2
PROJECT DESCRIPTION
2.1
Purposes,
Project Objectives and Environmental Benefit of the
Project
2.1.1 The objective of the Project
is to rehabilitate and improve the existing tunnel tubes of the Lion Rock
Tunnel (LRT) and to take this opportunity to enhance the capacity of the tunnel
and the connecting roads as far as possible, with a view to extending the
service life of the LRT and help alleviating the traffic congestion at the LRT
during peak hours and the traffic impact during maintenance.
2.1.2 Smoother traffic flows
enhanced by the proposed improvement works would alleviate the air quality and
noise impacts associated with traffic congestion during peak hours.
Although the noise sources at certain locations may be nearer to local
sensitive receivers due to the road widening works, noise mitigation measures
such as noise barriers and noise enclosures will be constructed under the
Project. These works could also help reduce the existing noise impact on
the adjacent sensitive receivers such as residential uses, hospital, etc.
Detailed noise assessments, the extent and locations of the noise mitigation
measures proposed and their envisaged improvements to noise impacts are
outlined in Section
4.
2.2
The
Need for the Project
Site
Location and Site History
2.2.1
The LRT is a trunk road linking traffic between Shatin and
Kowloon. It consists of two tunnel tubes each with two traffic lanes.
2.2.2 Between 1962 and 1967, the 1st
LRT (Kowloon bound) was constructed in association with the construction of
Kowloon Portal and Sha Tin Portal. Lion Rock Tunnel Road and a series of
slope feature were formed. Waterloo Road extended northward, widened and connected to Lung Cheung Road at north before
1967. The area, where was to the north of Lion Rock Tunnel Road at Sha
Tin, was still dominated by farmland in 1967.
2.2.3 In 1973, the 2nd
LRT (Shatin bound), which was situated to the west of and parallel to the first
tunnel, was under construction in association with the construction of another
Kowloon and Sha Tin Portals to accommodate the residential development along
Lion Rock Tunnel Road at Sha Tin.
2.2.4 Since the early 1970s, more
abandoned farmlands, which were situated at the flatland at Sha Tin, had become
utilized by residential buildings and cottages. Reclamation along Shing
Mun River and quarrying activities at Shui Cheun O had started before 1978.
A circular loop of Hung Mui Kuk Road near World-wide Garden was
constructed and connected to Lion Rock Tunnel Road at the north before 1980.
2.2.5 Between 1980 and 1983, Sha
Tin Road was constructed and connected to Lion Rock Tunnel Road at the east in
association with the formation of a series of slope features.
Scenario
without the Project
2.2.6 The Kowloon bound and Shatin
bound tunnel tubes have been put in use for over 50 years and 40 years
respectively. Signs of deterioration of tunnel structures have become
apparent. Due to heavy traffic demand, the time slots of only a few hours
during night time for tunnel closure cannot allow
comprehensive repair and strengthening works to be undertaken.
2.2.7 Being an old design, the LRT
does not meet the current standards in various aspects including waterproofing,
dimensions (e.g. headroom and width), smoke
extraction, evacuation, durability, Traffic Control and Surveillance System
(TCSS), etc.
2.2.8 As LRT and LRT Road are
already operating close to or above capacity, they could not cope with the
ever-growing traffic demand. This has led to long traffic queues to
appear along the connecting roads including the LRT Road at Shatin side, as
well as the Lung Cheung Road and Waterloo Road at Kowloon side. The
ever-growing congested traffic and long traffic queues have the potential to
worsen the air quality and noise impacts to the sensitive receivers along these
connecting road links. Furthermore, some of the LRT traffic may also
choose an alternative route and use other tunnels and roads to travel between
Kowloon and Shatin instead when there is serious congestion at LRT and LRT
Road. Many of these existing road links in urban Kowloon and Shatin are
already operating close to or above capacity. Increase in traffic along these
road links will worsen the traffic conditions and in turn also worsen the noise
and air quality impacts in Kowloon and Shatin.
Scenario
with the Project
2.2.9 Comprehensive rehabilitation
of the two existing tunnel tubes can bring LRT
up to current standard and extend its serviceable years; thereby enhancing the
tunnel environment and road safety level. Enhancing the capacity of the
LRT and the connecting roads as far as possible is also necessary to improve
the traffic flow at this critical link between Shatin and Kowloon.
2.2.10 The Project comprises of
construction of a new middle tunnel, rehabilitating the existing Shatin bound
Lion Rock Tunnel tubes and enlargement of existing Kowloon bound Lion Rock
Tunnel tubes. The traffic conditions within the LRT, after the implementation
of the proposed improvement works, could also be enhanced, alleviating congestions and improving the traffic conditions to
acceptable levels. From an environmental perspective, this could lead to
smoother traffic flows which in turn could decrease the noise and air quality
impacts.
2.2.11 Furthermore, road widening
works are also proposed along the Lion Rock Tunnel Road which could also
enhance the traffic conditions, thereby leading to smoother traffic flows and
potential reduction in congestion, journey times and queue lengths at the
Shatin side. At Kowloon side, the Project will provide an additional traffic
lane in the form of a separate, one-lane vehicular bridge across Lung Cheung
Road along Lion Rock Tunnel Road northbound. This will allow direct entry into
Lion Rock Tunnel Road (northbound) for traffic from Lung Cheung Road
(westbound), thereby significantly reducing the existing congestion and
vehicular queue length along the nearside lane of Lung Cheung Road (westbound)
and Waterloo Road (northbound).
2.2.12 Aside from reducing the noise
and air quality impacts through smoother traffic movements, reduced travelling
times and queue lengths, the Project also provides direct noise mitigation measures
such as noise barriers to alleviate noise impact on nearby sensitive receivers
along LRT Road. Existing traffic noise impacts on the nearby sensitive
receivers such as those along LRT Road could be alleviated as much as possible.
Detailed noise assessments, the extent and locations of the noise mitigation
measures proposed and their envisaged improvements to noise impacts are
outlined in Section
4.
2.2.13 Nevertheless, the Project
will induce environmental impacts during construction such as construction
noise, dusts, site runoff etc. It is envisaged that with the implementation of
quieter Powered Mechanical Equipment (PME) and good site practices, the
construction environmental impacts could be limited to acceptable levels. It
should also be noted that while the works under the Project are designed to
avoid encroachment on the Lion Rock Country Park (LRCP) and natural habitats as
far as possible, encroaching into the LRCP is inevitable near the existing
tunnel toll plaza and along Lion Rock Tunnel Road near Hung Mui Kuk
Interchange. The impact to the LRCP has been assessed and detailed mitigation
measures proposed are outlined in Section 8.
2.2.14 A summary of the environmental
benefits and disbenefits with and without the Project is provided in Table
2.1 below.
Table
2.1 Summary of Environmental Benefits and
Disbenefits With and Without the Project
Scenarios
|
Environmental Benefits
|
Environmental Disbenefits
|
With Project
|
·
Provides direct noise mitigation measures such as
noise barriers to alleviate noise impact on nearby sensitive receivers along
LRT Road.
·
Provides additional traffic capacities to the Lion
Rock Tunnel and Lion Rock Tunnel Road, thereby relieving congestion and
decrease the impacts to air quality and noise sensitive receivers subject to
the locations.
·
Opportunity to improve the environmental performance
(e.g. greening, aesthetics) of the tunnel
ventilation and administration buildings.
|
·
Encroachment into the LRCP and woodland, and tree
felling (woodland and tree compensation will be implemented)
·
Large amounts of Construction and Demolition
(C&D) materials will be generated due to tunnelling and site formation
works (potential for re-use on-site and at other projects)
·
Construction phase environmental impacts such as
construction noise, dust, site runoff etc. (implement good site practices)
|
Without Project
|
·
No impacts to LRCP and woodland, and no tree
felling.
·
No wastes generated.
·
No construction phase environmental impacts to
sensitive receiver (e.g. construction noise, dust,
site runoff etc.)
|
·
Many of the existing major road links are already
operating close to or above their capacity. Congestion is expected to occur
more frequently not only at Lion Rock tunnel and Lion Rock Tunnel Road but
also to large areas in Kowloon and Sha Tin, therefore, long term impacts to
sensitive receivers would be worsen.
|
2.3
Location
and Scope of the Project
2.3.1 The location and scope of the
Project is shown in 60604728/R42b/Figure 2.2 to 60604728/R42b/Figure 2.5.
The EIA study covers the LRT, Lion Rock Tunnel Road (both Kowloon and Sha Tin
sides), a section of Hung Mui Kuk Road near World-wide Garden, a short section
of Waterloo Road adjoining Lion Rock Tunnel Road, and a short section of minor
road works along Lung Cheung Road (E/B).
2.3.2 The scope of the Project
comprises the construction of the new tunnel tube to facilitate the subsequent
rehabilitation of two existing tunnel tubes, widening of the connecting roads
and the associated works. The details are as follows:-
(a) Construction of a
three-lane road tunnel of approximately 1.4 km long between the two existing
tunnel tubes of the LRT;
(b) Enlargement of the
existing Kowloon bound tunnel tube to a three-lane road tunnel, together with
the construction of cross passages linking the enlarged Kowloon bound tunnel
tube with the new middle tunnel;
(c) Carry out refurbishment
works on the existing Shatin bound tunnel tube and replacement/rehabilitation
of the existing fire services provisions;
(d) Provision of equipment
including TCSS for operation of the tunnels;
(e) Demolish the existing
toll plaza together and provision of equipment and facilities for free-flow tolling;
(f) Re-provision of
tunnel buildings including tunnel administration building (ADB), ventilation
buildings (VBs) etc., construction of a vehicular crossover bridge to support
tunnel operations, and construction of footbridges and any other tunnel support
facilities;
(g) Widening of LRT Road at
Kowloon side to dual three-lane from the slip roads of Lung Cheung Road
interchange to LRT Kowloon portal and construct a single lane vehicular bridge
crossing over Lung Cheung Road for the Shatin bound direction;
(h) Widening of the slip
road from Lion Rock Tunnel Road (S/B) to Lung Cheung Road (E/B) to two lanes,
and realigning the slip road from Lung Cheung Road (E/B) to Lion Rock Tunnel
Road (N/B);
(i) Widening of LRT Road at Shatin side to dual three-lane between the
existing tunnel portal to Fung Shing Court (except a section of the northbound
carriageway between the slip roads to and from Hung Mui Kuk Road which would
remain two lanes);
(j) Reprovisioning
of Footbridge NF74 near Fung Shing Court;
(k) Provision of noise
barriers / enclosures to mitigate the road traffic noise impact on noise
sensitive receivers; and
(l) Ancillary works
including slope works, water mains diversion, road lighting, drainage,
landscaping works, etc.
2.4
Design
Changes to the Project
2.4.1 Subsequent to the issue of
the EIA Study Brief (No. ESB-323/2019) in November 2019, some changes were made
to the project boundary, layout and design to
facilitate the project development and latest traffic needs. The project layout
submitted under the Project Profile (No. PP-589/2019) is attached in 60604728/R42b/Figure 2.6 to 60604728/R42b/Figure 2.9.
In accordance with Clause 6.2 of the EIA Study Brief, it was checked if there
was any key change in the scope of the Project mentioned in Section 1.2
of the EIA Study Brief and in Project Profile (No. PP-589/2019), confirmations
would have to be sought from the Director of Environmental Protection in
writing on whether or not the scope of issues covered by the EIA Study Brief
can still cover the key changes, and the additional issues, if any, that the
EIA report must also address. It is confirmed by EPD on 28 June 2021 that the
proposed changes to the project would not fundamentally alter the key scope of
issues covered by the EIA Study Brief (No. ESB-323/2019). The EIA Study Brief
is still valid for the preparation of the EIA Report. The reply from EPD is
presented in Appendix 2.1.
2.5
Consideration
of Alternative Options
2.5.1 Assessments have been carried
out to ensure that the Project will yield the most environmental benefits. 60604728/R42b/Figure
2.11 outlines the site constraints in the vicinity of the
Project. Major aspects of the Project reviewed include the following:
·
Need for a new tunnel;
·
Alignment of the tunnel;
·
Tunnel ancillary facilities;
·
Alignment of the road widening;
Need
for a New Tunnel
2.5.2 The need for a new third
tunnel was explored. To ensure safety to the tunnel users, the one-tube-two-way
traffic arrangement (i.e. similar to the existing
arrangement during routine tunnel maintenance after midnight) will have to be
implemented full-time while one of the existing tunnel tubes is undergoing
enlargement. However, this will reduce the traffic capacity of the LRT. Given
that the LRT is one of the most heavily used road tunnels in Hong Kong, this
will cause traffic impacts at both ends of the tunnel. Traffic queues and
congestions are expected along the tunnel connecting roads (e.g.
Lion Rock Tunnel Road, Waterloo Road, Lung Cheung Road etc.) which in turn will
lead to increased air quality impacts and noise impacts. Hence a new third
tunnel is needed to facilitate uninterrupted traffic during construction.
Consideration has also been given for an adoption of tunnelling works instead
of traditional open-cut method for the provision of additional carriageways so as to avoid direct impacts on aboveground habitats within
LRCP.
New
Tunnel Alignment
2.5.3 There are three alignment
options for the new tunnel, namely West Option, East Option and Middle Option,
which will be detailed in the following sections. Extensive environmental
considerations have been taken into account during the
evaluation of options in order to minimize environmental impacts and maximize
environmental benefits as far as possible.
New
Tunnel at West of the existing LRT Northbound Tunnel (West Option)
2.5.4 For the tunnel alignment
option west to the existing LRT, it should also be noted that local constraints
at the existing Kowloon portal such as the WSD service reservoirs, the new
residential development at Lot No. NKIL 6579 etc. meant that the new tunnel
portal at Kowloon side could only be situated at the site adjacent to the
residential development of Vista Panorama along Waterloo Road northbound. In
addition to the proximity of the new tunnel portal to Vista Panorama, the
tunnel would also be 200m longer than the middle option, which means that it
would be substantially more expensive and that approximately 15% more tunnel
excavation materials will be generated and reused as far as possible before
disposal. In addition, more construction vehicles will be needed to transport
these additional wastes away which in turn will also increase the impacts to
air quality and noise sensitive receivers.
2.5.5 This option would also
require the construction of a deep TBM retrieval shaft at the natural hillside
near the existing Kowloon portal. Though not within the boundary of the LRCP,
the shaft will result in substantial reduction of wooded area and substantial
tree felling. It should also be noted that the west tunnel alignment option
would be constructed along a potential fault line as inferred from published
geological maps. Adverse ground conditions may be encountered during tunneling,
potentially leading to excess groundwater ingress and ultimately drawdown of
the existing groundwater table along the tunnel alignment. This could have
significant impacts to the flora and fauna within LRCP and the Beacon Hill Site
of Special Scientific Interest (SSSI). As such, extensive ground treatment
works will be required giving rise to significant increase in construction
costs and programme.
2.5.6 Besides, traffic to and from
Lung Cheung Road will require large detour resulting much longer travelling
time. The longer distance travelled and the traffic congestion due to the
additional traffic diverted from Lung Cheung Road to the local roads may result
in potential air quality and noise impacts on nearby sensitive receivers.
2.5.7 Furthermore, construction of
a new private residential development is currently underway within land lot
NKIL Lot 6579 (i.e. southwest of the existing Lion
Rock High Level No. 2 Primary Service Reservoir) near the Kowloon Portal.
Connecting roads linking along LRT Road will hence be very close to the new
development and may cause potential air quality and noise impacts on future
residents/stakeholders etc. during construction and operation stages.
Nevertheless, the northbound traffic will enter the new tunnel earlier which
will significantly reduce the traffic (and hence noise and air quality impacts)
between Vista Panorama and the LRT. Tunnel alignment of the West Option is
presented in 60604728/R42b/Figure 2.12.
New
Tunnel at East of the existing LRT Southbound Tunnel (East Option)
2.5.8 For the tunnel alignment
option east to the existing LRT, the situation is similar to
the west in that the portal is also spatially constrained by the WSD service
reservoirs at the Kowloon portal, and by the CLP pylons and overhead
transmission lines (OHL) at the Shatin side.
2.5.9 As for aligning the third
road tunnel to the east of the existing LRT southbound tunnel tube, extensive
site formation works (approximately 9,000m² plan area) will have to be carried
out at the Shatin Portal, which falls within the LRCP. Any direct encroachment
upon LRCP should be avoided to the maximum practicable extent and alternative
alignments should be explored. The tunnel would also be longer than the Middle
Option, which means that it would be substantially more expensive and that
approximately more tunnel excavated materials will be generated and requiring
disposal if the material could not be reused. More construction vehicles will
also be needed to transport these additional wastes away which in turn will
also increase the impacts to air quality and noise sensitive receivers.
2.5.10 It is also expected that the
extent of site formation works will clash with the existing CLP pylons. It is
unlikely to relocate the CLP pylon and overhead transmission lines. Tunnel
alignment of the East Option is presented in 60604728/R42b/Figure
2.13.
New
Tunnel in between of the existing LRT Tunnels (Middle Option)
2.5.11 The alignment of the new
tunnel is ultimately proposed to be in between of the existing LRT tubes.
This alignment is chosen as it will not spatially conflict with existing
facilities such as the WSD service reservoirs, CLP pylons and residential
developments. This middle tunnel alignment is also shorter than the west
and east options (approximately 1400m only), thereby being the most cost
effective and will produce the least amount of excavated materials.
2.5.12 This middle alignment is also
further away from the inferred fault west of the existing LRT, hence the risk
of excessive groundwater drawdown (and therefore the potential adverse impacts
to the habitats of the LRCP and Beacon Hill SSSI) is much smaller than the west
alignment option. The middle alignment will also require the least site
formation works at the portal areas and therefore envisaged to have
significantly less tree felling and disturbance to the natural hillside than
the east and west option. Unlike the east option, no excavation within
LRCP is envisaged due to the middle tunnel alignment. Hence, adverse ecological
impacts on LRCP would be comparatively smaller for Middle Option. Also, the
hillside vegetation at the LRCP and Tei Lung Hau are valuable visual and landscape resources of the
Project. Unlike the West and East Options, the Middle Option will only
encroach a very small area of vegetation within the LRCP. In addition,
the Middle Option is located between the existing tunnels where the affected
portal areas are mostly disturbed slopes with plantation. The extent of
excavation for the Middle Tunnel is much smaller than the West and East
Options. Hence it is considered that the Middle Option will have the least
visual and landscape impact. Tunnel alignment of the Middle Option is
presented in 60604728/R42b/Figure 2.4
and 60604728/R42b/Figure 2.5.
2.5.13 Comparison of the
environmental benefits and disbenefits of the various tunnel alignment studied
is presented in Table 2.2 below.
Table
2.2 Comparison of Environmental Benefits
and Disbenefits of various Tunnel Alignment Options
Option
|
Environmental Benefits
|
Environmental Disbenefits
|
West of the existing Lion Rock Tunnels
(West Option)
|
·
Impacts to air quality and noise on sensitive
receivers between Vista Panorama and the LRT envisaged to be lower relative
to the Middle Option.
|
·
The portal at Kowloon will have to be at the
existing plantation area along Waterloo Road directly adjacent to Vista Panorama
(increased potential air quality, noise and landscape and visual impacts).
·
Major traffic detours at Kowloon side necessary
during construction phase leading to increased traffic, congestion,
travelling time and hence increased impacts to air quality and noise
sensitive receivers.
·
Longer tunnel necessary relative to the middle
option, hence more excavated materials generated and construction vehicles
for material transportation needed. Hence potentially increase air quality
and noise impacts.
·
Tunnel runs directly under the Beacon Hill SSSI, and also runs parallel to an existing fault line.
Potential water drawdown during construction thereby lowering the groundwater
table and affecting the LRCP and Beacon Hill SSSI.
·
More direct loss of natural habitats as compare with
Middle Option, and hence potential adverse ecological
impacts.
|
In between of the existing Lion Rock Tunnels
(Middle Option)
(Preferred Option)
|
·
Shortest tunnel alignment, therefore least C&D
wastes generated. Shortest construction time and least number of construction
vehicles envisaged.
·
Least visual and landscape impacts as area between
tunnels considered disturbed terrain.
·
No major traffic detours expected during
construction.
·
No blocking of views / visual impacts to residential
developments along Waterloo Road.
·
Less direct loss of natural habitats as compare with
East and West Options, and hence smaller adverse ecological impacts.
|
|
East of the existing Lion Rock Tunnels
(East Option)
|
|
·
Extensive surface excavation necessary within LRCP
at Shatin side for the new tunnel portal. Extensive tree felling.
·
Major traffic detours at Kowloon side necessary
during construction phase leading to increased traffic, congestion,
travelling time and hence increased impacts to air quality and noise
sensitive receivers.
·
Longer tunnel necessary relative to the middle
option, hence more wastes generated and construction
vehicles needed for material transportation. Hence potentially increase air
quality and noise impacts.
·
More direct loss of natural habitats as compare with
Middle Option, and hence potential adverse ecological impacts.
|
Tunnel
Ancillary Facilities
2.5.14 According to TD’s planning,
it is envisaged that Free-Flow Tolling System (FFTS) will be implemented at the
Lion Rock Tunnel before the construction commencement of the Project in Q1
2025. As such, portion of the existing toll plaza could be decommissioned right
away, with the area at existing toll booths 11 to 13 and the associated roads
before and after these toll booths (i.e. south of the
existing toll plaza) to be readily freed up for other usages.
Need
for Cross-over Bridge
2.5.15 It should be noted that the
tunnel operator will have to comply with strict rescue and recovery operational
requirements. During emergency situations, the requirement on the response time
of tunnel staff to reach the site of any broken-down vehicles and/or traffic
accidents within the tunnel administration area (including the tunnel tubes) is
two minutes. Depending on the vehicle type, the broken-down vehicle and any
debris will have to be cleared and the traffic lane has to
be reopened within 5 to 12 minutes of arrival of the recovery vehicle. The
existing crossover facility is located adjacent to the existing ADB near the
Shatin Portal. However, it will be demolished together with the ADB as both are
in the way of the future traffic from the new middle tunnel. As such, a
vehicular crossover bridge adjacent to the reprovisioned ADB is proposed to
avoid large detours and also to meet the stringent
response time and clearance time requirements during emergencies.
Need
for the car park and crossover bridge to be near the Tunnel Administration
Building
2.5.16 The car park is envisaged to
accommodate 60 nos. of vehicles in total (which include private vehicles, Light
Recovery Vehicles (LRV), Heavy Recovery Vehicles (HRV), motorcycles etc.), and
is expected to be at about 4,650m² on plan in accordance with the design
requirement. As advised by the tunnel operator, the driver of the rescue and
recovery vehicles will be stationed in the ADB. Hence it is imperative for the
car park to be located in close proximity of the ADB
in order to meet the stringent response and clearance time requirements. The
vehicular cross-over bridge should also be close to the car park to avoid large
detours and longer travelling times which in turn increases the response time
of the rescue and recovery vehicles during emergencies.
Recommended
Location of Reprovisioned Tunnel Administration Building and Car Park
2.5.17 As mentioned in Section
2.5.2, due to heavy usage at the existing Lion Rock Tunnel, it will be
necessary to construct a new, third tunnel between the existing tubes, and then
divert the existing traffic to this new middle tunnel before improvement works
to the existing tunnel tubes could commence. As the existing administration
building (ADB) is currently located at the area between the northbound and
southbound lanes near the Shatin Portal, it will be in the way of the future
tunnel traffic and hence will have to be decanted and demolished prior to
commissioning of the new middle tunnel. The area south of the existing toll
plaza (i.e. freed up due to the implementation of
FFTS) provides an ideal location for the reprovisioned ADB. The area provides
an unobstructed view of the Lion Rock Tunnel Road at Shatin side, and as the
area is flat and on paved (previously carriageway) area unlike other areas near
the Shatin Portal, no site formation works is necessary
and no potential loss of woodland and natural habitats is envisaged.
Furthermore, construction of the ADB could begin immediately after commencement
of construction, thereby minimizing the construction time of the Project.
2.5.18 Considerations were also
previously given to locate the reprovisioned ADB at the Kowloon Portal.
However, the available space at Kowloon Portal is very limited as it is heavily
constrained by three existing services reservoirs (namely the Lion Rock High
Level No. 1 Primary Service Reservoir, Lion Rock High Level No. 2 Primary
Service Reservoir and Lion Rock Low Level Primary Service Reservoir) and the
residential development at Land Lot No. NKIL6579.
2.5.19 The car park and part of the
crossover bridge is proposed to be located southwest of the reprovisioned ADB.
The area is a relatively flat area compared with the topographies of the
alternative locations explored, which has fewer construction constraints and
potential hazards. Another advantage is the filling/excavation works required
are comparatively minimal for the formation of the platform of the proposed car
park when compared to other alternative locations as mentioned below.
Nevertheless, avoidance of LRCP was explored. Although the proposed
car park will be located within the developed area and an engineered slope
within LRCP, direct impacts on woodland within LRCP is avoided and the number
of affected trees is negligible as compared with other alternative locations.
Alternative
Location of the Car Park
2.5.20 The following alternative
locations near Shatin Portal were explored for the proposed car park and
compared with the current adopted location. Please refer to 60604728/R42b/Figure
2.14 for locations of the alternatives considered as follows:-
·
Location 1: Feature No. 7SW-D/FR33 (i.e.
north of the existing toll plaza);
·
Location 2: Feature No. 7SW-D/C47 and 7SW-D/F430 (near
Tei Lung Hau);
·
Location 3: Feature No. 7SW-D/C97 (east of the
existing Kowloon bound tunnel); and
·
Location 4: Agricultural land adjacent to the Sha Tin
South Fresh Water Service Reservoir
Location
1: At Feature No. 7SW-D/FR33
2.5.21 This alternative location is
situated north of the existing toll plaza. It is on the other side of the Lion
Rock Tunnel Road opposite of the reprovisioned ADB. Feature No. 7SW-D/FR33 is a
rock fill slope at a gradient of about 33°, which is much steeper than the
recommended location of the car park. If the car park is to be located at this
area, the walking distance by the response staff from the reprovisioned ADB
will be longer than the recommended location, and will
overall take a longer response time to reach the incident site during
emergencies. This is not desirable from an operational and traffic point of
view.
2.5.22 In addition, extensive
filling works which will encroach upon the existing woodland downslope of
7SW-D/FR33 will be required. In general, the maturity and species composition
of woodlands at Tei Lung Hau
are similar to the potentially affected woodland
within LRCP as stated above. The woodland near 7SW-D/FR33 is also a
mature woodland which also dominated by native common species. It is estimated
that about 0.71ha of woodland (in addition to 1.08 ha of plantation) will be
permanently lost for this option. Given the sloping terrain of 7SW-D/FR33,
there will also be additional safety risks. Falling objects from the site may
roll down to Ka Tin Court downslope, and workers will have to work at a much
higher height and on much steeper terrain than the recommended location. As for
environmental, Ka Tin Court and Union Hospital will be subjected to prolonged
construction activities in their vicinity, and therefore more adverse air
quality and noise impacts. There is also the risk of harmful materials leaking
into the natural watercourse downslope at the northeast of 7SW-D/FR33 which in
turn affects the water quality and ultimately ecology. Notwithstanding the
above, the construction cost and time need for this alternative location will
also be higher than the recommended location.
Location
2: At Feature No. 7SW-D/C47 and 7SW-D/F430
2.5.23 This alternative location is
situated at Tei Lung Hau
which is to the east across the LRT Road. It is a knoll with elevation spanning
from 92mPD to 116mPD. Gradient of 7SW-D/C47 is at about 56°. The walking
distance from the reprovisioned ADB will be about 280m, which will
significantly prolong the response time of rescue and recovery vehicles
reaching the incident site during emergencies. Furthermore, due to the
topography at Tei Lung Hau,
if the car park is to be located at this area, extensive excavation will have
to be carried out which will involve the near complete removal of the knoll.
This will lead to a permanent woodland loss of approximately 0.62 ha, with also
a plantation loss of about 0.10ha. This potentially impacted mature woodland
has a closed canopy and dominated by common native tree species. Furthermore,
both 7SW-D/C47 and 7SW-D/F430 are steep slopes located directly adjacent to the
busy roadway. It will pose a higher safety risks to
the road users than the recommended location. There is also the risk of harmful
materials leaking/falling into the natural/modified watercourses downslope at
the east of 7SW-D/C47 which in turn affects the water quality and ultimately
ecology. Notwithstanding the above, the construction cost and time need for
this alternative location will also be higher than the recommended
location.
Location
3: At Feature No. 7SW-D/C97
2.5.24 This alternative location is
situated east of the existing approach road to the Kowloon bound tunnel at the
Shatin Portal. Similar to other alternative locations,
the car park is situated further away than the recommended location, and hence
will have a longer response time for rescue and recovery vehicles to reach the
incident site during emergencies. Furthermore, this alternative location lies
within the LRCP. If the car park has to be located in
this area, extensive excavation works leading to a permanent woodland and
plantation loss of 0.47ha and 0.25ha respectively including those within LRCP
will have to be carried out. This potentially impacted woodland within LRCP is
a mature woodland. A closed canopy was observed and dominated species
within this woodland are common native species in Hong Kong. Furthermore,
the extent of excavation works is envisaged to encroach the footprint of the
existing CLP cable pylon which could in turn reduce the stability of the cable
tower which is highly undesirable. Feature No. 7SW-D/C97 is an existing 42°
soil cut slope. This will pose higher safety risks to both road users and
workers than the recommended location. If the car park has to
be located in this area, the excavation works will have to be carried out
directly adjacent to the existing busy roadway. There is also an engineering
concern with a view to meeting stringent requirement dictated by Technical
Circular for carrying out such an extensive site formation works above
underground railway structures, namely, from Diamond Hill Station to Hin Keng Station along Tuen Ma Line. Notwithstanding the above, the
construction cost and time need for this alternative location will also be
higher than the recommended location.
Location
4: Agricultural land adjacent to the Sha Tin South Fresh Water Service
Reservoir (STSFWSR)
2.5.25 Considerations were also
given to locate the proposed car park at the existing agricultural land and
woodland area east of the STSFWSR. Although this area is mostly flat, it is
more than 640m away from reprovisioned ADB. The separation of the car park and
ADB is considered too large, and the response time for rescue and recovery
vehicles to arrive at the scene of incident will be significantly delayed. It
is highly undesirable from an operational viewpoint. There is currently
vehicular access south, west and north of STSFWSR.
This access road is currently maintained by WSD for their routine maintenance
of the service reservoir. However, due to security concerns, proposal for
co-sharing the access road through Sha Tin South Fresh Water Service Reservoir
with the tunnel operator is not acceptable from WSD’s standpoint. It should
also be noted that although there are vehicular accesses in the area, there is
no direct access to the agricultural land in question. Site formation works
will be required to construct the access road. It is estimated that if the car
park is to be located in this area, the total permanent
woodland loss will be about 0.35ha. There is also the risk of harmful materials
leaking/falling into the natural/modified watercourses downslope at the east of
the STSFWSR and west of the existing agricultural land. The proposed works at
this location could, in turn, affect the water quality and ultimately ecology
downstream. Notwithstanding the above, the construction cost and time need for
this alternative location will also be higher than the recommended
location.
Road Widening Alignment
2.5.26 There are two alignment
options for the proposed road widening works along LRT Road, namely uphill or
downhill of LRT Road. Extensive environmental considerations have been taken into account during the evaluation of options in order
to avoid/minimize encroachment into the LRCP and maximize environmental
benefits as far as possible.
Widening
of LRT Road (Uphill)
2.5.27 This scheme requires road
widening works to be carried out uphill of LRT Road within the LRCP and very
near existing burial grounds and graves. Due to the steepness of the uphill
slopes, it is envisaged that slope cutting for the road widening works will
result in the loss of a substantial portion of the country park’s surface and
burial grounds, and removal/relocation of graves/urns will become inevitable.
Hence it is considered that retaining structures will, in general, be more
suitable in this case as the extent of disturbance to the upslope area is
envisaged to be much smaller.
2.5.28 Given the proximity to the
LRT Road, there is little to no buffer space between the uphill slopes and the
carriageway of LRT Road. Therefore, widening LRT Road uphill will most probably
need to occupy one southbound traffic lane. Large hoardings will also be
necessary to prevent falling objects onto LRT Road during the uphill site
formation works. It is also envisaged that the main access to the works areas
will be via LRT Road.
2.5.29 An advantage of this scheme
is that the proposed road widening works is not envisaged to be any closer to
the downhill developments than the current LRT Road.
2.5.30 However, the uphill option
will encroach extensively within the LRCP as compared to the downhill option.
This should be avoided to the maximum practicable extent. In addition, not only
does the uphill option significantly reduce the country park’s green area, it will also lead to the direct loss of woodland habitats,
watercourses, flora and fauna. Burial grounds, graves and urns are also
scattered extensively near the periphery of LRCP. The future traffic will also
be much nearer to popular recreation amenities such as Wilson Trail and the
Hung Mui Kuk Nature Trails.
2.5.31 From a traffic point of view,
a major drawback of the uphill option is that it is very likely that temporary
closure of a southbound traffic lane will be inevitable during uphill site
formation given that there is currently limited to no buffer space between the
uphill slopes and LRT Road. This will create bottlenecks and greatly worsen the
already congested southbound (Kowloon bound) traffic during the morning peak
hours. In addition, construction traffic to the uphill works sites will have to
be via LRT Road further exacerbating the traffic. Although construction traffic
using LRT Road could be limited to non-peak hours, this would no doubt have a
direct impact on the construction programme.
2.5.32 Extent of the uphill site
formation works is also expected to be much greater than its downhill
counterpart. As such, the uphill option is expected to produce much more
excavated materials (i.e. more construction vehicles).
Furthermore, the downhill option could better utilize the existing
upgraded/up-to-standards slopes and thus is more cost effective. The risk of
falling objects is also much greater for the uphill option. Also, extensive
excavation, vibrations from large piling machines etc. under the uphill option
may also induce relict natural terrain landslides which would have otherwise
stayed dormant.
Widening
of LRT Road (Downhill)
2.5.33 60604728/R42b/Figure
2.10 shows the comparison of uphill and downhill options.
Although the downhill option will be nearer to the downslope residential
buildings, villages, school and hospital, and thus likely to induce more
adverse impacts on air quality and noise to these sensitive receivers,
mitigation measures such as noise barriers/enclosures will be provided as
described in Section
4, it is envisaged that less encroachment upon much sensitive
LRCP as well as woodland area located along uphill side by virtue of shifting
the widening works towards downhill, hence less disturbance such as tree
felling is anticipated. It is also envisaged that the capital costs and social
costs of the uphill option are higher than the downhill option. Moreover,
implementation of the uphill option will also be more difficult and
time-consuming. Construction uphill is also expected to be longer. Furthermore,
road widening uphill will likely require the temporary closure of one traffic
lane along LRT Road and that more construction vehicles will also make use of
LRT Road to access the road widening works areas. These will cause traffic
congestions along LRT Road southbound which in turn can cause air quality
impacts and noise impacts to sensitive receivers along LRT Road. The alignment
of road widening downhill and uphill are presented in 60604728/R42b/Figure 2.2 to 60604728/R42b/Figure 2.5
and 60604728/R42b/Figure 2.6 to 60604728/R42b/Figure 2.9
respectively.
2.5.34 Hence, it is recommended to
adopt the downhill option for the Project and carry out the road widening works
downhill of the existing LRT Road as far as practicable. The need of uphill
works near Hung Mui Kuk is required for the road widening works to avoid direct
encroachment into existing buildings of World-wide Gardens.
2.5.35 Comparison of the
environmental benefits and disbenefits on the road widening works alignment
studied is presented in Table 2.3 below.
Table
2.3 Comparison of Environmental Benefits
and Disbenefits of various Road Widening Works Alignment Options
Option
|
Environmental Benefits
|
Environmental Disbenefits
|
Road Widening Uphill
|
·
Further away from local sensitive receivers and
hence in general lower in impacts to air quality and noise sensitive
receivers and visual in operation phase.
|
·
Extensive excavation within the uphill woodland area
and LRCP which induce potential impacts to the local ecology, water quality
and increased tree felling.
·
May require to take up one
existing traffic lane during excavation. This will reduce the capacity of the
road and increase chance of congestion, which in turn will increase impacts
to air quality and noise sensitive receivers during construction phase.
·
Extensive excavation and resultant large extent of
retaining structures along uphill will be visually intrusive and incompatible
to the natural setting of the LRCP at Shatin side, which is considered as a
major landscape and visual resource.
|
Road Widening Downhill
(Preferred Option)
|
·
Avoid/Minimized impacts and encroachment to the LRCP
and the uphill woodland area.
·
Minimize tree felling.
·
Generate much less C&D wastes in general as
reduced excavation into the natural slopes, and road widening downhill
requires filling which can facilitate the use of excavated materials (say
from tunnel portal excavation).
·
Access to the site / works area could be via the downhill
local roads and avoid the busy LRTR, thereby reducing the number of
construction vehicles using LRTR and hence reducing the chance of causing
congestion at LRTR. Reduced the potential impacts to air quality and noise
sensitive receivers.
|
·
The widened road will be nearer to certain sensitive
receivers (i.e. the residential developments located
downhill of LRTR at Shatin side). Nevertheless, the impacts could be
mitigated / reduced with the provision of mitigation measures such as noise
barriers and/or enclosures.
·
The installation of noise enclosure will be key
visual impact to the visually sensitive receivers along the LRTR at Shatin
side. Appropriate aesthetic pleasing design of noise enclosure could be
applied to mitigate the impact.
|
Natural Terrain Hazard Mitigation
Measures (NTHMMs)
2.5.36 Potential landslide hazards from the natural terrain above the existing
Lion Rock Tunnel Road (LRTR) to the operation and road users of the LRTR is
identified. Large- scale slope stabilization and debris resisting barriers are
the typical mitigation measures for the natural terrain hazards.
2.5.37 Given that the natural terrain hazards identified fall within the
boundary of LRCP and any proposed NTHMMs at the natural hillside would have
significant environmental and ecological impacts to the habitats of the LRCP
inherently, it is therefore to recommend the construction of rigid barriers at
the edge of the widened LRTR (on the developed/paved areas within the boundary
of LRCP) as the preventative measures of the potential landslide hazards with
an aim to avoiding extensive excavation and tree felling at the LRCP area. The
approximate location of the proposed rigid barriers is shown in 60604728/R42b/Figure
2.3.
2.5.38 Aside from the proposed rigid barriers within LRCP, erection of flexible
barrier is adopted for the mitigation measures of the natural terrain hazard
outside LRCP. As the majority of the road widening
work along LRTR outside LRCP towards downhill, erection of flexible barriers at
the uphill side is chosen instead of the large-scale slope stabilization works
or erection of rigid barriers, of which it will be inevitably involving
extensive excavation and tree felling at the uphill side along LRTR. The
approximate location of the flexible barriers has been carefully studied in order
to minimise the direct environmental and ecological impacts to the natural
habitat outside the boundary of LRCP and presented in 60604728/R42b/Figure
2.2 & 60604728/R42b/Figure
2.3.
2.6
Construction Methodologies
2.6.1 This section describes the
planning of the construction of the Project, covering the key aspects including
the envisaged methods of natural terrain hazard mitigation measures,
tunnel construction, other infrastructures and the sequence of works.
Natural
Terrain Hazard Mitigation Measures (Flexible Barriers) outside LRCP
2.6.2 The erection of flexible
barriers is a lean construction as the mitigation measure for natural terrain
hazard against large-scale slope stabilization works and construction of rigid barriers, and mainly involves limited no. of drilling
works for anchors installation including manual construction of footing for the
supporting of steel posts. Also, the existing maintenance access of the slope
features would be used as the temporary site access for the construction of the
flexible barriers while the temporary construction plant and storage area would
be located distantly away from the woodland and sensitive area in order to further minimize the disturbance to the
environment and natural habitats. The location and orientation of anchors and
footings would be designed carefully to avoid unnecessary tree felling as far
as practicable, and small-scale trimming of vegetation would be limited at the
location of anchors and footings.
Natural
Terrain Hazard Mitigation Measures (Rigid Barriers) within LRCP
2.6.3 The erection of 2 rigid
barriers within LRCP primarily involves construction of reinforced concrete
(RC) retaining structures with possibly mini-piles/pre-bored
H piles as foundation. The foundation of the rigid barriers will be carried out
by either small drilling rig or pre-bored H pile drilling rig while small-scale
excavation works is also anticipated. Given the fact that the rigid barriers
are to be proposed at the paved/developed areas along LRTR instead of
large-scale slope stabilization works and construction of rigid barriers at the
natural hillside within LRCP, it is therefore envisaged that the impact to LRCP
is tremendously minimized in view of the construction scale and location of the
proposed rigid barriers.
Tunnelling
Method
2.6.4 Based on the available
geological profile, it is envisaged that tunnel excavation will be mostly
carried out in good quality granite rock masses. They are typically excavated
by either drill & blast or by tunnel boring machine (TBM) or other mechanical
excavation methods such as drill and break. The preferred method of tunnel
construction is greatly influenced by the local constraints and nearby
sensitive receivers.
2.6.5 As discussed in Section
2.2.6, the Kowloon bound and Shatin bound tunnel tubes have been in use for
over 50 years and 40 years respectively. Signs of deterioration of the tunnel
structures have become apparent. As such, the existing LRT tunnel tubes are
major sensitive receivers during construction of the new middle tunnel. Given
the existing conditions of the LRT and the close proximity
to the proposed tunneling works (approximately 10m to 15m), it is envisaged
that only a small charge weight of explosives will be permitted if blasting is
adopted. It should also be noted that apart from the existing LRT tunnel tubes
themselves, there are also other major sensitive receivers nearby such as the
five large diameter WSD watermains which supply freshwater to a large
population in Kowloon and Hong Kong Island. In addition, the large vibrations
from blasting may give rise to stability concerns on the natural slopes at the
tunnel portals. There are also concerns on the potential risks and hazards to
life to the public during transport and handling of explosives. The concerns on
hazard to life is a major environmental consideration in selecting the
tunnelling method.
2.6.6 It is also envisaged that
locating an explosive magazine nearby will be extremely challenging given the
proximity to residential developments, water treatment works and service
reservoirs, major trunk roads and strategic traffic corridors etc. Without an
explosive magazine, the blasting cycle will be heavily constrained and as such,
delivery of explosives by CEDD Mines Department before each blast will most likely
be confined between 11am and 2pm under normal circumstances. This means that
blasting has to be carried out in the afternoon. The
daily transport and handling of explosives will have serious impacts to hazard
to life. It is also likely that the LRT has to be
closed to traffic during blasting and also after each blast to check for
misfires. This is highly undesirable from a traffic point of view considering
that the LRT has one of the highest usages in Hong Kong. Though not peak
periods, traffic queues and congestions are also expected at connecting roads
on both sides of LRT, thereby increasing the impacts to air quality and noise
sensitive receivers.
2.6.7 In general, ground-borne
noise impacts from TBM or drill and break tunnelling can be more easily
controlled than that of drill and blast. The advance rate of the TBM could be
altered, and the choice of plants and equipment used for drill and break
tunnelling could be modified to cater for different site conditions and
constraints. 24-hour tunneling using a TBM and drill and break is also
considered feasible and this will bring significant
benefits to the implementation programme.
2.6.8 Despite the potential
environmental benefits of using TBM, its environmental disbenefits include generation
of more C&D materials than the drill and blast method. This is due to the
fact that typically, the horizontal spatial requirements of a road tunnel is greater than the vertical one (even more so with
increasing number of traffic lanes). TBM is circular so in this case, the drill
and blast method could provide more flexibility for a more efficient tunnel
cross section. Furthermore, given the large TBM size, the extent of site
formation works at the Shatin Portal (and therefore impacts to the existing
woodland) may be larger than the drill and blast method. Nevertheless, given
the heavy constraints of using blasting, and with considerations on hazard to
life, air quality impacts, noise impacts, cost effectiveness, safety to tunnel
users, water supply, proximity to residential developments and Potentially
Hazardous Installations (PHI) etc., it is recommended not to adopt blasting.
Instead, mechanical excavation such as using TBM and
drill and break methods should be used for the tunnelling works.
2.6.9 Comparison of the
environmental benefits and disbenefits of the various tunnelling methods
studied is presented in Table 2.4 below.
Table
2.4 Comparison of Environmental Benefits
and Disbenefits of various Tunnelling Methods
Option
|
Environmental Benefits
|
Environmental Disbenefits
|
Tunnel Boring Machine (TBM)
(Preferred Option)
|
·
Controllable production rates to minimise the
adverse impacts.
·
More easily controlled vibrations than drill and
blast method.
·
Potential impacts in terms of noise, dust and hazard to life restricted to near the launching
area.
·
Existing traffic could be maintained (unlike when
during and after blasting) and so no additional traffic congestion (and
therefore impacts to air quality noise) due to using TBM.
·
No significant hazards to the public envisaged
during delivery and handling of the TBM.
|
·
Extent of site formation works (and therefore
impacts to the existing woodland area) may be larger than the drill and blast
method due to large TBM required.
·
More C&D materials are expected to be generated
relative to the drill and blast method.
|
Drill and blast
|
·
Duration of construction nuisance will be shorter.
·
Less C&D materials are expected.
|
·
Large ground-borne noise impacts and vibrations due
to blasting which could potentially affect the fauna and flora of the
woodland area near the tunnel.
·
Closure of the existing Lion Rock Tunnels may be
necessary during and after blasting to check for misfires. As the Lion Rock
Tunnel is very heavily used, traffic congestion is expected along a long
section of Lion Rock Tunnel Road at Shatin side and along Waterloo Road at
Kowloon side, thereby increasing impacts to air quality and noise sensitive
receivers.
·
Transport and handling of explosives to the tunnel
staging area will have to pass by many residential areas within Sha Tin,
thereby posing hazards to the public.
|
Area
for Stockpiling
2.6.10 Since the construction of the
new middle third tunnel is round-the-clock and generates significant amount of excavated spoils, the stockpiling area is then
proposed accordingly. The following alternative locations near Shatin Portal
were explored for the proposed area for stockpiling and compared with the
current adopted location. Please refer to 60604728/R42b/Figure
2.15 for locations of the alternatives considered as follows:-
·
Location 1: Area immediate next to the existing toll
plaza at uphill side (on Feature No. 7SW-D/F31);
·
Location 2: Area at Tei Lung
Hau (above Feature No. 7SW-D/C47).
Location
1: Area immediate next to the existing toll plaza at uphill side (on Feature
No. 7SW-D/F31)
2.6.11 The stockpiling area
immediately adjacent to the existing tunnel vehicle depot south of the existing
toll plaza is one of the options at first glance, where the car parking
facilities will be also proposed and located in the operation stage. For this
reason, it is envisaged that there is no additional loss of woodland area and
ecological impacts due to the proposed stockpiling area. However, portions of
the proposed stockpiling area will be located within the woodland area as well
as LRCP. This location for temporary stockpiling area is not considered in view
of these issues.
Location
2: Area at Tei Lung Hau
(above Feature No. 7SW-D/C47).
2.6.12 Consideration was previously
given to locate the stockpiling area at Tei Lung Hau. Nevertheless, the area at Tei
Lung Hau is also classified as woodland area and a
watercourse runs nearby this area. As no permanent works are proposed at this
area, locating the stockpiling area at this location will incur additional
woodland loss and ecological impacts unavoidably, the vegetation at the
hillside of Tei Lung Hau is
also deemed to be a visual resource. Hence relocating the stockpiling area away
from Tei Lung Hau could
also minimize the visual impacts of the Project.
2.6.13 Having reviewed the above
considerations, the locations 1 and 2 will not be considered for the
stockpiling area and the proposed stockpiling area is now located at the north
of the existing toll plaza near downhill side within the footprint of the
permanent works (i.e. no additional ecological
impacts) and outside of LRCP.
Construction
of administration building/ ventilation buildings and tunnel associated
structures
2.6.14 The Project’s administration
building and the Shatin ventilation building will be situated at the Shatin
Portal whereas the Kowloon ventilation building will be situated at the Kowloon
Portal. The ventilation buildings and administration building will be constructed
by typical reinforced concrete construction method which includes i) formwork and falsework erection, ii) rebar fixing, iii)
concrete pouring and curing, and iv) formwork striking and back propping.
Superstructures will adopt bottom-up construction. Construct ground floor
slabs, beams, columns and walls to the lowest level and process upwards to roof
level. No percussive piling is envisaged under the construction scheme. Other
tunnel associated structures, such as depots, car parking facilities etc. will
be constructed by cast-in-situ method using similar method. Considerations on
the construction methods such as an adoption of cast in-situ instead of
pre-cast have also been given to the site condition and construction scale of
the tunnel associated buildings/structures. Since there is an insufficient
working space allowing for storage and mobilization of the pre-cast elements,
the adoption of cast in-situ for the tunnel associated buildings/structures is
therefore considered as a safe mean of construction method in a view to
avoiding mobilization of the pre-cast elements with a live traffic running
nearby.
Construction
of the road widening works along LRT Road
2.6.15 Road widening works along LRT
Road would mainly comprise construction of slopes and retaining walls. The
construction of the road widening roads mainly in the downhill area
significantly replaced the need for massive equipment for bored piling works
uphill to relatively much smaller filling and retaining structures (e.g. L-shaped walls) downhill that require simpler and more
environmentally friendly equipment. The works are to a large extent governed by
i) topographical constraint due to sloping ground
conditions of the sites; ii) weather condition; iii) possible obstructions to
the construction; and iv) geotechnical uncertainties which include ground and
groundwater conditions. Owning to limited working space along LRTR,
construction of L-shaped retaining structure by pre-cast element is
impracticable in view of limited storage area and mobilization space required
for pre-cast elements. However, to further reduce the environmental impacts,
steel prefabricated formwork instead of traditional timber formwork will be
adopted for the construction of L-shaped retaining structures as well as street
furniture such as profile barrier as far as practical so as
to minimize the C&D waste generated.
2.6.16 To avoid excessive cumulative
environmental impacts to the nearby sensitive receivers, the proposed widening
works along LRT Road are divided into four work zones, and with major site
formation and foundations works of adjacent work zones sequenced to be
constructed at different phases under the construction programme.
2.6.17 In addition, the programme and sequence of works of this Project were
planned in consideration of other nearby concurrent projects and therefore to
minimize the cumulative environmental impacts during the construction stage of
this Project. With regards to the road works along Lion Rock Tunnel Road,
“Revised Trunk Road T4” project by Civil Engineering and Development Department
(CEDD) and the “Reprovisioning of Sha Tin Water Treatment Works – South Works”
project by Water Supplies Department (WSD) were considered having the highest
possibility to impose cumulative negative environmental impacts to with our
proposed road works to the nearby receivers which was in particular taken into
account during the project planning.
2.6.18 Considering the “Revised
Trunk Road T4” project by CEDD, the tentative construction works at Revised
Trunk Road T4 will be completed in September 2028, while the start of the
construction works under this Project at the work zone 1 near Sun Tin Wai
Estate / Fung Shing Court is programmed to start in December 2028, thereby
avoiding the cumulative environmental impacts, including but not limited to
noise and air impacts, that may impose to the nearby sensitive receivers during
the construction of the project.
2.6.19 Considering the “In-situ
Reprovisioning of Sha Tin Water Treatment Works – South Works" project by
WSD, the tentative construction programme for their
substantial civil works will be completed by January 2025. Therefore, to
minimize the cumulative impact with the said project, the substantial civil
works at the Work Zone 5 at Sha Tin Portal was scheduled to commence in May
2025.
2.6.20 The details regarding the aforementioned projects can also refer to Section 2.8
below.
2.6.21 The proposed 6.5m wide single
lane elevated vehicular bridge to add an additional traffic lane along the Lion
Rock Tunnel Road (N/B) across Lung Cheung Road at Kowloon side shall comprise
upstand beams which shall be precast offsite, delivered and erected by mobile
crane onsite. The slab shall be constructed using the cast in-situ method to
avoid prolonged traffic diversion/congestion during erection which could
ultimately cause air quality and noise impacts. No percussive piling is
envisaged under the construction scheme.
2.6.22 Environmental friendly construction
equipment such as installing sheet piles using the press-in method in-lieu of
vibratory methods should be utilized as far as possible, such as during
construction of the pile caps of the proposed viaduct and during site formation
works for road widening.
2.7
Project Programme
2.7.1 The Project construction
works are anticipated to commence in Q1 2025 with widening of Lion Rock Tunnel
Road at Shatin except Toll Plaza area beginning in Q1 2025. According to the
latest programme, the tentative completion year for
the whole Project is 2034, with commissioning of six traffic lanes (excluding
bus lanes) along LRT and LRT Road in 2034.
2.7.2 Reprovisioning of the new
administration building and two new ventilation
buildings shall be carried out in the early phases of construction between 2025
to 2028. At the same time, slope formation works will be carried out to form
the tunnel launching area at Shatin Portal. Procurement, delivery
and assembly of the TBM will also take place in this period. Tunnelling of the
new middle tunnel by TBM is envisaged to commence in 2027. After commissioning
of the new middle tunnel (2-lane, Kowloon bound direction) in 2029, the
existing Kowloon bound traffic will be diverted to the new middle tunnel and
enlargement of the existing Kowloon bound tunnel shall follow with
commissioning of the 3-lane tunnel in 2032. At this time, the Kowloon bound
traffic within the new middle tunnel shall be diverted to the enlarged Kowloon
bound tunnel. The new middle tunnel shall then be temporarily closed off for
minor modification works before commissioning the third traffic lane. Diversion
of the existing Shatin bound traffic to the new middle tunnel will take place
in 2034. The existing Shatin tunnel will then be closed off for refurbishment,
with the refurbished tunnel expected to be completed by 2034. Concurrent to the
tunnelling works, the road widening works along Lion Rock Tunnel Road at both
Shatin (except toll plaza area) and Kowloon side shall
be carried out between 2025 to 2033, with full commissioning of the dual 3-lane
carriageway arrangement along LRT and LRT Road in 2034. Timeline showing the
traffic arrangement of the tunnels is presented in Table 2.5 below.
Table 2.5 Timeline of traffic arrangement of the tunnels
Tentative Schedule
|
Existing Shatin Bound Tunnel
|
New Middle Tunnel
|
Existing Kowloon Bound Tunnel
|
Q1 2025 –
Q1 2029
|
2 lanes
|
In construction
|
2 lanes
|
Q2 2029 –
Q4 2032
|
2 lanes
|
2 lanes
(Kowloon bound)
|
Closed for
Enlargement
|
Q4 2032 –
Q4 2033
|
2 lanes
|
Closed for demolition
of temporary partition wall
|
3 lanes
|
Q1 2034 –
Q4 2034
|
Closed for Refurbishment
|
3 lanes
(Shatin bound)
|
3 lanes
|
2.7.3 A tentative construction programme for the Project is provided in Appendix 2.2. This programme
provides the basis for the assessments presented in the EIA Report, and
tentative phasing of major construction works are outlined in Table 2.6 below.
Table
2.6 Tentative Phasing of Major
Construction Works
Major Works
|
Tentative Schedules
|
Construction of tunnel
ancillary facilities at Shatin Portal (including testing and commissioning):
§ new vehicular cross-over bridge and footbridge
§ new administration building
§ new ventilation building
§ Workshops, depots, car parking
facilities, FFTS gantries etc.
§ slope formation works
§ landscaping works
Other misc. works at
Shatin Portal:
§ reprovision of surge tank
§ watermain diversion
§ woodland compensation*
Construction of
tunnel ancillary facilities at Kowloon Portal (including testing and
commissioning):
§ new ventilation building
§ new portal structure
§ slope formation
§ landscaping works
|
Shatin Portal:
Q1 2025 to Q2 2031
Kowloon Portal:
Q3 2025 to Q4 2030
|
Tunnelling works (including
testing and commissioning):
§ Construction of new middle third
tunnel tube by TBM
§ Enlargement of existing Kowloon
bound tunnel tube by drill & break method
§ Refurbishment of the existing
Shatin bound tunnel tube
|
New middle third
tunnel tube:
Q1 2025 to Q1 2029
(Construction)
Q4 2032 – Q4 2033
(Closed for demolition of partition wall)
Kowloon bound tunnel
tube:
Q2 2029 to Q4 2032
Existing Shatin bound
tunnel tube:
Q1 2034 to Q4 2034
|
Road widening works and
road widening associated works at Shatin and Kowloon:
§ road widening works
§ slope formation works
§ retaining wall works
§ construction of noise mitigation
measures (Shatin only) (i.e., noise barrier)
§ Reprovisioning of Footbridge NF74
§ utilities diversion
§ landscaping works including
compensatory tree planting
§ new vehicular bridge across Lung Cheung Road
(Kowloon only)
|
Q1 2025 to Q4 2033
|
Note:
* Schedule refers to Section 8.10.41
2.8
Concurrent Projects
2.8.1
“Relocation of Diamond Hill
Fresh Water and Salt Water Service Reservoirs to Cavern” project by WSD, which
is a designated project, relocates the service reservoirs, including Diamond
Hill Fresh Water Service Reservoir and Diamond Hill Salt Water Reservoir into
caverns for releasing the existing Diamond Hill service reservoir sites for
housing and/or other compatible and beneficial uses while ensuring a reliable,
adequate and quality supply of water. Its construction is tentatively scheduled
to commence in 2022 for major construction works in 2026 and full completion in
2027.
2.8.2 The “Revised Trunk Road T4”
project by CEDD, which is a designated project, links up the end of the Project
at Sha Tin Road. Based on the available information at the time of this EIA
study, part of the Revised Trunk Road T4 Project involves widening of a section
of Sha Tin Road near Pok Hong Estate of about 150m
from dual 2-lane to dual 4-lane; and it would be carried out from 2023 to
September 2028.
2.8.3 The “In-situ Reprovisioning
of Sha Tin Water Treatment Works – South Works” project by WSD, which is a
designated project, is to increase the treatment capacity of the South Works of
Sha Tin Water Treatment Works from 364,000 m³/day to 550,000 m³/day to meet the
anticipated increase in fresh water demand due to progressive implementation of
new public and private housing developments and to reprovision the aged water
treatment facilities of the South Works. Its construction is tentatively
scheduled to commence in the second half of 2020 for major construction works
completion in January 2025 and completion of remaining landscaping works in
2027.
2.8.4 The “Proposed Drainage
Improvement Works at Chui Tin Street and Chui Tin Street Soccer Pitch” is to
improve the conveyance capacity of the drainage network and relieve the flood
risk in some local areas in Sha Tin and Sai Kung. Based on the available information
at the time of this EIA Study, the works will include stormwater pumping
storage schemes, box culverts and drainage upgrading works. Construction of the
project is tentatively scheduled to commence in 2023 for phased completion in
2031.
2.8.5 Potential cumulative
environmental impacts arising from these concurrent projects during the
construction and operation phases of the Project have been assessed in the EIA
Report. For construction phase, due to temporal overlapping of construction
works of the Project and the “Relocation of Diamond Hill Fresh Water and Salt Water Service Reservoirs to Cavern” and “Proposed
Drainage Improvement Works at Chui Tin Street and Chui Tin Street Soccer
Pitch”, cumulative environmental impact would be anticipated. For
operation phase, due to the close proximity,
cumulative environmental impact from “Revised Trunk Road T4” and “In-situ
Reprovisioning of Sha Tin Water Treatment Works – South Works” would be
anticipated. The potential cumulative impacts is presented in Section
3, 4,
5,
8
and 10.
No cumulative impact is expected for other environmental aspects, such as waste
implication, land contamination, cultural heritage, hazard to life. The
location plan of the concurrent projects is presented in 60604728/R42b/Figure
2.16.
2.9
Public
Concerns
2.9.1 Consultation activity for the
Project has been carried out during the application of the Project Profile
under EIAO. The Project Profile was exhibited for public inspection
between 25 September 2019 to 8 October 2019. Consultation with Kowloon City
District Council and Wong Tai Sin District Council was conducted on 16 June
2022 and 21 June 2022 respectively, while consultation with Sha Tin District
Council was scheduled to conduct in August 2022. The environmental comments
received mainly focused on the ecological impacts and expressed concerns on the
impacts of the proposed work on the surrounding natural habitats such as
woodland and water streams. Considering these public comments, the
proposed works have been designed to avoid encroaching the natural habitats as
far as possible. For unavoidable habitat losses, compensation are proposed. The potential ecological and water quality
impacts, and the proposed mitigation measures are presented in Section
8 and Section 5 of this EIA respectively.
2.9.2 There were also concerns on
noise impacts due to the additional traffic generated under the Project. Noise
barriers and semi-enclosures are proposed to be provided along Lion Rock Tunnel
Road if necessary. The exact locations and extent of the proposed noise
mitigation measures are detailed in Table 4.22 & 60604728/R42b/Figure
4.4 and 60604728/R42b/Figure 4.4.1 to
60604728/R42b/Figure 4.4.4 in Section 4 of this
EIA. Other environmental comments include concerns over impacts to air quality,
cultural heritage and waste generation and the follow-up actions to be taken
are summarized in Table 2.7., which are addressed under Sections
3, 9
and 6
under this EIA respectively.
Table 2.7 Summary of Concerns and Follow Up Actions
Concerns / Issues
|
Follow Up Actions to be Taken
|
§ Road traffic noise impact due to the
additional traffic generated from the Project
|
§ Noise mitigation measures including noise
barriers and noise-enclosure are proposed along Lion Rock Tunnel Road. As
such, the predicted noise levels at nearby NSRs will comply with the road
traffic noise criteria.
Please refer to Section 4.7 for
road traffic noise impact assessment.
|
§ Adverse water quality of watercourses near
project area due to construction activities from the Project
|
§ Proper site management practices and the
mitigation measures as recommended in the EIA would be implemented. As such,
no adverse water quality impact would be anticipated during construction
phase.
Please refer to Section 5.7 for
mitigation measures for minimizing water quality impact.
|
§ Loss of surrounding natural habitat due to
encroachment of project into LRCP
|
§ Middle Option for alignment of new tunnel
and downhill
road widening at LRTR was adopted to reduce encroachment into LRCP and reduce
loss of habitat to a minimum extent.
§ Woodland compensatory planting is provided
near Project Boundary for any unavoidable woodland loss within LRCP would be
compensated off-site.
Please refer to Section 8.10 for
mitigation measures for minimizing ecology impact.
|
§ Increased air pollutant
concentration due to construction activities and additional traffic generated
from the Project
|
§ Construction and operation phase
air quality impact assessment was conducted in compliance with the
requirements set out in the EIAO-TM. Suitable mitigation measures will
be implemented during construction and operation stages as recommended in the
EIA.
Please refer to Section 3.7 for
air quality impact assessment.
|
§ Adverse impact to cultural heritage site
(Tsang Tai Uk) from construction activities
|
§ Project road alignment is revised. Tsang Tai Uk is now located at substantial distance from Project
Site. No adverse impact is anticipated during construction phase.
Please refer to Section 9 for
details of Cultural Heritage Impact Assessment.
|
§ Removal of trees within LRCP and surrounding
areas due to the Project
|
§ Middle Option for alignment of new tunnel
and downhill road widening at LRTR was adopted to reduce
encroachment into LRCP and minimize removal of trees within LRCP.
§ Compensatory tree planting is proposed
for trees affected in LRCP near the tunnel portal area and toll plaza administration
area. Off-site woodland compensatory planting is also provided.
Please refer to Section 10.8 for
details of landscape and visual mitigation measures.
|
§ Potential hydrological impacts
on natural watercourses
arising from construction activities
|
§ Appropriate water control strategies should be implemented to
minimize the groundwater infiltration during the tunnel construction.
Please refer to Section 5.7 for
details of mitigation measures for minimizing groundwater infiltration.
§ Surface water level monitoring of natural
watercourses in the vicinity of the underground tunnel improvement works area
should be conducted during the construction and operation stages.
Please refer to Section 8.13 for
the details of monitoring on surface water level of natural watercourses.
|