TABLE OF CONTENTS

Page

16               Implementation Schedule of Recommended Mitigation Measures. 16-1

16.1            Implementation Schedule of Recommended Mitigation Measures. 16-1


 

 

16                   Implementation Schedule of Recommended Mitigation Measures

16.1                Implementation Schedule of Recommended Mitigation Measures

16.1.1.1         This section presents the implementation schedule of mitigation measures for the Project. Table 16.1 summarises the details of the recommended mitigation measures for all works areas.  For each recommended mitigation measures, both the location and timing for the measure have clearly been identified as well as the parties responsible for implementing the measure and for maintenance (where applicable).         

Table 16.1     Implementation Schedule of Recommended Mitigation Measures

EIA Ref.

EM&A Log Ref.

Environmental Protection Measures

Location / Duration of Measures / Timing of Completion of Measures

Implementation Agent

Implementation Stage [1]

Relevant Legislation & Guidelines

Des

C

O

Dec

 

Air Quality Impact

 

Construction Phase

Table 3.5

2.4.1

The rock crushing plant is configured as an enclosed system.

Dust collector with dust removal efficiency of 99% will be provided at the exhaust of the rock crusher during rock crushing.

Watering will be provided to maintain material in wet condition.

Vehicles would be required to pass through the wheel washing facilities provided at site exit.

Rock Crushing Plant / Construction Phase

Contractor

¡Ô

¡Ô

 

¡Ô

Air Pollution Control Ordinance (APCO)

3.8.1

2.4.1

Watering eight times a day on active works areas, exposed areas and unpaved haul roads to reduce dust emission by 87.5%.

All active works areas, exposed areas and unpaved haul roads

Contractor

 

¡Ô

 

¡Ô

APCO

3.8.1

2.4.1

Dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation and good site practices:

¡P         Use of regular watering to reduce dust emissions from exposed site surfaces and unpaved roads, particularly during dry weather.

¡P         Use of frequent watering for particularly dusty construction areas and areas close to ASRs.

¡P         Side enclosure and covering of any aggregate or dusty material storage piles to reduce emissions.  Where this is not practicable owing to frequent usage, watering shall be applied to aggregate fines.

¡P         Open stockpiles shall be avoided or covered.  Where possible, prevent placing dusty material storage piles near ASRs.

¡P         Tarpaulin covering of all dusty vehicle loads transported to, from and between site locations.

¡P         Establishment and use of vehicle wheel and body washing facilities at the exit points of the site.

¡P         Provision of wind shield and dust extraction units or similar dust mitigation measures at the loading area of barging point, and use of water sprinklers at the loading area where dust generation is likely during the loading process of loose material, particularly in dry seasons/ periods.

¡P         Provision of not less than 2.4m high hoarding from ground level along site boundary where adjoins a road, streets or other accessible to the public except for a site entrance or exit.

¡P         Imposition of speed controls for vehicles on site haul roads.

¡P         Where possible, routing of vehicles and positioning of construction plant should be at the maximum possible distance from ASRs.

¡P         Every stock of more than 20 bags of cement or dry PFA should be covered entirely by impervious sheeting or placed in an area sheltered on the top and the 3 sides.

¡P         Instigation of an environmental monitoring and auditing program to monitor the construction process in order to enforce controls and modify method of work if dusty conditions arise.

Construction Sites

Contractor

 

¡Ô

 

¡Ô

APCO and Air Pollution Control (Construction Dust) Regulation

 

Operation Phase

3.5.2

-

Sludge tanks with totally enclosed design proven by DSD should be deployed for transporting sludge. 

With thorough cleaning practice and regular condition test of the sludge tanks, odour emission and leachate leakage during storage and transportation are not anticipated. 

Cavern Sewage Treatment Works (CSTW) / Operation Phase

Project Proponent / Operator

¡Ô

 

¡Ô

 

-

3.6.2, 3.7.2

2.4.2

All treatment units with potential odour emission will be covered and the exhausted air will be conveyed to the deodouriser (with 80 ¡V 97% odour removal efficiency) for treatment before discharge to the environment.

CSTW / Operation Phase

Design team / Project Proponent / Operator

¡Ô

 

¡Ô

 

-

3.7.2

2.4.2

The following appropriate odour control measures would be implemented.

(i)   Adopting the advantage of caverns as natural barriers for odour control;

(ii)  Covering up of odour sources;

(iii) Preventing odour leakage through the access tunnels by applying negative pressure inside caverns;

(iv) Installing deodourizing units to clean up the collected foul air;

(v)  Discharging exhausted air at height to further enhance the dilution effect; and

(vi) Enhancing the odour management of the sludge transportation.

CSTW / Operation Phase

Design team / Project Proponent / Operator

¡Ô

 

¡Ô

 

-

3.10.2

2.3.1

Odour monitoring at the inlet and outlet of the deodourizing units is proposed to be conducted for first three years of the operation of CSTW, quarterly in the first year, and once every 6 months in the second and third years if monitoring results remain below the limit levels.

CSTW / Operation Phase

Project Proponent / Operator

¡Ô

 

¡Ô

 

-

3.10.2

2.3.2

An Odour Complaint Registration System is also proposed in the EM&A programme to check whether the deodorizing units can fulfill the recommended odour removal performance.

CSTW / Operation Phase

Operator

 

 

¡Ô

 

-

3.10.2

-

Any unexpected leakage from tanks could be observed with monitoring equipment. Monitoring equipment would be installed in the CSTW to monitor the concentration of H2S, CO and CO2 and methane. Investigation and repair works would be carried out immediately if abrupt increase of these concentrations are reported. Emergency Plan would be established for these upset conditions.

CSTW / Operation Phase

Project Proponent / Operator

¡Ô

 

¡Ô

 

-

 

Noise Impact

 

Construction Phase

4.5.1.6

-

Re-provision of 220m length noise barrier with 10mPD on temporary access haul road to replace the existing 150m length noise barrier with 9.2mPD to 10mPD on Ma On Sha Road.  The location of the relocated noise barrier is shown in Figure No. 60334056/EIA/4.02 and Appendix 4.07. Once the construction work for the CSTW is completed, the temporary access roads would be demolished and the relevant section of Ma On Shan Road and associated noise barrier would be recovered as before.

Proposed temporary access / Construction Phase

Contractor

 

¡Ô

 

 

Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM), Noise Control Ordinance (NCO)

4.8.1

3.8.1

The use of quiet plant associated with the construction works is prescribed in British Standard ¡§Code of practice for noise and vibration control on construction and open sites, BS5228¡¨ which contains the SWLs for specific quiet PME. 

All Construction Work Sites

Contractor

 

¡Ô

 

¡Ô

EIAO-TM, NCO

4.8.1

3.8.1

To alleviate the construction noise impact on the affected NSRs, movable noise barrier for Air Compressor, Bar Bender and Cutter, Breaker, Chisel, Saw, Compactor, Mixers, Pump, Crane, Desander, Drilling Rig, Dump Truck, Excavator, Generator, Grab, Lorry, Paver, Poker and Roller  are proposed. 

All Construction Work Sites

Contractor

 

¡Ô

 

¡Ô

EIAO-TM, NCO

4.8.1

3.8.1

Provision of noise barrier/acoustic mats for Drilling Jumbo so as to have screening effecting with 10 dB(A) noise attenuation

Drilling Jumbo operate outside the portal and within 20m inside the portal

Contractor

 

¡Ô

 

 

EIAO-TM, NCO

4.8.1

3.8.1

To further alleviate the construction noise impact on the Neighbourhood Advice-Action Council Harmony Manor, it is proposed to limit the number of on-time operating PMEs within 120m of this NSR during construction of access road.

Construction Site for access road for magazine at A Kung Kok Road

Contractor

 

¡Ô

 

¡Ô

EIAO-TM, NCO

4.9.1

3.8.1

In addition to the above-mentioned mitigation measures, good site practices listed below shall be adopted by all the contractors to further ameliorate the noise impacts. 

¡P         Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction program.

¡P         Silencers or mufflers on construction equipment should be utilised and should be properly maintained during the construction program.

¡P         Mobile plant, if any, should be sited as far away from NSRs as possible.

¡P         Machines and plant (such as trucks) that may be in intermittent use should be shut down between works periods or should be throttled down to a minimum.

¡P         Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs.

¡P         Material stockpiles and other structures should be effectively utilised, wherever practicable, in screening noise from on-site construction activities.

 

All Construction Work Sites

Contractor

 

¡Ô

 

¡Ô

EIAO-TM, NCO

 

Operation Phase

4.7.4

3.8.2

The maximum allowable sound power levels for the ventilation shaft, ventilation buildings at main portal and emergency portal, ventilation fan for chiller plant room and cooling tower at the administration building as presented in Table 4.16 of the EIA Report should be achieved such that the nearest affected NSRs can be in compliance with the noise criteria

Ventilation Shaft, Administration Building and Ventilation Buildings/ Operation Phase

Project Proponent

¡Ô

 

¡Ô

 

EIAO-TM, NCO

4.11.2

3.8.2

Prior to the operational phase of the Project, a commissioning test for the ventilation buildings, the ventilation shaft, ventilation fan for chiller plant room at administration building and cooling tower at the administration building would be conducted to ensure compliance with the relevant allowable maximum sound power levels.

Ventilation Shaft, Administration Building and Ventilation Buildings/ Operation Phase

Contractor

 

 

¡Ô

 

EIAO-TM, NCO

 

 

Water Quality Impact

 

Construction Phase

5.7.2

4.10

Water used in ground boring and drilling for SI or rock / soil anchoring should as far as practicable be re-circulated after sedimentation. When there is a need for final disposal, the wastewater should be discharged into storm drains via silt removal facilities.

Construction Sites / Construction Phase

Contractor

 

¡Ô

 

 

Water Pollution Control Ordinance (WPCO), EIAO-TM

5.7.2

4.10

All vehicles and plant should be cleaned before they leave a construction site to minimise the deposition of earth, mud, debris on roads. A wheel washing bay should be provided at every site exit if practicable and wash-water should have sand and silt settled out or removed before discharging into storm drains. The section of construction road between the wheel washing bay and the public road should be paved with backfill to reduce vehicle tracking of soil and to prevent site run-off from entering public road drains.

Construction Sites / Construction Phase

Contractor

 

¡Ô

 

 

Professional Persons Environmental Consultative Committee (ProPECC) Practice Note (PN) 1/94, WPCO, Waste Disposal Ordinance (WDO)

 

5.7.2

4.10

Good site practices should be adopted to remove rubbish and litter from construction sites so as to prevent the rubbish and litter from spreading from the site area. It is recommended to clean the construction sites on a regular basis.

Construction Sites / Construction Phase

Contractor

 

¡Ô

 

 

WPCO, EIAO-TM

5.7.2

4.10

The site practices outlined in ProPECC PN 1/94 ¡§Construction Site Drainage¡¨ should be followed where applicable to minimise surface run-off and the chance of erosion.

Construction Sites / Construction Phase

Contractor

 

¡Ô

 

 

WPCO, EIAO-TM, ProPECC PN 1/94

5.7.2

4.10

There is a need to apply to EPD for a discharge licence for discharge of effluent from the construction site under the WPCO.  The discharge quality must meet the requirements specified in the discharge licence.  All the runoff and wastewater generated from the works areas should be treated so that it satisfies all the standards listed in the TM-DSS.  The beneficial uses of the treated effluent for other on-site activities such as dust suppression, wheel washing and general cleaning etc., can minimise water consumption and reduce the effluent discharge volume.  If monitoring of the treated effluent quality from the works areas is required during the construction phase of the Project, the monitoring should be carried out in accordance with the relevant WPCO licence which is under the ambit of RO of EPD.

Construction Sites / Construction Phase

Contractor

 

¡Ô

 

 

WPCO, EIAO-TM, (TM-DSS)

5.7.2

4.10

Contractor must register as a chemical waste producer if chemical wastes would be produced from the construction activities.  The Waste Disposal Ordinance (Cap 354) and its subsidiary regulations in particular the Waste Disposal (Chemical Waste) (General) Regulation, should be observed and complied with for control of chemical wastes.

Construction Sites / Construction Phase

Contractor

 

¡Ô

 

 

WPCO, EIAO-TM, WDO

5.7.2

4.10

Any service shop and maintenance facilities should be located on hard standings within a bonded area, and sumps and oil interceptors should be provided.  Maintenance of vehicles and equipment involving activities with potential for leakage and spillage should only be undertaken within the areas appropriately equipped to control these discharges.

Construction Sites / Construction Phase

Contractor

 

¡Ô

 

 

WPCO, EIAO-TM

5.7.2

4.10

Disposal of chemical wastes should be carried out in compliance with the WDO.  The Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes published under the Waste Disposal Ordinance should be followed to avoid leakage or spillage of chemicals. 

Construction Sites / Construction Phase

Contractor

 

¡Ô

 

 

WPCO, EIAO-TM, WDO

5.7.2

4.10

Sufficient chemical toilets should be provided in the works areas.  A licensed waste collector should be deployed to clean the chemical toilets on a regular basis.

Construction Sites / Construction Phase

Contractor

 

¡Ô

 

 

WPCO, EIAO-TM

5.7.2

4.10

Notices should be posted at conspicuous locations to remind the workers not to discharge any sewage or wastewater into the surrounding environment.

Construction Sites / Construction Phase

Contractor

 

¡Ô

 

 

WPCO, EIAO-TM

5.7.2

4.10

The practices outlined in ETWB TC (Works) No. 5/2005 ¡§Protection of natural streams/rivers from adverse impacts arising from construction works¡¨ should also be adopted where applicable to minimise the water quality impacts upon any natural streams or surface water systems.

Construction Sites / Construction Phase

Contractor

 

¡Ô

 

 

WPCO, EIAO-TM, ETWB TC (Works) No. 5/2005

5.7.2

4.10

Appropriate measures during the construction of the cavern construction should be implemented to minimise the groundwater infiltration.

Construction Sites / Construction Phase

Contractor

 

¡Ô

 

 

WPCO, EIAO-TM

5.7.2

4.10

No directly discharge of groundwater from contaminated areas should be adopted.  Prior to any excavation works within the potentially contaminated areas at the existing STSTW site, the baseline groundwater quality in these areas should be reviewed based on the relevant SI data and any additional groundwater quality measurements to be performed with reference to Guidance Note for Contaminated Land Assessment and Remediation and the review results should be submitted to EPD for examination. If the review results indicated that the groundwater to be generated from the excavation works would be contaminated, this contaminated groundwater should be either properly treated or properly recharged into the ground in compliance with the requirements of the TM-DSS.   If wastewater treatment is to be deployed for treating the contaminated groundwater, the wastewater treatment unit shall deploy suitable treatment processes (e.g. oil interceptor / activated carbon) to reduce the pollution level to an acceptable standard and remove any prohibited substances (such as TPH) to an undetectable range. All treated effluent from the wastewater treatment plant shall meet the requirements as stated in TM-DSS and should be either discharged into the foul sewers or tankered away for proper disposal.

Construction Sites / Construction Phase

Contractor

 

¡Ô

 

 

WPCO, EIAO-TM, Guidance Note for Contaminated Land Assessment and Remediation

5.7.2

4.10

If deployment of wastewater treatment is not feasible for handling the contaminated groundwater, groundwater recharging wells should be installed as appropriate for recharging the contaminated groundwater back into the ground. The recharging wells should be selected at places where the groundwater quality will not be affected by the recharge operation as indicated in section 2.3 of the TM-DSS.  The baseline groundwater quality should be determined prior to the selection of the recharge wells, and submit a working plan to EPD for agreement.  Pollution levels of groundwater to be recharged shall not be higher than pollutant levels of ambient groundwater at the recharge well. Groundwater monitoring wells should be installed near the recharge points to monitor the effectiveness of the recharge wells and to ensure that no likelihood of increase of groundwater level and transfer of pollutants beyond the site boundary. Prior to recharge, free products should be removed as necessary by installing the petrol interceptor.  The Contractor should apply for a discharge licence under the WPCO through the Regional Office of EPD for groundwater recharge operation or discharge of treated groundwater

Construction Sites / Construction Phase

Contractor

 

¡Ô

 

 

WPCO, EIAO-TM, TM-DSS

5.7.2

4.10

THEES connection works should be synchronized with the THEES maintenance, for a duration not longer than 4 weeks each outside the algae blooming season (January to May) and frequency of THEES maintenance shall be no more than once per year during the construction phase of the Project.

Tolo Harbour / Construction Phase

Project Proponent / Contractor

¡Ô

¡Ô

 

 

EIAO-TM

 

Construction and Operation Phases

5.10.2

4.10

Shutdown of the THEES for maintenance should be shortened as far as possible. It is recommended that the maintenance of the THEES tunnel should be avoided during the algae blooming season (January to May). 

Tolo Harbour / Construction and Operation Phase

Project Proponent

 

¡Ô

¡Ô

 

WPCO, EIAO-TM

5.10.2

4.10

Relevant government departments including EPD, WSD, AFCD as well as the key stakeholders for mariculture and fisheries in Tolo Harbour should be informed of the maintenance event prior to any discharge.

Tolo Harbour / Construction and Operation Phase

Project Proponent

 

¡Ô

¡Ô

 

WPCO, EIAO-TM

5.10.3

4.2-4.5

An event and action plan and a water quality monitoring programme (as presented in the EM&A Manual) should be implemented for the THEES maintenance discharge

Tolo Harbour / Construction and Operation Phase

Project Proponent

 

¡Ô

¡Ô

 

WPCO, EIAO-TM

5.10.1

4.10

Silt screen may be installed at the flushing water intakes during the THEES maintenance discharge should it appear necessary. Close communication between DSD and WSD should be maintained to minimize any impact on the flushing water intakes due to THEES maintenance discharge.

WSD flushing water intakes / Construction and Operation Phase

WSD / Project Proponent

 

¡Ô

¡Ô

 

WPCO, EIAO-TM

 

Design and Operation Phases

5.8.3

4.6

In case adverse impact on KTN is identified based on the result of the three-month monitoring programme after commissioning of the project, the operation conditions of the treatment and THEES system should be investigated, and corrective and remedial action should be implemented to improve the effluent discharge from the CSTW. Furthermore, DSD should extend the water quality monitoring programme for at least three months or as agreed by the Director of Environmental Protection.

Project site / Design and Operation Phases

Project Proponent

 

 

¡Ô

 

WPCO, EIAO-TM

5.11.2

4.10

Dual power supply or ring main supply from CLP Power Hong Kong Ltd. CLP should be provided for the CSTW to prevent the occurrence of power failure.  In addition, standby facilities for the main treatment units and standby equipment parts / accessories should also be provided in order to minimise the chance of emergency discharge.  CLP should be consulted in order to ascertain the power supply for normal plant operation within the caverns.  It is recommended that government departments including EPD, WSD and AFCD as well as the key stakeholders for mariculture and fisheries in Tolo Harbour should be informed as soon as possible in case of any emergency discharge so that appropriate actions can be taken.

Project site / Design and Operation Phases

Project Proponent

¡Ô

 

¡Ô

 

WPCO, EIAO-TM

5.11.2

4.10

In case of emergency discharge, the plant operators of CSTW should carry out necessary follow-up actions according to the procedures of the current contingency plan formulated for the existing STSTW to minimise the water quality impact.

Project site / Operation Phase

Project Proponent

 

 

¡Ô

 

WPCO, EIAO-TM

5.11.2

4.10

WSD may also consider, should it appear necessary, to shut down the Sha Tin seawater pumping station for a short period of time in case of emergency discharge in order to minimize any adverse impacts.

Sha Tin seawater pumping station / Operation Phase

WSD / Project Proponent

 

 

¡Ô

 

WPCO, EIAO-TM

5.13.2

4.10

BMPs to reduce storm water and non-point source pollution are also proposed as follows:

Design Measures

¡P         Exposed surface shall be avoided within the road and portal sites to minimise soil erosion.  The access road and the portal areas shall be either hard paved or covered by landscaping area where appropriate.

¡P         Streams near the Project site will be retained to maintain the original flow path.  The drainage system will be designed to avoid flooding.

¡P         Green areas / planting etc. should be introduced alongside the access road and within the portal areas, as far as possible, to minimise runoff pollution.

Devices/ Facilities to Control Pollution

¡P         Screening facilities such as standard gully grating and trash grille, with spacing which is capable of screening off large substances such as fallen leaves and rubbish should be provided at the inlet of drainage system. 

¡P         Road gullies with standard design and silt traps should be provided to remove particles present in stormwater runoff, where appropriate. 

Administrative Measures

¡P         Good management measures such as regular cleaning and sweeping of road surface/ open areas are suggested. The road surface/ open area cleaning should also be carried out prior to occurrence rainstorm.

¡P         Manholes, as well as stormwater gullies, ditches provided at the Project site should be regularly inspected and cleaned (e.g. monthly).  Additional inspection and cleansing should be carried out before forecast heavy rainfall.

Project site / Design and Operation Phase

Project Proponent

¡Ô

 

¡Ô

 

WPCO, ProPECC PN 5/93

 

Land Contamination

6.7.1

-

Further site walkover and/or detailed land contamination assessment will be required for sites that are inaccessible or currently in operation / yet to be constructed (i.e. existing STSTW, David Camp and part of existing Sha Tin VDC, and proposed A Kung Kok Shan Road surface magazine site within the Project boundary). The site walkover, detailed land contamination assessment and if necessary, remediation works should be carried out after decommissioning of the sites but prior to re-development and should include the following:

¡P         Prior to the commencement of the SI works, review the CAP to confirm whether the proposed SI works (e.g. sampling locations, testing parameters etc.) are still valid and to confirm the appropriate RBRGs land use scenario for the development;

¡P         Submit supplementary CAP(s), presenting the findings of the above review for EPD endorsement. If land contamination issues were identified within David Camp or part of existing VDC / proposed A Kung Kok Shan Road surface magazine site within the Project boundary in the further site walkover, findings of the site walkover and the proposal for SI works should also be presented in the supplementary CAP(s);

¡P         Carry out SI works according to the supplementary CAP endorsed by EPD;

¡P         Submit CAR(s), detailing findings of the SI works and nature/extent of any soil/groundwater contamination, and, if contaminated identified, RAP(s), discussing the appropriate remedial methods and mitigation measures, for the identified contamination, for EPD agreement; and

¡P         Carry out soil/groundwater remediation works according to EPD agreed RAP and submit RR(s) afterwards for EPD agreement. The remediation works and agreement of RR should be completed prior to re-development.

Existing STSTW, David Camp and VDC / Construction Phase

Project Proponent / Contractor

 

¡Ô

 

¡Ô

(for existing STSTW)

Guidance Note for Contaminated Land Assessment and Remediation, Practice Guide for Investigation and Remediation of Contaminated Land, Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management

6.7.2

-

If contamination were identified, mitigation measures as recommended in the RAP should be followed and should include the following:

¡P         Excavation profiles must be properly designed and executed with attention to the relevant requirements for environment, health and safety;

¡P         Excavation shall be carried out during dry season as far as possible to minimise contaminated runoff from contaminated soils;

¡P         Supply of suitable clean backfill material (or treated soil) after excavation;

¡P         Stockpiling site(s) shall be lined with impermeable sheeting and bunded. Stockpiles shall be fully covered by impermeable sheeting to reduce dust emission. If this is not practicable due to frequent usage, regular watering shall be applied. However, watering shall be avoided on stockpiles of contaminated soil to minimise contaminated runoff.

¡P         Vehicles containing any excavated materials shall be suitably covered to limit potential dust emissions or contaminated wastewater run-off, and truck bodies and tailgates shall be sealed to prevent any discharge during transport or during wet conditions;

¡P         Speed control for the trucks carrying contaminated materials shall be enforced;

¡P         Vehicle wheel and body washing facilities at the site¡¦s exist points shall be established and used; and

¡P         Pollution control measures for air emissions (e.g. from biopile blower and handling of cement), noise emissions (e.g. from blower or earthmoving equipment), and water discharges (e.g. runoff control from treatment facility) shall be implemented and complied with relevant regulations and guidelines.

Project Site / Construction Phase

Contractor

 

¡Ô

 

¡Ô

(for existing STSTW)

Guidance Note for Contaminated Land Assessment and Remediation, Practice Guide for Investigation and Remediation of Contaminated Land, Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management

 

Hazard to Life

 

Construction Phase

7.14.1

6.2.2

The following recommendations are justified to be implemented to meet the EIAO-TM requirements:

¡P         The truck should be designed to minimise the amount of combustible in the cabin. The fuel carried in the fuel tank should also be minimised to reduce the duration of any fire;

¡P         The accident involvement frequency of the explosives delivery truck should be minimised through implementation of several administrative measures, such as providing training programme to the driver, regular ¡§tool box¡¨ briefing session, implementing a defensive driving attitude, selecting driver with good safety record, and providing regular medical checks for the driver;

¡P         Avoidance of returning unused explosives to the magazine, only the required quantity of explosives for a particular blast should be transported;

¡P         Maintain a minimum headway of 10 minutes between two consecutive truck convoys whenever practicable; and

¡P         The fire involvement frequency should be minimised by carrying better types of fire extinguishers and with bigger capacity onboard of the explosives delivery truck. Emergency plans and trainings could also be provided to make sure that the fire extinguishers are used adequately.

Explosives dlivery route / Construction Phase

Contractor

¡Ô

¡Ô

 

 

EIAO-TM

7.14.2

6.2.3

The magazine should be designed, built, operated and maintained in accordance with Mines Division¡¦s guidelines and appropriate industry best practice. In addition, the following recommendations should be implemented:

¡P         The security plan should address different alert security level to reduce opportunity for arson or deliberate initiation of explosives;

¡P         Emergency plan should be developed to address uncontrolled fire in magazine area, and drill of the emergency plan should be regularly carried out;

¡P         Suitable work control system should be set-up, such as an operational manual including Permit-to-Work system, to ensure that work activities undertaken during operation of the magazine are properly controlled;

¡P         Good house-keeping within the magazine to ensure no combustible materials are accumulated;

¡P         Good house-keeping outside the magazine stores to ensure no combustible materials are accumulated; and

¡P         Regular checking of the magazine store to ensure no water seepage through the roof, walls or floor.

Magazine Site/ Construction Phase

Contractor

¡Ô

¡Ô

 

 

-

7.14.3

6.2.4

The following recommendations should be implemented:

¡P         Emergency plan should be developed to address uncontrolled fire during transport. Case of fire near an explosive delivery truck in jammed traffic should be included in the plan. Activation of fuel and battery isolation switches on vehicle when fire breaks out should also be included in the emergency plan to reduce likelihood of prolonged fire leading to explosion;

¡P         Working guideline should be developed to define procedure for explosives transport during adverse weather such as thunderstorm;

¡P         Detonators should be transported separately from other Class 1 explosives. Separation of vehicles should also be maintained through the trip;

¡P         Develop procedure to ensure the availability of parking space on site for the explosives delivery truck. Delivery should not be commenced if parking space on site is not secured;

¡P         Hot work or other activities should be banned in the vicinity of the explosives offloading or charging activities;

¡P         Lining should be provided within the transportation box on the vehicle;

¡P         Fire screen should be used between cabin and the load on the vehicle;

¡P         Ensure packaging of detonators remains intact until handed over at blasting site;

¡P         Ensure that cartridged emulsion packages are not damaged before every trip; and

¡P         Use experienced driver with good safety record.

To and from Magazine Site / Construction Phase

Contractor

¡Ô

¡Ô

 

 

-

7.14.4

6.2.5

The following recommendations should be implemented for the safe use of explosives:

¡P         Blast Charge Weight should be within MIC as specified for the given blast face;

¡P         Temporary mitigation measures such as blast doors or heavy duty blast curtains should be installed at the portals or shafts and at suitable locations underground to prevent flyrock and control the air overpressure;

¡P         Multiple faces blasting will be carried out for the construction of cavern in this project. Good communication and control will need to be adopted in ensuring that the works are carried out safely;

¡P         It is not intended to carry out complete evacuation of the construction areas and secure refuge areas should be identified to workers in the areas;

¡P         A Chief Shotfirer and a Blasting Engineer shall be employed in addition to the normal blasting personnel to ensure that the works are safe and coordinated between blasting areas;

¡P         Shotfirer to be provided with a lightning detector, and appropriate control measures should be in place;

¡P         Speed limit for the diesel vehicle truck and bulk emulsion truck in the access tunnel and cavern should be imposed. The truck may be escorted while underground to ensure route is clear from hazards and obstructions; and

¡P         Hot work should be suspended during passage of the diesel vehicle truck and bulk emulsion truck in the access tunnel and cavern.

¡P         A boulder survey should be undertaken based on the likely PPV values that would result from the blasting process. Those boulders subject to the vibration higher than the allowable limit should be strengthened, removed, or constructed with boulder fence, prior to the commencement of blasting.

CSTW / Construction Phase

Contractor

¡Ô

¡Ô

 

 

-

 

Operation Phase

 

 

Nil

 

 

 

 

 

 

 

 

Ecological Impact (Terrestrial and Marine)

 

Construction Phase

8.8.2

7.2.1

Construction of access roads and other temporary works should be carefully designed (e.g. elevated road for crossing streams) to avoid / minimise habitat loss and fragmentation.

Project site ¡V areas access road / Pre-Construction Phase

Design team / Project Proponent

¡Ô

 

 

 

-

8.8.3

7.2.2

Minimise habitat loss to nearby habitats and associated wildlife by implementing the following mitigation measures: -

¡P      confining the works within the site boundary;

¡P      controlling access of site staff to avoid damage to the vegetation in surrounding areas; and

¡P      placement of equipment or stockpile in the existing disturbed / urbanised land within the site boundary of the Project to minimise disturbance to vegetated areas;

Project site / Construction Phase

Contractor

 

¡Ô

 

 

-

8.8.3

7.2.2

Reinstatement planting should be implemented upon the completion of construction works to minimise the ecological impact arising from the temporary habitat loss

Project Site (Main Portal Area / Secondary Portal Area / Access Road / Temporary Works Area) /Construction Phase

Project Proponent

¡Ô

¡Ô

 

¡Ô

 

8.8.2, 8.8.3 & 8.10

7.2.2

Detailed Vegetation Survey shall be conducted by a suitably qualified botanist / ecologist within the works area requiring vegetation clearance prior to commencement of works to identify plant species of conservation importance.

The potentially affected individuals shall be tagged and fenced off for preservation, and in the case of unavoidable loss, for transplantation to nearby suitable habitat(s).

Proposed works areas (Main Portal, Secondary Portal, Access Road) / Pre-Construction Phase

Project Proponent / Qualified botanist or ecologist

 

¡Ô

 

 

 

8.8.2, 8.8.3 & 8.10

7.3.1

A Protection and Transplantation Proposal including the subsequent monitoring visit for the affected plant species should be prepared and conducted by a suitably qualified local ecologist.  The Proposal should be submitted for approval at least one month before works commencement.

To review the performance of the transplantation exercise, monitoring of transplanted flora should be conducted monthly after the transplantation throughout the construction phase.  The parameters to be monitored should include the health condition and survival rate of the transplanted flora and presence of weedy species.  Any observations and recommendations should be reported in monthly EM&A reports

Recipient Site for transplanted species / Construction Phase

Project Proponent / Qualified botanist or ecologist

 

¡Ô

 

 

 

8.8.3

7.2.2

Mitigation measures should be implemented to control runoff from the construction site, as well as the adopting guidelines and good site practices for handling and disposal of construction discharges in order to minimise the potential indirect impact on the streams (particularly S2) resulting from site runoff.

Precautionary measures should also be implemented to minimise indirect impacts to the streams, such as isolating the work site by placing sandbags and silt curtains, covering up construction materials, debris and spoil to avoid being washed into the stream, and properly collecting and treating construction effluent and sewage.

Access Road on Nui Po Shan / Construction Phase

Contractor

 

¡Ô

 

 

ETWB TCW No. 5/2005

8.8.3

7.2.2

Implement good site practice to further minimise impacts from disturbance such as noise, air quality and water quality issues, such as: -

¡P      the use of quiet plant and EPD¡¦s QPME and the availability of British Standards 5228 has been considered;

¡P      the use of movable noise barrier;

¡P      the use of temporary noise screening structures or purpose-built temporary noise barriers;

¡P      install site hoarding as temporary noise barrier where construction works are undertaken;

¡P      only well-maintained plant should be operated on site and plant should be serviced regularly during the construction programme;

¡P      Mitigation measures stipulated in the ProPECC PN 1/94 ¡§Construction Site Drainage¡¨ should be complied to minimise water quality impact;

¡P      Installation of stand-by pump, emergency power supply and telemetry system to avoid sewage overflow and surcharge to sewerage system due to power/equipment failure.

Project site / Construction Phase

Contractor

 

¡Ô

 

 

-

8.8.3

7.2.2

Minimise groundwater infiltration during cavern construction with the following water control strategies:-

¡P      Probing Ahead: As a normal practice, the Contractor will undertake rigorous probing of the ground ahead of excavation works to identify zones of significant water inflow. The probe drilling results will be evaluated to determine specific grouting requirements in line with the tunnel / cavern advance. In such zones of significant water inflow that could occur as a result of discrete, permeable features, the intent would be to reduce overall inflow by means of cut-off grouting executed ahead of the tunnel / cavern advance;

¡P      Pre-grouting: Where water inflow quantities are excessive, pre-grouting will be required to reduce the water inflow into the tunnel / cavern. The pre-grouting will be achieved via a systematic and carefully specified protocol of grouting;

¡P      In principle, the grout pre-treatment would be designed on the basis of probe hole drilling ahead of the tunnel / cavern face;

¡P      The installation of waterproof lining would also be adopted after the formation of the tunnels and caverns.

Project site / Construction Phase

Contractor

 

¡Ô

 

 

-

8.8.3

7.2.2

In the event of excessive infiltration being observed as a result of the tunnelling or excavation works even after incorporation of the water control strategies, post-grouting should be applied as far as practicable as described below:

¡P      Post-grouting: Groundwater drawdown will be most likely due to inflows of water into the tunnel / cavern that have not been sufficiently controlled by the pre-grouting measures in high permeability area. Where this occurs post grouting will be undertaken before the lining is installed. Whilst unlikely to be required in significant measure, such a contingency should be allowed for reduction in permeability of the tunnel / cavern surround (by grouting) to limit inflow to acceptable levels.

The practical groundwater control measures stated above are proven technologies and have been extensively applied in other past projects. These measures or other similar methods, as approved by the Engineer to suit the works condition shall be applied to minimise the groundwater infiltration.

Project site / Construction Phase

Contractor

 

¡Ô

 

 

-

8.8.3

7.2.2

In case seepage of groundwater occurs, groundwater should be pumped out from works areas and discharged to the storm system via silt trap.  Uncontaminated groundwater from dewatering process should also be discharged to the storm system via silt removal facilities.

Project site / Construction Phase

Contractor

 

¡Ô

 

 

-

8.8.3

7.2.2

Mitigation measures recommended in the water quality impact assessment for controlling water quality impact will also serve to protect marine ecological resources from indirect impacts and ensure no unacceptable impact on marine ecological resources.

Relevant government departments including EPD, WSD and AFCD as well as key stakeholders for mariculture and fisheries in Tolo Harbour should be informed of the THEES maintenance / emergency discharge event prior to any discharge.

It is recommended that the temporary effluent bypass event and the THEES maintenance period should be shortened as far as possible. 

 

Tolo Harbour / Construction Phase

Contractor and Operator

 

¡Ô

 

 

-

 

Construction and Operation Phase

8.8.3

7.2.2

Overall reduction of glare during both construction and operation phase should be considered.  A balance between lighting for safety, and avoiding excessive lighting can be achieved through the use of directional lighting to avoid light spill into sensitive areas, and control/timing of lighting periods of some facilities, particularly at the secondary portal which lies approximately 200 m northwest of Ma On Shan Country Park.

Project site / Construction and Operation Phase

Contractor and Operator

 

¡Ô

¡Ô

 

-

8.8.3

7.2.2

During the decommissioning and demolition of the existing STSTW, the direction and lighting periods should be controlled during ardeid breeding season (March to August) to minimise the potential indirect impact on Penfold Park Egretry and the ardeids flying over the existing STSTW.  

Existing STSTW / Decommissioning / March to August

Contractor

 

 

 

¡Ô

-

8.10

7.3

It is anticipated that the construction of rock caverns would not have adverse impacts   on   groundwater   in   Nui   Po Shan.      Nonetheless,   surface   water level   or   groundwater   level   near   the caverns    will    be    closely    monitored during the construction and operation stage.

Project site /

Construction and Operation Phase

Contractor and Operator

 

¡Ô

¡Ô

 

-

 

Compensatory Planting

8.8.4& 8.10.1

7.2.3

Compensatory planting would be provided at main and secondary portal areas, and along the access road.

Main portal, secondary portal, and along access road

Project Proponent

¡Ô

¡Ô

 

 

DEVB TC(W) No. 7/2015

8.8.4 & 8.10.1

7.2.3

To facilitate successful planting, a detailed Woodland Compensation Plan should be prepared by local ecologists with at least 10 years relevant experience to form the basis of the proposed compensatory planting.  The Woodland Compensation Plan should include implementation details, management requirement, as well as monitoring requirements (e.g. frequency and parameters) of the compensatory planting area.  Approval of the Plan should be obtained from EPD at least three months before the prior to commencement of compensatory woodland planting.

Compensatory planting area (Main portal, secondary portal, and along access road) / pre-construction

Project Proponent

¡Ô

¡Ô

 

 

 

8.8.4 & 8.10.1

7.2.3

Upon the completion of planting, monitoring of the woodland compensation areas should be implemented, with maintenance works (e.g. irrigation, weeding, pruning, control of pests and diseases, replacement planting, repair of damage, etc.) conducted as necessary.

Compensatory planting area (Main portal, secondary portal, and along access road) / Operation

Project Proponent / CSTW Operator

 

 

¡Ô

 

 

 

Fisheries Impact

9.6

8.2

Potential impacts on fisheries resources and fishing operations arising from the Project have been avoided and minimised by construction of a connection pipes to the existing emergency outfall of STSTW by trenchless method underneath Shing Mun River with the least water quality impact.  In addition, the temporary effluent bypass event for THEES connection work would be synchronized within regular THEES maintenance.  Therefore, additional water quality impact and fisheries impact from changes of water quality have been avoided.  Furthermore, the THEES maintenance discharge would avoid the blooming season of algae (i.e. January to May) to minimise the potential water quality impacts.  It is recommended that any THEES maintenance period should be shortened as far as possible. 

Tolo Harbour /Construction and Operation Phase

Project Proponent / Contractor

¡Ô

¡Ô

 

 

-

9.6

8.2

Mitigation measures recommended in the water quality impact assessment for controlling water quality impact will also serve to protect fisheries from indirect impacts and ensure no unacceptable impact on fisheries resources and operations.   For more detailed mitigation measures regarding water quality refer to Sections 5.7.2 and 5.13.2 of the EIA Report.

Construction and Operation Phase

Contractor and Operator

 

¡Ô

¡Ô

 

-

9.6

8.2

Relevant government departments including EPD, WSD and AFCD as well as key stakeholders for mariculture and fisheries in Tolo Harbour should be informed prior to the THEES maintenance / emergency discharge events. 

Tolo Harbour / Construction and Operation Phase

Project Proponent

 

¡Ô

¡Ô

 

 

 

Landscape and Visual Impact

Table 10.10

-

CM1 - Preservation of Existing Vegetation

Construction Sites/ Construction Phase

Project Proponent

¡Ô

¡Ô

 

¡Ô

DEVB TCW No. 7/2015 and latest Guidelines on Tree Preservation during Development issued by GLTM Section of DEVB

Table 10.10

-

CM2 - Transplanting of Affected Trees

Construction Sites/ Construction Phase

Project Proponent

¡Ô

¡Ô

 

¡Ô

DEVB TCW No. 7/2015 and the latest Guidelines on Tree Transplanting issued by GLTM Section of DEVB

Table 10.10

-

CM3 - Compensatory Tree Planting

Construction Sites/ Construction Phase

Project Proponent

¡Ô

¡Ô

 

¡Ô

DEVB TCW No. 7/2015

Table 10.10

-

CM4 - Control of Night-time Lighting Glare

Construction Sites/ Construction Phase

Project Proponent

¡Ô

¡Ô

 

¡Ô

 

Table 10.10

-

CM5 - Erection of Decorative Screen Hoarding

Construction Sites/ Construction Phase

Project Proponent

¡Ô

¡Ô

 

¡Ô

 

Table 10.10

-

CM6 - Management of Construction Activities and Facilities

Construction Sites/ Construction Phase

Project Proponent

¡Ô

¡Ô

 

¡Ô

 

Table 10.10

-

CM7 - Reinstatement of Temporarily Disturbed Landscape Areas

Construction Sites/ Construction Phase

Project Proponent

¡Ô

¡Ô

 

¡Ô

 

Table 10.11

-

OM1 - Tree and Shrub Planting at the Temporary Project Magazine Site after Completion of Engineering Works

Temporary Project Magazine Site / Operation Phase

Project Proponent

¡Ô

¡Ô

¡Ô

 

 

Table 10.11

-

OM2 - Aesthetically pleasing design of Aboveground Structures

Tunnel Portals, Administration Building, Ventilation Buildings, Electrical Substations and Ventilation Shaft / Operation Phase

Project Proponent

¡Ô

¡Ô

¡Ô

 

 

Table 10.11

-

OM3 - Aesthetically pleasing design of Highways Structures

Access Road to Ventilation Shaft / Operation Phase

Highways Department

¡Ô

¡Ô

¡Ô

 

 

Table 10.11

-

OM4 - Reprovision of Cycle Track

Cycle track / Operation Phase

Highways Department

¡Ô

¡Ô

¡Ô

 

 

Table 10.11

-

OM5 - Provision of Green Roof

Administration Building and Ventilation Buildings / Operation Phase

Project Proponent

¡Ô

¡Ô

¡Ô

 

 

Table 10.11

-

OM6 - Provision of Buffer Planting

Main and Secondary Portal Areas / Operation Phase

Project Proponent

¡Ô

¡Ô

¡Ô

 

 

Table 10.11

-

OM7 - Hydroseeding on the disturbed ground surface after demolition works prior to future redevelopment of the existing STSTW

Existing STSTW / Operation Phase

Lands Department (LandsD) or future development agent in existing STSTW

¡Ô

¡Ô

¡Ô

 

 

Table 10.11

-

OM8 - Woodland Mix Planting on Soil Slopes

Soil Slopes / Operation Phase

Project Proponent

¡Ô

¡Ô

¡Ô

 

 

 

Cultural Heritage Impact

11.5.1.1

10.1.1

No potential direct or indirect impact to cultural heritage resource is anticipated, and therefore no mitigation measures are required.

N/A

N/A

 

 

 

 

EIAO

EIAO-TM

Antiquities and Monuments Ordinance

Guidelines for Cultural Heritage Impact Assessment

 

Wastes Management Implications

12.6.2

11.2.2

Appropriate waste handling, transportation and disposal methods for all waste arising generated during the construction works for the Project should be implemented to ensure that construction wastes do not enter the nearby streams or drainage channel.

It is anticipated that adverse impacts would not arise on the construction site, provided that good site practices are strictly followed.  Recommendations for good site practices during the construction activities include:

      Nomination of approved personnel, such as a site manager, to be responsible for good site practices, and making arrangements for collection of all wastes generated at the site and effective disposal to an appropriate facility.

      Training of site personnel in proper waste management and chemical waste handling procedures.

      Provision of sufficient waste reception/ disposal points, of a suitable vermin-proof design that minimises windblown litter.

      Arrangement for regular collection of waste for transport off-site and final disposal.

      Appropriate measures to minimise windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers.

      Regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors.

      A recording system for the amount of wastes generated, recycled and disposed (including the disposal sites) should be proposed.

      A Waste Management Plan should be prepared and should be submitted to the Engineer for approval.  One may make reference to ETWB TCW No. 19/2005 for details.

In order to monitor the disposal of C&D material at landfills and public filling areas, as appropriate, and to control fly tipping, a trip-ticket system should be included as one of the contractual requirements to be implemented by an Environmental Team undertaking the Environmental Monitoring and Audit work.  One may make reference to DEVB TCW No.6/2010 for details.

Project Site Area / Construction Phase

Contractor

 

¡Ô

 

¡Ô

Waste Disposal Ordinance

12.6.3

11.2.3

Good management and control of construction site activities / processes can minimise the generation of waste.  Waste reduction is best achieved at the planning and design stage, as well as by ensuring the implementation of good site practices.  Recommendations to achieve waste reduction include:

      Segregate and store different types of construction related waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal.

      Provide separate labelled bins to segregate recyclable waste such as aluminium cans from other general refuse generated by the work force, and to encourage collection by individual collectors.

      Any unused chemicals or those with remaining functional capacity shall be recycled.

      Maximising the use of reusable steel formwork to reduce the amount of C&D material.

      Prior to disposal of C&D waste, it is recommended that wood, steel and other metals shall be separated for re-use and / or recycling to minimise the quantity of waste to be disposed of to landfill.

      On-site crushing and sorting facilities are being considered to reduce the rock size to fulfill the size requirements from relevant waste collection / transfer / disposal facilities;

      Adopt proper storage and site practices to minimise the potential for damage to, or contamination of, construction materials.

      Plan the delivery and stock of construction materials carefully to minimise the amount of surplus waste generated.

      Adopt pre-cast construction method instead of cast-in-situ method for construction of concrete structures as much as possible; and

      Minimise over ordering of concrete, mortars and cement grout by doing careful check before ordering.

In addition to the above measures, other specific mitigation measures are recommended below to minimise environmental impacts during handling, transportation and disposal of wastes.

Project Site Area / Construction Phase

Contractor

 

¡Ô

 

¡Ô

Waste Disposal Ordinance

12.6.4

11.2.4

Storage of materials on site may induce adverse environmental impacts if not properly managed, recommendations to minimise the impacts include:

      Waste, such as soil, should be handled and stored well to ensure secure containment, thus minimising the potential of pollution;

      Maintain and clean storage areas routinely;

      Stockpiling area should be provided with covers as much as practicable and water spraying system to prevent materials from wind-blown or being washed away; and

      Different locations should be designated to stockpile each material to enhance reuse.

Project Site Area / Construction Phase

Contractor

 

¡Ô

 

¡Ô

-

12.6.4

11.2.4

Licensed waste haulers should be employed for the collection and transportation of waste generated. The following measures should be enforced to minimise the potential adverse impacts:

      Remove waste in timely manner;

      Waste collectors should only collect wastes prescribed by their permits;

      Impacts during transportation, such as dust and odour, should be mitigated by the use of covered trucks or in enclosed containers;

      Obtain relevant waste disposal permits from the appropriate authorities, in accordance with the Waste Disposal Ordinance (Cap. 354), Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 345) and the Land (Miscellaneous Provisions) Ordinance (Cap. 28);

      Waste should be disposed of at licensed waste disposal facilities; and

      Maintain records of quantities of waste generated, recycled and disposed.

Project Site Area / Construction Phase

Contractor

 

¡Ô

 

¡Ô

Waste Disposal Ordinance

 

Waste Disposal (Charges for Disposal of Construction Waste) Regulation

 

Land (Miscellaneous Provisions) Ordinance

12.6.4

11.2.4

Land transport will be used for transportation of excavated and stockpile materials.  It is expected there will be 1260 vehicles per day for transporting waste during peak construction phase.  The tentative transportation routings for the disposal of various types of wastes are shown in Table 12.4.  The transportation routing may be changed subject to the traffic conditions.  Nevertheless, it is anticipated that there is no adverse impact from the waste during transportation with the implementation of appropriated measures (e.g. using water-tight containers and covered trucks).

Transportation Route of Waste / Construction Phase

Contractor

 

¡Ô

 

 

-

12.6.4

11.2.4

In order to monitor the disposal of C&D materials at PFRFs and landfills and to control fly-tipping, a trip-ticket system should be established in accordance with DEVB TCW No. 6/2010.  A recording system for the amount of waste generated, recycled and disposed, including the disposal sites, should also be set up.  Warning signs should be put up to remind the designated disposal sites. Close-circuited television should be installed at the vehicular entrance and exit of the site as additional measures to prevent fly-tipping.

Project Site Area / Construction Phase

Contractor

 

¡Ô

 

¡Ô

DEVB TCW No. 6/2010

12.6.4

11.2.5

In addition to the above general measures, other specific mitigation measures on handling the C&D materials and materials generated from site formation and demolition work are recommended below, which should form the basis of the WMP to be prepared by the contractor(s) in construction phase.

Project Site Area / Construction Phase

Contractor

 

¡Ô

 

¡Ô

Technical Circular (Works) No. 19/2005 Environmental Management on Construction Site

12.6.5

11.2.5

In order to minimise the impact resulting from collection and transportation of C&D materials for off-site disposal, the excavated material arising from site formation and foundation works should be reused on-site as backfilling material and for landscaping works as far as practicable. Other mitigation requirements are listed below:

      A WMP, which becomes part of the EMP, should be prepared in accordance with ETWB TCW No.19/2005;

      A recording system for the amount of wastes generated, recycled and disposed (including the disposal sites) should be adopted for easy tracking; and

      In order to monitor the disposal of C&D materials at public filling facilities and landfills and to control fly-tipping, a trip-ticket system should be adopted (refer to DEVB TCW No. 6/2010).

It is recommended that specific areas should be provided by the Contractors for sorting and to provide temporary storage areas (if required) for the sorted materials. 

Project Site Area / Construction Phase

Contractor

 

¡Ô

 

¡Ô

Waste Disposal Ordinance

ETWB TCW No.19/2005

DEVB TCW No. 6/2010

12.6.5

11.2.5

The Contactor should prepare and implement an EMP in accordance with ETWB TCW No.19/2005, which describes the arrangements for avoidance, reuse, recovery, recycling, storage, collection, treatment and disposal of different categories of waste to be generated from construction activities.  Such a management plan should incorporate site specific factors, such as the designation of areas for segregation and temporary storage of reusable and recyclable materials.  The EMP should be submitted to the Engineer for approval.  The Contractor should implement waste management practices in the EMP throughout the construction stage of the Project.  The EMP should be reviewed regularly and updated by the Contractor, preferably on a monthly basis.

Project Site Area / Construction Phase

Contractor

 

¡Ô

 

 

ETWB TCW No.19/2005

12.6.5

11.2.5

All surplus C&D materials arising from or in connection with construction works should become the property of the Contractor when it is removed unless otherwise stated.  The Contractor would be responsible for devising a system to work for on-site sorting of C&D materials and promptly removing all sorted and process materials arising from the construction activities to minimise temporary stockpiling on-site. The system should be included in the EMP identifying the source of generation, estimated quantity, arrangement for on-site sorting, collection, temporary storage areas and frequency of collection by recycling Contractors or frequency of removal off-site.

Project Site Area / Construction Phase

Contractor

 

¡Ô

 

¡Ô

-

12.6.6

11.2.6

The practices of good housekeeping for CSTW listed below should be followed to ameliorate any odour impact from handling, collection, transportation and disposal of sludge:

      Screens should be cleaned regularly to remove any accumulated organic debris

      Grit and screening transfer systems should be flushed regularly with water to remove organic debris and grit

      Grit and screened materials should be transferred to closed containers

      Scum and grease collection wells and troughs should be emptied and flushed regularly to prevent putrefaction of accumulated organics

      Skim and remove floating solids and grease from primary clarifiers regularly

      Frequent sludge withdrawal from tanks is necessary to prevent the production of gases

      Sludge should be transported to the STF by water-tight containers to avoid Hydrogen Sulphide (H2S)/odour emission and ingress of water into the containers which would lower the sludge dryness during transportation

      Sludge cake should be transferred to closed containers

      Sludge containers should be flushed with water regularly

      Sludge trucks and containers should be washed thoroughly before leaving the CSTW to avoid any odour nuisance during transportation

Operation Phases

Operator

 

 

¡Ô

 

Waste Disposal Ordinance

12.6.6

11.2.6

In addition, all wastewater generated from the sludge dewatering process and all contaminated water from the cleaning operations recommended for odour control will be diverted to the relocated STSTW for proper treatment.

Operation Phases

Operator

 

 

¡Ô

 

Waste Disposal Ordinance

12.6.7

11.2.7

If chemical wastes are produced at the construction site or during operation, the Contractor during construction or the operator during operation will be required to register with the EPD as a chemical waste producer and to follow the guidelines stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes. Good quality containers compatible with the chemical wastes should be used, and incompatible chemicals should be stored separately. Appropriate labels should be securely attached on each chemical waste container indicating the corresponding chemical characteristics of the chemical waste, such as explosive, flammable, oxidising, irritant, toxic, harmful, corrosive, etc. The Contractor shall use a licensed collector to transport and dispose of the chemical wastes, to the licensed Chemical Waste Treatment Centre, or other licensed facilities, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.

Construction and Operation Phases

Contractor / Operator

 

¡Ô

¡Ô

 

Waste Disposal (Chemical Waste) (General) Regulation

 

Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes

12.6.8

11.2.8

Recycling of waste paper, aluminium cans and plastic bottles should be encouraged, it is recommended to place clearly labelled recycling bins at designated locations which could be accessed conveniently.  Other general refuse should be separated from chemical and industrial waste by providing separated bins for storage to maximise the recyclable volume.

Construction and Operation Phases

Contractor / Operator

 

¡Ô

¡Ô

 

Public Health and Municipal Services Ordinance (Cap.132)

12.6.8

11.2.8

A reputable licensed waste collector should be employed to remove general refuse on a daily basis to minimise odour, pest and litter impacts.

Construction and Operation Phases

Contractor / Operator

 

¡Ô

¡Ô

 

Public Health and Municipal Services Ordinance (Cap. 132)

 

Health Impact

-

-

Not applicable.

 

 

 

 

 

 

 

 

 

<End of Section 16>

 



[1] Des = Design; C = Construction; O = Operation; Dec = Decommissioning