TABLE OF CONTENTS
Page
4 NOISE Impact. 4-3
4.1 Introduction. 4-3
4.2 Environmental Legislation, Standards and Criteria. 4-3
4.3 Description of Environment 4-7
4.4 Noise Sensitive Receivers. 4-7
4.5 Identification of Pollutant Sources. 4-10
4.6 Assessment Methodology. 4-12
4.7 Prediction and Evaluation of Environmental Impacts. 4-16
4.8 Mitigation of Adverse Environmental Impacts. 4-19
4.9 Evaluation of Residual Impacts. 4-21
4.10 Environmental Monitoring and Audit 4-23
4.11 Conclusion. 4-24
LIST OF TABLES
Table 4.1 Area Sensitivity Ratings (ASRs) 4-3
Table 4.2 Basic Noise Levels (BNLs) 4-4
Table 4.3 Ground-borne Noise Criteria (ANL, Leq, 5min dB(A)) 4-5
Table 4.4 Acceptable Noise Level for Fixed Plant Noise. 4-6
Table 4.5 Background Noise Measurement Results. 4-6
Table 4.6 Representative Noise Sensitive Receivers affected by
Relocated STSTW to Cavern during Construction and Operation Phases. 4-8
Table 4.7 Acceptable Noise Levels of the Representative Noise
Sensitive Receivers. 4-8
Table 4.8 Fixed Plant Noise Criteria of Representative Noise
Sensitive Receivers. 4-9
Table 4.9 Representative Noise Sensitive Receivers for
Assessment of Ground-borne Noise Impacts Due to Construction Works. 4-9
Table 4.10 Representative Noise Sensitive Receivers affected by
Decommissioning/Demolition of the Existing STSTW.. 4-10
Table 4.11 Summary of Reference Vibration Level of PMEs. 4-14
Table 4.12 Wave Propagation Properties of Soil 4-14
Table 4.13 Loss factor for Coupling into Building Foundation. 4-14
Table 4.14 Unmitigated Construction Noise Levels due to the
Project at Representative NSRs During Normal Daytime Working Hours. 4-17
Table 4.15 Predicted Construction Ground-borne Noise Impact
Associated with the PME Use at Open Works Areas 4-17
Table 4.16 Maximum Sound Power Levels for Fixed Plant Noise
Sources. 4-18
Table 4.17 Predicted Fixed Plant Noise Levels at Representative
Noise Sensitive Receivers. 4-18
Table 4.18 Mitigated Construction Noise Levels due to the Project
at Representative NSRs During Normal Daytime Working Hours (Using Quiet PME) 4-19
Table 4.19 Mitigated Construction Noise Levels due to the Project
at Representative NSRs During Normal Daytime Working Hours (with further
Mitigation Measures) 4-20
Table 4.20 Evaluation of Residual Noise Impacts during
Construction Phase. 4-22
LIST OF FIGURES
60334056/EIA/4.01 Locations
of Representative Noise Sensitive Receivers for Construction Noise and
Operation Fixed Plant Noise
60334056/EIA/4.02 Location
of Temporary Access Haul Road During Construction Phase
60334056/EIA/4.03 Locations
of Representative Noise Sensitive Receivers for Ground-Borne Noise During
Construction Phase
LIST OF APPENDICES
Appendix
4.01 Measured Prevailing
Background Noise Levels
Appendix
4.02 Photographs of Existing
Noise Sensitive Receivers
Appendix
4.03 Construction Programme
for Noise Calculations
Appendix
4.04 Construction Plant
Inventory under Unmitigated Scenario
Appendix
4.05 Predicted Construction
Noise Levels under Unmitigated Scenario
Appendix
4.06 Calculation of
Construction Ground-borne Noise (Unmitigated Scenario)
Appendix
4.07 Peak Traffic Flow during
Construction Phase and Operation Phase
Appendix
4.08 Calculation of Maximum
Allowable Sound Power Levels for Fixed Plant Noise
Appendix
4.09 Construction Plant
Inventory under Mitigated Scenario
Appendix
4.10 Predicted Construction
Noise Levels under Mitigated Scenario
4
NOISE Impact
4.1.1.1
This section presents an assessment of the
potential noise impacts associated with the construction and operation of the
Project. The noise impact assessment is
conducted in accordance with the requirements of Annex 5 and Annex 13 of the
EIAO-TM as well as the requirements set out under Clause 3.4.2 of the EIA Study
Brief.
4.2.1.1
Noise impacts are assessed in accordance with the criteria and methodology
given in the Technical Memoranda made under the NCO, and the EIAO-TM.
4.2.1.2
The NCO provides the statutory framework for
noise control. This defines
statutory limits applicable to equipment used during the construction and
operation phases of the proposed works in the study area. The NCO invokes four Technical
Memoranda, which define the technical means for noise assessment:
¡P
Technical Memorandum on Noise
from Places other than Domestic Premises, Public Places or Construction Sites
(IND-TM);
¡P
Technical Memorandum on Noise
from Construction Work in Designated Areas (DA-TM);
¡P
Technical Memorandum on Noise
from Construction Work other than Percussive Piling (GW-TM); and
¡P
Technical Memorandum on Noise
from Percussive Piling (PP-TM).
4.2.1.3
The NCO and the accompanying Technical Memoranda
provide a mechanism for assessing noise levels and provide the statutory power
to control noise.
4.2.1.4
With regard to the assessments of the
construction noise impact during restricted hours and operational fixed plant noise impact, the
NCO designates acceptable noise levels for Noise Sensitive Receivers (NSRs) on
the basis of an Area Sensitivity Rating (ASR), based on the characteristics of
the area within which they are located such as rural, village, low-density
residential, or urban (see Table 4.1). Within these areas, the presence
of "influencing factors"
(IFs) (such as the presence of industrial activities or major roads) can
further affect the ASR and hence the acceptable noise levels.
Table 4.1 Area
Sensitivity Ratings (ASRs)
|
|
|
|
|
Rural Area
|
A
|
B
|
B
|
Urban Area
|
B
|
C
|
C
|
Low density residential area
consisting of low-rise or isolated high-rise developments
|
A
|
B
|
C
|
Area other than those above
|
B
|
B
|
C
|
4.2.2
Construction Noise ¡V General Construction
4.2.2.1
The NCO provides the statutory framework for
noise control of construction works, other than percussive piling, using PME
between the hours of 1900 and 0700 hours or at any time on Sundays and general
holiday (i.e. restricted hours).
Noise control on construction activities taking place at other times is
subject to the Criteria for Evaluating Noise Impact stated in Table 1B of Annex
5 in the EIAO-TM. The noise limit
is Leq(30 minutes) 75 dB(A) at the façades of dwellings and Leq(30
minutes) 70 dB(A) at the façade of schools (Leq(30 minutes) 65
dB(A) during examinations).
Table 4.2 Basic
Noise Levels (BNLs)
|
|
|
|
|
Evening (1900 to 2300 hours) (1)
|
60
|
65
|
70
|
Night (2300 to 0700 hours)
|
45
|
50
|
55
|
Note: (1) Includes Sundays and Public
Holidays during daytime and evening
4.2.2.3
The Noise Control Authority will consider a
well-justified CNP application, for construction works within restricted hours as
guided by the relevant Technical Memoranda issued under the NCO. The Noise Control Authority will take
into account of contemporary conditions / situations of adjoining land uses and
any previous complaints against construction activities at the site before
making his decision in granting a CNP.
Nothing in this EIA shall bind the Noise Control Authority in making his
decision. If a CNP is to be issued,
the Noise Control Authority shall include in it any condition he thinks
fit. Failure to comply with any
such conditions will lead to cancellation of the CNP and prosecution action
under the NCO.
4.2.2.4
Under the DA-TM, the use of five types of
Specified Powered Mechanical Equipment (SPME) and three types of Prescribed
Construction Work (PCW) within a designated area during restricted hours would
require a valid CNP. The SPME
includes hand-held breaker, bulldozer, concrete lorry mixer, dump truck and
hand-held vibratory poker. The PCW
are:
¡P
Erecting or dismantling of
formwork or scaffolding;
¡P
Loading, unloading or handling
of rubble, wooden boards, steel bars, wood or scaffolding material; and
¡P
Hammering.
4.2.2.5
In general, it should not be presumed that a CNP
would be granted for carrying out PCW within a designated area during
restricted hours. The CNP may be
granted for the execution of construction works during restricted hours
involving the use of PME and/ or SPME if the relevant ANLs and criteria stipulated in the GW-TM and DA-TM can be met.
4.2.2.6
Percussive piling is prohibited between 1900 and
0700 hours on any weekday not being a general holiday and at any time on Sunday
or general holiday. A CNP is
required for the carrying out of percussive piling between 0700 and 1900 hours
on any day not being a general holiday.
PP-TM sets out the requirements for working and determination of the
permitted hours of operations. Referring to the construction method for
the Project, percussive piling is not required.
4.2.3.1
Construction ground-borne noise is under the
control of the NCO, the EIAO, and their subsidiary Technical Memorandum. With reference to the IND-TM under the
NCO, the criteria for noise transmitted primarily through the structural
elements of the building or buildings should be 10dB(A) less than the relevant
ANL. These criteria apply to all
residential buildings, schools, clinics, hospitals, temples and churches.
4.2.3.2
The construction ground-borne noise criteria in
daytime (0700-1900 hours) (except General Holidays & Sunday) will therefore
be 10dB(A) less than the Criteria for Evaluating Noise Impact stated in Table
1B of Annex 5 in the EIAO-TM:
¡P
Leq(30 minutes) 65
dB(A) at the façades of dwellings;
¡P
Leq(30 minutes) 60
dB(A) at the façade of schools (Leq(30 minutes) 55 dB(A) during
examinations)
4.2.3.3
As descripted in Section
4.2.2.2, construction noise (including construction ground-borne noise)
within restricted hours (i.e. between 1900 and 0700 on a normal working day or
at any time on a general holiday and Sunday) is controlled by the GW-TM. A CNP is required for construction
activities involving the use of PME carried out in restricted hours and the
construction ground-borne noise at NSRs shall be limited to 10 dB(A) below the
respective ANLs for the ASR category of ¡§A¡¨, ¡§B¡¨ and ¡§C¡¨ at the NSRs. A summary of these criteria is given in Table 4.3.
Table 4.3 Ground-borne
Noise Criteria (ANL, Leq, 5min dB(A))
|
|
|
|
|
Evening (1900 to 2300 hours) (1)
|
50
|
55
|
60
|
Night (2300 to 0700 hours)
|
35
|
40
|
45
|
Note: (1) Includes Sundays and Public
Holidays during daytime and evening
4.2.4.1
There is no statutory procedure or criteria under
the NCO and EIAO for assessing the blasting impacts and is therefore beyond the
scope of the EIA. However, the
administrative and procedural control of all blasting operations in Hong Kong
is vested in the Mines Division of the CEDD. The Dangerous Goods (General)
Regulations, Chapter 295B also
stipulates that no person shall carry out blasting unless he possesses a valid
mine blasting certificate to be issued by the Mines Division of CEDD. The Superintendent of Mines will review
the application on a case-by-case basis before issuing the Mine Blasting
Certificate. According to the
Clause 2.1.2 of EIA Study Brief, alternative construction methods to replace
basting have been considered to minimise
the construction noise impact as far as possible. TBM method would be adopted
for the laying of pipelines below Shing Mun River or in hard rock. For the
construction of caverns, as discussed in Section 2.8.2, the
drill-and-blast method would be the most effective solution in this Project.
Furthermore, the drill-and-blast method for the caverns could shorten the
construction period and therefore minimize the noise nuisance induced. Blasting
should be carried out outside sensitive hours as far as practicable, and the
blasting schedule should be submitted to the concerned authority for approval
prior for its implementation.
4.2.5.1
For road traffic noise, Annex 5, Table 1A ¡§A Summary
of Noise Criteria¡¨ of the EIAO-TM defines the criteria L10(1 hour)
for the road traffic noise at various NSRs:
¡P
70dB(A) at the façades of
residential dwellings, hotels, offices;
¡P
65dB(A) at the façades of
schools, places of public worship, courts of law, places where unaided voice
communication is required; and
¡P
55dB(A) at the façades of
hospital or clinics.
4.2.6.1
Fixed plant noise sources are controlled by the
NCO and IND-TM. The ANLs for the
NSRs are determined based on the ASR.
The ANLs for different ASRs during different periods are summarised in Table
4.4 below.
Table 4.4 Acceptable
Noise Level for Fixed Plant Noise
|
|
|
|
|
Day (0700 to 1900 hours)
|
60
|
65
|
70
|
Evening (1900 to 2300 hours)
|
60
|
65
|
70
|
Night (2300 to 0700 hours)
|
50
|
55
|
60
|
4.2.6.2
The NSRs at the north of the relocated STSTW are
high rise housing developments as well as low rise development such as village
houses and education institutions.
This area is not urban area or rural area. The type of this area is considered as
¡§Area other than those above¡¨.
Since traffic noise from busy Tate¡¦s Cairn Highway which is an IF affect
some NSRs in this area. The ASR of
the NSRs in this area would be ¡§B¡¨ or ¡§C¡¨ depending on whether the IF directly
or indirectly affects or does not affect the respective NSRs.
4.2.6.3
The other NSRs located at the west and
south-west of the relocated STSTW are village houses and low rise Government,
Institution or Community (GIC) developments. These NSRs are located next to the green
belt area, therefore, the type of these NSRs is considered as ¡§Rural
Area¡¨. However, the NSRs at the
west of the site are directly affected by traffic noise from Tate¡¦s Cairn
Highway and the ASR for this area is considered as ¡§B¡¨. The ASR of the NSRs at the south-west of
the site is considered as ¡§A¡¨ in the assessment.
4.2.6.4
The
relocated STSTW and associated facilities would be operated 24-hour a day, ANL
for night time with lower acceptable noise levels is adopted as the noise
criteria for fixed noise sources for residential NSRs. Whereas for school, the ANLs for daytime and evening
period are adopted in
view of the normal opening hours of school.
4.2.6.5
As stipulated in Annex 5 of the EIAO-TM, the
noise standard for planning purposes for fixed noise source are (a) 5 dB(A)
below the appropriate ANL, or (b) the prevailing background noise levels (for
quiet areas with level 5 dB(A) below the ANL). In this regard, noise measurement was
undertaken in the vicinity of the representative NSRs to study the prevailing
noise level. The measured prevailing background noise results are presented in
Appendix 4.01 and summarized
in below Table 4.5. Should the prevailing background noise level be lower than the ANL by
more than 5dB(A), the background noise level would be adopted as the assessment
criteria.
Table 4.5 Background
Noise Measurement Results
Measurement Location
|
Description
|
Measured Min Leq 30-min, dB(A)
|
Measurement Method
|
Day / Evening [1]
|
Night [2]
|
M1
|
Chevalier Garden
|
44
|
42
|
Façade
|
M2
|
Wellborn Kindergarten
|
46
|
45
|
Façade
|
M4
|
Ma On Shan Tsung Tsin Secondary School
|
61
|
53
|
Free-field [3]
|
M5
|
SKH Ma On Shan Holy Spirit
Primary School
|
59
|
52
|
Free-field [3]
|
M6
|
Ah Kung Kok Fisherman¡¦s
Village
|
56
|
49
|
Façade
|
M7
|
The Neighbourhood
Advice-Action Council Harmony Manor
|
49
|
44
|
Façade
|
Notes:
[1] Daytime means 07:00 ¡V 19:00 and Evening time
means 19:00 ¡V 23:00.
[2] Night time means 23:00 ¡V 07:00 of the next
day.
[3] Façade correction of
+3 dB(A) has been added to the measurement results for free-field measurement.
4.2.6.6
In any event, the ASR assumed in the EIA Report
is for indicative assessment only.
It should be noted that the fixed noise sources are controlled under
Section 13 of the NCO. At the time
of investigation, the Noise Control Authority shall determine noise impact from
concerned fixed noise sources on the basis of prevailing legislation and
practices being in force and taking account of contemporary
conditions/situations of adjoining land uses. Nothing in the EIA Report shall bind the
Noise Control Authority in the context of law enforcement against all the fixed
noise sources being assessed.
4.3.1.1
The relocated STSTW is located at Nui Po Shan at
the east of Shing Mun River.
Surrounding area of the relocated STSTW is a mixture of residential
uses, village type development and institutional uses. The existing noise climate of the study
area is dominated by the railway noise from the existing Ma On Shan Line and
traffic noise arising from Tate¡¦s Cairn Highway, Ma On Shan Road and A Kung Kok
Street. The study area for noise impact
assessment for the works of the relocated STSTW is defined by a distance of
300m from the Project boundary as shown in Figure No. 60334056/EIA/4.01.
4.3.1.2
The existing STSTW is located on the coast at
the mouth of the Shing Mun River where it enters Tolo Harbour. The site occurs within urban developed area,
surrounded by residential buildings in the west and Sha Tin Racecourse in the
south. The study area for noise
impact assessment for the works of the decommissioning of the existing STSTW is defined by a distance of
300m from the site boundary of the existing STSTW.
4.4.1.1
The study area for noise impact assessment is
defined by a distance of 300m from the site boundary of the construction site
and the cavern for the relocated STSTW.
The representative NSRs for the construction and operation of the
relocated STSTW are identified and given in Table 4.6
below. Their locations are shown in
Figure No. 60334056/EIA/4.01.. Photographs of all the identified existing NSRs
are provided in Appendix
4.02.
Table 4.6 Representative
Noise Sensitive Receivers affected by Relocated STSTW to Cavern during
Construction and Operation Phases
|
|
|
|
|
NR-C01
|
Chevalier Garden
|
Residential
|
70
|
C/O
|
NR-C02
|
Wellborn Kindergarten
|
Education
|
160
|
C/O
|
NR-C03
|
Hay Nien Primary School
|
Education
|
110
|
C/O
|
NR-C04
|
Ma On Shan Tsung Tsin Secondary
School
|
Education
|
90
|
C/O
|
NR-C05
|
Tai Shui Hang Village
|
Residential
|
210
|
C/O
|
NR-C06
|
Kam Tai Court
|
Residential
|
180
|
C/O
|
NR-C07
|
S.K.H. Ma On Shan Holy Spirit
Primary School
|
Education
|
210
|
C/O
|
NR-C08
|
Ah Kung Kok Fishermen Village
|
Residential/ Retail
|
10
|
C/O
|
NR-C09
|
Hong Kong Mountaineering Union
|
Societal / Storage
|
220
|
C
|
NR-C10
|
The Neighbourhood Advice-Action
Council Harmony Manor
|
Mental Health
Hospital
|
100
|
C/O
|
NR-C11
|
Shing Mun Springs Rehabilitation
Centre
|
Rehabilitation Centre
|
240
|
C
|
Note:
Construction
Assessment refers to assessment for noise impact due to construction of Cavern
STSTW; Operation Assessment refers to assessment of fixed plant noise impact
from operation of CSTW.
4.4.1.2
Table 4.7 presents
the ANLs of the representative NSRs based on the fixed plant noise criteria
mentioned in above Section 4.2.6. Considering the ANLs and the background noise
measurement results presented in Table 4.5, Table 4.8 presents the fixed plant noise criteria
of the representative NSRs in this assessment.
Table 4.7 Acceptable
Noise Levels of the Representative Noise Sensitive Receivers
NSR
|
Influence Factor (IF)
|
AADT
|
Degree to which NSR is affected by IF
|
Area Sensitive Rating (ASR)
|
ANL, dB(A)
|
Day / Evening
|
Night
|
NR-C01
|
N/A
|
N/A
|
Not Affected
|
A
|
60
|
50
|
NR-C02
|
N/A
|
N/A
|
Not Affected
|
A
|
60
|
-
|
NR-C03
|
Ma On Shan Road
|
37,730
|
Indirectly Affected
|
B
|
65
|
-
|
Tate¡¦s Cairn Highway
|
64,620
|
NR-C04
|
Ma On Shan Road
|
37,730
|
Indirectly Affected
|
B
|
65
|
-
|
Tate¡¦s Cairn Highway
|
64,620
|
NR-C05
|
Ma On Shan Road
|
37,730
|
Indirectly Affected
|
B
|
65
|
55
|
NR-C06
|
Ma On Shan Road
|
37,730
|
Directly Affected
|
C
|
70
|
60
|
Tate¡¦s Cairn Highway
|
64,620
|
NR-C07
|
Ma On Shan Road
|
37,730
|
Directly Affected
|
C
|
70
|
-
|
Tate¡¦s Cairn Highway
|
64,620
|
NR-C08
|
Ma On Shan Road
|
37,730
|
Indirectly Affected
|
B
|
65
|
55
|
Tate¡¦s Cairn Highway
|
64,620
|
NR-C10
|
N/A
|
N/A
|
Not Affected
|
A
|
60
|
50
|
Note:
AADT refers to the
annual average daily traffic referenced to The Annual Traffic Census (ATC) 2014
of the Transport Department.
Table 4.8 Fixed Plant Noise Criteria of
Representative Noise Sensitive Receivers
NSR
|
ANL - 5, dB(A)
|
Background Noise Measurement Location
|
Measured Min Noise Level, dB(A)
|
Fixed Plant Noise Criteria, dB(A)
|
Day
|
Night
|
Day
|
Night
|
NR-C01
|
55
|
45
|
M1
|
44
|
42
|
42
|
NR-C02
|
55
|
-
|
M2
|
46
|
-
|
46
|
NR-C03
|
65
|
-
|
M4
|
61
|
-
|
61
|
NR-C04
|
60
|
-
|
M4
|
61
|
-
|
60
|
NR-C05
|
60
|
50
|
M4
|
61
|
53
|
50
|
NR-C06
|
65
|
55
|
M5
|
59
|
52
|
52
|
NR-C07
|
65
|
-
|
M5
|
59
|
52
|
52
|
NR-C08
|
60
|
50
|
M6
|
56
|
49
|
49
|
NR-C10
|
55
|
45
|
M7
|
49
|
44
|
44
|
4.4.1.3
Under the assumption of worst-case scenario, six NSRs are identified for the
assessment of ground-borne
noise impact due to the use of PME at close vicinity. These identified
NSRs are presented in Table 4.9 and its locations are
shown in Figure No.
60334056/EIA/4.03.
Table 4.9 Representative
Noise Sensitive Receivers for Assessment of Ground-borne Noise Impacts Due to
Construction Works
|
|
|
|
|
GBNSR-1
|
Chevalier Garden
|
Residential
|
Main Portal
|
78
|
GBNSR-2
|
Ah Kung Kok Fishermen Village
|
Residential
|
Main Portal
|
44
|
GBNSR-3
|
The Neighbourhood Advice-Action
Council Harmony Manor
|
Mental Health
Hospital
|
Access Road for
Ventilation Shaft and Project Explosives
Magazine at A Kung Kok Shan
|
29
|
GBNSR-4
|
Kam Tai Court
|
Residential
|
Emergency Outfall
Construction
|
24
|
GBNSR-5
|
Seaview Villa
|
Residential
|
Decommissioning and
Demolition of Existing STSTW
|
157
|
GBNSR-6
|
Ma On Shan Tsung Tsin Secondary
School
|
Education
|
Main Portal
|
95
|
4.4.1.4
The representative NSRs which are likely to be affected
by demolition of existing STSTW are identified and given in Table
4.10 below. Their locations
are shown in Figure No.
60334056/EIA/4.01.
Photographs of these identified existing NSRs are provided in Appendix 4.02.
Table 4.10 Representative
Noise Sensitive Receivers affected by Decommissioning/Demolition of the
Existing STSTW
|
|
|
|
NR-D01
|
Seaview Villa
|
Residential
|
150
|
NR-D02
|
Kam On Garden
|
Residential
|
220
|
NR-D03
|
Sha Tin Lookout
|
Residential
|
270
|
NR-D04
|
Evergreen Villa
|
Residential
|
290
|
NR-D05
|
Racecourse Gardens
|
Residential
|
280
|
NR-D06
|
Kam Tai Court
|
Residential
|
270
|
NR-D07
|
S.K.H. Ma On Shan Holy Spirit
Primary School
|
Education
|
280
|
4.4.1.5
Two temporary access haul roads between Ma On
Shan Road and the cavern work site for construction vehicles/trucks would be
provided during construction phase.
The two temporary access haul roads would be located within the
construction works area. These
temporary access haul roads would be demolished after construction phase. The locations of the temporary access haul
roads are indicated in Figure
No. 60334056/EIA/4.02. Relevant sections of Ma On Shan Road
would have minor temporary modification for these merging points. A small
portion of existing noise
barrier at Ma On Shan Road would be temporary removed and re-provided along the
temporary access haul road due to this modification. Once the construction work
for the relocated STSTW is completed, these two temporary access haul roads
would be demolished and the relevant section of Ma On Shan Road and associated
noise barrier would be recovered as before. The nearest NSR, Ah Kung Kok Fishermen
Village, which is located in the vicinity of the concerned noise barrier, is
selected for traffic noise impact assessment to study and demonstrate adequate
noise protection to the surrounding when the existing barrier at the concerned
road section of Ma On Shan Road is temporarily replaced by a noise barrier on
the temporary access road.
4.5.1.1
Construction noise is expected from the use of
PME during various construction activities, such as excavation, concreting,
compaction works, material handling activities etc, at all land-based works
areas including the existing and relocated STSTW, improvement measures at A
Kung Kok Street, alternative access to and from the relocated STSTW and
temporary explosives magazine site at A Kung Kok Shan. For the cavern construction at Nui Po
Shan, since most of the construction works for relocated STSTW including water
reclamation facilities would be carried out underground / inside the rock mass,
noise would be limited to areas near the portal, other above ground structures
such as the ventilation shaft, fan plant rooms and the workshop and chemical
store and the potential PME activities at the temporary stockpiling area.
4.5.1.2
As mentioned in Section 2, only the
construction period of proposed Sha Tin ISEPS would be overlapped with the
period for construction of cavern STSTW. However, the work site of ISEPS is
located more than 300m from cavern STSTW works site, cumulative noise impact is
not expected.
4.5.1.3
Drill-and-blast method will be adopted for the
cavern construction. Potential
ground-borne noise impacts arising from breaking the rock head may affect the
NSRs in the close vicinity of the works site. The PMEs which are potentially in
generating of ground-borne noise would be drill rigs, hydraulic breakers and
hand-held breakers. TBM
method will be adopted for construction of an effluent pipeline connecting to
THEES tunnel and it would also pose potential ground-borne noise impact to the
NSRs in the vicinity of the work site.
4.5.1.4
Blasting construction method is not considered
with respect to noise annoyance, as the duration of blasting is very short and
infrequent. No assessment has been
carried out regarding noise annoyance impacts within any of the identified
sensitive receivers.
4.5.1.5
Based on the current construction programme,
there is no construction work outside the cavern within the restricted hours,
therefore, only construction noise impact assessments for both air-borne and
ground-borne noise during day hours according to the EIAO-TM is conducted in
the study.
4.5.1.6
During construction phase, two temporary access
roads would be provided to divert the truck traffic from cavern work site to Ma On Shan Road
directly. As mentioned in Section
4.4.1.5, a small portion of existing noise
barrier (9.2mPD to 10mPD) at Ma On Shan Road at this merging location would be
temporary removed and re-provided along the temporary access haul road. Traffic noise impact assessment is
therefore conducted to study and demonstrate adequate noise protection to the
surrounding when the existing barrier at the concerned road section of Ma On
Shan Road is temporarily replaced by a noise barrier on the temporary access
road. Once the construction work
for the relocated STSTW is completed, the temporary access roads would be
demolished and the relevant section of Ma On Shan Road and associated noise
barrier would be recovered as before.
4.5.2.1
Potential fixed plants noise impact during
operation of the relocated STSTW would be generated from the operation of the
ventilation shaft, ventilation buildings, fan plant rooms, pumps, general
exhaust fans and ventilation fan of deodourization units etc. Since most of these fixed plants will be
fully enclosed inside concrete structures or by physical rock mass within the
caverns, noise impact from these
facilities is anticipated to be insignificant. The air-conditioning/ventilating system
operated at the administration building include air handling units, chiller and
cooling tower. The cooling tower
would be located at the rooftop of the administration building. The chiller would be located inside the
plant room (concrete structure) with provision of ventilation system. The noise impact from operation of the
chiller would be negligible but the ventilation fan for the plant room would be
potential noise source. Fixed plant
noise due to the above ground ventilation shaft, cooling tower at the roof of
administration building, ventilation fan for the chiller plant room at
administration building and
ventilation buildings would dominate the fixed plant noise impact to NSRs in the vicinity. The pumps of the water reclamation
facilities would be the main potential noise sources during operation. However, these facilities are located
inside cavern, the noise arising from the pumps is anticipated to be
insignificant.
4.5.2.2
During operation phase of the Project, the
vehicles from relocated STSTW would pass through A Kung Kok Street and then to
Ma On Shan Road. The peak hour
traffic flow of A Kung Kok Street in Year 2016 is 931 nos. vehicle. The maximum number of vehicles due to
the operation of relocated STSTW is anticipated to be less than 20 nos.
vehicles per hour. The increase
noise level due to operation of the relocated STSTW at A Kung Kok Street would
be insignificant. As comparing with
the traffic flow in the roads within the study area such as Ma On Shan Road and
Tate¡¦s Cairn Highways (over 7000 vehicles in peak hour), the increase in
traffic flow from operation of relocated STSTW on the road network is
negligible, therefore no significant off-site road traffic impact would be
expected.
4.5.3.1
Construction noise is expected from the use of
PME during various decommissioning and demolition activities, such as
excavation, material handling activities, etc. at the existing STSTW and the
temporary explosives magazine site at A Kung Kok Shan. Potential construction noise impact
would affect the nearby NSRs.
4.5.4.1
Construction noise impact due to the
reconstruction and upgrading of the existing upstream sewage pumping stations,
is expected to be minor due to the small scale works and the construction
periods are expected to be short term.
4.5.4.2
To redirect the sewage from the existing STSTW
to the relocated STSTW, an ISEPS will be constructed at the existing
STSTW.
Construction
Noise ¡V Airborne Noise
4.6.1.1
The construction noise assessment methods for
the construction of the proposed relocated STSTW and the decommissioning of the
existing STSTW are presented below.
4.6.1.2
The assessment follows the procedures given in the GW-TM. For the assessment of noise from PME,
the distance attenuation is
determined by using the following formula:
Distance Attenuation in dB(A) = 20 log D + 8
[where D is distance in metres]
4.6.1.3
Sound Power Levels (SWL) of equipment are taken from Table 3 of the
GW-TM. Where no SWL is given in the
GW-TM, reference is made
to British Standard 5228: Part 1: 2009 Code of practice for noise and vibration
control on construction and open sites and previous similar studies. For each construction activity, PMEs are grouped according to their likely concurrent usage. The plant inventory and percentage
on-time utilization of the PME for the assessment has been
confirmed to be practical and suitable for the proposed works.
4.6.1.4
Noise impact is assessed on the basis of the following assumptions:
¡P
Noise impact at the nearest
sensitive facades of the residential buildings to the source positions is
assessed;
¡P
A +3 dB(A) façade correction is
added to the predicted noise levels to account for the facade effect at each
NSR; and
¡P
All PME items required for a particular
construction activity is located at the notional source position, in accordance
with the GW-TM.
4.6.1.5
In accordance with the GW-TM, the notional
source position is a position mid-way between the approximate geographical
centre of the construction site and its boundary nearest to the NSR. As the size of the construction site is
large such that the notional source position would be greater than 50m from the
point on the site boundary nearest to the NSR. The position shall be taken to
be a point 50m from that point on the site boundary measured along the line
between the approximate geographical centre of the site and the point on the
site boundary nearest to the NSR.
4.6.1.6
There are two haul roads for the access of the
cavern site to Ma On Shan Road. The
impact from construction vehicles is calculated in accordance with the
following formula as stipulated in BS5228: Part 1:2009.
Leq (30 mins) = LWA
− 33 + 10logQ − 10logV − 10logd + A
where:
LWA is the SWL of the
plant, in decibels (dB)
Q is
the number of vehicles per hour
V is
the average vehicle speed, in kilometres per hour (km/h)
d is the distance of receiving position from the
centre of haul road, in metres (m)
A is the angle of view correction, A =
10log(angle of view in degrees /180)
Construction Noise
¡V Ground-borne Noise
4.6.1.7
The projection methodology is recommended by the
U.S. Department of Transportation and Federal Transit Administration[1]. This projection methodology has been
used in the Ground-Borne Noise & Vibration Assessment for Shatin to Central
Link (SCL) EIA[2]
approved by EPD (EIA Register No. AEIAR-166/2012).
4.6.1.8
The main components of the proposed prediction
model for ground-borne noise are:
¡P
Vibration source level from
operation of PME;
¡P
Vibration propagation through
the ground to the structure foundation;
¡P
Vibration reduction due to the
soil/structure interface;
¡P
Vibration propagation through
the building and into occupied areas; and
¡P
Conversion from floor and wall vibration
to noise.
4.6.1.9
The vibration level Lv,rms at a
distance R from the source is related to the vibration source level at a
reference distance Ro.
The conversion from vibration levels to ground-borne noise levels is determined by the following factors:
Cdist: Distance
attenuation
Cdamping: Soil
damping loss across the geological media
Cbuilding: Coupling
loss into building foundation
Cfloor: Coupling
loss per floor
Cnoise: Conversion
factor from floor vibration levels to noise levels
Cmulti: Noise
level increase due to multiple sources
Ccum: Cumulative
effect due to neighbouring sites
The predicted ground-borne noise
level Lp inside the noise sensitive rooms is given by the
following equation.
Lp =
Lv,rms + Cdist + Cdamping + Cbuilding
+ Cfloor + Cnoise + Cmulti + Ccum
Reference Vibration Sources
4.6.1.11
Reference is made to the assessment approach, source terms and
transmission factors adopted in the approved EIA study for the SCL project. The reference vibration levels of the PMEs are summarized in Table 4.11.
Table 4.11 Summary
of Reference Vibration Level of PMEs
|
|
|
Drilling
rig
|
0.536
|
rms
Vibration velocity level at reference distance of 5.5m
|
Hydraulic
breaker
|
0.298
|
rms
Vibration velocity level at reference distance of 5.5m
|
Hand-held
breaker
|
0.279
|
rms
Vibration velocity level at reference distance of 5.5m
|
TBM/
micro TMB*
|
2.5
|
PPV
Vibration velocity level at reference distance of 5.5m
|
Note: *
Reference vibration level of micro TMB is assumed to be the same as TMB for
conservative purpose
Distance Attenuation
4.6.1.12
Ground-borne noise can attenuate by longer
distance of vibration energy transmission pathway. For this assessment, the shortest plan
distances between the GBNSRs and the closest work areas are identified for correction. For separate distance over 300m,
ground-borne noise assessment is
excluded.
Soil Damping
4.6.1.13
Internal losses of soil would cause the
vibration amplitude to decay against the propagation distance and the decay relationship
is based on the equation set out in the Transportation Noise Reference Book[3].
V(R) = V(Ro)
´ e-2pf
h R/2c
The velocity amplitude V is dependent
on the frequency f in Hz, the soil loss factor h,
the wave speed c in m/s, the distance R from the source to the NSR. The properties of soil materials are
shown in Table 4.12.
Table 4.12 Wave
Propagation Properties of Soil
|
|
|
|
Soil
|
1500
|
0.5
|
1.7
|
Rock
|
3500
|
0.01
|
2.65
|
4.6.1.14
No damping attenuation is applied in this
assessment as conservative approach.
Coupling Loss into Building Structures
4.6.1.15
The coupling loss into building structures represents
the change in the incident ground-surface vibration due to the presence of the
piled building foundation. In this
assessment, the correction has adopted the value in the ¡§Transit Noise and
Vibration Impact Assessment¡¨ published by Federal Transit Administration which
is given in Table 4.13.
Table 4.13 Loss
factor for Coupling into Building Foundation
|
|
Wood
Frame Houses
|
-5
dB
|
1
¡V 2 Storey Masonry
|
-7
dB
|
3
¡V 4 Storey Masonry
|
-10
dB
|
Large
Masonry on Piles
|
-10
dB
|
Large
Masonry on Spread Footings
|
-13
dB
|
Foundation in Rock
|
0
dB
|
Coupling Loss per Floor
4.6.1.16
The coupling loss per floor represents the floor-to-floor
vibration transmission attenuation.
For multi-storey buildings, a common value for the attenuation of
vibration from floor-to-floor is approximately 1 dB attenuation in the upper
floor regions and greater than 3 dB attenuation at lower floors. Coupling loss of 1 dB reduction per
floor is assumed in this report for a conservative assessment to account for
any possible amplification due to resonance effects.
Conversion from Floor Vibration to Noise Levels
4.6.1.17
Conversion from floor vibration levels to indoor
reverberant noise levels is based on standard acoustic principles. The conversion factor is dependent on
the surface area S of the room in m2, the radiation efficiency s,
the volume of the room V in m3 and the room reverberation time RT in
seconds. Conversion factors from
floor vibration levels to indoor reverberant noise levels adopted in the assessment are
27 dB for residential
units, which is in line with the
previous approved EIA reports.
Noise Level Increase due to Multiple Sources
4.6.1.18
This represents the increase in noise level due
to multiple noise sources. The factor adopted for this
assessment is based on the number of plants used concurrently and the
construction programme from the construction plant list. Appendix 4.03
presents the construction programme and Appendix 4.04
presents the construction plant inventory under the unmitigated scenario.
Cumulative Effect due to Neighbouring Sites
4.6.1.19
Any cumulative effect of construction
ground-borne noise at GBNSRs due to neighbouring sites shall be included. However, for this
site, there is no neighbouring
site inducing ground-borne noise.
Conversion to A-weighted Noise
4.6.1.20
For assessment of ground-borne noise at GBNSRs,
a 20 dB(A) reduction is
adopted for conversion to A-weighted noise. This conversion
factor is obtained from
the ¡§Transit Noise and Vibration Impact Assessment¡¨ and is also adopted in the previous approved EIA reports.
Traffic Noise due
to Relocation of Noise Barrier during Construction Phase
4.6.1.21
As mentioned in Section
4.5.1.6, traffic noise impact
assessment is conducted to determine the potential impact due to relocation of
a small portion of 3m high noise barrier from existing Ma On Shan Road to the
temporary access haul road. Traffic
noise is
predicted using the methodology provided in the UK Department of Transport
Calculation of Road Traffic Noise (CRTN) 1988. Road traffic noise levels are presented
in terms of noise levels exceeded for 10% of the one-hour period during the
peak traffic flow, i.e. L10(1hour) dB(A). The projected Year 2022 peak hour
traffic flows and vehicle compositions, which is the maximum traffic flow during the construction period
and has been agreed with TD, is adopted in the assessment.
4.6.1.22
For the purpose of the traffic noise assessment
in this study, the roads
within 300m from the proposed project alignment are included in the assessment. The locations of the existing noise
barrier and the re-provisioned noise barrier, and the assessment points are
shown in Appendix 4.07.
4.6.1.23
The following two scenarios are studied:
¡P
Without Project Scenario - Existing
road layout and configuration of the noise mitigation scheme on Ma On Shan
Road/Tate¡¦s Cairn Highways in Year 2022
¡P
With Project Scenario -
Existing road layout and configuration of the noise mitigation scheme on Ma On
Shan Road/ Tate¡¦s Cairn Highway except that a small portion of noise barrier at
Ma On Shan Road is relocated to the temporary access road in Year 2022
Fixed Plant Noise
4.6.2.1
For determination of assessment criteria, 2-days noise measurement (one at
weekday and one at Sunday/public holiday) were conducted at the representative NSRs to study the
prevailing noise levels. 24-hours
per day noise measurement was
carried out at each representative NSR. The measurements were conducted in accordance with the calibration
and measurement procedures stated in the IND-TM. The measurement results and the
assessment criteria for the representative NSRs due to fixed noise impact from
the Project, as adopted in this EIA Study are presented in Appendix 4.01.
4.6.2.2
The following standard acoustic formula is used for calculating the
sound pressure levels (SPL) at the representative NSRs due to fixed plant noise
impact.
SPL
= Max SWL ¡V DC + FC ¡V BC
Where:
SPL Sound
Pressure Level, in dB(A)
Max
SWL Maximum
Permissible SWL, in dB(A)
DC Distance
Attenuation, in dB(A) (i.e. 20logD + 8 [where D is the distance in metres])
FC Façade
Correction, in dB(A) (i.e. 3 dB(A))
BC Barrier
Correction, in dB(A)
4.6.2.3
It is assumed that all the fixed plant within
the same location would be operated simultaneously for the worst-case
scenario. Screening correction
offered by buildings or other structures such as office and residential
buildings is taken into
account in calculating the predicted noise levels. According to the GW-TM, effective
barriers can result in noise reduction of 5 to 10 dB(A) for the fixed plant
depending on the line of sight of the representative NSRs. A positive 3 dB(A) is added to the predicted noise
levels at the NSRs due to the façade effect.
4.6.2.4
A positive 3 dB(A) for corrections of tonality is considered in the
assessment.
4.7.1.1
For normal daytime working hours, exceedances of
the construction noise criteria would be predicted at representative NSRs in
the absence of mitigation measures based on the construction programme as shown
in Appendix 4.03
and the construction plant inventory presented in Appendix 4.04. The locations of the construction works
areas, the details of construction noise calculations and results are presented
in Appendix 4.05. A summary of the unmitigated noise
assessment results is shown in Table 4.14.
Table 4.14 Unmitigated
Construction Noise Levels due to the Project at Representative NSRs During
Normal Daytime Working Hours
|
|
|
|
NR-C01
|
Chevalier Garden
|
75
|
79
|
NR-C02
|
Wellborn Kindergarten*
|
70
|
80
|
NR-C03
|
Hay Nien Primary School
|
70 (65)
|
81
|
NR-C04
|
Ma On Shan Tsung Tsin Secondary
School
|
70 (65)
|
82
|
NR-C05
|
Low rise residential buildings on
Tai Shui Hang South Street
|
75
|
77
|
NR-C06
|
Kam Tai Court
|
75
|
79
|
NR-C07
|
S.K.H. Ma On Shan Holy Spirit
Primary School
|
70 (65)
|
79
|
NR-C08
|
Ah Kung Kok Fishermen Village
|
75
|
82
|
NR-C09
|
Hong Kong Mountaineering Union
|
75
|
73
|
NR-C10
|
The Neighbourhood Advice-Action
Council Harmony Manor
|
75
|
89
|
NR-C11
|
Shing Mun Springs Rehabilitation
Centre
|
75
|
81
|
NR-D01
|
Seaview Villa
|
75
|
78
|
NR-D02
|
Kam On Garden
|
75
|
73
|
NR-D03
|
Sha Tin Lookout
|
75
|
73
|
NR-D04
|
Evergreen Villa
|
75
|
76
|
NR-D05
|
Racecourse Gardens
|
75
|
71
|
NR-D06
|
Kam Tai Court
|
75
|
70
|
NR-D07
|
S.K.H. Ma On Shan Holy Spirit
Primary School
|
70 (65)
|
71
|
Note: Bolded values indicate exceedance to
noise criteria.
* According to
the information provided by Wellborn Kindergarten, there is no examination
period.
4.7.1.2
The above results show that the exceedances would be predicted at most of
the residential and educational NSRs during normal teaching period and
examination period. Noise mitigation measures would
therefore be required to reduce noise levels to the stipulated noise standards.
4.7.2.1
Ground-borne noise impact from PMEs to the
nearby sensitive receivers is
predicted following the methodology described in Section 4.6,
and the prediction results are summarized in Table 4.15.
Detailed calculations are provided in Appendix 4.06.
Results show that all representative GBNSRs would comply with the
criteria under EIAO-TM.
Table 4.15 Predicted
Construction Ground-borne Noise Impact Associated with the PME Use at Open
Works Areas
|
|
|
|
|
GBNSR-1
|
Chevalier Garden
|
51
|
65
|
Yes
|
GBNSR-2
|
Village House in A Kung Kok
|
52
|
65
|
Yes
|
GBNSR-3
|
The Neighbourhood Advice-Action Council
Harmony Manor
|
53
|
65
|
Yes
|
GBNSR-4
|
Kam Tai Court
|
45
|
65
|
Yes
|
GBNSR-5
|
Seaview Villa
|
40
|
65
|
Yes
|
GBNSR-6
|
Ma On Shan Tsung Tsin Secondary
School
|
45
|
55
|
Yes
|
4.7.3.1
The length of existing noise barrier on the
concerned road section of Ma On Shan Road at the height of 9.2 mPD to 10mPD to
be temporary removed would be 150m.
The noise barrier with the length of 220m at 10mPD would be re-provided
along the temporary access haul road. Traffic noise levels have been predicted
at representative noise assessment points at Ah Kung Kok Fishermen Village
(2-storey high village houses) for the scenarios of with existing barrier
configuration and temporary barrier arrangement in Year 2022, which is the peak flow
during construction period.
Assessment results indicate that there is negligible difference in noise
levels at the representative noise assessment points between two scenarios. The details of the assessment and Year
2022 peak hour traffic flows are presented in Appendix 4.07.
4.7.4.1
Referring to the preliminary engineering design,
the maximum SWLs of the ventilation shaft, cooling tower, ventilation fan for
chiller plant room and ventilation buildings at main portal and secondary
portal are presented in Table 4.16 and
considered in the fixed noise impact assessment. Table 4.17
presents the predicted fixed plant noise levels at representative
NSRs. The detailed calculation is
shown in Appendix 4.08.
Table 4.16 Maximum
Sound Power Levels for Fixed Plant Noise Sources
|
|
|
VB-M
|
Ventilation Building at Main Portal
|
90
|
VB-E
|
Ventilation Building at Secondary Portal
|
90
|
ADB-C
|
Ventilation Fan for Chiller Plant Room at Administration Building
|
85
|
ADB-CT
|
Cooling Tower at roof of Administration
Building
|
88
|
VS
|
Ventilation Shaft
|
95
|
Table 4.17 Predicted
Fixed Plant Noise Levels at Representative Noise Sensitive Receivers
|
|
|
|
NR-C01
|
Chevalier Garden
|
42
|
42
|
NR-C02
|
Wellborn Kindergarten
|
46
|
45
|
NR-C03
|
Hay Nien Primary School
|
61
|
43
|
NR-C04
|
Ma On Shan Tsung Tsin Secondary School
|
60
|
43
|
NR-C05
|
Low rise residential buildings on
Tai Shui Hang South Street
|
50
|
41
|
NR-C06
|
Kam Tai Court
|
52
|
42
|
NR-C07
|
S.K.H. Ma On Shan Holy Spirit Primary School
|
52
|
41
|
NR-C08
|
Ah Kung Kok Fishermen Village
|
49
|
46
|
NR-C10
|
The Neighbourhood Advice-Action Council Harmony Manor
|
44
|
44
|
4.7.4.2
The assessment results show that no exceedance of
the fixed plant noise criteria would be expected at the nearest NSRs.
4.8
Mitigation of Adverse Environmental
Impacts
4.8.1.1
In order to reduce the excessive noise impact at
the affected NSRs during normal daytime working hours, adoption of quiet PME is
recommended. The contractor(s) may
be able to obtain particular models of plant that are quieter than the PMEs
given in GW-TM. It is considered
too restrictive to specify that a contractor has to use specific items of plant
for the construction operations. It
is practical to specify the total SWL of all plant to be used on site so that
the contractor(s) is allowed some flexibility to select plant to suit his
needs.
4.8.1.2
The use of quiet plant associated with the
construction works is prescribed in British Standard ¡§Code of practice for
noise and vibration control on construction and open sites, BS5228¡¨ which
contains the SWLs for specific quiet PME.
The SWLs of quiet PMEs adopted for the assessment are detailed in Appendix 4.09. The mitigated noise levels with the
adoption of the quiet PMEs are summarized in Table 4.18
and the detailed mitigated noise assessment results are presented in Appendix 4.10.
Table 4.18 Mitigated
Construction Noise Levels due to the Project at Representative NSRs During
Normal Daytime Working Hours (Using Quiet PME)
|
|
|
|
NR-C01
|
Chevalier Garden
|
75
|
71
|
NR-C02
|
Wellborn Kindergarten*
|
70
|
70
|
NR-C03
|
Hay Nien Primary School
|
70 (65)
|
72
|
NR-C04
|
Ma On Shan Tsung Tsin Secondary
School
|
70 (65)
|
74
|
NR-C05
|
Low rise residential buildings on Tai
Shui Hang South Street
|
75
|
68
|
NR-C06
|
Kam Tai Court
|
75
|
73
|
NR-C07
|
S.K.H. Ma On Shan Holy Spirit
Primary School
|
70 (65)
|
73
|
NR-C08
|
Ah Kung Kok Fishermen Village
|
75
|
73
|
NR-C09
|
Hong Kong Mountaineering Union
|
75
|
66
|
NR-C10
|
The Neighbourhood Advice-Action Council
Harmony Manor
|
75
|
80
|
NR-C11
|
Shing Mun Springs Rehabilitation
Centre
|
75
|
72
|
NR-D01
|
Seaview Villa
|
75
|
75
|
NR-D02
|
Kam On Garden
|
75
|
70
|
NR-D03
|
Sha Tin Lookout
|
75
|
70
|
NR-D04
|
Evergreen Villa
|
75
|
73
|
NR-D05
|
Racecourse Gardens
|
75
|
68
|
NR-D06
|
Kam Tai Court
|
75
|
67
|
NR-D07
|
S.K.H. Ma On Shan Holy Spirit
Primary School
|
70 (65)
|
68
|
Note: Bolded values indicate exceedance to
noise criteria, italic values indicate exceedance to noise criterion during
examination period only.
* According to
the information provided by Wellborn Kindergarten, there is no examination
period.
4.8.1.3
With the use of quiet PMEs, exceedance would
still be predicted at educational NSR NR-C03, NR-C04, NR-C07 and residential
NSR NR-C10 during construction works for relocated STSTW. During demolition of existing STSTW,
exceedance of noise criterion for examination period would be anticipated at
educational NSR NR-D07.
4.8.1.4
To alleviate the construction noise impact on
these affected educational NSRs, movable noise barrier for Air Compressor, Bar
Bender and Cutter, Breaker, Chisel, Saw, Compactor, Concrete Mixers, Pump,
Crane, Desander, Drilling Rig, Dump Truck, Excavator, Generator, Grab, Lorry,
Paver, Poker and Roller are proposed.
Movable temporary noise barriers that can be located close to noisy
plant and be moved iteratively with the plant along a worksite can be very
effective for screening noise from NSRs.
A typical design which has been used locally is a wooden framed barrier
with a small cantilevered upper portion of superficial density no less than
14kg/m2 on a skid footing with 25mm thick internal sound absorptive
lining. This measure is
particularly effective for low level zone of NSRs. A cantilevered top cover would be
required to achieve screening benefits at upper floors of NSRs. It is anticipated that suitably designed
barriers could achieve at least 5 ¡V 10 dB(A) reduction. In addition, noise barrier/acoustic mat
for the Drilling Jumbo is also proposed when it is operated outside the portal
and within 20m inside the portal so as to have screening effecting with 10
dB(A) noise attenuation.
4.8.1.5
For residential NSR NR-C10, in view of site
constraint, it is not possible to install the movable noise barrier. In order to further alleviate the
construction noise impact on this NSR, it is proposed to limit the number of
on-time operating PMEs within 120m of this NSR during construction of access
road. With this measure in place,
the predicted construction noise levels at this NSR would comply with the
criterion of 75 dB(A).
4.8.1.6
Noise reduction from the use of mitigation
measures including quiet plant and noise barrier/acoustic mat for construction
plants and limitation of the number of on-time operating PMEs as described
above have been applied in the assessment.
Details of construction noise calculations and results for the
¡§mitigated¡¨ scenario are presented in Appendix 4.10. The predicted mitigated cumulative noise
levels at representative NSRs are summarised in the Table 4.19.
Table 4.19 Mitigated
Construction Noise Levels due to the Project at Representative NSRs During
Normal Daytime Working Hours (with further Mitigation Measures)
|
|
|
|
|
NR-C03
|
Hay Nien Primary School
|
70 (65)
|
Quiet PME +
Movable Noise Barrier/Acoustic Mat
|
63
|
NR-C04
|
Ma On Shan Tsung Tsin Secondary
School
|
70 (65)
|
|
64
|
NR-C07
|
S.K.H. Ma On Shan Holy Spirit Primary
School
|
70 (65)
|
|
66
|
NR-C10
|
The Neighbourhood Advice-Action
Council Harmony Manor
|
75
|
Quiet PME + Limit of the number of on-time operating PMEs within 120m
of the NSR during construction of access road
|
75
|
NR-D07
|
S.K.H. Ma On Shan Holy Spirit Primary
School
|
70 (65)
|
Quiet PME +
Movable Noise Barrier
|
64
|
Note: Bolded values indicate exceedance to noise
criteria, italic values indicate exceedance to noise criterion during
examination period only.
4.8.1.7
With the installation of further mitigation
measures, all representative NSRs would comply with the EPD noise criteria
except that educational NSR NR-C07 would exceed the criterion for examination
period. At the time of the
assessment, the school can only has the examination schedule in the Year
2015-2016, therefore, the prediction on any exceedance of criterion for
examination period is based on this schedule. Referring to the examination schedule
provided by this school, the examination period in each year is 3 days in
January and 3 days in June respectively.
The potential impact on the educational NSR NR-C07 is summarized as
below:
Exceedance of 1 dB(A) :
¡P
3 days in January and 3 days in
June 2021;
¡P
3 days in January and 3 days in
June 2022; and
¡P
3 days in January 2023.
4.8.2.1
Results show that all representative GBNSRs
would comply with the criterion, mitigation measure is not required.
4.8.3.1
The predicted noise levels of the representative
NSRs in the vicinity of the fixed plant sources such as ventilation shaft,
cooling tower at the roof of administration building, ventilation fan for
chiller plant room at administration building and ventilation buildings would
comply with the noise criterion,
no further mitigation measure is required.
4.9
Evaluation of Residual Impacts
4.9.1.1
With the implementation of proposed mitigation
measures in Section 4.8.1, exceedance of 1
dB(A) would still be predicted at educational NSR NR-C07 (S.K.H. Ma On Shan
Holy Spirit Primary School) during examination period. Based on the
observations from site visits, this school has already
been noise insulated with air-conditioners. With the provision of air-conditioners,
it is considered that the noise impact would be minimized by keeping the
windows closed during examination period.
Notwithstanding this, due to more stringent noise criterion of 65 dB(A),
it is recommended that particularly noisy construction activities, should be
scheduled to avoid examination periods of this NSR as far as practicable. The Contractor should liaise with the
school representative(s) to obtain the examination schedule so as to avoid
noisy construction activities during school examination period. The residual impacts are evaluated in
accordance with Section 4.4.3 of the EIAO-TM
as shown in Table 4.20 below.
Table 4.20 Evaluation
of Residual Noise Impacts during Construction Phase
|
|
Health and health of biota or risk of life
|
The extent of noise nuisance would be unlikely to induce public
health concern.
|
Magnitude of the adverse environmental impacts
|
The predicted exceedance of construction
noise for NSR NR-C07 is 1 dB(A) during examination
period. All practicable measures
have been proposed and exhausted to minimize the noise impact. In addition,
it is noted that noise insulation works with air-conditionings have been
installed at this school. With
the provision of air-conditioners, it is considered that the noise impact
would be minimized by keeping the windows closed during examination period.
|
Geographic extent of the adverse environmental impact
|
The geographic extent of the adverse impact from noise is
anticipated to be limited to NSR NR-C07 during examination period.
|
Duration and frequency of the adverse environmental impacts
|
The predicted exceedance durations of
construction noise for NSR NR-C07 during examination period are:
Exceedance of 1 dB(A) :
¡P
3 days in January and 3 days
in June 2021;
¡P
3 days in January and 3 days
in June 2022; and
¡P
3 days in January 2023.
All practicable measures have been proposed and exhausted to
minimize the noise impact.
|
Likely size of the community or the environmental that may be
affected by the adverse impacts
|
NSR NR-C07 would be temporarily affected by residual construction
noise during examination period.
|
Degree to which the adverse environmental impacts are reversible
or irreversible
|
Not Applicable in noise section.
|
Ecological context
|
Not Applicable in noise section
|
Degree of disruption to sites of cultural heritage
|
Not Applicable in noise section
|
International and regional importance
|
The impacts are localized and not of international and regional
importance
|
Likelihood and degree of uncertainty of adverse environmental
impact
|
The impacts predicted are based upon worst case assumptions and as
such, would not occur to the extent predicted on all occasions.
|
4.9.1.2
In addition to the mitigation measures mentioned
in Section 4.8, the good site practices listed below
shall be adopted by all the contractors to further ameliorate the noise
impacts. Although the noise
mitigating effects are not easily quantifiable and the benefits may vary with
the site conditions and operating conditions, good site practices are easy to
implement and do not impact upon the works schedule.
¡P
Only well-maintained plant
should be operated on-site and plant should be serviced regularly during the
construction program;
¡P
Silencers or mufflers on
construction equipment should be utilised and should be properly maintained
during the construction program;
¡P
Mobile plant, if any, should be
sited as far away from NSRs as possible;
¡P
Machines and plant (such as
trucks) that may be in intermittent use should be shut down between works
periods or should be throttled down to a minimum;
¡P
Plant known to emit noise
strongly in one direction should, wherever possible, be orientated so that the
noise is directed away from the nearby NSRs; and
¡P
Material stockpiles and other
structures should be effectively utilised, wherever practicable, in screening
noise from on-site construction activities.
4.9.2.1
No residual fixed plant noise impact due to the
operation of the Project is expected.
4.10.1.1
An EM&A programme is recommended to be
established according to the predicted occurrence of noisy activities. The recommended mitigation
measures should be implemented during construction stage. Details of the programme are provided in
a stand-alone EM&A Manual.
4.10.1.2
No adverse impact is expected due to the
operation of the fixed plants. Operational fixed plant noise monitoring
is therefore considered not necessary. Prior to the operational phase of the
Project, a commissioning test for the ventilation buildings, cooling tower and
ventilation fan for chiller plant room at administration building, and the
ventilation shaft should be conducted to ensure compliance with the relevant
designed maximum SPLs.
4.11.1.1
This assessment has presented the construction
noise impacts of the Project during construction of relocated STSTW including water
reclamation facilities, decommissioning and demolition of existing STSTW and
the temporary explosives magazine.
The predicted maximum unmitigated noise levels at representative NSRs
would range from 70 to 89 dB(A).
With the adoption of quiet PME, use of movable noise barrier/acoustic
mat, and limitation of the number
of on-time operating PMEs within 120m of the Neighbourhood Advice-Action
Council Harmony Manor during construction of access road, , the noise levels
due to the Project itself at all representative residential NSRs would comply
with the EIAO-TM criterion of 75 dB(A).
All representative educational NSRs would also comply with the noise
criteria except that exceedance of noise criterion by 1 dB(A) during
examination period is still predicted at educational NSR NR-C07 due to
construction activities at the main portal and at Area 73. As this NSR is located in close vicinity
of these work areas, all practical mitigation measures have been exhausted. Since the affected period would be limited
to examination periods and the affected educational NSR has been noise
insulated with air conditioners, it is considered that the residual noise
impact is in short term period and would be minimized by keeping the windows
closed during the affected examination periods.
4.11.1.2
During the actual construction period, as much
as practically possible should be done to reduce the construction noise, and
on-going liaison with all concerned parties and site monitoring should also be
conducted during the course of the construction period. A construction noise EM&A programme
is recommended to check the compliance of the noise criteria during normal
daytime working hours.
4.11.1.3
Ground-borne construction noise impacts pertinent
to the use of hydraulic breaker, hand-held breaker, drill rig and TBM would
comply with criteria of NCO. No
adverse ground-borne construction noise impacts would be predicted and therefore no noise mitigation
measure and noise monitoring are proposed.
4.11.1.4
Blasting noise due to construction of cavern is
not considered with respect to noise annoyance, as the duration of blasting is
very short and infrequent.
Nevertheless, blasting should be carried out outside sensitive hours as
far as practicable, and the blasting schedule should be submitted to the
concerned authority for approval prior for its implementation. Blasting should be carried out by a
person possesses a valid mine blasting certificate by Mines Division of CEDD.
4.11.1.5
For the temporary modification works at the
merging point of Ma On Shan Road and temporary access haul road, the
re-provision of 220m length noise barrier with 10mPD on temporary access haul
road to replace the existing 150m length noise barrier with 9.2mPD to 10mPD on
Ma On Sha Road would pose negligible difference in the overall traffic noise
level at the sensitive facades in the vicinity. Once the construction work is completed,
the noise barrier on the concerned road section of Ma On Shan Road would be
re-installed according to the existing configuration.
4.11.2.1
The noise impact associated with the operation
of the Project has been assessed.
The predicted fixed plant noise levels at the representative NSRs would
comply with the criteria based on the plant design information provided by the
Engineer at the time of the assessment.
If there is any change in engineering design information during detailed
design stage or fitting-out stage, the fixed source noise design should be
reviewed by the Engineer/Contractor to ensure that both the NCO and EIAO-TM
criteria at the NSRs can be met in the future. Prior to the operational phase of the
Project, a commissioning test for the ventilation buildings, the ventilation shaft,
ventilation fan for chiller plant room at administration building and cooling
tower at the administration building would be conducted to ensure compliance
with the relevant allowable maximum sound power levels.
<End of Section 4>