General
· Technical Memorandum on the Environmental Impact Assessment Process (EIAO-TM);
· Technical Memorandum on Noise from Percussive Piling (PP-TM);
· Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM);
· Technical Memorandum on Noise from Construction Work in Designated Areas (DA-TM); and
· Technical Memorandum on Noise from Places other than Domestic Premises, Public Places or Construction Sites (IND-TM);
Construction Noise during Non-restricted Hours
Table 4.1 Noise Criteria for Daytime Construction Noise
Uses |
Daytime (0700 to1900 hours on any day not being a Sunday or general holiday), Leq (30mins), dB(A) |
Domestic premises |
75 |
Educational Institution |
70 |
Educational Institution (during examination) |
65 |
Notes:
(a) The above standards apply to uses which rely on opened windows for ventilation.
(b) The above standards shall be viewed as the maximum permissible noise levels assessed at 1m from the external façade
Construction Noise during Restricted Hours
Table 4.2 ANLs under GW-TM
Time Period |
ANL on Different Area Sensitivity Rating During Restricted Hours (Leq, 5mins, dB(A)) |
||
ASR A |
ASR B |
ASR C |
|
All days during evening (1900 to 2300 hours), and general holidays (including Sundays) during the day-time and evening (0700 to 2300 hours) |
60 |
65 |
70 |
All days during the night-time (2300 to 0700 hours) |
45 |
50 |
55 |
· Erecting or dismantling of formwork or scaffolding;
· Loading, unloading or handling of rubble, wooden boards, steel bars, wood or scaffolding material; and
· Hammering.
Table 4.3 ANLs under DA-TM
Time Period |
ANL on Different Area Sensitivity Rating During Restricted Hours (Leq, 5mins, dB(A)) |
||
ASR A |
ASR B |
ASR C |
|
All days during evening (1900 to 2300 hours), and general holidays (including Sundays) during the day-time and evening (0700 to 2300 hours) |
45 |
50 |
55 |
All days during the night-time (2300 to 0700 hours) |
30 |
35 |
40 |
Construction Ground-borne Noise
Table 4.4 Noise Criteria for Construction Ground-borne Noise
Type of NSR / Assessment Point (d) |
Ground-borne Noise Criteria(a) |
||
Daytime (0700 to1900 hours on any day not being a Sunday or general holiday), Leq (30mins), dB(A) |
(Leq 5 mins, dB(A)) |
All days during the
night-time (Leq 5 mins, dB(A)) |
|
Domestic premises, hotels and service apartments |
65 |
55 |
40 |
Schools |
60 / 55 (c) |
55 |
N/A (b) |
Notes:
(a) Ground-borne noise transmitted primarily through structural elements of the building(s) affects internal area of the building(s), and hence it is assumed that the NSR at the internal location of building(s) is not affected by Influencing Factors (IF) such as major roads and industrial areas. As all of the identified ground-borne NSRs within the study area of the Project are located in either “Urban Area” or “Area other than above”, therefore, Area Sensitivity Rating of “B” is considered for identifying criteria during restricted hours.
(b) Generally, no sensitive use/operation during this time period.
(c) A 5dB(A) reduction to the ground-borne noise criteria is recommended for school during examination period.
(d) Assessment point locates at an internal location of a building in which the NSR is located.
Road Traffic Noise
Table 4.5 Noise Criteria for Road Traffic Noise
NSR ID |
Road Traffic Noise Criteria, L10 (1hr), dB(A) |
All domestic premises including temporary housing accommodation |
70 |
Hotel and hostels |
70 |
Offices |
70 |
Educational institutions including kindergartens, nurseries and all others where unaided voice communication is required |
65 |
Places of public Worship and courts of law |
65 |
Hospitals, clinics, convalescences and homes for the aged, diagnostic rooms, wards |
55 |
Remarks:
(a) The road traffic noise criteria apply to uses which rely on opened window for ventilation only.
(b) The road traffic noise criteria should be viewed as the maximum permissible noise levels assessed at 1 m from the external façade.
Fixed Noise Sources
Table 4.6 Noise Criteria for Fixed Noise Sources
Time Period |
Fixed Noise Criteria for Different Area Sensitivity Rating(Leq 30 min, dB(A)) (a) |
|||||
ANL, dB(A) |
ANL-5, dB(A) for |
|||||
ASR A |
ASR B |
ASR C |
ASR A |
ASR B |
ASR C |
|
Day (0700 to 1900 hrs) |
60 |
65 |
70 |
55 |
60 |
65 |
Evening (1900 to 2300 hrs) |
60 |
65 |
70 |
55 |
60 |
65 |
Night (2300 to 0700 hrs) |
50 |
55 |
60 |
45 |
50 |
55 |
(a) The fixed noise criteria apply to uses which rely on opened window for ventilation only.
(b) The above standards should be viewed as the maximum permissible noise levels assessed at 1 m from the external façade.
Table 4.7 Identified Noise Sensitive Receivers within 300m from the Boundary of the Project (Kowloon Side)
NSR ID |
Description |
Land Use |
PHD |
Planned Housing Development (NKJ6579) |
Planned Residential |
LCC |
Lung Cheung Court |
Residential |
WG |
Welcome Gardens |
Residential |
MC |
Marple Court |
Residential |
AC |
Alice Court |
Residential |
JC |
Jumbo Court |
Residential |
WH |
Westland Heights |
Residential |
EH |
Eastland Heights |
Residential |
PH |
Peninsula Heights |
Residential |
MH |
Meridian Hill |
Residential |
TP |
The Palace |
Residential |
KKC |
Ka Keung Court |
Residential |
LSTYKHSS |
Lok Sin Tong Yu Kan Hing Secondary School |
Educational |
TMC |
Tin Ma Court |
Residential |
K01 |
Beverley Heights |
Residential |
K02 |
Pearl Court |
Residential |
K03 |
Vista Panorama |
Residential |
K04 |
Chermain Heights |
Residential |
K05 |
Dragon Heights |
Residential |
K06 |
Joy Garden |
Residential |
K07 |
Manhattan Court |
Residential |
K08 |
Le Chateau |
Residential |
K09 |
Moonbeam Terrace |
Residential |
K10 |
Luso Apartments |
Residential |
K11 |
Beacon Hill School |
Educational |
K12 |
Orion Court |
Residential |
K13 |
Ede Terrace |
Residential |
K14 |
Eden Gate Tower 1 |
Residential |
K15 |
Arcadia Gardens |
Residential |
K16 |
Verdun Villa |
Residential |
K17 |
Hong Kong Baptist University |
Residential |
K18 |
Commercial Radio |
Office |
K19 |
Radio Television Hong Kong TV House |
Office |
K20 |
Radio Television Hong Kong Broadcasting House |
Office |
K21 |
Carlton Court |
Residential |
K22 |
Boland Court |
Residential |
K23 |
Belmont Heights |
Residential |
K24 |
Fairyland Garden |
Residential |
K25 |
Broadway Towers |
Residential |
K26 |
Comfort Court |
Residential |
K27 |
Marconi Court |
Residential |
K28 |
Twilight Court |
Residential |
K29 |
Faber Garden |
Residential |
K30 |
Phoenix Court |
Residential |
K31 |
Fessenden Court |
Residential |
K32 |
Kwong Fai Court |
Residential |
K33 |
Avon Court |
Residential |
K34 |
Merry Court |
Residential |
K35 |
Jade Court |
Residential |
K36 |
Rockford Mansion and Clifford Mansion |
Residential |
K37 |
Merlin Court |
Residential |
K38 |
Ava Court |
Residential |
K39 |
Radio Television Hong Kong Education Television Centre |
Office |
K40 |
Happy Garden |
Residential |
K41 |
87 - 91 Broadcast Drive |
Residential |
K42 |
Kit Sam Lam Bing Yim Secondary School |
Educational |
K43 |
Wang Tau Hom Estate |
Educational |
K44 |
Price Memorial Catholic Primary School |
Educational |
K45 |
Tin Wang Court |
Residential |
K46 |
Grace Methodist Church Kindergarten |
Educational |
K47 |
Tsui Chuk Garden |
Residential |
S16 (a) |
Lion Rock Country Park |
Recreational |
Notes:
(a) In accordance with Annex 13 of the EIAO-TM, country parks are considered to be a NSR. However, the EIAO-TM and IND-TM do not provide a specific noise limits for Country Parks.
Table 4.8 Identified NSRs within 300m from the Boundary of the Project (Shatin Side)
NSR ID |
Description |
Land Use |
STWTWSQ |
Shatin Water Treatment Works Staff Quarter |
Residential |
KATC |
Ka Tin Court |
Residential |
HLMSS |
Helen Liang Memorial Secondary School |
Educational |
KSC |
Ka Shun Court |
Residential |
UC |
Union Court |
Residential |
HP |
Hill Paramount |
Residential |
JG |
Julimount Garden |
Residential |
Educational |
||
WWG |
World-Wide Garden |
Residential |
KTC |
King Tin Court |
Residential |
GLG |
Golden Lion Garden |
Residential |
HMKR |
Hung Mui Kuk Road Village Houses |
Residential |
KTV |
Kak Tin Village / Kak Tin Village Kung Miu |
Residential |
MWG |
Merry World Garden |
Residential |
KTVT |
Kak Tin Village Temple (Koon Yam Kok and Fat Wan Lan Yuek) |
Place of Public Worship |
STGPS |
Shatin Government Primary School |
Educational |
STW |
Sun Tin Wai Estate |
Residential |
STTNV |
Shatin Tau New Village |
Residential |
FSC |
Fung Shing Court |
Residential |
STT |
Shatin Tau Village |
Residential |
S01 |
Hin Keng Estate |
Residential |
S02 |
C.U.H.K.F.A.A. Thomas Cheung School |
Educational |
S03 |
Hin Tin Village Houses |
Residential |
S04 |
Union Hospital |
Hospital |
S05 |
Parc Royale |
Residential |
S06 |
Choi Jun School |
Educational |
S07 |
Ha Keng Hau Village Houses |
Residential |
S08 |
Lung Hang Estate |
Residential |
S09 |
Golden Lion Garden Stage 1 |
Residential |
S10 |
Shatin Methodist College |
Educational |
S11 |
Christian Alliance H. C. Chan Primary School |
Educational |
S12 |
Shatin Methodist College (Ample Campus) |
Educational |
S13 |
Kwok Tak Seng Catholic Secondary School |
Educational |
S14 |
Chun Shek Estate |
Residential |
S15 |
Shan Ha Wai (Tsang Tai Uk) Village Houses |
Residential |
S16 (a) |
Lion Rock Country Park |
Recreational |
S17 |
Lok Sin Tong Young Ko Hsiao Lin Secondary School |
Educational |
Notes:
(a) In accordance with Annex 13 of the EIAO-TM, country parks are considered to be a NSR. However, the EIAO-TM and IND-TM do not provide a specific noise limits for Country Parks.
Noise Assessment Points for Construction Noise Impact Assessment
Table 4.9 Identified Representative Noise Assessment Points for Construction Noise Impact Assessment
NAP ID |
Description |
Land Use |
Number of Storeys |
Floor of selected assessment point (a) |
Kowloon Side |
||||
EH1 |
Eastland Heights |
Residential |
6 |
1/F, 5/F & 6/F |
MC1 |
Rear Block, Marple Court |
Residential |
9 |
1/F, 3/F & 9/F |
PH2 |
Block B, Peninsula Heights |
Residential |
15 |
1/F, 8/F & 15/F |
PHD1 |
Planned Housing Development (NKIL6579) |
Planned Residential |
13 |
1/F, 7/F & 13/F |
Shatin Side |
||||
WSH2 |
Wah Shing House, Fung Shing Court |
Residential |
34 |
1/F, 3/F& 34/F |
STTNV1 |
Village House, Sha Tin Tau New Village |
Residential |
1 |
G/F |
STTNV2 |
Village House, Sha Tin Tau New Village |
Residential |
1 |
G/F |
STTNV5 |
Village House, Sha Tin Tau New Village |
Residential |
2 |
G/F,1/F |
STW2 |
Shing Wai House, Sun Tin Wai Estate |
Residential |
20 |
1/F, 10/F & 20/F |
STW6 |
Yu Wai House, Sun Tin Wai Estate |
Residential |
17 |
1/F, 9/F & 17/F |
STGPS2
|
Sha Tin Government Primary School |
Educational |
7 |
1/F. 5/F & 7/F |
KTV2 |
House 3, Kak Tin Village |
Residential |
1 |
G/F |
MWG1 |
Merry World Garden |
Residential |
3 |
1/F. 2/F & 3/F |
KTV5 |
House 36, Kak Tin Village |
Residential |
3 |
1/F. 2/F & 3/F |
HMKR1 |
Hung Mui Kuk Road Village Houses |
Residential |
1 |
G/F |
WWG5 |
Block 4, World-Wide Gardens |
Residential |
20 |
1/F, 10/F & 20/F |
WWG8 |
Block 3A, World-Wide Gardens |
Residential |
21 |
1/F, 10/F & 21/F |
JG4 |
Block 3. Julimount Garden |
Residential |
21 |
1/F, 4/F & 21/F |
HP1 |
House 1, Hill Paramount |
Residential |
3 |
1/F. 2/F & 3/F |
UC1 |
Union Court |
Residential |
24 |
1/F, 5/F & 24/F |
KSC1 |
Ka Shun Court |
Residential |
31 |
1/F, 15/F & 31/F |
KATC1 |
Ka Yin House, Ka Tin Court |
Residential |
35 |
1/F, 20/F & 35/F |
Note:
(a) Bolded floor levels indicate the floor closest to the construction work zones. The selected floors are considered as representative floors for the NSR in the assessment.
Noise Assessment Points for Ground-borne Construction Noise
Noise Assessment Points for Road Traffic Noise Impact Assessment
Table 4.10 Noise Assessment Points for Road Traffic Noise Impact Assessment
NAP ID |
Description |
Land Use |
Number of Noise Sensitive Storeys |
Road Traffic Noise Criteria, L10 (1hr), dB(A) |
Kowloon Side |
||||
AC1 |
Alice Court |
Residential |
9 |
70 |
EH1 |
Eastland Heights |
Residential |
6 |
70 |
EH2 |
||||
JC1 |
Jumbo Court |
Residential |
9 |
70 |
LCC1 |
Lung Cheung Court |
Residential |
4 |
70 |
LCC2 |
5 |
70 |
||
LCC3 |
7 |
70 |
||
MC1 |
Rear Block, Marple Court |
Residential |
9 |
70 |
PH1 |
Peninsula Heights
|
Residential |
15 |
70 |
PH2 |
70 |
|||
PHD1 |
Planned Housing Development (NKIL6579) |
Planned Residential |
13 |
70 |
PHD2 |
||||
PHD3 |
||||
WG1 |
Welcome Gardens |
Residential |
9 |
70 |
WH1 |
Wetland Heights |
Residential |
8 |
70 |
KKC1 |
Ka Keung Court |
Residential |
37 |
70 |
LSTYKHSS1 |
Lok Sin Tong Yu Kan Hing Secondary School |
Educational |
6 |
65 |
TMC1 |
Tin Ma Court |
Residential |
37 |
70 |
MH1 |
Meridian Hill |
Residential |
9 |
70 |
TP1 |
The Palace |
Residential |
33 |
70 |
Shatin Side |
||||
STWTWSQ |
Sha Tin Water Treatment Works Staff Quarters |
Residential |
4 |
70 |
KATC1 |
Ka Tin Court |
Residential |
35 |
70 |
HLMSS1 |
Helen Liang Memorial Secondary School |
Educational |
6 |
65 |
KSC1 |
Ka Shun Court |
Residential |
31 |
70 |
UC1 |
Union Court |
Residential |
24 |
70 |
HP1 |
Hill Paramount |
Residential |
3 |
70 |
HP2 |
27 |
70 |
||
JG1 |
Julimount Garden |
Residential |
25 |
70 |
JG2 |
23 |
70 |
||
JG3 |
21 |
70 |
||
JG4 |
21 |
70 |
||
JG5 |
20 |
70 |
||
JG6 |
18 |
70 |
||
POHCKMC |
Pok Oi Hospital Chan Kai Memorial College |
Educational |
6 |
65 |
WWG1 |
World-Wide Garden |
Residential |
15 |
70 |
WWG2 |
70 |
|||
WWG3 |
70 |
|||
WWG4 |
20 |
70 |
||
WWG5 |
70 |
|||
WWG6 |
70 |
|||
WWG7 |
21 |
70 |
||
WWG8 |
70 |
|||
WWG9 |
70 |
|||
KTC1 |
King Tin Court |
Residential |
30 |
70 |
KTC2 |
70 |
|||
KTC3 |
70 |
|||
KTC4 |
70 |
|||
GLG1 |
Golden Lion Garden |
Residential |
28 |
70 |
GLG2 |
70 |
|||
HMKR1 |
Hung Mui Kuk Road Village Houses |
Residential
|
1
|
70 |
HMKR2 |
70 |
|||
KTV1 |
Kak Tin Village and Kak Tin Village Kung Miu |
Residential |
3 |
70 |
KTV2 |
70 |
|||
KTV3 |
70 |
|||
KTV4 |
70 |
|||
KTV5 |
70 |
|||
MWG1 |
Merry World Garden |
Residential |
3 |
70 |
KTVT1 |
Koon Yam Kok |
Place of Public Worship |
1 |
65 |
KTVT2 |
Fat Wan Lan Yeuk |
Place of Public Worship |
1 |
65 |
STGPS1 |
Shatin Government Primary School |
Educational |
7 |
65 |
STGPS2 |
3 |
65 |
||
Sun Tin Wai Estate |
Residential |
20 |
70 |
|
STW2 |
70 |
|||
STW3 |
70 |
|||
STW4 |
70 |
|||
STW5 |
17 |
70 |
||
STW6 |
70 |
|||
STTNV1 |
Shatin Tau New Village |
Residential |
1 |
70 |
STTNV2 |
70 |
|||
STTNV3 |
70 |
|||
STTNV4 |
70 |
|||
STTNV5 |
2 |
70 |
||
FSC1 |
Fung Shing Court |
Residential |
34 |
70 |
FSC2 |
70 |
|||
FSC3 |
70 |
|||
STT1 |
Shatin Tau Village |
Residential |
3 |
70 |
STT2 |
70 |
Noise Assessment Points for Fixed Noise Sources Impact Assessment
Construction Phase
· Construction of a road tunnel of approximately 1.4 km long between the two existing tunnel tubes of the LRT by Tunnel Boring Machine (TBM);
· Enlargement of the existing Kowloon bound tunnel tube to a three-lane road tunnel, together with the construction of cross passages linking the new Kowloon bound tunnel tube with the new tunnel
· Full-scale rehabilitation/reconstruction of the existing tunnel tubes of the LRT from tunnel lining to equipment and fittings following the latest standards;
· Demolish the existing toll plaza together with the provision of equipment and facilities for free-flow tolling;
· Re-provision of tunnel buildings including tunnel administration building, ventilation buildings etc.;
· Widening of Lion Rock Tunnel Road at Kowloon side to dual three-lane from slip road of Lung Cheung Road interchange to LRT Kowloon portal and construct a single lane vehicular bridge crossing over Lung Cheung Road for the Shatin bound direction;
· Widening of the slip road from Lion Rock Tunnel Road southbound (S/B) to Lung Cheung Road eastbound (E/B) to two lanes, and realigning the slip road from Lung Cheung Road (E/B) to Lion Rock Tunnel Road northbound (N/B);
· Widening of a section of Lion Rock Tunnel Road at Shatin side to dual three-lane from tunnel toll plaza to Fung Shing Court;
· Provision of noise barriers/enclosures to mitigate the noise impact on noise sensitive receivers;
· Reprovisioning of footbridge NF74; and
· Ancillary works including slope works/formation (including rigid and flexible barriers for natural terrain hazard mitigation measures), road lighting, drainage, landscaping works, etc.
· TBM Tunneling and works inside tunnels
· Construction of Noise Barrier Structures
· Demolition and Erection of Sign Gantries
· Construction of New Vehicular Bridge next to Existing K7A Vehicular Bridge
· Construction of New Vehicular Cross-over Bridge at Shatin Portal
Operation Phase Road Traffic Noise Sources
(a) Construction of a new single lane vehicular bridge parallel to the existing K7A vehicular bridge to provide direct connection between the road section mentioned in 4.5.7(b) to the northbound road section mentioned in 4.5.7(c) (Road Section (a) in Appendix 4.17b);
(b) A section of existing Waterloo Road N/B: widening from two lanes to three lanes (Road Section (b) in Appendix 4.17b);
(c) A section of existing Lion Rock Tunnel Road (immediate next to the proposed Kowloon portal) both N/B and S/B (southbound): widening from dual two lanes to dual three lanes, and alignment shift to align with the tunnel portals (Road Section (c) in Appendix 4.17b);
(d) An existing slip road from Lion Rock Tunnel Road S/B to Lung Cheung Road E/B (eastbound): widening of the slip road from one lane to two lanes, and alignment shift to the northeast direction (Road Section (d) in Appendix 4.17b); and
(e) An existing slip road from Lung Cheung Road E/B to Lion Rock Tunnel Road N/B: alignment shift to the northwest direction (Road Section (e) in Appendix 4.17b).
(a) A section of the existing Lion Rock Tunnel Road (from Lion Rock Tunnel Shatin portal to Fung Shing Court): widening from dual two lanes to dual three lanes and straightening except a section of the northbound carriageway between the slip roads to and from Hung Mui Kuk Road;
(b) An existing slip road from Hung Mui Kuk Road southbound to Lion Rock Tunnel Road southbound: minor shift of the northern road kerb;
(c) An existing slip road from Lion Rock Tunnel Road northbound to Hung Mui Kuk Road northbound: alignment shift towards the west; and
(d) An existing slip road from Hung Mui Kuk Road southbound to Lion Rock Tunnel Road northbound: alignment shift towards the north.
Operation Phase Fixed Noise Sources
Assessment Methodology - Airborne Construction Noise
· Identify all existing NSRs in the assessment area and select assessment points to represent identified NSRs which would most likely be affected by noise from the construction work;
· Identify and quantify an inventory of noise sources for representative construction equipment;
· Identify representative phases of construction that would have noticeable varying construction noise emissions at existing NSRs at the assessment area;
· Assign sound power levels (SWLs) to the proposed PME according to the GW-TM or other sources;
· Calculate distance attenuation based on the distance between NSR and the notional noise source position;
· Apply corrections in the calculations such as façade reflection, potential screening effects and acoustic reflection, if any;
· Predict construction noise levels at the selected assessment points in the absence of any mitigation measures at different phases of construction of the Project;
· Consider cumulative impact from concurrent projects within 300m of the NSRs, if any;
· Compare the cumulative construction noise level against the corresponding noise criterion and propose suitable mitigation measures where necessary; and
· Evaluate the residual construction noise impact in accordance with section 4.4.3 of the EIAO-TM and estimate the total number of existing dwellings, classrooms and other noise sensitive elements that will be exposed to residual noise impact exceeding the criteria set in Annex 5 in the EIAO-TM.
Assessment Methodology - Airborne Construction Noise During Restricted Hours
Assessment Methodology - Ground-borne Construction Noise
· Vibration source levels from operation of TBM and concerned PMEs (e.g. hydraulic breaker, drill rig and hand-held breaker);
· Vibration propagation through the ground to the structure foundation;
· Vibration reduction due to the soil/structure interface;
· Vibration propagation through the building and into occupied areas; and
· Conversion from floor and wall vibration to noise.
Cdist: Distance attenuation
Cdamping: Soil damping loss across the geological media
Cbuilding: Coupling loss into building foundation
Cfloor: Coupling loss per floor
Cnoise: Conversion factor from floor vibration levels to noise levels
Cmulti: Noise level increase due to multiple sources
Ccum: Cumulative effect due to neighbouring sites
Lp = Lv,rms + Cdist + Cdamping + Cbuilding + Cfloor + Cnoise + Cmulti + Ccum
Reference Vibration Sources
Table 4.11 Summary of Reference Vibration Level of PMEs
PME |
Reference Vibration Level, mm/s |
Remarks |
Drilling rig |
0.536 |
rms Vibration velocity level at reference distance of 5.5m |
Hydraulic breaker |
0.298 |
rms Vibration velocity level at reference distance of 5.5m |
Hand-held breaker |
0.279 |
rms Vibration velocity level at reference distance of 5.5m |
TBM |
2.5(a) |
PPV Vibration velocity level at reference distance of 5.5m |
Notes:
(a) Reference was made to the approved KSL EIA Report. The geology encountered during the KSL EIA study consists predominately of granite, which is similar to the geology expected to be encountered in the study area. The KSL source vibration measurements are therefore considered the most appropriate available information for the purpose of assessing TBM ground-borne noise.
Distance Attenuation (Cdist)
Cdist = 20 x log (R/R0), where
R = Separation between the tunnel boundary and the NSR;
R0 = Reference distance of the vibration measurement (i.e. 5.5m)
Soil damping Factor (Cdamping)
Coupling Loss into Building Foundation, (Cbuilding)
Table 4.12 Loss factor for coupling into building foundation
Frequency |
Octave Band Frequencies, Hz |
|||||
16 |
31.5 |
63 |
125 |
250 |
500 |
|
Loss factor for coupling into building foundation, dB |
-7 |
-7 |
-10 |
-13 |
-14 |
-14 |
Coupling Loss per Floor (Cfloor)
Conversion from Floor Vibration to Noise Levels (Cnoise)
Noise Level Increase due to Multiple Sources (Cmulti)
Cumulative Effect due to Neighbouring Sites (Ccum)
Conversion to A-weighted Noise
Prediction and Evaluation of Environmental Impacts
Unmitigated Airborne Construction Noise Impact (Non-Restricted Hours)
Table 4.13 Summary of Unmitigated Construction Noise Levels
NAP ID |
Description |
Daytime Noise Criterion, Leq (30mins), dB(A) |
Predicted Unmitigated Construction Noise Levels, Leq (30mins), dB(A) |
Max. Noise Exceedance, dB(A) |
||
Kowloon Side |
||||||
EH1 |
Eastland Heights |
75 |
63 - 85 |
10 |
||
MC1 |
Marple Court |
75 |
70 - 79 |
4 |
||
PH2 |
Peninsula Heights |
75 |
75 - 84 |
9 |
||
PHD1 |
Planned Housing Development (NKIL6579) |
75 |
73 - 86 |
11 |
||
Shatin Side |
||||||
WSH2 |
Wah Shing House, Fung Shing Court |
75 |
80 - 86 |
11 |
||
STTNV1 |
Village House, Sha Tin Tau New Village |
75 |
80 - 86 |
11 |
||
STTNV2 |
Village House, Sha Tin Tau New Village |
75 |
83 - 89 |
14 |
||
STTNV5 |
Village House, Sha Tin Tau New Village |
75 |
82 - 89 |
14 |
||
STW2 |
Shing Wai House, Sun Tin Wai Estate |
75 |
81 - 86 |
11 |
||
STW6 |
Yu Wai House, Sun Tin Wai Estate |
75 |
75 - 83 |
8 |
||
STGPS2 |
Sha Tin Government Primary School |
70 65 (during examination) |
74 - 82 |
12 (17 during Exam) |
||
KTV2 |
House 3, Kak Tin Village |
75 |
70 - 82 |
7 |
||
MWG1 |
Merry World Garden |
75 |
71 - 83 |
8 |
||
KTV5 |
House 36, Kak Tin Village |
75 |
63 - 90 |
15 |
||
HMKR1 |
Hung Mui Kuk Road Village Houses |
75 |
62 - 84 |
9 |
||
WWG5 |
Block 4, World-Wide Gardens |
75 |
74 - 84 |
9 |
||
WWG8 |
Block 3A, World-Wide Gardens |
75 |
66 - 91 |
16 |
||
JG4 |
Block 3. Julimount Garden |
75 |
63 - 87 |
12 |
||
HP1 |
House 1, Hill Paramount |
75 |
71 - 85 |
10 |
||
UC1 |
Union Court |
75 |
71 - 85 |
10 |
||
KSC1 |
Ka Shun Court |
75 |
66 - 81 |
6 |
||
KATC1 |
Ka Yin House, Ka Tin Court |
75 |
65 - 81 |
6 |
||
Remarks:
- Boldfaced values indicate exceedance to the respective noise criterion.
Unmitigated Airborne Construction Noise Impact (Restricted Hours)
Table 4.14 Summary of Unmitigated Construction Noise Levels during Restricted Hours
NAP ID |
Max. Predicted Unmitigated Construction Noise Levels, dB(A) |
Noise Criterion, dB(A) Night-time (2300-0700) |
Compliance |
Kowloon Side |
|||
EH1 |
70 |
50 |
No |
MC1 |
64 |
No |
|
PH2 |
62 |
No |
|
PHD1 |
80 |
No |
|
Shatin Side |
|||
WSH2 |
73 |
50 |
No |
STTNV1 |
75 |
No |
|
STTNV2 |
75 |
No |
|
STTNV5 |
73 |
No |
|
STW2 |
76 |
No |
|
STW6 |
71 |
No |
|
KTV2 |
71 |
No |
|
MWG1 |
63 |
No |
|
KTV5 |
70 |
No |
|
HMKR1 |
73 |
No |
|
WWG5 |
83 |
No |
|
WWG8 |
83 |
No |
|
JG4 |
74 |
No |
|
UC1 |
67 |
No |
|
HP1 |
73 |
No |
|
KSC1 |
64 |
No |
|
KATC1 |
61 |
No |
Remarks:
- Boldfaced values indicate exceedance to the respective noise criterion.
Notes:
(a) In this assessment, it was assumed that only one work location for demolition and erection of sign gantry will be active.
Unmitigated Ground-borne Construction Noise Impact during Non-Restricted Hours
Table 4.15 Summary of Unmitigated Construction Ground-borne Noise Levels during Non-Restricted Hours
NAP ID |
Predicted Unmitigated Ground-borne Construction Noise Levels, Leq (30mins), dB(A) |
Daytime Noise Criterion, Leq (30mins), dB(A) |
Compliance |
Construction of New Middle Third Tunnel |
|||
PHD1 |
58 |
65 |
Yes |
Enlargement of Existing Kowloon bound Tunnel |
|||
PHD1 |
49 |
65 |
Yes |
Rehabilitation of Existing Shatin Bound Tunnel |
|||
PHD1 |
53 |
65 |
Yes |
Unmitigated Ground-borne Construction Noise Impact during Restricted Hours
Table 4.16 Summary of Unmitigated Construction Ground-borne Noise Levels during Restricted Hours
NAP ID |
Predicted Unmitigated Construction Noise Levels, dB(A) |
Noise Criterion, dB(A) |
Compliance |
||
Evening (1900-2300) |
Night-time (2300-0700) |
Evening (1900-2300) |
Night-time (2300-0700) |
||
Construction of New Middle Third Tunnel |
|||||
PHD1 |
42 |
55 |
40 |
Yes |
No |
Enlargement of Existing Kowloon bound Tunnel |
|||||
PHD1 |
49 |
55 |
40 |
Yes |
No |
Rehabilitation of Existing Shatin Bound Tunnel |
|||||
PHD1 |
53 |
55 |
40 |
Yes |
No |
Mitigation Measures
· Good site practices to limit noise emissions at the sources;
· Use of quiet powered mechanical equipment;
· Use of movable noise barrier, noise enclosure, noise insulating fabric, silencer, etc. to screen noise from construction plant;
· Install acoustic tunnel door or enclosure at portals for construction activities to be carried out inside tunnel during restricted hours; and
· Use of purpose-built noise barrier or acoustic shed for road works during restricted hours; and
· Providing sufficient separation distance between NSRs and items of PME.
Good Site Practice
· Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction program;
· Silencers or mufflers on construction equipment should be utilised and should be properly maintained during the construction program;
· Mobile plant, if any, should be sited as far from NSRs as possible;
· Machines and plant (such as trucks) that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum; and
· Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs.
Quiet Powered Mechanical Equipment
Table 4.17 SWL of QPME adopted for Construction Noise Mitigation
QPME / Quiet PME |
QPME Reference Number |
Brand |
Model Number |
SWL, dB(A) |
Air Compressor |
EPD-09710 |
AIRMAN |
PDS185S-5C5 |
94 |
Roller, vibratory |
EPD-09720 |
SAKAI |
SW502S-1 |
94 |
Crane, mobile |
EPD-10792 |
KOBELCO |
CKS900 |
101 |
Loader, wheeled |
EPD-09366 |
Liebherr |
L524 |
100 |
Asphalt Paver |
EPD-01226R |
VOLVO |
ABG5770 |
104 |
Bulldozer, tracked |
EPD-07836 |
SHANTUI |
DH13K |
105 |
Generator |
EPD-03347 |
Denyo |
DCA-220ESM |
93 |
Hand-held Percussive Breaker |
EPD-09826 |
Hilti |
TE 2000-AVR |
100 |
Crane, mobile |
EPD-05797 |
Maeda |
CC985-1 |
91 |
Excavator, wheeled/tracked |
EPD-10780 |
KOMATSU |
PC138US-8 |
97 |
Use of Movable Noise Barrier, Purpose-built Barrier, Noise Insulating Fabric and Noise Enclosure
Install Acoustic Tunnel Door or Enclosure at the Kowloon Portal for Tunnelling Activities during Restricted Hours
Use of Purpose-built Noise Barrier or acoustic shed for Road Works during Restricted Hours
Providing Sufficient Separation between NSR and Construction Activities during Restricted Hours
Mitigated Construction Noise Levels during Non-Restricted Hours
Table 4.18 Summary of Mitigated Construction Noise Levels during Non-Restricted Hours
NAP ID |
Description |
Daytime Noise Criterion, Leq (30mins), dB(A) |
Predicted Mitigated Construction Noise Levels, Leq (30mins), dB(A) |
Max. Noise Exceedance, dB(A) |
Kowloon Side |
||||
EH1 |
Eastland Heights |
75 |
52 - 74 |
- |
MC1 |
Marple Court |
75 |
56 - 68 |
- |
PH2 |
Peninsula Heights |
75 |
61 - 72 |
- |
PHD1 |
Planned Housing Development (NKIL6579) |
75 |
62 - 75 |
- |
Shatin Side |
||||
WSH2 |
Wah Shing House, Fung Shing Court |
75 |
69 - 74 |
- |
STTNV1 |
Village House, Sha Tin Tau New Village |
75 |
69 - 74 |
- |
STTNV2 |
Village House, Sha Tin Tau New Village |
75 |
72 - 77 |
2 |
STTNV5 |
Village House, Sha Tin Tau New Village |
75 |
70 - 76 |
1 |
STW2 |
Shing Wai House, Sun Tin Wai Estate |
75 |
69 - 74 |
- |
STW6 |
Yu Wai House, Sun Tin Wai Estate |
75 |
65 - 71 |
- |
STGPS2
|
Sha Tin Government Primary School |
70 65 (during examination) |
63 - 70 |
- (5 during Exams) |
KTV2 |
House 3, Kak Tin Village |
75 |
58 - 69 |
- |
MWG1 |
Merry World Garden |
75 |
55 - 70 |
- |
KTV5 |
House 36, Kak Tin Village |
75 |
47 - 77 |
2 |
HMKR1 |
Hung Mui Kuk Road Village Houses |
75 |
46 - 72 |
- |
WWG5 |
Block 4, World-Wide Gardens |
75 |
60 - 72 |
- |
WWG8 |
Block 3A, World-Wide Gardens |
75 |
53 - 78 |
3 |
JG4 |
Block 3. Julimount Garden |
75 |
50 - 74 |
- |
HP1 |
House 1, Hill Paramount |
75 |
60 - 75 |
- |
UC1 |
Union Court |
75 |
56 - 75 |
- |
KSC1 |
Ka Shun Court |
75 |
51 - 71 |
- |
KATC1 |
Ka Yin House, Ka Tin Court |
75 |
56 - 72 |
- |
Further Noise Mitigation Measures for Non-Compliance NSRs – Sequencing Operation of Construction Activities at Critical Works Area and Reduction of number of PME
Table 4.19 Summary of Mitigated Construction Noise Levels after implementation of Further Noise Mitigation Measures
NAP ID |
Buffer Zone Size |
Further Mitigation Measures |
Daytime Noise Criterion, Leq (30mins), dB(A) |
Maximum Predicted Mitigated Construction Noise Levels, Leq (30mins), dB(A) |
Max. Noise Exceedance, dB(A) |
WWG8 |
50m |
· Only one type of construction activity is allowed to be carried out at the same time · Vibratory Compactor should reduce from 6 nos. to 4 nos. when “Road Surfacing” Works is carried out within the respective buffer zones |
75 |
75 |
- |
KTV5 |
40m |
· Only one type of construction activity is allowed to be carried out at the same time · Vibratory Compactor should reduce from 6 nos. to 4 nos. when “Road Surfacing” Works is carried out within the respective buffer zones |
75 |
75 |
- |
STTNV5 |
45m |
· Only one type of construction activity is allowed to be carried out at the same time |
75 |
75 |
- |
STTNV2 |
45m |
· Only one type of construction activity is allowed to be carried out at the same time |
75 |
75 |
- |
Cumulative Construction Noise Impact
Revised Trunk Road T4 in Sha Tin
In-situ Reprovisioning of Sha Tin Water Treatment Works - South Works - Designs and Construction
Relocation of Diamond Hill Fresh Water and Salt Water Service Reservoirs to Caverns
The Proposed Drainage Improvement Works at Chui Tin Street and Chui Tin Street Soccer Pitch
Mitigated Construction Noise Levels during Restricted Hours
Mitigated Construction Ground-borne Noise Levels during Restricted Hours
Evaluation of Residual Construction Noise Impacts
Identification of Project Roads Sections
Assessment Methodology
(a) With-Project unmitigated scenario at the assessment year with maximum traffic projection within 15 years upon operation of the Project, i.e. Year 2041
(b) With-Project mitigated scenario at Year 2041
(c) Prevailing scenario at Year 2024 (for indirect mitigated measures eligibility test)
(a) is not higher than the standard (stated in Section 4.2.11); and
(b) has no significant contribution to the overall noise from other existing roads, if the cumulative noise level, i.e. noise from the road project under the subject DP together with “Other roads”, exceeds the standard.
(a) The predicted overall noise level exceeds the noise standard in accordance with EIAO-TM (as stated in Section 4.2.11); and
(b) The predicted overall noise level is at least 1.0 dB(A) more than the prevailing traffic noise level, i.e. the total traffic noise level existing before the works to construct the road were commenced; and
(c) The contribution from the Project to the increase in the predicted overall noise level is at least 1.0 dB(A).
Prediction and Evaluation of Road Traffic Noise Impact (With-Project Unmitigated Scenario)
Table 4.20 Summary of Predicted Road Traffic Noise Levels under Unmitigated Scenario at Kowloon Side
NSR ID |
Criterion, L10 (1-hr) dB(A) |
Predicted Noise Level, L10 (1-hr) dB(A) |
Whether Noise Mitigation Measures on “Project Roads” are Required or Not |
|||
Overall |
“Project Roads” |
“Other Roads” |
Max. “Project Roads” Contribution when Overall Noise Level exceed Criteria |
|||
AC |
70 |
69 ~ 80 |
41 ~ 62 |
69 ~ 80 |
0.1 |
No |
EH |
70 |
74 ~ 79 |
46 ~ 63 |
74 ~ 79 |
0.1 |
No |
JC |
70 |
69 ~ 78 |
42 ~ 61 |
69 ~ 78 |
0.2 |
No |
KKC |
70 |
73 ~ 74 |
24 ~ 45 |
73 ~ 74 |
< 0.1 |
No |
LCC |
70 |
68 ~ 80 |
37 ~ 55 |
68 ~ 80 |
0.1 |
No |
LSTYKHSS |
65 |
76 ~ 76 |
16 ~ 16 |
76 ~ 76 |
< 0.1 |
No |
MC |
70 |
68 ~ 80 |
43 ~ 61 |
68 ~ 80 |
< 0.1 |
No |
MH |
70 |
83 ~ 86 |
39 ~ 44 |
83 ~ 86 |
< 0.1 |
No |
PH |
70 |
80 ~ 83 |
45 ~ 61 |
80 ~ 83 |
0.1 |
No |
PHD |
70 |
58 ~ 71 |
- |
58 ~ 71 |
< 0.1 |
No |
TMC |
70 |
78 ~ 82 |
- |
78 ~ 82 |
< 0.1 |
No |
TP |
70 |
71 ~ 75 |
43 ~ 54 |
71 ~ 75 |
0.1 |
No |
WG |
70 |
69 ~ 81 |
44 ~ 60 |
69 ~ 81 |
0.1 |
No |
WH |
70 |
69 ~ 79 |
42 ~ 61 |
69 ~ 79 |
0.1 |
No |
Remarks:
- Boldfaced values indicate exceedance to the respective noise criterion.
- Hyphenated indicate less than 10 dB(A) noise level.
- With reference to CRTN, noise levels should be rounded to nearest integer for comparison with the criterion.
Table 4.21 Summary of Predicted Road Traffic Noise Levels under Unmitigated Scenario at Shatin Side
NSR ID |
Criterion, L10 (1-hr) dB(A) |
Predicted Noise Level, L10 (1-hr) dB(A) |
Whether Noise Mitigation Measures on “Project Roads” are Required or Not |
|||
Overall |
“Project Roads” |
“Other Roads” |
Max. “Project Roads” Contribution when Overall Noise Level exceed Criteria |
|||
FSC |
70 |
66 ~ 78 |
65 ~ 76 |
60 ~ 76 |
8.5 |
Yes |
GLG |
70 |
73 ~ 79 |
58 ~ 68 |
71 ~ 79 |
2.1 |
Yes |
HLMSS |
65 |
52 ~ 56 |
52 ~ 56 |
20 ~ 20 |
- |
No |
HMKR |
70 |
64 ~ 65 |
55 ~ 56 |
63 ~ 64 |
- |
No |
HP |
70 |
60 ~ 74 |
57 ~ 74 |
47 ~ 59 |
17.2 |
Yes |
JG |
70 |
69 ~ 78 |
64 ~ 77 |
64 ~ 71 |
12.5 |
Yes |
KATC |
70 |
55 ~ 70 |
55 ~ 70 |
32 ~ 47 |
- |
No |
KSC |
70 |
52 ~ 69 |
52 ~ 69 |
24 ~ 25 |
- |
No |
KTC |
70 |
71 ~ 76 |
52 ~ 67 |
70 ~ 76 |
1.9 |
Yes |
KTV |
70 |
60 ~ 72 |
60 ~ 72 |
19 ~ 58 |
23.1 |
Yes |
KTVT1 |
65 |
63 ~ 63 |
62 ~ 62 |
51 ~ 51 |
- |
No |
KTVT2 |
65 |
62 ~ 62 |
62 ~ 62 |
41 ~ 41 |
- |
No |
MWG |
70 |
63 ~ 65 |
63 ~ 65 |
39 ~ 43 |
- |
No |
POHCKMC |
65 |
64 ~ 65 |
49 ~ 53 |
64 ~ 65 |
- |
No |
STGPS |
65 |
69 ~ 74 |
63 ~ 69 |
68 ~ 74 |
2.4 |
Yes |
STT |
70 |
62 ~ 71 |
54 ~ 64 |
62 ~ 70 |
0.9 |
No |
STTNV |
70 |
67 ~ 78 |
67 ~ 77 |
53 ~ 69 |
9.0 |
Yes |
STW |
70 |
71 ~ 78 |
67 ~ 78 |
62 ~ 68 |
15.2 |
Yes |
STWTWSQ |
70 |
53 ~ 54 |
53 ~ 54 |
15 ~ 15 |
- |
No |
UC |
70 |
59 ~ 72 |
59 ~ 72 |
35 ~ 56 |
17.8 |
Yes |
WWG |
70 |
71 ~ 83 |
62 ~ 83 |
58 ~ 72 |
23.3 |
Yes |
Remarks:
- Boldfaced values indicate exceedance to the respective noise criterion.
- Hyphenated indicate no exceedance for the NSR.
- With reference to CRTN, noise levels should be rounded to nearest integer for comparison with the criterion.
Consideration of Direct Mitigation Measures at Kowloon side
Recommended Direct Mitigation Measures at Shatin side
Table 4.22 Summary of Noise Mitigation Measures at Shatin Side
ID |
Noise Mitigation Measures |
Approximate Length (m) |
Nearest NSRs with their IDs to be Benefitted(1) |
S-C-01 |
7m tall + 3.5m at 90 degree cantilever barrier |
130 |
UC, HP and JG |
S-S-03 |
7.5m to 12m tall semi-enclosure |
410 |
UC, HP, JG and WWG |
S-C-02 |
7m tall + 3.5m at 90 degree cantilever barrier with absorptive material at the vertical panel (facing World Wide Garden) |
50 |
WWG |
S-S-01 |
7.5m to 12m tall semi-enclosure |
400 |
KTC, GLG, and WWG |
S-V-01 |
2m tall vertical barrier |
40 |
KTV |
S-S-02 |
7.5m to 12m tall semi-enclosure |
490 |
KTV, KTVT, STGPS, STW and FSC |
S-C-03 |
7m to 10m tall + 3.5m at 90 degree cantilever barrier |
60 |
FSC and STT |
S-V-02 |
6m tall vertical barrier |
70 |
STTNV |
S-V-03 |
6m tall vertical barrier |
60 |
STTNV |
Remarks:
(1) At least one dwelling or one classroom benefited, i.e. at least 1.0 dB(A) decrease in predicted overall noise level under mitigated scenario, compared with unmitigated scenario.
Consideration of Other Direct Mitigation Measures at Shatin side
Prediction and Evaluation of Road Traffic Noise Impact (With-Project Mitigated Scenario)
Table 4.23 Summary of With-Project Mitigated Road Traffic Noise Assessment Results at Assessment Year (Shatin Side)
NSR ID |
Criterion, L10 (1-hr) dB(A) |
Predicted Noise Level, L10 (1-hr) dB(A) |
Whether Further Noise Mitigation Measures on “Project Roads” are Required or Not |
|||
Overall |
“Project Roads” |
“Other Roads” |
Max. “Project Roads” Contribution when Overall Noise Level exceed Criteria |
|||
FSC |
70 |
56 ~ 75 |
45 ~ 59 |
55 ~ 75 |
0.2 |
No |
GLG |
70 |
71 ~ 79 |
50 ~ 63 |
70 ~ 79 |
0.7 |
No |
HLMSS |
65 |
52 ~ 56 |
52 ~ 56 |
20 ~ 20 |
- |
No |
HMKR |
70 |
64 ~ 64 |
51 ~ 52 |
63 ~ 64 |
- |
No |
HP |
70 |
56 ~ 70 |
51 ~ 70 |
47 ~ 59 |
- |
No |
JG |
70 |
66 ~ 71 |
50 ~ 69 |
64 ~ 71 |
0.1 |
No |
KATC |
70 |
54 ~ 70 |
54 ~ 70 |
32 ~ 47 |
- |
No |
KSC |
70 |
52 ~ 69 |
52 ~ 69 |
24 ~ 25 |
- |
No |
KTC |
70 |
71 ~ 76 |
45 ~ 61 |
70 ~ 76 |
0.5 |
No |
KTV |
70 |
59 ~ 70 |
57 ~ 70 |
19 ~ 58 |
- |
No |
KTVT1 |
65 |
62 ~ 62 |
61 ~ 61 |
51 ~ 51 |
- |
No |
KTVT2 |
65 |
61 ~ 61 |
61 ~ 61 |
41 ~ 41 |
- |
No |
MWG |
70 |
62 ~ 64 |
62 ~ 64 |
39 ~ 43 |
- |
No |
POHCKMC |
65 |
64 ~ 65 |
44 ~ 49 |
64 ~ 65 |
- |
No |
STGPS |
65 |
69 ~ 74 |
57 ~ 65 |
68 ~ 74 |
0.9 |
No |
STT |
70 |
61 ~ 69 |
35 ~ 43 |
61 ~ 69 |
- |
No |
STTNV |
70 |
62 ~ 70 |
61 ~ 70 |
51 ~ 67 |
- |
No |
STW |
70 |
59 ~ 68 |
47 ~ 65 |
58 ~ 68 |
- |
No |
STWTWSQ |
70 |
53 ~ 54 |
53 ~ 54 |
15 ~ 15 |
- |
No |
UC |
70 |
55 ~ 69 |
55 ~ 69 |
35 ~ 56 |
- |
No |
WWG |
70 |
50 ~ 72 |
45 ~ 64 |
48 ~ 72 |
0.9 |
No |
Remarks:
- Boldfaced values indicate exceedance to the respective noise criterion.
- Hyphenated indicate no exceedance for the NSR.
- With reference to CRTN, noise levels should be rounded to nearest integer for comparison with the criterion.
Noise Sensitive Receivers Exposed to Exceedance
Table 4.24 Estimated Number of Dwellings, Classrooms and Other NSRs Exposed to Exceedance
NSR Type |
Estimated Number of NSR |
||||
Kowloon Side |
Shatin Side |
||||
Prevailing Scenario in 2024 |
Unmitigated Scenario in 2041 |
Prevailing Scenario in 2024 |
Unmitigated Scenario in 2041 |
Mitigated Scenario in 2041 |
|
Dwellings |
544 |
546 |
1,754 |
1,701 |
462 |
Classroom |
24 |
24 |
40 |
40 |
40 |
Place of Public Worship |
- |
- |
1 |
0 |
0 |
NSRs Benefited from and Protected by the Proposed Direct Mitigation Measures
Table 4.25 Estimated Number of Dwellings, Classrooms and Other NSRs Benefited from and Protected by Provision of Direct Noise Mitigation Measures
NSR Type |
Estimated Number of NSR in Shatin Side |
|
Benefited |
Protected |
|
Dwellings |
1,510 |
1,239 |
Classroom |
16 |
0 |
Place of Public Worship |
1 |
0 |
Total |
1,527 |
1,239 |
Remarks:
- “Benefited” indicates a reduction of at least 1.0 dB(A) predicted overall noise level at the NSR due to the provision of direct noise mitigation measures.
- “Protected” indicates the predicted overall noise level at the NSR reduced from exceedance to compliance to the respective criterion due to the provision of direct noise mitigation measures.
Tunnel Portal Noise Impact
Evaluation of Residual Road Traffic Noise Impacts
Assessment Methodology – Fixed Noise
SPL = SWL – DC + FC + TC
Where:
SPL = Sound Pressure Level at NSR, in dB(A)
SWL = Sound Power Level of the PME, in dB(A)
DC = Distance Attenuation, in dB(A) (i.e. 20logD + 8 [where D is the distance in metres])
FC = Façade Correction, in dB(A) (i.e. 3 dB(A))
TC = Tonality Correction, in dB(A) (i.e. 6 dB(A))
Prediction and Evaluation of Fixed Noise Impact
Evaluation of Residual Fixed Noise Sources Impacts
Construction Noise
Operation Phase Road Traffic Noise
Operation Phase Fixed Noise
Construction Noise
Road Traffic Noise
Fixed Noise
[1] https://www.transit.dot.gov/sites/fta.dot.gov/files/docs/FTA_Noise_and_Vibration_Manual.pdf
[2] https://www.epd.gov.hk/epd/misc/construction_noise/contents/index.php/en/road-works/item/74-mitigation-measures/157-construction-noise-barrier.html
[3] https://www.epd.gov.hk/epd/misc/construction_noise/contents/index.php/en/road-works/item/74-mitigation-measures/157-construction-noise-barrier.html