CONTENTS

12        SUMMARY OF ENVIRONMENTAL OUTCOMES. 12-1

12.1     Introduction. 12-1

12.2     Summary of Environmental Benefits and Environmental Achievements of the
Project
. 12-1

12.3     Environmental Benefits of Environmental Protection Measures Recommended  12-2

12.4     Estimated Population Protected from Various Environmental Impacts. 12-10

 

TABLES

 

Table 12.1             Key Design Considerations and the Associated Environmental Benefits  12-2

Table 12.2             Key Environmental Mitigation Measures / Good Site Practices /Enhancement Measures and their Associated Benefits     12-3


12                         SUMMARY OF ENVIRONMENTAL OUTCOMES

 

12.1                   Introduction

 

12.1.1             This chapter summarises the overall environmental outcomes due to the construction and operation of the Project in accordance with Section 3.6.1 of the EIA Study Brief (No.: ESB-342/2021).  The Project was given consideration of alternative options based on findings from various engineering and environmental reviews.  Chapter 2 outlines the details and benefits of the Project, as well as the consideration of alternatives during the design stage.  By implementing suitable measures to satisfy all statutory requirements, all preferred options considered and ensured that environmental impacts could be avoided or minimised, as practicable, and mitigated, as necessary.  The technical assessments conducted in Chapters 3 to 10 have demonstrated that all the statutory requirements in the EIA Study Brief (No.: ESB-342/2021) and EIAO-TM have been complied with. 

12.1.2             The following sections summarise the environmental outcomes arising from this EIA study, the approaches that have been adopted to either avoid or minimise various environmental impacts throughout the design process, and the associated environmental enhancement and mitigation measures.

12.2                   Summary of Environmental Benefits and Environmental Achievements of the Project

 

12.2.1             As described in Section 2.5, avoidance or minimization of the environmental impacts have been one of the key considerations throughout the design of the Project.  The key design considerations and the associated environmental benefits for different design approaches are discussed below.

 

12.2.2             The key environmental benefits achieved by selected the preferred option are listed below.

 

l   Minimisation of the need for land reclamation;

l   Avoidance of excavation works at Scenic Hill for the ATCL alignment;

l   Minimisation of waste generation;

l   Minimisation of noise disturbance and air quality impact during construction;

l   Avoidance of encroaching into the marine park and ecological sensitive area; and

l   Avoidance of open sea dredging works during construction works.

 

12.2.3             The key environmental benefits and achievements of the Project are listed below.

 

l   Adoption of environmentally friendly construction methods;

l   Promote the use of environmentally friendly vehicle system; and

l   Reduce vehicular emissions.

 

12.2.4             They key environmental benefits achieved by selected the preferred option are listed in Table 12.1 below.

Table 12.1          Key Design Considerations and the Associated Environmental Benefits

Design Approach

Key Design Considerations and the Associated Environmental Benefits

Minimisation of the need for land reclamation (see details in Section 2.5.1.5)

l   During the planning and design stage, the ATCL alignment is designed to minimise land reclamation works

l   Minimising the need for land reclamation while maximise the ATCL at-grade section.

Avoidance of excavation works at Scenic Hill for the ATCL alignment (see details in Section 2.5.1.6)

l   The preferred option does not require excavation works at Scenic Hill for the ATCL alignment to avoid the loss of habitat of Romer¡¦s Tree Frog.

l   Minimising the waste generation from excavated materials.

Minimisation of waste generation (see details in Section 2.5.1.7)

l   The preferred alignment option maximises the use of at-grade roads instead of elevated roads to minimize the waste generated from the construction of additional structures for elevated road.

Avoidance of encroaching into the marine park and ecological sensitive area (see details in Section 2.5.3.2)

l   Locating the marine facilities away from the Proposed North Lantau Marine Park and ecologically sensitive area (e.g. the artificial reef at the Chek Lap Kok Marine Exclusion Zone).

Avoidance of open sea dredging works during construction (see details in Sections 2.5.3.2, 2.6.1.6 & 2.7.2.5)

l   No open sea dredging works is required for the Project by strategically locate the marine facilities between the Airport Island and HKP Island.

l   Avoid direct impacts on the marine ecological resources and fisheries impact.

Adoption of environmentally friendly construction method (see details in Section 2.5.4.1)

l   Minimisation of construction noise and vibration impact to the nearby Chinese White Dolphins and marine species for the pile construction through the quieter piling method (e.g. bored piling method).

Promote the use of environmentally friendly vehicle system (see details in Section 2.5.1.4)

l   The use of zero emission vehicles during operational phase can help improve roadside air quality.

 

12.3                   Environmental Benefits of Environmental Protection Measures Recommended

 

12.3.1             A detailed assessment and identification of site constraints and impacts, as well as mitigation measures and good site practices, have been conducted and recommended in the EIA study in order to further reduce the environmental impacts due to the Project.    The key good site practices, enhancement measures, mitigation measures and their associated benefits are summarised in Table 12.2.


Table 12.2          Key Environmental Mitigation Measures / Good Site Practices / Enhancement Measures and their Associated Benefits

Area/Issue

Key Recommended Mitigation Measures/ Good Site Practices/ Enhancement Measures

Associated Benefits

Air Quality

Construction Phase:

¡P         Implementation of sufficient dust control measures as stipulated under the APCO, Air Pollution Control (Construction Dust) Regulation (Cap 311R) and good site practices to minimise construction dust impact.

¡P         Watering regularly on heavy construction works sites, exposed site surfaces and unpaved haul roads to reduce dust emission by 91.7%, subject to actual site condition.

¡P         Adoption of liquid fuel with a sulphur content of not more than 0.005% by weight as stipulated under Air Pollution Control (Fuel Restriction) Regulation and good site practices to minimise emission from construction plant and equipment.

¡P         Adoption of locally supplied marine light diesel (MLD) with sulphur content of not more than 0.05% by weight as stipulated under Air Pollution Control (Marine Light Diesel) Regulation to minimise SO2 emission from construction vessels.

 

Operational Phase:

¡P         100% adoption of zero emission vehicles on the whole of the ATCL route.

¡P         Installation of electricity pedestal at each berthing facilities for use in order to minimise the vessel emissions.

¡P       Protect Air Sensitive Receivers (ASRs) by reducing fugitive dust and gaseous emissions during construction phase, and by minimizing vehicular and marine emissions during operational phase.

Noise

Construction Phase:

¡P         Implementation of mitigation measures such as good site practices, use of quieter Powered Mechanical Equipment (PME), noise insulating fabric, noise barrier and noise enclosure to screen noise from PMEs, and use of quieter construction methods including hydraulic concrete crusher, non-explosive chemical expansion agent, self-compacting concrete and silent piling by Press-in Method.

¡P         Construction Noise Management Plan(s) (CNMP) with reference to Section 8 and Annex 21 of the EIAO-TM should be prepared to submit during pre-tender stage, if any, and before commencement of construction works, so that both the verification of the inventory of noise sources, and the assessment of the effectiveness and practicality of all identified measures for mitigating the construction noise impact of the Project, would be performed during the design, tendering and implementation stage of the construction works.  A clear method statement of all the recommended mitigation measures for controlling the construction noise impacts should be formulated in the CNMP(s) to be prepared by future Contractors, such that all the recommended mitigation measures shall be implemented and executed properly. 

¡P         Good site practices are recommended during construction phase.  Measures include:

-          Only well-maintained plant should be operated on-site and plants should be serviced regularly during the construction period;

-          Mobile plant, if any, should be sited as far from NSRs as possible;

-          Plant known to emit noise strongly in one direction should, wherever possible, be properly orientated so that the noise is directed away from the nearby NSRs;

-          Use of site hoarding as a noise barrier to screen noise at low level NSRs;

-          Machines and plant that may be used intermittently should be shut down between works periods or should be throttled down to a minimum; and

-          Any material stockpiles and other structures should be effectively utilised, wherever practicable, to screen the noise from on-site construction activities.

Operational Phase:

¡P         A noise commissioning test of the zero emission vehicles should be carried out prior to operation, and the Sound Power Level (SWL) should be 100dB(A) or below.

 

¡P       Protect Noise Sensitive Receivers (NSRs) by reducing construction and operational noise.

Water Quality

Construction Phase:

¡P         Limited the maximum number of piles allowed for concurrent installation for marine viaduct (max.: 2 piles to be installed concurrently) and marine facilities (max.: 2 piles to be installed concurrently).  Also, silt curtain should be set up to enclose the entire active work area before construction of temporary working platforms and piling works for marine facilities and marine viaduct to control sediment dispersion.

¡P         Implementation of appropriate measures and good site practices in accordance with the guidelines stipulated in Water Pollution Control Ordinance (WPCO), Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-ICW) and Practice Note for Professional Persons, Construction Site Drainage (ProPECC PN1/94).

¡P         Adoption of proper site management and good housekeeping practices to minimise the potential water quality impact due to spillage events.

 

Operational Phase:

¡P         Deployment of cage type silt curtain during maintenance dredging.  It is also recommended to limit the maximum working rate for maintenance dredging to be 40m3 per hour and only one closed grab dredger will be working in any time.  

¡P         Implementation of other good site practices implemented during construction phase for marine construction works for maintenance dredging during operational phase.

¡P         Adoption of proper site management and good housekeeping practices to minimise the potential water quality impact due to spillage events.

¡P         Regular cleaning and removal of floating refuse should be conducted within marine water and coastal area within and around the Project to avoid excessive accumulation.  Also, any new drainage outfall(s) under this Project will be located outside of the marine facilities.

¡P         A surface water drainage system of the ATCL should be provided to collect road runoff to the new drainage system with new stormwater outfall and adequate designed pollution removal devices such as silt trap and, as necessary, oil/grease trap, which should be regularly cleaned and maintained to ensure proper functioning.

 

¡P       Protect the neighbouring Water Sensitive Receivers (WSRs) during construction and operational phase.

Waste Management

¡P         Implementation of a WMP, segregation waste to avoid cross-contamination, transporting inert waste to public fill reception facilities and recycle non-inert C&D material.

¡P         Implementation of good waste management and control practices to avoid generation of excessive amount of waste materials.  The marine sediment is expected to be excavated and reuse option is considered as far as possible.

¡P         Implementation of a trip-ticket system for each works contract in accordance with DevB TC(W) No. 6/2010 to ensure that the disposal of C&D materials are properly documented and verified.

¡P         Implementation of suitable mitigation measures, such as the requirements as stipulated in the ADV-19.

¡P         Handle chemical waste in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes, and disposal of chemical waste at licensed chemical waste recycling / treatment facilities.

¡P         Excavation, treatment, transportation and disposal of sediments in accordance with the Air Pollution Ordinance (Construction Dust) Regulation.

¡P         For off-site disposal of excavated marine sediments, the basic requirements and procedures specified under ADV-21 shall be followed.

¡P         Application of marine dumping permit under the Dumping at Sea Ordinance for marine sediment disposal.

¡P         GPS or equivalent systems will be equipped to all dump trucks for real-time tracking and monitoring of transportation of inert C&D materials to designated locations.

 

¡P       Minimise waste generation.

¡P       Ensure proper handling of chemical waste.

¡P       Avoid potential adverse environmental impacts associated with handling, collection and disposal of waste.

¡P       Ensure the C&D materials are disposed to the designated outlets.

Ecology

(Marine)

Construction Phase:

¡P         All vessels used in this Project will be required to slow down to 10 knots around the Project¡¦s marine works areas and areas with potential high dolphin usage, including existing and proposed marine parks.

¡P         Implementation of standard site management practices, water quality mitigation measures, and vessel speed restriction as a precautionary measure during the construction and operation of the Project would reduce impacts. 

 

Operational Phase:

¡P         Deployment of silt curtain during maintenance dredging and good site practice, are expected to mitigate impacts to marine ecological resources.

All vessels used in this Project will be required to slow down to 10 knots around the Project¡¦s marine works areas and areas with potential high dolphin usage, including existing and proposed marine parks.

 

¡P       Minimise the impact on impacts on marine ecological resources and marine parks.

Ecology

(Terrestrial)

Construction Phase:

¡P         Adoption of good site practice to minimise the indirect disturbances to surrounding habitats and associated wildlife.

 

Operational Phase:

¡P         Precautionary measures are recommended with respect to water quality control and disturbance to adjacent wildlife in order to further reduce the impacts.

 

¡P       Minimise the potential indirect disturbances to surrounding habitat and associated wildlife.

Fisheries

Construction Phase

¡P         Water Quality Impact Assessment mitigation measures will be sufficient to mitigate the impact on fisheries (e.g.  Deployment of cage-type silt curtain during construction, good site practice.

¡P         No addition mitigation measure is required.

 

Operational Phase:

¡P         Deployment of silt curtain during maintenance dredging and good site practice, are expected to mitigate impacts to fisheries.

¡P         Appropriate notification, communications, site protection and marking would be adopted to reduce navigation risks with fishing vessels.

¡P         No fisheries-specific mitigation measures are required.

¡P       Minimise the impact on fisheries resources during construction and operational phase.

Cultural Heritage

¡P         No cultural heritage mitigation measures and further MAI are required.

¡P         As a precautionary measure, the project proponent and his/her contractor are required to inform AMO immediately when any antiquities or supposed antiquities under the Antiquities and Monuments Ordinance (Cap 53) are discovered during the seabed disturbance works in the Project site.

 

¡P       Verify the presence of marine archaeology.

 

 

Landscape and Visual

Construction Phase:

¡P         CM1 - Preservation of Existing Trees and Other Vegetation

¡P         CM2 - Transplanting of Affected Trees

¡P         CM3 - Compensatory Tree Planting

¡P         CM4 - Control of Night-time Lighting Glare

¡P         CM5 - Erection of Decorative Screen Hoardings

¡P         CM6 - Management of Construction Activities and Facilities

¡P         CM7 - Reinstatement of Temporarily Disturbed Landscape Areas

 

Operational Phase:

¡P         OM1 - Aesthetically Pleasing Design of Aboveground / Above Sea Structures

¡P         OM2 - Provision of Amenity Planting and Landscape Features

 

¡P       Minimise landscape and visual impact during construction and operational phases.

 

 

 

 

 

 

 

 

 

 


12.4                   Estimated Population Protected from Various Environmental Impacts

 

12.4.1             Through the avoidance and/or minimization of environmental impacts surrounding the Project site, population and environmental sensitive areas have been protected from the construction and operation of the Project.  

 

12.4.2             The protected populations include the following:

 

¡P            Existing ASRs and/or NSRs at Offices at Hong Kong Port Passenger Crossing Building, AsiaWorld-Expo, Hong Kong SkyCity Marriott Hotel, Regala SkyCity Hotel, SkyPier, Hong Kong Airlines Training Academy, Cathay City, Seaview Crescent, Novotel Citygate Hong Kong, Ling Liang Church E Wun Secondary School, Ling Liang Church Sau Tak Primary School, One Citygate, Fu Tung Plaza, Ching Chung Hau Po Woon Primary School, Po On Commercial Association Wan Ho Kan Primary School, Tung Chung Crescent, Fu Tung Estate and Yu Tung Court by implementation of good site practices during the construction phase of the Project;

¡P            Planned ASRs and/or NSRs at the Planned Visitation Church Development, Campus and Dormitory of the Hong Kong International Aviation Academy, Offices SkyPier Terminal, 11 SKIES and Planned Commercial Use by implementation of good site practices during the construction phase of the Project; and

¡P            All existing and planned ASRs and/or NSRs as mentioned above during the operational phase of the Project.