CONTENTS
1.3 Environmental
Impact Assessment Study
1.4 Purpose of this
Executive Summary
2.1 Purpose and
Objectives of the Project
2.4 “Without Project” Scenario
2.5 Alternative Options of the Project
2.6 Description of
the Preferred Option
2.7 Construction
Methods and Engineering Requirements
2.8 Summary of
Environmental Benefits and Environmental Achievements of the Project
3 SUMMARY OF
ENVIRONMENTAL IMPACT ASSESSMENT
3.4 Waste Management
Implications
4 ENVIRONMENTAL
MONITORING AND AUDIT
TABLES
Table 2.1 Summary of ATCL Alignment Options Considered
Table 2.2 Summary of Marine Facilities Location Options Considered
Table 2.3 Advantages and Disadvantages of Different Construction
Methods
Table 2.4 Key Elements of the Project
Table 2.5 Key Design Considerations and the Associated
Environmental Benefits
FIGURES
Figure 1.2 Layout
of Proposed Marine Facilities
Figure 2.1 Alternative
ATCL Alignment and TCC Station Siting Options
1.1.1.1
Airport Authority Hong Kong (AAHK) first put forward its vision to
transform Hong Kong International Airport (HKIA) into an Airport City in the “From City Airport to Airport City”
report published in 2019. The
Airport City vision envisages growing HKIA’s position as the preeminent
international aviation hub in Asia Pacific, while transforming HKIA into a new
landmark and one of the key economic growth engines for Hong Kong. To realise the Airport City vision, AAHK
has adopted a strategy to fully capitalise on the unique geographical advantage
of HKIA and capture opportunities arising from the new infrastructures
connected to the airport, such as the Hong Kong-Zhuhai-Macao Bridge (HZMB).
1.1.1.2
The commissioning of the HZMB in 2018 has greatly improved the
connectivity between Hong Kong and cities in the Greater Bay Area (GBA), and
further expand the catchment area of HKIA as the region’s leading international
aviation hub. To meet the growing
demand and extend the airport’s reach, AAHK will continue to strengthen HKIA’s
capacity for passenger and cargo service, through the expansion into a Three-runway
System (3RS) and other capacity enhancement plans. In addition, AAHK is introducing a
growing cluster of functional enhancements with a view to transforming the
airport into a new landmark and attracting more visitors to the Airport City
from within Hong Kong, the GBA and other parts of Asia. Such functional enhancements include
SKYCITY, a major integrated development that comprises retail complexes, dining
areas, hotels, leisure and entertainment facilities, as well as AsiaWorld-Expo (AWE) future developments and other related
plans, with complementary infrastructural support and technological
innovations.
1.1.1.3
The infrastructural support to the airport’s capacity and
functional enhancements includes, among others, a series of AAHK’s
recommendations for land uses on the Hong Kong Port (HKP) (formerly known as
Hong Kong Boundary Crossing Facilities) Island of HZMB. The key project items include the
building of automated car parks for transit air passengers and visitors
travelling via HZMB, and the Airportcity Link, a
vehicular and pedestrian bridge, on which the AAHK operates an autonomous
transportation system to connect HKP Island and SKYCITY, and plans to extend
such system to Tung Chung Town Centre.
In addition, land parcels on the HKP Island have been reserved for the
development of air cargo logistics.
As announced in the Chief Executive’s 2020 Policy Address, the HKSAR
Government has accepted these proposals.
It is also noted in the 2020 Policy Address that optimising the use of
the land adjacent to the airport will not only provide more job opportunities
and a better living environment for the expanding Tung Chung community, but
also inject new development elements and economic impetus into the whole North
Lantau.
1.1.1.4
Under the strategic context as discussed above, the Airport Tung
Chung Link Project (hereafter referred to as the “Project”) is proposed. The Project involves the construction
and operation of (i) a proposed Airport Tung Chung
Link (hereafter referred to as ATCL) to connect HKP Island, Airport Island and Tung Chung
Town Centre via a dedicated road link, with the use of an autonomous
transportation system (supported by zero emission vehicles); and (ii) marine
facilities in the waters between Airport Island and HKP Island, including a pier and berthing facilities to serve pleasure vessels and to provide marine transport services associated with tourism.
1.1.1.5
The ATCL alignment is shown in Figure 1.1 and the layout of proposed marine facilities is shown in Figure 1.2.
1.1.1.6
A Project Profile (No. PP-623/2021) for the Project was submitted
to Environmental Protection Department (EPD) for application of an EIA Study
Brief, which was subsequently issued on 26 July 2021 (No. ESB-342/2021).
1.2.1.1
The Project involves the construction and operation of (i) a proposed Airport Tung Chung Link (ATCL) to connect HKP Island,
Airport Island and Tung Chung Town Centre via a dedicated road link as shown in
Figure 1.1; and (ii) marine facilities in the waters between Airport Island
and HKP Island as shown in Figure 1.2. The Project scope of
works consists of:
ATCL
i.
Construction of about 5km long road with approximately 2,660m
at-grade section, 880m land viaduct and 230m marine viaduct, and a provision
spur line of an approximate 980m long connecting the planned Aviation Academy
for future extension;
ii.
Construction of 4 at-grade and 1 elevated ATCL stations;
iii. Construction
of a depot; and
iv. Realignment/ Reprovision of affected facilities and construction of
ancillary facilities such as walkways, footbridges and plant room(s);
Marine
Facilities
v.
Construction of a pier and berthing facilities with about 73
berths;
vi. Construction
of ancillary facilities including floating platforms, wave attenuator, gangway, guide piles, etc; and
vii. Maintenance
dredging for the marine facilities.
1.2.1.2
The Project will comprise the following Designated Projects (DPs)
under Part I, Schedule 2 of the EIA Ordinance (EIAO):
• Item A.6(c) – A
transport depot located less than 200m from the nearest boundary of an existing
or planned educational institution;
• Item A.8 – A road
or railway bridge more than 100m in length between abutments;
• Item C.3(a) –
Reclamation works resulting in 5% decrease in cross sectional area calculated
on the basis of 0.0mPD in a sea channel;
• Item C.12(b) – A
dredging operation exceeding 500,000m3 or a dredging operation which
is less than 100m from a seawater intake point; and
• Item O.2 – A
marina designed to provide moorings or dry storage for not less than 30 vessels
used primarily for pleasure or recreation.
1.3.1.1 An
environmental impact assessment (EIA) study was conducted for the Project in
accordance with the requirements of the EIA Study Brief (ESB-342/2021) and the Technical Memorandum on Environmental Impact
Assessment Process (EIAO-TM).
The purpose of this EIA study is to provide information on the nature
and extent of environmental impacts arising from the construction and operation
of the Project and associated works that will take place concurrently. This information will contribute to
decisions by the Director of Environmental Protection on:
i.
the overall acceptability of any adverse environmental
consequences that are likely to arise as a result of the Project;
ii.
the conditions and requirements for the detailed design,
construction and operation of the Project to mitigate against adverse
environmental consequences wherever practicable; and
iii.
the acceptability of residual impacts after the proposed
mitigation measures are implemented.
1.4.1.1 This
Executive Summary (ES) highlights the key information and findings of the ATCL
Project EIA study.
2.1.1.1 The purposes
and objectives of the Project are to enhance connectivity between Tung Chung,
Airport Island and HKP Island and provide an alternative transportation option
served by autonomous transportation system with zero emission vehicles. The Project also provides marine
facilities including the SKYCITY Pier and berthing facilities to serve pleasure
vessels and to provide marine transport services associated with tourism.
Enhancement of
Connectivity
Airport Tung
Chung Link – Autonomous Transportation System connecting Tung Chung
2.2.1.1 The Airport City
Link (ACL) project, being developed by AAHK, is a purpose-built bridge on which
a vehicular road and a pedestrian walkway will be provided to connect the HKP
Island and SKYCITY. As an
environmental initiative, ACL will only be served exclusively by AAHK’s
electric vehicles, such that there is no air pollutant emission during its
operation. Non-AAHK vehicles are
restricted from accessing the ACL.
In the longer term, ACL will be served by AAHK’s autonomous
transportation system. As the next
step, ATCL, as an extension of the ACL’s autonomous transportation system being
planned and operated by AAHK, will run along the road on the eastern coast of
the Airport Island to connect to Tung Chung Town Centre. With the use of zero emission vehicles
(e.g. electric vehicles), and ultimately an autonomous transportation system
(supported by zero emission autonomous vehicles) for the ATCL, the Airport
Island will be seamlessly connected with the HKP Island and Tung Chung Town
Centre in an environmentally-friendly manner.
Marine Facilities – SKYCITY Pier and Berthing
Facilities
2.2.1.2 To the east
of the Airport Island along the coast of SKYCITY, marine facilities will be
provided in the area including a pier and berthing facilities. World international airports today are
placing a stronger emphasis on multi-modal connectivity with neighbourhood
destinations. Marine connectivity
of yachts and ferries have been increasingly common to diversify leisure and
tourism opportunities and foster an attractive lifestyle destination. The proposed marine facilities could
maintain and strengthen HKIA’s position as an international aviation hub,
bringing up with competition amongst other major international airports to
deliver the best experience for visitors and travellers.
2.3.1
General
2.3.1.1 The
Project offers numerous benefits to the neighbourhood and environment through
the planning design. These benefits
include additional transport option - zero emission transport, mitigating
emissions from increased passenger inflow and greater connectivity and
socio-economic growth. The details of
the benefits are further discussed in the below sections.
2.3.2
Additional Transport Option- Zero
Emission Transport
2.3.2.1
The increased number of people visiting the Airport Island as induced by the SKYCITY and Tung Chung
Town Centre developments may cause greater demands on other transport services available
in the areas, especially in a post-pandemic scenario. The ATCL in this respect will provide an additional land transportation option between HKP Island, SKYCITY and Tung
Chung Town Centre. With the use of
zero emission vehicles, it will provide a greener mode of transport for the area than other modes of transport (e.g. buses, taxis,
private cars). ATCL can also
shorten the travelling distance and time, and provide a developed integrated
system interconnectivity. As such,
this attractive alternative will alleviate the pressure on general transport services and
provide a more comfortable and environmental-friendly travel experience for
passengers.
2.3.2.2
Furthermore, the marine facilities including a pier and berthing
facilities that proposed in this Project will also provide an additional marine
transportation option for the area.
The pier will be equipped to provide marine transport services associated
with tourism. Zero emission vessel
is a competitive solution for decarbonisation and is currently under active
development. The proposed pier will
allow the future use of zero emission vessels, when these become commercially
available in the market. In
addition, an electricity pedestal will be installed at each berthing facility
to provide on-shore power supply to vessels for reducing marine emissions at
berth.
2.3.2.3
In the event of traffic accidents that might occur on the existing
key commuting lanes to/from the HKIA, the Project would provide alternative
land and marine transport options for commuters and thus maintain the
transportation services to/from the Airport Island.
2.3.3
Mitigation of Emission from
Increased Passenger Inflow
2.3.3.1
As a green airport, a sustainable strategy is adopted to achieve
carbon emission reduction and sustainable living, as far as practicable. Since the ATCL incorporates
environmental protection measures such as 100% adoption of zero emission
vehicles, there will be no vehicular air pollutant emissions coming from the
vehicles on the whole of the ATCL route.
Thus, the ATCL may help mitigate such increases in vehicular emissions
brought about by the expected increases in traffic to and from the Airport
Island area as it provides an additional greener mode of transport using the
zero emission vehicles between Tung Chung, Airport Island and HKP Island.
2.3.3.2 The ATCL may
help achieve a reduction of emissions that would have otherwise been emitted
through travellers utilizing other emissive modes of transport.
2.3.4
Greater
Connectivity
and Socio-Economic
Growth
2.3.4.1
Upon the commencement of the Three-Runway System (3RS) operation,
it is estimated that 123,000 direct employments will be created at HKIA. The Project, in conjunction with the 3RS,
the HZMB and the developments in SKYCITY, could bring further economic opportunities for Hong Kong and the GBA region. The Project will
enhance connectivity and the attractiveness of the leisure and entertainment
related facilities planned for the SKYCITY at HKIA, and catalyse a greater
socio-economic growth for the Airport Island and the wider Tung Chung community, as the Project provides greater accessibility to job
opportunities and stimulates economic impetus into the North Lantau area.
2.4.1.1 Without
the Project, the increase in patronage arising from traffic resumption and new
developments (e.g. East Coast Support Area (ECSA) commercial developments,
SKYCITY developments and HKP developments) may induce an overall additional
transport demands and the associated vehicular emission in the area.
2.4.1.2 A
greater burden may also be put onto public transport services at the HKIA in
light of the 3RS operation as well as other developments. This may cause crowding and capacity
issue for certain transport services such as the public franchised buses if
adaptions are not made to accommodate an increase in commuters to and from the
HKIA area.
2.4.1.3 Without
the marine facilities, local residents and visitors would be limited to
transport between HKIA, HZMB, SKYCITY developments and tourist attractions in
Hong Kong via land-based transportation.
2.5.1.1 Due
considerations have been given in formulating options to address the
environmental challenges in this Project. The hierarchy of “Avoid, Minimize and
Mitigate” has been fully adopted in the process to protect the environment as
much as practicable. A summary of
the key considerations for options on the alignments, siting of the stations, depot,
marine facilities, construction methods and sequence of construction works is
given in Section 2.5.
2.5.2
Consideration
of ATCL Alignment
Option
2.5.2.1 Alignment
of Option 1 runs inland after crossing Tung Chung Navigation Channel, and turns
to run along seaside after passing Hong Kong Airlines (HKA) Training Academy,
with northern connections at ACL SKYCITY Station and HKP Station. Similar to Option 1, Option 2 adopts a
similar alignment with Option 1 but runs inland after passing HKA Training
Academy, with northern connections at ACL SKYCITY Station and HKP Station. Alignment of Option 3 runs along seaside
after crossing Tung Chung Navigation Channel, and joins the elevated ACL which
provides connection with ACL SKYCITY Station and HKP Station. The options for ATCL alignment are shown
in Figure 2.1.
2.5.2.2 Amongst
the three options, Option 1 may require land reclamation of about 5,000m2
to avoid a relatively sharp turn and enable the ATCL carriageway alignment to
connect to SkyCity Station via East Coast Road. In long term, land reclamation near the
culverts (at the existing seawall on the southern side of the proposed marine
facilities) would potentially block water circulation via box culverts and this
may lead in the change of hydrodynamic regime. In short term, contaminant release due
to dredging works for land reclamation may deteriorate the water quality near
the proposed seawater intake at SkyPier and habitat
loss of the marine ecology and fisheries.
Hence, Option 1 is less preferable.
2.5.2.3 Amongst
the three options, Option 1 and Option 2 may require excavation works at Scenic
Hill for the ATCL alignment which may affect the watercourse/waterbody and the
adjoining vegetated area, hence result in loss of habitat of Romer’s Tree Frog
and impose potential impacts to the known breeding site of Romer’s Tree
Frog. Option 3 has avoided the
encroaching to the Scenic Hill and avoided the direct and indirect impacts to
the ecologically sensitive habitats.
2.5.2.4 Option
1 and Option 2 require additional structures for flyover/viaduct, hence bored
piles, excavation works at Scenic Hill for the ATCL alignment. Option 3 only requires modifying the
existing road to maximise the use of at-grade roads instead of elevated roads
to suit with the ATCL alignment.
Thus, comparatively small scale of construction activities (e.g.
construction of piles) will be involved and less amount of estimated
construction wastes would be generated.
Hence, Option 3 is preferable.
2.5.3
Siting
of Station
2.5.3.1 TCC
Station is the main hub of the ATCL.
It acts as the intermodal gateway to the entire autonomous
transportation system, with links to public transport system provided at the
Tung Chung Town Centre area. Two
location options for TCC Station have been considered. Option S1 is located near Citygate and
Tat Tung Road, whereas Option S2 is located near the Tung Chung Crescent Block
5, as shown in Figure 2.1.
2.5.3.2 Both
options are connected to the Citygate in view of the connectivity. Option S1 is situated next to the
planned visitation church development with priests’ quarters. In comparison, Option S2 is
located in close proximity to Tung Chung Crescent and more construction noise
and dust impact to the nearby sensitive receivers would be anticipated. Moreover, a sharp turn is required for
approaching and leaving the Options S2, it is not desirable for autonomous
vehicle. Therefore, Option S1 is
preferable.
2.5.3.3 Locations of
other stations (besides TCC Station) for the ATCL alignment options are shown
in Figure 2.1. ECSA-S Station and ECSA-N Station of
Option 3, and CAX Station and CNA Station of Option 1 or Option 2 are mainly
serving ECSA developments, while Approach Lights (AL) Station of Option 3 and
SKYCITY Station of Option 1 or Option 2 is intended to connect the future
developments in SkyCity. Option 3 is the only option to connect
Academy Station which supports the transport system of Aviation Academy and
other topside developments in HKP Island. Therefore, Option 3 is preferable.
2.5.3.4 A summary of
the key considerations for alignment options are shown in Table 2.1.
Table
2.1 Summary
of ATCL Alignment Options Considered
ATCL
Alignment Options (see Figure 2.1) |
Benefits |
Dis-benefits |
Preferred
Option (Y/N) |
Option
1 – Alignment
runs inland after crossing Tung Chung Navigation Channel, and turns to run
along seaside after passing Hong Kong Airlines (HKA) Training Academy, with
northern connections at ACL SKYCITY Station and HKP Station |
·
Nil |
·
Require land reclamation of about 5,000m2
causing a potential loss of habitats for marine ecology and fisheries ·
Land reclamation is close to the existing culverts
that allow water circulation between the bay area and Tung Chung, thus inducing water quality and ecological issue in short term and resulting
in the change
of the hydrodynamic regime in long
term ·
Require excavation works at Scenic Hill for the ATCL
alignment which results in loss of habitat of Romer’s Tree frog and generates higher
volume (approximate over 5,500m3) of excavated materials ·
More waste generation from the additional structures
for flyover/viaduct, such as bored piles, excavation works at Scenic Hill,
and land reclamation works ·
Not able to support the population commuting to the
planned Aviation Academy and other topside developments on HKP Islands |
N |
Option
2 – Similar
to Option 1 but continues to run inland after passing HKA Training Academy,
with northern connections at ACL SKYCITY Station and HKP Station |
·
Avoidance
of land reclamation to minimise potential habitat loss of the marine ecology
and fisheries, water quality impact and waste generation |
·
Require excavation works at Scenic Hill for the ATCL
alignment which results in loss of habitat of Romer’s Tree frog and generates
higher volume (approximate over 5,500m3) of excavated materials ·
More waste generation from the additional structures
for flyover/viaduct, such as bored piles and excavation works at Scenic Hill ·
Not able to support the population commuting to the
planned Aviation Academy and other topside developments on HKP Islands |
N |
Option
3 – Alignment
runs along seaside after crossing Tung Chung Navigation Channel, and joins
the elevated ACL which provides connection with ACL SKYCITY Station and HKP
Station |
·
Avoidance of land reclamation to minimise
potential habitat loss of the marine ecology and fisheries, water quality impact
and waste generation ·
Avoidance of excavation works at Scenic Hill to minimise the loss of habitat of Romer’s Tree frog, and
waste generation ·
Maximise the
at-grade section as compared to Options 1 & 2 and thus, less waste generation from the
additional structures for
flyover/viaduct such as bored piles ·
Academy
Station (in Option 3 only) supports the transport system of Aviation Academy
and also other topside developments in HKP Island ·
Passenger
reaches all stations along ATCL/ACL directly with no passenger interchange is
required |
·
Nil |
Y |
2.5.4
Consideration of Depot Location
2.5.4.1
Considering the ease of access and land availability, two
potential locations have been considered for the depot along ATCL. Option D1 is located at the land near
the Academy Station at the south of
HKP Island and Option D2 is located near the Scenic Hill Tunnel.
2.5.4.2 The
depot shall provide essential regular maintenance servicing for autonomous
vehicles employed for the ATCL.
Major servicing shall be carried out off-site by the AV supplier
specialist services. The depot
consists of a plant room and depot area.
The plant room is designed to be maximum approximately 7-10m high
single-storey building. Considering
the implication on various environmental aspects and its accessibility, two
potential locations (Option D1 and Option D2 as shown in Figure 2.2) have
been considered for the depot along ATCL.
2.5.4.3
The proposed depot is small-scaled and does not involve
polluting process such as paint spraying and dry polishing activities. Electrified equipment will be used for
maintenance works and exhaust emission of Non-road
Mobile Machinery (NRMMs)
adopted are expected to be limited.
Thus, adverse air quality impact associated with the associated
maintenance works at the depot is not anticipated. On the other hand, Option D1 and Option
D2 will be located at over 1.5km and about 600m from the nearest noise
assessment point (i.e. Seaview Crescent) respectively. Moreover, air-conditioning would be
provided for the planned Aviation Academy and HKA Training Academy located near
Option D1 and Option D2 respectively.
No adverse environmental impact will be expected for both options during
the construction and operational phase.
2.5.4.4
As Option D1 is located within the Closed Area, permit is
required to access the site of Option D1.
In comparison, Option D2 is connected to the public road network (e.g. Kwo Lo Wan Road), which provides easier access for
stakeholders during both the construction and operational phases.
2.5.4.5
Considering the environmental considerations and site
accessibility, Option D2 is preferred.
2.5.5
Consideration of Marine Facilities Location
2.5.5.1 Considering
the integration to the Airport City concept, there are two potential location
options for the proposed marine facilities. The locations are at the north of Chek Lap Kok, waterspaces
near the AsiaWorld – Expo (Option MF-A) and waterspaces between Airport Island and HKP Island (Option
MF-B) have been taken into considerations. Options for the proposed marine
facilities are shown in Figure 2.3.
2.5.5.2 Option
MF-A is located near the Proposed North Lantau Marine Park (NLMP) and ecologically sensitive area (e.g. the artificial reef
at the Chek Lap Kok Marine
Exclusion Zone). Option MF-B is
located within the SkyPier basin where is further
away from the proposed NLMP and
ecologically sensitive area, and no open sea dredging works is required due to
sufficient water depth. Thus, it is
considered less impact on the water quality and marine ecology on Option MF-B
than Option MF-A.
2.5.5.3 Moreover, the
wave attenuator for the proposed marine facilities of Option MF-A will provide
a relatively sharp turn and cause additional floating refuse easily trapped or
accumulated. Option MF-B
is located between Airport Island and HKP Island. Floating refuse potentially trapped or
accumulated will be similar to the existing condition. Therefore, Option MF-B is preferable.
Table
2.2 Summary
of Marine Facilities Location Options Considered
Marine Facilities Location Option (see
Figure 2.3) |
Benefits |
Dis-benefits |
Constraint
Descriptions |
Preferred
Option (Y/N) |
Option MF-A – Near AsiaWorld – Expo to the north of Chek Lap Kok |
· The closest location to the existing airport facility |
·
Open sea dredging may be required
during construction phase due to insufficient water depth. Marine maintenance dredging
is required to allow the vessels access berthing facilities during operation
phase. Open sea dredging during
both construction and operation phases would impose potential impacts on
waste management, fisheries, marine ecology and water quality · Potential impact on water quality and marine ecology would be
imposed to the Proposed North Lantau Marine Park and the artificial reef at
the Chek Lap Kok Marine
Exclusion Zone ·
The
installation of wave attenuator will provide a relatively sharp turn and cause additional floating refuse easily trapped
or accumulated |
· It is located at the approach light area of the existing north
runway (future Centre Runway) and also located within Hong Kong International
Airport Approach Areas (HKIAAA) no.3, which no vessel shall pass or
enter. As a result, this option is
not feasible |
N |
Option MF-B– Located between Airport Island and HKP Island |
· Most convenient location near
the Airport City development and ATCL alignment ·
Locating
the marine facilities away from the existing and planned marine parks, any
potential water quality and ecological and fisheries impacts would be
considered less as compared to Option MF-A · Only marine maintenance
dredging is required, less marine sediment would be
generated · The floating refuse potentially trapped or accumulated will be
similar to the existing condition |
· Management of mooring area and vessel height specific
arrangement shall be imposed · Marine maintenance dredging is required to allow the vessels access berthing
facilities, which would impose potential impacts on waste management,
fisheries, marine ecology and water quality |
· It is located within the SkyPier Basin, which considered to be the most sheltered
area near Airport City development.
The south of the basin is within HKIAAA no.5, which no vessel with
height exceeding 15m shall pass or enter |
Y |
2.5.6
Consideration for the Design Layout of Marine Facilities
2.5.6.1
Marine facilities would provide services to general public
travelling to the Airport or HKP Island.
Reference has been made to other international airports such as
Singapore Changi Airport, where similar sea access facilities are provided near
the airport for leisure and tourism, and transport where necessary.
2.5.6.2
The design of the marine facilities has accounted for the
anticipated number of usages by travellers and the required mix of berth type
in different sizes to optimise the configuration and number of berths
required. As shown in Figure 1.2, the marine facilities consist of 73 berths for majority of
medium-sized to small-sized vessels. By making reference
to local marinas (e.g. Aberdeen Marina Club, Gold Coast Yacht and Country Club
and Lantau Yacht Club), around 86% of berths are provided for boat length from
11-20m, around 8% of berths are provided for boat length equal to or less than
10m and around 6% of berths are provided for boat length from 21-35m. A relative high number of berths for
medium-sized vessel in the proposed design allows flexibility for the use by
smaller vessels as most common sizes of vessel found in Hong Kong range from 6m-35m with
majority less than 20 m. The
proposed design is considered as the most efficient and cost-effective
configuration which optimizes the safe manoeuvrability for vessels while
accommodating the essential berthing and associated facilities.
2.5.7
Consideration of Construction Method
2.5.7.1 Potential
environmental impacts have been duly considered and assessed throughout the EIA
stage to avoid the adverse environmental impacts of the Project. As such, environmentally conscious
construction methodologies have been adopted to avoid, minimise and mitigate
environmental impact from the Project as far as practicable. The consideration of different
construction methods are summarised in Table 2.3
below.
2.5.7.2 In
comparison with percussive piling, bored piling construction generates less
noise and vibration. To minimise
the construction noise impact generated from the Project to Chinese White
Dolphins, bored pile foundation will be adopted for marine viaduct and land
viaduct for ATCL, and SKYCITY Pier and berthing facilities in marine
facilities.
2.5.7.3 For
the pier columns/bridge deck construction, either precast method or in-situ
method will be adopted. Potential
environmental impacts of the both construction methods of cast in-situ and
precast concrete for pier columns /bridge decks have been assessed in this EIA
report and are considered mitigatable.
Table
2.3 Advantages
and Disadvantages of Different Construction Methods
Method |
Advantages |
Disadvantages |
Piling
Construction |
||
Percussive Piling Method |
· Piles can be precast to the required specifications · Require shorter construction time, reduce the duration of
potential environmental impacts |
· The vibration/ underwater noise from the equipment and plants
might affect the marine ecology, soil condition and adjacent structures · Relatively higher noise impact from the percussive piling method · Higher headroom required |
Bored Piling Method |
· Relatively lower noise and vibration than using percussive
piling method. Hence, less
disturbance to Chinese White Dolphins (CWDs) and marine species, less
disruption to soil condition and adjacent structure · Less headroom restriction |
· More expensive, comparing with percussive piling method · Longer construction time, relatively |
Pier
Column / Bridge Deck Construction |
||
Precast Method |
· Pre-casting activities are carried out off site in a fabrication
yard. Hence, better control on
workmanship and construction quality. · As the casting carried out off site, the impact on-site for air
quality, noise, water quality, waste management during construction phase
will be minimised. ·
Require
Less construction equipment on site, the
noise impact will also be minimised. · Less site constraint due to erection of temporary falsework |
· Since the structure for this Project are not modular in design,
the tailor-made precast units for construction of mould takes longer
construction time and generate more waste than in-situ method · The shipping of the precast unit will be constrained by the
height limit of the airport · Require more plant and equipment to erect the precast segments ·
Reduce
design flexibility as the mould for fabrication is fixed |
In-situ Method |
· Post-tensioning is possible · Longer service time period and minimal maintenance · Require relatively less special skilled workers · Steel formworks will be used instead of timber to maximize the
reuse of formwork, and minimize the waste generation · More flexibility to deal with design changes |
· Require large area for erection of temporary falsework · Workmanship and construction quality are difficult to control |
2.5.8
Consideration of Construction Works Sequence
2.5.8.1
From the baseline information, while Chinese White Dolphins (CWDs)
utilise waters in the Assessment Area, the likelihood of the areas within and
in the vicinity of the Project site as important habitat for CWDs is low and
the said areas are not considered as unique and important habitats for CWDs. Also, the marine works area involving
piling during the construction stage is relatively small. Unacceptable impacts from the Project to
water quality and CWDs are not expected with the implementation of appropriate
preventive and mitigation measures recommended in the EIA report. Therefore, no specific construction works
sequence would be required with respect to water quality and CWDs.
2.5.8.2
To optimize construction works
sequence with the least potential impacts to the surroundings, at
most two marine piles will be installed / constructed concurrently at the
proposed marine facilities works area and the marine viaduct works area across
Tung Chung Navigation Channel, respectively, during construction phase. In addition, the piling works will only
be conducted after setting up temporary working platform within the active marine
works areas surrounded by silt curtain.
2.6.1
ATCL and
Marine Facilities
2.6.1.1 Considering
all the environmental constraints identified and engineering/operational
requirements, the design team has developed the preliminary design for the
Project, with the key elements summarized in
Table 2.4. Figure 1.1 shows all
the key elements for the Project.
Table 2.4 Key
Elements of the Project
Key Elements |
Descriptions |
1.
ATCL alignment |
·
At-grade
sections: 2,660m (approx.) ·
Land
viaduct sections: 880m (approx.) ·
Marine
viaduct section: 230m (approx.) ·
The spur
line of approximately 980m connecting to the Academy Station |
2.
Stations of ATCL |
·
Tung
Chung Central (TCC) Station (elevated) ·
ECSA-N
Station (at-grade) ·
ECSA-S
Station (at-grade) ·
AL Station (at-grade) ·
Academy
Station (at-grade) ·
With
provision of lavatories |
3.
Other associated works |
·
Connecting
works to planned ACL ·
Walkway
and footbridges at ECSA-N Station, ECSA-S Station, and connection with
at-grade road section and land viaduct section near ACL ·
Depot
for maintenance, storage, charging and cleaning of zero emission vehicles ·
Reprovision/realignment of the affected facilities, such as bus
stop, cycling track, footpath, etc. ·
Diversion/reprovision of affected utilities ·
Plant
room(s) |
4.
Marine Facilities |
·
SKYCITY
Pier ·
Berthing
facilities ·
Maintenance
Dredging |
2.7.1.1 The
construction methods proposed are based on environmental and engineering
feasibility of the Project. Bored piling
method, in-situ method and precast method have been considered for the
construction of marine viaduct and land viaduct, while
in-situ concreting and open cut excavation have been
considered for the construction of the at-grade road and depot. For the construction
of marine facilities, socketed H-piles have been taken into account for the construction
of
SKYCITY
Pier along with the wave attenuator, while guide
piles have been considered for the construction of floating
pontoon.
2.8.1.1 As
described in Section 2.5,
avoidance or minimization of the environmental impacts have been one of the key
considerations throughout the design of the Project. The key design considerations and the
associated environmental benefits for different design approaches achieved by
selecting the preferred options and brought by the Project are listed in Table 2.5 below.
Table 2.5 Key
Design Considerations and the Associated Environmental Benefits
Design Approach |
Key Design Considerations and the Associated Environmental Benefits |
Minimisation of the need for land reclamation |
l During the planning and design stage, the ATCL
alignment is designed to minimise land reclamation works l
Minimising the
need for land reclamation while maximise the ATCL at-grade section. |
Avoidance of excavation works at Scenic Hill for the ATCL alignment |
l No excavation works at Scenic Hill for the
ATCL alignment is required to avoid the loss of habitat of Romer’s Tree Frog. l Minimising the waste generation from excavated
materials. |
Minimisation of waste generation |
l Maximising the use of at-grade roads instead of
elevated roads to minimize the waste generated from the construction of
additional structures for elevated road. |
Avoidance of encroaching into the marine park and ecological sensitive
area |
l Locating
the marine facilities away from the Proposed North Lantau Marine Park and
ecologically sensitive area (e.g. the artificial reef at the Chek Lap Kok Marine Exclusion
Zone). |
Avoidance of open sea dredging works during construction |
l No open sea dredging works is required for the
Project by strategically locating the marine
facilities between the Airport Island and HKP Island. l Avoid direct impacts on the marine ecological
resources and fisheries impact. |
Adoption of environmentally friendly construction method |
l Minimisation of construction noise and vibration
impact to the nearby Chinese White Dolphins and marine species for the pile construction through the quieter
piling method (e.g. bored piling method). |
Promote the use of environmentally friendly vehicle system |
l The use of zero emission vehicles during
operational phase can help improve roadside air quality. |
2.9.1.1
The
construction works of the Project will be tentatively commenced in Q4 2025 and
be completed in 2027/2028. A
summary of the key construction works period is listed below.
·
ATCL (including ATCL alignment,
stations and other associated works)
Tentative construction period: Q4 2025 to Q1 2028
Tentative commissioning year:
2028
·
Marine Facilities (including SKYCITY Pier and berthing facilities)
Tentative construction period: Q2 2026 to Q4 2027
Tentative commissioning year:
2028
2.10.1.1 The Project Profile was submitted to the EPD on 15 Jun
2021. During the public
consultation period, 5 written comments, concerning the needs of the Project and its potential impacts in water
quality, waste management, ecology and fisheries, were received. The concerned impacts have been assessed in this EIA study and
summarized in Sections 3.3, 3.4, 3.5 and 3.6, and no adverse impacts are
anticipated from this Project.
2.10.1.2 During the course of the EIA study, AAHK reached out
to different stakeholders through meetings, briefings-cum-airport visits and
webinars, including community groups, members of District Councils in the
airport’s five neighbouring districts, business chambers, professional groups,
unions and youth organisations.
AAHK introduced the Airport City strategy, including the ATCL Project,
to the stakeholders and sought their feedback on the Project. No environmental issue in relation to
the ATCL Project was raised during the outreach. On 27 July 2021, AAHK briefed Islands
District Council members on Airport City developments including the ATCL
Project, receiving positive views from the members, who opined that the ATCL
Project would provide a convenient and environmentally friendly means of
transport to the Lantau District.
3.1.1
Construction Phase
3.1.1.1
During
construction phase, site clearance, utilities protection and diversion works,
slope work, excavation, piling and roadworks, site formation, etc. could
generate construction dust, a quantitative construction dust impact assessment
has been carried out, taking into account the
cumulative impacts from other major pollution emissions in the immediate
neighbourhood as well as the concurrent construction projects in the
vicinity. The assessment for
construction dust impact is within 500m study area from the Project
boundary. With the implementation
of the mitigation measures as stipulated in the Air Pollution Control
(Construction Dust) Regulation, dust control measures (e.g. watering once every
two hours for all exposed site surfaces with dust emission and unpaved roads)
and good site practices, the predicted results concluded that the cumulative Total
Suspended Particulate (TSP), Respirable Suspended Particulate (RSP) and Fine Suspended
Particulate (FSP) concentrations at all air sensitive receivers (ASRs) would
comply with the relevant Air Quality Objectives (AQOs). Hence, adverse air quality impact during
the construction phase is not anticipated.
3.1.1.2 By following Air
Pollution Control (Fuel Restriction) Regulation, Air Pollution Control (Marine
Light Diesel) Regulation, Air Pollution Control (NRMM) (Emission) Regulation
and good site practices (e.g. avoidance of exempted NRMMs where practicable),
the gaseous emissions from construction plants, equipment and vessels are
considered to be minimal and adverse air quality impact is not anticipated.
3.1.2
Operational Phase
3.1.2.1
Given that zero
emission vehicles will be adopted for autonomous transportation system of the
Project, no air quality impact is expected from the zero emission vehicles on
the entire ATCL and station during normal operation. The proposed depot will provide
essential regular maintenance servicing for zero emission vehicles employed for
the ATCL. Electrified equipment
would be provided, hence, no gaseous and particulate emissions generated from
exhaust emissions of the electrified equipment used for maintenance operations
are expected. There will be NRMMs
in the proposed depot. Air
Pollution Control (NRMMs) (Emission) Regulation and Air Pollution Control (Fuel
Restriction) Regulation will be followed to control the fuel combustion
emission from NRMMs. Exhaust
emissions of NRMMs adopted for maintenance operations are expected to be
limited. Thus, adverse air quality
impact associated with any required maintenance works of zero emission vehicles
at the depot is not anticipated. There
will be no adverse air quality impact from the vehicles on the entire ATCL, the
proposed depots and stations.
3.1.2.2
As the potential air quality impacts
from marine vessel emission at the proposed marine facilities are anticipated, a
quantitative operational air quality impact assessment has been carried out, taking into account the cumulative impacts from other major
pollution emissions in the immediate neighbourhood. An
assessment area for operational air quality impact assessment is defined as by
a distance of 500m from the boundary of proposed marine facilities. The predicted cumulative concentration of
RSP, FSP, Nitrogen Dioxide and Sulphur Dioxide at all ASRs would comply with
the relevant AQOs. Adverse air quality impact is not anticipated during operation of the
Project.
3.2.1
Construction Phase
3.2.1.1
Construction
noise impact assessment has been conducted. During the construction phase, Powered
Mechanical Equipment (PME) to be used for the construction works will be the
primary noise source. The
construction of ATCL alignment is one of the major noise sources.
3.2.1.2 Without the
implementation of mitigation measures, the predicted maximum unmitigated
construction noise levels at the representative noise sensitive receivers
(NSRs) would be 57 - 97 dB(A). With the implementation of mitigation
measures including quieter construction methods, use of quieter
PME, use of noise barrier, noise enclosure and noise insulating fabric, the
predicted mitigated construction noise levels at the NSRs would be 50 - 75 dB(A). Hence, the mitigated
construction noise levels at all the representative NSRs would comply with the
EIAO-TM, and hence adverse construction noise impacts from the Project are not
anticipated.
3.2.2
Operational Phase
3.2.2.1
Operational
noise impact assessment has also been conducted. The distances from marine facilities,
depot, and plant room to the nearest NSR are outside 300m, which is ranged from
approximately 500m to 2.3km. Given the large separation distances
from the operation noise sources, adverse operational noise impact from the
proposed facilities are not anticipated. Natural ventilation will be adopted for
the proposed stations, and hence noise impact from mechanical ventilation is
not expected. There are no other fixed plant at the proposed stations.
3.2.2.2
For the
operational noise from zero emission vehicle (e.g. electric vehicle), the Airport
Authority Hong Kong (AAHK) is committed to
acquire zero emission vehicles with a maximum Sound Power Level (SWL) of 100
dB(A) or below, and confirmed that the said vehicles are available in the
market today. With the proper
selection of zero emission vehicle, the operational noise levels would comply
with the EIAO-TM, and hence adverse operational noise impacts from the Project
are not anticipated. Notwithstanding
this, noise commissioning test for zero emission vehicle will be conducted
prior to operation of ATCL to check the compliance of the noise criteria.
3.3.1
Construction Phase
3.3.1.1 Based on the selected construction method, no
open sea dredging works for the Project is required. Potential water quality impact from
marine-based and land-based construction works, the generation of wastewater,
and the sewage from workforce under the Project have been
assessed. Silt curtain would be set
up to enclose the entire active work area before the commencement of piling
works for marine facilities and marine viaduct to control sediment dispersion. At most two marine piles will be
installed / constructed concurrently at the proposed marine facilities work
area and the viaduct works area across Tung Chung Navigation Channel,
respectively during construction phase.
Good site practices, such as adopting clean ballast system, sufficient
vessel clearance from seabed, etc, are recommended to minimise the potential
water quality impact from marine construction works. With the implementation of the recommended
mitigation measures, adverse water quality impact from the Project during the construction phase is not anticipated.
3.3.2
Operational Phase
3.3.2.1 The potential water quality impact arising from the operation of the Project
has been assessed. This impact is associated
with the change in flow regime from the presence of the Project facilities,
maintenance dredging, sewage and wastewater generated from workforce, depot
operation, and potential oil spillage from the operation of the marine
vessels. Modelling assessment
indicated change in flow regime due to the presence of the Project facilities
(1) would be localized within the embayment area between the Airport Island and
the Hong Kong Port and have no noticeable impact beyond and (2) would not
affect the identified beneficial uses within the embayment, and thus will not
result in unacceptable water quality impact.
3.3.2.2 Maintenance dredging will be carried out to allow
vessels to access the marine facilities at low tide and to enhance navigational
safety. Cage type silt curtain will
be provided during maintenance dredging for the marine facilities and the
maximum allowable rate of dredging would be limited to 40 m3/hr. No unacceptable change in water quality
from maintenance dredging would be expected with the above mitigation
measures. Other mitigation
measures, including no direct discharge of untreated sewage, regular cleaning
and removal of floating refuse, no new drainage outfall in marine facilities,
provision of adequately designed pollution removal devices to new drainage will
be implemented. With the
implementation of the recommended mitigation measures, adverse water quality impact from the Project during the
operational phase is not anticipated.
3.4.1
Construction Phase
3.4.1.1 Potential
waste management implications from the generation of waste during the
construction phase have been evaluated.
The waste types generated from the Project would include C&D
materials, marine sediment, chemical wastes from maintenance of construction
plant and equipment, general refuse from the workforce, and floating refuse. It has been estimated that 21,379m3
of inert C&D materials, 1,950 m3 of non-inert C&D materials,
2,803m3 of land-based and marine-based sediment, less than 100 litres
per month of chemical waste, 198 tonnes of general refuse, as well as 3m3
per year of floating refuse.
3.4.1.2 In order to
reduce the disposal quantity of waste, waste re-use and recycling on-site would
be implemented. The amounts of
waste to be backfilled on-site include 5,963 m3 of inert C&D
material and 375 m3 of land-based sediment while the waste to be
recycled include 450 m3 of non-inert C&D material, 9 tonnes of
general refuse and 1 m3 per year of floating refuse.
3.4.1.3 With proper
implementation of the mitigation measures such as good site practices, waste
reduction through good management and control, proper storage, collection and
transportation of waste, all dump trucks engaged on site for delivery of
C&D materials from the site to designated locations equipped with Global
Positioning System (GPS) or equivalent system Automatic Identification System
(AIS) for real time tracking and monitoring of their travel routings and
parking locations in order to avoid illegal dumping or landfilling of C&D
materials etc., adverse environmental impacts from waste management during
construction phase are not anticipated.
3.4.1.4 1,895m3
and 533m3 of land-based and marine-based sediment will be
disposed of for Type 1 – Open Sea Disposal and Type 1 – Open Seas
Disposal (Dedicated Sites) respectively. With implementation of the recommended
mitigation measures and the requirements of Practice Note for Authorized
Persons and Registered Structural Engineers on Management Framework for
Disposal of Dredged/Excavated Sediment (PNAP ADV-21), adverse environmental
impacts arising from the excavation, treatment, transportation and disposal of
marine sediment are not anticipated.
3.4.2
Operational Phase
3.4.2.1 Potential
waste management implications from the generation of waste during the
operational phase have been evaluated.
The main waste types include chemical waste, municipal solid waste from
maintenance activities and staff and passengers, floating refuse and marine
sediments from maintenance dredging at marine facilities. It has been estimated that maximum
35,000m3 of marine sediment from maintenance dredging in every two
years, less than 100 litres of chemical waste per month, 11 tonnes of general
refuse per year and 3m3 of floating refuse per year will be
generated during operational phase, with the implementation of the recommended
mitigation measures and the requirements of PNAP ADV-21 for excavation,
treatment, handling, transportation and disposal.
3.5.1
Construction Phase
Terrestrial Ecology
3.5.1.1
Due consideration on impact avoidance
and impact minimisation have been taken in the Project. The construction activities for the
proposed ATCL and marine facilities largely fell within the existing developed
area (about 98% of the whole Project site) where is already subject to
extensive human disturbance. Impacts
arising from the Project mainly include the habitat loss within the Project
site (i.e. including habitat loss of 0.31 ha of the mixed woodland (largely
restricted to urbanized developed area) at Scenic Hill), potential direct
impacts on species of conservation importance and indirect disturbances to
surrounding habitats and associated wildlife during the construction phase.
3.5.1.2
It should be noted that all of the
identified individuals of flora species of conservation importance are located
outside the Project site, and thus, no direct impact on flora species of
conservation importance is expected. Fauna species of conservation importance
recorded within the Project site are of relatively high mobility such as
avifauna, bat and butterfly, and therefore, these species are not subject to
direct impact from the Project. The
recorded breeding sites for Romer’s Tree Frog comprise watercourse/waterbody
and the adjoining vegetated area. These
sites are located at the west of the Scenic Hill and of some distance to the
Project site. Thus, the recorded
Romer’s Tree Frog would not be directly affected.
3.5.1.3 Given the road/ paved surface and road edge
vegetated areas are not preferred habitats for fauna species of conservation
importance, direct impact on wildlife (esp. fauna species of conservation
importance) due to the Project is considered to be negligible.
Marine Ecology
3.5.1.4
The construction works is of temporary nature,
which includes piling works for the marine viaduct (to be completed within 2
years) and construction activities for the proposed marine facilities (to be
completed within 10 months), with small extent of area affected (i.e. ~0. 67ha of seabed and temporary habitat disturbance of
~8.33ha of water column and intertidal habitat), and the benthic communities,
subtidal and intertidal habitats as well as coral communities found within and in
the vicinity of the Project site are of low ecological importance. With the implementation of standard site
management practices and water quality mitigation measures (e,g, deployment of silt curtain), adverse marine ecological impacts on
the benthic communities, subtidal and intertidal habitats and coral communities
due to the construction of the Project are not anticipated.
3.5.1.5
The
Project will result in the temporary disturbance of approximately 9ha of marine
habitat for Chinese White Dolphins (CWDs).
Based on the literature
review and the results of Passive Acoustic Monitoring survey (i.e. very low
acoustic detections recorded during 4-month monitoring period),
while CWDs utilise waters in the Assessment Area, CWD usage of marine habitat in the vicinity of the
Project site is low and the areas within and in the vicinity of the Project site are
not considered as unique and important habitats for CWDs.
Given the slow-moving
works vessels involved (i.e. about 12-16 vessel movements, including barges, tug boats/supporting vessels, per day at each work area) and the existing
marine traffic in North Lantau waters, adverse impact on CWDs and the
functionality of Brothers Marine Park (BMP) and the proposed North Lantau
Marine Park (NLMP) due to the increased marine traffic are not
anticipated. To mitigate the
potential underwater noise impacts generated from the marine works, bored
piling and vibratory piling methods with the low frequency range over soft
marine deposit of the seabed will be adopted. Adverse impacts to CWDs and the
functionality of BMP and the proposed NLMP due to the construction of the
Project are not anticipated.
3.5.2
Operational Phase
Terrestrial
Ecology
3.5.2.1 Considering
the degraded nature and involved small-scaled loss of 0.31ha mixed woodland,
and the area would likely be developed into a landscape feature with vegetation
planting, adverse terrestrial ecological impact due to loss of mixed woodland
is not anticipated. The rest of the
Project site was developed area of low ecological value, and hence, indirect
disturbance to surrounding habitats and associated wildlife during operational
phase is considered to be minor.
Marine Ecology
3.5.2.2
During operation of the proposed marine
facilities and marine viaduct, permanent loss of less than 0.01ha of benthic
habitat and disturbance of approximately 8.33ha of marine ecological habitat
are expected. As mentioned in Section 3.5.1.5, the areas within and
in the vicinity of the Project site is not considered as unique and important
habitats for CWDs. Compared with
the existing marine traffic in North Lantau waters, the increase in slow-moving
vessels due to the operation of the proposed marine facilities and the
maintenance dredging is considered to be minor. With the control over marine
transportation (e.g. use of designated fairways, speed restriction when
approaching existing and proposed marine parks, avoidance of anchoring within
existing and proposed marine parks), the potential risk of vessel collision
with CWDs and impact to CWDs due to the increase in underwater sound during
operation of the proposed marine facilities is not anticipated. Based on the findings of the water
quality impact assessment, the change in water quality from
maintenance dredging and the change in hydrodynamic properties due to the
Project are also expected to be minor.
With the implementation of abovementioned mitigation measures, adverse
marine ecological impacts during the operation of the Project are therefore not
anticipated.
3.6.1
Construction Phase
3.6.1.1
During the construction phase of the
Project, temporary disturbance to fisheries habitats and loss of access to
fishing ground with an area of ~9 ha is expected. Given that
the small scale
of the area
is of low fisheries operation and low to
moderate fisheries production, and the low commercial value of fisheries
resources, impacts on fisheries are considered to be minor. Impact of elevated levels of underwater
sound as a result of construction activities and the vessel operation of marine
facilities are also considered
to be minor.
3.6.2
Operational Phase
3.6.2.1
During operation phase of the marine facilities and marine
viaduct, permanent loss of
fishing ground of less than 0.01 ha for pile structures of marine viaduct
section and loss of access to approximately 8.33 ha of fishing ground
are expected. However, the affected area is considered
to very small compared to the availability of fishing grounds elsewhere in
Northern Lantau waters available for fishing activities. Hence, impacts on fisheries are
considered to be minor. Underwater
sound due to vessel operation is considered to be minor to fisheries
resources. Indirect impacts to
fisheries resources related to perturbations to key water quality parameters
from maintenance dredging are expected to be minor as the predicted changes in
water quality are localised to immediate vicinity of the Project. No unacceptable change in water quality would be
expected. Hence, no adverse
fisheries impacts arising from the operation of the
Project are anticipated.
3.7.1
Construction Phase
Terrestrial
Archaeology
3.7.1.1 Ha Law Wan Site
of Archaeological Interest (SAI) is partly located within the Assessment Area
with large separation distance (~295m) from the Project site. With its considerable distance from the
works area, neither direct nor indirect impact is anticipated during the
construction of the Project. No other
cultural heritage resources were identified within the Project site.
Marine
Archaeology
3.7.1.2 Supplementary
geophysical surveys were conducted in the Marine Facilities Survey Area (MF
Site) and eight sonar contacts were identified which are
interpreted as modern debris, dumped materials, and navigation buoys, while
five magnetic anomalies found in ATCL Site are interpreted as debris. They are considered to have no marine archaeological
potential. Furthermore, the seabed
in MF Site has been highly disturbed with deep scars from anchoring and seabed
disturbance works in the past for many years with very low marine
archaeological potential, the potential impact is considered minimal.
3.7.1.3 As
sonar contacts and magnetic anomalies
identified from geophysical surveys are of no marine
archaeological potential, no marine archaeological impact is anticipated and
therefore no
mitigation measures and further MAI are required.
3.7.1.4
As
a precautionary measure, the project proponent and his/her contractor are required
to inform AMO immediately when any antiquities or supposed antiquities under
the Antiquities and Monuments Ordinance (Cap. 53) are discovered during the
seabed disturbance works in the MF Site and the ATCL Site.
3.7.2
Operational Phase
Terrestrial
Archaeology
3.7.2.1 Given the
considerable distance from Ha Law Wan SAI, adverse cultural heritage impact is
not anticipated during operational phase of the Project.
Marine
Archaeology
3.7.2.2
As
no adverse cultural heritage/marine archaeological impact is anticipated in
operational phase of the Project, no mitigation measure is required.
3.8.1.1 A few Landscape Character Areas (LCAs) and Landscape Resources (LRs) are identified
within the Project site. With the
implementation of proper mitigation measures during construction phase and
operation phase (e.g. tree preservation, compensation/transplanting for
affected trees, provision of amenity planting and landscape features), residual
landscape impacts are ‘Slight’ /
‘Insubstantial’ on most of the LRs and LCAs. However, ‘Moderate’ residual
impacts are anticipated only on LR5 (Amenity Landscape Areas along Airport Road
and Chek Lap Kok Road) and
LCA1 (Transport Corridor Landscape) during the construction and operation
phases.
3.8.1.2
Approximately 985
nos. of existing trees and 141 nos. of planned trees were identified within 5m
of the proposed ATCL alignment, of which approx. 385 to 435 nos. of
existing trees that would not be affected by the proposed works will be
retained, while 690 to 740 nos. of trees that would be directly affected by the
proposed works will be proposed to be removed or transplanted as far as
practicable. There is no Old and
Valuable Trees (OVT) in accordance with DEVB TC(W) NO. 5/2020 is identified
within the Project boundary. Approximately 535 nos. of trees are
proposed to be compensated / transplanted within the proposed works area. Under the proposed scheme for the
Project, opportunities for tree compensation within the Project boundary has
been fully explored and incorporated in the proposed mitigation measures as
much as practicable. To further mitigate the visual and
landscape impact of the Project, approximately 155 to 205 nos. of the trees
would be compensated off-site within the Airport Island and HKP Island.
3.8.1.3 The visual impacts on Visual Sensitive Receivers (VSRs)
such as the VSR1 (Residents of Tung Chung Crescent), VSR2 (Residents of Fu Tung
Estate), VSR3 (Residents of Seaview Crescent), VSR8 (Residents of Visitation
Church), VSR9 (Workers of Visitation Church), VSR10 (Residents of Campus and
Dormitory of the Hong Kong International Aviation Academy), VSR12 (Users of
Tung Chung Development Pier) and VSR29 (Users of Tung Chung Town Centre
Waterfront Promenade) are anticipated to be
moderate without the provision of mitigation measures during construction
phase. However, with the implementation
of recommended mitigation measures such as the provision of amenity planting,
aesthetically pleasing design, the residual visual impacts would be reduced to
‘Slight’ / ‘Insubstantial’ by operation day 1 and ‘Insubstantial’ by operation
year 10 when the mitigation measures have matured and taken effect. Hence, the visual impacts are considered
acceptable with the mitigation measures.
3.8.1.4 In view of the above, it is considered that
the overall landscape and visual impact associated with the construction and
operation of the Project are acceptable with the implementation of the recommended
mitigation measures.
4.1.1.1
The EIA study of the Project has demonstrated its compliance with
the EIA Study Brief and EIAO-TM requirements. Actual impacts during the construction
works will be monitored through a detailed EM&A programme. Full details of the programme are
presented in a separate EM&A Manual associated with the EIA Report. The EM&A programme will provide
management actions to check the effectiveness of the recommended mitigation
measures and compliance with relevant statutory criteria, thereby ensuring the
environmental acceptability of the construction and operation of the Project.
5.1.1.1 This EIA
study assessed the overall acceptability of the environmental impacts arising
from the construction and operation of the Project, in accordance with the EIA
Study Brief (No. ESB-342/2021), EIAO-TM and other relevant guidelines and
criteria. The findings of EIA study
indicated that, with the implementation of the recommended mitigation measures,
the Project would be environmentally acceptable. An EM&A programme has been
recommended to check the effectiveness of the recommended mitigation measures.