CONTENTS
9.2 Legislative
Requirements and Evaluation Criteria
9.4 Marine
Archaeological Review
and Marine Archaeological Potential Establishment
9.5 Cultural
Heritage Impact Assessment.
9.7 Residual
and Cumulative Impacts.
9.8 Environmental
Monitoring & Audit (EM&A)
TABLES
Table 9.1 Details
of Survey Types with Objectives and Survey Spacing
Table 9.3 Summary
of Previous Marine Archaeological Investigations/Impact Assessments Conducted
Table 9.4 Sonar
Contact Identified in Marine Facilities Survey Site
Table 9.5 Position
of High Magnetic List
FIGURES
Figure 9.1 Cultural Heritage Impact
Assessment Area
Figure 9.2 MAI
Assessment Area and Previous Geophysical Surveys Conducted in Adjacent Area
Figure 9.3 Geophysical
Survey Area
APPENDICES
Appendix 9.1 Extract
of Relevant EIA Studies
Appendix 9.2 Geophysical
Survey Track Plot
Appendix 9.3 Sonar
Contact Images
Appendix 9.4 Magnetic
Anomalies Images
9.1.1.1
This
section presents the cultural heritage impact assessment (CHIA) which includes
a Marine Archaeological Investigation due to the construction and operation of
the Project.
9.2.1
General
9.2.1.1
The
following legislation, standards, guidelines and requirements are applicable to
the cultural heritage impact assessment in the Project.
·
Environmental
Impact Assessment Ordinance (Cap. 499) (EIAO) and the associated Technical
Memorandum on the EIA Process (EIAO-TM);
·
Antiquities
and Monuments Ordinance (Cap. 53) (A&M Ordinance);
·
Hong
Kong Planning Standards and Guidelines (HKPSG);
·
Requirements
for Cultural Heritage Impact Assessment (CHIA) from Appendix H of EIA Study
Brief (ESB-342/2021); and
·
Guidelines
for Marine Archaeological Investigation (MAI).
9.2.2
Environmental Impact
Assessment Ordinance (Cap 499)
9.2.2.1
Annex
10 of the EIAO-TM outlines the criteria for assessment of impact on sites of
cultural heritage. The general
presumption is in favour of the protection and conservation of all sites of
cultural heritage. In addition,
adverse impacts on sites of cultural heritage shall be kept to the absolute
minimum.
9.2.2.2
Annex
19 of the EIAO-TM outlines the approaches required in investigating and
assessing the impacts on sites of cultural heritage. There is no quantitative standard in
deciding the relative importance of these sites, but in general, sites of
unique archaeological, historical or architectural value will be considered as
highly significant. Preservation in
totality is preferred. If, due to
site constraints and other factors, only preservation in part is possible, this
must be fully justified with alternative proposals or layout designs, which
confirm the impracticability of total preservation.
9.2.3
Antiquities and Monuments
Ordinance (Cap. 53)
9.2.3.1
The
Antiquities and Monuments Ordinance (Cap. 53) (A&M Ordinance) provides
statutory protection against the threat of development on Declared Monuments to
enable their preservation for posterity.
The A&M Ordinance also establishes the statutory procedures to be
followed in making such a declaration.
9.2.3.2
Any
person who discovers an antiquity, or supposed antiquity, is required to report
the discovery to the Antiquities Authority.
9.2.4
Hong Kong Planning
Standards and Guidelines (HKPSG)
9.2.4.1
The
Chapter 10, Conservation, of the HKPSG provides general guidelines and measures
for the conservation of historical buildings, sites of archaeological interest
and other antiquities.
9.2.5
Requirements for Cultural
Heritage Impact Assessment (CHIA)
9.2.5.1
Appendix
H of EIA Study Brief (ESB-342/2021)
provides requirements on conducting Cultural Heritage Impact Assessment for the
Project.
9.2.6
Guidelines for Marine
Archaeological Investigation (MAI)
9.2.6.1 Guidelines
for MAI
provided in Appendix H of the EIA Study Brief (ESB-342/2021) details the standard
practice, procedures and methodology which shall be undertaken in determining
marine archaeological baseline and potential, presence of archaeological
artefacts, evaluating the potential impact and establishing suitable mitigation
measures.
9.2.6.2
The
MAI was undertaken in accordance with the survey scope and methodology defined
in the Technical Note on Marine Archaeological Investigation dated February
2022 which was confirmed by the EPD with no further comment.
9.3.1
Criteria, Guidelines and
Requirements
9.3.1.1
This
CHIA follows the criteria and guidelines in Annexes 10 and 19 of the EIAO-TM
and the Requirements for MAI as stated in Appendix H of the EIA Study Brief
(ESB-342/2021).
9.3.2
Assessment Area
9.3.2.1
The construction works of the Project consists of (i) the Airport Tung Chung Link (ATCL) to connect Hong Kong
Port (HKP) Island and Tung Chung Town Centre via a road link, and (ii) marine
facilities in the waters between Airport Island and HKP Island. The
CHIA will cover a Marine Archaeological Investigation (MAI). The location of the Project
is shown in Figure 9.1.
9.3.2.2
The Assessment Area for the MAI is defined by a distance of 300m from the boundary
of the Project area (as shown in Figure
9.2) according to Clause 3.4.10.2 of the EIA Study
Brief (ESB-342/2021), which includes areas
to be affected by the marine works associated with the construction works of
the Project.
9.3.3
Baseline Review
9.3.3.1
A baseline review was conducted to collate existing information
to identify the archaeological potential and their likely character, extent,
quality and value. The
baseline review focus on known sources including:
a)
Civil Engineering and Development Department,
Geotechnical Engineering Office – The Department holds extensive seabed survey
data collected from previous geological research;
b)
Marine Department, Hydrographic Office – the
Department holds a substantial archives of
hydrographic data and charts;
c)
The Royal Naval Hydrographic Department in the UK –
the Department maintains an archive of all survey data collected by naval
hydrographers;
d)
Relevant Government departments such as Antiquities
and Monuments Office, Environmental Protection Department etc
to obtain information on dredging history on the location of the Project; and
e)
Internet and libraries sources of relevant studies.
9.3.3.2
The findings provide historical records and more
detailed geological analysis of submarine features which may have been
subsequently masked by more recent sediment deposits and accumulated debris.
9.3.4
Geophysical Surveys
9.3.4.1
Desktop review identified that previous geophysical
surveys were conducted in adjacent areas.
However, two information gap areas in relation to the proposed works for
the Project have been identified that were not covered by previous geophysical
surveys. They are shown in Figure
9.2.
Area 1 partly overlaps with the proposed marine facilities and at the
coast east of the northern section of the Airport Tung Chung Link alignment for
the Project. Area 2 is where the
proposed marine viaduct sections of the Project situated.
9.3.4.2
Geophysical surveys of the Assessment Area of the
Project were conducted at areas that may involve seabed disturbance works in
the construction site boundary of the Project, these are the Marine Facilities Survey
Area (MF Site), which is partly located within information gap Area 1, and the Airport
Tung Chung Link Survey Area (ATCL Site), which is located within information
gap Area 2. The geophysical survey only covered ATCL Site as no seabed disturbance works
would be involved in the marine area outside the ATCL Site within the
construction site boundary. Their
locations are shown in Figure 9.2. The geophysical survey covering these two
work areas will provide adequate field information for the assessment of marine
archaeological impact of the Project, as the rest of the information gap area
is not impacted by the proposed works for the Project. The data received from the geophysical surveys
were analysed in detail to provide:
·
Exact
definition of the areas of greatest archaeological potential;
·
Assessment
of the depth and nature of the seabed sediments to define which areas consist
of suitable material to bury and preserve archaeological material;
·
Detailed
examination of Sub-bottom Profiling and Magnetic Survey records to map anomalies
in and on the seabed which may be archaeological
material; and
·
Detailed
examination of the multi beam sonar data to assess the archaeological potential
of the sonar contact.
9.3.4.3
Geophysical surveys covered areas that involve potential
seabed disturbance works and were conducted by Geotechnics & Concrete
Engineering (H.K.) LTD on 7th Apr, 8th Apr
and 20th Apr 2022. In the MF Site, Multi beam echo sounding
(MBES) and Side scan sonar (SSS) surveys were carried out on 7th Apr
2022. In the ATCL Site, marine magnetometer survey
(MAG)
was conducted on 7th April 2022, while MBES, SSS and Sub-bottom Profiling (SBP) surveys were conducted on 8th
Apr 2022. Seismic survey was repeated on 20th Apr 2022 due to data
corruption on some lines recorded earlier. The
data received from the surveys were analysed and the
findings are presented in Section 9.4.5.
Table 9.1 Details of Survey
Types with Objectives and Survey Spacing
Site |
Survey
Type |
Objective |
Survey Spacing |
MF
& ATCL |
Multi
beam echo sounding (MBES) |
To
provide seabed levels in details |
10m
plus infill lines |
MF
& ATCL |
Side
scan sonar (SSS) |
To
locate anomalous features and map sediment types on the seabed |
10m
plus coastline |
ATCL |
Sub-bottom
Profiling (SBP) |
To
provide levels and thicknesses of geological interfaces, if identified |
10m
x 30m |
ATCL |
Marine magnetometer (MAG) |
To identify metallic objects and any
archaeological remains on, or just beneath the seabed |
10m
|
Note: It is not practical to conduct SBP and MAG
at MF Site since there is no room for vessel movement with MF site constraint
by having seawalls enclosed three sides. |
Table 9.2 Equipment
List
Type |
Equipment |
Survey Vessel |
GEO1 |
Horizontal
positioning |
NovAtel PwrPak7 GNSS system |
Single beam echo
sounding |
Knudsen 320M
dual frequency single beam echo sounder |
Sub-bottom
profiler |
LVB |
Magnetometer |
Geometrics G-882
marine magnetometer |
Software |
C-Nav
computerized navigation suite |
Geometrics
MAGLOG software |
|
C-View digital
recording and processing system |
|
Others |
A/C generators,
computers and bar check
equipment |
|
|
Survey Vessel |
Profiler |
Horizontal
positioning |
NovAtel PwrPak7 GNSS system |
Single beam echo
sounding |
Knudsen 320M
dual frequency single beam echo sounder |
Multi Beam Echo
sounding |
NORBIT iWBMS Multi-beam Echo Sounder |
Applanix POS MV Wavemaster
II Inertial Navigation System |
|
Side scan sonar |
EdgeTech 4125 digital side scan sonar system |
Software |
C-Nav
computerized navigation suite |
C-View digital
recording and processing system |
|
Others |
A/C generators,
computers and bar check
equipment |
9.3.5
Establishing Marine
Archaeological Potential
9.3.5.1
The findings from the baseline review and geophysical
surveys were reviewed and analysed to provide an
indication of the likely character and extent of marine archaeological
resources within the Assessment Area.
The results are presented in below sections.
9.3.6
Further Archaeological Actions
9.3.6.1
Should marine archaeological potential be identified
that require further examination to fill in information gaps for subsequent
assessment, further marine archaeological actions such as detailed geophysical
surveys, Remote Operated Vehicle (ROV), Visual Diver Survey or Watching Brief
at potential area may be recommended.
9.3.7
Impact Assessment and
Recommendations
9.3.7.1
Based on the findings and analysis of the baseline
conditions and results of the evaluation of the marine archaeological
potential, an impact assessment was conducted to evaluate the potential marine archaeological
impacts of the Project, and recommend marine archaeological actions or
mitigation measures if necessary.
Baseline Review
9.4.1
Review of Historical
Documents
Maritime
Activities in Tung Chung Water
9.4.1.1
As
recorded by the 1819 version of Xinan
Gazetteer (新安縣誌),
Tung Chung was one of the salt pans involved in the battle between the locals
of Lantau Island and the government over the issue on illegal salting
trading activities in 1197. Almost all of the residents of Lantau
Island were killed by the government in 1197. After this event, 300
naval forces were garrisoned at the island (Murray, 1987; 張一兵,
1997).
9.4.1.2
The
area of Tung Chung was associated with different pirate battles in the
past. The Nine-day Battle took place in Tung Chung bay in November
of 1809. Cheung Po Tsai surrendered to the Qing Government in
1810. It is recorded that at the time of surrender, Cheung Po Tsai
had over 270 junks, 16,000 men, 5,000 women, 7,000 swords, and 1,200 guns (Cortesão, 1944). In order to prevent the threat
of pirate activities, two Tung Chung Small Batteries and Tung
Chung Fort were built in 1817 and 1832 respectively. It
reflected the large scale of pirate activities during the 1800s in Tung Chung (蕭國健,
1997).
9.4.1.3
At
the same time, the Northern Lantau Channel was used by foreign merchants from the
16th century. The channel was an anchorage area since this period
and was systematically recorded on a map in 1856. The Portuguese
merchant Jorge Aĺvares landed on Lantau Island in
August 1513 and later-on the Portuguese set up trading points in Lantau Island
between 1513 and 1522. It was recorded that a sea battle between
Chinese navy and Portuguese fleets was fought in the waters between Lantau
Island and Tuen Mun in 1521. The Chinese
navy destroyed the Portuguese fort in the same year. After the
Second Opium War in 1858, the western countries gained the navigation right of
China and Hong Kong waters. Frequent maritime trading business was
recorded in the channel of northern Lantau (劉蜀永,
2009).
9.4.1.4
In the Second Opium War, British warships attacked the
Imperial Chinese navy in 1858 in the water channel between Chek
Lap Kok Island and Tung Chung (香港歷史博物館,
2009). A broken cannon and a cannon ball
manufactured around 1808 were discovered on the seabed off Tung Chung and Chek Lap Kok during the
construction of the HKIA in 1993 (Meacham, 1994). It
indicated that the seabed of Tung Chung may contain archeological potential,
especially those related to the marine battles after 1808.
Archaeological
Background of Hong Kong International Airport (HKIA) Island
9.4.1.5
The
Hong Kong International Airport (HKIA) was built at former Chek
Lap Kok Island which is a reclaimed land. Terrestrial archaeological
investigations and rescue excavations were therefore conducted prior to the
airport development in 1989. Archaeological investigations carried
out in Chek Lap Kok Island
were recorded in 1923, 1925, 1931, and 1933 by Walter Schofield. In
the 1950s, members of the Hong Kong University Archaeological Team discovered
Neolithic period stone and pottery artefacts on the island. In 1979, the Hong Kong Archaeological
Society began studies on the archaeological sites on the island, and discovered
cultural deposit from Neolithic, Tang and Song periods (Meacham, 1994).
9.4.1.6 The
Hong Kong Archaeological Society conducted archaeological rescue excavations on
sites including Ha Law Wan Site of Archaeological Interest (SAI) (its location can
be seen in Figure 9.1) between September 1990 and July 1991 due to the
decision to build Hong Kong’s new airport on Chek Lap
Kok in 1989 (Meacham, 1994).
The Yuan period kiln complex was identified in the site and later preserved in Ancient Kiln Park of the HKIA.
9.4.2
Review of
Geological Conditions
9.4.2.1 The
solid geology of the Assessment Area belong to East Lantau Rhyolite formation and Fill
formation at the southern western part of the Tung Chung link, consists of Hang Hau
Formation comprising mud with beach deposit, and Chek
Lap Kok Formation comprising coarse sediments with
gravels (EGS, 2022).
9.4.3
Review of
Charts & United Kingdom Hydrographic Office ‘Wreck’ Files
9.4.3.1 Review
of old admiralty charts and database of known shipwrecks/undefined sites in the
HKSAR maintained by the United Kingdom Hydrographic Office identified no
potential marine archaeological interest / wrecks in the MAI Assessment
Area.
9.4.4
Review
of Previous Marine Archaeological Investigation/Impact Assessment
9.4.4.1 A
preliminary review of four previous Marine Archaeological Investigations/Impact
Assessments were conducted as part of the EIA for this project. Table 9.3 below
summarized the marine archaeological works conducted.
Table 9.3 Summary of Previous Marine
Archaeological Investigations/Impact Assessments Conducted
EIA
Projects |
MAI
Conducted |
Intermodal Transfer Terminal - Bonded
Vehicular Bridge and Associated Roads EIA Report [Register No.: AEIAR-216/2018] ([1]) |
Only desktop MAI was conducted. |
Tung Chung New Town Extension EIA Report [Register No.: AEIAR-196/2016] ([2]) |
No geophysical survey was conducted. Data gap Identified at the Tung Chung
Bay for the near shore areas of North Lantau where accessibility for vessels is
constrained. Thus, a diver survey
was conducted in 2012 to fill in the information gap area. The diver survey was conducted by
circular searches and 20 diver surveys were conducted along the Tung Chung
Bay coast. No marine
archaeological deposit was identified.
The dive survey area is outside the MAI Assessment Area for this
Project. |
Hong Kong – Zhuhai – Macao Bridge Hong Kong
Boundary Crossing Facilities – Investigation (HZMB-BCF) EIA Report [Register No.: AEIAR-145/2009] ([3]) |
Three geophysical surveys as part of the
EIAs for both HZMB-BCF and HZMB-NLH Projects were carried out (see HKBCF
Geophysical Survey Area in Figure 9.2 showing the geophysical
survey coverage in or adjacent to the MAI Assessment Area for
this Project). An area of approximately 750 m x 750 m
was not recorded during the geophysical surveys for HZMB-BCF in the vicinity
of aeronautical lights and landfall of the Hutchison cable on the eastern
shore of Chek Lap Kok
(see Image 24 extracted from EIA
report for HZMB-NLH in Appendix 9.1)
but
a fibreglass speed boat was used in the very shallow waters and thus echo
sounding only was conducted. Diver surveys were
conducted in 2009 at three objects (SC006, SC010, and SC011) identified from
geophysical surveys but they are confirmed to have no marine archaeological
significance (see Figure 12.1
extracted from EIA report for HZMB-BCF in Appendix 9.1). |
Hong Kong-Zhuhai-Macao Bridge and
Connection with North Lantau Highway (HZMB-NLH) EIA Report [Register No.: AEIAR-144/2009] ([4]) |
Three geophysical surveys (including
multi-beam echo sounding, seismic, side scan sonar and magnetic surveys) were
carried out during May to June 2004, November to December 2005 and November
to December 2008 as part of the EIAs for both HZMB-BCF and HZMB-NLH Projects
(see HKLR Geophysical Survey Area in Figure 9.2 showing the geophysical
survey coverage in or adjacent to the MAI Assessment Area for this
Project). Because of the variable
water depths throughout the survey area, a fibreglass speed boat was used in
the very shallow waters in the Airport Channel (situated between Lantau and
CLK) for echo sounding only. Further to the geophysical surveys
conducted as mentioned above, a total number of twenty-six (26) objects were
identified from the geophysical surveys considered to have marine
archaeological potential. A
visual diver survey was conducted in 2009 to obtain field data to assess
their archaeological significance.
They were confirmed to have no marine archaeological significance (see
Image 27 extracted from EIA report
for HZMB-NLH in Appendix 9.1. No. 23 to 26 and on
transect fall within the MAI Assessment Area for this Project). |
9.4.5
Review of Geophysical Survey Results
9.4.5.1 Geophysical
surveys as part of the Project covered potential seabed disturbance works
involved areas and were conducted by Geotechnics
& Concrete Engineering (H.K.) LTD on 7th
Apr, 8th Apr and 20th
Apr 2022 to
study the seabed features and to locate anomalous features in the surveyed areas. Side Scan Surveys were conducted in both
MF Site and ATCL Site, while Magnetometer Survey was conducted only in ATCL
Site. The survey findings were
processed by the geophysicists and reviewed by the qualified marine
archaeologist, Dr William Jeffery, and cultural heritage specialist, Ms Peggy Wong.
The survey track plots are shown in Appendix 9.2. Details
of survey types with objectives and survey spacing are shown in Table 9.1, and the equipment list is shown in Table 9.2.
Marine
Facilities Survey Area (MF Site)
9.4.5.2 In Marine
Facilities Survey Area (MF Site), which is partly located within information
gap Area 1, the observed seabed is highly disturbed and characterized by deep
seabed scars with isolated debris. The
majority of the sediments are interpreted as fine sediments dominated by sandy
silt and clay. Boulders and rubbles
were located close to the seawalls. Areas of high reflectivity patch are
observed in the southern area. They
are interpreted as possible dense sand or gravel.
9.4.5.3 Eight
sonar contacts (SC001 to SC008) were identified. They are located at a range of water
depth from -3.4 mPD to -5.3 mPD
and their dimensions are shown in Table
9.4. SC001, SC002 and SC004 are interpreted as
modern debris due to their random placement, their irregular shape and small
size, low side scan sonar signal strength intensity, and lack of a shadow indicating
low elevation. They could be
natural or man-made material but given they are located on a seabed that has
been worked and re-worked over the years as seen by the highly disturbed seabed
with deep scars (see sonar contact image SC004 in Appendix 9.3 showing example of deep scars), they would be greatly
impacted and have no marine archaeological interest; SC003, SC005 and SC006 are
interpreted as Navigation Buoys without marine archaeological interest. SC007 and SC008 are located close to the
rubble mound and appear to be some type of metal framework and most likely dumped
materials, given their location at the base of the rubble mound, and are considered
of no archaeological interest. The
locations of all these features are shown in Figure 9.3 and
the sonar contact images are shown in Appendix 9.3.
Airport Tung Chung Link Survey Area (ATCL Site)
9.4.5.4 At ATCL
Site, boulders and rubbles dominate along the shoreline in the north and in the
south of the channel. Majority of
the sediments inside the channel is fine sediments interpreted as soft silt or clay.
Isolated boulders are spotted in
the southern part of the channel.
9.4.5.5 Through
the magnetic survey, five magnetic anomalies
(MC001 to MC005) were identified. These
anomalies were interpreted as debris and of no archaeological potential. A significant ferrous archaeological
object detectable would be an iron cannon, but none of the nano-Tesla
(nT) values are in the range for a cannon, e.g. a one
tonne
cannon at two metres depth of water would give a value of c. 2,000 nT (MC005 nT is 43 and is in one
to two metres of water); and at seven metres depth of water the nT value would be about 500 (MC001, MC002, MC003, MC004 have
a nT value of eight to twelve and are in five to
eight metres of water) (Green, 2004). Their details are shown in Table 9.5,
locations are shown in Figure
9.3, and the magnetic
anomalies images, including any seabed features in the vicinity of the magnetic
anomalies are shown in Appendix
9.4. No side scan sonar contacts or
sub-bottom anomalies were identified.
Table
9.4 Sonar
Contact Identified in Marine Facilities Survey Site
Contact
number |
Latitude Longitude |
Easting Northing |
Water depth
(-mPD) |
Dimensions
(m) |
Description |
SC001 |
22° 19.043' N
113° 56.497'
E |
812281.0E 819669.9N |
4.2 |
0.6x0.6xnmh |
Debris |
SC002 |
22° 19.023' N
113° 56.526'
E |
812331.3E 819633.2N |
5.1 |
0.9x0.8x0.3 |
Debris |
SC003 |
22° 18.995' N
113° 56.522'
E |
812323.6E 819580.9N |
5.1 |
0.5x1.2xnmh |
Navigation
buoy |
SC004 |
22° 18.997' N
113° 56.542'
E |
812358.3E 819585.1N |
5 |
1.2x1.2x0.7 |
Debris |
SC005 |
22° 19.017' N
113° 56.612'
E |
812477.7E 819621.7N |
5 |
0.2x0.4xnmh |
Navigation
buoy |
SC006 |
22° 19.006' N
113° 56.643'
E |
812532.1E 819601.8N |
3.4 |
0.9x0.5xnmh |
Navigation
buoy |
SC007 |
22° 18.960' N 113° 56.531'
E |
812339.1E 819517.2N |
5.3 |
10x1x0.35 |
Dumped
materials |
SC008 |
22° 18.956' N 113° 56.533'
E |
812341.9E 819509.4N |
5.2 |
7x5.8x0.3 |
Dumped
materials |
Table
9.5 Position of
High Magnetic List
Contact
number |
Latitude Longitude |
Easting Northing |
Gradients (nT/m) |
MC001 |
22° 17.642' N 113° 56.147' E |
811675.5E 817085.2N |
8 |
MC002 |
22° 17.649' N 113° 56.125' E |
811638.5E 817097.9N |
7.6 |
MC003 |
22° 17.643' N 113° 56.125' E |
811638.4E 817086.8N |
7.6 |
MC004 |
22° 17.638' N 113° 56.121' E |
811631.1E 817079.0N |
12.2 |
MC005 |
22° 17.681' N 113° 56.067' E |
811538.1E 817157.6N |
43.4 |
9.4.6
Marine
Archaeological Potential
9.4.6.1 Based
on the historical review, human activities and cultural deposits have occurred
since the Neolithic period in Tung Chung waters, and Tang and Song period
cultural materials have been found on Chek Lap Kok
Island. A Yuan
period kiln complex has also been found in the Ha Law Wan SAI which is partly located
within the Assessment Area, showing past human activities and settlements. This evidence highlights how the waters
of the Assessment Area may have marine archaeological potential.
9.4.6.2 The desktop review
identified no declared monuments, proposed monuments, graded historic sites/buildings/structures,
sites/buildings/structures in the new list of proposed grading items; and Government
historic sites identified by the Antiquities and Monuments Office (AMO) within
the Assessment Area.
9.4.6.3 Preliminary
review of old admiralty charts and a database of known shipwrecks/undefined
sites in the HKSAR maintained by the United Kingdom Hydrographic Office identified
no potential marine archaeological interest / wrecks in the MAI Assessment
Area.
9.4.6.4 Although
sub-bottom profiling (SBP) and marine magnetometer (MAG) were not conducted at
the MF Site since there is no room for vessel movement with MF site constraint
by having seawalls enclosed three sides, the seabed in MF Site has been highly
disturbed with deep scars from anchoring and seabed disturbance works in the
past for many years. The seabed has
been heavily disturbed and remixed down to several metres
greatly impacting any sub-bottom anomalies, if present. Therefore, the marine archaeological
potential within MF Site is very low.
9.4.6.5 There
are eight sonar contacts (SC001 to SC008) in MF Site and five magnetic anomalies (MC001
to MC005) in ATCL Site.
9.4.6.6 In MF
Site, SC001, SC002 and SC004 are interpreted as debris, SC007 and SC008 as dumped
materials, and SC003, SC005 and SC006 are interpreted as navigation buoys and
of no marine archaeological interest.
9.4.6.7 In ATCL
Site, all five magnetic anomalies are considered as debris, and while their
actual origins are not clear they are not considered to have archaeological
potential. No side scan sonar
contacts or sub-bottom anomalies were identified.
Potential
Sources of Impact
9.4.6.8
The
marine construction works of the proposed Project would mainly be the marine
viaduct section of ATCL and marine facilities including a pier and berthing
facilities. Although these works
would not involve open sea dredging and the marine viaduct’s foundation would
generally involve only the use of in-situ bored plies founded on bedrock, potential
impacts arising from these activities include:
·
Direct
loss of potential marine archaeological deposits (if present) due to seabed
disturbance works from temporary working platform on the seaside for the
piling works at the seawall for the construction of marine viaduct;
·
Indirect
impact on access for future archaeological surveys; and
·
Permanent
disturbance to marine archaeological deposits if they are
found to be within the Assessment Area.
9.5.1
Construction Phase
9.5.1.1 The desktop review identified
no declared monuments, proposed monuments, graded historic sites/buildings/structures, sites/buildings/structures
in the new list of proposed grading items; and Government historic sites
identified by the AMO fall within the Assessment Area. No impact to these cultural heritage
resources is anticipated.
9.5.1.2 A part of the Ha Law Wan
SAI is located within the Assessment Area with large separation distance (295m)
from the proposed works of the Project (See Figure
9.1). No impact is anticipated.
9.5.1.3 Geophysical surveys
conducted for the Project identified eight sonar
contacts (SC001 to SC008) in the MF Site and five magnetic anomalies (MC001
to MC005) in the ATCL Site. SC001,
SC002 and SC004 are interpreted as modern debris, SC003, SC005 and SC006 are
interpreted as navigation buoys, and SC007 & SC008 are interpreted as dumped
materials, while MC001 to MC005 are considered as debris. They are considered to have no marine
archaeological potential. No marine
archaeological impact is anticipated.
9.5.1.4 Although sub-bottom
profiling (SBP) and marine magnetometer (MAG) were not conducted at the Marine
Facilities Survey Area (MF Site), the seabed in MF Site has been highly
disturbed with deep scars from anchoring and seabed disturbance works in the
past for many years with very low marine archaeological potential, the
potential impact is considered minimal.
9.5.2
Operational Phase
9.5.2.1 No excavation works will be
involved in operational phase of the Project,
therefore no adverse cultural heritage or marine archaeological impact is
anticipated.
9.6.1
Construction Phase
9.6.1.1 No impact on declared
monuments, proposed monuments, graded historic sites/buildings/structures, sites/buildings/structures
in the new list of proposed grading items; and Government historic sites and
Site of Archaeological Interest has been identified. No mitigation measure is required.
9.6.1.2 As sonar
contacts and magnetic anomalies
identified from geophysical surveys are of no marine
archaeological potential, no marine archaeological impact is anticipated and
therefore no mitigation
measures is required.
9.6.1.3 Although sub-bottom
profiling (SBP) and marine magnetometer (MAG) were not conducted at the Marine
Facilities Survey Area (MF Site), the seabed in MF Site has been highly
disturbed with deep scars from anchoring and seabed disturbance works in the
past for many years with very low marine archaeological potential, the
potential impact is considered minimal.
As a precautionary measure, the project proponent and
his/her contractor are required to inform AMO immediately when any antiquities
or supposed antiquities under the A&M Ordinance are discovered during the
seabed disturbance works in the MF Site and the ATCL Site.
9.6.2
Operational Phase
9.6.2.1 As no adverse cultural
heritage/marine archaeological impact is anticipated in operational phase of
the Project, no mitigation measure is required.
9.7.1.1 No
adverse residual and cumulative cultural heritage impacts are anticipated.
9.8.1
Construction Phase
9.8.1.1
No EM&A is required. However, as a precautionary
measure, the project proponent and his/her contractor are required to inform
AMO immediately when any antiquities or supposed antiquities under the A&M Ordinance
are discovered during the seabed disturbance works in the MF Site and the ATCL
Site.
9.8.2
Operational Phase
9.8.2.1
As
no adverse cultural heritage/marine archaeological impact is anticipated during
operational phase of the Project, no EM&A is required.
9.9.1.1 No impact on declared
monuments, proposed monuments, graded historic sites/buildings/structures,
sites/buildings/structures in the new list of proposed grading items; and Government
historic sites are identified within the Assessment Area. No impact to these cultural heritage
resources arising from the Project is anticipated. No mitigation measures is required.
9.9.1.2 A part of Ha Law Wan SAI located
within the Assessment Area with large separation distance (approximately 295m)
from the proposed works of the Project.
No impact is anticipated and thus no mitigation measures is required.
9.9.1.3 The desktop review
supplemented with the results of geophysical surveys conducted for the Project
identified eight sonar contacts in MF Site, which are interpreted
as modern debris, dumped materials, and navigation buoys, while five magnetic
anomalies found in ATCL Site are interpreted as debris. They are considered to have no marine archaeological potential. No marine archaeological impact arising
from the Project is anticipated. No
mitigation measures and further MAI are required.
9.9.1.4 Although
sub-bottom profiling (SBP) and marine magnetometer (MAG) were not conducted at
the Marine Facilities Survey Area (MF Site), the seabed in MF Site has been
highly disturbed with deep scars from anchoring and seabed disturbance works in
the past for many years with very low marine archaeological potential, the
potential impact is considered minimal. As a precautionary measure, the project
proponent and his/her contractor are required to inform AMO immediately when
any antiquities or supposed antiquities under the Antiquities and Monuments
Ordinance (Cap. 53) are discovered during the seabed disturbance works in the
MF Site and the ATCL Site.
9.10.1
English
EGS, 2022 Marine
Geophysical Surveys - Preliminary Report. April 2022
Green, J.N. 2004 Maritime
Archaeology: A Technical Handbook.
Elsevier Academic Press, Amsterdam,
Meacham, W. 1994
Archaeological Discovery at Chek Lap Kok. Hong Kong: The Hong Kong Archaeological Society.
Meacham, W. 1994 Archaeological Investigations on Chek Lap Kok Island. Hong
Kong: The Hong Kong Archaeological Society.
Murray, D.H. 1987 Pirates of the South China Coast 1790-1810.
Stanford University Press.
Cortesão, A. 1944 The Suma Oriental
of Tomé Pires and the Book of
Francisco Rodrigues. London: Hakluyt Society.
9.10.2
Chinese
張一兵1997 《深圳古代簡史》,北京:文物出版社。
蕭國健 1997 《關城與炮台》,香港市政局。
劉蜀永 2009 《香港簡明史》,三聯書店香港有限公司。
香港歷史博物館 2009 《我武維揚──近代中國海軍史新論》,香港歷史博物館。
9.10.3
Internet
Antiquities and Monuments
Office. 2022. Declared monuments in
Hong Kong (as of 20 May 2022); [information on line]; available from https://www.amo.gov.hk/filemanager/amo/common/form/DM_Mon_List_e.pdf; internet; access on 2 May
2023
Antiquities and Monuments
Office. 2022. Government Historic sites Identified by AMO (as at May 2022);
[information on line]; available from https://www.amo.gov.hk/filemanager/amo/common/form/build_hia_government_historic_sites.pdf; internet; access on 2 May
2023
Antiquities and Monuments
Office. 2022. List of the 1444
Historic Buildings with Assessment Results (as at 9 March 2023); [information
on line]; available from https://www.aab.gov.hk/filemanager/aab/en/content_29/AAB-SM-chi.pdf; internet; access on 2 May
2023
Antiquities and Monuments
Office. 2022. List of new items for
grading assessment with assessment results (as at 9 March 2023); [information
on line]; available from https://www.aab.gov.hk/filemanager/aab/en/content_29/list_new_items_assessed.pdf; internet; access on 2 May
2023.
List of Sites of
Archaeological Interest in Hong Kong (as at Nov 2012). Available from: https://www.amo.gov.hk/filemanager/amo/common/form/list_archaeolog_site_eng.pdf; accessed on 2 May 2023.
AECOM, 2018, Intermodal Transfer Terminal -
Bonded Vehicular Bridge and Associated Roads. EIA Report for Airport Authority
Hong Kong. Available from https://www.epd.gov.hk/eia/register/report/eiareport/eia_2572018/Index.htm; accessed on 2 May 2023.
Ove Arup & Partners
Hong Kong Limited, 2015,
Tung Chung New Town Extension EIA Report for Civil Engineering
Development Department. Available
from https://www.epd.gov.hk/eia/register/report/eiareport/eia_2332015/html/EIA/Text/General/Combined_html%20version.htm; accessed on 2 May 2023.
Ove Arup & Partners
Hong Kong Limited, 2009,
Hong Kong – Zhuhai – Macao Bridge Hong Kong Boundary Crossing
Facilities – Investigation EIA Report for Highways Department. Available from https://www.epd.gov.hk/eia/register/report/eiareport/eia_1732009/Contents%20Page%20(PDF).htm; accessed on 2 May 2023.
Ove Arup & Partners
Hong Kong Limited, 2009,
Hong Kong-Zhuhai-Macao Bridge and Connection with North Lantau
Highway EIA Report for Civil Engineering Development Department. Available from https://www.epd.gov.hk/eia/register/report/eiareport/eia_1722009/Contents%20Page.htm; accessed on 2 May 2023.
([1]) AECOM, 2018, Intermodal Transfer Terminal - Bonded
Vehicular Bridge and Associated Roads
EIA Report
for Airport Authority Hong Kong.
Available from https://www.epd.gov.hk/eia/register/report/eiareport/eia_2572018/Index.htm; accessed on
25 August 2022.
([2]) Ove Arup & Partners Hong
Kong Limited, 2015, Tung Chung New
Town Extension EIA Report for Civil Engineering Development Department. Available from https://www.epd.gov.hk/eia/register/report/eiareport/eia_2332015/html/EIA/Text/General/Combined_html%20version.htm;
accessed on 25 August 2022.
([3]) Ove Arup & Partners Hong
Kong Limited, 2009, Hong Kong –
Zhuhai – Macao Bridge Hong Kong Boundary Crossing Facilities – Investigation
EIA Report for Highways Department.
Available from
https://www.epd.gov.hk/eia/register/report/eiareport/eia_1732009/Contents%20Page%20(PDF).htm;
accessed on 25 August 2022.
([4]) Ove Arup & Partners Hong
Kong Limited, 2009, Hong Kong-Zhuhai-Macao
Bridge and Connection with North Lantau Highway EIA Report for Civil
Engineering Development Department.
Available from
https://www.epd.gov.hk/eia/register/report/eiareport/eia_1722009/Contents%20Page.htm;
accessed on 25 August 2022.