CONTENTS

 

6........... WASTE MANAGEMENT. 6-1

6.1         Introduction. 6-1

6.2         Environmental Legislation, Standards and Guidelines. 6-1

6.3         Assessment Methodology. 6-5

6.4         Identification and Evaluation of Waste Management Implications. 6-7

6.5         Mitigation Measures. 6-22

6.6         Residual Impacts. 6-30

6.7         Environmental Monitoring and Audit 6-30

6.8         Conclusions. 6-31

 

TABLES

 

Table 6.1         Key Project Elements and associated Waste Generation. 6-7

Table 6.2         Estimated Amount of Inert C&D Materials to be Generated during Construction Phase  6-9

Table 6.3         Estimated Amount of Inert C&D Materials to be Reused On-site during Construction Phase  6-9

Table 6.4         Summary of Chemical Screening Results (Land-based Sediment) 6-11

Table 6.5         Summary of Biological Screening Results (Land-based Sediment) 6-11

Table 6.6         Summary of Chemical Screening Results (Marine-based Sediment) 6-12

Table 6.7         Summary of Biological Screening Results (Marine-based Sediment) 6-12

Table 6.8         Summary of Disposal Options. 6-13

Table 6.9         Summary of Quantities of Waste Generated during Construction Phase. 6-17

Table 6.10       Tentative Transportation Routing for Different Types of Wastes. 6-19

 

 

FIGURES

 

Figure 6.1        Actual Sediment Sampling Locations, Updated Excavation Area, Location of Marine Sediment and Location of Stockpiling Area

Figure 6.2a      Transportation Route for Wastes (Page 1 of 2)

Figure 6.2b      Transportation Route for Wastes (Page 2 of 2)

 

APPENDICES

 

Appendix 6.1  Approved Sediment Sampling and Testing Plan

Appendix 6.2  Summary of Chemical Screening Test Results

Appendix 6.3  Summary of Biological Screening Test Results

Appendix 6.4  Estimated Volume of Land-based Sediment to be Generated

Appendix 6.5  Estimated Volume of Marine-based Sediment to be Generated

 


6                         WASTE MANAGEMENT

6.1                   Introduction

6.1.1.1       This section identifies potential waste that may arise from the construction of the Project, and assesses potential environmental impacts associated with their handling and disposal.  The operation of the Project is unlikely to produce a large quantity of waste, and adverse environmental impacts are therefore not expected.

6.1.1.2       Options of reuse, minimisation, recycling, treatment, storage, collection, transport and disposal of such wastes were examined.  Procedures for waste reduction and management were considered, along with recommendations for environmental control measures to ensure that negative impacts are avoided or minimized when appropriate.

6.2                   Environmental Legislation, Standards and Guidelines

6.2.1             General

6.2.1.1       The criteria and guidelines for assessing waste management implications are outlined in Annexes 7 and 15 respectively in the Technical Memorandum on Environmental Impact Assessment (EIAO-TM) and EIA Study Brief (No. ESB-342/2021).

6.2.1.2      The following legislation is relevant to the handling, treatment and disposal of waste in HKSAR:

·               Waste Disposal Ordinance (Cap 354);

·               Waste Disposal (Chemical Waste) (General) Regulation (Cap 354C);

·               Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap 354N);

·               Land (Miscellaneous Provisions) Ordinance (Cap 28);

·               Public Health and Municipal Service Ordinance – Public Cleansing and Prevention of Nuisances Regulation (Cap 132BK);

·               Dumping at Sea Ordinance (Cap 466);

·               Practice Note for Authorized Persons and Registered Structural Engineers on Management Framework for Disposal of Dredged/ Excavated Sediment (PNAP ADV-21); and

·               Works Bureau Technical Circular (WBTC) No. 12/2000 Fill Management

 

Waste Disposal Ordinance (Cap 354)

6.2.1.3      The Waste Disposal Ordinance (WDO) prohibits unauthorised disposal of wastes.  Construction waste is defined under the Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap 354N) as any substance, matters or thing that is generated from construction work and abandoned, whether or not it has been processed or stockpiled before being abandoned.  It does not include any sludge, screening or matter removed or generated from any desludging, desilting or dredging works.  Under the WDO, wastes can only be disposed of at sites licensed by the Environmental Protection Department (EPD).  A breach of the WDO can lead to a fine and/or imprisonment.  The WDO also stipulates the requirements for issuing licenses for the collection and transportation of wastes.

Waste Disposal (Chemical Waste) (General) Regulation (Cap 354C)

6.2.1.4      As defined in Schedule 1 of this Regulation, chemical waste includes any scrap material or unwanted substance present in such a form, quantity or concentration that causes pollution or poses an environmental or health risk.

6.2.1.5      Under this Regulation, a person shall not produce or cause to be produced chemical wastes unless he/she is registered with the EPD.  Any person who contravenes this requirement commits an offence and is liable to a fine and/or imprisonment.  

6.2.1.6      Chemical wastes must be treated, utilising on-site plant licensed by the EPD or have a licensed collector to transport the wastes to a licensed facility.  For each consignment of wastes, the waste producer, collector and disposer of the chemical wastes must sign all relevant parts of a computerised trip ticket.  The system is designed to trace wastes from production to disposal

6.2.1.7       The Regulation also prescribes the labelling and warning signs to be displayed on site along with the storage facilities.  Moreover, the waste producer is required to prepare and make available written emergency procedures for spills, leaks, or accidents arising from storage of chemical wastes in order to minimise pollution and danger to human health and life.  It is also necessary for waste producers to provide employees with training on such procedures.

Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap 354N)

6.2.1.8      Under this Regulation, wastes can only be disposed of at designated waste disposal facilities licensed by the EPD.  For construction work with a value of more than HK$1 million, the main contractor is required to establish a billing account at the EPD before transporting the construction waste to the designated waste disposal facilities (for example, landfill and public fill).  The vessels for delivering construction waste to the Public Fill Reception Facilities (PFRF) require prior approval from the Public Fill Committee (PFC).  Any breach of these regulations may lead to a fine and/or imprisonment.

Land (Miscellaneous Provisions) Ordinance (Cap 28)

6.2.1.9      The inert portion of Construction and Demolition (C&D) materials (including rocks, soil, broken concrete, building debris, etc.) may be taken to Public Fill Reception Facilities (PFRFs).  PFRFs usually form part of land reclamation schemes and are operated by the Civil Engineering and Development Department (CEDD) and others.  The Land (Miscellaneous Provisions) Ordinance requires individuals or companies who deliver public fill to PFRFs to obtain Dumping Licenses.  The licenses are issued by CEDD under delegated authority from the Director of Lands.

Public Health and Municipal Service Ordinance – Public Cleansing and Prevention of Nuisances Regulation (Cap 132BK)

6.2.1.10  The Regulation provides further control on illegal tipping of wastes on unauthorised (unlicensed) sites.  Illegal dumping of wastes can lead to a fine and imprisonment.

Dumping at Sea Ordinance (Cap 466)

6.2.1.11  This Ordinance came into operation in April 1995 and empowers the Director of Environmental Protection (DEP) to control the disposal and incineration of substances and particles at sea for the protection of the marine environment.  Under the Ordinance, a dumping permit from the DEP is required for the disposal of regulated substances within and outside the waters of Hong Kong.  The permit contains terms and conditions which include the following specifications, but not limited to:

·               Type and quantity of substances permitted to be dumped;

·               Location of the disposal grounds;

·               Requirement of equipment for monitoring the disposal operations; and

·               Environmental monitoring requirements.

6.2.1.12   Marine disposal of any dredged/excavated sediment is subject to control under the Dumping at Sea Ordinance (DASO).  Dredged/excavated sediment destined for marine disposal is classified based on its contaminant levels with reference to the Practice Note for Authorized Persons and Registered Structural Engineers on Management Framework for Disposal of Dredged/ Excavated Sediment (PNAP ADV-21) stipulated a set of sediment quality criteria or Chemical Exceedance Levels (CEL) for contaminants including metals, metalloid and organic pollutants.

Practice Note for Authorized Persons and Registered Structural Engineers on Management Framework for Disposal of Dredged/ Excavated Sediment (PNAP ADV-21)

6.2.1.13  The PNAP ADV-21 outlines the approval procedures for dredging/excavating sediment and the marine disposal framework, the requirements for sediment quality assessment and provides guidelines for determining sediment classifications based on contamination levels.  Furthermore, the document also set out the arrangement for disposing of classified sediments.

Works Bureau Technical Circular (WBTC) No. 12/2000 Fill Management

6.2.1.14  WBTC 12/2000 describes the management of fill resources, construction and demolition material, and dredged and excavated sediment.

6.2.2             Other Relevant Guidelines

6.2.2.1      The following guidelines are also related to waste management and disposal:

·               Waste Disposal Plan for Hong Kong (1989);

·               Hong Kong Planning Standards and Guidelines (HKPSG), Chapter 9 – Environment;

·               Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes, EPD (1992);

·               A Guide to the Chemical Waste Control Scheme (EPD);

·               A Guide to the Registration of Chemical Waste Producers;

·               Works Branch Technical Circular (WBTC) No. 32/92, The Use of Tropical Hard Wood on Construction Site;

·               WBTC No. 2/93, Public Dumps;

·               WBTC No. 2/93B, Public Filling Facilities;

·               WBTC No. 16/96, Wet Soil in Public Dumps;

·               WBTC Nos. 4/98 and 4/98A, Use of Public Fill in Reclamation and Earth Filling Projects;

·               WBTC No. 19/2001, Metallic Site Hoardings and Signboards;

·               WBTC No. 12/2002, Specifications Facilitating the Use of Recycled Aggregates;

·               WBTC Nos. 25/99, 25/99A and 25/99C, Incorporation of Information on Construction and Demolition Material Management in Public Works Sub-committee Papers;

·               PNAP ADV-19, Practice Note for Authorized Persons and Registered Structural Engineers on Construction and Demolition Waste;

·               CEDD TC No. 11/2019, Management of Construction and Demolition Materials;

·               Development Bureau Technical Circular (Works) (DevB TCW) No. 06/2010, Trip Ticket System for Disposal of Construction & Demolition Materials, Development Bureau, Hong Kong SAR Government;

·               DevB TCW No. 08/2010, Enhanced Specification for Site Cleanliness and Tidiness.  Development Bureau, Hong Kong SAR Government;

·               DevB TCW No. 09/2011, Enhanced Control Measures for Management of Public Fill.  Development Bureau, Hong Kong SAR Government; and

·               Section 4.1.3 of Chapter 4 of the Project Administration Handbook (PAH) for Civil Engineering Works, Management of Construction and Demolition Materials including Rock.

6.3                   Assessment Methodology

6.3.1             Construction Phase

6.3.1.1       The assessment approach was based on the criteria and guidelines for assessing waste management implications as stated in Annexes 7 and 15 of the EIAO-TM and the EIA Study Brief No.  ESB-342/2021.

6.3.1.2       The waste management hierarchy has been applied in assessing and developing mitigation measures associated with the waste generation.  A waste management hierarchy ranks waste management methods according to their desirability, and includes the following methods in descending order:

·               Avoidance;

·               Minimisation;

·               Recycling/ reuse;

·               Treatment; and

·               Disposal.

6.3.1.3      All opportunities for reducing waste generation were assessed based upon the following factors:

·               Avoiding or minimising waste generation through changes in the design;

·               Adopting better management practices to promote segregation of waste materials;

·               Reuse and recycle; and

·               Diverting waste to public fill reception facilities or other construction sites.

6.3.1.4       The selected option in Sections 2.5 – 2.7 have considered the design, general layout, construction methods and programme to minimise the waste generation from the Project.  The following key items to minimise the generation of waste are taken into consideration:

·            Avoid reclamation for the ATCL alignment to minimise waste generation (refer to Section 2.5.1.5);

·            Avoid additional structures for flyover/viaduct, such as bored piles, excavation works at Scenic Hill for ATCL alignment to minimise waste generation (refer to Section 2.5.1.7) ;

·            Avoid open sea dredging to minimise the marine sediment generation (refer to Table 2.7);

·            Minimise the chance of floating refuse trapped or accumulated within the Project area (refer to Table 2.7);

·            Minimise the waste generation by adopting the precast method and casting the pier column/ bridge deck off site (refer to Table 2.8); and

·            Minimise the waste generation by adopting the steel formworks instead of timber (refer to Table 2.8).

 

6.3.1.5      The types and quantities of waste were estimated, and disposal options for each category of waste were identified, as well as the environmental impacts of the handling, collection and disposal of waste.  In reference to the following approach, the potential environmental impacts associated with the handling, transportation and disposal of waste resulting from the construction work were assessed:

·               Estimation of the types, timing and quantities of the wastes to be generated; and

·               Assessment of the potential environmental impacts on the capacity of waste collection, transfer and disposal facilities.

6.3.1.6       The impact caused by handling (including stockpiling, labelling, packaging and storage), collection, transportation and re-use/disposal of wastes was addressed in detail and appropriate mitigation measures were proposed.  This assessment covered the following areas: potential hazard, air and odour emissions, noise, wastewater discharge and public transport caused by handling (including stockpiling, labelling, packaging & storage), collection, transportation and reuse/ disposal of different types of waste.

6.3.2             Operational Phase

6.3.2.1       The assessment of waste management implications has been undertaken in accordance with Annexes 7 and 15 of the EIAO-TM and the EIA Study Brief No.  ESB-342/2021.  The waste management hierarchy comprising avoidance, minimization, recycling/ reuse, treatment and disposal has also been adopted for the assessment.

Proposal for Waste Management

6.3.2.2       The disposal options for various types of waste have been evaluated before considering options for reducing waste generation, on-site or off-site recycling, and reuse.  After considering the opportunities for reducing waste generation and maximizing reuse, the types and quantities of the remaining wastes required to be disposed of have been estimated and the disposal options for each type of wastes have been described.  The potential environmental impacts from the management of wastes have been assessed and relevant mitigation measures have been proposed.

6.4                   Identification and Evaluation of Waste Management Implications

6.4.1             Construction Phase

6.4.1.1      The waste generated from the construction of the Project would be classified into distinct categories based on their nature and disposal options.  These could include:

·               Construction and Demolition (C&D) materials;

·               Land-based and Marine-based sediment;

·               Chemical waste;

·               General refuse; and

·               Floating refuse.

Main Construction Activities and Waste Generation

6.4.1.2       During the construction phase, the main activities which would potentially result in the generation of waste include site clearance, site formation, excavation, foundation works for the marine facilities and ATCL, as well as stations and associated facilities.  No baring point or conveyor system will be established, constructed or operated under the Project and in the Project area.  Only existing public barging point will be used in the Project.  A summary of key project elements and the associated waste generation is given Table 6.1.

Table 6.1       Key Project Elements and associated Waste Generation

Key Project Elements

Construction Activities

Potential types of Waste to be Generated

ATCL alignment-

Marine Viaduct Section

·        Site clearance

·        In-situ concreting

·        Bored piles and pile caps

·        Site reinstatement

·        C&D material

·        Chemical waste

·        General refuse

·        Floating refuse

·                Marine-based sediment

ATCL alignment -

At-grade Section

·        Site clearance

·        In-situ concreting

·        Site reinstatement

·        C&D material

·        Chemical waste

·        General refuse

ATCL alignment -

Land Viaduct Section

·        Site clearance

·        Bored piles and pile caps

·        In-situ concreting

·        Site reinstatement

·        C&D material

·        Chemical waste

·        General refuse

·        Land-based sediment

Depot

·        Site clearance

·        Minor site formation

·        In-situ concreting

·        Superstructure construction

·        Site reinstatement

·        C&D material

·        Chemical waste

·        General refuse

Marine Facilities

·        Site clearance

·        In-situ concreting

·        Bored piles and pile caps

·        Site reinstatement

·        C&D material

·        Chemical waste

·        General refuse

·        Floating refuse

·        Marine-based sediment

Stations (TCC, ECSA-S, ECSA-N, AL, Academy) and associated footbridges

·        Site clearance

·        Socketed H-piles construction

·        Foundation works

·        Site reinstatement

·        C&D material

·        Chemical waste

·        General refuse

·        Land-based sediment

Construction and Demolition (C&D) Materials

6.4.1.3      Refer to Section 6.3.1.4, the design, layout, construction method, and programme have all been considered to reduce the generation of inert C&D materials during construction phase.

6.4.1.4      C&D materials generated during construction would comprise materials that are suitable for reuse on-site or as public fill and a portion of waste material that will require disposal to landfill.  For the purposes of this assessment, these two fractions denoted as inert C&D materials (i.e. soil, rock, rubble, concrete) and non-inert C&D materials (i.e.  timber, bamboo, vegetation, packaging waste) are discussed below.

6.4.1.5      The temporary storage of C&D materials may contribute to the generation of dust, visual impacts from unsightliness and water quality impacts from runoff.  The disposal of C&D materials also has the potential to result in noise and dust impacts from loading and unloading and emissions from haul vehicles.

6.4.1.6       The C&D materials cannot be reused on-site will be delivered to PFRFs directly to avoid dust and secondary pollution.  Mitigation measures on storage and transportation of C&D materials shall be implemented to minimize the impacts during delivering/transportation.

6.4.1.7       Based on the latest layout, it was estimated that a total of 21,379m3 of inert C&D materials would arise from the Project.  The piling works, excavation works and construction of structures works would be the major activities that generate the majority of C&D materials in the Project.  Based on the tentative construction programme (refer to Appendix 2.1), the estimated amount inert C&D materials to be generated by year during the construction phase are summarised in Table 6.2.

 

Table 6.2       Estimated Amount of Inert C&D Materials to be Generated during Construction Phase

Construction Activities

Estimated Amount of Inert C&D Materials to be Generated, m3

Year

2025

2026

2027

2028

Total

Piling Works

233

1,312

1,013

33

2,591

Construction of Structures

145

897

539

2

1,583

Excavation Works

1,413

8,401

6,368

1,023

17,205

  

6.4.1.8       The inert C&D materials should be reused on-site as far as practicable before exported off-site or delivered to PFRF (Tuen Mun Area 38 Fill Bank or Chai Wan Public Fill Barging Point) for beneficial use in other projects with potential fill demand in order to minimise the net amount of inert C&D materials generated from the Project.  Most of the C&D materials are inert materials and potentially can be reused on-site, the generated inert C&D materials will be reuse for backfilling along the ATCL.  Estimated 5,963m3 of inert C&D materials would be reused from the Project.  The estimated amount of inert C&D materials to be reused on site during construction phase by year are summarised in Table 6.3.

Table 6.3       Estimated Amount of Inert C&D Materials to be Reused On-site during Construction Phase

Construction Activities

Estimated Amount of Inert C&D Material to be Reused On-site, m3

Year

2025

2026

2027

2028

Total

Piling Works

15

75

31

0

121

Construction of Structures

2

11

3

0

16

Excavation Works

430

2,568

2,424

404

5,826

6.4.1.9      In addition to the inert C&D materials that would be generated by the Project and would be suitable for reuse on-site and as public fill, a total of 1,950 m3 of non-inert C&D material would also be generated and include:

·               Cleared vegetation and top soil from site clearance;

·               Wood from formwork; and

·               Materials and equipment wrappings etc.

6.4.1.10  During the erection of formwork, wood wastage can be reduced through use of prefabricated elements which minimises in-situ casting and use of formwork.  Through good site practices and specification of appropriate procedures for construction works, useful materials could be reused and recycled as far as possible and thus further reduce waste generation.  Estimated 450m3 of non-inert C&D materials would be reused from the Project. 

6.4.1.11   The stockpiling area for prefabrication units or construction materials (e.g. non-inert materials) storage located near marine viaduct at the Tung Chung area is proposed, the materials should be properly stored and covered with impervious sheeting to prevent any dust emission. With the implementation of mitigation measures and good site practices for handling and storage of the construction materials stated in Section 6.5.1, adverse dust impact and other environmental pollution nuisance is not anticipated.  The location of the stockpiling area of construction materials is indicated in Figure 6.2.

6.4.1.12   Measures would be implemented to minimise the generation of non-inert C&D materials and to prevent contamination for sorting of non-C&D materials at the designated areas.  Non-inert C&D materials such as wood, glass and plastic should be recycled as far as practicable before disposal to landfill (West New Territories Landfill) as a last resort. The handling, storage, or disposal of these materials are not expected to have adverse environmental impacts.

Land-based and Marine-based Sediment

6.4.1.13  Excavation works and construction of bored piles will be carried out for land viaduct.  The areas of the proposed excavation of land-based sediment are shown in Figure 6.1.

6.4.1.14  Bored piles with casing will be used to construct the foundation of the marine facilities and viaducts.  Nevertheless, it is unavoidable that marine-based sediment will have to be excavated from the bored piles for the construction of the foundation.  The areas of the proposed excavation of marine-based sediment are shown in Figure 6.1.

6.4.1.15   A sediment sampling and testing plan (SSTP) and an updated SSTP to serve the purpose of fulfilling this EIA study under the EIAO were approved by EPD on 1 December 2021 and 7 July 2022 respectively.  The final approved SSTP is provided in Appendix 6.1.  According to the SSTP, sediment contamination is expected to be Category L and Category M.  A sampling grid of 200 meters x 200 meters has been adopted based on paragraph 4(a) of memo issued by Development Bureau on 6 October 2010, “Control Measures for Management of Dredged/Excavated Contaminated Sediment” (ref: 0 in DevB(W) 515/83/04).  Total 23 boreholes are proposed for land-based and marine-based sediment samplings at the sediment excavation areas.  Construction areas that only involve shallow excavation (e.g. road diversions) which will not include piling works or encounter marine sediment are excluded from the sampling works.  Due to underground structures, underground utilities and safety issues, the boreholes were deviated from the proposed locations but are still within the sampling grid proposed in the approved SSTP.  The as-built sampling locations are shown in Figure 6.1.

6.4.1.16   Site investigation works were conducted from May 2022 to September 2022 based on the approved SSTP.  BHE1 – BHE4 and BHD4 are representing the marine-based sediments while BHD1 – BHD3 and BHD5 – BHD19 are representing the land-based sediment.  The as-built sampling locations of the boreholes are given in Figure 6.1.  Except for BHD5 and BHD6, all proposed boreholes (BHD1-BHD4, BHD7-19 and BHE1-4) in the approved SSTP were encountered with either land-based sediment or marine-based sediment. 

Land-based Sediment

6.4.1.17   Total 78 samples from 16 sampling boreholes were collected for chemical screening.  Based on the chemical screening results, 8 samples from BHD2, BHD3, BHD7, BHD9, BHD11 and BHD12 were exceeded the Lower Chemical Exceedance Level (LCEL) but below the Upper Chemical Exceedance Level (UCEL).  The remaining samples were identified as Category L sediment.  Summary of chemical screening results for land-based sediment are tabulated in Table 6.4 and detailed chemical screening results are attached in Appendix 6.2.

Table 6.4       Summary of Chemical Screening Results (Land-based Sediment)

 

Category

No. of Samples

Percentage of Samples Collected

Category L (equal to or below LCEL)

70

89.7%

Category M (above LCEL but equal to or below UCEL)

8

10.3%

Total

78

100.0%

 

6.4.1.18   The samples exceeded LCEL were conducted biological screening, summary of biological screening results for land-based sediment are tabulated in Table 6.5 and detailed biological results are attached in Appendix 6.3.  

Table 6.5       Summary of Biological Screening Results (Land-based Sediment)

Biological Screening Results

No. of Samples Passed

No. of Samples Failed

Percentage of Samples Passed

10-day burrowing amphipod survival test

8

0

100%

20-day burrowing polychaete survival and growth test

8

0

100%

48-96 hour larvae (bivalve or echinoderm) survival and normality test

8

0

100%

Total

8

0

100%

Marine-based Sediment

6.4.1.19   Total 36 samples from 5 sampling boreholes were collected for chemical screening.  Based on the chemical screening results, 14 samples from BHD4, BHE1, BHE2, BHE3, and BHE4 were exceeded the LCEL but below the UCEL.   The remaining samples were identified as Category L sediment.  Summary of chemical screening results for marine-based sediment are tabulated in Table 6.6 and detailed chemical screening results are attached in Appendix 6.2.

Table 6.6       Summary of Chemical Screening Results (Marine-based Sediment)

Category

No. of Samples

Percentage of Samples Collected

Category L (equal to or below LCEL)

22

61.1%

Category M (above LCEL but equal to or below UCEL)

14

38.9%

Total

36

100.0%

6.4.1.20   The samples exceeded LCEL were conducted biological screening, summary of biological screening results for marine-based sediment are tabulated in Table 6.7 and detailed biological results are attached in Appendix 6.3.  

Table 6.7       Summary of Biological Screening Results (Marine-based Sediment)

Biological Screening Results

No. of Samples Passed

No. of Samples Failed

Percentage of Samples Passed

10-day burrowing amphipod survival test

14

0

100%

20-day burrowing polychaete survival and growth test

14

0

100%

48-96 hour larvae (bivalve or echinoderm) survival and normality test

14

0

100%

Total

14

0

100%

6.4.1.21   According to the PNAP ADV-21, the chemical and biological screening results determined the classification and disposal arrangement for the sediments.  It is anticipated that only approximately 2,803m3 of marine sediment would be generated through mucking out activity during piling and excavation works along ATCL, construction of marine facilities and its associated facilities.  Approximate 375m3 will be reused on site and 1,895m3 of marine sediment will be disposed for Type 1 open sea disposal and 533m3 will be disposed to the Type 1- Open Sea Disposal (Dedicated Sites) at disposal site allocated by MFC.  No marine sediment failed the biological and Type 2- Confined Marine Disposal and Type 3- Special Treatment/Disposal is not required for this Project.  Summary of the disposal options and estimation of the volume of land-based and marine-based sediments to be generated are provided in Appendix 6.4, Appendix 6.5 and Table 6.8.

Table 6.8       Summary of Disposal Options

Disposal Options

Marine Sediment Category

Estimated Volume to be excavated (m3)

Tentative Volume to be reused on-site (m3)

Tentative Volume to be disposed (m3)

Type 1 - Open Sea Disposal

Category L

2,270

375

1,895

Type 1 - Open Sea Disposal (Dedicated Sites) at disposal site(s) allocated by MFC

Category M 

(passed the biological screening)

533

0

533

Type 2 – Confined Marine Disposal

Category M

(failed the biological screening)

0

0

0

Category H

(not require biological screening or passed in biological screening)

0

0

0

Type 3 – Special Treatment / Disposal

Category H

(failed in biological screening

0

0

0

Total

2,803

375

2,428

6.4.1.22    In order to minimize environmental impact, it is best to reuse as much sediment as possible within the Project site.    It should be explored whether land-based sediment can be reused on site, including as stabilization / solidification (S/S) technique prior to reuse by mixing with cement (e.g.  Portland cement).  For marine-based sediment treatment for reuse would be further explored subject to the land area requirements, environmental impacts of treatment methods, the physical properties (e.g. water content) of dredged sediments, the off-site disposal should be considered as a last resort.  Most of the land-based marine sediment is generated from the construction of bored piles. Possible re-use locations for the treated sediment include the landscape areas.  Subject to availability of suitable location and review on the backfilling method during detailed design stage, part of the land-based sediment would be reused on site.  In order to reuse the marine sediment for backfilling, the treated marine sediment will be provided with the necessary strength.  Moreover, the treated marine sediment will be tested for Toxicity Characteristic Leaching Procedure (TCLP) and Unconfined Compressive Strength (UCS) and should meet the Universal Treatment Standards (UTS) with reference to EPD’s Practice Guide for Investigation and Remediation of Contaminated Land and the UCS standard prior to reuse.  Only treated marine sediment which passed the UTS and UCS standards can be reused as backfilling in the Project.  If the treated marine sediment failed the UTS and UCS requirements, it will need to undergo the S/S process again.  A pilot-scale trial should be carried out before the commencement of treatment to determine the ratio of cement/sediment that could meet the treatment standard.  When all other options for reusing the land-based sediment have been considered, land-based sediment disposal should be considered as the last option. 

6.4.1.23  Should disposal of sediment is unavoidable, the Contractor shall be responsible for the arrangement of its management and disposal.  If the sediment is to be disposed of, the Contractor shall be responsible for the application of the Dumping at Sea Ordinance (DASO) permit required including carrying out the field investigations, samplings, chemical and biological laboratory testings to characterize the sediment/ mud concerned in accordance with the requirements stipulated under PNAP ADV-21.

6.4.1.24  The Project Proponent / Contractor would need to obtain Marine Fill Committee's agreement on the rationale for sediment removal / disposal as early as possible and make relevant submissions under PNAP ADV-21 to EPD's Marine Dumping Control Section/Territorial Control Office (TCO).

6.4.1.25  During the excavation and transportation of the sediment, potential odour may arise.  In order to minimise the impact, the excavated sediments shall properly covered when placed on trucks or barges.  Loading of the excavated sediment to the barge shall be controlled to avoid splashing and overflowing of the sediment slurry to the surrounding water.  Section 6.5 will further discuss on the mitigation measures for marine sediment disposal.

Chemical Waste

 

6.4.1.26  In the course of construction activities for the Project, the following chemical wastes are likely to be generated:

·                Scrap batteries or acid/alkali from fire appliance maintenance activities;

·                Used paints, engine oils, hydraulic fluids and waste fuel;

·                Spent mineral oils/cleansing fluids from machineries; and

·                Spent solvent/solution, some of which may be halogenated, from equipment cleansing activities.

6.4.1.27  Chemical wastes may pose environmental, health and safety hazards if not stored and disposed of appropriately as outlined in the Waste Disposal (Chemical Waste) (General) Regulation and the Code of Practice on the Packing, Labelling and Storage of Chemical Waste.  These hazards may include:

·                Toxic effects to workers;

·                Adverse effects on air quality, water quality and land contamination due to spillage;

·                Hazards of fire; and

·                Disruption of sewage treatment works should the chemical waste enter the sewerage system.

6.4.1.28  The generation of chemical wastes from the construction plant and equipment to be used during construction phase is limited and it is anticipated that <100L of chemical wastes would be generated every month.  With the appropriate procedures to handle, store, transport and dispose of the chemical waste generated, adverse environmental and health impacts including the potential hazards of fire would not be anticipated.

6.4.1.29  Notwithstanding, the Contractor should register with EPD as a Chemical Waste Producer pursuant to the Regulation and the chemical waste should be collected by licensed chemical waste collectors for subsequent disposal at licensed chemical waste disposal facilities, for example the Chemical Waste Treatment Centre (CWTC) in Tsing Yi.  Hence, no adverse chemical waste impacts arising from the construction phase are anticipated.

General Refuse

6.4.1.30   The construction site with workers and site office would generate a range of general refuse that will need to be disposed of, including food waste, aluminum cans, and waste paper, etc.

 

6.4.1.31   The number of workers is not available at this stage but it is anticipated that there will be no more than 250 staff to be stationed on site at any one time during the construction phase of the Project.  Based on a waste generation of 0.94kg per person stated in the Monitoring of Solid Waste in Hong Kong Waste Statistics for 2021, the estimated daily amount of general refuse would be 235 kg, that is, about 198 tonnes of general refuse would be generated in the 30 months of the construction period.

 

6.4.1.32  The storage of general refuse has the potential to cause adverse environmental impacts, for example odour nuisance if the waste is not collected frequently, windblown litter, water quality impacts if the waste enters water bodies, visual impacts, etc.  Construction sites may also attract pests, vermin and other disease vectors if the waste storage areas were not well maintained.  Disposal of waste at areas other than approved refuse transfer stations and landfills can also lead to similar adverse impacts.

6.4.1.33  Provided that mitigation measures are adopted, adverse environmental impacts caused by the storage, handling, transport and disposal of general refuse would not be anticipated.   

6.4.1.34  It is recommended that the general refuse should be classified and any recyclable wastes, including aluminum cans, papers, plastic bottles etc. should be sorted and collected for recycling.  Other non-recyclable waste should be collected on a daily basis and disposed of at landfill.

Floating Refuse

6.4.1.35   According to Section 2.5.3, the location of wave attenuator for the marine facilities has been carefully designated to minimise the chance of trapping floating refuse.  The other option (MF-A) providing a relatively sharp turn and cause addition floating refuse easily trapped or accumulated within the Project area.  Considering the location option, the preferred option (MF-B) is located between Airport Island and HKP Island, and the waste potentially trapped or accumulated will be similar to the existing situation. Only limited amount of refuse may be trapped along the shoreline at marine facilities during heavy rains or typhoons.

6.4.1.36  However, potential floating refuse generated by the site workers may be concerned due to poor site waste management.   As the maximum number of workers working at the marine facilities site will be 30-40 at a same time, no adverse impact from the waste generated by site workers is anticipated.  With proper site waste management and provision of adequate rubbish bins for site workers, floating refuse arising from the construction activities is not anticipated.  Any refuse generated during construction site should be stored in enclosed bin to avoid adverse impacts to the surroundings, including marine environment.   Moreover, floating refuse at the embayment may be found/trapped along the shoreline of the Project or unintentionally brought from the project site into the shoreline during heavy rains or typhoons.  However, if any refuse is accidentally trapped in the marine waters within the Project Area, it will be collected by the Contractor regularly and disposed of a general refuse if any refuse is accidentally trapped in the marine waters within the Project Area.

6.4.1.37  With reference to the Tung Chung New Town Extension EIA (AEIAR-196/2016), it is estimated that 11.5m3 of floating refuse would be collected from the 3.4km long artificial seawall during the construction phase. Considering the total length at the embayment of this Project is 0.9km long, it is anticipated that approximately 3m3 of floating refuse would be collected every year by the Contractor and disposed of as general refuse.

Summary of Quantities of Waste generated during Construction Phase

6.4.1.38  The estimated types and quantities of waste to be generated by the Project implementation and recommended disposal options are summarised in Table 6.9.

Table 6.9         Summary of Quantities of Waste Generated during Construction Phase

 

Waste Type

Estimated Quantity

Proposed Handling/ Disposal Method

Generated

Re-use/Recycle

Disposal

On-site

Off-site

Inert C&D Materials

21,379m3

5,963m3

0m3

15,416m3

Tuen Mun Area 38 Fill Bank or Chai Wan Public Fill Barging Point

Non-Inert C&D Materials (Metal, paper and plastics etc.)

1,950m3

450m3

1,500m3

Metal, Paper & Plastic will be recycled as far as possible, the remaining materials will be disposed at West New Territories (WENT) Landfill

Land-based sediment

2,136m3

375m3

1,761m3

Treatment by Cement S/S and reuse onsite as backfilling materials, the remaining land-based marine sediment will be tentative disposed to South Cheung Chau and East of Ninepin. Final disposal sites shall be determined by MFC. Off-site disposal should be considered as a last resort.

Marine-based sediment

667 m3

0m3

667m3

Treatment for reuse (e.g. Treatment by Cement S/S) would be further explored, off-site disposal should be considered as a last resort. Marine-based sediment will be tentative disposed to South Cheung Chau and East of Ninepin.  Final disposal sites shall be determined by MFC. 

Chemical Waste

<100L per month

0 L

<100L per month

Chemical Waste Collector to Chemical Waste Treatment Centre in Tsing Yi and other licensed disposal facilities

General Refuse

198 Tonnes

(Up to 235 kg per day)

9 Tonnes

189 Tonnes

(Up to 235 kg per day)

Recycle as far as possible, then disposal the non-recyclable refuse at West New Territories (WENT) Landfill

Floating Refuse

3m3 per year

1m3 per year

2m3 per year

Recycle as far as possible, then disposal the non-recyclable refuse at West New Territories (WENT) Landfill

Transportation Arrangement for Waste Disposal during Construction Phase

6.4.1.39   No barging points or conveyor systems will be established, constructed or operated under the Project and in the Project area.  Only existing barging point will be used in the Project. The waste generated from the Project will be delivered and disposed by land/marine transportation to the designated disposal location.  According to Table 6.2, taken year 2026 into consideration, the maximum inert C&D materials to be disposed will be approximate 7,956m3, with bulk factor 1.1 and general capacity of construction truck is about 7.5m3 and barge capacity is about 300m3, about 4 trucks and 1 barge per day is expected for delivering the inert C&D materials.  Beside inert C&D materials, about 1 truck per day will be used for delivering the non-inert C&D materials and general refuse.

 

6.4.1.40   Category L and Category M marine sediments were found at the Project Site.  The tentative disposal outlet for open sea disposal of dredged sediment will be at South Cheung Chau and East of Ninepin.  The final disposal sites shall be determined by MFC and exact transportation routing for disposal will be proposed when applying the dumping permit.

 

6.4.1.41   The tentative transportation routing for the disposal of different types of wastes generated during the construction phase is summarised in Table 6.10 and illustrated in Figure 6.2a and Figure 6.2b. 

Table 6.10       Tentative Transportation Routing for Different Types of Wastes

Waste Type

Proposed Disposal Outlet

Tentative transportation Routing

Frequency

Inert C&D Materials

Tuen Mun Area 38 Fill Bank  or Chai Wan Public Fill Barging Point

Tuen Mun Area 38 Fill Bank:

Via North Lantau Highways, Chek Lap Kok Road, TM-CLK Link, Lung Mun Road

 

Chai Wan Public Fill Barging Point:

Via Ha Pang Fairway, Kap Shui Mun Fairway, Western Fairway, Northern Fairway, Central Fairway, Hung Hom Fairway and Eastern Fairway

 

Maximum 4 trucks/ day and 1 barge/ day

-Non-Inert C&D Materials (exclude materials would be collected by recycler)

-General Refuse

-Floating Refuse

West New Territories Landfill

Via Chek Lap Kok Road, North Lantau Highway, Shun Long Road, TM-CLK Link, Lung Mun Road, Lung Kun Tan Road, Nim Wan Road

Maximum 1 truck/ day

Chemical Waste

Chemical Waste Treatment Centre in Tsing Yi

Via Airport Road, Chek Lap Kok Road, North Lantau Highway Road, Lantau Link, Tsing Sha Highway, Tsing Yi Road 

Maximum 1 truck/ day

Marine sediments

South Cheung Chau and East of Ninepin*

East of Ninepin:

Via Kwo Lo Wan Road, Scenic Road, Chek Lap Kok South Road barging point#, Ha Pang Fairway, Kap Shui Mun Fairway, Western Fairway, Northern Fairway, Central Fairway, Hung Hom Fairway, Eastern Fairway and Tathong Channel

 

South Cheung Chau:

Via Kwo Lo Wan Road, Scenic Road, Chek Lap Kok South Road barging point#, west of Lamma Island, Western Fairway, and West Lamma Channel

Maximum 3 trucks and 1 barge/day

Remarks:         *Final disposal sites shall be determined by MFC

#Existing barging point which is not established, constructed or operated under the Project

 

6.4.2             Operational Phase

6.4.2.1       The operation of the Project would generate the following categories of wastes:

 

·                Municipal solid waste;

·                Chemical waste;

·                Floating refuse; and

·                Marine sediment from maintenance dredging.

Municipal Solid Waste (MSW)

6.4.2.2      During the operational phase, MSW such as paper, plastic and office waste (i.e. paper, food, plastic bottles, aluminium cans) would be generated by staff and passengers, and scrap materials from road and maintenance, and discarded materials from maintenance of the vehicles (i.e. metal parts of the vehicles).

6.4.2.3       The storage and handling of these wastes may cause adverse environmental impacts.  The amount of general refuse that would arise during operational phase of the Project cannot be confirmed at this stage since it would be subject to operational needs and the number of staff and passengers in future.  The estimated number of staff would be around 30, subject to operational need in the future.  Based on a waste generation of 0.94kg per person stated in the Monitoring of Solid Waste in Hong Kong Waste Statistics for 2021, the estimated daily amount of general refuse would be 29 kg, that is, about 11 tonnes of general refuse would be generated annually from the site staff during operational phase.

 

6.4.2.4      Additionally, approximately 100 kg of general refuse is anticipated to be generated daily by the passengers during the operational phase, subject to further review.  The most common types of waste generated by the passengers are food, paper, cans and plastic.  No adverse impact from the amount of MSW generated from the passengers is anticipated.

6.4.2.5      The general refuse and waste from maintenance activities would include paper, plastic, food, plastic bottles, aluminium cans, scrap materials, discarded materials, etc.  The total quantity of municipal solid waste to be generated from staff and passengers is relatively small and the wastes shall be collected by the reputable waste collector regularly. Therefore, no adverse environmental impact is anticipated.

Chemical Waste

6.4.2.6      Maintenance activities in depot would generate chemical waste including scrap batteries, used fluorescent tubes, cleansing materials and discarded electronic equipment.  In addition, lubricants, paints, used batteries, mineral oil, coolants, and solvents would be generated during the operational phase.  In view of the chemical wastes generated from the operational activities, it is anticipated that only a few hundred kilograms of scrap batteries and <100L of chemical wastes would be generated every month.  This waste may pose environmental, health and safety hazards.  Measures as stipulated in the Waste Disposal (Chemical Waste) (general) Regulation and the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes would be strictly followed for the handling and disposal of chemical waste.

6.4.2.7      These wastes may pose adverse environmental, health and safety hazard if not properly managed.  Considering the maximum quantity of chemical waste to be generated during the operational phase would be <100L per month, subject to future operational needs, no adverse environmental impact is anticipated with proper storage, handling and disposal of this waste.  An Emergency Response Plan to prevent and handle chemical spillages caused by the depot operations during operational phase shall be prepared.

Floating Refuse

6.4.2.8      With the provision of adequate rubbish bins at marine facilities and along ATCL, floating refuse arisen from the Project is not expected.  Considering that the floating refuse from outside waters may be trapped by the berthing facilities and floating pontoons, control measures such as regular inspection and collection of floating refuse within the Project area should be implemented.  In reference to Section 6.4.1.37, approximate 3m3 of floating refuse will be collected annually, regular clean up of floating refuse will be carried out by AAHK or it’s operator(s). With the implementation of the control measures, the adverse impact from the accumulation of floating refuse is not anticipated. 

Marine-based Sediment during Maintenance Dredging

6.4.2.9       Maintenance dredging within the proposed marine facilities would be required regularly to maintain safe navigable water depth close to the existing seabed level.  The timing and extent of dredging will be planned based on findings of regular geophysical surveys.  Maintenance dredging will be carried out in every two years.  The maintenance dredging would be required during operation of the proposed marine facilities.  The timing and extend of dredging will be further review based on findings of regular geophysical surveys.  In order to restore the seabed level to the current level every two years, maximum 500mm depth marine sediment will be dredged during maintenance dredging.  The maximum maintenance dredging area is about 70,000m2, which equivalent to the dredging volume of 35,000m3.  The maximum working rate for maintenance dredging is assumed to be 40m3 per hour and only one closed grab dredger will be working in any time. It assumes maximum 480m3 will be dredged daily, which 2 barge trips for disposal will be required daily.  Similar to the arrangement for project construction, sediment sampling, testing, handling and disposal procedures as stipulated by the PNAP ADV-21 will be followed and complied with.  The marine disposal site will be allocated by the MFC/CEDD based on the sediment quality.  Adverse impact from the maintenance dredging is not anticipated. 

6.5                   Mitigation Measures

6.5.1             Construction Phase

6.5.1.1       The mitigation measures for construction phase are recommended based on the waste management hierarchy principles.  Recommendations of good site practices, waste reduction measures as well as the waste storage, collection and transportation are described in the following sub-sections.

Good Site Practices

6.5.1.2       Adverse waste management implications are not expected, provided that good site practices are strictly implemented.  The following good site practices are recommended throughout the construction activities:

 

·                Nomination of an approved personnel, such as a site manager, to be responsible for the implementation of good site practices, arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site;

·                Training of site personnel in site cleanliness, appropriate waste management procedures and concepts of waste reduction, reuse and recycling;

·                Provision of sufficient waste disposal points and regular collection for disposal;

·                Appropriate measures to minimize windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers;

·                Regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors;

·                Provision of wheel washing facilities at site exit before the trucks leave the works areas to minimize dust disturbance due to the trucks transportation to the public road network; and

·                The Contractor should prepare a Waste Management Plan (WMP) as part of the Environmental Management Plan (EMP) in accordance with the PNAP ADV-19.  The WMP should be submitted to the Project Manager/ Representatives of project proponent for approval.  Mitigation measures proposed in the EIA Report and the EM&A Manual should be adopted.

Waste Reduction Measures

6.5.1.3       Amount of waste generation can be significantly reduced through good management and control.  Waste reduction is best achieved at the planning and design phase, as well as by ensuring the implementation of good site practices.  The following recommendations are proposed to achieve reduction:

 

·                Segregate and store different types of waste in different containers, skip or stockpiles to enhance reuse or recycling of materials and their proper disposal;

·                Proper storage and good site practices to minimize the potential contamination of construction materials;

·                Plan and stock construction materials carefully to minimize amount of waste generated and avoid unnecessary generation of waste; and

·                Provide training to workers on the importance of appropriate waste management procedures, including waste reduction, reuse and recycling.

Storage, Collection and Transportation of Waste

6.5.1.4       Storage of waste on site may induce adverse environmental implications if not properly managed.  The following recommendation should be implemented to minimize the impacts:

 

·                Non-inert C&D materials such as top soil should be handled and stored well to ensure secure containment of the materials;

·                Stockpiling area/ temporary stockpiling area should be provided with covers and water spraying system to prevent materials from wind-blown or being washed away; and

·                Different locations should be designated to stockpile each material to enhance reuse.

6.5.1.5       The collection and transportation of waste from works areas to respective disposal sites may also induce adverse environmental impacts if not properly managed.  The following recommendation should be implemented to minimize the impacts:

 

·                Remove waste in timely manner;

·                Employ the trucks with cover or enclosed containers for waste transportation;

·                Obtain relevant waste disposal permits from the appropriate authorities;

·                Disposal of waste should be done at licensed waste disposal facilities; and

·                In order to monitor the disposal of C&D materials at PFRFs and landfills and to control fly-tipping, a trip-ticket system should be established in accordance with DEVB TCW No. 6/2010.  A recording system for the amount of waste generated, recycled and disposed, including the disposal sites, should also be set up.  Warning signs should be put up to remind the designated disposal sites.  CCTV should be installed at the vehicular entrance and exit of the site as additional measures to prevent fly-tipping.

 

6.5.1.6       In addition to the above measures, other specific mitigation measures on handling the C&D materials, marine sediment, chemical waste and general refuse generated from construction phase are recommended in the following sub-sections.

C&D Material

6.5.1.7       Wherever practicable, C&D materials should be segregated from other wastes to avoid contamination and ensure acceptability at PFRFs areas or reclamation sites.  The following mitigation measures should be implemented in handling the C&D materials:

 

·                Carry out on-site sorting;

·                Make provisions in the Contract documents to allow and promote the use of recycled aggregates where appropriate; and

·                Implement a trip-ticket system for each works contract in accordance with DEVB TCW No. 06/2010 to ensure that the disposal of C&D materials is properly documented.

·                Ensure that all dump trucks carrying C&D materials to the designated locations are equipped with GPS or equivalent devices so that the travel routes and parking locations can be tracked and monitored.  A real-time GPS tracking system connecting to the internet or intranet will allow efficient tracking and monitoring to avoid illegal dumping or landfilling of C&D materials.  The data collected by GPS or equivalent system should be recorded properly for checking by Environmental Team (ET) and Independent Environmental Checker (IEC) regularly.

6.5.1.8       Details of the recommended on-site sorting and reuse of C&D materials are given below:

 

On-site Sorting of C&D Materials

·                Storage areas would be located within the site during construction phase for temporary storage of inert C&D materials. 

·                All C&D materials arising from the construction would be sorted on-site to recover the inert C&D materials and reusable and recyclable materials prior to disposal off-site as far as practicable.  Non-inert portion of C&D materials should also be reused whenever possible and be disposal of at landfills as a last resort.

·                The Contractor would be responsible for on-site sorting of C&D materials and promptly remove all sorted and processed material arising from the construction activities to minimize temporary stockpiling on-site. 

Reuse of C&D Materials

6.5.1.9       The following potential measures should be explored to maximize the reuse/ recycle of C&D materials generated from the Project:

 

·                Reuse suitable inert C&D materials on-site as far as practicable;

·                Reuse suitable excavated rock by reworking at approved quarries (e.g.  Crushed as aggregates);

·                Sorting of demolition debris and excavated materials from demolition works to recover reusable/ recyclable portions (e.g.  Soil, broken concrete, metal); and

·                Protect recyclable material to keep it in usable condition.

Land-based and Marine-based Sediment

6.5.1.10   Excavated marine sediment should be reused as far as possible within the Project Site before considering disposal.  Subject to availability of suitable location and review on the backfilling method, part or all of the marine sediment would be reused on site.  Possible methods for the reuse of marine sediment on site including the reuse as backfilling materials after mixing with cement should be explored.  The criteria for reuse of treated sediments are proposed with reference to the Unconfined Compressive Strength (UCS) and the Universal Treatment Standards (UTS), which specify the Toxicity Characteristics Leaching Procedure (TCLP) test limits as given in Section 4.1 and Table 4.6 of the Practice Guide for Investigation and Remediation of Contaminated Land.  A pilot trial will be carried out for the concerned sediments in order to confirm the treatment options. During the cement stabilization / solidification (S/S) process, the below mitigation measures shall be adopted to minimise the potential environmental impacts:

 

·                Cement mixing process should be enclosed to minimize odour/ dust emissions.

·                Loading, unloading, handling, transferring and storing for treated and untreated sediment should be carried out with good site practices that prevents or minimizes dust emissions.

·                An impermeable surfacing shall be placed under the mixing areas and a cover should be provided to prevent dust emission and possible cross contamination.

·                Good housekeeping should be maintained at the mixing and treatment area.

·                Treated and untreated sediments should be clearly separated and stored separately.

·                Surface runoff from the mixing and treatment areas should be properly collected and stored separately, and then properly treated to levels in compliance with the relevant effluent standards as required under the Water Pollution Control Ordinance before final discharge.

·                Prior to the cement mixing operation, safety training and environmental training should be provided to all related site staff and workers.

·                For the Cement S/S works, at least one safety officer shall be provided by the Main Contractor to identify possible hazards and ensure the implementation of all relevant safety measures.

·                Skilled and qualified personnel should be employed to carry out the work and the plant operator must obtain valid certificate to complete the job. The safety officer must ensure that sufficient trainings will be provided to all workers with respect to the safety awareness and safety precaution of work.

·                Backhoe / Excavator should be examined by Registered Professional Engineer according to statutory requirements before use. Only the plant operators with valid qualified certificates should be allowed to operate the relevant plants.

·                All workers in site area should wear appropriate personal protective equipment, such as safety helmet, safety shoes, gloves, goggles and protective coveralls (if necessary). No person should approach to the backhoe / excavator during their operation.

·                Workers, vehicles, instruments, and equipment in touch with the marine sediment will be properly decontaminated by cleaned with non-phosphate detergent and rinsed with distilled water between each excavation and sampling event and before leaving the site.

·                The excavated area should be vacated and fenced off and adequate warning signs should be displayed.

·                In order to minimize the duration of contact between marine sediment and workers, excavation works should be done within short period of time. No excavation should be held during the rainy days to avoid the migration of contaminants on site.

·                Smoking, eating or drinking during activities with exposure to the contaminated materials should be prohibited.

 

6.5.1.11   Marine disposal option for the marine sediment should only be considered as the last resort upon exhaustion of reuse options.  In case off-site disposal is unavoidable, the possible mitigation measures to handle the sediment are summarized as follows:

 

·                All construction plant and equipment shall be designed and maintained to minimise the risk of sediments being released into the water column or deposited in the locations other than designated location.

·                All vessels should be sized so that adequate clearance is maintained between vessels and the seabed in all tide conditions, to minimise that undue turbidity is not generated by turbulence from vessel movement or propeller wash.

·                Adequate freeboard shall be maintained on barges to ensure that decks are not washed by wave action.

·                All marine sediments shall be transported to the designated location by water-tight containers and dump trucks with tarpaulin cover.

6.5.1.12    The requirements and procedures for dredged/excavated sediment specified under the PNAP ADV-21 should be followed.  The contractor must ensure that all the necessary waste disposal and marine dumping permits or licences are obtained prior to the commencement of the construction works.

6.5.1.13    To avoid illegal dumping, all dumping vessels have to be approved in a marine dumping permit issued under the DASO.  Each of the vessels has to be installed with an automatic recording equipment, namely the Front End Mobile Unit (FEMU), which is a key component of the Real Time Tracking & Monitoring of Vessel (RTTMV) System of EPD.  The FEMU transmits self-monitoring data direct from the barge at sea to the Control Centre at EPD through GPRS mobile communication network.  The transportation route avoiding the ecological sensitive areas will be proposed when applying the dumping permit.

Chemical Waste

6.5.1.14   For those processes which generated chemical waste, it may be possible to find alternatives to eliminate the use of chemicals, to reduce the generation quantities or to select a chemical type of less impact on environment, health and safety as far as possible.  Wherever possible, opportunities for the reuse and recycling of materials will be taken.

 

6.5.1.15   If chemical waste is produced at the construction site, the Contractor should register with EPD as a chemical waste producer.  Storage, handling, transport and disposal of chemical waste should be arranged in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes published by the EPD.  Chemical waste should be stored in appropriate containers and collected by a licensed chemical waste collector.  Chemical waste (e.g.  Spent lubricant oil) should be recycled at an appropriate facility as far as possible, while the chemical waste that cannot be recycled should be disposed of at either the CWTC, or another licensed facility, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.   Below mitigation measures shall be adopted:

 

·                The containers used for storing chemical waste should be suitable for the substance to be held, resistant to corrosion, maintained in good conditions and securely closed;

·                The containers should have a capacity of <450L unless the specifications have been approved by the EPD;

·                The label on the containers should be clearly labelled in English and Chinese and comply with the requirements prescribed in Schedule 2 of Waste Disposal (Chemical Waste) (General) Regulation;

·                The storage area for the chemical waste should be used solely for the storage of chemical wastes;

·                The storage area should be enclosed on at least three sides by a wall, partition or fence with a height of not less than two metres or the total height of containers in stack, whichever is less;

·                Where containers of liquid chemical wastes are stored, the area should be designed with impermeable floor and provided with a bund with capacity to accommodate 110% of the volume of the largest container or 20% by volume of the chemical waste stored in the area, whichever is greatest;

·                Adequate ventilation should be allowed in the storage area by leaving some space between the top of the enclosure walls and the ceiling, or provision of louvers on the sides of the enclosure walls;

·                The storage area should be sufficiently covered to prevent rainfall from entering the public drainage system via storage area (water collected within the bund must be tested and disposed of as chemical waste, if necessary);

·                Separate containers should be used for packing different types of waste or waste arising from different sources and process to minimise mixing of incompatible materials;

·                Drip tray should be provided to chemical waste containers.  The drip tray should be clean up regularly.  Clean up should be done before foreseeable inclement weather such as typhoon or heavy rain; and

·                Waste oils, chemicals or solvents shall not be disposed of to drain.

General Refuse

6.5.1.16   General refuse should be stored in enclosed bins separately from C&D materials/ wastes and chemical wastes.  Sufficient bins shall be provided for storage of general refuse as required under the Public Cleansing and Prevention of Nuisances Regulation.  Recycling bins should also be placed to encourage recycling.  Preferably enclosed and covered areas should be provided for general refuse collection and routine cleaning for these areas should also be implemented to keep areas clean.  A reputable waste collector should be employed to remove general refuse on a regular basis and disposed of to the nearest landfill or refuse transfer station.  Burning of refuse on construction sites is prohibited.  Disposal of general refuse is recommended before foreseeable inclement weather such as typhoon or heavy rain.  Segregation and storage of different types of waste should be promoted to facilitate the reuse and recycling of the materials.  Separately labelled bins for the deposition of aluminium cans, paper and plastic bottles etc.  Should be provided as far as practicable.  Arrangements should be made with the recycling companies to collect the recycle waste as required.  It is expected that such arrangements would minimize potential environmental impacts.

 

6.5.1.17   The Contractor should implement an education programme for workers relating to avoiding, reducing, reusing and recycling general waste.  Participation in a local collection scheme should be considered by the Contractor to facilitate waste reduction.

Floating Refuse

6.5.1.18   Tool-box training shall be provided to site workers to ensure proper site waste management and good site practice are implemented.  Weekly inspection shall also be carried out to ensure no floating refuse is found within the Project Area.  If any refuse is accidentally trapped in the marine waters within the Project Area, it will be collected by the Contractor and recycled as far as possible, the remaining waste will be disposed of as general refuse. 

6.5.2             Operational Phase

Municipal Solid Waste (MSW)

6.5.2.1       Designated areas will be assigned for proper storage and collection of MSW generated on site.  Segregation of MSW will be conducted on site to allow for maximisation of recycling opportunities.  It is recommended to place clearly labelled recycling bins at designated locations which could be accessed conveniently.  A reputable waste collector should be employed to remove MSW regularly to minimise potential impacts arising from storage and collection of MSW.

Chemical Waste

6.5.2.2      If chemical waste is produced, AAHK or it’s operator(s) would be required to register with the EPD as a Chemical Waste Producer(s).  The guidelines stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes should be followed in handling of chemical waste. 

6.5.2.3      Appropriate containers with proper labels should be used for storage of chemical wastes.  Chemical wastes should be collected and delivered to designated outlet by a licensed chemical waste collector.  Chemical waste shall be disposed of at appropriate facility such as the CWTC by licensed collectors.

6.5.2.4      AAHK or it’s operator(s) shall prepare an Emergency Response Plan (ERP) to prevent and handle chemical spillages caused by the operations of depot during the operational stage.  The ERP shall include the spill prevention and precaution, responses action and procedures for spill clean up and disposal.  If any spillage occurs, AAHK or it’s operator(s) shall Inform Environmental Protection Department, Fire Services Department and Police in the case where the spillage of chemicals would cause serious contamination of an area or risk of pollution.

Floating Refuse

6.5.2.5      Adequate rubbish bins shall be provided at marine facilities and ATCL.  Control measures such as regular inspection and collection of floating refuse should be carried out.  If any floating refuse is found within the Project area, it will be collected and recycled as far as possible, the remaining waste will be disposed of as general refuse.

Marine-based Sediment during Maintenance Dredging

6.5.2.6       The requirements and procedures for dredged/excavated sediment specified under the PNAP ADV-21 should be followed.  AAHK or it’s operator(s) must ensure that all the necessary waste disposal and marine dumping permits or licences are obtained prior to the commencement of the maintenance works at the marine facilities.

6.5.2.7       To avoid illegal dumping, all dumping vessels have to be approved in a marine dumping permit issued under the DASO.  Each of the vessels has to be installed with an automatic recording equipment, namely the Front End Mobile Unit (FEMU), which is a key component of the Real Time Tracking & Monitoring of Vessel (RTTMV) System of EPD.  The FEMU transmits self-monitoring data direct from the barge at sea to the Control Centre at EPD through GPRS mobile communication network.  The transportation route avoiding the ecological sensitive areas will be proposed when applying the dumping permit.  The mitigation measures listed in Sections 6.5.1.11 to 6.5.1.13 shall be adopted to handle the sediments.

6.6                   Residual Impacts

6.6.1.1      With the implementation of good site practice to properly store, handle and dispose of the waste generated from the Project, no adverse residual impact is anticipated during the construction and operational phases of the Project.

6.7                   Environmental Monitoring and Audit

6.7.1.1      During the construction period, it is the Contractor’s responsibility to ensure that all waste produced during the construction of the Project are handled, stored and disposed of in accordance with good waste management practices, relevant legislation and waste management guidelines.

6.7.1.2      It is recommended that the waste arisings generated during the construction activities should be audited once per week by the Environmental Team (ET) to determine if wastes are being managed in accordance with approved procedures.  The audits should look at all aspects of on-site waste management practices including waste generation, storage, recycling, transport and disposal.  Apart from site inspections, documents including licenses, permits, disposal and recycling records should be reviewed and audited for compliance with the legislation of the recommended good site practice and other waste management mitigation measures.

6.7.1.3      During operation, with the implementation of good waste management practices, no adverse environmental impact is anticipated, and therefore waste monitoring and audit programme during the operational phase is not required.

6.8                   Conclusions

6.8.1.1       During the construction phase, waste types generated from the Project would likely include C&D materials (from foundation and construction works of proposed ATCL), land-based and marine-based sediment, chemical wastes from maintenance of construction plant and equipment, general refuse from the workforce and floating refuse.  The Contractor is requested to implement recommendations to avoid and minimize waste generation and off-site disposal during construction.

6.8.1.2       As the marine facilities is located between the Airport Island and HKP Island, limited amount of refuse may be trapped along the shoreline at marine facilities during heavy rains or typhoons. Given that the Project would implementation of appropriate control measures during construction and operational phase, it is considered that the future quantity of refuse to be found within the Project are would be similar to the existing situation.  

6.8.1.3       During construction phase, approximate 2,803m3 land-based and marine-based sediment will be excavated from the Project.  Total 2,270m3 and 533m3 marine sediment classified as Type 1- Open Sea Disposal and Type 1- Open Sea Disposal (Dedicated Sites) respectively.  No adverse environment impacts would be expected from the excavation, treatment, transportation and disposal of marine sediment.

6.8.1.4       During the operational phase, the main waste types generated would be chemical waste, MSW from maintenance activities and staff and passengers, floating refuse and marine sediment from maintenance dredging at marine facilities.  Maximum 35,000m3 of marine-based sediment will be dredged every 2 years from the maintenance dredging. Requirements and procedures for dredged/excavated sediment specified under the PNAP ADV-21 should be followed.  It is anticipated that no adverse impacts would arise if the mitigation measures were implemented.