4.2 Relevant Legislations, Standards & Guidelines
4.3 Description of the Existing Noise Environment
4.4 Construction Noise Impact Assessment
4.5 Operational Noise Impact Assessment
Table
4.1 : Noise Standards for Daytime Construction Activities
Table
4.2 : Acceptable Noise Levels
Table
4.3 : Recommended Noise Criteria for Operational Noise
Table
4.4 : Construction Activities Schedule
Table
4.5 : Representative Noise Sensitive Receivers (Construction Phase)
Table
4.7 : Silenced Equipments
Table
4.8 : Noise Mitigation Measures for Certain PME
Table
4.11: Major Noise Generating Equipment (Operational Phase)
Table
4.12: Representative Noise Sensitive Receivers (Operational Phase)
Table
4.14: Proposed Noise Mitigation Measures for Equipments during Operation Phase
Technical Memorandum on Noise from Places other than Domestic Premises, Public Places or Construction Sites (IND-TM):
Technical Memorandum on Noise from Construction Work in Designated Areas (DA-TM);
Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM); and
Technical Memorandum on Noise from Percussive Piling (PP-TM).
Construction Noise
Table 4.1 : Noise Standards for Daytime Construction Activities
Noise Sensitive Uses |
07:00 to 19:00 hours on any day not being a Sunday or general holiday, Leq (30 min), dB(A) |
Domestic premises, hotels and hostel |
75 |
Educational institutions (normal teaching periods) |
70 |
Educational institutions (examination periods) |
65 |
Notes:
1) The above noise standards apply to uses, which rely on opened windows for ventilation.
2) The above standards shall be viewed as the maximum permissible noise levels assessed at 1m from the external facade.
3) The above standards shall be met as far as possible. All practicable mitigation measures shall be exhausted and the residual impacts minimized.
Operational Noise
Table 4.2 : Acceptable Noise Levels
Time Period |
ASR A |
ASR B |
ASR C |
All days during the evening (19:00 to 23:00 hours), and general holidays (including Sundays) during the day-time and evening (0700 to 2300 hours) |
60 |
65 |
70 |
All days during the night-time (23:00 to 07:00 hours) |
50 |
55 |
65 |
5 dB(A) below the appropriate ANL set out in the IND-TM (the ANL-5 dB(A) criterion), or
The prevailing background noise level where the prevailing background noise level is 5 dB(A) below the appropriate ANL (although during the operation the NCO will be the controlling legislation).
Table 4.3 : Recommended Noise Criteria for Operational Noise
Operation Location |
Measured Noise Level (daytime / night-time), dB(A) |
ANL-5 dB(A) criterion (daytime / night-time), dB(A) |
Recommended Noise Criteria (daytime / night-time), dB(A) |
Tai O STW |
50 / 49 |
55 / 45 |
50 / 45 |
Fan Kwai Tong SPS |
45 / 42 |
55 / 45 |
45 / 42 |
Hang Mei SPS |
45 / 39 |
55 / 45 |
45 / 39 |
Notes:
1) In view of no influencing factors in Tai O, Area Sensitivity Rating “A” has been assumed, with reference to Table 1 of IND-TM.
Works Type 1 - Construction of Sewer (Open Cut Method)
Works Type 2 - Construction of Sewer (Trenchless Method)
Works Type 3 - Upgrading of Existing Sewer
Works Type 4 - Construction of Tai O Sewage Treatment Works and Seawall Construction
Works Type 5 - Construction of Hang Mei Sewage Pumping Station
Works Type 6 - Construction of Fan Kwai Tong Sewage Pumping Station
Works Type 7 - Temporary Working Area at Yim Tin Pok Temporary Playground
Table 4.4 : Construction Activities Schedule
Works Stage |
Construction Activities |
Calculated Worst-case SWL, dB(A) |
Works Type 1 - Construction of Sewer (Open Cut Method) |
||
Stage 1 |
Breaking up of road surface |
108 |
Stage 2 |
Excavation of soil material |
95 |
Stage 3 |
Steel fixing & concreting of manholes |
109 |
Stage 4 |
Laying of bedding material |
109 |
Stage 5 |
Backfilling and soil compaction |
99 |
Stage 6 |
Reinstatement of road surface |
109 |
Works Type 2 - Construction of Sewer (Trenchless Method) |
||
Stage 1 |
Excavation of Pits |
122 |
Stage 2 |
Pipe Laid by Trenchless Method |
117 |
Stage 3 |
Steel fixing and concreting of manholes |
80 |
Stage 4 |
Reinstatement of road surface |
80 |
Works Type 3 - Upgrading of Existing Sewer |
||
Stage 1 |
Breaking up of road surface |
108 |
Stage 2 |
Excavation of soil material |
95 |
Stage 3 |
Removal of existing sewers and laying of new sewers |
94 |
Stage 4 |
Steel fixing & concreting of manholes |
109 |
Stage 5 |
Laying of bedding material |
109 |
Stage 6 |
Backfilling and soil compaction |
99 |
Stage 7 |
Reinstatement of road surface |
109 |
Works Type 4 - Construction of Tai O Sewage Treatment Works & Seawall Construction |
||
Stage 1 |
Form part of permanent seawall – by forming rock / Gabion wall |
111 |
Stage 2 |
Fill the reclamation to 3mPD |
111 |
Stage 3 |
Core boreholes |
113 |
Stage 4 |
Construction of Substructures in New Reclamation Areas |
126 |
Stage 5 |
Temporary Treatment Installation |
113 |
Stage 6 |
Removal of existing structures |
124 |
Stage 7 |
Construction of new superstructure |
119 |
Stage 8 |
Installation of major E&M equipments |
115 |
Stage 9 |
Remove Temporary Treatment Units and construct the new Sludge Dewatering House |
119 |
Stage 10 |
Installation of ancillary equipments and removal of the temporary platform |
110 |
Works Type 5 - Construction of Hang Mei Sewage Pumping Station |
||
Stage 1 |
Site Clearance |
94 |
Stage 2 |
Piling |
99 |
Stage 3 |
Excavation |
122 |
Stage 4 |
Steel fixing & concreting for structure |
115 |
Stage 5 |
Backfilling and Soil Compaction |
105 |
Stage 6 |
Installation of E&M equipment |
112 |
Works Type 6 - Construction of Fan Kwai Tong Sewage Pumping Station |
||
Stage 1 |
Site Clearance |
94 |
Stage 2 |
Piling |
99 |
Stage 3 |
Excavation |
122 |
Stage 4 |
Steel fixing & concreting for structure |
115 |
Stage 5 |
Backfilling and Soil Compaction |
105 |
Stage 6 |
Installation of E&M equipment |
112 |
Works Type 7 - Temporary Working Area at Yim Tin Pok Temporary Playground |
||
Stage 1 |
Site clearance |
94 |
Stage 2 |
Operation of concrete mixer |
96 |
Note:
1) The various stages involved for each work type will not be undertaken concurrently.
2) Note that the works programme is subject to variables such as weather, conflicts with utilities, etc. and is variable upon these conditions.
3) “SWL” is the calculated worst-case total sound power level due to the operation of the plant inventory for that works stage based on the unmitigated scenario.
Noise Sensitive Receivers
Table 4.5 : Representative Noise Sensitive Receivers (Construction Phase)
NSR |
Description of NSR |
Nature of Use |
No. of Floor |
Base mPD |
Figure No. |
Construction Phase Works Type that will affect the NSR |
||||||
|
|
|
|
|
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
SST |
CZSA Drug Treatment and Rehabilitation Centre for Male Drug Abusers |
Rehab Centre |
2 |
5.8 |
4.1 |
|
|
|
√ |
|
|
|
HST |
Hung Shing Temple |
Temple |
1 |
3.5 |
4.2 |
√ |
|
|
|
|
|
|
STP2 |
No.16 Shek Tsai Po Street |
Residential |
3 |
3.2 |
4.2 |
√ |
|
√ |
|
|
|
|
STP3 |
No.6 Shek Tsai Po Street |
Residential |
3 |
3.2 |
4.2 |
√ |
|
√ |
|
|
|
|
STP4 |
No.88 Shek Tsai Po Street |
Residential |
2 |
3.0 |
4.3 |
|
|
√ |
|
|
|
|
STP5 |
No.21 Shek Tsai Po Street |
Residential |
2 |
3.0 |
4.3 |
√ |
|
√ |
|
|
|
|
STP1 |
No.391A Shek Tsai Po Street |
Residential |
3 |
5.2 |
4.4 |
√ |
|
√ |
|
|
|
|
KHB2 |
No.33 Kat Hing Back Street |
Residential |
2 |
3.7 |
4.5 |
√ |
|
|
|
|
|
|
TOM |
No.4 Tai O Market Street |
Residential |
2 |
3.0 |
4.5 |
√ |
|
|
|
|
|
|
TOTP1 |
No.190 Tai O Tai Ping Street |
Residential |
3 |
3.2 |
4.5 |
√ |
|
|
|
|
|
|
TOTP3 |
No.150 Tai O Tai Ping Street |
Residential |
3 |
3.0 |
4.5 |
√ |
|
|
|
|
|
|
KHH |
Kam Hin House |
Residential |
6 |
3.9 |
4.6 |
√ |
|
|
|
|
|
√ |
TOTP4 |
Wing Chor School |
School |
3 |
3.0 |
4.6 |
√ |
|
|
|
|
|
|
TOWO1 |
No.10 Tai O Wing On Street |
Residential |
2 |
3.0 |
4.6 |
√ |
|
|
|
|
|
|
TOWO2 |
No.52 Tai O Wing On Street |
Residential |
2 |
3.0 |
4.6 |
√ |
|
|
|
|
|
|
TOWO3 |
No.100 Tai O Wing On Street |
Residential |
3 |
3.0 |
4.6 |
√ |
|
|
|
|
|
|
LUT1 |
No.53 Leung UK Tsuen |
Residential |
3 |
2.7 |
4.7 |
√ |
|
|
|
|
|
|
LUT2 |
No.21A Leung UK Tsuen |
Residential |
3 |
4.5 |
4.7 |
√ |
|
|
|
|
|
|
NCT1 |
No. 6 Nam Chung Tsuen |
Residential |
3 |
4.4 |
4.8 |
√ |
|
|
|
|
|
|
NCT3 |
No. 7C Nam Chung Tsuen |
Residential |
1 |
3.8 |
4.8 |
√ |
|
|
|
|
|
|
NCT6 |
No.10 Nam Chung Tsuen |
Residential |
2 |
7.0 |
4.8 |
√ |
|
|
|
|
√ |
|
NTST1 |
No.4 Nam Tong Sun Tsuen |
Residential |
2 |
3.0 |
4.8 |
√ |
|
|
|
|
|
|
BCM |
Buddhist Cheung Mui Kwai Kindergarten |
School |
1 |
4.6 |
4.9 |
√ |
|
|
|
|
|
|
BHMC |
Buddhist Fat Ho Memorial College |
School |
6 |
4.2 |
4.9 |
√ |
|
|
|
|
|
√ |
WHV1 |
Wa Kwong Temple (Wang Hang Village) |
Temple |
1 |
3.0 |
4.10 |
√ |
|
|
|
|
|
|
WHV2 |
No. 4 Wang Hang Village |
Residential |
1 |
3.0 |
4.10 |
√ |
|
|
|
|
|
|
WHV3 |
No.1 Wang Hang Village |
Residential |
1 |
3.0 |
4.10 |
√ |
|
|
|
|
|
|
WHV4 |
No.21 Wang Hang Village |
Residential |
3 |
3.1 |
4.11 |
√ |
√ |
|
|
√ |
|
|
WHV5 |
No.14 Wang Hang Village |
Residential |
1 |
3 |
4.11 |
√ |
√ |
|
|
√ |
|
|
WHV6 |
No. 18 Wang Hang Village |
Residential |
2 |
3.6 |
4.11 |
√ |
√ |
|
|
√ |
|
|
WHV7 |
No. 25 Wang Hang Village |
Residential |
3 |
3.6 |
4.11 |
√ |
√ |
|
|
√ |
|
|
Notes:
Works Type 1 – Construction of sewer (Open Cut Method)
Works Type 2 – Construction of sewer (Trenchless Method)
Works Type 3 – Upgrading of existing sewers
Works Type 4 – Construction of Tai O Sewage Treatment Works & Seawall Construction
Works Type 5 – Construction of Hang Mei Sewage Pumping Station
Works Type 6 – Construction of Fan Kwai Tong Sewage Pumping Station
Works Type 7 – Temporary Working Area at Yim Tin Pok Temporary Playground
Impact Evaluation
Locate the NSRs which would most likely be affected by noise from construction work;
Determine the items of Powered Mechanical Equipment (PME) for each discrete construction activity, based on available information or agreed plant inventories;
Calculate the distance attenuation and screening effects to NSRs from notional noise source. Under the Technical Memorandum on Noise from Construction work other than Percussive Piling (GW-TM), the distance attenuation will be determined by the following formula;
Distance Attenuation in dB(A) = 20 Log D + 8 [where D is distance in metres];
A +3 dB (A) façade correction is added to the predicted noise levels to account for the façade effect at each NSR;
Calculate the unmitigated Predicted Noise Level (PNL) and correct it for façade reflection to obtain the Corrected Noise Level (CNL) at any NSRs;
If necessary, re-select typical project-specific silenced equipment and other types of mitigation measure to address noise exceedance, e.g. noise barrier and calculate the mitigated noise impact; and
Compare the mitigated CNL with the noise standards to determine acceptability and the need for further mitigation/ EM&A.
Table
4.6 : Predicted Worst-case Cumulative Construction Noise Levels
at Representative NSRs - Unmitigated Scenario
NSR |
Description of NSR |
Predicted Worst-case (Unmitigated) Construction Noise Level of different Works Type, dB(A) |
|||||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
Total |
||
SST |
CZSA Drug Treatment and Rehabilitation Centre for Male Drug Abusers |
74 |
74 |
||||||
HST |
Hung Shing Temple |
79 |
79 |
||||||
STP2 |
No.16 Shek Tsai Po Street |
104 |
63 |
104 |
|||||
STP3 |
No.6 Shek Tsai Po Street |
104 |
67 |
104 |
|||||
STP4 |
No.88 Shek Tsai Po Street |
104 |
104 |
||||||
STP5 |
No.21 Shek Tsai Po Street |
104 |
104 |
107 |
|||||
STP1 |
No.391A Shek Tsai Po Street |
104 |
87 |
87 |
|||||
KHB2 |
No.33 Kat Hing Back Street |
98 |
98 |
||||||
TOM |
No.4 Tai O Market Street |
104 |
104 |
||||||
TOTP1 |
No.190 Tai O Tai Ping Street |
98 |
98 |
||||||
TOTP3 |
No.150 Tai O Tai Ping Street |
104 |
104 |
||||||
KHH |
Kam Hin House |
83 |
47 |
83 |
|||||
TOTP4 |
Wing Chor School |
89 |
89 |
||||||
TOWO1 |
No.10 Tai O Wing On Street |
98 |
98 |
||||||
TOWO2 |
No.52 Tai O Wing On Street |
104 |
104 |
||||||
TOWO3 |
No.100 Tai O Wing On Street |
104 |
104 |
||||||
LUT1 |
No.53 Leung UK Tsuen |
104 |
104 |
||||||
LUT2 |
No.21A Leung UK Tsuen |
95 |
95 |
||||||
NCT1 |
No. 6 Nam Chung Tsuen |
95 |
95 |
||||||
NCT3 |
No. 7C Nam Chung Tsuen |
104 |
104 |
||||||
NCT6 |
No.10 Nam Chung Tsuen |
86 |
96 |
97 |
|||||
NTST1 |
No.4 Nam Tong Sun Tsuen |
104 |
104 |
||||||
BCM |
Buddhist Cheung Mui Kwai Kindergarten |
70 |
70 |
||||||
BHMC |
Buddhist Fat Ho Memorial College |
58 |
48 |
58 |
|||||
WHV1 |
Temple (Wang Hang Village) |
104 |
104 |
||||||
WHV2 |
No. 4 Wang Hang Village |
104 |
104 |
||||||
WHV3 |
No.1 Wang Hang Village |
104 |
104 |
||||||
WHV4 |
No.21 Wang Hang Village |
77 |
83 |
84 |
87 |
||||
WHV5 |
No.14 Wang Hang Village |
85 |
76 |
74 |
86 |
||||
WHV6 |
No.18 Wang Hang Village |
104 |
83 |
86 |
104 |
||||
WHV7 |
No. 25 Wang Hang Village |
104 |
83 |
86 |
104 |
Notes:
Underlined bold figure (e.g. 77) indicates an exceedance of the 75 dB(A) noise criteria (or 70 dB(A) for schools during normal teaching hours and 65 dB(A) during examination periods)
Noise criteria for TOTP4, BCM and BHMC is 70 dB(A) (65 dB(A) during examination periods).
Works Type 1 – Construction of sewer (Open Cut Method)
Works Type 2 – Construction of sewer (Trenchless Method)
Works Type 3 – Upgrading of existing sewers
Works Type 4 – Construction of Tai O Sewage Treatment Works & Seawall Construction
Works Type 5 – Construction of Hang Mei Sewage Pumping Station
Works Type 6 – Construction of Fan Kwai Tong Sewage Pumping Station
Works Type 7 – Temporary Working Area at Yim Tin Pok Temporary Playground
General Mitigation Measures
only well-maintained plants should be operated on-site and plants should be serviced regularly during the construction works;
machines and plants that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum;
plants known to emit noise strongly in one direction should, where possible, be orientated to direct noise away from the NSRs;
mobile plant should be sited as far away from NSRs as possible; and
material stockpiles and other structures should be effectively utilized, where practicable, to screen noise from on-site construction activities.
Level 1 Noise Mitigation Measures - Quiet PMEs and Temporary Noise Barrier
Table 4.7 : Silenced Equipments
Description of PME |
Equivalent Quiet PME |
SWL, dB(A) |
Generator |
BS 5228 Table C4/78 |
94 |
Poker, vibratory, hand-held |
BS 5228 Table C4/34 |
97 |
Road Roller |
BS 5228 Table D8/25 |
96 |
Breaker, excavator mounted |
BS 5228 Table C9/12 |
113 |
Excavator |
BS 5228 Table C4/65 |
99 |
Excavator, tracked |
QPME EPD-02101 |
90 |
Crane, mobile mounted |
BS 5228 Table C4/50 |
99 |
Dumper |
BS 5228 Table D3/98 |
101 |
Vibratory Compactor |
BS 5228 Table D8/25 |
96 |
Drill Rig |
BS 5228 Table D10/2 |
112 |
Hydraulic Vibratory Driver for driving Sheet Piling |
BS 5228 Table D4/12 |
94 |
Enclosure for stationary plant – assuming 15 dB(A) reduction on stationary plant;
Temporary noise barrier for stationary plant – assuming 10 dB(A) reduction on stationary plants;
Temporary noise barrier for mobile plant – assuming 5 dB(A) reduction on mobile plants.
Table 4.8 : Noise Mitigation Measures for Certain PME
Description of PME |
Proposed Mitigation Measures |
Assumed Noise Reduction, dB(A) |
Backhoe (mini) |
Noise Barrier (Mobile) |
5 |
Breaker, excavator mounted |
Noise Barrier (Mobile) |
5 |
Crane, mobile mounted |
Noise Barrier (Mobile) |
5 |
Excavator |
Noise Barrier (Mobile) |
5 |
Excavator, tracked |
Noise Barrier (Mobile) |
5 |
Dumper |
Noise Barrier (Mobile) |
5 |
Breaker, hand-held, mass≥20kg and ≤35kg |
Noise Barrier (Stationary) |
10 |
Vibratory compactor |
Noise Barrier (Stationary) |
10 |
Piling, earth auger, auger |
Noise Barrier (Stationary) |
10 |
Hoist (electric) |
Noise Barrier (Stationary) |
10 |
Bentonite Filtering Plant |
Noise Barrier (Stationary) |
10 |
Ventilation Fan |
Noise Barrier (Stationary) |
10 |
Grout Mixer |
Noise Barrier (Stationary) |
10 |
Grout Pump |
Noise Barrier (Stationary) |
10 |
Hydraulic Vibratory Driver for driving Sheet Piling |
Noise Barrier (Stationary) |
10 |
Welding Machine |
Noise Barrier (Stationary) |
10 |
Concrete Pump |
Noise Barrier (Stationary) |
10 |
Saw, circular, wood |
Noise Barrier (Stationary) |
10 |
Submersible Pump |
Noise Barrier (Stationary) |
10 |
Winch (electric) |
Noise Barrier (Stationary) |
10 |
Drill/grinder, hand-held |
Noise Barrier (Stationary) |
10 |
Road Roller |
Noise Barrier (Stationary) |
10 |
Tunnel Boring Machine |
Noise Barrier (Stationary) |
10 |
Pulverizer mounted on excavator |
Noise Barrier (Stationary) |
10 |
Submersible Pump |
Enclosure (Stationary) |
15 |
Generator |
Enclosure (Stationary) |
15 |
Poker, vibratory hand-held |
Enclosure (Stationary) |
15 |
Bar bender and cutter (electric) |
Enclosure (Stationary) |
15 |
Table 4.9 : Predicted Maximum Construction
Noise Levels
at Representative NSRs with Level 1 Mitigation Measures
NSR |
Description of NSR |
Predicted Mitigated (Level 1) Construction Noise Level of different Works Type, dB(A) |
|||||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
Total |
||
SST |
CZSA Drug Treatment and Rehabilitation Centre for Male Drug Abusers |
71 |
71 |
||||||
HST |
Hung Shing Temple |
54 |
54 |
||||||
STP2 |
No.16 Shek Tsai Po Street |
80 |
39 |
80 |
|||||
STP3 |
No.6 Shek Tsai Po Street |
80 |
43 |
80 |
|||||
STP4 |
No.88 Shek Tsai Po Street |
80 |
80 |
||||||
STP5 |
No.21 Shek Tsai Po Street |
80 |
80 |
83 |
|||||
STP1 |
No.391A Shek Tsai Po Street |
80 |
63 |
80 |
|||||
KHB2 |
No.33 Kat Hing Back Street |
74 |
74 |
||||||
TOM |
No.4 Tai O Market Street |
80 |
80 |
||||||
TOTP1 |
No.190 Tai O Tai Ping Street |
74 |
74 |
||||||
TOTP3 |
No.150 Tai O Tai Ping Street |
80 |
80 |
||||||
KHH |
Kam Hin House |
59 |
47 |
59 |
|||||
TOTP4 |
Wing Chor School |
64 |
64 |
||||||
TOWO1 |
No.10 Tai O Wing On Street |
74 |
74 |
||||||
TOWO2 |
No.52 Tai O Wing On Street |
80 |
80 |
||||||
TOWO3 |
No.100 Tai O Wing On Street |
80 |
80 |
||||||
LUT1 |
No.53 Leung UK Tsuen |
80 |
80 |
||||||
LUT2 |
No.21A Leung UK Tsuen |
70 |
70 |
||||||
NCT1 |
No. 6 Nam Chung Tsuen |
70 |
70 |
||||||
NCT3 |
No. 7C Nam Chung Tsuen |
80 |
80 |
||||||
NCT6 |
No.10 Nam Chung Tsuen |
62 |
75 |
75 |
|||||
NTST1 |
No.4 Nam Tong Sun Tsuen |
80 |
80 |
||||||
BCM |
Buddhist Cheung Mui Kwai Kindergarten |
46 |
46 |
||||||
BHMC |
Buddhist Fat Ho Memorial College |
33 |
48 |
48 |
|||||
WHV1 |
Temple (Wang Hang Village) |
80 |
80 |
||||||
WHV2 |
No. 4 Wang Hang Village |
80 |
80 |
||||||
WHV3 |
No.1 Wang Hang Village |
80 |
80 |
||||||
WHV4 |
No.21 Wang Hang Village |
53 |
69 |
63 |
70 |
||||
WHV5 |
No.14 Wang Hang Village |
61 |
62 |
53 |
65 |
||||
WHV6 |
No.18 Wang Hang Village |
80 |
69 |
65 |
80 |
||||
WHV7 |
No. 25 Wang Hang Village |
80 |
69 |
65 |
80 |
Notes:
Underlined bold figure (e.g. 77) indicates an exceedance of the 75 dB(A) noise criteria (or 70 dB(A) for schools during normal teaching hours and 65 dB(A) during examination periods)
Noise criteria for TOTP4, BCM and BHMC is 70 dB(A) (65 dB(A) during examination periods).
Works Type 1 – Construction of sewer (Open Cut Method)
Works Type 2 – Construction of sewer (Trenchless Method)
Works Type 3 – Upgrading of existing sewers
Works Type 4 – Construction of Tai O Sewage Treatment Works & Seawall Construction
Works Type 5 – Construction of Hang Mei Sewage Pumping Station
Works Type 6 – Construction of Fan Kwai Tong Sewage Pumping Station
Works Type 7 – Temporary Working Area at Yim Tin Pok Temporary Playground
Level 2 Noise Mitigation Measures – Good Scheduling of Works
Level 3 Noise Mitigation Measures –
Alternative Construction Method
NSR |
Description of NSR |
Predicted Mitigated (Level 1) Construction Noise Level of different Works Type, dB(A) |
|||||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
Total |
||
SST |
CZSA Drug Treatment and Rehabilitation Centre for Male Drug Abusers |
71 |
71 |
||||||
HST* |
Hung Shing Temple |
49 |
49 |
||||||
STP2 |
No.16 Shek Tsai Po Street |
75 |
34 |
75 |
|||||
STP3 |
No.6 Shek Tsai Po Street |
75 |
38 |
75 |
|||||
STP4 |
No.88 Shek Tsai Po Street |
75 |
75 |
||||||
STP5 |
No.21 Shek Tsai Po Street |
75 |
75 |
75(1) |
|||||
STP1 |
No.391A Shek Tsai Po Street |
75 |
58 |
75 |
|||||
KHB2* |
No.33 Kat Hing Back Street |
69 |
69 |
||||||
TOM |
No.4 Tai O Market Street |
75 |
75 |
||||||
TOTP1* |
No.190 Tai O Tai Ping Street |
69 |
69 |
||||||
TOTP3 |
No.150 Tai O Tai Ping Street |
75 |
75 |
||||||
KHH* |
Kam Hin House |
54 |
47 |
55 |
|||||
TOTP4* |
Wing Chor School |
59 |
59 |
||||||
TOWO1* |
No.10 Tai O Wing On Street |
69 |
69 |
||||||
TOWO2 |
No.52 Tai O Wing On Street |
75 |
75 |
||||||
TOWO3 |
No.100 Tai O Wing On Street |
75 |
75 |
||||||
LUT1 |
No.53 Leung UK Tsuen |
75 |
75 |
||||||
LUT2* |
No.21A Leung UK Tsuen |
66 |
66 |
||||||
NCT1* |
No. 6 Nam Chung Tsuen |
66 |
66 |
||||||
NCT3 |
No. 7C Nam Chung Tsuen |
75 |
75 |
||||||
NCT6* |
No.10 Nam Chung Tsuen |
57 |
75 |
75 |
|||||
NTST1 |
No.4 Nam Tong Sun Tsuen |
75 |
75 |
||||||
BCM* |
Buddhist Cheung Mui Kwai Kindergarten |
41 |
41 |
||||||
BHMC* |
Buddhist Fat Ho Memorial College |
28 |
48 |
48 |
|||||
WHV1 |
Temple (Wang Hang Village) |
75 |
75 |
||||||
WHV2 |
No. 4 Wang Hang Village |
75 |
75 |
||||||
WHV3 |
No.1 Wang Hang Village |
75 |
75 |
||||||
WHV4* |
No.21 Wang Hang Village |
48 |
69 |
63 |
70 |
||||
WHV5* |
No.14 Wang Hang Village |
56 |
62 |
53 |
63 |
||||
WHV6 |
No.18 Wang Hang Village |
75 |
69 |
65 |
75(2) |
||||
WHV7 |
No. 25 Wang Hang Village |
75 |
69 |
65 |
75(2) |
Cumulative Impact
Improvement of Works at Tai O – Design and Construction
Natural Terrain Hazard Mitigation Works
Water Supply from Tung Chung to Tai O (Previously name as Improvement of Water Supply for Tai O Facelift)
Replacement and Rehabilitation of Water Mains Stage 4, Mains on Hong Kong and Islands – Investigation, Design and Construction
HZMB and related
projects, including HKLR, HKBCF and TM-CLKL
Conclusion
Table 4.11: Major Noise Generating Equipment (Operational Phase)
Location |
Equipment |
No. of Units |
Typical Sound Power Level, dB(A) |
Sub-total Sound Power Level, dB(A) |
Hang Mei Sewage Pumping Station |
||||
Plant Room |
Submersible pump (Ref. 1) |
1 |
85 |
85 |
Deodourization fan (Ref. 2) |
1 |
85 |
85 |
|
Exhaust Fan (Ref. 3) |
1 |
79 |
79 |
|
Fan Kwai Tong Sewage Pumping Station |
||||
Plant Room |
Submersible pump (Ref. 1) |
1 |
85 |
85 |
Deodourization fan (Ref. 2) |
1 |
85 |
85 |
|
Exhaust Fan (Ref. 3) |
1 |
79 |
79 |
|
Tai O Sewage Treatment Works |
||||
Sewage Treatment Facilities Facilities |
Submersible pump (Ref. 1) |
16 |
85 |
97 |
Mechanically raked fine screen (Ref. 4) |
2 |
92 |
95 |
|
Deodourization fan (Ref. 2) |
14 |
85 |
96 |
|
Exhaust Fan (Ref. 3) |
45 |
79 |
96 |
|
Mechanical pump (Ref. 5) |
25 |
92 |
106 |
|
Blower (Ref. 6) |
6 |
85 |
93 |
Notes:
Only noisy equipments have been included. Other equipments
which do not have significant noise emissions have not been included.
(Ref 1) SWL of plant
referenced to CNP283
(Ref 2)
SWL of plant refers to Good Practices on Ventilation System Noise Control based
on the flow rate of 17,000 m3/hr and 125 Pa.
(Ref
3) SWL of plant referenced to approved EIA of Harbour Area Treatment Scheme
(HATS) Stage 2A (EIA-148/2008) and Good Practices on Ventilation System Noise
Control based on the flow rate of 1,300m3/hr.
(Ref
4) SWL of plant has referenced to the approved EIA Report on Tai Po Sewage
Treatment Works Stage V (EIA-097/2004).
(Ref
5) SWL of plant refers to Good Practices on Pumping System Noise Control based
on the horsepower of pumpset 20hp at 1800 rpm.
(Ref
6) SWL of plant refers to the tender specification for Shatin
STW Stage 3 Upgrading and approved EIA of Harbour Area Treatment Scheme (HATS)
Stage 2A (EIA-148/2008).
Noise Sensitive Receivers
Table 4.12: Representative Noise Sensitive Receivers (Operational Phase)
NSR |
Description of NSR |
Approximate Nearest Horizontal Separation(1) |
||
Tai O STW |
Hang Mei SPS |
Fan Kwai Tong SPS |
||
SST |
CZSA Drug Treatment and Rehabilitation Centre for Male Drug Abusers |
211m |
No direct line of sight (over 800m) |
No direct line of sight (over 1.4km) |
NCT6 |
No.10 Nam Chung Tsuen |
No direct line of sight (over 1.5km) |
11m |
|
WHV4 |
No.21 Wang Hang Village |
46m |
No direct line of sight (over 800m) |
|
WHV6 |
No.18 Wang Hang Village |
35m |
||
WHV7 |
No. 25 Wang Hang Village |
41m |
||
PT2(2) |
GIC Site (currently occupied as Nam Chung Village Aqua Privy) |
No direct line of sight (over 800m) |
14m |
(2) Planned NSR
Operational Noise Impact Evaluation
Table 4.13: Predicted Worst-case Maximum Operational Noise Levels at Representative NSRs – Without Mitigation Measures
NSR |
NSR Description |
Predicted Unmitigated Noise Level, dB(A) |
Night-time (2300 – 0700) Noise Criterion, dB(A) |
Day-time (0700 – 1900) & Evening time (1900 – 2300) Noise Criterion, dB(A) |
SST |
CZSA Drug Treatment and Rehabilitation Centre for Male Drug Abusers |
56 |
45 |
50 |
NCT6 |
No.10 Nam Chung Tsuen |
59 |
42 |
45 |
WHV4 |
No.21 Wang Hang Village |
50 |
39 |
45 |
WHV6 |
No.18 Wang Hang Village |
53 |
39 |
45 |
WHV7 |
No. 25 Wang Hang Village |
51 |
39 |
45 |
PT2(1) |
GIC Site (currently occupied as Nam Chung Village Aqua Privy) |
58 |
42 |
45 |
Possible Noise Mitigation Measures and Mitigated Impacts
Table 4.14: Proposed Noise Mitigation Measures for Equipments during Operation Phase
Location |
Equipment |
Mitigation Measures |
Noise Reduction |
Hang Mei
Sewage Pumping Station |
Submersible pump |
enclosed inside SPS building structure |
-20 dB(A) |
Deodourization fan |
enclosed inside SPS building structure |
-20 dB(A) |
|
Exhaust fan |
noise source does not have direct line of sight to NSR |
-10 dB(A) |
|
Fan Kwai Tong Sewage Pumping Station |
Submersible pump |
enclosed inside SPS building structure |
-20 dB(A) |
Deodourization fan |
enclosed inside SPS building structure |
-20 dB(A) |
|
Exhaust fan |
noise source does not have direct line of sight to NSR |
-10 dB(A) |
|
Tai O Sewage Treatment
Works |
Submersible pump |
enclosed inside treatment unit building structure |
-20 dB(A) |
Mechanically raked fine screen |
enclosed inside STW building structure |
-20 dB(A) |
|
Deodourization fan |
enclosed inside STW building structure |
-20 dB(A) |
|
Exhaust Fan |
Noise source does not have direct line of sight to NSR |
-10 dB(A) |
|
Mechanical Pump |
enclosed inside STW building structure |
-20 dB(A) |
|
Blower |
enclosed inside STW building structure |
-20 dB(A) |
Table 4.15 : Predicted Maximum Operational Noise Levels at Representative NSRs
– With Mitigation Measures
NSR |
NSR Description |
Predicted Mitigated Noise Level, dB(A) |
Night-time (2300 – 0700) Noise Criterion, dB(A) |
Day-time (0700 – 1900) & Evening time (1900 – 2300) Noise Criterion, dB(A) |
SST |
CZSA Drug Treatment and Rehabilitation Centre for Male Drug Abusers |
38 |
45 |
50 |
NCT6 |
No.10 Nam Chung Tsuen |
41 |
42 |
45 |
WHV4 |
No.21 Wang Hang Village |
33 |
39 |
45 |
WHV6 |
No.18 Wang Hang Village |
36 |
39 |
45 |
WHV7 |
No. 25 Wang Hang Village |
34 |
39 |
45 |
PT2(1) |
GIC Site (currently occupied as Nam Chung Village Aqua Privy) |
41 |
42 |
45 |
Residual Impact
Environmental Monitoring and Audit Requirements
Conclusion