TABLE OF CONTENTS

Page

3              Air Quality Impact. 3-3

3.1          Introduction. 3-3

3.2          Environmental Legislations, Standards and Guidelines. 3-3

3.3          Description of Environment 3-4

3.4          Identification of Air Sensitive Receivers. 3-5

3.5          Identification of Pollutant Sources. 3-8

3.6          Assessment Methodology. 3-11

3.7          Prediction and Evaluation of Environmental Impacts. 3-24

3.8          Mitigation of Adverse Environmental Impacts. 3-35

3.9          Evaluation of Residual Impacts. 3-46

3.10        Environmental Monitoring and Audit 3-46

3.11        Conclusion. 3-47

 

LIST OF TABLES

Table 3.1         Hong Kong Air Quality Objectives. 3-4

Table 3.2         Average Concentrations of Pollutant in the Recent Five Years (Year 2010 ¡V 2014) at Sha Tin EPD Air Quality Monitoring Station. 3-5

Table 3.3         Representative Air Sensitive Receivers affected by Construction of Relocated STSTW and Demolition of Existing STSTW.. 3-6

Table 3.4         Representative Air Sensitive Receivers in the vicinity of Relocated STSTW for Operational Odour Impact Assessment 3-7

Table 3.5         Rock Crushing Operation with Dust Control Measures. 3-12

Table 3.6         Emission Factor for Dust Emitting Construction Activity. 3-13

Table 3.7         Particle Size Distribution of Various Processes. 3-14

Table 3.8         Summary of Measured Odour Emission Rate in Existing STSTW.. 3-18

Table 3.9         Odour Emission Rates for the Relocated STSTW.. 3-19

Table 3.10       Summary of Required Odour Removal Efficiency for Deodorization System.. 3-23

Table 3.11       Design Parameter of the Ventilation Shaft 3-24

Table 3.12       Conversion Factors to 5-second Mean Concentration for Point Source. 3-25

Table 3.13       Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Construction of Relocated STSTW) (Unmitigated Scenario) 3-25

Table 3.14       Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Demolition of Existing STSTW) (Unmitigated Scenario) 3-28

Table 3.15       Predicted Operational Odour Impact on Representative Air Sensitive Receivers (Interim Stage) 3-33

Table 3.16       Predicted Operational Odour Impact on Representative Air Sensitive Receivers (Ultimate Stage) 3-34

Table 3.17       Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Construction of Relocated STSTW) (Tier 1, Mitigated Scenario) 3-36

Table 3.18       Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Demolition of Existing STSTW) (Tier 1, Mitigated Scenario) 3-40

Table 3.19       Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Construction of Relocated STSTW) (Tier 2a, Mitigated Scenario) 3-44

Table 3.20       Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Construction of Relocated STSTW) (Tier 2b, Mitigated Scenario) 3-44

Table 3.21       Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Demolition of Existing STSTW) (Tier 2, Mitigated Scenario) 3-46

 

 LIST OF FIGURES

60334056/EIA/3.01         Representative Air Sensitive Receivers for Construction Dust Impact From Relocated STSTW

60334056/EIA/3.02         Representative Air Sensitive Receivers for Operational Odour Impact From Relocated STSTW

60334056/EIA/3.03         Maximum Cumulative Hourly TSP Concentration (mg/m3) at 1.5 mAG (Construction of CSTW) (Unmitigated)

60334056/EIA/3.04         10th Highest Cumulative Daily RSP Concentration (mg/m3) at 1.5 mAG (Construction of CSTW) (Unmitigated)

60334056/EIA/3.05         10th Highest Cumulative Daily FSP Concentration (mg/m3) at 1.5 mAG (Construction of CSTW) (Unmitigated)

60334056/EIA/3.06         Cumulative Annual RSP Concentration (mg/m3) at 1.5 mAG (Construction of CSTW) (Unmitigated Scenario)

60334056/EIA/3.07         Cumulative Annual FSP Concentration (mg/m3) at 1.5 mAG (Construction of CSTW) (Unmitigated Scenario)

60334056/EIA/3.08         Maximum Cumulative Hourly TSP Concentration (mg/m3) at 1.5 mAG (Construction of CSTW) (Tier 1, Mitigated Scenario)

60334056/EIA/3.09         10th Highest Cumulative Daily RSP Concentration (mg/m3) at 1.5 mAG (Construction of CSTW) (Tier 1, Mitigated Scenario)

60334056/EIA/3.10         10th Highest Cumulative Daily FSP Concentration (mg/m3) at 1.5 mAG (Construction of CSTW) (Tier 1, Mitigated Scenario)

60334056/EIA/3.11         Maximum Cumulative Hourly TSP Concentration (mg/m3) at 1.5 mAG (Construction of CSTW) (Tier 2a, Mitigated Scenario)

60334056/EIA/3.12         Maximum Cumulative Hourly TSP Concentration (mg/m3) at 1.5 mAG (Construction of CSTW) (Tier 2b, Mitigated Scenario)

60334056/EIA/3.13         10th Highest Cumulative Daily RSP Concentration (mg/m3) at 1.5 mAG (Construction of CSTW) (Tier 2A, Mitigated Scenario)

60334056/EIA/3.14         Cumulative Annual RSP Concentration (mg/m3) at 1.5 mAG (Construction of CSTW) (Mitigated Scenario)

60334056/EIA/3.15         Cumulative Annual FSP Concentration (mg/m3) at 1.5 mAG (Construction of CSTW) (Mitigated Scenario)

60334056/EIA/3.16         Maximum Cumulative Hourly TSP Concentration (mg/m3) at 1.5 mAG (Demolition of Existing STSTW) (Unmitigated Scenario)  

60334056/EIA/3.17         10th Highest Cumulative Daily RSP Concentration (mg/m3) at 1.5 mAG (Demolition of Existing STSTW) (Unmitigated Scenario)   

60334056/EIA/3.18         10th Highest Cumulative Daily FSP Concentration (mg/m3) at 1.5 mAG (Demolition of Existing STSTW) (Unmitigated Scenario)  

60334056/EIA/3.19         Cumulative Annual RSP Concentration (mg/m3) at 1.5 mAG (Demolition of Existing STSTW) (Unmitigated Scenario)  

60334056/EIA/3.20         Cumulative Annual FSP Concentration (mg/m3) at 1.5 mAG (Demolition of Existing STSTW) (Unmitigated Scenario)  

60334056/EIA/3.21         Maximum Cumulative Hourly TSP Concentration (mg/m3) at 1.5 mAG (Demolition of Existing STSTW) (Tier 1, Mitigated Scenario)

60334056/EIA/3.22         10th Highest Cumulative Daily RSP Concentration (mg/m3) at 1.5 mAG (Demolition of Existing STSTW) (Tier1, Mitigated Scenario)

60334056/EIA/3.23         10th Highest Cumulative Daily FSP Concentration (mg/m3) at 1.5 mAG (Demolition of Existing STSTW) (Tier1, Mitigated Scenario)

60334056/EIA/3.24         Maximum Cumulative Hourly TSP Concentration (mg/m3) at 1.5 mAG (Demolition of Existing STSTW) (Tier 2, Mitigated Scenario)

60334056/EIA/3.25         Cumulative Annual RSP Concentration (mg/m3) at 1.5 mAG (Demolition of Existing STSTW) (Mitigated Scenario)  

60334056/EIA/3.26         Cumulative Annual FSP Concentration (mg/m3) at 1.5 mAG (Demolition of Existing STSTW) (Mitigated Scenario)  

60334056/EIA/3.27         Contours of 5-Second Average Odour Concentration in OU/m3 at 1.5 mAG (Interim Stage)

60334056/EIA/3.28         Contours of 5-Second Average Odour Concentration in OU/m3 at 30 mAG (Interim Stage)

60334056/EIA/3.29         Contours of 5-Second Average Odour Concentration in OU/m3 at 100 mAG (Interim Stage)

60334056/EIA/3.30         Contours of 5-Second Average Odour Concentration in OU/m3 at 120 mAG (Interim Stage)

60334056/EIA/3.31         Contours of 5-Seconds Average Odour Concentration in OU/m3 at 1.5mAG (Ultimate Stage)

60334056/EIA/3.32         Contours of 5-Seconds Average Odour Concentration in OU/m3 at 30 mAG (Ultimate Stage)

60334056/EIA/3.33         Contours of 5-Seconds Average Odour Concentration in OU/m3 at 100 mAG (Ultimate Stage)

60334056/EIA/3.34         Contours of 5-Seconds Average Odour Concentration in OU/m3 at 120 mAG (Ultimate Stage)

 LIST OF APPENDICES

Appendix 3.01             Details of Representative Air Sensitive Receivers

Appendix 3.02a           Construction of CSTW - Calculation of Dust Emission Source (Short-term Prediction (Tier 1))

Appendix 3.02b           Construction of CSTW - Calculation of Dust Emission Source (Short-term Prediction (Tier 2))

Appendix 3.02c           Construction of CSTW - Calculation of Dust Emission Source (Annual Prediction)

Appendix 3.02d           Construction of CSTW - Dust Emission Source Listing

Appendix 3.02e           Demolition of Existing STSTW - Calculation of Dust Emission Source

Appendix 3.02f            Calculation of Dust Suppression Efficiency by Watering

Appendix 3.03             Traffic Data of Year 2022 and 2027

Appendix 3.04             Calculation of Vehicular Emission Source

Appendix 3.05             Odour Survey for Sha Tin Cavern Sewage Treatment Works

Appendix 3.06             Calculation of Odour Emission Rate of CSTW

Appendix 3.07             Photographs of Concerned Areas during Construction Phase

 

3                      Air Quality Impact

3.1                  Introduction

3.1.1.1           This section presents the framework of assessing potential air quality impacts arising from construction and operation of the Project.  The potential air quality impacts are expected to be dust nuisance during the construction phase of the Project and odour nuisance during the operation phase of the relocated STSTW.  Representative Air Sensitive Receivers (ASRs) are identified for the air quality assessment.  Appropriate mitigation measures are proposed to alleviate the potential air quality impact if necessary.

 

3.2                  Environmental Legislations, Standards and Guidelines

3.2.1.1           The criteria for evaluating air quality impacts and the guidelines for air quality assessment are laid out in Annex 4 and Annex 12 of the EIAO-TM as well as the requirements set out under Clause 3.4.1 of the EIA Study Brief.

3.2.2               Air Quality Objectives & Technical Memorandum on EIA Process

3.2.2.1           The Air Pollution Control Ordinance (APCO) provides the statutory authority for controlling air pollutants from a variety of sources.  The Hong Kong Air Quality Objectives (AQOs), which stipulate the maximum allowable concentrations over specific periods for typical pollutants, should be met.  The relevant AQOs are listed in Table 3.1.

Table 3.1       Hong Kong Air Quality Objectives

Pollutants

Averaging Time

Concentration Limit (µg/m3)(1)

Number of Exceedance Allowed

Respirable Suspended Particulates (PM10)(2)

24-hour

100

9

Annual

50

N/A

Fine Suspended Particulates (PM2.5)(3)

24-hour

75

9

Annual

35

N/A

Notes:

(1)   Measured at 293K and 101.325kPa

(2)   Suspended particulates in air with a nominal aerodynamic diameter of 10µm or smaller.

(3)   Suspended particulates in air with a nominal aerodynamic diameter of 2.5µm or smaller.

 

3.2.2.2           Apart from AQOs, the limit of hourly Total Suspended Particulates (TSP) concentration should not exceed 500 µg/m3 (measured at 25¢XC and one atmosphere) for construction dust impact assessment according to Annex 4 of EIAO-TM.

3.2.2.3           In accordance with Annex 4 of EIAO-TM, the limit of 5 odour units based on an averaging time of 5 seconds for odour prediction assessment should not be exceeded at any ASRs.

3.2.3               Air Pollution Control (Construction Dust) Regulation

3.2.3.1           Notifiable and regulatory works are under the control of Air Pollution Control (Construction Dust) Regulation.  This Project is expected to include notifiable works (foundation and superstructure construction and demolition) and regulatory works (temporary stockpile, dusty material handling, excavation and blasting).  Contractors and site agents are required to inform Environmental Protection Department (EPD) and adopt dust reduction measures to minimize dust emission, while carrying out construction works, to the acceptable level.

 

3.3                  Description of Environment

3.3.1.1           The Project is to construct a new STW at Nui Po Shan of A Kung Kok on the southern side of Shing Mun River to replace the existing STSTW and to demolish the existing STSTW upon full operation of the relocated STSTW.  The study area includes Sha Tin area and Ma On Shan area in vicinity of the relocated STSTW and the existing STSTW.

3.3.1.2           The study area in Sha Tin and Ma On Shan area is a new town area with mainly residential buildings and educational institutes.  Existing air quality in the study area is affected by emissions from the existing traffic from Tolo Highway and Tate¡¦s Cairn Highway.

3.3.1.3           The nearest EPD fixed air quality monitoring station is located at Sha Tin Government Secondary School. The annual average monitoring data recorded at EPD¡¦s Sha Tin air quality monitoring station has shown steady trend of pollutants¡¦ concentration in the past five years. The recent five years (2010 - 2014) annual average concentrations are summarized in Table 3.2.

Table 3.2       Average Concentrations of Pollutant in the Recent Five Years (Year 2010 ¡V 2014) at Sha Tin EPD Air Quality Monitoring Station

Pollutant

2014

2013

2012

2011

2010

Mean

Maximum Hourly TSP Concentration (µg/m3)

N/A

136

110

161

135

135.5

Annual Average TSP Concentration (µg/m3)

N/A

57

54

66

67

61.0

10th Highest Daily Average PM10 Concentration (µg/m3)

93

107

85

95

96

95.1

Annual Average PM10 Concentration (µg/m3)

39

42

39

47

45

42.4

10th Highest Daily Average PM2.5 Concentration (µg/m3)

67

85

62

N/A

N/A

71.3

Annual Average Concentration (µg/m3)PM2.5

25

29

26

N/A

N/A

26.7

Remark:

(1)   Monitoring data of TSP in 2014 is not available.

(2)   2nd highest hourly TSP in 2010 is considered because the highest record is affected by a dust plume originated from northern part of China (Air Quality in Hong Kong 2014, HKEPD)

(3)   Monitoring of Fine Suspended Particulates (FSP) commenced since Nov 2011. No monitoring data is available before 2011.

 

3.4                  Identification of Air Sensitive Receivers

3.4.1.1           In accordance with Annex 12 of the EIAO-TM, domestic premises, hotel, hostel, hospital, clinic, nursery, temporary housing accommodation, school, educational institution, office, factory, shop, shopping centre, place of public worship, library, court of law, sports stadium or performing arts centre are considered as ASRs. 

3.4.1.2           Potentially affected ASRs by construction dust arisen from the construction of relocated STSTW, emergency outfall and demolition of the existing STSTW are generally identified within 500m study boundary from the Project boundary. 

3.4.1.3           Regarding operational odour impact by relocated STSTW, potentially affected ASRs are generally identified within 500m study boundary from the ventilation shaft, portal facilities and relocated STSTW site.  Due to major public concern on the odour impact on the local community, ASRs outside the 500m study boundary are also identified to investigate the impact in a longer range.

3.4.1.4           The representative ASRs which would likely be affected by the construction of relocated STSTW, sewage bypass outfall, temporary explosives magazine site, and decommissioning and demolition of the existing STSTW and temporary explosives magazine site are identified and given in Table 3.3 below. Their locations are illustrated in Figure No. 60334056/EIA/3.01 and their coordinates are presented in Appendix 3.01.

Table 3.3            Representative Air Sensitive Receivers affected by Construction of Relocated STSTW and Demolition of Existing STSTW

ASRs

Description

Land Use

Shortest Distance from Project Work Site Boundary

Assessment Height Above Ground (mAG)

ASR1

Chevalier Garden

Residential

225

1.5, 5, 10, up to 80 with 10m interval

ASR2

Wellborn Kindergarten

Education

95

1.5, 5, 10, 20

ASR3

Hay Nien Primary School

Education

140

1.5, 5, 10, 20, 30

ASR4

Ma On Shan Tsung Tsin Secondary School

Education

130

1.5, 5, 10, 20, 30

ASR5

Tai Shui Hang Village

Residential

240

1.5, 5, 10

ASR6

Block H, Kam Tai Court

Residential

95

1.5, 5, 10, up to 120 with 10m interval

ASR7

S.K.H. Ma On Shan Holy Spirit Primary School

Education

110

1.5, 5, 10, 20, 30

ASR8

Ah Kung Kok Fishermen Village

Residential/Retail

170

1.5, 5, 10

ASR9

China Hong Kong Mountaineering and Climbing Union

Societal/Storage

375

1.5, 5, 10

ASR10

Breakthrough Youth Village

Religion/Charity

360

1.5, 5, 10, 20, 30

ASR11

Cheshire Home Sha Tin

Hospital

475

1.5, 5, 10, 20

ASR12

The Neighbourhood Advice-Action Council Harmony Manor

Mental Health Hospital

70

1.5, 5, 10, 20

ASR13

Shing Mun Springs Rehabilitation Centre

Rehabilitation Centre

100

1.5, 5, 10, 20

ASR14

Mui Tsz Lam Village

Residential

1110

1.5, 5, 10

ASR15

Ma On Shan Park / Promenade

Recreational Use

55

1.5

ASR16

Block F, Kam Tai Court

Residential

165

1.5, 5, 10, up to 120 with 10m interval

ASR17

Sausalito

Residential

390

1.5, 5, 10, up to 90 with 10m interval

ASR18

Ocean View

Residential

450

1.5, 5, 10, up to 100 with 10m interval

ASR19

Marine Police Outer Waters District Headquarters and Marine Police North Police Station

Government Office

70

1.5, 5, 10, 20

ASR20

Ah Kung Kok Fishermen Village

Residential/Retail

390

1.5, 5, 10

ASR21

Seaview Villa

Residential

160

1.5, 5, 10

ASR22

Racecourse Gardens

Residential

260

1.5, 5, 10, up to 50 with 10m interval

 

3.4.1.5           The representative ASRs which would likely be affected by potential operational odour impact from relocated STSTW have been identified and are given in Table 3.4 below.  Their locations are illustrated in Figure No. 60334056/EIA/3.02 and their coordinates are presented in Appendix 3.01.

Table 3.4            Representative Air Sensitive Receivers in the vicinity of Relocated STSTW for Operational Odour Impact Assessment

ASRs

Description

Land Use

Shortest Distance from the Ventilation Shaft/Portal /Caverns (m)

Assessment Height Above Ground (mAG)

ASR1

Chevalier Garden

Residential

810

1.5, 5, 10, up to 80 with 10m interval

ASR1a

Chevalier Garden (Block 17)

Residential

800

1.5, 5, 10, up to 80 with 10m interval

ASR1b

Chevalier Garden (Block 6)

Residential

870

1.5, 5, 10, up to 70 with 10m interval

ASR1c

Chevalier Garden (Block 1)

Residential

810

1.5, 5, 10, up to 70 with 10m interval

ASR2

Wellborn Kindergarten

Education

800

1.5, 5, 10, 20

ASR3

Hay Nien Primary School

Education

940

1.5, 5, 10, 20, 30

ASR4

Ma On Shan Tsung Tsin Secondary School

Education

970

1.5, 5, 10, 20, 30

ASR5

Tai Shui Hang Village

Residential

1000

1.5, 5, 10

ASR6

Block H, Kam Tai Court

Residential

1100

1.5, 5, 10, up to 120 with 10m interval

ASR7

S.K.H. Ma On Shan Holy Spirit Primary School

Education

1130

1.5, 5, 10, 20, 30

ASR8

Ah Kung Kok Fishermen Village

Residential/Retail

800

1.5, 5, 10

ASR9

China Hong Kong Mountaineering and Climbing Union

Societal/Storage

800

1.5, 5, 10

ASR10

Breakthrough Youth Village

Religion/Charity

420

1.5, 5, 10, 20, 30

ASR11

Cheshire Home Sha Tin

Hospital

530

1.5, 5, 10, 20

ASR12

The Neighbourhood Advice-Action Council Harmony Manor

Mental Health Hospital

320

1.5, 5, 10, 20

ASR13

Shing Mun Springs Rehabilitation Centre

Rehabilitation Centre

420

1.5, 5, 10, 20

ASR14

Mui Tsz Lam Village

Residential

1360

1.5, 5, 10

ASR15

Ma On Shan Park / Promenade

Recreational Use

1180

1.5

ASR16

Block F, Kam Tai Court

Residential

1200

1.5, 5, 10, up to 120 with 10m interval

ASR17

Sausalito

Residential

1650

1.5, 5, 10, up to 90 with 10m interval

ASR18

Ocean View

Residential

1970

1.5, 5, 10, up to 100 with 10m interval

ASR19

Marine Police Outer Waters District Headquarters and Marine Police North Police Station

Government Office

1720

1.5, 5, 10, 20

ASR20

Ah Kung Kok Fishermen Village

Residential

800

1.5, 5, 10

ASR21

Seaview Villa

Residential

1730

1.5, 5, 10

ASR22

Racecourse Gardens

Residential

1610

1.5, 5, 10, up to 50 with 10m interval

ASR23

Pictoria Garden

Residential

1230

1.5, 5, 10, up to 70 with 10m interval

ASR24

Kam On Garden

Residential

1860

1.5, 5, 10

ASR25

Royal Ascot

Residential

1950

1.5, 5, 10, up to 120 with 10m interval

ASR26

Sha Tin Hospital

Hospital

900

1.5, 5, 10, up to 40 with 10m interval

ASR27

Garden Vista

Residential

1240

1.5, 5, 10, up to 80 with 10m interval

ASR28

Topsail Plaza

Industrial

1020

1.5, 5, 10, up to 50 with 10m interval

ASR29

Hong Kong Baptist University Affiliated School Wong Kam Fai Secondary School

Education

1020

1.5, 5, 10, up to 50 with 10m interval

ASR30

The Castello

Residential

1050

1.5, 5, 10, up to 120 with 10m interval

ASR31

Planned ASR at existing STSTW site

Residential & Recreational

1400

1.5, 5, 10, up to 120 with 10m interval

 

3.5                  Identification of Pollutant Sources

3.5.1               Construction Phase

3.5.1.1           The identified potential air quality impacts during construction phase of the relocation of STSTW (including water reclamation facilities) would arise from fugitive dust emissions generated by various construction activities, including excavation, rock crushing, blasting operation, portal construction, material handling, transportation and removal, construction trucks, stockpiling, wind erosion etc, at all land-based works areas including the existing and relocated STSTW, accesses to and from the relocated STSTW and temporary stockpile area at Area 73.  A temporary explosives magazine site would also be provided at A Kung Kok Shan.  Potential dust emission would be generated from construction of this temporary explosives magazine including construction of access road from A Kung Kok Shan Road to this temporary magazine site, site formation and construction of explosives compound structures.  Once the construction works for the relocated STSTW is completed, the temporary explosives magazine site would be decommissioned but it is expected limited dust impact generated from demolition of the explosives compound structures and the affected period would be last for a week.

3.5.1.2           The rock crusher will be situated inside the cavern and is configured as an enclosed system with dust collector.  Rocks would be transported from the drill and blast area within the cavern to the rock crusher by trucks.  The trucks would unload the rocks to the feed hopper with water spraying.  Dust collection will be provided at the exhaust of the enclosed system to suppress the dust emission during rock crushing.  Its performance will be assured by regular inspection and adequate stock of spare parts.  The crushed rocks will be conveyed via enclosed belt system to temporary stockpile before transferred to trucks. Water spray will be provided at conveyor belt and temporary stockpile to maintain the crushed products in wet condition.

3.5.1.3           The existing STSTW will be decommissioned after the relocated STSTW is in full operation.  The demolition of the facilities in the existing STSTW will be started after decommissioning.  All the tanks / sludge will be cleaned before demolition. Therefore, odour emission is unlikely arise from construction of the Project.

3.5.1.4           Some of the buildings at the existing STSTW have been built over 40 years. Asbestos containing materials (ACM) may be found in these old buildings.  As the existing STSTW is still in operation, asbestos survey on these buildings is not available at the time of this assessment.  It is proposed that the asbestos investigations shall be conducted by registered asbestos consultants before the decommissioning of existing STSTW.  If any ACM is identified, the asbestos consultant shall formulate overall asbestos management and abatement strategies.  The removal and disposal of the ACM shall be conducted by registered asbestos contractor following the Air Pollution Control (Asbestos) (Administration) Regulation.

Identification of Key Air Pollutants of Emission from Construction Activities

3.5.1.5           As mentioned above, major construction activities with significant particulate emission include foundation work, superstructure construction, temporary stockpiling, dust material handling, excavation, rock crushing and concrete production, as well as demolition of existing STSTW facilities.  On-site use of diesel powered engines is the potential source for other gaseous pollutants such as nitrogen dioxide (NO2) and sulphur dioxide (SO2) and smoke.  However, the number of such equipment required on-site will be limited and under normal operation.  Equipment with proper maintenance is unlikely to cause significant smoke and gaseous emissions.  Thus particulates from construction activities would be the major air pollutant during construction phase.  According to Annex 4 of the EIAO-TM, TSP is the criteria pollutant for construction dust impact assessment.  Quantitative assessment of TSP emission impact as well as other particulates PM10 and PM2.5 stipulated in AQOs is conducted for assessing construction dust impact due to the Project.

3.5.2               Operation Phase

3.5.2.1           The potential odour impacts on the neighbour ASRs would be the major air quality concerns during the operation of the relocated STSTW.  It is anticipated that the relocation of the existing STSTW into caverns would allow effective control of odour arising from the sewage treatment process and would significantly reduce the potential odour impacts.  All treatment units with potential odour emission will be covered and the exhausted air will be conveyed to the deodourizer for treatment before discharge to the environment via ventilation shaft.  The potential odour source during the operation phase of the relocated STSTW would therefore be the ventilation shaft.

3.5.2.2           In order to provide proper odour control and treatment before discharge to the ambient, four sets of deodourization unit would be installed at 4 different locations of the relocated STSTW for treating odorous gas collected from preliminary and primary treatment processes, sludge treatment process, UV disinfection process, secondary treatment and liquid-solid separation processes.

3.5.2.3           These deodourization units adopted long proven deodorization technologies, i.e. biotrickling and activate carbon absorption that are commonly adopted in STW including the existing STSTW. The scattered and localized odour treatment provision would minimize the risk of total system failure if only one centralized odour treatment facility is provided. In order to achieve high level of system reliability and redundancy, power source to the deodourization units would be in dual feed and dual ring arrangement from two separate CLP Power Hong Kong Ltd. (CLP) substations.  Further, at least one standby of odour extraction fan, biotrickling filter or activated carbon filter would be provided for each set of the deodourization unit.

3.5.2.4           As the relocated STSTW will receive same catchment as the existing STSTW, it is anticipated that influent quality will remain the same. With the alike influent quality and design treatment capacity, similar treatment technologies will be adopted for the relocated STSTW that includes preliminary treatment, primary treatment, biological treatment, solid-liquid separation and UV disinfection.

3.5.2.5           The water reclamation facilities including membrane filtration and/or reverse osmosis as mentioned in Section 2.5.1.2 at the relocated STSTW would not generate any aerial emission in the process, therefore, no air quality impact is anticipated from operation of the water reclamation facilities.

3.5.2.6           It is expected that the proposed relocated STSTW would induce a very slight increase in off-site traffic (about 25 nos. of dewatered sludge tankers per day) near Nui Po Shan.  The type of dewatered sludge tankers is proposed to adopt Euro VI type vehicle.   In view of minimal traffic flow and lower emissions from the vehicles, negligible off-site road traffic emission impact on the roadside ASRs due to small amount of induced traffic would be expected.  In order to minimise the odour impact, the loading and unloading activities will be conducted at the plant in cavern.  The loading/unloading bay will be properly vented to deodourization unit for treatment before release to the ambient.  The dewatered sludge tankers would be manufactured and fabricated in accordance to the design intends.  All the tankers would be required to conduct water test and smoke test to validate its performance. 

3.5.2.7           The odour impact from sludge transfer tanks could be controlled by properly design and good cleaning practices of the sludge transfer tanks.  The loading of sludge transfer tank is the potential odour source during the transportation when there are gaps between the tank opening and its cover.  Sludge tanks with totally enclosed design should be deployed for transporting sludge.  With thorough cleaning practice and regular condition test of the sludge tanks, odour emission and leachate leakage during storage and transportation would not pose a concern. 

Identification of Key Air Pollutants of Emission from Operation Activities

3.5.2.8           The odour emission releasing via the ventilation shaft would be the major pollutant due to the operation of relocated STSTW, and therefore, quantitative assessment of odour impact is conducted.  In view of minor induced traffic from operation of relocated STSTW, vehicular emission due to off-site traffic would be negligible.

 

3.6                  Assessment Methodology

3.6.1               Construction Phase

Emission Inventory

3.6.1.1           According to ¡§Guidelines on Assessing the ¡¥TOTAL¡¦ Air Quality Impacts¡¨, three components of contribution should be considered in evaluating the air quality impact due to the Project upon ASRs, namely primary, secondary and background contributions.

Primary Contributions

3.6.1.2           Primary contributions are the project-induced emission which contributes to the local air quality impact.  Thus, construction dust emission associated with the construction works of the Project is the primary contributions during the construction phase.

3.6.1.3           Construction activities with significant particulate emission are identified from the construction method suggested by engineering design.  Construction dust emission rate are estimated based on emission factors of US Environmental Protection Agency (USEPA) Compilation of Air Pollution Emission Factors (AP-42), 5th edition and activity data from the engineer design.    The major dust emitting construction activities for the Project considered in the modelling assessment include:

(a)        Drill & Blast for Cavern, Main Access Tunnel / Secondary Access Tunnel

¡P         Excavation  and material handling within the construction site modelled as heavy construction activities;

¡P         Wind erosion of open active area; and

¡P         Rock crusher with loading, crushing and screening.

(b)        Construction of Temporary Haul Road / Access Road, Explosives Compound Structures

¡P         Excavation and material handling within the construction site modelled as heavy construction activities; and

¡P         Wind erosion of open active area.

(c)        Stockpiling of Excavated Material

¡P         Stockpiling and material handling within the construction site modelled as heavy construction activities; and

¡P         Wind erosion of open active area.

(d)        Demolition of existing STSTW and Explosives Compound Structures

¡P         Concrete breaking and material handling within the construction site modelled as heavy construction activities; and

¡P         Wind erosion of open active area.

3.6.1.4           The dust control measures have been incorporated into the design of rock crusher, as presented Table 3.5. A schematic diagram of a rock crushing plant inside cavern is presented in Appendix 3.02a. These dust control measures of construction activities are taken into account in the estimation of dust emission. 

Table 3.5            Rock Crushing Operation with Dust Control Measures

Process

Description

Dust Control Measure

Rock Crusher

Unloading, Screening and Crushing

Unloading from trucks, screening and crushing

¡P         The rock crushing plant is configured as an enclosed system with dust collector.

¡P         Dust collector will be provided at the exhaust of the rock during rock crushing. Assume typical dust removal efficiency at 99%.

¡P         Watering will be provided to maintain material in wet condition.

Trucks

Vehicle leaving the works area

¡P         Vehicles would be required to pass through the wheel washing facilities provided at site exit.

 

3.6.1.5           Activity data including excavation rate, material handling rate, percentage active area, moisture content, silt content, number of construction trucks and truck speed are based on the preliminary engineering design.  The emission factors for identified dust sources are summarized in Table 3.6. The detailed calculation of dust emission rates and the justification for the percentage active area of construction work sites are presented in Appendix 3.02a, b, c and e.

Table 3.6            Emission Factor for Dust Emitting Construction Activity

Emission Source

Activity

Emission Factor

Remarks

Portal Exhaust from the Cavern and Tunnel

Heavy Construction Activities

E = 2.69 Mg/hectare/month of activity

(TSP)

100% area actively operating (for short-term concentration prediction)

 

10% area actively operating (for annual concentration prediction)

AP-42, Section 13.2.3, 1/95 ed.

 

Loading Point of Rock Crusher within Cavern

E = 8.00E-06 kg/Mg

(PM10)

 

100% actively operating

AP-42, 5th ed. 8/04 ed., Section 11.19.2, Table 11.19.2-1

 

 

TSP-to-RSP factor = 2.1

TSP-to-RSP Factor

Response to Comment, February 23, 2004 draft, AP-42 Section 11.19.2

 

Crushing by  Rock Crusher within Cavern

E = 2.70E-03 kg/Mg

(TSP)

100% actively operating

AP-42, 5th ed. 8/04 ed., Section 11.19.2, Table 11.19.2-1

 

E = 1.20E-03 kg/Mg

(PM10)

AP-42, 5th ed. 8/04 ed., Section11.19.2, Table 11.19.2-1

 

E = 1.20E-03 kg/Mg

(PM2.5)

Adopt PM10 Emission Factor as upper bound

Screening by  Rock Crusher within Cavern

E = 1.80E-03 kg/Mg

(TSP)

100% actively operating

AP-42, 5th ed. 8/04 ed., Section11.19.2, Table 11.19.2-1

 

E = 1.10E-03 kg/Mg

(PM10)

AP-42, 5th ed. 8/04 ed., Section11.19.2, Table 11.19.2-1

 

E = 1.10E-03 kg/Mg

(PM2.5)

PM2.5 Emission Factor

Adopt PM10 Emission Factor as upper bound

Construction Sites at Main Portal, Secondary Portal,

A Kung Kok Shan Explosives Magazine Site, Area 73 and Unpaved Haul Road

 

Demolition Site at Existing STSTW and Explosives Compound Structures at Magazine Site

Heavy Construction Activities

E = 2.69 Mg/hectare/month of activity

(TSP)

100% area actively operating (for short-term concentration prediction)

 

10% area actively operating (for annual concentration prediction)

AP-42, Section 13.2.3, 1/95 ed.

 

Wind Erosion

E = 0.85 Mg/hectare/year

(TSP)

100% area actively operating (for short-term concentration prediction)

 

10% area actively operating (for annual concentration prediction)

AP-42, 5th ed., Table 11.9-4

 

3.6.1.6           Construction dust emission factors in AP-42 would be in terms of TSP.  Fractions of finer particulates are to be estimated from the TSP emission which requires the size distribution information of the concerned process, in order to compare against the AQOs.  The particle size distributions of general construction processes are available in AP-42 by USEPA.  Particle size distributions of general construction processes are listed in Table 3.7. Construction dust emission inventory in PM10 and PM2.5 are estimated by applying the factors of associated process to TSP emission.  The emission rates in TSP, PM10 and PM2.5 of each dust source are presented in Appendix 3.02d and e.

Table 3.7            Particle Size Distribution of Various Processes

Process

Cumulative % of TSP

RSP

FSP

Reference

Aggregate Handling (equivalent to Heavy Construction Activities)

47.3%

7.2%

Page 13.2.4-4, Section 13.2.4, AP-42, USEPA (Version 11/06 )

 

3.6.1.7           For the prediction of the highest hourly average TSP, the 10th highest daily average and annual average Respirable Suspended Particulates (RSP) and Fine Suspended Particulates (FSP) concentrations, 12-hour (07:00-19:00) per normal working day is assumed for the construction period in the assessment.  Since no construction activity would occur on Sundays and public holidays, only wind erosion would be assumed for these days as well as for other non-working hours (19:00 to 07:00 of the following day) on normal working days.

Secondary Contributions

3.6.1.8           Secondary contributions are the air pollutant emissions immediate neighborhood of the Project Site contributing further to the local air quality impact.  Any particulates emission sources within 500m of the project boundary with notable impact shall be identified and considered in the construction phase impact assessment.  The secondary contribution in particulates mainly comes from the vehicular emission in the vicinity of the Project, in particular Tolo Highway and Tate¡¦s Cairn Highway.  As mentioned in Section 2.10, the construction programme of Proposed Works for Upstream Sewerage Facilities for Relocation of STSTW would be overlapped with construction of CSTW.  As reviewed, only the work site of the modification / improvement work of sewage pumping station at A Kung Kok would be located within 500m from work site of CSTW.  Since this modification/improvement work would be minor and in small scale, its contribution to cumulative dust impact is anticipated to be insignificant.  Sha Tin ISEPS and the rest of concurrent projects would locate more than 500m away from the major construction work of the cavern. Owing to the locality of construction dust impact, no cumulative construction dust impact due to these concurrent projects would be expected.

3.6.1.9           Based on the tentative construction programme presented in Appendix 2.03, the major construction tasks are construction of tunnels and caverns for relocated STSTW and demolition of existing STSTW.  These two tasks would be carried out at different work site areas and their construction programme would not be overlapped.  The worst-case year scenario of individual construction task would be assessed in this study.  The construction of tunnels, caverns and its driveways will be conducted during Year 2019 ¡V 2024.  Referring to Table 7.1, the total explosive delivery trips for the tunnel main portal, the maximum number of the delivery trips would occur in Year 2022.  It means that maximum rate of spoil generated from drill and blast of cavern and maximum flow of dump trucks for spoil handling from cavern to stockpile would be peak in Year 2022.  Fugitive dust impact due to spoil handling and traffic of dump trucks will reach its maximum in Year 2022 together with the construction dust impact due to the cavern construction.  Therefore, the worst-case year scenario for construction of tunnel and cavern for relocated STSTW considered in the assessment is Year 2022.  For the demolition of existing STSTW, it will be undertaken after the commencement of relocated STSTW as early in Year 2027 and would be completed in Year 2028.  Since the majority of excavation works would be conducted in Year 2027, the worst-case year scenario for demolition of existing STSTW considered in the assessment is Year 2027.  Year 2022 and Year 2027 traffic forecasts are selected for calculation of vehicular emission which are adopted as the secondary contribution in dust impact during cavern construction and demolition of existing STSTW respectively.  The traffic forecasts have been endorsed by Transport Department (TD).  The traffic data including 24-hour traffic flow with vehicle percentage, trips, daily vehicle-kilometer-travelled (VKT), speed fraction in 16 types of vehicle for the assessment year are presented in Appendix 3.03. 

3.6.1.10         Emission Factors Hong Kong Model (EMFAC-HK) version 2.6 has been adopted to estimate the vehicular emission rates of RSP and FSP for different road types, namely expressway, district distributor and local distributor.  This is essential in representing the variation of vehicle emissions for different road types which has different vehicle travel speeds and vehicle compositions in local context.

3.6.1.11         The ¡§2010 Licensed Vehicle by Age and Technology Group Fractions¡¨ provided in EPD¡¦s website, is adopted in this assessment.  Since the provided exhaust technology fractions are only up to Year 2010, those after Year 2010 are projected in accordance with EPD¡¦s Guideline on Modelling Vehicle Emissions ¡V Appendix 2 ¡§Implementation Schedule of Vehicle Emission Standards in Hong Kong (Updated as at 20 December 2013)¡¨ and Appendix 3 ¡§EMFAC-HK V2.6.0 Exhaust Technology Group Indexes¡¨.

3.6.1.12         According to EPD¡¦s Guideline on Modelling Vehicle Emissions - Appendix 2, the implementation schedules of Euro V and Euro VI standards are in the middle of a year for some vehicle classes or fuel types.  Since the detailed fraction data is not available after Year 2010, as a conservative approach, the exhaust technology fractions of these vehicle classes or fuel types are assumed to be kept as the previous standards fully for the scheduled year, while upgraded to the higher standards fully at the following year.  Evaporative technology fraction in the model is based on the default value.

3.6.1.13         As recommended in the EPD¡¦s Guideline on Modelling Vehicle Emissions, default vehicle populations forecast in EMFAC-HK is used.

3.6.1.14         The default accrual rates in EMFAC-HK are estimated from the local mileage data adjusted to reflect the total VKT for each vehicle class.  The default value has been used.

3.6.1.15         For those roads with cold starts, the diurnal variation of daily trips in the study area applied in the EMFAC-HK model is provided by the traffic team.

3.6.1.16         VKT represents the total distance travelled on a weekday.  The VKT is calculated by multiplying the number of vehicle which based on the highest predicted hourly traffic flow, and the length of road travelled in the study area.  The diurnal variation of VKT in the study area is provided by the traffic team, and the input in the model is by vehicle/fuel/hour.

3.6.1.17         Speed fraction represents the percentage in different speed ranges of each vehicle type weighted by VKT.  The speed limits of existing road were made reference to the Traffic Aids (plan marked the road marking, traffic sign and speed limits) from TD.

3.6.1.18         The resulting hourly emissions of RSP and FSP have been divided by the number of vehicles and the distance travelled to obtain the emission factors in gram per miles per vehicle which are to be directly adopted by the air dispersion model.

3.6.1.19         All major roads within 500m study boundary, including Tolo Highway and Tate¡¦s Cairn Highway are incorporated into the assessment as indicated in Appendix 3.04.  The calculation of the composite emission rates for each road links are presented as well in the appendix. 

Background Contributions

3.6.1.20         As suggested by ¡§Guidelines on Assessing the ¡¥TOTAL¡¦ Air Quality Impacts¡¨, an integrated modelling system, Pollutants in the Atmosphere and their Transport over Hong Kong model (PATH) which is developed and maintained by EPD is applied to estimate the background pollutant concentrations.  Mesoscale Model 5 (MM5) meteorological data of the same gird cell should also be adopted to drive local air quality modelling over the grid area as recommended by the guideline.

3.6.1.21         As dataset of PATH consist only the background concentration of PM10, daily and annual average PM2.5 background concentration are estimated by a factor of 0.75 and 0.71 to PM10 concentration respectively, as suggested by ¡§Guidelines on the Estimate of PM2.5 for Air Quality Assessment in Hong Kong¡¨.

3.6.1.22         Dataset of PATH has no TSP background either.  TSP background concentration will be assumed to constitute of 100% of PM10 concentration.  PM10 concentration from PATH is directly adopted as TSP background concentration for the assessment.

3.6.1.23         The study area covers 4 grid cells of PATH, namely grid (31, 35), (32, 34), (32, 35) and (33, 34).  PATH dataset (Year 2020) of these four grid cells are adopted as the background concentration for the assessment. 

Dispersion Modelling & Modelling Approach

3.6.1.24         Fugitive Dust Model (FDM) (1993 version), approved air dispersion model by EPD, is applied to assess potential primary dust impact from the construction works and secondary ones due to concurrent construction works.

3.6.1.25         California Line Source Dispersion Model, version 4 (CALINE4), the USEPA approved line source air dispersion model developed by the California Department of Transport is used to assess the secondary contribution due to vehicular emission from nearby highways.

3.6.1.26         Within 3km radius of the relocated STSTW, more than 50% of area is Shing Mun River and flat land, the land use of the study area is therefore classified as ¡§Rural¡¨.  Sha Tin is a new development town.  The surface roughness applied in the FDM model is thus taken as 100 cm according to EPD¡¦s ¡§Guidelines on Choice of Models and Model Parameters¡¨.

3.6.1.27         According to ¡§Guidelines on Assessing the ¡¥TOTAL¡¦ Air Quality Impacts¡¨, MM5 meteorological data extracted from PATH system should be used to drive the local air quality models on an hour-by-hour basis while adopting the air quality data from PATH system as background concentration.  Hourly meteorological conditions including wind data, temperature and mixing heights are to be extracted from MM5 data.  Hourly pasquill stability class is to be determined by PCRAMMET Meteorological Program (PCRAMMET) with input from MM5 data.  No missing meteorological data is expected when adopting MM5 data.  Anemometer height is assumed to be 10 metres above ground for the first layer of MM5 data as input.

3.6.1.28         Cumulative dust impact upon ASRs is derived from the sum of predictions by local air quality models and background concentration from PATH system on hour-by-hour basis.  Averaging results, namely hourly, daily and annual, are derived from the cumulative hour-by-hour results in accordance with Title 40, Code of Federal Regulations (USEPA 40 CFR) Part 51 ¡§Revision to the Guideline on Air Quality Models, Version 2005¡¨.  Cumulative average predictions at each ASR amongst 365 days are ranked in descending concentration and compared with the maximum allowable concentration to determine the number of exceedance throughout a year.  The dust impact upon ASRs is evaluated by number of exceedance per annum against the AQO criteria.

3.6.1.29         Active construction activities might be undertaken at multiple works faces spreading across each site.  It is not feasible to determine the exact location of individual dust emission source at a specific time.  As such, for the purpose of predicting annual concentrations and in conservative approach, it is assumed that dust emissions would be distributed across the whole area of each site with all activities operating at the same time for a complete year.  The dust emission rates are estimated based on the annual average percentage active works area of each works site.  Based on the preliminary engineering design, the annual average active area is estimated to be 10% as presented in Appendix 3.02b and e and would be assumed for predicting the annual average concentrations.  The rock crusher is considered to be working at full capacity throughout the construction period, taken as a worst-case assumption, i.e. 100% emission from the operation of the rock crusher with the dust collector with 99% dust removal efficiency is assumed in the model.

3.6.1.30         Works activities and plant would not be concentrated in certain areas of the site close to ASRs for an extended period of time during the construction period.  However, notwithstanding that such a scenario would not be expected to occur, a hypothetical Tier 1 screening test assuming 100% active area of construction site of the Project with mitigation measures in place has been undertaken for predicting hourly and daily average TSP levels.  It aims to highlight the hot spot locations where construction dust may potentially become an issue.  However, it should be emphasized that Tier 1 screening test is a hypothetical one which is very conservative and does not occurred in reality.

3.6.1.31         The Tier 1 results have allowed a more focused Tier 2 assessment to be undertaken at the specific hot spot locations where TSP non-compliance is predicted under the Tier 1 screening test, a focused Tier 2 assessment is undertaken whereby the percentage of daily maximum active works areas, which is assumed to be 20%, for the Project are positioned closest to the potentially worst affected ASRs. The Tier 2 assessment areas are shown in Appendix 3.02b and e.  Same as for predicting annual average TSP levels, 100% emission from the operation of rock crusher with the dust collector with 99% dust removal efficiency is assumed in the model.

3.6.2               Operation Phase ¡V Odour Impact Assessment

Odour Emission Inventory

3.6.2.1           As the relocated STSTW will receive same catchment as the existing STSTW, it is anticipated that influent quality will remain the same. With the alike influent quality and design treatment capacity, similar treatment technologies will be adopted for the relocated STSTW that includes preliminary treatment, primary treatment, biological treatment, solid-liquid separation and UV disinfection. The schematic diagram of the plant layout, is referred to Section 2. The odour emission rates of sewage treatment facilities in the relocated STSTW therefore made reference to the odour emission rates of treatment facilities in the existing STSTW.  Several site visits and on-site sampling were conducted in summer 2015 to identify the potential odour emission sources in the existing STSTW.  The sources included inlet fine screen, open areas of inlet channel, screening skips, aerated grit channel, primary influent channel, primary sedimentation tanks, primary effluent channel, aeration tanks (anoxic and aerobic zones), final sedimentation tanks, Mixed Liquor Suspended Solid (MLSS) channel, dewatered sludge skips and digested sludge holding tanks at sludge dewatering house, influent and effluent channels of primary sedimentation tanks, Surplus Activated Sludge (SAS) holding tanks, thickened SAS holding tanks and overflow boxes of the digestion tanks.

3.6.2.2           On-site odour measurement has been conducted at the facilities of existing STSTW on 15 and 17 July 2015 to determine the odour emission rates by odour sampling and olfactometric analysis.  The ambient temperature during sampling was ranged from 31 to 36 ¢XC.  The report of the odour sampling and analysis including the sampling location plan and sampling procedures is presented in Appendix 3.05.  The measured odour emission rates of the sampling locations are summarized in Table 3.8. The odour emission rate adopted at each source in the relocated STSTW is presented in Table 3.9.  As the sludge treatment facilities and dewatering treatment in relocated STW is different from the existing STSTW, the odour emission rate of these facilities will follow the odour emission rates from the operation of Stonecutters Island Sewage Treatment Works (SCISTW). 

Table 3.8            Summary of Measured Odour Emission Rate in Existing STSTW

Location

Sample ID

Maximum Emission Rate (OU/m²/s)

Screening Skip

F2

3.83

Inlet Channel

F1

5.42

Aerated Grit Channel

F3

2.71

Primary Influent Channel

F4

3.41

Primary Sedimentation Tank

F5

2.90

Primary Effluent Channel

F6

4.82

Aeration Tank (Aerobic Zone)

F7

0.07

Aeration Tank (Anoxic Zone)

F8

0.14

Final Sedimentation Tank

F9

0.03

MLSS Channel

F10

0.02

Dewatered Sludge Skip

F12

1.14

Digester Overflow Box

A4

1.26


Table 3.9               Odour Emission Rates for the Relocated STSTW

Odour Source in Relocated STSTW

No. of Duty Unit

Dimension of Surface (m) per unit

Total Exposed Surface Area (m2)

Corresponding Odour Source in existing STSTW

Odour Emission Rate (OU/m²/s)

Odour Control Method

Primary Treatment

Inlet Chamber

1

6.7 x 16.5

111

Inlet Channel

5.42

Covered Exposed Area + Deodourizer (DO1)

Fine Screen

4

7 x 2

56

Inlet Channel

5.42

Covered Exposed Area + Deodourizer (DO1)

Fine Screen By Pass

1

16.5 x 1.5

25

Inlet Channel

5.42

Covered Exposed Area + Deodourizer (DO1)

Fine Screen Screenings Handling Area

1

6 x 5

30

Screening Skip

3.83

Covered Exposed Area + Deodourizer (DO1)

Fine Screen Outlet Channel

1

14.2 x 4.5

64

Inlet Channel

5.42

Covered Exposed Area + Deodourizer (DO1)

Distribution Channel

1

1

26.25 x 2.5

13.5 x 7

95

Inlet Channel

5.42

Covered Exposed Area + Deodourizer (DO1)

Aerated Grit Channels

5

15 x 4

300

Aerated Grit Channel

2.71

Covered Exposed Area + Deodourizer (DO1)

Grit Handling Area

4

4.5 x 3.5

63

Screening Skip

3.83

Covered Exposed Area + Deodourizer (DO1)

Aerated Grit Channel Outlet Channel

2

17 x 2.25

77

Primary Influent Channel

3.41

Covered Exposed Area + Deodourizer (DO1)

Header Channel to Primary Sedimentation Tank

2

259 x 2

1036

Primary Influent Channel

3.41

Covered Exposed Area + Deodourizer (DO1)

Header Distribution Channel to Primary Sedimentation Tank

8
2

7.4 x 2
28 x 2.5

398

Primary Influent Channel

3.41

Covered Exposed Area + Deodourizer (DO1)

Primary Treatment

Primary Sedimentation Tank

10

51 x 9

4590

Primary Sedimentation Tank

2.90

Covered Exposed Area + Deodourizer (DO1)

Primary Sedimentation Weir

4

28 x 2

224

Primary Sedimentation Tank

2.90

Covered Exposed Area + Deodourizer (DO1)

Primary Sedimentation Tank Outlet Channel

4

15 x 2

120

Primary Effluent Channel

4.82

Covered Exposed Area + Deodourizer (DO1)

Header Channel to Biological

2

227.5 x 2

910

Primary Effluent Channel

4.82

Covered Exposed Area + Deodourizer (DO1)

Sludge Treatment (1)

Thickening Facilities

3

6.5 x 2

39

Stonecutter Island STW

26.42

Covered Exposed Area + Deodourizer (DO2)

Thickened Sludge Holding Tank

2

N/A

354 +

298

Stonecutter Island STW

26.42

Covered Exposed Area + Deodourizer (DO2)

Direct Dewatering Facilities

10

10 x 3.6

360

Stonecutter Island STW

26.42

Covered Exposed Area + Deodourizer (DO2)

Skip Room

10

6 x 2.4

144

Stonecutter Island STW

26.42

Covered Exposed Area + Deodourizer (DO2)

Dewatering Treatment (1)

Primary Sludge Holding Tank

1

18 x 9.4

169

Stonecutter Island STW

26.42

Covered Exposed Area + Deodourizer (DO3)

Thickening Centrate Tank

1

10 x 9.4

94

Stonecutter Island STW

26.42

Covered Exposed Area + Deodourizer (DO3)

Direct Dewatering Facilities

10

10 x 3.6

360

Stonecutter Island STW

26.42

Covered Exposed Area + Deodourizer (DO3)

Thickened Sludge Holding Tank

1

N/A

298

Stonecutter Island STW

26.42

Covered Exposed Area + Deodourizer (DO3)

Skip Room

10

6 x 2.4

144

Stonecutter Island STW

26.42

Covered Exposed Area + Deodourizer (DO3)

Final Treatment

UV Distribution Channel

1

10.5 x 8.1

85

Final Sedimentation Tank / MLSS Channel

0.03

Covered Exposed Area + Deodourizer (DO3)

UV

5

12.4 x 3

186

Final Sedimentation Tank / MLSS Channel

0.03

Covered Exposed Area + Deodourizer (DO3)

UV Outlet Channel

2

1

12.7 x 2.2

34.9 x 1.7

56

59

Final Sedimentation Tank / MLSS Channel

0.03

Covered Exposed Area + Deodourizer (DO3)

Secondary Treatment

Biological Tank

Header Distribution to Biological

5

117.9 x 2

1179

Aeration Tank (Anoxic Zone)

0.14

Covered Exposed Area + Deodourizer (DO4)

Anoxic Zone

35

10.2 x 13.75

4909

Aeration Tank (Anoxic Zone)

0.14

Covered Exposed Area + Deodourizer (DO4)

Aerobic Zone

35

12.1 x 13.75

5823

Aeration Tank (Aerobic Zone)

0.07

Covered Exposed Area + Deodourizer (DO4)

Biological Outlet Channel

5

144.2 x 2

1442

Aeration Tank (Anoxic Zone)

0.14

Covered Exposed Area + Deodourizer (DO4)

Header Channel to Dissolved Air Flotation (DAF)

2

226.3 x 2

905

Aeration Tank (Anoxic Zone)

0.14

Covered Exposed Area + Deodourizer (DO4)

Header Distribution to DAF

4

77.25 x 2

618

Aeration Tank (Anoxic Zone)

0.14

Covered Exposed Area + Deodourizer (DO4)

Final Treatment

DAF Units

20

8 x 11

1760

Final Sedimentation Tank / MLSS Channel

0.03

Covered Exposed Area + Deodourizer (DO4)

DAF Outlet

4

77.75 x 2

622

Final Sedimentation Tank / MLSS Channel

0.03

Covered Exposed Area + Deodourizer (DO4)

Header Channel to UV

2

233.35 x 2

933

Final Sedimentation Tank / MLSS Channel

0.03

Covered Exposed Area + Deodourizer (DO4)

Header Distribution to UV

1

9.8 x 2

20

Final Sedimentation Tank / MLSS Channel

0.03

Covered Exposed Area + Deodourizer (DO4)

Note:

(1)   The odour emission rates for sludge treatment and dewatering treatment facilities are made reference to Appendix 3.4 of the approved EIA Report for Harbour Area Treatment Scheme (HATS) Stage 2A (EIA-148/2008).

 

 


3.6.2.3           All odour sources in caverns will be confined and ventilated to the deodorization units for treatment before discharge to the ambient. The odour emission rate was based on the projection of existing STSTW odour sample measurements under several rounds of Odour Survey and Stonecutters Island STW. Appropriate level of odour treatment, i.e. one or two stage(s) deodorization system will be accordingly provided for odour sources.

3.6.2.4           With reference to the ¡§Code of Practice on Assessment and Control of Odour Nuisance from Waste Water Treatment Works, April 2005¡¨ published by the Scottish Executive, odour removal efficiency of two common odour abatement technologies, namely bio-filters and dry scrubbing (carbon or impregnated media) are of at least 95%. Therefore, for one-stage and two-stage deodorization system, the combined practicable odour removal efficiency could be up to 95% and 99.75% respectively.

3.6.2.5           However, as a more conservative approach for this assessment, odour removal efficiencies of 80% and 97% are assumed for one-stage and two-stage deodorization system respectively which is practically achievable. Table 3.10 summarizes the performance of proposed treatment technologies to be installed for specific treatment process. 

Table 3.10          Summary of Required Odour Removal Efficiency for Deodorization System

Deodorization Unit

Location

Possible Treatment Technology

Odour Removal Efficiency

DO1

¡P         Preliminary Treatment

¡P         Primary Treatment

Biotrickling Filter Plus Activated Carbon Filter

97%

DO2

¡P         Thickening Facilities

¡P         Dewatering Facilities

¡P         Dewatered Sludge Handling Facilities

¡P         Thickened Sludge Holding Tanks

Biotrickling Filter Plus Activated Carbon Filter

97%

DO3

¡P         Dewatering Facilities

¡P         Dewatered Sludge Handling Facilities

¡P         Centrate Holding Tank

¡P         Primary Sludge Holding Tank

¡P         Thickened Sludge Holding Tank

¡P         UV Disinfection Channels

Biotrickling Filter Plus Activated Carbon Filter

97%

DO4

¡P         Biological Treatment

¡P         Solid-Liquid Separation

Activated Carbon Filter

80%

 

3.6.2.6           The processing capacity of relocated STSTW is expected to reach 280,000 m3/day upon commencement up to Year 2036 (hereafter as interim stage) and reach 340,000 m3/day from Year 2036 onward (hereafter as Ultimate Stage).  With reference to the findings of odour measurement survey, the potential odour emission after deodorization treatment is estimated to be at 3,530 OU/s at interim stage and 4,420 OU/s at ultimate stage.  The calculation of odour emission rates is shown in Appendix 3.06.

3.6.2.7           The ventilation shaft is proposed to be located further south of A Kung Kok Shan Road, as illustrated in Figure No. 60334056/EIA/3.02.  The current configuration of the relocated STSTW includes 4 deodorization units plus 1 stand-by each for contingency, which situate close to odour sources for targeted treatment. The odour removal efficiency of three deodorization units would be 97% and one unit would be at 80%. The design parameters of the ventilation shaft are summarized in the Table 3.11.  The exit temperature is assumed to be 30¢XC in this assessment.

Table 3.11          Design Parameter of the Ventilation Shaft

Parameter

Design Value

Base elevation

177 mPD

Height of ventilation outlet above ground surface

5 metres

Dimension (diameter in metres) of ventilation outlet

4.8 metres

Exit velocity

13.51 m/s (interim stage)

15 m/s (ultimate stage)

Operation hour

24 Hours

 

Dispersion Modelling & Modelling Approach

3.6.2.8           Air quality impacts of odour on the ASRs from the operation of the relocated STSTW are modelled with the air dispersion model, Industrial Sources Complex Short Term 3 (ISCST3), which is approved by EPD.

3.6.2.9           It is assumed that the proposed deodorizing units/system of relocated STSTW operate continuously on a 24-hour-per-day basis with steady state ventilation rate and exhaust gas velocity in the assessment, unless specified in the engineering design.  The assessment heights are at predetermined heights above ground level according to the height of the ASRs.  The contour plots of the predicted odour levels at the worst affected heights of the ASRs are produced.

3.6.2.10         Odour emission from the exhaust outlet of the deodorizer is modelled as point source in the assessment.

3.6.2.11         Within 3km radius of the relocated STSTW, more than 50% of area is Shing Mun River and flat land, the land use of the study area is therefore classified as ¡§Rural¡¨.  Sha Tin is a new development town.  The surface roughness applied in the ISCST3 model is thus taken as 100cm in according to EPD¡¦s ¡§Guidelines on Choice of Models and Model Parameters¡¨.

3.6.2.12         One year valid meteorological data including wind data, stability class, ambient temperature extracted from Sha Tin meteorological station, which is located at Sha Tin Racecourse and is the nearest meteorological station to STSTW, and the mixing height data recorded at the King¡¦s Park Weather Station are adopted for the assessment.  Since the mixing data of year 2012, 2013 and 2014 are less than the EPD¡¦s requirement of 90 percent valid data, the latest available meteorological data of year 2011 is therefore selected for modelling use in the assessment.

3.6.2.13         The modelled hourly odour concentrations at the ASRs are converted into the peak 5-second odour concentrations so as to compare with the odour criteria (5 odour units based on an averaging time of 5 seconds) stipulated in the EIAO-TM.  EPD¡¦s ¡§Guidelines on Choice of Models and Model Parameters¡¨ recommends the methodology proposed by Duffee et al.[1] and Keddie[2] in performing the conversion from hourly to 5-second average concentration.  In addition, Turner[3] has identified that the Pasquill-Gifford vertical dispersion parameter used in the ISCST3 model is around 3 to 10 minutes.  As a conservative assumption, the hourly average estimated by ISCST3 model is assumed as 15 minutes, and the conversion factors for the predicted 1-hour averaged concentration of odour at the receivers would be adjusted to 5-second averaging time by the values shown in Table 3.12

Table 3.12          Conversion Factors to 5-second Mean Concentration for Point Source

Pasquill Stability Class

Conversion Factor

15 min to 3 min

3 min to 5 sec

Overall

A

2.23

10

22.3

B

2.23

10

22.3

C

1.7

5

8.5

D

1.38

5

6.9

E

1.31

5

6.55

F

1.31

5

6.55

 

3.7                  Prediction and Evaluation of Environmental Impacts

3.7.1               Construction Phase

3.7.1.1           The cumulative dust impacts due to construction of relocated STSTW and demolition of existing STSTW at the representative ASRs have been evaluated.  The predicted unmitigated cumulative maximum hourly average TSP, 10th highest daily and annual average PM10 and PM2.5 concentrations at the representative ASRs are summarized in Table 3.13 and Table 3.14

Table 3.13          Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Construction of Relocated STSTW) (Unmitigated Scenario)

ASR

Assessment Height (mAG)

Cumulative Concentration (µg/m3)

Maximum Hourly TSP

10th Highest Daily PM10

10th Highest Daily PM2.5

Annual PM10

Annual PM2.5

ASR1

1.5

7575

199

64

43

30

5

7316

201

64

43

30

10

6233

194

62

43

30

20

3731

172

60

43

29

30

1910

132

59

42

29

40

1487

104

59

41

29

50

1092

85

58

41

29

60

760

79

58

40

28

70

568

77

57

40

28

80

458

77

57

40

28

ASR2

1.5

2850

112

60

41

29

5

2856

113

60

41

29

10

2580

112

59

41

29

20

1869

105

59

41

29

ASR3

1.5

9480

303

81

47

31

5

9228

300

79

47

31

10

7954

277

74

46

31

20

4991

208

65

44

30

30

2519

144

60

43

29

ASR4

1.5

14458

274

80

47

31

5

12920

271

80

47

31

10

9655

244

77

46

31

20

4207

183

70

44

30

30

2020

141

61

42

29

ASR5

1.5

4755

208

63

44

30

5

4749

210

63

44

30

10

4282

199

62

44

30

ASR6

1.5

10170

247

76

45

30

5

9678

247

75

45

30

10

7976

228

72

44

30

20

4483

189

63

43

30

30

1958

147

60

42

29

40

1451

115

58

41

29

50

1039

95

58

41

29

60

712

81

58

40

28

70

576

78

58

40

28

80

460

77

57

40

28

90

378

77

57

40

28

100

330

77

57

40

28

110

287

77

57

40

28

120

248

77

57

40

28

ASR7

1.5

7460

233

73

44

30

5

7144

233

72

44

30

10

5910

220

69

44

30

20

3423

180

63

43

29

30

1720

141

59

42

29

ASR8

1.5

11785

443

118

55

34

5

10569

432

117

54

34

10

7896

396

110

53

34

ASR9

1.5

6587

214

77

46

31

5

6418

214

77

46

31

10

5525

205

75

45

31

ASR10

1.5

1968

141

64

39

27

5

1995

143

63

39

27

10

1834

141

63

39

27

20

1413

131

61

39

27

30

964

119

59

38

27

ASR11

1.5

1334

140

65

39

27

5

1375

142

65

39

27

10

1315

139

64

39

27

20

1146

132

63

39

27

ASR12

1.5

1885

132

58

39

27

5

1564

121

57

39

27

10

907

105

57

39

27

20

760

95

56

38

26

ASR13

1.5

1308

118

57

39

27

5

1351

118

57

39

27

10

1275

110

57

39

27

20

1073

99

56

38

27

ASR14

1.5

294

75

55

38

27

5

311

75

55

38

27

10

307

75

55

38

27

ASR15

1.5

4953

243

71

44

30

ASR16

1.5

5992

159

61

42

29

5

5890

161

61

42

29

10

5095

154

60

42

29

20

3314

131

59

42

29

30

1812

117

58

41

29

40

1107

100

58

41

29

50

895

88

58

41

29

60

701

81

58

40

28

70

539

79

58

40

28

80

482

78

57

40

28

90

433

77

57

40

28

100

394

77

57

40

28

110

365

77

57

40

28

120

346

77

57

40

28

ASR17

1.5

1142

83

57

40

28

5

1192

83

57

40

28

10

1123

83

57

40

28

20

935

83

57

40

28

30

721

80

57

40

28

40

517

79

57

40

28

50

440

79

57

40

28

60

419

79

57

40

28

70

398

79

57

40

28

80

378

79

57

40

28

90

360

78

57

40

28

ASR18

1.5

829

79

57

40

28

5

876

79

57

40

28

10

835

79

57

40

28

20

725

79

57

40

28

30

595

79

57

40

28

40

463

79

57

40

28

50

347

79

57

40

28

60

341

79

57

40

28

70

334

78

57

40

28

80

327

78

57

40

28

90

321

77

57

40

28

100

316

77

57

40

28

ASR19

1.5

1330

89

57

41

29

5

1346

90

57

41

29

10

1197

89

57

41

29

20

995

87

57

41

29

ASR20

1.5

9291

266

85

48

32

5

8873

267

84

48

32

10

7368

252

82

47

32

ASR21

1.5

1794

87

59

41

29

5

1824

89

59

41

29

10

1632

88

58

41

29

ASR22

1.5

1713

83

57

41

29

5

1752

84

57

41

29

10

1571

83

57

41

29

20

1146

81

57

41

29

30

736

80

57

40

29

40

451

79

57

40

29

50

384

78

56

40

28

Remark:

Boldfaced value represents that the predicted concentration exceeds the respective criterion.

 

Table 3.14          Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Demolition of Existing STSTW) (Unmitigated Scenario)

ASR

Assessment Height (mAG)

Cumulative Concentration (µg/m3)

Maximum Hourly TSP

10th Highest Daily PM10

10th Highest Daily PM2.5

Annual PM10

Annual PM2.5

ASR1

1.5

661

83

58

40

28

5

697

83

58

40

28

10

684

83

58

40

28

20

642

83

58

40

28

30

585

82

58

40

28

40

518

80

58

40

28

50

448

80

58

40

28

60

380

79

57

40

28

70

346

79

57

40

28

80

339

79

57

40

28

ASR2

1.5

554

80

58

40

28

5

586

81

58

40

28

10

577

81

58

40

28

20

548

80

58

40

28

ASR3

1.5

819

88

59

40

28

5

861

89

59

40

28

10

820

88

59

40

28

20

745

87

59

40

28

30

655

85

59

40

28

ASR4

1.5

860

89

59

40

28

5

902

90

59

40

28

10

855

90

59

40

28

20

776

88

59

40

28

30

674

85

59

40

28

ASR5

1.5

760

84

59

40

28

5

800

85

59

40

28

10

765

85

59

40

28

ASR6

1.5

1204

98

60

41

29

5

1253

99

60

41

29

10

1169

97

59

41

29

20

923

94

59

40

28

30

721

86

59

40

28

40

549

83

59

40

28

50

484

80

58

40

28

60

428

79

58

40

28

70

379

79

58

40

28

80

336

79

57

40

28

90

300

78

57

40

28

100

272

77

57

40

28

110

252

77

57

40

28

120

240

77

57

40

28

ASR7

1.5

1349

103

59

41

29

5

1400

105

59

41

29

10

1296

104

59

41

28

20

995

96

59

41

28

30

701

88

59

40

28

ASR8

1.5

854

95

60

40

28

5

890

96

60

40

28

10

855

95

60

40

28

ASR9

1.5

954

90

60

40

28

5

999

90

60

40

28

10

923

89

60

40

28

ASR10

1.5

722

77

56

37

26

5

769

77

56

37

26

10

733

77

55

37

26

20

628

77

55

37

26

30

499

77

55

37

26

ASR11

1.5

571

81

56

37

26

5

604

81

56

37

26

10

574

81

56

37

26

20

485

80

56

37

26

ASR12

1.5

309

74

55

37

26

5

330

74

55

37

26

10

319

74

55

37

26

20

306

74

55

37

26

ASR13

1.5

360

75

55

37

26

5

383

76

55

37

26

10

376

75

55

37

26

20

356

75

55

37

26

ASR14

1.5

235

74

55

38

27

5

250

74

55

38

27

10

248

74

55

38

27

ASR15

1.5

1719

125

59

41

29

ASR16

1.5

1566

108

59

41

29

5

1616

111

59

41

29

10

1478

109

59

41

28

20

1090

100

59

41

28

30

705

90

59

40

28

40

597

82

59

40

28

50

518

79

58

40

28

60

441

79

58

40

28

70

368

79

57

40

28

80

303

78

57

40

28

90

281

77

57

40

28

100

262

77

57

40

28

110

245

77

57

40

28

120

237

77

57

40

28

ASR17

1.5

555

81

58

40

28

5

595

84

58

40

28

10

579

83

58

40

28

20

532

80

58

40

28

30

468

79

58

40

28

40

396

79

58

40

28

50

373

77

58

40

28

60

356

77

58

40

28

70

339

77

58

40

28

80

323

77

57

40

28

90

308

77

57

40

28

ASR18

1.5

635

79

58

40

28

5

680

79

58

40

28

10

665

79

58

40

28

20

622

79

58

40

28

30

564

78

58

40

28

40

496

78

58

40

28

50

424

77

58

40

28

60

353

77

58

40

28

70

287

77

58

40

28

80

229

77

57

40

28

90

228

77

57

40

28

100

228

77

57

40

28

ASR19

1.5

4567

216

67

44

29

5

4167

215

67

44

29

10

2752

197

65

44

29

20

1275

151

60

43

29

ASR20

1.5

807

93

60

40

28

5

849

94

60

40

28

10

810

93

60

40

28

ASR21

1.5

3338

220

65

45

29

5

3103

221

65

45

29

10

2117

206

64

44

29

ASR22

1.5

1578

163

68

43

29

5

1576

166

68

43

29

10

1425

161

67

43

29

20

1164

148

66

43

29

30

894

132

62

42

29

40

719

118

61

42

29

50

625

101

60

41

28

Remark:

Boldfaced value represents that the predicted concentration exceeds the respective criterion.

 

3.7.1.2           Based on the predictions presented in Table 3.13 and Table 3.14, the predicted cumulative maximum hourly average TSP, 10th highest daily and annual average PM10 and PM2.5 concentrations at some representative ASRs would exceed the criteria stipulated in EIAO-TM and AQOs under unmitigated scenario.  The contour plots of cumulative maximum hourly average TSP, 10th highest daily and annual average PM10 and PM2.5 concentrations at 1.5 metres above ground are presented in Figure Nos. 60334056/EIA/3.03 to 3.07 and Figure Nos. 60334056/EIA/3.16 to 3.20 for the construction of relocated STSTW and the demolition of existing STSTW respectively.  As the predicted dust impact exceeds the criteria, proper dust mitigation measures should be implemented.

3.7.2               Operation Phase

3.7.2.1           In response to the public concern on the potential odour impact during operation of the relocated STSTW, the following appropriate odour control measures would be implemented.

(i)         Adopting the advantage of caverns as natural barriers for odour control;

(ii)        Covering up of odour sources;

(iii)       Preventing odour leakage through the access tunnels by applying negative pressure inside caverns;

(iv)       Installing deodourizing units to clean up the collected foul air;

(v)        Discharging exhausted air at height to further enhance the dilution effect; and

(vi)       Enhancing the odour management of the sludge transportation.

3.7.2.2           The ventilation shaft for the relocated STSTW would be sit at a remote location on the hill, The odour emission from the ventilation shaft exhaust is to be treated by deodourizers at 80% - 97% odour removal efficiency (three deodourizers at 97% and one at 80%) before venting to the ambient.  The proposed deodourization technologies include activated carbon and biotrickling filter.  Subject to the detailed design, a combination of both technologies may be utilized for enhanced odour removal performance.  To minimize the involvement of the handling of chemicals, chemical scrubbers are not considered.  The odour impacts on representative ASRs in interim and ultimate stages are predicted and the assessment results are summarized in Table 3.15 and Table 3.16, respectively.  The maximum 5-second average odour concentration among representative ASRs in the interim and ultimate stages are 0.9 OU/m3 and 0.8 OU/m3, respectively.  The odour concentration at each representative ASR is well below the criterion of 5 OU/m3.

3.7.2.3           According to Table 3.15 and Table 3.16, the maximum odour concentration would likely occur at 30 meters above ground (mAG) for low-rise building, and 100 mAG and 120 mAG for high-rise building.  Therefore ambient odour concentrations at these levels, as well as the lowest assessment level 1.5 mAG are predicted.  The contour plots of 5-second average odour concentration at 1.5 mAG, 30 mAG, 100 mAG and 120 mAG are presented respectively in Figure Nos. 60334056/EIA/3.27, 3.28, 3.29 and 3.30 for interim stage and Figure Nos. 60334056/EIA/3.31, 3.32, 3.33 and 3.34 for ultimate stage.  The prediction odour impacts on ASRs with sensitive uses at these levels are well below the criterion of 5 OU/m3.  No adverse odour impact due to the operation of the relocated STSTW would be expected.


Table 3.15             Predicted Operational Odour Impact on Representative Air Sensitive Receivers (Interim Stage)

5-second Average Odour Concentrations in OU/m3 at Different Heights (Height in mAG)

ASR ID

1.5

5

10

20

30

40

50

60

70

80

90

100

110

120

ASR1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

-

-

-

-

ASR1a

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.2

0.2

0.3

-

-

-

-

ASR1b

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

-

-

-

-

-

ASR1c

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.2

0.2

-

-

-

-

-

ASR2

0.1

0.1

0.1

0.1

-

-

-

-

-

-

-

-

-

-

ASR3

0.1

0.1

0.1

0.1

0.1

-

-

-

-

-

-

-

-

-

ASR4

0.1

0.1

0.1

0.1

0.1

-

-

-

-

-

-

-

-

-

ASR5

0.1

0.1

0.1

-

-

-

-

-

-

-

-

-

-

-

ASR6

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.2

0.2

0.2

ASR7

0.1

0.1

0.1

0.1

0.1

-

-

-

-

-

-

-

-

-

ASR8

0.2

0.2

0.2

-

-

-

-

-

-

-

-

-

-

-

ASR9

0.2

0.2

0.2

-

-

-

-

-

-

-

-

-

-

-

ASR10

0.3

0.3

0.3

0.3

0.3

-

-

-

-

-

-

-

-

-

ASR11

0.3

0.3

0.3

0.3

-

-

-

-

-

-

-

-

-

-

ASR12

0.0

0.0

0.1

0.1

-

-

-

-

-

-

-

-

-

-

ASR13

0.0

0.0

0.0

0.1

-

-

-

-

-

-

-

-

-

-

ASR14

0.2

0.2

0.2

-

-

-

-

-

-

-

-

-

-

-

ASR15

0.2

-

-

-

-

-

-

-

-

-

-

-

-

-

ASR16

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.2

0.2

0.3

ASR17

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

-

-

-

ASR18

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

-

-

ASR19

0.3

0.3

0.3

0.3

-

-

-

-

-

-

-

-

-

-

ASR20

0.3

0.3

0.3

-

-

-

-

-

-

-

-

-

-

-

ASR21

0.2

0.2

0.2

-

-

-

-

-

-

-

-

-

-

-

ASR22

0.3

0.3

0.3

0.3

0.3

0.3

0.3

-

-

-

-

-

-

-

ASR23

0.1

0.1

0.1

0.1

0.2

0.2

0.2

0.3

0.4

-

-

-

-

-

ASR24

0.2

0.2

0.2

-

-

-

-

-

-

-

-

-

-

-

ASR25

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.3

0.3

0.2

ASR26

0.2

0.2

0.2

0.2

0.2

0.2

-

-

-

-

-

-

-

-

ASR27

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

-

-

-

-

ASR28

0.2

0.2

0.2

0.2

0.2

0.2

0.3

-

-

-

-

-

-

-

ASR29

0.3

0.3

0.3

0.3

0.3

0.3

0.3

-

-

-

-

-

-

-

ASR30

0.9

0.9

0.9

0.9

0.9

0.9

0.9

0.9

0.9

0.9

0.9

0.9

0.9

0.6

ASR31

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.2

0.2

0.3

0.3

0.4

0.5

 

Table 3.16             Predicted Operational Odour Impact on Representative Air Sensitive Receivers (Ultimate Stage)

5-second Average Odour Concentrations in OU/m3 at Different Heights (Height in mAG)

ASR ID

1.5

5

10

20

30

40

50

60

70

80

90

100

110

120

ASR1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

-

-

-

-

ASR1a

0.1

0.1

0.1

0.1

0.1

0.1

0.2

0.2

0.3

0.4

-

-

-

-

ASR1b

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

-

-

-

-

-

ASR1c

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.2

0.3

-

-

-

-

-

ASR2

0.1

0.1

0.1

0.1

-

-

-

-

-

-

-

-

-

-

ASR3

0.1

0.1

0.1

0.1

0.1

-

-

-

-

-

-

-

-

-

ASR4

0.1

0.1

0.1

0.1

0.1

-

-

-

-

-

-

-

-

-

ASR5

0.1

0.1

0.1

-

-

-

-

-

-

-

-

-

-

-

ASR6

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.2

0.2

0.2

0.3

ASR7

0.1

0.1

0.1

0.1

0.1

-

-

-

-

-

-

-

-

-

ASR8

0.3

0.3

0.3

-

-

-

-

-

-

-

-

-

-

-

ASR9

0.3

0.3

0.3

-

-

-

-

-

-

-

-

-

-

-

ASR10

0.4

0.4

0.4

0.4

0.4

-

-

-

-

-

-

-

-

-

ASR11

0.3

0.3

0.3

0.3

-

-

-

-

-

-

-

-

-

-

ASR12

0.0

0.0

0.0

0.1

-

-

-

-

-

-

-

-

-

-

ASR13

0.0

0.0

0.0

0.1

-

-

-

-

-

-

-

-

-

-

ASR14

0.3

0.3

0.3

-

-

-

-

-

-

-

-

-

-

-

ASR15

0.2

-

-

-

-

-

-

-

-

-

-

-

-

-

ASR16

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.1

0.2

0.2

0.3

0.4

ASR17

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

-

-

-

ASR18

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.3

-

-

ASR19

0.3

0.3

0.3

0.3

-

-

-

-

-

-

-

-

-

-

ASR20

0.3

0.3

0.3

-

-

-

-

-

-

-

-

-

-

-

ASR21

0.2

0.2

0.2

-

-

-

-

-

-

-

-

-

-

-

ASR22

0.4

0.4

0.4

0.4

0.4

0.4

0.4

-

-

-

-

-

-

-

ASR23

0.2

0.2

0.2

0.2

0.2

0.2

0.3

0.4

0.5

-

-

-

-

-

ASR24

0.3

0.3

0.3

-

-

-

-

-

-

-

-

-

-

-

ASR25

0.2

0.2

0.2

0.2

0.2

0.2

0.2

0.3

0.3

0.3

0.3

0.3

0.3

0.3

ASR26

0.2

0.2

0.2

0.2

0.2

0.2

-

-

-

-

-

-

-

-

ASR27

0.2

0.2

0.2

0.2

0.3

0.3

0.3

0.3

0.3

0.3

-

-

-

-

ASR28

0.3

0.3

0.3

0.3

0.3

0.3

0.3

-

-

-

-

-

-

-

ASR29

0.4

0.4

0.4

0.4

0.4

0.4

0.4

-

-

-

-

-

-

-

ASR30

0.7

0.7

0.7

0.7

0.7

0.7

0.7

0.7

0.7

0.7

0.8

0.8

0.8

0.8

ASR31

0.1

0.1

0.1

0.2

0.2

0.2

0.2

0.2

0.2

0.3

0.3

0.4

0.5

0.6

 


3.8                  Mitigation of Adverse Environmental Impacts

3.8.1               Construction Phase

3.8.1.1           In order to minimize the construction dust impact, the following dust mitigation measures shall be implemented:

¡P         Watering eight times a day on active works areas, exposed areas and unpaved haul roads to reduce dust emission by 87.5%.  The calculation for the proposed dust suppression efficiency by watering is presented in Appendix 3.02f.  Any potential dust impact and watering mitigation would be subject to the actual site condition.  For example, a construction activity that produces inherently wet conditions or in cases under rainy weather, the above water application intensity may not be unreservedly applied.  While the above watering frequency is to be followed, the extent of watering may vary depending on actual site conditions but should be sufficient to achieve the removal efficiency.  The dust levels would be monitored and managed under an EM&A programme as specified in the EM&A Manual.

3.8.1.2           With the implementation of the above measures, the predicted cumulative maximum hourly average TSP, 10th highest daily and annual average PM10 and PM2.5 concentrations at the representative ASRs are summarized in Table 3.17 and Table 3.18 for construction of Sha Tin CSTW and demolition of existing STSTW respectively.  The contour plots of cumulative maximum hourly average TSP, 10th highest daily and annual average PM10 and PM2.5 concentrations at 1.5 mAG are presented in Figure Nos. 60334056/EIA/3.08 to 3.10 and 3.14 to 3.15 and  Figure Nos. 60334056/EIA/3.21 to 3.23 and 3.25 to 3.26 for construction of relocated STSTW and demolition of existing STSTW respectively.

Table 3.17          Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Construction of Relocated STSTW) (Tier 1, Mitigated Scenario)

ASR

Assessment Height (mAG)

Cumulative Concentration (µg/m3)

Maximum Hourly TSP

10th Highest Daily PM10

10th Highest Daily PM2.5

Annual PM10

Annual PM2.5

ASR1

1.5

979

79

58

40

28

5

948

79

58

40

28

10

820

79

58

40

28

20

523

79

58

40

28

30

285

79

58

40

28

40

211

78

57

40

28

50

184

77

57

40

28

60

162

76

57

40

28

70

145

76

57

40

28

80

138

76

57

40

28

ASR2

1.5

395

79

58

40

28

5

395

79

58

40

28

10

363

79

57

40

28

20

278

79

57

40

28

ASR3

1.5

1148

82

58

40

28

5

1118

82

58

40

28

10

967

81

58

40

28

20

614

79

58

40

28

30

321

77

57

40

28

ASR4

1.5

1786

84

58

40

28

5

1602

84

58

40

28

10

1213

82

58

40

28

20

523

80

58

40

28

30

292

77

57

40

28

ASR5

1.5

587

79

58

40

28

5

586

79

58

40

28

10

531

78

58

40

28

ASR6

1.5

1273

80

57

41

29

5

1214

80

57

40

29

10

1011

80

57

40

28

20

596

77

57

40

28

30

296

77

57

40

28

40

210

77

57

40

28

50

162

76

57

40

28

60

138

76

57

40

28

70

138

76

57

40

28

80

138

76

57

40

28

90

138

76

57

40

28

100

138

76

57

40

28

110

138

76

57

40

28

120

138

76

57

40

28

ASR7

1.5

953

79

57

40

28

5

916

79

57

40

28

10

768

79

57

40

28

20

471

77

57

40

28

30

255

77

57

40

28

ASR8

1.5

1441

105

60

41

29

5

1294

104

60

41

29

10

973

100

59

41

29

ASR9

1.5

813

87

59

40

28

5

793

87

59

40

28

10

687

86

59

40

28

ASR10

1.5

302

75

54

37

26

5

305

75

54

37

26

10

286

75

54

37

26

20

236

75

54

37

26

30

182

74

54

37

26

ASR11

1.5

196

75

55

37

26

5

201

75

55

37

26

10

195

75

55

37

26

20

179

75

54

37

26

ASR12

1.5

280

74

53

37

26

5

239

74

53

37

26

10

174

72

53

37

26

20

157

72

53

37

26

ASR13

1.5

223

74

53

37

26

5

228

74

53

37

26

10

219

74

53

37

26

20

195

73

53

37

26

ASR14

1.5

132

73

55

38

27

5

132

73

55

38

27

10

132

73

55

38

27

ASR15

1.5

619

80

58

40

28

ASR16

1.5

777

77

57

40

28

5

765

77

57

40

28

10

671

77

57

40

28

20

458

77

57

40

28

30

279

77

57

40

28

40

173

77

57

40

28

50

148

76

57

40

28

60

138

76

57

40

28

70

138

76

57

40

28

80

138

76

57

40

28

90

138

76

57

40

28

100

138

76

57

40

28

110

138

76

57

40

28

120

138

76

57

40

28

ASR17

1.5

188

76

57

40

28

5

194

76

57

40

28

10

186

76

57

40

28

20

163

76

57

40

28

30

138

76

57

40

28

40

138

76

57

40

28

50

138

76

57

40

28

60

138

76

57

40

28

70

138

76

57

40

28

80

138

76

57

40

28

90

138

76

57

40

28

ASR18

1.5

150

76

57

40

28

5

156

76

57

40

28

10

151

76

57

40

28

20

138

76

57

40

28

30

138

76

57

40

28

40

138

76

57

40

28

50

138

76

57

40

28

60

138

76

57

40

28

70

138

76

57

40

28

80

138

76

57

40

28

90

138

76

57

40

28

100

138

76

57

40

28

ASR19

1.5

205

76

57

40

28

5

213

76

57

40

28

10

205

76

56

40

28

20

182

76

56

40

28

ASR20

1.5

1136

90

59

41

29

5

1087

90

59

41

29

10

908

88

59

41

28

ASR21

1.5

272

76

57

40

29

5

276

76

57

40

29

10

253

76

57

40

29

ASR22

1.5

227

75

57

40

28

5

231

75

57

40

28

10

210

75

56

40

28

20

159

75

56

40

28

30

142

75

56

40

28

40

142

75

56

40

28

50

141

75

56

40

28

Remark:

Boldfaced value represents that the predicted concentration exceeds the respective criterion.

 


 

Table 3.18          Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Demolition of Existing STSTW) (Tier 1, Mitigated Scenario)

ASR

Assessment Height (mAG)

Cumulative Concentration (µg/m3)

Maximum Hourly TSP

10th Highest Daily PM10

10th Highest Daily PM2.5

Annual PM10

Annual PM2.5

ASR1

1.5

167

78

57

40

28

5

172

78

57

40

28

10

170

78

57

40

28

20

165

77

57

40

28

30

157

77

57

40

28

40

149

77

57

40

28

50

145

76

57

40

28

60

144

76

57

40

28

70

143

76

57

40

28

80

142

76

57

40

28

ASR2

1.5

153

77

57

40

28

5

157

77

57

40

28

10

156

77

57

40

28

20

153

77

57

40

28

ASR3

1.5

185

79

58

40

28

5

190

79

58

40

28

10

187

79

58

40

28

20

178

78

57

40

28

30

166

78

57

40

28

ASR4

1.5

191

79

58

40

28

5

196

79

58

40

28

10

192

79

58

40

28

20

182

78

57

40

28

30

169

78

57

40

28

ASR5

1.5

168

79

58

40

28

5

172

79

58

40

28

10

170

79

58

40

28

ASR6

1.5

231

79

58

40

29

5

237

79

58

40

28

10

226

79

58

40

28

20

198

79

58

40

28

30

174

78

57

40

28

40

167

78

57

40

28

50

160

77

57

40

28

60

154

77

57

40

28

70

147

76

57

40

28

80

142

76

57

40

28

90

138

76

57

40

28

100

138

76

57

40

28

110

138

76

57

40

28

120

138

76

57

40

28

ASR7

1.5

249

79

58

40

28

5

255

79

58

40

28

10

242

79

58

40

28

20

204

79

58

40

28

30

175

78

57

40

28

ASR8

1.5

193

79

58

40

28

5

197

79

58

40

28

10

192

79

58

40

28

ASR9

1.5

168

79

58

40

28

5

171

79

58

40

28

10

168

79

58

40

28

ASR10

1.5

150

74

54

37

28

5

156

74

54

37

28

10

151

74

54

37

28

20

143

73

54

37

28

30

143

73

53

37

28

ASR11

1.5

143

74

54

37

28

5

143

74

54

37

28

10

143

74

54

37

28

20

143

73

54

37

28

ASR12

1.5

143

73

53

37

28

5

143

73

53

37

28

10

143

73

53

37

28

20

143

72

53

37

28

ASR13

1.5

143

73

53

37

28

5

143

73

53

37

28

10

143

73

53

37

28

20

143

72

53

37

28

ASR14

1.5

132

73

55

38

27

5

132

73

55

38

27

10

132

73

55

38

27

ASR15

1.5

295

81

58

40

28

ASR16

1.5

276

79

58

40

28

5

282

79

58

40

28

10

265

79

58

40

28

20

216

79

58

40

28

30

172

78

57

40

28

40

155

77

57

40

28

50

149

77

57

40

28

60

146

76

57

40

28

70

143

76

57

40

28

80

140

76

57

40

28

90

138

76

57

40

28

100

138

76

57

40

28

110

138

76

57

40

28

120

138

76

57

40

28

ASR17

1.5

161

77

57

40

28

5

164

77

57

40

28

10

163

77

57

40

28

20

160

77

57

40

28

30

157

77

57

40

28

40

152

77

57

40

28

50

147

77

57

40

28

60

143

77

57

40

28

70

139

76

57

40

28

80

138

76

57

40

28

90

138

76

57

40

28

ASR18

1.5

151

77

57

40

28

5

154

77

57

40

28

10

153

77

57

40

28

20

152

77

57

40

28

30

149

77

57

40

28

40

147

77

57

40

28

50

144

77

57

40

28

60

141

76

57

40

28

70

138

76

57

40

28

80

138

76

57

40

28

90

138

76

57

40

28

100

138

76

57

40

28

ASR19

1.5

640

82

58

41

29

5

590

82

58

41

29

10

413

81

57

41

29

20

206

79

57

40

28

ASR20

1.5

185

79

59

40

28

5

189

79

58

40

28

10

185

79

58

40

28

ASR21

1.5

491

81

57

41

29

5

461

81

57

41

29

10

337

80

57

41

29

ASR22

1.5

230

85

57

40

28

5

237

85

57

40

28

10

221

84

57

40

28

20

196

81

57

40

28

30

166

80

57

40

28

40

143

78

57

40

28

50

142

78

57

40

28

Remark:

Boldfaced value represents that the predicted concentration exceeds the respective criterion.

 

3.8.1.3           Based on the prediction of Tier 1 screening, the predicted hourly TSP levels and daily RSP levels would still exceed the criterion stipulated in EIAO-TM while the predicted annual RSP levels, daily and annual FSP levels at all representative ASRs would comply with the criteria of AQOs.  During construction of relocated STSTW, the predicted hourly TSP would exceed the criterion at A Kung Kok Fisherman Village (ASR8, ASR9 and ASR20), and area of Chevalier Garden (ASR1), Tai Shui Hang (ASR3, ASR4 and ASR5), and Kam Tai Court (ASR6, ASR7, ASR15 and ASR16).  During demolition of existing STSTW, the predicted hourly TSP would exceed the criterion at Marine Police Outer Waters District Headquarters and Marine Police North Police Station (ASR19).

3.8.1.4           Those ASRs with non-compliance in hourly TSP levels under Tier 1 screening during the construction of relocated STSTW are selected to undergo Tier 2 assessment. Two hot spot areas have been identified by Tier 1 screening, which are A Kung Kok Fishermen Village and Kam Tai Court. Two scenarios of Tier 2 assessment, namely Tier 2a and 2b, are therefore conducted for these two areas accordingly by considering maximum percentage active area of 20% for heavy construction activity and positioning the dust sources closest to the hot spot area.  In fact, the assumption of 20% active area for Tier 2 assessment is a conservative approach as the estimation of maximum active work area is 4.7% for CSTW.  The crusher within the cavern and haul roads are assumed to be working in full capacity in both scenarios.  In particular, dust sources of Main Portal and Area 73 are positioned next and opposite to A Kung Kok Fishermen Village in Tier 2a while they are positioned opposite to Chevalier Garden, Tai Shui Hang and Kam Tai Court in Tier 2b.  Dust sources of A Kung Kok Shan explosives magazine site and Secondary Portal are positioned towards these two areas.  The allocation of dust source in both Tier 2a and 2b is illustrated in Appendix 3.02d.  The predicted results of Tier 2a and 2b are summarized in Table 3.19 and Table 3.20.  The tier 2 contours plots of cumulative maximum hourly average TSP and 10th highest daily average RSP concentrations at 1.5 mAG are presented in Figure Nos. 60334056/EIA/3.11, 3.12 and 3.13.  According to these contour plots, the exceedance zone at 1.5mAG would confine to the construction work areas of main portal area, temporary road and Area 73, and would also appear in hill area southeast of A Kung Kok Fishermen Village.  To confirm that no land lots with air sensitive uses within the exceedance zone at 1.5mAG, a site survey was conducted on 30 December 2015.  Site photos are shown in Appendix 3.07.


 

Table 3.19          Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Construction of Relocated STSTW) (Tier 2a, Mitigated Scenario)

ASR

Assessment Height (mAG)

Cumulative Concentration (µg/m3)

Maximum Hourly TSP

10th Highest Daily PM10

ASR8

1.5

426

83

5

358

81

10

242

79

ASR9

1.5

199

78

5

194

78

10

172

78

ASR20

1.5

283

78

5

271

78

10

227

78

Remark:

Boldfaced value represents that the predicted concentration exceeds the respective criterion.

 

Table 3.20          Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Construction of Relocated STSTW) (Tier 2b, Mitigated Scenario)

ASR

Assessment Height (mAG)

Cumulative Concentration (µg/m3)

Maximum Hourly TSP

ASR1

1.5

262

5

255

10

230

20

173

30

144

40

138

50

138

60

138

70

138

80

138

ASR3

1.5

263

5

256

10

222

20

155

30

139

ASR4

1.5

448

5

400

10

310

20

162

30

138

ASR5

1.5

159

5

159

10

157

ASR6

1.5

346

5

329

10

277

20

180

30

138

40

138

50

138

60

138

70

138

80

138

90

138

100

138

110

138

120

138

ASR7

1.5

298

5

283

10

236

20

156

30

138

ASR15

1.5

219

ASR16

 

1.5

245

5

242

10

216

20

159

30

138

40

138

50

138

60

138

70

138

80

138

90

138

100

138

110

138

120

138

Remark:

Boldfaced value represents that the predicted concentration exceeds the respective criterion.

 

3.8.1.5           Marine Police Outer Waters District Headquarters and Marine Police North Police Station (ASR19) which would be non-compliance in hourly TSP level under Tier 1 screening during demolition of existing STSTW also undergoes a Tier 2 assessment.  The allocation of dust source in Tier 2 is illustrated in Appendix 3.02e.  The predicted results of Tier 2 are presented in Table 3.21.  The Tier 2 contour plot of cumulative maximum hourly TSP concentration is shown in Figure No. 60334056/EIA/3.24.  According to the contour plot, the exceedance area would confine to the area of the demolition work areas and appear at Sha Tin Seafront Salt Water Pumping Station and cycling track outside the existing STSTW.  To confirm that no land lots with air sensitive uses within the exceedance zone at 1.5mAG, a site survey was conducted on 30 December 2015.  Site photos are shown in Appendix 3.07.

Table 3.21          Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Demolition of Existing STSTW) (Tier 2, Mitigated Scenario)

ASR

Assessment Height (mAG)

Cumulative Concentration (µg/m3)

Maximum Hourly TSP

ASR19

1.5

282

5

270

10

213

20

141

Remark:

Boldfaced value represents that the predicted concentration exceeds the respective criterion.

 

3.8.1.6           Based on the contour plots presented above, localized exceedances of particulates concentration are predicted in the vicinity of the Project.  However, no existing or planned ASR is identified within these predicted exceedance areas during the construction phase of the project, which has been confirmed with site survey conducted on 30 December 2015. The modeling results indicate that the predicted cumulative particulate concentrations at all representative ASRs would comply with the respective AQOs and criteria stipulated in EIAO-TM.

3.8.1.7           In addition to the dust control measures described above, dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation and good site practices listed below shall be carried out to further minimize construction dust impact:

¡P         Use of regular watering to reduce dust emissions from exposed site surfaces and unpaved roads, particularly during dry weather.

¡P         Use of frequent watering for particularly dusty construction areas and areas close to ASRs.

¡P         Side enclosure and covering of any aggregate or dusty material storage piles to reduce emissions.  Where this is not practicable owing to frequent usage, watering shall be applied to aggregate fines.

¡P         Open stockpiles shall be avoided or covered.  Where possible, prevent placing dusty material storage piles near ASRs.

¡P         Tarpaulin covering of all dusty vehicle loads transported to, from and between site locations.

¡P         Establishment and use of vehicle wheel and body washing facilities at the exit points of the site.

¡P         Provision of wind shield and dust extraction units or similar dust mitigation measures at the loading area of barging point, and use of water sprinklers at the loading area where dust generation is likely during the loading process of loose material, particularly in dry seasons/ periods.

¡P         Provision of not less than 2.4m high hoarding from ground level along site boundary where adjoins a road, streets or other accessible to the public except for a site entrance or exit.

¡P         Imposition of speed controls for vehicles on site haul roads.

¡P         Where possible, routing of vehicles and positioning of construction plant should be at the maximum possible distance from ASRs.

¡P         Every stock of more than 20 bags of cement or dry pulverized fuel ash (PFA) should be covered entirely by impervious sheeting or placed in an area sheltered on the top and the 3 sides.

¡P         Instigation of an EM&A program to monitor the construction process in order to enforce controls and modify method of work if dusty conditions arise.

3.8.2               Operational Odour Impact

3.8.2.1           With the implementation of proposed odour control measures as mentioned in Section 3.7.2.1 and Section 3.7.2.2, the predicted odour concentrations at the representative ASRs are well below the criterion of 5 OU/m3 and would comply with the EIAO-TM. No further mitigation measure would be required during the operation phase.

 

3.9                  Evaluation of Residual Impacts

3.9.1               Construction Phase

3.9.1.1           With the implementation of the mitigation measures as stipulated in the Air Pollution Control (Construction Dust) Regulation together with the recommended dust control measures and good site practices on the work sites, no adverse residual impact would be expected from construction of relocated STSTW and demolition of existing STSTW and temporary explosives magazine.

3.9.2               Operation Phase

3.9.2.1           During operation phase of the Project, the predicted 5-second average odour concentration at the representative ASRs would comply with the EIAO-TM. No adverse residual impact is expected.

 

3.10                Environmental Monitoring and Audit

3.10.1            Construction Phase

3.10.1.1         EM&A for potential dust impacts should be conducted during the construction phase of the Project so as to check compliance with legislative requirements.  Details of the monitoring and audit programme are contained in a stand-alone EM&A Manual.

3.10.2            Operation Phase

3.10.2.1         No adverse impact would be generated during the operation phase of CSTW. Therefore, odour monitoring at the inlet and outlet of the deodourizing units is proposed to be conducted for first three years of the operation of CSTW, quarterly in the first year, and once every 6 months in the second and third years if monitoring results remain below the limit levels.  An Odour Complaint Registration System is also proposed in the EM&A programme to check whether the deodorizing units can fulfill the recommended odour removal performance. 

3.10.2.2         Any unexpected leakage from tanks could be observed with monitoring equipment.  Monitoring equipment would be installed in the CSTW to monitor the concentration of H2S, carbon monoxide (CO) and carbon dioxide (CO2) and methane. Investigation and repair works would be carried out immediately if abrupt increase of these concentrations are reported. Emergency Plan would be established for these upset conditions.

 

3.11                Conclusion

3.11.1            Construction Phase

3.11.1.1         The potential air quality impacts from the construction works of the Project including decommissioning and demolition of existing STSTW and temporary explosives magazine  would mainly be related to construction dust from excavation, materials handling, spoil removal and wind erosion.  With the implementation of mitigation measures specified in the Air Pollution Control (Construction Dust) Regulation together with the recommended dust suppression measures, good site practices, and EM&A programme, the predicted dust impact at ASRs would comply with the hourly, daily and annual particulate criteria stipulated in the AQOs and EIAO-TM.

3.11.2            Operation Phase

3.11.2.1         The relocated STSTW is fully enclosed in the cavern and the potential odour emission from the sewage treatment facilities would all be treated in the deodourizing units before discharge into atmosphere from the ventilation shaft which is located at a remote area on the hill.  With further implementation of odour control measures as mentioned in Section 3.7.2, the assessment results show that the predicted 5-second average odour concentration at the representative ASRs and within the Study Area would comply with the criterion in EIAO-TM.  The Project is considered to have considerable improvement on the air quality condition at the study area as comparing with the operation of existing STSTW.

3.11.2.2         No air quality impact is anticipated with the operation of the water reclamation facilities inside cavern. 

 

<End of Section 3>

 

 

 



[1]        Richard A. Duffee, Martha A. O¡¨Brien and Ned Ostojic (1991). Odor Modeling ¡V Why and How, Recent Developments and Current Practices in Odor Regulation, Controls and Technology, Air & Waste Management Association

[2]        Keddie, A. W. C (1980). Dispersion of Odours, Odour Control ¡V A Concise Guide, Warren Spring Laboratory

[3]        Turner, D. (1994). Workbook of Atmosphere Dispersion Estimates, 2nd Edition, Lewis Publishers