
|
¡Ô |
|
EIAO-TM, NCO |
|
4.11.2 |
3.8.2 |
Prior to the
operational phase of the Project, a commissioning test for the ventilation
buildings, the ventilation shaft, ventilation fan for chiller plant room at
administration building and cooling tower at the administration building
would be conducted to ensure compliance with the relevant allowable maximum
sound power levels. |
Ventilation
Shaft,
Administration Building and Ventilation
Buildings/ Operation Phase |
Contractor |
|
|
¡Ô |
|
EIAO-TM, NCO |
|
|
Water
Quality Impact |
|||||||||
|
Construction Phase |
|||||||||
5.7.2 |
4.10 |
Water used in
ground boring and drilling for SI or rock / soil anchoring should as far as practicable
be re-circulated after sedimentation. When there is a need for final
disposal, the wastewater should be discharged into storm drains via silt
removal facilities. |
Construction Sites / Construction Phase |
Contractor |
|
¡Ô |
|
|
Water Pollution Control Ordinance (WPCO), EIAO-TM |
|
5.7.2 |
4.10 |
All vehicles and
plant should be cleaned before they leave a construction site to minimise the
deposition of earth, mud, debris on roads. A wheel washing bay should be
provided at every site exit if practicable and wash-water should have sand
and silt settled out or removed before discharging into storm drains. The section of construction
road between the wheel washing bay and the public road should be paved with
backfill to reduce vehicle tracking of soil and to prevent site run-off from
entering public road drains. |
Construction Sites / Construction Phase |
Contractor |
|
¡Ô |
|
|
Professional Persons Environmental Consultative Committee (ProPECC)
Practice Note (PN) 1/94, WPCO, Waste Disposal Ordinance (WDO) |
|
5.7.2 |
4.10 |
Good site practices should be adopted to
remove rubbish and litter from construction sites so as to prevent the rubbish and litter
from spreading from the site area. It is recommended to clean the
construction sites on a regular basis. |
Construction Sites / Construction Phase |
Contractor |
|
¡Ô |
|
|
WPCO, EIAO-TM |
|
5.7.2 |
4.10 |
The site practices outlined in ProPECC PN 1/94 ¡§Construction Site
Drainage¡¨ should be followed where applicable to minimise surface run-off and
the chance of erosion. |
Construction Sites / Construction Phase |
Contractor |
|
¡Ô |
|
|
WPCO, EIAO-TM, ProPECC PN 1/94 |
|
5.7.2 |
4.10 |
There is a need to apply to EPD for a
discharge licence for discharge of
effluent from the construction site under the WPCO. The discharge quality must meet the
requirements specified in the discharge licence. All the runoff and wastewater
generated from the works areas should be treated so that it satisfies all the
standards listed in the TM-DSS.
The beneficial uses of the treated effluent for other on-site
activities such as dust suppression, wheel washing and general cleaning etc.,
can minimise water consumption and reduce the effluent discharge volume. If monitoring of the treated effluent
quality from the works areas is required during the construction phase of the
Project, the monitoring should be carried out in accordance with the relevant
WPCO licence which is under the ambit of RO of EPD. |
Construction Sites / Construction Phase |
Contractor |
|
¡Ô |
|
|
WPCO, EIAO-TM, (TM-DSS) |
|
5.7.2 |
4.10 |
Contractor must
register as a chemical waste producer if chemical wastes would be produced
from the construction activities. The Waste
Disposal Ordinance (Cap 354) and its subsidiary regulations in particular the
Waste Disposal (Chemical Waste) (General) Regulation, should be observed and
complied with for control of chemical wastes. |
Construction Sites / Construction Phase |
Contractor |
|
¡Ô |
|
|
WPCO, EIAO-TM, WDO |
|
5.7.2 |
4.10 |
Any service shop and
maintenance facilities should be located on hard standings within a bonded
area, and sumps and oil interceptors should be provided. Maintenance of vehicles and equipment
involving activities with potential for leakage and spillage should only be
undertaken within the areas appropriately equipped to control these
discharges. |
Construction Sites / Construction Phase |
Contractor |
|
¡Ô |
|
|
WPCO, EIAO-TM |
|
5.7.2 |
4.10 |
Disposal of chemical wastes should be carried out in compliance with
the WDO. The Code of Practice on
the Packaging, Labelling and Storage of Chemical Wastes published under the
Waste Disposal Ordinance should be followed to avoid leakage or spillage of
chemicals. |
Construction Sites / Construction Phase |
Contractor |
|
¡Ô |
|
|
WPCO, EIAO-TM, WDO |
|
5.7.2 |
4.10 |
Sufficient
chemical toilets should be provided in the works areas. A licensed waste collector should be
deployed to clean the chemical toilets on a regular basis. |
Construction Sites / Construction Phase |
Contractor |
|
¡Ô |
|
|
WPCO, EIAO-TM |
|
5.7.2 |
4.10 |
Notices should be posted at conspicuous locations to
remind the workers not to discharge any sewage or wastewater into the
surrounding environment. |
Construction Sites / Construction Phase |
Contractor |
|
¡Ô |
|
|
WPCO, EIAO-TM |
|
5.7.2 |
4.10 |
The practices
outlined in ETWB TC (Works) No. 5/2005 ¡§Protection of natural streams/rivers
from adverse impacts arising from construction works¡¨ should also be adopted
where applicable to minimise the water quality impacts upon any natural
streams or surface water systems. |
Construction Sites / Construction Phase |
Contractor |
|
¡Ô |
|
|
WPCO, EIAO-TM, ETWB TC (Works) No. 5/2005 |
|
5.7.2 |
4.10 |
Appropriate
measures during the construction of the cavern construction should be
implemented to minimise the groundwater infiltration. |
Construction Sites / Construction Phase |
Contractor |
|
¡Ô |
|
|
WPCO, EIAO-TM |
|
5.7.2 |
4.10 |
No directly discharge of groundwater from contaminated
areas should be adopted. Prior to
any excavation works within the potentially contaminated areas at the
existing STSTW site, the baseline groundwater quality in these areas should
be reviewed based on the relevant SI data and any additional groundwater
quality measurements to be performed with reference to Guidance Note for
Contaminated Land Assessment and Remediation and the review results
should be submitted to EPD for examination. If the review results indicated
that the groundwater to be generated from the excavation works would be
contaminated, this contaminated groundwater should be either properly treated
or properly recharged into the ground in compliance with the requirements of
the TM-DSS. If wastewater
treatment is to be deployed for treating the contaminated groundwater, the
wastewater treatment unit shall deploy suitable treatment processes (e.g. oil
interceptor / activated carbon) to reduce the pollution level to an
acceptable standard and remove any prohibited substances (such as TPH) to an
undetectable range. All treated effluent from the wastewater treatment plant
shall meet the requirements as stated in TM-DSS and should be either
discharged into the foul sewers or tankered away for proper disposal.
|
Construction Sites / Construction Phase |
Contractor |
|
¡Ô |
|
|
WPCO, EIAO-TM, Guidance Note for Contaminated Land Assessment and
Remediation |
|
5.7.2 |
4.10 |
If deployment of
wastewater treatment is not feasible for handling the contaminated
groundwater, groundwater recharging wells should be installed as appropriate
for recharging the contaminated groundwater back into the ground. The recharging
wells should be selected at places where the groundwater quality will not be
affected by the recharge operation as indicated in section 2.3 of the
TM-DSS. The baseline groundwater
quality should be determined prior to the selection of the recharge wells,
and submit a working plan to EPD for agreement. Pollution levels of groundwater to be
recharged shall not be higher than pollutant levels of ambient groundwater at
the recharge well. Groundwater monitoring wells should be installed near the
recharge points to monitor the effectiveness of the recharge wells and to
ensure that no likelihood of increase of groundwater level and transfer of
pollutants beyond the site boundary. Prior
to recharge, free products should be removed as necessary by installing the
petrol interceptor. The
Contractor should apply for a discharge licence under the WPCO through the
Regional Office of EPD for groundwater recharge operation or discharge of
treated groundwater |
Construction Sites / Construction Phase |
Contractor |
|
¡Ô |
|
|
WPCO, EIAO-TM, TM-DSS |
|
5.7.2 |
4.10 |
THEES connection works should be synchronized with
the THEES maintenance, for a duration not longer than 4 weeks each outside
the algae blooming season (January to May) and frequency of THEES maintenance
shall be no more than once per year during the construction phase of the
Project. |
Tolo Harbour / Construction Phase |
Project Proponent / Contractor |
¡Ô |
¡Ô |
|
|
EIAO-TM |
|
|
Construction and
Operation Phases |
|||||||||
5.10.2 |
4.10 |
Shutdown of the THEES for maintenance should
be shortened as far as possible. It is recommended that the maintenance of
the THEES tunnel should be avoided during the algae blooming season
(January to May). |
Tolo Harbour / Construction and Operation Phase |
Project Proponent |
|
¡Ô |
¡Ô |
|
WPCO, EIAO-TM |
|
5.10.2 |
4.10 |
Relevant
government departments including EPD, WSD, AFCD as well as the key
stakeholders for mariculture and fisheries in Tolo Harbour should be informed
of the maintenance event prior to any discharge.
|
Tolo Harbour / Construction and Operation Phase |
Project Proponent |
|
¡Ô |
¡Ô |
|
WPCO, EIAO-TM |
|
5.10.3 |
4.2-4.5 |
An event and action plan and a water quality
monitoring programme (as presented in the EM&A Manual) should be implemented
for the THEES maintenance discharge |
Tolo Harbour / Construction and Operation Phase |
Project Proponent |
|
¡Ô |
¡Ô |
|
WPCO, EIAO-TM |
|
5.10.1 |
4.10 |
Silt screen may be installed at the flushing
water intakes during the THEES maintenance discharge should it appear
necessary. Close communication between DSD and WSD should be maintained to
minimize any impact on the flushing water intakes due to THEES maintenance
discharge. |
WSD flushing
water intakes / Construction and Operation Phase |
WSD / Project Proponent |
|
¡Ô |
¡Ô |
|
WPCO, EIAO-TM |
|
|
Design and Operation Phases |
|||||||||
5.8.3 |
4.6 |
In case adverse impact on KTN is identified
based on the result of the three-month monitoring programme after
commissioning of the project, the operation conditions of the treatment and
THEES system should be investigated, and corrective and remedial action
should be implemented to improve the effluent discharge from the CSTW.
Furthermore, DSD should extend the water quality monitoring programme for at
least three months or as agreed by the Director of Environmental Protection. |
Project site / Design and Operation Phases |
Project Proponent |
|
|
¡Ô |
|
WPCO, EIAO-TM |
|
5.11.2 |
4.10 |
Dual power supply or ring main supply from
CLP Power Hong Kong Ltd. CLP should be provided for the CSTW to prevent the occurrence of power failure. In addition, standby facilities for
the main treatment units and standby equipment parts / accessories should
also be provided in order to minimise the chance of emergency discharge. CLP should be consulted in order to
ascertain the power supply for normal plant operation within the caverns. It is recommended that government departments
including EPD, WSD and AFCD as well as the key stakeholders for mariculture
and fisheries in Tolo Harbour should be informed as soon as possible in case
of any emergency discharge so that appropriate actions can be taken. |
Project site / Design and Operation Phases |
Project Proponent |
¡Ô |
|
¡Ô |
|
WPCO, EIAO-TM |
|
5.11.2 |
4.10 |
In case of emergency discharge, the plant
operators of CSTW should carry out necessary follow-up actions according to the procedures of the current contingency plan
formulated for the existing STSTW to minimise the water quality
impact. |
Project site / Operation Phase |
Project Proponent |
|
|
¡Ô |
|
WPCO, EIAO-TM |
|
5.11.2 |
4.10 |
WSD may also consider, should it appear
necessary, to shut down the Sha Tin seawater pumping station for a short
period of time in case of emergency discharge in order to minimize any
adverse impacts. |
Sha Tin seawater
pumping station / Operation Phase |
WSD / Project Proponent |
|
|
¡Ô |
|
WPCO, EIAO-TM |
|
5.13.2 |
4.10 |
BMPs to reduce
storm water and non-point source pollution are also proposed as follows: Design
Measures ¡P
Exposed
surface shall be avoided within the road and portal sites to minimise soil
erosion. The access road and the
portal areas shall be either hard paved or covered by landscaping area where
appropriate. ¡P
Streams near the Project site will be retained
to maintain the original flow path. The drainage system will be designed to avoid flooding. ¡P
Green areas / planting etc. should be introduced
alongside the access road and within the portal areas, as far as possible, to
minimise runoff pollution. Devices/
Facilities to Control Pollution ¡P
Screening facilities such as standard gully grating and trash
grille, with spacing which is capable of screening off large substances such
as fallen leaves and rubbish should be provided at the inlet of drainage
system. ¡P
Road gullies with standard design and silt traps should be
provided to remove particles present in stormwater runoff, where
appropriate. Administrative Measures ¡P
Good management measures such as regular cleaning and sweeping
of road surface/ open areas are suggested. The road surface/ open area
cleaning should also be carried out prior to occurrence rainstorm. ¡P
Manholes, as well as stormwater gullies, ditches provided at the
Project site should be regularly inspected and cleaned (e.g. monthly). Additional inspection and cleansing
should be carried out before forecast heavy rainfall. |
Project site / Design and Operation Phase |
Project Proponent |
¡Ô |
|
¡Ô |
|
WPCO, ProPECC PN 5/93 |
|
|
Land
Contamination |
|||||||||
6.7.1 |
- |
Further site
walkover and/or detailed land contamination assessment will be required for sites
that are inaccessible or currently in operation / yet to be constructed (i.e.
existing STSTW, David Camp and part of existing Sha Tin VDC, and proposed A
Kung Kok Shan Road surface magazine site within the Project boundary). The
site walkover, detailed land contamination assessment and if necessary,
remediation works should be carried out after decommissioning of the sites
but prior to re-development and should include the following: ¡P
Prior to the
commencement of the SI works, review the CAP to confirm whether the proposed
SI works (e.g. sampling locations, testing parameters etc.) are still valid
and to confirm the appropriate RBRGs land use scenario for the development; ¡P
Submit
supplementary CAP(s), presenting the findings of the above review for EPD endorsement.
If land contamination issues were identified within David Camp or part of
existing VDC / proposed A Kung Kok Shan Road surface magazine site within the
Project boundary in the further site walkover, findings of the site walkover
and the proposal for SI works should also be presented in the supplementary
CAP(s); ¡P
Carry out SI
works according to the supplementary CAP endorsed by EPD; ¡P
Submit CAR(s),
detailing findings of the SI works and nature/extent of any soil/groundwater
contamination, and, if contaminated identified, RAP(s), discussing the
appropriate remedial methods and mitigation measures, for the identified
contamination, for EPD agreement; and ¡P
Carry out
soil/groundwater remediation works according to EPD agreed RAP and submit
RR(s) afterwards for EPD agreement. The remediation works and agreement of RR
should be completed prior to re-development. |
Existing STSTW, David Camp and VDC /
Construction Phase |
Project Proponent / Contractor |
|
¡Ô |
|
¡Ô (for existing STSTW) |
Guidance Note for Contaminated Land Assessment and Remediation,
Practice Guide for Investigation and Remediation of Contaminated Land,
Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land
Management |
|
6.7.2 |
- |
If contamination
were identified, mitigation measures as recommended in the RAP should be
followed and should include the following: ¡P
Excavation
profiles must be properly designed and executed with attention to the
relevant requirements for environment, health and safety; ¡P
Excavation shall
be carried out during dry season as far as possible to minimise contaminated
runoff from contaminated soils; ¡P
Supply of
suitable clean backfill material (or treated soil) after excavation; ¡P
Stockpiling
site(s) shall be lined with impermeable sheeting and bunded. Stockpiles shall
be fully covered by impermeable sheeting to reduce dust emission. If this is
not practicable due to frequent usage, regular watering shall be applied.
However, watering shall be avoided on stockpiles of contaminated soil to
minimise contaminated runoff. ¡P
Vehicles
containing any excavated materials shall be suitably covered to limit
potential dust emissions or contaminated wastewater run-off, and truck bodies
and tailgates shall be sealed to prevent any discharge during transport or
during wet conditions; ¡P
Speed control
for the trucks carrying contaminated materials shall be enforced; ¡P
Vehicle wheel
and body washing facilities at the site¡¦s exist points shall be established
and used; and ¡P
Pollution
control measures for air emissions (e.g. from biopile blower and handling of
cement), noise emissions (e.g. from blower or earthmoving equipment), and
water discharges (e.g. runoff control from treatment facility) shall be
implemented and complied with relevant regulations and guidelines. |
Project Site / Construction Phase |
Contractor |
|
¡Ô |
|
¡Ô (for existing STSTW) |
Guidance Note for Contaminated Land Assessment and Remediation,
Practice Guide for Investigation and Remediation of Contaminated Land,
Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land
Management |
|
|
Hazard to
Life |
|||||||||
|
Construction Phase |
|||||||||
7.14.1 |
6.2.2 |
The following
recommendations are justified to be implemented to meet the EIAO-TM
requirements: ¡P
The truck should
be designed to minimise the amount of combustible in the cabin. The fuel
carried in the fuel tank should also be minimised to reduce the duration of
any fire; ¡P
The accident
involvement frequency of the explosives delivery truck should be minimised
through implementation of several administrative measures, such as providing
training programme to the driver, regular ¡§tool box¡¨ briefing session,
implementing a defensive driving attitude, selecting driver with good safety
record, and providing regular medical checks for the driver; ¡P
Avoidance of
returning unused explosives to the magazine, only the required quantity of
explosives for a particular blast should be transported; ¡P
Maintain a
minimum headway of 10 minutes between two consecutive truck convoys whenever
practicable; and ¡P
The fire
involvement frequency should be minimised by carrying better types of fire
extinguishers and with bigger capacity onboard of the explosives delivery
truck. Emergency plans and trainings could also be provided to make sure that
the fire extinguishers are used adequately. |
Explosives dlivery route / Construction Phase |
Contractor |
¡Ô |
¡Ô |
|
|
EIAO-TM |
|
7.14.2 |
6.2.3 |
The magazine
should be designed, built, operated and maintained in accordance with Mines Division¡¦s
guidelines and appropriate industry best practice. In addition, the following
recommendations should be implemented: ¡P
The security
plan should address different alert security level to reduce opportunity for
arson or deliberate initiation of explosives; ¡P
Emergency plan
should be developed to address uncontrolled fire in magazine area, and drill
of the emergency plan should be regularly carried out; ¡P
Suitable work
control system should be set-up, such as
an operational manual including Permit-to-Work system, to ensure that work activities undertaken during
operation of the magazine are properly controlled; ¡P
Good
house-keeping within the magazine to ensure no combustible materials are
accumulated; ¡P
Good house-keeping
outside the magazine stores to ensure no combustible materials are
accumulated; and ¡P
Regular checking
of the magazine store to ensure no water seepage through the roof, walls or
floor. |
Magazine Site/ Construction Phase |
Contractor |
¡Ô |
¡Ô |
|
|
- |
|
7.14.3 |
6.2.4 |
The following
recommendations should be implemented: ¡P
Emergency plan
should be developed to address uncontrolled fire during transport. Case of
fire near an explosive delivery truck in jammed traffic should be included in
the plan. Activation of fuel and battery isolation switches on vehicle when
fire breaks out should also be included in the emergency plan to reduce
likelihood of prolonged fire leading to explosion; ¡P
Working
guideline should be developed to define procedure for explosives transport
during adverse weather such as thunderstorm; ¡P
Detonators
should be transported separately from other Class 1 explosives. Separation of
vehicles should also be maintained through the trip; ¡P
Develop
procedure to ensure the availability of parking space on site for the
explosives delivery truck. Delivery should not be commenced if parking space
on site is not secured; ¡P
Hot work or
other activities should be banned in the vicinity of the explosives
offloading or charging activities; ¡P
Lining should be
provided within the transportation box on the vehicle; ¡P
Fire screen
should be used between cabin and the load on the vehicle; ¡P
Ensure packaging
of detonators remains intact until handed over at blasting site; ¡P
Ensure that
cartridged emulsion packages are not damaged before every trip; and ¡P
Use experienced
driver with good safety record. |
To and from Magazine Site / Construction Phase |
Contractor |
¡Ô |
¡Ô |
|
|
- |
|
7.14.4 |
6.2.5 |
The following
recommendations should be implemented for the safe use of explosives: ¡P
Blast Charge
Weight should be within MIC as specified for the given blast face; ¡P
Temporary
mitigation measures such as blast doors or heavy duty blast curtains should
be installed at the portals or shafts and at suitable locations underground
to prevent flyrock and control the air overpressure; ¡P
Multiple faces
blasting will be carried out for the construction of cavern in this project.
Good communication and control will need to be adopted in ensuring that the
works are carried out safely; ¡P
It is not
intended to carry out complete evacuation of the construction areas and
secure refuge areas should be identified to workers in the areas; ¡P
A Chief
Shotfirer and a Blasting Engineer shall be employed in addition to the normal
blasting personnel to ensure that the works are safe and coordinated between
blasting areas; ¡P
Shotfirer to be
provided with a lightning detector, and appropriate control measures should
be in place; ¡P
Speed limit for
the diesel vehicle truck and bulk emulsion truck in the access tunnel and
cavern should be imposed. The truck may be escorted while underground to
ensure route is clear from hazards and obstructions; and ¡P
Hot work should
be suspended during passage of the diesel vehicle truck and bulk emulsion
truck in the access tunnel and cavern. ¡P
A boulder survey should be undertaken based on the
likely PPV values that would result from the blasting process. Those boulders
subject to the vibration higher than the allowable limit should be
strengthened, removed, or constructed with boulder fence, prior to the
commencement of blasting. |
CSTW / Construction Phase |
Contractor |
¡Ô |
¡Ô |
|
|
- |
|
|
Operation Phase |
|||||||||
|
|
Nil |
|
|
|
|
|
|
|
|
|
Ecological Impact (Terrestrial and Marine) |
|||||||||
|
Construction Phase |
|||||||||
8.8.2 |
7.2.1 |
Construction of access
roads and other temporary works should be carefully designed (e.g. elevated
road for crossing streams) to avoid / minimise habitat loss and
fragmentation. |
Project site ¡V areas access road / Pre-Construction Phase |
Design team / Project Proponent |
¡Ô |
|
|
|
- |
|
8.8.3 |
7.2.2 |
Minimise habitat
loss to nearby habitats and associated wildlife by implementing the following
mitigation measures: - ¡P confining the works within the site
boundary; ¡P controlling access of site staff to avoid damage
to the vegetation in surrounding areas; and ¡P placement of equipment or stockpile in the
existing disturbed / urbanised land within the site boundary of the Project
to minimise disturbance to vegetated areas; |
Project site / Construction Phase |
Contractor |
|
¡Ô |
|
|
- |
|
8.8.3 |
7.2.2 |
Reinstatement planting should be implemented upon the completion of
construction works to minimise the ecological impact arising from the
temporary habitat loss |
Project Site (Main Portal Area / Secondary Portal Area
/ Access Road / Temporary Works Area) /Construction Phase |
Project Proponent |
¡Ô |
¡Ô |
|
¡Ô |
|
|
8.8.2, 8.8.3
& 8.10 |
7.2.2 |
Detailed Vegetation Survey
shall be conducted by a suitably qualified botanist /
ecologist within the works area requiring vegetation clearance prior
to commencement of works to identify plant species of
conservation importance. The potentially
affected individuals shall be tagged and fenced off for preservation, and in
the case of unavoidable loss, for transplantation to nearby suitable habitat(s). |
Proposed works areas (Main Portal, Secondary Portal, Access Road) /
Pre-Construction Phase |
Project Proponent / Qualified botanist or ecologist |
|
¡Ô |
|
|
|
|
8.8.2, 8.8.3 & 8.10 |
7.3.1 |
A Protection and Transplantation
Proposal including the subsequent monitoring visit for the affected plant
species should be prepared and conducted by a suitably qualified local
ecologist. The Proposal should be
submitted for approval at least one month before works commencement. To review the
performance of the transplantation exercise, monitoring of transplanted flora
should be conducted monthly after the transplantation throughout the
construction phase. The
parameters to be monitored should include the health condition and survival
rate of the transplanted flora and presence of weedy
species. Any observations and
recommendations should be reported in monthly EM&A reports |
Recipient Site for transplanted species / Construction Phase |
Project Proponent / Qualified botanist or ecologist |
|
¡Ô |
|
|
|
|
8.8.3 |
7.2.2 |
Mitigation
measures should be implemented to control runoff from the construction site,
as well as the adopting guidelines and good site practices for handling and disposal
of construction discharges in order to minimise the potential indirect impact
on the streams (particularly S2) resulting from site runoff. Precautionary
measures should also be implemented to minimise indirect impacts to the
streams, such as isolating the work site by placing sandbags and silt
curtains, covering up construction materials, debris and spoil to avoid being
washed into the stream, and properly collecting and treating construction
effluent and sewage. |
Access Road on Nui Po Shan / Construction Phase |
Contractor |
|
¡Ô |
|
|
ETWB TCW No. 5/2005 |
|
8.8.3 |
7.2.2 |
Implement good
site practice to further minimise impacts from disturbance such as noise, air
quality and water quality issues, such as: - ¡P the use of quiet plant and EPD¡¦s QPME and the
availability of British Standards 5228 has been considered; ¡P the use of movable noise barrier; ¡P the use of temporary noise screening
structures or purpose-built temporary noise barriers; ¡P install site hoarding as temporary noise
barrier where construction works are undertaken; ¡P only well-maintained plant should be
operated on site and plant should be serviced regularly during the
construction programme; ¡P Mitigation measures stipulated in the
ProPECC PN 1/94 ¡§Construction Site Drainage¡¨ should be complied to minimise
water quality impact; ¡P Installation of stand-by pump, emergency
power supply and telemetry system to avoid sewage overflow and surcharge to
sewerage system due to power/equipment failure. |
Project site / Construction Phase |
Contractor |
|
¡Ô |
|
|
- |
|
8.8.3 |
7.2.2 |
Minimise
groundwater infiltration during cavern construction with the following water
control strategies:- ¡P Probing Ahead: As a normal practice, the
Contractor will undertake rigorous probing of the ground ahead of excavation
works to identify zones of significant water inflow. The probe drilling
results will be evaluated to determine specific grouting requirements in line
with the tunnel / cavern advance. In such zones of significant water inflow
that could occur as a result of discrete, permeable features, the intent
would be to reduce overall inflow by means of cut-off grouting executed ahead
of the tunnel / cavern advance; ¡P Pre-grouting: Where water inflow
quantities are excessive, pre-grouting will be required to reduce the water
inflow into the tunnel / cavern. The pre-grouting will be achieved via a
systematic and carefully specified protocol of grouting; ¡P In principle, the grout pre-treatment
would be designed on the basis of probe hole drilling ahead of the tunnel /
cavern face; ¡P The installation of waterproof lining
would also be adopted after the formation of the tunnels and caverns. |
Project site / Construction Phase |
Contractor |
|
¡Ô |
|
|
- |
|
8.8.3 |
7.2.2 |
In the event of excessive infiltration being observed as a result of
the tunnelling or excavation works even after incorporation of the water
control strategies, post-grouting should be applied as far as practicable as
described below: ¡P Post-grouting: Groundwater drawdown will be
most likely due to inflows of water into the tunnel / cavern that have not
been sufficiently controlled by the pre-grouting measures in high
permeability area. Where this occurs post grouting will be undertaken before
the lining is installed. Whilst unlikely to be required in significant
measure, such a contingency should be allowed for reduction in permeability
of the tunnel / cavern surround (by grouting) to limit inflow to acceptable
levels. The practical
groundwater control measures stated above are proven technologies and have
been extensively applied in other past projects. These measures or other
similar methods, as approved by the Engineer to suit the works condition
shall be applied to minimise the groundwater infiltration. |
Project site / Construction Phase |
Contractor |
|
¡Ô |
|
|
- |
|
8.8.3 |
7.2.2 |
In case seepage
of groundwater occurs, groundwater should be pumped out from works areas and
discharged to the storm system via silt trap. Uncontaminated groundwater from
dewatering process should also be discharged to the storm system via silt
removal facilities. |
Project site / Construction Phase |
Contractor |
|
¡Ô |
|
|
- |
|
8.8.3 |
7.2.2 |
Mitigation measures recommended in the water quality impact assessment
for controlling water quality impact will also serve to protect marine
ecological resources from indirect impacts and ensure no unacceptable impact
on marine ecological resources. Relevant government departments including EPD, WSD and AFCD as well as
key stakeholders for mariculture and fisheries in Tolo Harbour should be
informed of the THEES maintenance / emergency discharge event prior to any
discharge. It is recommended that the temporary effluent bypass event and the
THEES maintenance period should be shortened as far as possible. |
Tolo Harbour / Construction Phase |
Contractor and Operator |
|
¡Ô |
|
|
- |
|
|
Construction and Operation Phase |
|||||||||
8.8.3 |
7.2.2 |
Overall reduction
of glare during both construction and operation phase should be
considered. A balance between
lighting for safety, and avoiding excessive lighting can be achieved through
the use of directional lighting to avoid light spill into sensitive areas,
and control/timing of lighting periods of some facilities, particularly at
the secondary portal which lies approximately 200 m northwest of Ma On Shan
Country Park. |
Project site / Construction and Operation Phase |
Contractor and Operator |
|
¡Ô |
¡Ô |
|
- |
|
8.8.3 |
7.2.2 |
During the
decommissioning and demolition of the existing STSTW, the direction and
lighting periods should be controlled during ardeid breeding season (March to
August) to minimise the potential indirect impact on Penfold Park Egretry and
the ardeids flying over the existing STSTW. |
Existing STSTW / Decommissioning / March to August |
Contractor |
|
|
|
¡Ô |
- |
|
8.10 |
7.3 |
It is anticipated
that the construction of rock caverns would not have adverse impacts on groundwater in Nui Po Shan.
Nonetheless, surface water level or groundwater level near the caverns will be closely monitored during the
construction and operation stage. |
Project site / Construction and Operation Phase |
Contractor and Operator |
|
¡Ô |
¡Ô |
|
- |
|
|
Compensatory Planting |
|||||||||
8.8.4& 8.10.1 |
7.2.3 |
Compensatory
planting would be provided at main and secondary portal areas, and along the
access road. |
Main
portal, secondary portal, and along access road |
Project Proponent |
¡Ô |
¡Ô |
|
|
DEVB TC(W) No. 7/2015 |
|
8.8.4 & 8.10.1 |
7.2.3 |
To facilitate successful
planting, a detailed Woodland Compensation Plan should be prepared by local
ecologists with at least 10 years relevant experience to form the basis of
the proposed compensatory planting.
The Woodland
Compensation Plan should include
implementation details, management requirement, as well as monitoring
requirements (e.g. frequency and parameters) of the compensatory planting
area. Approval of the Plan should
be obtained from EPD at least three months before the prior to commencement
of compensatory woodland planting. |
Compensatory planting area (Main portal, secondary portal, and along
access road) / pre-construction |
Project Proponent |
¡Ô |
¡Ô |
|
|
|
|
8.8.4 & 8.10.1 |
7.2.3 |
Upon the completion of planting, monitoring of the woodland compensation
areas should be implemented, with maintenance works (e.g. irrigation,
weeding, pruning, control of pests and diseases, replacement planting, repair
of damage, etc.) conducted as necessary. |
Compensatory planting area (Main portal, secondary portal,
and along access road) / Operation |
Project Proponent / CSTW Operator |
|
|
¡Ô |
|
|
|
|
Fisheries
Impact |
|||||||||
9.6 |
8.2 |
Potential impacts
on fisheries resources and fishing operations arising from the Project have been
avoided and minimised by construction of a connection pipes to the existing
emergency outfall of STSTW by trenchless method underneath Shing Mun River
with the least water quality impact.
In addition, the temporary effluent bypass event for THEES connection
work would be synchronized within regular THEES maintenance. Therefore, additional water quality
impact and fisheries impact from changes of water quality have been avoided. Furthermore, the THEES maintenance
discharge would avoid the blooming season of algae (i.e. January to May) to
minimise the potential water quality impacts. It is recommended that any THEES
maintenance period should be shortened as far as possible. |
Tolo Harbour /Construction and Operation Phase |
Project Proponent / Contractor |
¡Ô |
¡Ô |
|
|
- |
|
9.6 |
8.2 |
Mitigation measures recommended in the water quality impact assessment
for controlling water quality impact will also serve to protect fisheries
from indirect impacts and ensure no unacceptable impact on fisheries
resources and operations. For more detailed mitigation measures
regarding water quality refer to Sections 5.7.2
and 5.13.2 of the
EIA Report. |
Construction and Operation Phase |
Contractor and Operator |
|
¡Ô |
¡Ô |
|
- |
|
9.6 |
8.2 |
Relevant
government departments including EPD, WSD and AFCD as well as key
stakeholders for mariculture and fisheries in Tolo Harbour should be informed
prior to the THEES maintenance / emergency discharge events. |
Tolo Harbour / Construction and Operation Phase |
Project Proponent |
|
¡Ô |
¡Ô |
|
|
|
|
Landscape
and Visual Impact |
|||||||||
Table 10.10 |
- |
CM1 -
Preservation of Existing Vegetation |
Construction Sites/ Construction Phase |
Project Proponent |
¡Ô |
¡Ô |
|
¡Ô |
DEVB TCW No. 7/2015 and latest Guidelines on Tree
Preservation during Development issued by GLTM Section of DEVB |
|
Table 10.10 |
- |
CM2 -
Transplanting of Affected Trees |
Construction Sites/ Construction Phase |
Project Proponent |
¡Ô |
¡Ô |
|
¡Ô |
DEVB TCW No. 7/2015 and the latest Guidelines on Tree
Transplanting issued by GLTM Section of DEVB |
|
Table 10.10 |
- |
CM3 -
Compensatory Tree Planting |
Construction Sites/ Construction Phase |
Project Proponent |
¡Ô |
¡Ô |
|
¡Ô |
DEVB TCW No. 7/2015 |
|
Table 10.10 |
- |
CM4 - Control of
Night-time Lighting Glare |
Construction Sites/ Construction Phase |
Project Proponent |
¡Ô |
¡Ô |
|
¡Ô |
|
|
Table 10.10 |
- |
CM5 - Erection of
Decorative Screen Hoarding |
Construction Sites/ Construction Phase |
Project Proponent |
¡Ô |
¡Ô |
|
¡Ô |
|
|
Table 10.10 |
- |
CM6 - Management
of Construction Activities and Facilities |
Construction Sites/ Construction Phase |
Project Proponent |
¡Ô |
¡Ô |
|
¡Ô |
|
|
Table 10.10 |
- |
CM7 -
Reinstatement of Temporarily Disturbed Landscape Areas |
Construction Sites/ Construction Phase |
Project Proponent |
¡Ô |
¡Ô |
|
¡Ô |
|
|
Table 10.11 |
- |
OM1 - Tree and
Shrub Planting at the Temporary Project Magazine Site after Completion of
Engineering Works |
Temporary Project Magazine Site /
Operation Phase |
Project Proponent |
¡Ô |
¡Ô |
¡Ô |
|
|
|
Table 10.11 |
- |
OM2 -
Aesthetically pleasing design of Aboveground Structures |
Tunnel Portals, Administration Building, Ventilation Buildings, Electrical Substations and Ventilation Shaft / Operation Phase |
Project Proponent |
¡Ô |
¡Ô |
¡Ô |
|
|
|
Table 10.11 |
- |
OM3 -
Aesthetically pleasing design of Highways Structures |
Access Road to Ventilation Shaft /
Operation Phase |
Highways Department |
¡Ô |
¡Ô |
¡Ô |
|
|
|
Table 10.11 |
- |
OM4 - Reprovision
of Cycle Track |
Cycle track / Operation Phase |
Highways Department |
¡Ô |
¡Ô |
¡Ô |
|
|
|
Table 10.11 |
- |
OM5 - Provision
of Green Roof |
Administration Building and Ventilation Buildings / Operation Phase |
Project Proponent |
¡Ô |
¡Ô |
¡Ô |
|
|
|
Table 10.11 |
- |
OM6 - Provision
of Buffer Planting |
Main and Secondary Portal Areas / Operation Phase |
Project Proponent |
¡Ô |
¡Ô |
¡Ô |
|
|
|
Table 10.11 |
- |
OM7 -
Hydroseeding on the disturbed ground surface after demolition works prior to
future redevelopment of the existing STSTW |
Existing STSTW / Operation Phase |
Lands Department (LandsD)
or future development agent in existing STSTW |
¡Ô |
¡Ô |
¡Ô |
|
|
|
Table 10.11 |
- |
OM8 - Woodland
Mix Planting on Soil Slopes |
Soil Slopes / Operation Phase |
Project Proponent |
¡Ô |
¡Ô |
¡Ô |
|
|
|
|
Cultural
Heritage Impact |
|||||||||
11.5.1.1 |
10.1.1 |
No potential direct or indirect impact to cultural heritage resource is
anticipated, and therefore no mitigation measures are required. |
N/A |
N/A |
|
|
|
|
EIAO EIAO-TM Antiquities and Monuments Ordinance Guidelines for Cultural Heritage Impact Assessment |
|
|
Wastes
Management Implications |
|||||||||
12.6.2 |
11.2.2 |
Appropriate waste
handling, transportation and disposal methods for all waste arising generated
during the construction works for the Project should be implemented to ensure
that construction wastes do not enter the nearby streams or drainage channel. It is anticipated
that adverse impacts would not arise on the construction site, provided that
good site practices are strictly followed. Recommendations for good site
practices during the construction activities include: •
Nomination of
approved personnel, such as a site manager, to be responsible for good site
practices, and making arrangements for collection of all wastes generated at
the site and effective disposal to an appropriate facility. •
Training of site
personnel in proper waste management and chemical waste handling procedures. •
Provision of
sufficient waste reception/ disposal points, of a suitable vermin-proof
design that minimises windblown litter. •
Arrangement for
regular collection of waste for transport off-site and final disposal. •
Appropriate
measures to minimise windblown litter and dust during transportation of waste
by either covering trucks or by transporting wastes in enclosed containers. •
Regular cleaning
and maintenance programme for drainage systems, sumps and oil interceptors. •
A recording
system for the amount of wastes generated, recycled and disposed (including
the disposal sites) should be proposed. •
A Waste
Management Plan should be prepared and should be submitted to the Engineer
for approval. One may make
reference to ETWB TCW No. 19/2005 for details. In order to
monitor the disposal of C&D material at landfills and public filling
areas, as appropriate, and to control fly tipping, a trip-ticket system should
be included as one of the contractual requirements to be implemented by an
Environmental Team undertaking the Environmental Monitoring and Audit
work. One may make reference to
DEVB TCW No.6/2010 for details. |
Project Site Area / Construction Phase |
Contractor |
|
¡Ô |
|
¡Ô |
Waste Disposal Ordinance |
|
12.6.3 |
11.2.3 |
Good management
and control of construction site activities / processes can minimise the
generation of waste. Waste
reduction is best achieved at the planning and design stage, as well as by ensuring
the implementation of good site practices. Recommendations to achieve waste
reduction include: •
Segregate and
store different types of construction related waste in different containers,
skips or stockpiles to enhance reuse or recycling of materials and their
proper disposal. •
Provide separate
labelled bins to segregate recyclable waste such as aluminium cans from other
general refuse generated by the work force, and to encourage collection by
individual collectors. •
Any unused
chemicals or those with remaining functional capacity shall be recycled. •
Maximising the
use of reusable steel formwork to reduce the amount of C&D material. •
Prior to
disposal of C&D waste, it is recommended that wood, steel and other metals
shall be separated for re-use and / or recycling to minimise the quantity of
waste to be disposed of to landfill. •
On-site crushing
and sorting facilities are being considered to reduce the rock size to
fulfill the size requirements from relevant waste collection / transfer /
disposal facilities; •
Adopt proper
storage and site practices to minimise the potential for damage to, or
contamination of, construction materials. •
Plan the
delivery and stock of construction materials carefully to minimise the amount
of surplus waste generated. •
Adopt pre-cast
construction method instead of cast-in-situ method for construction of
concrete structures as much as possible; and •
Minimise over
ordering of concrete, mortars and cement grout by doing careful check before
ordering. In addition to
the above measures, other specific mitigation measures are recommended below
to minimise environmental impacts during handling, transportation and
disposal of wastes. |
Project Site Area / Construction Phase |
Contractor |
|
¡Ô |
|
¡Ô |
Waste Disposal Ordinance |
|
12.6.4 |
11.2.4 |
Storage of
materials on site may induce adverse environmental impacts if not properly
managed, recommendations to minimise the impacts include: •
Waste, such as soil,
should be handled and stored well to ensure secure containment, thus
minimising the potential of pollution; •
Maintain and
clean storage areas routinely; •
Stockpiling area
should be provided with covers as much as practicable and water spraying
system to prevent materials from wind-blown or being washed away; and •
Different
locations should be designated to stockpile each material to enhance reuse. |
Project Site Area / Construction Phase |
Contractor |
|
¡Ô |
|
¡Ô |
- |
|
12.6.4 |
11.2.4 |
Licensed waste haulers
should be employed for the collection and transportation of waste generated.
The following measures should be enforced to minimise the potential adverse
impacts: •
Remove waste in
timely manner; •
Waste collectors
should only collect wastes prescribed by their permits; •
Impacts during
transportation, such as dust and odour, should be mitigated by the use of
covered trucks or in enclosed containers; •
Obtain relevant
waste disposal permits from the appropriate authorities, in accordance with
the Waste Disposal Ordinance (Cap. 354), Waste Disposal (Charges for Disposal
of Construction Waste) Regulation (Cap. 345) and the Land (Miscellaneous
Provisions) Ordinance (Cap. 28); •
Waste should be
disposed of at licensed waste disposal facilities; and •
Maintain records
of quantities of waste generated, recycled and disposed. |
Project Site Area / Construction Phase |
Contractor |
|
¡Ô |
|
¡Ô |
Waste Disposal Ordinance Waste Disposal (Charges for Disposal of Construction Waste) Regulation Land (Miscellaneous Provisions) Ordinance |
|
12.6.4 |
11.2.4 |
Land transport
will be used for transportation of excavated and stockpile materials. It is expected there will be 1260
vehicles per day for transporting waste during peak construction phase. The tentative transportation routings
for the disposal of various types of wastes are shown in Table
12.4. The transportation
routing may be changed subject to the traffic conditions. Nevertheless, it is anticipated that
there is no adverse impact from the waste during transportation with the
implementation of appropriated measures (e.g. using water-tight containers
and covered trucks). |
Transportation Route of Waste / Construction Phase |
Contractor |
|
¡Ô |
|
|
- |
|
12.6.4 |
11.2.4 |
In order to
monitor the disposal of C&D materials at PFRFs and landfills and to
control fly-tipping, a trip-ticket system should be established in accordance
with DEVB TCW No. 6/2010. A
recording system for the amount of waste generated, recycled and disposed,
including the disposal sites, should also be set up. Warning signs should be put up to
remind the designated disposal sites. Close-circuited television should be
installed at the vehicular entrance and exit of the site as additional
measures to prevent fly-tipping. |
Project Site Area / Construction Phase |
Contractor |
|
¡Ô |
|
¡Ô |
DEVB TCW No. 6/2010 |
|
12.6.4 |
11.2.5 |
In addition to
the above general measures, other specific mitigation measures on handling
the C&D materials and materials generated from site formation and
demolition work are recommended below, which should form the basis of the WMP
to be prepared by the contractor(s) in construction phase. |
Project Site Area / Construction Phase |
Contractor |
|
¡Ô |
|
¡Ô |
Technical Circular (Works) No. 19/2005 Environmental Management on
Construction Site |
|
12.6.5 |
11.2.5 |
In order to
minimise the impact resulting from collection and transportation of C&D
materials for off-site disposal, the excavated material arising from site formation
and foundation works should be reused on-site as backfilling material and for
landscaping works as far as practicable. Other mitigation requirements are
listed below: •
A WMP, which
becomes part of the EMP, should be prepared in accordance with ETWB TCW
No.19/2005; •
A recording
system for the amount of wastes generated, recycled and disposed (including
the disposal sites) should be adopted for easy tracking; and •
In order to
monitor the disposal of C&D materials at public filling facilities and landfills
and to control fly-tipping, a trip-ticket system should be adopted (refer to
DEVB TCW No. 6/2010). It is recommended
that specific areas should be provided by the Contractors for sorting and to
provide temporary storage areas (if required) for the sorted materials. |
Project Site Area / Construction Phase |
Contractor |
|
¡Ô |
|
¡Ô |
Waste Disposal Ordinance ETWB TCW No.19/2005 DEVB TCW No. 6/2010 |
|
12.6.5 |
11.2.5 |
The Contactor
should prepare and implement an EMP in accordance with ETWB TCW No.19/2005, which
describes the arrangements for avoidance, reuse, recovery, recycling,
storage, collection, treatment and disposal of different categories of waste
to be generated from construction activities. Such a management plan should
incorporate site specific factors, such as the designation of areas for
segregation and temporary storage of reusable and recyclable materials. The EMP should be submitted to the
Engineer for approval. The
Contractor should implement waste management practices in the EMP throughout
the construction stage of the Project.
The EMP should be reviewed regularly and updated by the Contractor,
preferably on a monthly basis. |
Project Site Area / Construction Phase |
Contractor |
|
¡Ô |
|
|
ETWB TCW No.19/2005 |
|
12.6.5 |
11.2.5 |
All surplus C&D materials arising from or in connection with
construction works should become the property of the Contractor when it is
removed unless otherwise stated.
The Contractor would be responsible for devising a system to work for
on-site sorting of C&D materials and promptly removing all sorted and
process materials arising from the construction activities to minimise
temporary stockpiling on-site. The system should be included in the EMP
identifying the source of generation, estimated quantity, arrangement for
on-site sorting, collection, temporary storage areas and frequency of
collection by recycling Contractors or frequency of removal off-site. |
Project Site Area / Construction Phase |
Contractor |
|
¡Ô |
|
¡Ô |
- |
|
12.6.6 |
11.2.6 |
The practices of good
housekeeping for CSTW listed below should be followed to ameliorate any odour
impact from handling, collection, transportation and disposal of sludge: •
Screens should
be cleaned regularly to remove any accumulated organic debris •
Grit and screening
transfer systems should be flushed regularly with water to remove organic
debris and grit •
Grit and
screened materials should be transferred to closed containers •
Scum and grease
collection wells and troughs should be emptied and flushed regularly to
prevent putrefaction of accumulated organics •
Skim and remove
floating solids and grease from primary clarifiers regularly •
Frequent sludge
withdrawal from tanks is necessary to prevent the production of gases •
Sludge should be
transported to the STF by water-tight containers to avoid Hydrogen Sulphide
(H2S)/odour emission and ingress of water into the containers which would
lower the sludge dryness during transportation •
Sludge cake
should be transferred to closed containers •
Sludge
containers should be flushed with water regularly •
Sludge trucks
and containers should be washed thoroughly before leaving the CSTW to avoid
any odour nuisance during transportation |
Operation Phases |
Operator |
|
|
¡Ô |
|
Waste Disposal Ordinance |
|
12.6.6 |
11.2.6 |
In addition, all wastewater generated
from the sludge dewatering process and all contaminated water from the
cleaning operations recommended for odour control will be diverted to the
relocated STSTW for proper treatment. |
Operation Phases |
Operator |
|
|
¡Ô |
|
Waste Disposal Ordinance |
|
12.6.7 |
11.2.7 |
If chemical
wastes are produced at the construction site or during operation, the
Contractor during construction or the operator during operation will be required
to register with the EPD as a chemical waste producer and to follow the
guidelines stated in the Code of Practice on the Packaging, Labelling and
Storage of Chemical Wastes. Good quality containers compatible with the
chemical wastes should be used, and incompatible chemicals should be stored
separately. Appropriate labels should be securely attached on each chemical
waste container indicating the corresponding chemical characteristics of the
chemical waste, such as explosive, flammable, oxidising, irritant, toxic,
harmful, corrosive, etc. The Contractor shall use a licensed collector to
transport and dispose of the chemical wastes, to the licensed Chemical Waste
Treatment Centre, or other licensed facilities, in accordance with the Waste
Disposal (Chemical Waste) (General) Regulation. |
Construction and Operation Phases |
Contractor / Operator |
|
¡Ô |
¡Ô |
|
Waste Disposal (Chemical Waste) (General) Regulation Code of Practice on the Packaging, Labelling and Storage of Chemical
Wastes |
|
12.6.8 |
11.2.8 |
Recycling of waste paper, aluminium cans and plastic bottles should be
encouraged, it is recommended to place clearly labelled recycling bins at
designated locations which could be accessed conveniently. Other general refuse should be
separated from chemical and industrial waste by providing separated bins for
storage to maximise the recyclable volume. |
Construction and Operation Phases |
Contractor / Operator |
|
¡Ô |
¡Ô |
|
Public Health and Municipal
Services Ordinance (Cap.132) |
|
12.6.8 |
11.2.8 |
A reputable licensed
waste collector should be employed to remove general refuse on a daily basis
to minimise odour, pest and litter impacts. |
Construction and Operation Phases |
Contractor / Operator |
|
¡Ô |
¡Ô |
|
Public Health and Municipal Services Ordinance (Cap. 132) |
|
|
Health
Impact |
|||||||||
- |
- |
Not applicable. |
|
|
|
|
|
|
|
|
<End of Section 16>