CONTENTS
2.1 Purposes
and Objectives of the Project
2.4 “Without
Project” Scenario
2.5 Alternative
Options of the Project
2.6 Description
of the Preferred Option
2.7 Construction
Methods and Engineering Requirements
TABLES
Table 2.1 Alternative Options – ATCL
Alignments
Table 2.2 Alternative Options – TCC Station Siting
Table 2.3 Considerations on ATCL Alignment
Options
Table 2.4 Alternative Options – Depot
Locations
Table 2.5 Alternative Options – Marine Facilities
Locations
Table 2.6 Considerations on Marine
Facilities Location Options
Table 2.7 Advantages
and Disadvantages of Construction Methods
Table 2.8 Summary of Key ATCL Elements
Table 2.9 Summary of Concurrent Projects
Table 2.10 Summary of Concerns and
Responses
FIGURES
Figure 2.1 Alternative
ATCL Alignment and TCC Station Siting Options
Figure 2.2 Alternative
Depot Location Options
Figure 2.4 Alternative
Marine Facilities Location Options
Figure 2.5(a) Illustrations of Construction Methods – Land
Viaduct and Marine Viaduct
Figure 2.5(b) Illustrations of Construction Methods – At-Grade
Road Section – Method 1
Figure 2.5(c) Illustrations of Construction Methods – At-Grade
Road Section – Method 2
Figure 2.5(d) Illustrations of Construction Methods – At-Grade
Road Section – Method 3
Figure 2.5(e) Illustrations of Construction Methods - Wave
Attenuator and Floating Pontoon
Figure 2.6 Locations
of Concurrent Projects
APPENDICES
Appendix 2.1 Tentative
Construction Programme
2.1.1.1
The purposes and objectives of the Project are to enhance
connectivity between Tung Chung, Airport Island and HKP Island and provide an
alternative transportation option served by autonomous transportation system
with zero emission vehicles. The
Project also provides marine facilities including the SKYCITY Pier and berthing
facilities to serving pleasure vessels and providing marine transport services
associated with tourism.
Enhancement of
Connectivity
Airport Tung Chung Link – Autonomous Transportation System connecting
Tung Chung
2.2.1.1
The ACL project, being developed by AAHK, is a purpose-built
bridge on which a vehicular road and a pedestrian walkway will be provided to
connect the HKP Island and SKYCITY.
As an environmental initiative, ACL will only be served exclusively by
AAHK’s electric vehicles, such that there is no air pollutant emission during
its operation. Non-AAHK vehicles
are restricted from accessing the ACL.
In the longer term, ACL will be served by AAHK’s autonomous
transportation system. As the next
step, ATCL, as an extension of the ACL’s autonomous transportation system being
planned and operated by AAHK, will run along the road on the eastern coast of
the Airport Island to connect to Tung Chung Town Centre. With the use of zero emission vehicles (e.g.
electric vehicles), and ultimately an autonomous transportation system
(supported by zero emission autonomous vehicles) for the ATCL, the Airport
Island will be seamlessly connected with the HKP Island and Tung Chung Town
Centre in an environmentally-friendly manner.
Marine Facilities – SKYCITY Pier and Berthing
Facilities
2.2.1.2 To the east of the Airport Island along the coast of SKYCITY, marine facilities will be provided in the area including a pier and berthing facilities. World international airports today are placing a stronger emphasis on multi-modal connectivity with neighbourhood destinations. Marine connectivity of yachts and ferries have been increasingly common to diversify leisure and tourism opportunities and foster an attractive lifestyle destination. The proposed marine facilities could maintain and strengthen HKIA’s position as an international aviation hub, bringing up with competition amongst airports to deliver the best experience for visitors and travellers.
2.3.1
General
2.3.1.1
The Project offers numerous benefits to the neighbourhood and
environment through the planning design.
These benefits include additional transport option - zero emission transport, mitigating emissions from increased passenger
inflow and greater connectivity and socio-economic growth. The details of the benefits are further
discussed in the below sections.
2.3.2
Additional
Transport Option – Zero Emission Transport
2.3.2.1
The increased number of people visiting the Airport Island as
induced by the SKYCITY and Tung Chung Town Centre developments may cause
greater demands on other transport services available in the areas, especially
in a post-pandemic scenario. The
ATCL in this respect will provide an additional land transportation option
between HKP Island, SKYCITY and Tung Chung Town Centre. With the use of zero emission vehicles,
it will provide a greener mode of transport for the area than other modes of
transport (e.g. buses, taxis, private cars). ATCL can also shorten the travelling
distance and time, and provide a developed integrated system
interconnectivity. As such, this
attractive alternative will alleviate the pressure on general transport
services and provide a more comfortable and environmental-friendly travel
experience for passengers.
2.3.2.2
Furthermore, the marine facilities including a pier and berthing
facilities that proposed in this Project will also provide an additional marine
transportation option for the area.
The pier will be equipped to provide marine transport services
associated with tourism. Zero
emission vessel is a competitive solution for decarbonisation and is currently
under active development. The
proposed pier will allow the future use of zero emission vessels, when these
become commercially available in the market. In addition, an electricity pedestal
will be installed at each berthing facility to provide on-shore power supply to
vessels for reducing marine emissions at berth.
2.3.2.3
In the event of traffic accidents that might occur on the existing
key commuting lanes to/from the HKIA, the Project would provide alternative
land and marine transport options for commuters and thus maintain the
transportation services to/from the Airport Island.
2.3.3
Mitigation of
Emission from Increased Passenger Inflow
2.3.3.1
As a green airport, a sustainable strategy is adopted to achieve
carbon emission reduction and sustainable living, as far as practicable. Since the ATCL incorporates
environmental protection measures such as 100% adoption of zero emission
vehicles, there will be no vehicular air pollutant emissions coming from the
vehicles on the whole of the ATCL route.
Thus, the ATCL may help mitigate such increases in vehicular emissions
brought about by the expected increases in traffic to and from the Airport
Island area as it provides an additional greener mode of transport using the
zero emission vehicles between Tung Chung, Airport and HKP Island.
2.3.3.2
The ATCL may help achieve a reduction of emissions that would have
otherwise been emitted through travellers utilizing other emissive modes of
transport.
2.3.4
Greater
Connectivity and Socio-Economic Growth
2.3.4.1
Upon the commencement of the Three-Runway System (3RS) operation,
it is estimated that 123,000 direct employments will be created at HKIA. The Project, in conjunction with the
3RS, the HZMB and the developments in SKYCITY, could bring further economic
opportunities for Hong Kong and the GBA region. The Project will enhance connectivity
and the attractiveness of the leisure and entertainment related facilities
planned for the SKYCITY at HKIA, and catalyse a greater socio-economic growth
for the Airport Island and the wider Tung Chung community, as the Project
provides greater accessibility to job opportunities and stimulates economic
impetus into the North Lantau area.
2.4.1
Potential
Emissions from Increased Traffic Flow
2.4.1.1
As mentioned in Section 2.3, the increase
in patronage arising from traffic resumption and new developments (e.g. ECSA commercial developments, SKYCITY
developments and HKP developments) may induce an overall additional transport
demands and the associated vehicular emissions in the area, if it is a “Without
Project” scenario.
2.4.2
Increased
Burden on Current Transport
2.4.2.1
A greater burden may also be put onto public transport services at
the HKIA in light of the 3RS operation as well as other developments previously
mentioned. This may cause crowding
and capacity issue for certain transport services such as the public franchised
buses if adaptions are not made to accommodate an increase in commuters to and
from the HKIA area.
2.4.3
Limited
Transportation Method
2.4.3.1 Without the marine facilities, local residents and visitors can
only travel between HKIA, HZMB, SKYCITY developments and tourist attractions in
Hong Kong via land-based transportation.
2.5.1
ATCL
Alignment
2.5.1.1
A number of ATCL alignment options, commencing at MTR Tung Chung
Station and connecting the Tung Chung area with the HKP Island and Airport
Island, have been considered during the design developments. Three options have been explored during
the design stage and summarised in Table 2.1 below. Figure 2.1 shows the
alternative ATCL alignment options.
2.5.1.2
The proposed ATCL is to connect HKP Island, Airport Island and
Tung Chung Town Centre via a dedicated road link. According to the transport demand and
the nearby public transport services, the stations are positioned at locations
with potential of high number of visitors, most conveniently accessed and
shortest distance to the major existing and future major developments for
enhancing transit and connectivity with different modes of transportation as
well as minimizing the environmental impact.
Table
2.1 Alternative
Options – ATCL Alignments
Option
ID |
Descriptions |
1 |
The terminus of Option 1 is proposed next to Tung Chung Central (TCC)
Station and the alignment is along Tat Tung Road, adjacent to the North
Lantau Highway (NLH). The
alignment runs north across Tung Chung Waterfront Road and the Tung Chung
Navigation Channel alongside the NLH bridge. As the marine viaduct reaches the Airport Island, its alignment
passes the east side of Scenic Hill. A Cathay City (CAX) Station is proposed
here. After passed through the
Scenic Hill, it then continues in an easterly direction to the south of the China
National Aviation Corporation (CNAC) Headquarters where another station
(abbreviated as CNA Station) is located.
After CNAC , the alignment swings back to a northerly direction
crossing over the Hong Kong Link Road (HKLR) on a long span viaduct to near
the East Coast Support Area (ECSA).
The alignment then descends to run at low level above the sea
alongside the seawall of Airport Island.
It then passes approach light masts of the South Runway Approach
Lights (SAL). Land reclamation of
about 5,000m2 is required to avoid a relatively sharp turn and enable
the ATCL carriageway alignment to connect to SkyCity Station via East Coast
Road. The alignment sways
eastwards towards the seaside over the reclaimed land then decks over the
existing Hong Kong Link Road (HKLR) and passes the south side of the marine
facilities. After the Skycity
Interchange roundabout, the alignment drops to reach SKYCITY, to facilitate a
cross platform interchange with the SKYCITY Station. After SKYCITY, the alignment reverses in the same direction and
passes in an easterly direction along the causeway between Airport Island and
HKP Island. The alignment then
ascends over the HKLR into HKP Station. |
2 |
Option 2 has been explored with reference to Option 1 but has
aimed to maximise the at-grade section as well as to eliminate the need for land
reclamation. The alignment for
Option 2 is similar to that of Option 1 and therefore this section will focus
only on the areas that are different from Option 1. After passing CAX Station and Hong Kong Airlines (HKA) training
Academy, the alignment follows a northerly direction again passing over
Airport Road but not over the Airport Express Line (AEL). Instead, the alignment descends onto
the verge area between Airport Road and the AEL. An at-grade section and CNA Station
are proposed opposite to the Civil Aviation Department Headquarter (CAD HQ)
Facilities Building. The alignment
will be quite remote from the CAD HQ and the pedestrian connection between this
at-grade section and these buildings will be via a footbridge constructed
above the AEL and East Coast Road and landing on a strip of vacant land next
to the CAD HQ Facilities Building. The alignment then passes along the green strip before climbing
again over Airport Road and over many ground level roads and flyovers, some
existing and some proposed for the Skycity Interchange Improvement scheme. The at-grade section runs
approximately from the south boundary of the CAD HQ Facilities Building until
it has to cross over Airport Road on viaduct south of Cheong Lin Road
roundabout. The alignment then
passes over the Skycity Interchange roundabout and into SKYCITY Station. Similar to Option 1, after SKYCITY, the alignment reverses in
the same direction and passes in an easterly direction along the causeway between
Airport Island and HKP Island.
The alignment then ascends over the HKLR into HKP Station. |
3 |
From TCC Station, the alignment runs north across Tung Chung
Waterfront Road and the Tung Chung Navigation Channel but swings sharply to
the East along the seawall and passes underneath the NLH and AEL
at-grade. The alignment then
turns North to run alongside Kwo Lo Wan Road. The alignment then continues at-grade
along the eastern coastline of Airport Island. Three stations, ECSA South (ECSA-S) Station,
ECSA North (ECSA-N) Station and Approach Lights (AL) Station, are proposed at
this at-grade road section to link up the ECSA. The alignment continues along the eastern coastline, adjacent to
the HKLR and next to the seawall service road. At certain constrained locations, the
running surface of the ATCL will be combined with this service road to
minimise modification to the existing seawall and avoid land reclamation. In addition, there are a number of
utilities running underneath the road and it is assumed that the at-grade
corridor will run on top of the utilities such that utility diversion is
minimised. The alignment then continues north and passes between the
lighting masts of the SAL. As
ACL is an elevated road, the at-grade ATCL carriageway that runs along the
shore at Airport Island will change to elevated form while approach HKP
Island in order to connect to the elevated ACL. An at-grade spur line of ATCL, including carriageway and walkway
with the same configuration as typical ATCL design, connects to southern
promenade of HKP Island and terminated at the Academy Station, for connecting
the planned Aviation Academy and other topside developments in HKP Island. |
2.5.1.3
To minimise the environmental impact imposed by the ATCL, key
issues for options related to potential land reclamation, loss of habitat of
Romer’s Tree Frog, waste generation and siting of stations are considered. Air quality, noise, water quality,
ecology, waste management, landscape and visual impact would be the major
environmental factors to consider in selecting the preferred ATCL alignment option
and will be discussed below.
2.5.1.4 Since the
ATCL will be exclusively utilizing zero emission vehicles, there will be no
vehicular emissions coming from vehicles on the whole of the link route. Hence, air quality during operational
phase would not be a major environmental consideration of selecting preferred
option.
Potential
Land Reclamation
2.5.1.5 Amongst the
three options, Option 1 may require land reclamation of about 5,000m2
to avoid a relatively sharp turn and enable the ATCL carriageway alignment to
connect to SkyCity Station via East Coast Road. In long term, land reclamation near the
culverts (at the existing seawall on the southern side of the
proposed marine facilities) would potentially block water circulation via box culverts and
this may lead in the change of hydrodynamic regime. In short term, contaminant release due
to dredging works for land reclamation may deteriorate the water quality near
the proposed seawater intake at SkyPier and habitat loss of the marine ecology
and fisheries. Moreover, the
construction of land reclamation would impose potential impacts on air quality,
noise, waste management and landscape and visual. Both long term and short-term impacts
would induce water quality and ecological issues. Hence, Option 1 is less preferable.
Loss of
Habitat of Romer’s Tree Frog
2.5.1.6 Romer’s Tree
Frog Liuixalus romeri is a species endemic
to Hong Kong first discovered in 1952 on Lamma Island (Karsen et al.
1986). Individuals were recorded in
woodland around Scenic Hill in the literature, which are believed to be
remnants of the original population in Chek Lap Kok[1]. The latest available report regarding
the Romer’s Tree Frog on Scenic Hill (survey conducted between May 2014 – Apr
2015) suggested that there were fewer adult frogs, tadpoles and eggs on Scenic
Hill in comparison with the 1992 survey before the construction of the Airport[2]. Amongst the three options, Option 1 and
Option 2 may require excavation works at Scenic Hill for the ATCL alignment
which may affect the watercourse/waterbody and the adjoining vegetated area,
hence result in loss of habitat of Romer’s Tree Frog and impose potential
impacts to the known breeding site of Romer’s Tree Frog. Option 3 has avoided the encroaching to
the Scenic Hill and avoided the direct and indirect impacts to the ecologically
sensitive habitats.
Waste Generation
2.5.1.7 The potential
open excavation works may also generate large amount of construction and
demolition (C&D) material which is not desirable in the current promotion
of waste reduction according to Waste Blueprint for Hong Kong 2035 launched by
Environment Bureau in 2021. Option
1 and Option 2 require additional structures for flyover/viaduct, hence bored piles, excavation works at Scenic Hill for the ATCL
alignment. Option 3 only requires
modifying the existing road to maximise the use of at-grade roads instead of
elevated roads to suit with the ATCL alignment. Thus, comparatively small scale of
construction activities (e.g. construction of piles) will be involved and less
amount of estimated construction wastes would be generated. Hence, Option 1 and Option 2 are less
preferred.
Siting of Stations
2.5.1.8 TCC Station
is the main hub of the ATCL. It
acts as the intermodal gateway to the entire autonomous transportation system,
with links to public transport system provided at the Tung Chung Town Centre
area. Two location options (Option
S1 and Option S2) for TCC Station have been considered near the Tung Chung Town
Centre and Tung Chung Crescent, both locations are summarised in Table 2.2 and shown in
Figure
2.1.
Table 2.2 Alternative Options – TCC Station
Siting
Option
ID |
Descriptions |
S1 |
Located
near Citygate and Tat Tung Road |
S2 |
Located
near the Tung Chung Crescent Block 5 |
2.5.1.9
Both options are connected to the Citygate in view of the
connectivity. Option S1 is situated
next to the planned visitation church development with priests’ quarters. In comparison, Option S2 is located in
close proximity to Tung Chung Crescent and more construction noise and dust
impact to the nearby sensitive receivers would be anticipated. Moreover, a sharp turn is required for
approaching and leaving the Option S2, it is not desirable for autonomous vehicles.
Therefore, Option S1 is preferable.
2.5.1.10
Locations of other stations (besides TCC Station) for the ATCL
alignment options are shown in Figure 2.1. ECSA-S Station and ECSA-N Station of
Option 3, and CAX Station and CNA Station of Option 1 or Option 2 are mainly
for the purpose of serving ECSA developments, while AL Station of Option 3 and
SKYCITY Station of Option 1 or Option 2 is intended to connect the future
developments in SkyCity. Option 3
is the only option to connect Academy Station which supports the transport
system of Aviation Academy and other topside developments in HKP Island. Therefore, Option 3 is preferable.
2.5.1.11 Considerations
of the ATCL alignment options including station siting options are listed and
summarised in Table 2.3.
Table 2.3 Considerations
on ATCL Alignment Options
Option ID |
Benefits |
Dis-benefits |
Preferred
Option |
1 |
· Nil |
· Require land reclamation of about 5,000m2 causing a
potential loss of habitats for marine ecology and fisheries · Land reclamation is close to the existing culverts that allow water
circulation between the bay area and Tung Chung thus inducing water quality
and ecological issue in short term and resulting in the change of
hydrodynamic regime in long term, and would induce water quality and ecological issue in
short term · Require excavation works at Scenic Hill for the ATCL alignment which
results in loss of habitat of Romer’s Tree frog and higher volume
(approximate over 5,500m3) of excavated materials generated · More waste generation from the additional structures for flyover/viaduct, such as bored piles, excavation works at Scenic Hill, and land
reclamation works · Not able to support the population commuting to the planned Aviation
Academy and other topside developments on HKP Islands |
No |
2 |
· Avoidance of land reclamation to minimise potential habitat loss of
the marine ecology and fisheries, water quality impact and waste generation |
· Require excavation works at Scenic Hill for the ATCL alignment which
results in loss of habitat of Romer’s Tree frog and higher volume
(approximate over 5,500m3) of excavated materials generated · More waste generation from the additional structures for flyover/viaduct, such as bored piles and excavation works at Scenic Hill · Not able to support the population commuting to the planned Aviation
Academy and other topside developments on HKP Islands |
No |
3 |
· Avoidance of land reclamation to minimise potential habitat loss of
the marine ecology and fisheries, water quality impact and waste generation ·
Avoidance of excavation works at Scenic
Hill to minimise the loss of habitat of Romer’s Tree frog and waste
generation · Maximise the at-grade section as compared to Options 1 & 2 and
thus, less waste generation from the additional structures for flyover/viaduct such as bored piles ·
Academy Station (in Option 3 only) supports the transport system
of Aviation Academy, other topside developments in HKP Island · Passenger reaches all stations along ATCL/ACL directly with no passenger
interchange is required |
· Nil |
Yes |
2.5.1.12
In view of the above, ATCL alignment Option 3 is selected as a
preferred option.
2.5.2
Depot
2.5.2.1 Considering
the ease of access and land availability, two potential locations have been
considered for the depot along ATCL. Option D1 is located at the land near the
Academy Station at the south of HKP Island and Option D2 is located near the
Scenic Hill Tunnel, both locations are summarised in Table
2.4 and shown in Figure 2.2.
Table 2.4 Alternative
Options – Depot Locations
Option ID |
Descriptions |
D1 |
Located at
the HKP Island and close to the proposed Academy Station |
D2 |
Located near
the Scenic Hill Tunnel area and close to the future ECSA development area |
2.5.2.2
The depot shall provide essential
regular maintenance servicing for autonomous vehicles employed for the
ATCL. Major servicing shall be
carried out off-site by the zero emission vehicle
supplier specialist services. The
depot consists of a plant room and depot area. The plant room is designed to be maximum
approximately 7-10m high single-storey building (refer to Figure 2.3). Considering
the implication on various environmental aspects and its accessibility, two
potential locations (Option D1 and Option D2 as shown in Figure 2.2)
have been considered for the depot along ATCL.
Environmental
Considerations
2.5.2.3 The proposed depot is small-scaled and does not involve polluting
process such as paint spraying and dry polishing activities. Electrified equipment will be used for
maintenance works and exhaust emission of Non-road Mobile Machinery (NRMM)
adopted are expected to be limited.
Thus, adverse air quality impact associated with the associated
maintenance works at the depot is not anticipated. On the other hand, Option D1 and Option
D2 will be located at over 1.5km and about 600m from the nearest noise
assessment point (i.e. Seaview Crescent) respectively. Moreover, air-conditioning would be
provided for the planned Aviation Academy and HKA Training Academy located near
Option D1 and Option D2 respectively.
No adverse environmental impact will be expected for both options during
the construction and operational phase.
Thus, the preferred location of the depot is mainly based on its
accessibility which is discussed below.
Site
Accessibility
2.5.2.4 As Option D1 is located within the Closed Area, permit is required
to access the site of Option D1. In
comparison, Option D2 is connected to the public road network (e.g. Kwo Lo Wan
Road), which provides easier access for stakeholders during both the
construction and operational phases.
2.5.2.5
Considering the environmental
considerations and site accessibility, Option D2 is preferred.
2.5.3
Marine
Facilities
Location Options
2.5.3.1 Considering
the integration to the Airport City concept, there are two potential location
options for the proposed marine facilities. As shown in Figure 2.4, the
location at the north of Chek Lap Kok, waterspaces near the AsiaWorld – Expo
(Option MF-A) and waterspaces between Airport Island and HKP Island (Option MF-B)
have been taken into considerations.
Alternative location for options of the proposed marine facilities are summarised
in
Table 2.5.
Table 2.5 Alternative
Options – Marine Facilities Locations
Option
ID |
Descriptions |
MF-A |
The
waterspaces in Option MF-A are located near the AsiaWorld -Expo to the north
of Chek Lap Kok. It is the
closest location to the existing airport facility |
MF-B |
The
waterspaces in Option MF-B are located between Airport Island and HKP Island. It is the most convenient location
with the most sheltered area near the Airport City development and ATCL
alignment |
2.5.3.3
Moreover, the wave attenuator for the marine facilities of Option
MF-A providing a relatively sharp turn and causing additional floating refuse
easily trapped or accumulated.
Alternatively, Option MF-B is located between Airport Island and HKP
Island. Floating refuse potentially
trapped or accumulated will be similar to the existing condition. Therefore, Option MF-B is preferred in
view of potential accumulation of floating refuse.
2.5.3.4 The constraints, benefits and dis-benefits of different location options
of the marine facilities with preferred option identified are summarised in Table 2.6.
Table 2.6 Considerations
on Marine Facilities Location Options
Option
ID |
Benefits |
Dis-benefits |
Constraint
Descriptions |
Preferred
Options |
MF-A |
· The closest
location to the existing airport facility |
· Open sea dredging may be required during construction phase due to
insufficient water depth. Marine
maintenance dredging is
required to allow the vessels access berthing facilities during operation
phase. Open sea dredging during both
construction and operation phases would impose potential impacts on waste
management, fisheries, marine ecology and water quality · Potential
impact on water quality and marine ecology would be imposed to the Proposed
North Lantau Marine Park and the artificial reef at the Chek Lap Kok Marine
Exclusion Zone · The
installation of wave attenuator will provide a relatively sharp turn and
cause additional floating refuse easily trapped or accumulated |
· It is
located at the approach light area of the existing north runway (future
Centre Runway) and also located within Hong Kong International Airport
Approach Areas (HKIAAA) no.3, which no vessel shall pass or enter. As a result, this option is not
feasible |
No |
MF-B |
· Most
convenient location near the Airport City development and ATCL alignment · Locating
the marine facilities away from the existing and planned marine parks, any
potential water quality and ecological and fisheries impacts would be
considered less as compared to Option MF-A · Only marine
maintenance dredging is required, less marine sediment would be generated · The
floating refuse potentially trapped or accumulated will be similar to the
existing condition |
· Management
of mooring area and vessel height specific arrangement shall be imposed · Marine maintenance dredging is
required to allow the vessels access berthing facilities, which would impose
potential impacts on waste management, fisheries, marine ecology and water
quality |
· It is
located within the SkyPier Basin, which considered to be the most sheltered
area near Airport City development.
The south of the basin is within HKIAAA no.5, which no vessel with
height exceeding 15m shall pass or enter |
Yes |
2.5.3.5
In view of the above, Option MF-B is selected as a preferred
option.
Design Layout
2.5.3.6
Marine facilities would provide services to general public
travelling to the Airport or HKP Island.
Reference has been made to other international airports such as
Singapore Changi Airport, where similar sea access facilities are provided near
the airport for leisure and tourism, and transport where necessary.
2.5.3.7
The design of the marine facilities has accounted for the
anticipated number of usages by travellers and the required mix of berth type
in different sizes to optimise the configuration and number of berths
required. As shown in Figure
1.2, the marine facilities consist of 73 berths for majority of
medium-sized to small-sized vessels. By making reference to local marinas
(e.g. Aberdeen Marina Club, Gold Coast Yacht and Country Club and Lantau Yacht Club),
around 86% of berths are provided for boat length from 11-20m, around 8% of
berths are provided for boat length equal to or less than 10m and around 6% of
berths are provided for boat length from 21-35m. A relative high number of berths for
medium-sized vessel in the proposed design allows flexibility for the use by
smaller vessels as most common sizes of vessel found in Hong Kong range from
6m-35m with majority less than 20 m.
The proposed design is considered as the most efficient and cost-effective
configuration which optimizes the safe manoeuvrability for vessels while
accommodating the essential berthing and associated facilities.
2.5.4
Environmental
Considerations of Construction Methods
Piling
Construction
2.5.4.1
Percussive piling and bored piling are the commonly piling methods
adopted for construction. In
comparison with percussive pilings, bored piling construction generates less
noise and vibration. To minimize
the construction noise impact generated from the Project to Chinese White
Dolphins, bored pile foundation will be adopted for marine viaduct and land
viaduct for ATCL, and SKYCITY Pier and berthing facilities in marine
facilities.
Pier Column /
Bridge Deck Construction
2.5.4.2
Construction of pier columns could be carried
out by (i) cast in-situ or (ii) precast method. Cast in-situ method will use steel
formwork to construct the pier column.
For pre-cast method, the precast concrete column unit prefabricated off
site will be transported to the site for installation.
2.5.4.3 Either cast
in-situ or precast method will be considered for the construction of bridge
deck. For both cast in-situ and
precast methods, the deck segments will be constructed by the balanced
cantilever method or conventional full span by span method, except for marine
viaduct of which only balanced cantilever method could be adopted. For cast in-situ using balanced
cantilevered method, cantilevered bridge deck segments would be casted on the
form-traveler and the deck segment will be constructed starting from the bridge
pier and on either side for balancing itself. Bridge deck would be casted on the of temporary working platforms
which would be used as supporting structures in conventional full span by span
method. For precast method, precast
units of the bridge deck will be manufactured off-site and delivered to the
site for installation by either balanced cantilevered or full span by span
method which would be similar to the above discussed. However, installation of pre-cast units
instead of concreting works would be carried out.
2.5.4.4
The advantages and
disadvantages of different construction methods for piles and pier
column/bridge deck are summarised in Table 2.7.
Potential environmental impacts of both construction methods of cast in-situ
and precast method for pier columns/bridge decks have been assessed in this EIA
study. No adverse environmental
impact is expected from the construction of the Project.
Table 2.7 Advantages
and Disadvantages of Construction Methods
Method |
Advantages |
Disadvantages |
Piling
Construction |
||
Percussive Piling Method |
·
Piles can be precast to the required specifications ·
Require shorter construction time, reduce the duration of
potential environmental impacts |
·
The vibration/ underwater noise from the equipment and plants
might affect the marine ecology, soil condition and adjacent structures ·
Relatively higher noise impact from the percussive piling method ·
Higher headroom required |
Bored Piling Method |
·
Relatively lower noise and vibration than using percussive
piling method. Hence, less
disturbance to Chinese White Dolphins and marine species, less disruption to
soil condition and adjacent structure ·
Less headroom restriction |
·
More expensive, comparing with percussive piling method ·
Longer construction time, relatively |
Pier Column
/ Bridge Deck Construction |
||
Precast Method |
·
Pre-casting activities are carried out off site in a fabrication
yard. Hence, better control on
workmanship and construction quality. ·
As the casting carried out off site, the impact on-site for air
quality, noise, water quality, waste management during construction phase
will be minimised. ·
Requires less construction equipment on site, the noise impact
will also be minimised ·
Less site constraint due to erection of temporary falsework |
·
Since the structure for this Project are not modular in design,
the tailor-made precast units for construction of mould takes longer
construction time and generate more waste than in-situ method ·
The shipping of the precast unit will be constrained by the
height limit of the airport ·
Reduce design flexibility as the mould for fabrication is fixed |
In-situ Method |
·
Post-tensioning is possible ·
Longer service time period and minimal maintenance ·
Require relatively less special skilled workers ·
Steel formworks will be used instead of timber to maximize the
reuse of formwork, and minimize the waste generation ·
More flexibility to deal with design changes |
·
Require large area for erection of temporary falsework ·
Workmanship and construction quality are difficult to control |
Consideration of Construction Works Sequence
2.5.4.5
From the baseline information, while Chinese White Dolphins (CWDs)
utilise waters in the Assessment Area, the likelihood of the areas within and
in the vicinity of the Project site as important habitat for CWDs is low and
the said areas are not considered as unique and important habitats for
CWDs. Also, the marine works area
involving piling during the construction stage is relatively small. Unacceptable impacts from the Project to
water quality and CWDs are not expected with the implementation of appropriate
preventive and mitigation measures recommended in the EIA report. Therefore, no specific construction
works sequence would be required with respect to water quality and CWD.
2.5.4.6
To optimize construction works sequence with the least potential
impacts to the surroundings, at most two marine piles will be installed /
constructed concurrently at the proposed marine facilities works area and the
marine viaduct works area across Tung Chung Navigation Channel, respectively,
during construction phase. In
addition, the piling works will only be conducted after setting up temporary
working platform within the active marine works areas surrounded by silt curtain.
2.6.1
ATCL
2.6.1.1
The ATCL provides transport links of about 5km in length connecting
Tung Chung, Airport and HKP Island. The carriageway adopts a single
2-lane configuration.
2.6.1.2 A summary of the key ATCL elements is
given in Table 2.8 below.
Table 2.8 Summary
of Key ATCL Elements
ATCL Elements |
Descriptions |
1.
ATCL alignment (in total approx. 5km) |
·
At-grade sections: 2,660m (approx.) ·
Land viaduct sections: 880m (approx.) ·
Marine viaduct section: 230m (approx.) ·
The spur line of approximately 980m
connecting to the Academy Station |
2.
Stations of ATCL |
·
Tung Chung Central (TCC) Station
(elevated) ·
ECSA-N Station (at-grade) ·
ECSA-S Station (at-grade) ·
Approach Lights (AL) Station
(at-grade) ·
Academy Station (at-grade) ·
With provision of lavatories |
3.
Other associated works |
·
Connecting works to planned ACL ·
Walkway and footbridges at ECSA-N
Station, ECSA-S Station, and connection with at-grade road section and land viaduct
section near ACL ·
Depot for maintenance, storage, charging
and cleaning of zero emission vehicles ·
Reprovision / realignment of the
affected facilities, such as bus stop, cycling track, footpath, etc. ·
Diversion / reprovision of affected
utilities ·
Plant room(s) |
2.6.1.3
The proposed ATCL is to connect HKP Island, Airport Island and
Tung Chung Town Centre via a dedicated road link. According to the transport demand and
the nearby public transport services, the stations are located at the potential
high visitor numbers for enhancing transit transport connectivity.
2.6.1.4
Five stations are set along the ATCL, namely (TCC Station, ECSA-S
Station, ECSA-N Station, AL Station
and Academy Station). Approximately
two lookout points will be introduced along the ATCL walkway for visitors to
enjoy the scenic view of the sea, HKP Island and Tung Chung.
2.6.1.5
Generally, the land viaduct, at grade road and marine viaduct are
proposed for the ATCL. The ATCL
except the short marine viaduct section will sit on the existing land along the
shoreline with minimal land formation works to minimize the amount of fill and
cut required. There will be no land
reclamation works required for the construction of the at-grade section of the
ATCL. Temporary working platforms is
proposed to sit on the existing seawall and remain above the High Water Mark and no seabed will be affected.
2.6.1.6
For marine viaduct section, no open sea dredging will be carried
out to minimise environmental impacts.
No off-site work areas is proposed for the Project. The details of the ATCL alignment and
facilities is provided in the below sections.
ATCL –
between Tung Chung Central Station and Airport Island (Land and Marine Viaduct
Section)
2.6.1.7 The ATCL land
viaduct originated from TCC Station will deck over part of the slip road from
North Lantau Highway (NLH) to Tung Chung Waterfront Road (TCWR), the cycling
track and associated walkway along Tat Tung Road and the landscape between
them, with a total length of approximately 290m.
2.6.1.8 For the
marine section, the viaduct, across the Tung Chung Navigation Channel, is
approximately 230m in length, supported by bridge concrete
piers. The location, number and size of piles and pile caps of
bridge piers of the ATCL will be similar to / close to the NLH, in order to
maintain the same marine navigation channel dimension as existing. The pier shape of the marine section
will be designed in a similar form of the NLH to provide a consistent appearance
between the two bridges. The deck
level will also be in line with the NLH.
The purpose of adopting this alignment for this marine viaduct is to
minimise the change on the flow regime along the Tung Chung Navigation Channel,
hence minimise the environmental impacts on water quality and marine ecology.
2.6.1.9
TCC Station is an elevated platform potentially connecting to One
Citygate with a relatively simple and lightweight appearance when comparing
with the surrounding buildings, to minimise the visual impact. The station is a covered area with
canopies in light colour materials and glass to allow cross ventilation and
natural light.
ATCL –
between Scenic Hill and ECSA (At-grade Section)
2.6.1.10
The ATCL, originating from TCC Station, will continue to run
elevated across the Tung Chung Navigation Channel and reach the Airport Island
near the base of Scenic Hill where it will then change to an at-grade road and
continue along the east shore of the Airport Island. Two intermediate stations, namely
ECSA-S Station and ECSA-N Station, will be introduced with passenger access
facilities to connect to the nearby leisure and commercial areas. These stations will be covered by a
canopy which provides a simple shelter against inclement weather, and minimises
the visual impact viewing from the sea.
The covered footbridges will be designed with canopies and mesh which
allow cross ventilation and natural light to the internal space.
ATCL – between
ECSA and ACL (At-grade Section)
2.6.1.11
ATCL will continue to run along shoreline and one intermediate station,
namely AL station, will be located at this section. The proposed alignment will not
interfere with the current anemometer station at Hong Kong Observatory (HKO).
ATCL –
Integration with ACL (Land Viaduct Section)
2.6.1.12
The at-grade ATCL carriageway that runs along the shore at Airport
Island will change to elevated viaduct form as it is approaching HKP Island in
order to connect to the elevated ACL.
On the other side, to connect with the Academy Station, an at-grade spur
line will run from the HKP Island and connect with the Academy Station. To provide pedestrian access between the
at-grade spur line and the elevated viaduct to ACL, a link footbridge equipped
with staircase and lift is introduced.
ATCL – A Spur
Line to Academy Station (At-grade Section)
2.6.1.13
An at-grade spur line of ATCL, including carriageway and walkway
with the same configuration as typical ATCL design, is proposed to connect to
southern promenade of HKP Island and terminated at the Academy Station. The Academy Station is introduced as the
terminal station of the spur line.
The position of the station is assumed to be at-grade and near the
southern promenade of the HKP Island.
Depot
2.6.1.14
A depot provides storage for zero emission vehicles where
maintenance has to be carried out ensuring the service and availability of the
zero emission vehicle system is not compromised. The depot does not involve polluting
process such as paint spraying and dry polishing activities. Vehicles that are not required for the
operation, can be stored in the depot.
Facilities provisions include essential and emergency vehicle repair and
maintenance workshop, vehicle storage area, charging area, cleaning area, and
other ancillary facilities such as equipment storage room, E&M facilities,
etc.
2.6.2
Marine Facilities
2.6.2.1
The proposed marine facilities are intended to enable marine
connectivity of the HKIA which offers leisure and tourism. The proposed marine facilities
will provide a pier (SKYCITY Pier) and berthing facilities for pleasure
vessels. Commercial fishing is
prohibited at the marine facilities.
SKYCITY Pier
2.6.2.2
The pier is proposed at the seaside adjacent to the south of the SkyPier
Terminal Bonded Bridge and ACL, and also in the vicinity of SKYCITY. Situated between the ACL and the
berthing facilities, the pier with two berths is proposed to provide marine
transport services associated with leisure and tourism. Landside facilities, such as toilets and
storage room, etc, will be provided in a building block in order to facilitate
pier’s operation. The marine
transport services will adopt fuel-powered marine vessels in the first place,
and zero emission vessels in the future subject to technological maturity and
market availability. The pier
consists of floating pontoon supported by guide piles. The pier will be managed by AAHK and/or
its agent. The pier is proposed to
accommodate vessels to take passengers from the Airport Island to tourist
attractions in Hong Kong, and is estimated to generate 30 vessel movements per
day.
Berthing
Facilities
2.6.2.3
The berthing facilities are developed with a view to promote
tourism and form part of the leisure offerings in SKYCITY. The facilities will be managed by AAHK
and/or its agent under pre-booking and pre-approval of services. Incoming vessels will travel through the
navigation channel and will make a turn to berth on one of assigned berth at
finger pontoons. Pleasure vessels
are expected to stay overnight given the parking nature of the berthing
facilities, projected to have a maximum berthing period of 1 month. The projected future peak marine traffic
activity of pleasure vessels to/from the proposed berthing facilities is anticipated
to be 44 vessel movements per day. In
addition, the marine vessels using the berthing facilities will be required to
turn off the engines when they are parked at the berthing facilities. Significant marine vessel emission is
not expected within the water channel, and the marine facilities would only
generate limited air quality impact.
Appropriate mitigation measures could be considered to minimise the
potential impacts on the air sensitive receivers in the vicinity of the marine
facilities.
2.6.2.4
The berthing facilities will have four floating platforms to
provide the general public tentatively 73 berths for medium-to-small size
pleasure vessels. The walkways and
fingers of the floating platforms will consist of concrete floating pontoons
supported by guide piles. The
northernmost section of the floating platforms will consist of wave attenuator
using concrete floating pontoons with wave attenuation function to reduce the
wave condition inside the bay area.
A gangway is proposed to connect the landside and seaside facilities.
2.6.2.5
For the landside facilities, a security gate and a kiosk area will
be located on the landside to control the entrance and departure to the
berthing facilities. Waiting areas
will be allocated on the landside to provide space for the users to transit to
airport. In order to facilitate the
operation of the berthing facilities, a 6m high one-storey building block (8m x
67m) is proposed to provide supporting facilities, such as shower and toilet
facilities, locker and changing room, etc. for the services users.
2.7.1
ATCL
Marine Viaduct
2.7.1.1 The construction of marine viaduct will not involve open sea dredging
and no excavated materials from the confined pile casings will be in direct
contact with the open sea water. Construction
of bored piles and pile caps for four marine bridge piers will be carried out
at the marine viaduct section of the ATCL, the construction method illustrated
in Figure 2.5(a).
Substructure Works (Piles and Pile Caps)
2.7.1.2 Construction of the marine viaduct’s foundation will generally involve
the use of in-situ bored piles founded on bedrock. After deploying the silt curtain to
surround the active marine works area, temporary working platform will then be
installed. After installation of temporary working
platform and deployment of silt curtain, piling equipment will be set up on a temporary working platform. Over the marine viaduct section, bored piling works will be conducted. Upon completion of bored piles, pile cap construction
will be commenced. Details are
provided below.
2.7.1.3 Temporary working platforms will be either
installed by (i) supporting casing or (ii) supporting casing reinforced by mini-piles,
subject to the site conditions.
2.7.1.4 Temporary Working
Platform by Supporting Casings: Silt curtain will be deployed before the installation
of temporary working platform and piling works as preventive measures for
containing and minimising sediment plume spread. The temporary foundations for the
temporary working platform will be positioned to the seabed by vibratory
hammer. The temporary working
platform will be prefabricated on barge and put on the temporary supporting
casings for installation. All
piling plants will be set up on the temporary working platform.
2.7.1.5 Temporary Working
Platform by Supporting Casings reinforced by Mini-piles: Silt
curtain will be deployed before the installation of temporary working platform
and piling works as preventive measures for containing and minimising sediment
plume spread. The temporary foundations
for the working platform will be positioned to the seabed by piling rig until
reaching rockhead and rock socket. The
materials inside the casing will be removed by flushing the borehole by
compressed air. Reinforcement will
be installed in the bored hole followed by grouting by tremie method. Temporary working platform will be
prefabricated on barge and put on the temporary supporting casings. All piling plants will be set up on temporary
working platform.
2.7.1.6 Bored Piles Construction: The pile construction will be carried out through placing a steel pile
casing at the pier site within the silt curtain, in which the siltation and
turbidity will be contained within casing and silt curtain. The silt curtain can reduce the
dispersion of suspended solid. A
funnel would be placed at the top of pile casing during excavation. This construction method would create a
confined environment for excavation, which could minimise the release of
suspended solids into the water column and reduce the risk of disturbance to
the seabed and the adjacent marine environment. Mechanical Grab and Reverse Circulation
Drill will be used inside the casing for excavation of sediments and rocks
respectively. As the pile construction will be confined
in the pile casing, no materials will be in direct contact with the open sea
water, hence to protect the water body, marine ecology and minimise the
fisheries impact. After the bored
piles construction, the temporary
foundations and the temporary working platform shall be removed to enable
construction of the pile cap and subsequent works.
2.7.1.7 Pile Cap Construction: Upon completion of bored
piles, the marine pile caps above high-tide level
will be installed through construction of precast pile cap shell, which is a
watertight enclosure. The precast
pile cap shell will protect the sides and bottom of the pile cap from ingress
of sea water during construction and made proper covers during its service
life. Additionally, rebar fixing,
and concreting works will be carried out inside the precast pile cap shell. Any seawater inside the precast pile cap
shell will be pumped out and the precast pile cap shell will prevent ingress of
seawater to create a dry working environment throughout the construction
process of pile cap. The rebar
fixing and concreting works will be subsequently carried out inside the precast
pile cap shell. There are 4 marine
bridge piers under the Project.
2.7.1.8 Pre-fixed steel reinforcement cage with permanent casing will be
installed inside the precast pile cap shell before concreting. Concrete from existing batching plants
will be delivered to the piling site by concrete trucks via marine route using
ro-ro barge for concreting the marine piles.
Superstructure Works (Pier
Columns, Bridge Deck and the rest of the road furniture)
2.7.1.9 Pier Columns: Construction
of pier columns could be carried out by (i) cast in-situ or (ii) precast method
as discussed in Section 2.5.4.2.
2.7.1.10 Bridge Deck: For the
construction of bridge deck, either precast construction method or in-situ construction method will be adopted as discussed in Section 2.5.4.3.
Land Viaducts
2.7.1.11 Bored Pile Construction: Percussive piling and bored piling are the
commonly piling methods adopted for construction. In comparison with percussive pilings,
bored piling construction generates less noise and vibration. To minimise the noise impact generated
from the Project, bored pile foundation will be adopted for land section of
ATCL viaduct. Predrilling at the
centre of each bored pile location will be carried out into the designed grade
of rock to form the rock socket. Pile
construction with concreting works will be conducted. Rebar lowering down and concreting works
while temporary casing is retrieved.
Minor excavation shall be required for the pile cap.
2.7.1.12 Pile Cap Construction: Similar to the marine viaduct section, cast
in-situ bored piles will be adopted for the foundation of the land viaduct and
the elevated platform deck. The
land pile caps will be embedded below ground level. Precast concrete shell will be installed
for the construction of the pile caps.
Concrete from existing batching plants will be delivered to the site by
concrete trucks via land route.
2.7.1.13 Pier Columns: Similar to the marine viaduct, the
construction of pier columns in land viaduct could be carried out by (i) cast
in-situ or (ii) precast method. (Section 2.7.1.9 refers)
2.7.1.14 Bridge Deck: Similar to the marine viaduct, either
precast construction method or in-situ construction method will be adopted. (Section
2.7.1.10 refers)
At-grade Road (including the spur line to Academy
Station)
2.7.1.15 The ATCL will
have at-grade sections of road. The typical at-grade road section will be
constructed by minor excavation for laying utilities and road drainage. Trench will be excavated using open-cut method and light shoring will be
provided for trench excavation.
2.7.1.16 For works near the seawall, existing rock
amour will need to be removed prior to construction. Temporary working platforms shall be
built to support excavation and subsequent construction works to avoid any
transfer of significant loadings to seawall.
2.7.1.17 Minor seawall modification works would be
required at sections where the proposed ATCL will be clashing with the seawall.
2.7.1.18
For this at-grade road section, the below three construction
methods are proposed to suit the designed alignment and the site conditions,
and to minimize the impact on the new ATCL on the existing seawall.
Method 1 – For
normal at-grade road
2.7.1.19
Method 1 is proposed if
the edge of the footpath is not extended beyond the seawall cope line. The excavation works will be carried out
by open cut method for underground utilities laying, and followed by
backfilling. Lastly, the concrete
or bituminous pavement will be constructed. The construction methods are illustrated
in Figure 2.5(b).
Method 2 – For
at-grade road with cantilevered slab
2.7.1.20
Method 2 is proposed if the edge of the footpath is less than or
equal to approximately 2m beyond the seawall cope line but above the High Water
Mark. For the construction of cantilever slab
beyond the seawall cope line, rock armours that clash with the cantilever slab would be removed by an excavator. Afterwards, the excavation would be
carried out by open cut method for underground utilities laying and construction
of the cantilever slab would be carried out using cast in-situ concreting
method. After reinstating the
removed rock armours, backfilling and construction of the road pavement will be
carried out. The
construction methods are illustrated in Figure 2.5(c).
Method 3 – For
at-grade road with cantilevered slab using Socketed H-piles
2.7.1.21
Method 3 is considered if the edge of the footpath is extended
more than approximately 2m beyond the seawall cope line. In Method 3, the ATCL beyond the seawall
cope line but within and above the High Water Mark will
be formed by beams and slabs which are supported by socketed H-piles. Firstly, the existing rock armours will
be removed and concrete blocks will be placed to form a working platform. Then, a silt curtain will be deployed and
construction of the socket H-piles will be carried out by piling machine. The piles will be protected from
corrosion and marine action by the left-in steel casing and applied corrosion
protective coating. After installation
of the H-piles, the excavation works behind the seawall cope line by open cut
method for underground utilities laying will be carried out. The pile cap and deck will then be
constructed. After reinstating the
removed rock armours/concrete blocks and backfilling, the removal of silt
curtain and construction of road pavement will be carried out. The construction methods are illustrated
in Figure 2.5(d).
2.7.1.22 All three methods
will be utilized along the ATCL and to different extents, where some sections
will require certain options in greater proportion than others.
Depot
2.7.1.23 The proposed depot would be constructed over the Scenic Hill Tunnel and
part of the box culvert leading to the outfall. Since the existing tunnel has been
designed for supporting road pavement on top of the tunnel, no additional
structure is required to support the parking space of autonomous vehicles.
2.7.1.24 Minor site formation works and shallow excavation would be carried out
at the proposed parking area. The
soil would then be compacted to the required density. The concrete pavement would be
constructed by in-situ concreting.
2.7.1.25 The excavation for the construction of raft footing would be carried out by open cut excavation. The raft footing would be constructed by in-situ concreting as well. The depot facilities would be
constructed on the raft footing.
Footbridge
2.7.1.26 Three footbridges which are located at the ECSA-N Station, ECSA-S Station
and near the land viaduct connecting to ACL respectively are proposed. Only footbridge at ECSA-N Station, which
spans over the existing Hong Kong Link Road (HKLR), shall be constructed over
HKLR. The structural form consists
of steel prefabricated with socketed H-pile that shall be driven.
2.7.1.27 The construction method of the footbridge at ECSA-N Station shall entail
predrilling and construction of piles. The pile caps and bridge piers will be
performed by in-situ concreting. Then,
the footbridge segments will be prefabricated and delivered on site, on site
welding at the temporary working platform will be carried out. Upon construction of staircases, lift
tower, canopy and street furniture, the temporary working platform shall be
removed.
2.7.1.28 The construction method of the footbridge at ECSA-S Station and the
footbridge near the land viaduct connecting to ACL shall entail the same
methodology as construction method of the footbridge at ECSA-N Station except
that the temporary platform will not be used.
2.7.2
Marine Facilities
2.7.2.1 The proposed sequence of the construction
activities for the marine facilities, which include the SKYCITY Pier and berthing
facilities (i.e. floating platforms, wave attenuator, fixed ramp and gangway,
etc.) are illustrated in Figure 2.5(e).
SKYCITY Pier
2.7.2.2 The construction sequence will start with
installation of piles for gangway and pier, then construct cast in-situ pile
cap and deck structure of the pier.
Lastly, installation of gangway and fenders on the sides of the pier
will be carried out. The gangway
will be assembled/ installed on the constructed deck structure.
2.7.2.3 A temporary working platform is needed for piling construction works and
will be constructed after the silt curtain deployed. The temporary working platform will be
erected and assembled at piling locations by deploying derrick lighter/ crane
barge.
2.7.2.4 For the floating pontoon(s), the guide
piles will be driven into seabed/rockhead level by piling machine set up on the
temporary working platform. The floating
pontoons for the floating platforms will be constructed at an existing
fabrication yard outside Hong Kong, and will arrive at the project site via
marine access. The pre-fabricated floating pontoons
will be lifted and secured segment by segment with guide piles by derrick
lighter/ crane barge.
2.7.2.5 For the socketed
H-piles of SKYCITY Pier, a temporary working platform will be constructed after the silt curtain
deployed. For the construction of
piles, the casing will be sunk down to the bedrock using drilling rig set up on
the temporary working platform, the marine-based sediment will be excavated and
extracted from top of the bored hole. Then, the socketed H-piles will be
installed by crane barge. Afterwards,
the temporary working platform shall be modified at the pile cap locations by
deploying derrick lighter for pile cap construction. The steel wall panels and base panels of
the temporary working platform will act as the wall and base to form the entire
formwork of the pile cap. Sealing
panels will be provided at any joints of the steel formwork to prevent any
leakage of concrete during pouring. Lastly, concrete will
then be poured by a concrete pump truck on a flat top barge. In order to avoid the impacts on the
water quality, fisheries and marine ecology, no open sea dredging will be involved. To further prevent any concrete from
entering into the sea, the flat top barge will be located as close as
practicable to the temporary working platform. If necessary, impervious sheet will be
placed between the flat top barge and the temporary working platform.
2.7.2.6 The building blocks for SKYCITY Pier is located
in landside of the marine facilities and is a reinforced concrete buildings
supported by raft foundation. Despite
excavation is required for the construction of the raft foundation, sheet
piling would be used to support the excavation and avoid the potential ground
water pollution. In-situ casting
approach would be adopted to suit site conditions.
Berthing
Facilities
2.7.2.7 The construction methods are similar to the
relevant items of SKYCITY Pier, which includes the floating pontoons on guide
plies for the floating platform of the berthing facilities (Section 2.7.2.4 refers), wave attenuator on socketed H-piles with pile caps to be
constructed using the modified temporary working platform (Section 2.7.2.5 refers), and reinforced concrete building blocks in landside (Section 2.7.2.6 refers).
2.7.3
Maintenance Dredging at Marine Facilities
2.7.3.1 Maintenance dredging within the proposed marine facilities would be
required regularly to maintain safe navigable water depth close to the existing
seabed level. Maintenance dredging
will be carried out in every two years.
The maintenance dredging would be required during operation of the
proposed marine facilities. Maintenance
dredging would maintain the seabed level within the area of marine facilities
at about the current level to provide enough depth for the designated type of
marine vessels to safe maneuverer and berth. In order to restore the seabed level to
the current level every two years, maximum 500mm depth marine sediment will be
dredged during maintenance dredging. The maximum working rate for maintenance
dredging is assumed to be 40m3 per hour and only one closed grab
dredger will be working in any time.
2.8.1.1 The construction works of the Project will be tentatively commenced in Q4
2025 and be completed in 2027/2028. A tentative construction programme for
the Project is provided in Appendix 2.1. A summary of the key construction works
period is listed below.
·
ATCL (including ATCL alignment, stations and other associated
works)
Tentative construction period: Q4 2025 to Q1 2028
Tentative commissioning year:
2028
·
Marine Facilities (including SKYCITY Pier and berthing facilities)
Tentative
construction period: Q2 2026 to Q4 2027
Tentative commissioning year:
2028
2.9.1.1 Key concurrent projects in the vicinity of the Project are identified
and summarised in Table 2.9 and their locations are shown in Figure 2.6. Potential cumulative impacts from these concurrent projects (if any) are assessed in this
EIA study.
Table 2.9 Summary
of Concurrent Projects
|
Project
Name |
Construction
Commencement Dates |
Construction
Completion Dates |
Considered
in the EIA Study |
|
ID |
Construction
Stage |
Operational
Stage |
|||
1 |
Tung Chung New Town Extension (TCNTE)[1] |
2018 |
2030 |
Outside
assessment area |
|
2 |
11 SKIES [2] |
2017 |
2023 |
No |
Yes |
3 |
Commercial Developments at ECSA [2] |
2025 |
2035 |
Yes |
Yes |
4 |
Development of Airport-related Supporting Uses at HKP Island [2] |
2021 |
2030 |
Yes |
Yes |
5 |
Tung Chung Line Extension [3] |
2023 |
2029 |
Yes |
Yes |
6 |
Planned Visitation Church Development[4] |
2023 |
2026 |
Yes |
Yes |
7 |
Airportcity Link[2] |
2022 |
2025 |
No |
Yes |
8 |
SkyPier Terminal Bonded Bridge[2] |
2020 |
2023 |
No |
Yes |
9 |
Commercial Development-cum-Public Market in Tung Chung Area 6[5] |
Programme
not available |
Yes |
Yes |
|
10 |
Planned Commercial Development[2] |
Programme
not available and under planning |
Yes |
Yes |
Note:
[1] Source: Project website
of Tung Chung New Town Extension (TCNTE)
(https://env.tcnte.hk/
)
[2] Source: Information
provided by AAHK
[3] Source: Tung
Chung Line Extension EIA Report (Register No.: AEIAR-235/2022)
[4] Source: Information
provided by the Project Proponent of the Visitation Church during
liaison meeting
[5] Source: Information
provided from Sustainable Lantau Office/CEDD
2.9.1.2
According
to relevant information from the project website of TCNTE (https://env.tcnte.hk/) under the Civil Engineering and Development Department (CEDD),
the reclamation and advance works have been commenced in 2018 and the site
formation and infrastructure works have been commenced in 2021. With reference to the approved EIA
Report (Register No.: AEIAR-196/2016), the tentative completion date will be
2030. Tung Chung New Town Extension
(TCNTE) is located more than 500m from the Project boundary. Considering the distances from the
Project, significant environmental impacts with the Project is not anticipated.
2.9.1.3
The 11 SKIES
including the hotel, retail, dining, entertainment developments which will be
completed by 2023. Therefore, the
operation of 11 SKIES would be considered as an ASR in the construction dust
impact assessment of the Project. No other environmental impacts would be
anticipated during construction and operational phases.
2.9.1.4
Commercial
developments at ECSA including office and hotel developments are located next
to the ATCL alignment, ECSA-N Station and ECSA-S Station. Considering the ECSA commercial developments
will be constructed concurrently with the Project, the cumulative construction
dust impact has been evaluated in this EIA study. No other environmental impacts would be
anticipated during construction and operational phases.
2.9.1.5
Development of airport-related supporting uses at HKP
Island including the development of automated car parks, aviation academy
campus, data centre and Refuse and Recycling Facility (RRF). The automated car parks will be located
to the east of the Passenger Clearance Building of the HKP providing parking
spaces for the travellers and users of the HZMB. The proposed aviation academy campus
will comprise training facilities with central air-conditioning. Moreover, the data centre will be
located at the south eastern side of the HKP and the RRF will be located at the
south-eastern side of the HKP. Considering
the building development will be constructed concurrently with the Project, the
cumulative construction dust impact has been considered in this EIA study. No other environmental impacts would be
anticipated during construction and operational phases.
2.9.1.6
Tung
Chung Line Extension is located about 250m away the site boundary. With reference to the approved EIA Report
(Register No.: AEIAR-235/2022), the tentative completion date will be 2029. Considering the development will be
constructed concurrently with the Project, the cumulative construction and
fixed noise impacts and construction dust impact has been considered in this
EIA study. No other environmental
impacts would be anticipated during construction and operational phases.
2.9.1.7
In addition, planned visitation church is
located next to the TCC Station of the ATCL. The site area of planned visitation church
is approximately 0.22 hectare. Due
to small-scale development and the concurrent period would be the final
construction stage of the planned visitation church, it is anticipated only interior
fitting out and minor exterior works will be carried out concurrently, the
environmental impact from this development would be limited. Therefore, significant cumulative
environmental impacts with this development are not anticipated.
2.9.1.8
Construction
of ACL and SkyPier Terminal Bonded Bridge will be completed by 2025 and 2023
respectively, and afterward come into operation. Since the constructed bridge piers and
traffic induced by these two projects are considered in air quality and water
quality impact assessments, the operation of these two developments have been considered
in this EIA study. However, significant cumulative environmental
impacts with this development are not anticipated.
2.9.1.9
A commercial development-cum-public market
in Tung Chung Area 6 is proposed and located near the existing Tung Chung
Station. The potential development
is relatively small with approximate 0.6 hectare and only includes a commercial
building. The development programme
has yet confirmed during the course of this EIA study. Considering limited environmental impacts
would be arisen from a small-scale commercial building development, significant
cumulative environmental impacts is not expected from this project.
2.9.1.10
The
planned commercial development near the SkyCity is still under planning. The schedule on commercial development
have yet to be confirmed. The
potential development is relatively small with area less than 1 hectare and
only includes a commercial building.
Considering limited
environmental impacts would be arisen from a small-scale commercial building
development, significant cumulative environmental impacts with this development
are not anticipated.
2.10.1.1
The Project Profile was submitted to the
EPD on 15 Jun 2021, and was exhibited for public consultation between 16 Jun
2021 to 29 Jun 2021. 5 written comments, concerning the needs of the Project and its
potential impacts in water quality, waste management, ecology and fisheries, were received. The
environmental concerns and the responses are summarised in Table 2.10. The concerned impacts have been assessed in this EIA study
(Chapters 5, 6, 7 and 8), and no adverse impacts are anticipated from this
Project.
Table 2.10 Summary
of Concerns and Responses
Key
Concerns |
Responses |
Romer’s tree frog and greenhouse frog |
To avoid the loss of habitat for Romer’s Tree Frog, excavation
works for the selected alignment of ATCL will not encroach Scenic Hill.
To further minimise potential impact to Romer’s Tree Frog,
screening for greenhouse frog, including adults and eggs, in soil and
landscape materials is recommended to be carried out before used for
backfilling/landscaping purpose.
Detailed assessment could be referred to Section 7.5 of this EIA report. |
Coastal environment |
The ATCL, except the marine viaduct section, will sit on the
existing land along the shoreline with minimal land formation works. During the construction phase,
there will be no land reclamation works required for the at-grade section of
the ATCL. Temporary working
platforms are proposed to sit on the existing seawall and remains above the High Water Mark. The associated water and ecology
impacts, have been assessed in Section
5.9 and Section 7.6
respectively and no adverse impacts are anticipated. |
Waste management on C&D materials |
The C&D materials from the proposed project shall be
properly stored, transported and disposal of at the designated locations. The tentative designated locations and
transportation routes have been considered in Section 6.4. A
real-time GPS tracking system connecting to the internet or intranet allowing
efficient tracking and monitoring to avoid illegal dumping or landfilling of
C&D materials has been recommended in Section 6.5. |
Water quality impacts to Tung Chung Bay/River |
Impact assessment to the adjacent sensitive receivers, including
Tung Chung Bay, has been conducted in Section
5. Appropriate preventive and mitigation measures are recommended
to minimise the potential water quality impact induced by the Project. Unacceptable water quality impact from
the construction works under the Project is not expected. Water quality impact to Tung Chung
River which is located further away from the Project is not expected as
well. |
Potential impact on mangrove skimmer species |
Mangrove communities are recorded in Tung Chung Bay, San Tau and
Tai Ho Wan which are more than 1km from the Project site, as such
unacceptable impacts to the mangrove communities including Mangrove skimmer
species are not anticipated. |
Potential impact on CWD |
Impact assessment on CWD has been conducted as discussed in Section 7.6 of the EIA Report.
Mitigation measures have been recommended as stated in Section 7.9 of the EIA Report. |
Needs of the Project |
The needs of the Project are to enhance the connectivity from
Airport Island to Tung Chung through Autonomous Transportation System. Also, the marine facilities are
to provide marine connectivity of yachts and ferries to the Airport Island. The needs of the Project have been discussed
in Section 2.2. |
Potential marine ecological impacts on corals and fisheries |
Impact assessment to marine ecology and fisheries has been
conducted as discussed in Section 7
and Section 8 of the EIA
Report. Unacceptable impacts to
marine ecology and fisheries are not anticipated. Water quality mitigation measures
proposed in Section 5.9 will be
sufficient to mitigate the impact on marine ecological resources, including
corals, and fisheries (e.g. control of dredging rate for maintenance
dredging, deployment of cage-type silt curtain during construction and
maintenance dredging, good site practice). |
2.10.1.2
During the course of the EIA study,
AAHK reached out to different stakeholders through meetings,
briefings-cum-airport visits and webinars, including community groups, members
of District Councils in the airport’s five neighbouring districts, business chambers,
professional groups, unions and youth organisations. AAHK introduced the Airport City
strategy, including the ATCL Project, to the stakeholders and sought their
feedback on the Project. No
environmental issue in relation to the ATCL Project was raised during the
outreach. On 27 July 2021, AAHK
briefed Islands District Council members on Airport City developments including
the ATCL Project, receiving positive views from the members, who opined that
the ATCL Project would provide a convenient and environmentally friendly means
of transport to the Lantau District.